Pipex FASTBUILD™ Packaged Pumping Stations can be supplied complete with Pipex FASTBUILD™ Valve Chambers and Pipex CHEMSAFE™ Pipe Systems heavy gauge HDPE rising mains. Alternatively the chambers can be supplied standalone for connection to any concrete, plastic, clay, FRP, cast iron or metallic drainage pipe system as required.
4. British American Tobacco Pumping Stations Boncourt Switzerland Location Switzerland Client British American Tobacco Design, fabricate and deliver 2 corrosion resistant chemical packaged pumping stations. Chamber # 1 was 3.4 m diameter X 4 metres deep. Chamber # was 2 2.4 m diameter X 3 metres. Chambers manufactured at Pipex factory in Plymouth, UK.
10. Project BP Global Alliance Location Various BP Petrol Stations Pipex Universal Manholes, valve chambers and electrical / communication cable draw pit chambers. Chambers BBA approved, guaranteed fully sealed, swift, simple and safe site installation. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.
13. Pipex Tanks & Vessels Project Storm Attenuation Tank Location Suffolk, South East England Pipex supply, factory fabrication and on site installation of 1 No. 14 M long x 2.5 M diameter HDPE tank which once installed on site, will be used to hold storm water as part of a storm attenuation system. The tanks were supplied to site with two pump sets with guide rails and lifting chains to assist Genzyme with the lifting of the heavy pump sets. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.
17. Project M25 Catchpits Location Various locations around the M25, London, UK. To fabricate and supply approximately 150 No. polypropylene (PP-H) catchpits with adjustable “top hats” and 150 No. PP-H catchpits without “top hats” for use road side on the M25 renovation works. These catchpits were supplied in a range of sizes and arrangements with adjustable “top hats” to suit onsite requirements. The majority of the catchpits were 1100mm high x 800mm wide x 600mm long. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.
18. Location Barry Docks, South Wales Client Dow Corning Ltd Supply of 49 no. Catchpits ranging for 1050mm Diameter to 2100mm Diameter. Also supply of polypropylene sumps to interface ‘Decathlon’ drainage channels with Catchpits. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.
21. Project Hawes Sewage Treatment Works (STW) Location Bradford, UK Supply and fabricate a 1500Ø x 2M deep PPH Flow Meter Chamber. The chamber was delivered complete with benching, sump, HDPE shuttering, top formwork and square turret to suit client’s manhole frame. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.
24. Project M25 Penstock Chambers Location M25 Ringroad, London To fabricate and supply 2 No. Pipex Penstock Chambers for installation roadside along the M25 motorway as part of the renovation works. 1 No. Penstock chamber : 2.4Mø x 3M high complete with 2 No. inlet ports & 1 No. outlet port with a 1M penstock. 1 No. Penstock chamber: 2.1Mø x 3.8M high complete with 3 No. inlet ports & 1 No. outlet port with a 400mm penstock. These penstocks were constructed from highly durable, corrosion resistant polypropylene with polyethylene shuttering for concrete pouring. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.
25. Project Chelmsford Penstock BP Service Station Location Essex, South East England. Pipex supply and factory manufacture of 1 No. PP-H 1200 mm diameter x 1000 mm deep Bespoke Penstock Chamber. C/w 150 mm diameter inlet, outlet and Penstock Valve. The Penstock Chamber was supplied to site with top cover and turret form work to suit consultants design. Pipex Limited / Trouvay & Cauvin Gulf ADSSC Product Approval.