SlideShare una empresa de Scribd logo
1 de 23
Descargar para leer sin conexión
Dulles Metrorail Silver Line:
Status Report &
Transportation Infrastructure
Finance and Innovation Act
(TIFIA) Funding Update
Transportation Committee
Fairfax County Board of Supervisors
May 7, 2013
Presentation Outline
• Phase 1 Status Report
• Phase 2 Status Report
• Transportation Infrastructure Finance and
Innovation Act (TIFIA) Funding Update
• Recommendation of Preliminary TIFIA
Allocation
• Requirements from Funding Partners
• Phase 1 Plan of Finance – Closeout
• Staff Recommendations
• Timeline
2
Phase 1 – Status Report (asofApril24,2013)
Status
• Construction: 90% Complete
• Final Design: 100% Complete
• Utility Relocation: 100% Complete
• Property Acquisition: All rights of entry obtained
• Track Work: 100% Complete
• Stations:
• McLean – 80%
• Tysons Corner – 75%
• Greensboro – 65%
• Spring Hill – 65%
• Wiehle – 84%
• First Delivery of Rail Cars – February 2014
• Wiehle Garage: 88% Complete
• Garage Substantial Completions: July 19, 2013
• Roadway Improvements (ROD): 67% complete
• August/September 2013 completion
Budget
• Revised Budget Authorized: $2.905B
• Expended to Date: $2.2B
• County Phase 1 share: $467.8M
• Tax District Funds: $400M (Funding Gap =
$67.8M)
• Fairfax County share of Project expenditures through
fourth quarter 2012 = $369.1M
• $150M received from Commonwealth
Schedule
• Substantial Completion: September 7, 2013
• WMATA Testing and Acceptance: August – December
2013
• West Falls Church Yard Completion: December 2013
• Sound Box and Tail Track: November 2013
• Estimated Passenger Revenue Service: December 31,
2013
Current Milestones – Past 30 Days
• Entire 3rd Rail energized for Metrorail train testing.
• Tunnel Clearance – No issues per WMATA
• All five stations under construction with efforts on
mechanical, electrical, plumbing, and station finishes
• Phase 1 Maintenance and Land Conveyance process
ongoing:
• Fairfax County will retain ownership of Kiss
and Ride at McLean
• Fairfax County will operate through an
easement Kiss and Ride at Spring Hill Station
• Regional planning effort underway for Phase 1 bus
service (Fairfax Connector, WMATA, Washington Flyer,
PRTC, Loudoun Transit)
• Fairfax County 2nd round of Public Meetings
ongoing
• Ask Fairfax online chat completed
3
Phase 2 – Status Report (asofApril24,2013)
Status
• Packet A Price Proposals Opened – April 19, 2013
• Project estimate Packet A = $1.4B - $1.6B vs. $1.177B
low bid
• Positive impact on toll rates = $300M (est.)
• Packet A Contract Award: May 2013
• Packet A Notice to Proceed: June 2013
• 5 Bid Packages:
• Packet A - Rail Line, Station, and Systems
(includes Innovation Center Station)
• Packet B – Yard and Shop
• Packet C (may not be issued) – Parking
Garages
• Packet D – ROW
• Packet E – Utilities
• Fairfax County working to fund & construct Herndon
and Innovation Center garages outside of project
• Financial Plan status:
• Transportation Sub Committee May 7, 2013
• BOS May 14, 2013
Innovation Center (RT 28) Station
• Station included in Packet A bid.
• County using its best efforts to mitigate
some station costs on south side. (ROW,
alternative site work funding, and
improved site layout for: garage, bus
bay, and kiss/ride design. )
• Station cost will have to be funding either in
part or whole per the funding agreement
(County funding agreement share 16.1%).
• County also pursuing funding from TIGER
Grants and NVTA
Budget
• Cost Estimate: $3.093B
• Cost Estimate with value engineering and
alternative funding for garages & Innovation
Center Station: $2.7B
• Cost to build garages in Fairfax County: $105M
est.
• Fairfax County share for Phase 2 ranges from
$433M – $498M, Tax District capped at $330M
Schedule
• Substantial Completion: Summer 2018
• Revenue Operations: Late 2018
Current Milestones Past 30 Days
• FTA oversight of Phase 2 under discussion:
Ongoing
• TIFIA Letter of Interest submitted: Ongoing
• WMATA Art in Transit: Selection: Ongoing
• Reston Town Center Tunnel Design under review
by WMATA and MWAA
4
Request Board Approval of
Staff Recommendations
• Approve the Preliminary TIFIA Allocation of $1.9b
amongst the Funding Partners, with County to receive
$475m
• Approve the County Credit Pledge of the C & I Fund and
the Phase 2 Tax District to TIFIA; Potential use of Moral
Obligation from General Fund to meet AA Category
Rating mandated from USDOT
• Request Credit Ratings from the bond rating agencies to
comply with TIFIA Credit Review ($90,000)
• Approve the $100,000 down payment required from the
County to move forward in the TIFIA Letter of Interest
(LOI) review process
• Review short term financing options to cover the $67m
for balance of County contributions for Phase 1. This will
be paid off with receipt of TIFIA funds
5
Transportation Infrastructure
Finance and Innovation Act
(TIFIA) Status Update -
Recommendation of Preliminary
TIFIA Allocation
6
TIFIA Financing Overview
• Federal credit assistance in the form of direct loans
(not grants) to finance surface transportation projects
of national and regional significance
• USDOT Secretary LaHood departing & accelerated
turnaround time for documents
• Improved access to capital markets, flexible
repayment terms, and potentially more favorable
interest rates than can be found in private capital
markets for similar instruments
• Loan Repayment Deferral Option - 5 years after
project completion (2023)
• Alternatively – conduct open market bond sale & debt
service payments immediately
7
Silver Line Cost Allocation –
Funding Partners
Funding
Partner
% Share TPE -
Baseline
$ Share TPE -
Baseline
Other –
Garages
Funding Partner
Total
(TPE Baseline +
Garages)
Dulles Toll Road* 75% $4,262,763,750 - $4,262,763,750
Fairfax 16.1% 915,073,285 146,721,000 1,061,794,285
Loudoun 4.8% 272,816,880 168,413,000 441,229,880
MWAA –
Aviation Funds 4.1% 233,031,085 - 233,031,085
Total 100.00% $5,683,685,000 $315,134,000 $5,998,819,000
* Includes $900m from FTA New Starts (16.1%), $275m from Commonwealth (4.9%). Net to
Dulles Toll Road is 54%. Allocation assumes the add’l $150m + $300m for Phase 2 will be used to
pay interest on Dulles Toll Road Revenue Bonds, not direct project costs.
8
Silver Line Total Project Estimate -
Fairfax County Costs 16.1%
Phase 1 Phase 2 Total
Total Baseline $2,905,685,000 $2,778,000,000 $5,683,685,000
County Share @ 16.1% 467,815,285 447,258,000 915,073,285
Less Tax Districts (400,000,000) (330,000,000) (730,000,000)
Net County due $67,815,285 $117,258,000 $185,073,285
Garages
Herndon-Monroe $80,959,000* $80,959,000
Route 28 65,762,000* 65,762,000
Total Garages $146,721,000 $146,721,000
TOTAL (Baseline + Garages) $467,815,285 $593,979,000 $1,061,794,285
*Per 100% P/E and consistent with MWAA documents; County believes costs will be lower and in the process of
a feasibility study
9
TIFIA Allocation:
Funding Partner Consensus
Funding Partner
Funding Partner
Total Project Cost
TIFIA
Allocation
Fairfax $1,061,794,285 $475,000,000
Loudoun 441,229,880 200,000,000
MWAA – Aviation Funds 233,031,085 -
Dulles Toll Road 4,262,763,750 1,304,610,270
Total $5,998,819,000 $1,979,610,270
• Meets MWAA goal of $1.2-$1.4b for the Toll Road
• Counties maintain equity of TIFIA allocation equal to
45% Total Project Cost
• December 2012 – Per USDOT Project Will Remain
Eligible for 33% TIFIA Loan or $1.9b ($5.9b * 33%)
10
TIFIA Premium Projections
A B C D E (C * D)
Funding
Partner
USDOT
Requested
Minimum
Credit Rating
Anticipated
TIFIA Premium
TIFIA
Allocation*
USDOT Premium
Subsidy
Allocation
Fairfax AA Category 2% $475,000,000 $9,500,000
Loudoun AA Category 2% 200,000,000 4,000,000
Dulles Toll Road
Investment Grade
(BBB Category) 12% 1,304,610,270 156,553,232
Total $1,979,610,270 $170,053,232
Premium allocation evaluated/ reviewed heavily by TIFIA office
when awarding project funding
* Assumes MWAA Aviation Funds receive no TIFIA Loan
11
TIFIA Status Update –
Requirements from Funding
Partners
12
TIFIA Financing
• Competitive Interest Rates that correlate to 30-Year
Treasury Note
• Flexible call options - prepay outstanding principal
• Potential future refunding opportunities
• USDOT Expected Ratings from Funding Partners
• AA Category Rating from Counties
• Investment Grade from Dulles Toll Road (MWAA)
• Pledge two County sources for Plan of Finance
• Commercial and Industrial Tax Fund
• Dulles Rail Phase 2 Tax District ($330 million)
• May be required to include Moral Obligation of the
County General Fund if AA Category Rating is not
achieved
13
USDOT Information Request –
April 2013
• Complete County Plan of Finance for TIFIA
• Commercial and Industrial Tax Fund
• Dulles Rail Phase 2 Tax District ($330 million)
• Indicative Rating Letter on the TIFIA Loan
• USDOT EXPECTS Counties to achieve rating in the AA Category
• Initial review from the Credit Rating Agencies ($90,000)
• Feasibility Study for Each Source of Credit Pledged
• MWAA Toll Road Study
• Counties expected to submit standard information: tax
assessment, economic, and demographic information
• Credit Processing Down Payment of $100,000 from each
funding partner
14
County Plan of Finance for TIFIA -
Commercial & Industrial Tax Fund
• Tax Rate of 12.5 cents per $100 of AV & generates
approximately $51m revenue annually
• Previously recommended to finance County project costs
outside of the two tax districts: Phase 1 ($67.8m) & Phase
2 ($117.3m)
• Planning Guideline for Long Term Forecasting:
• 50% of expenses for Tysons / Silver Line
• 50% of expenses for Remainder Countywide Projects
• Loan Repayment Deferral Option - 5 years after project
completion (2023)
• Redirect previously forecasted monies required for debt
service to fund other Countywide projects (equates to
approximately $70m total from 2014-2023)
15
County Plan of Finance for TIFIA -
Phase 2 Tax District $330 million
• Estimated stand alone current rating of this district likely “A”
Category, thus enhancement necessary
• Comparative Assessed Value 1/1/13: Phase 1 $11.4b vs. Phase 2 $7.5b
• Allow for growth district tax base / assessed value, similar to Phase
1 Tax District
• Phase 2 Tax Rate – 20 cents for FY 2014
• Initially began at 5 Cents in FY 2011, with 5 cent laddered increases
• Remain at this rate until rail service begins 2018, then ability to increase to
25 cents per Petition
• Accumulation of tax collections to provide for early repayment of
outstanding principal at regular intervals
• Staff recommendation that C & I Fund be used back this Tax District
for credit enhancement
• General Fund Moral Obligation may be needed to reach AA
Category if C & I Fund insufficient
16
Financing Dulles Rail - Alternate Options
Public Sector Sources Private Sector Sources
State/Feder
al Funding
General
Fund (Pay
Go) G.O. Bonds C&I Funds
Meals Tax
(Pay Go) 100% TIF Capped TIF
Service
District /CDA
Developer
Contributions
Cost of Financing /
Carrying Cost
(Lowest to High)
■ ■ ■  ■    ■
Length of Time to
Accrue Funds
(Sooner to Later)
  ■      
General Fund Impact
(Low to High)
■  ■ ■ ■   ■ ■
Impact on
Redevelopment
(Low to High)
 ■ ■  ■ ■ ■  
Impact to G.O. Debt
(Low to High)
■ ■  ■ ■ ■ ■ ■ ■
Ability to Meet Capital
Requirements
(High to Low)
    ■ ■  ■ 
Requires Third Party
Concurrence
(Degree of Difficulty)
 ■    ■ ■  
■ Low Impact and/or Most Beneficial
 Medium Impact and/or of Concern
 High Impact and/or Most Difficult
17
Other Potential Funding Options: NVTA & Federal TIGER Grants
Fairfax County Portion
Remaining Dulles Rail Financing
Phase 1 Phase 2 Total
Total Project Estimate (TPE) $2,905,685,000 $2,778,000,000 $5,683,685,000
County Share @ 16.1% 467,815,285 447,258,000 915,073,285
Less Tax Districts (400,000,000*) (330,000,000) (730,000,000)
Net County due $67,815,285 $117,258,000 $185,073,285
Total County Remaining
Financing Needed
$67,815,285 $447,258,000 $515,073,285
*paid to date to MWAA 18
Fairfax County Cashflow
Remaining Dulles Rail Financing
Source Funds Amount Source Debt
Service
Comment
TIFIA $67.8m C & I Fund Balance Phase 1 costs beyond
$400m from Phase 1 Tax District;
TIFIA may be used to repay short
term financing (2013)
TIFIA $117.3m C & I Fund Phase 2 costs beyond $330m from
Phase 2 Tax District (2013-2018)
TIFIA $289.9m Phase 2
Tax District
88% of Phase 2 Tax District’s $330m
(2013-2018)
Total TIFIA $475.0m 45% Total County Project Cost
Phase 2 Tax
District Bond Sale
or Cash
$40.1m Phase 2
Tax District
Phase 2 Tax District Bond Sale or
Cash Contribution (2018)
Total Remaining
Financing
$515.1m
19
County Phase 1 Cost - $467m
• Phase 1 Tax District fulfilled $400 million obligation
• Establish a plan of finance to cover remaining $67m
to close out the County’s Phase 1 contributions
• TIFIA Funds are not expected until end of the
Calendar Year 2013 at the earliest
• County Staff and Financial Advisor review of short
term financing options to address the $67m:
• Use portion of County’s current $100m Line of Credit
• Bond Anticipation Note (BAN)
• Staff recommendation: Utilize the Line of Credit &
then pay off from receipt of TIFIA funds. 20
Recommendations – Consistent
with May 14th Board Item
• Approve the Preliminary TIFIA Allocation of $1.9b amongst
the Funding Partners, with County to receive $475m
• Approve the County Credit Pledge of the C & I Fund and
the Phase 2 Tax District to TIFIA
• Goal to receive AA Category Rating and assumes no Moral
Obligation
• Phase 2 Tax District to utilize $290m of Preliminary TIFIA &
seeking Moral Obligation (e.g. Credit Enhancement) from C &
I Fund
• Request Credit Ratings from the bond rating agencies to
comply with TIFIA Credit Review ($90,000)
• Approve the $100,000 down payment required from the
County to move forward in the TIFIA LOI review process
• Review short term financing options to cover the $67m for
balance of County contributions for Phase 1. This will be
paid off with receipt of TIFIA funds
21
Timeline
Date Item
October 2012 MAP-21 Revised TIFIA Loan Notification (33% to 49%)
October 2012 Funding Partners Submits LOI USDOT TIFIA (@ 49%)
December 2012 TIFIA request to Funding Partners for more information
January 2013 Funding Partners discussion on TIFIA Allocation
April / May 2013 MWAA Awards Phase 2 Design-Build Contract
May 2013 Board Discussion on TIFIA Allocation
May 2013 Discussion with Bond Rating Agencies on County Credit for TIFIA
May 2013 Submit County materials to TIFIA
Summer 2013 County Interim Financing to cover balance of Phase 1 costs
December 2013 Targeted Closing on TIFIA Loan for Funding Partners
December 2013 Begin Service for Phase 1
Spring 2014 Refinance Interim Financing for balance Phase 1 costs
December 2018 Begin Service for Phase 2
22
Questions?
23

Más contenido relacionado

La actualidad más candente

Agenda Item 5: VDOT Paving Program
Agenda Item 5: VDOT Paving ProgramAgenda Item 5: VDOT Paving Program
Agenda Item 5: VDOT Paving ProgramFairfax County
 
Highway Safety Improvement Program and Safety Performance Management Measures...
Highway Safety Improvement Program and Safety Performance Management Measures...Highway Safety Improvement Program and Safety Performance Management Measures...
Highway Safety Improvement Program and Safety Performance Management Measures...RPO America
 
Statewide and Nonmetropolitan and Metropolitan Transportation Planning
Statewide and Nonmetropolitan and Metropolitan Transportation PlanningStatewide and Nonmetropolitan and Metropolitan Transportation Planning
Statewide and Nonmetropolitan and Metropolitan Transportation PlanningRPO America
 
VTA's Preliminary Envision Silicon Valley Project Evaluation
VTA's Preliminary Envision Silicon Valley Project EvaluationVTA's Preliminary Envision Silicon Valley Project Evaluation
VTA's Preliminary Envision Silicon Valley Project EvaluationSCVTA
 
Santa Clara County Past Sales Tax Measures
Santa Clara County Past Sales Tax MeasuresSanta Clara County Past Sales Tax Measures
Santa Clara County Past Sales Tax MeasuresSCVTA
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015Robust Marketing & Consulting (Pty) Ltd
 
Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15Robert Smith
 
VTA 2016 Measure B Program Areas
VTA 2016 Measure B Program AreasVTA 2016 Measure B Program Areas
VTA 2016 Measure B Program AreasSCVTA
 
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1Fairfax County
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentationSCVTA
 
Department of Public Enterprises presentation on SOEs
Department of Public Enterprises presentation on SOEsDepartment of Public Enterprises presentation on SOEs
Department of Public Enterprises presentation on SOEsSABC News
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Current Condition of Santa Clara County's Transportation System
Current Condition of Santa Clara County's Transportation SystemCurrent Condition of Santa Clara County's Transportation System
Current Condition of Santa Clara County's Transportation SystemSCVTA
 
2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant Workshop2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant WorkshopCuyahoga County Planning Commission
 
Special Local Road Fund
Special Local Road FundSpecial Local Road Fund
Special Local Road FundAlvin Almo
 

La actualidad más candente (20)

Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Agenda Item 5: VDOT Paving Program
Agenda Item 5: VDOT Paving ProgramAgenda Item 5: VDOT Paving Program
Agenda Item 5: VDOT Paving Program
 
Highway Safety Improvement Program and Safety Performance Management Measures...
Highway Safety Improvement Program and Safety Performance Management Measures...Highway Safety Improvement Program and Safety Performance Management Measures...
Highway Safety Improvement Program and Safety Performance Management Measures...
 
Statewide and Nonmetropolitan and Metropolitan Transportation Planning
Statewide and Nonmetropolitan and Metropolitan Transportation PlanningStatewide and Nonmetropolitan and Metropolitan Transportation Planning
Statewide and Nonmetropolitan and Metropolitan Transportation Planning
 
VTA's Preliminary Envision Silicon Valley Project Evaluation
VTA's Preliminary Envision Silicon Valley Project EvaluationVTA's Preliminary Envision Silicon Valley Project Evaluation
VTA's Preliminary Envision Silicon Valley Project Evaluation
 
Santa Clara County Past Sales Tax Measures
Santa Clara County Past Sales Tax MeasuresSanta Clara County Past Sales Tax Measures
Santa Clara County Past Sales Tax Measures
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
TeamTX Austin 2015 Presentations
TeamTX Austin 2015 PresentationsTeamTX Austin 2015 Presentations
TeamTX Austin 2015 Presentations
 
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
Briefing on MIG Expenditure for Select Committee on Appropriations 12 May 2015
 
Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15
 
BIADOT Transportation Presentation Oct11 09
BIADOT Transportation Presentation Oct11 09BIADOT Transportation Presentation Oct11 09
BIADOT Transportation Presentation Oct11 09
 
VTA 2016 Measure B Program Areas
VTA 2016 Measure B Program AreasVTA 2016 Measure B Program Areas
VTA 2016 Measure B Program Areas
 
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentation
 
Department of Public Enterprises presentation on SOEs
Department of Public Enterprises presentation on SOEsDepartment of Public Enterprises presentation on SOEs
Department of Public Enterprises presentation on SOEs
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
189-3 WV Surface Tax Map Standard (2009)
189-3 WV Surface Tax Map Standard (2009)189-3 WV Surface Tax Map Standard (2009)
189-3 WV Surface Tax Map Standard (2009)
 
Current Condition of Santa Clara County's Transportation System
Current Condition of Santa Clara County's Transportation SystemCurrent Condition of Santa Clara County's Transportation System
Current Condition of Santa Clara County's Transportation System
 
2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant Workshop2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant Workshop
 
Special Local Road Fund
Special Local Road FundSpecial Local Road Fund
Special Local Road Fund
 

Destacado

Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...
Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...
Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...Fairfax County
 
Section 8: The Leaders Decisions (part 2)
Section 8: The Leaders Decisions (part 2)Section 8: The Leaders Decisions (part 2)
Section 8: The Leaders Decisions (part 2)Richard Chamberlain
 
DPS Academic Plan: "Meeting the Challenge"
DPS Academic Plan: "Meeting the Challenge"DPS Academic Plan: "Meeting the Challenge"
DPS Academic Plan: "Meeting the Challenge"daytonschools
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 

Destacado (6)

Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...
Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...
Fairfax County Transportation Advisory Commission: Dulles Rail Phase I Bus Se...
 
Section 8: The Leaders Decisions (part 2)
Section 8: The Leaders Decisions (part 2)Section 8: The Leaders Decisions (part 2)
Section 8: The Leaders Decisions (part 2)
 
DPS Academic Plan: "Meeting the Challenge"
DPS Academic Plan: "Meeting the Challenge"DPS Academic Plan: "Meeting the Challenge"
DPS Academic Plan: "Meeting the Challenge"
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages & WMATA ...
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 

Similar a Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update

Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
 
Reston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosReston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosFairfax County
 
Funding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara CountyFunding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara CountySCVTA
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Fairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Fairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsFairfax County
 
Reston Transportation Service District FY 2019 Tax Rate Discussion
Reston Transportation Service DistrictFY 2019 Tax Rate DiscussionReston Transportation Service DistrictFY 2019 Tax Rate Discussion
Reston Transportation Service District FY 2019 Tax Rate DiscussionFairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateAdina Levin
 

Similar a Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update (20)

Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Reston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosReston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding Scenarios
 
Funding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara CountyFunding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara County
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
 
TPO FPC SMART BERT Funding Plan Presentation
TPO FPC SMART BERT Funding Plan PresentationTPO FPC SMART BERT Funding Plan Presentation
TPO FPC SMART BERT Funding Plan Presentation
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Georgia Transportation Infrastructure Bank
Georgia Transportation Infrastructure BankGeorgia Transportation Infrastructure Bank
Georgia Transportation Infrastructure Bank
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation Projects
 
Reston Transportation Service District FY 2019 Tax Rate Discussion
Reston Transportation Service DistrictFY 2019 Tax Rate DiscussionReston Transportation Service DistrictFY 2019 Tax Rate Discussion
Reston Transportation Service District FY 2019 Tax Rate Discussion
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
SMART Plan Regional Funding Profiles
SMART Plan Regional Funding ProfilesSMART Plan Regional Funding Profiles
SMART Plan Regional Funding Profiles
 
TPO FPC SMART Financial Plan Framework presentation
TPO FPC SMART Financial Plan Framework presentationTPO FPC SMART Financial Plan Framework presentation
TPO FPC SMART Financial Plan Framework presentation
 
TPO FPC SMART Presentation on Special Assessments
TPO FPC SMART Presentation on Special AssessmentsTPO FPC SMART Presentation on Special Assessments
TPO FPC SMART Presentation on Special Assessments
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule Update
 
TPO FPC SMART Special Assessments Presentation
TPO FPC SMART Special Assessments PresentationTPO FPC SMART Special Assessments Presentation
TPO FPC SMART Special Assessments Presentation
 

Más de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...Andy (Avraham) Blumenthal
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptxYasinAhmad20
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...anjanibaddipudi1
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...IT Industry
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeRahatulAshafeen
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdflambardar420420
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhbhavenpr
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfssuser5750e1
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...hyt3577
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...srinuseo15
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdomlunadelior
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkobhavenpr
 
Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Insiger
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsVoterMood
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...Faga1939
 

Último (20)

America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 

Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update

  • 1. Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update Transportation Committee Fairfax County Board of Supervisors May 7, 2013
  • 2. Presentation Outline • Phase 1 Status Report • Phase 2 Status Report • Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update • Recommendation of Preliminary TIFIA Allocation • Requirements from Funding Partners • Phase 1 Plan of Finance – Closeout • Staff Recommendations • Timeline 2
  • 3. Phase 1 – Status Report (asofApril24,2013) Status • Construction: 90% Complete • Final Design: 100% Complete • Utility Relocation: 100% Complete • Property Acquisition: All rights of entry obtained • Track Work: 100% Complete • Stations: • McLean – 80% • Tysons Corner – 75% • Greensboro – 65% • Spring Hill – 65% • Wiehle – 84% • First Delivery of Rail Cars – February 2014 • Wiehle Garage: 88% Complete • Garage Substantial Completions: July 19, 2013 • Roadway Improvements (ROD): 67% complete • August/September 2013 completion Budget • Revised Budget Authorized: $2.905B • Expended to Date: $2.2B • County Phase 1 share: $467.8M • Tax District Funds: $400M (Funding Gap = $67.8M) • Fairfax County share of Project expenditures through fourth quarter 2012 = $369.1M • $150M received from Commonwealth Schedule • Substantial Completion: September 7, 2013 • WMATA Testing and Acceptance: August – December 2013 • West Falls Church Yard Completion: December 2013 • Sound Box and Tail Track: November 2013 • Estimated Passenger Revenue Service: December 31, 2013 Current Milestones – Past 30 Days • Entire 3rd Rail energized for Metrorail train testing. • Tunnel Clearance – No issues per WMATA • All five stations under construction with efforts on mechanical, electrical, plumbing, and station finishes • Phase 1 Maintenance and Land Conveyance process ongoing: • Fairfax County will retain ownership of Kiss and Ride at McLean • Fairfax County will operate through an easement Kiss and Ride at Spring Hill Station • Regional planning effort underway for Phase 1 bus service (Fairfax Connector, WMATA, Washington Flyer, PRTC, Loudoun Transit) • Fairfax County 2nd round of Public Meetings ongoing • Ask Fairfax online chat completed 3
  • 4. Phase 2 – Status Report (asofApril24,2013) Status • Packet A Price Proposals Opened – April 19, 2013 • Project estimate Packet A = $1.4B - $1.6B vs. $1.177B low bid • Positive impact on toll rates = $300M (est.) • Packet A Contract Award: May 2013 • Packet A Notice to Proceed: June 2013 • 5 Bid Packages: • Packet A - Rail Line, Station, and Systems (includes Innovation Center Station) • Packet B – Yard and Shop • Packet C (may not be issued) – Parking Garages • Packet D – ROW • Packet E – Utilities • Fairfax County working to fund & construct Herndon and Innovation Center garages outside of project • Financial Plan status: • Transportation Sub Committee May 7, 2013 • BOS May 14, 2013 Innovation Center (RT 28) Station • Station included in Packet A bid. • County using its best efforts to mitigate some station costs on south side. (ROW, alternative site work funding, and improved site layout for: garage, bus bay, and kiss/ride design. ) • Station cost will have to be funding either in part or whole per the funding agreement (County funding agreement share 16.1%). • County also pursuing funding from TIGER Grants and NVTA Budget • Cost Estimate: $3.093B • Cost Estimate with value engineering and alternative funding for garages & Innovation Center Station: $2.7B • Cost to build garages in Fairfax County: $105M est. • Fairfax County share for Phase 2 ranges from $433M – $498M, Tax District capped at $330M Schedule • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 Current Milestones Past 30 Days • FTA oversight of Phase 2 under discussion: Ongoing • TIFIA Letter of Interest submitted: Ongoing • WMATA Art in Transit: Selection: Ongoing • Reston Town Center Tunnel Design under review by WMATA and MWAA 4
  • 5. Request Board Approval of Staff Recommendations • Approve the Preliminary TIFIA Allocation of $1.9b amongst the Funding Partners, with County to receive $475m • Approve the County Credit Pledge of the C & I Fund and the Phase 2 Tax District to TIFIA; Potential use of Moral Obligation from General Fund to meet AA Category Rating mandated from USDOT • Request Credit Ratings from the bond rating agencies to comply with TIFIA Credit Review ($90,000) • Approve the $100,000 down payment required from the County to move forward in the TIFIA Letter of Interest (LOI) review process • Review short term financing options to cover the $67m for balance of County contributions for Phase 1. This will be paid off with receipt of TIFIA funds 5
  • 6. Transportation Infrastructure Finance and Innovation Act (TIFIA) Status Update - Recommendation of Preliminary TIFIA Allocation 6
  • 7. TIFIA Financing Overview • Federal credit assistance in the form of direct loans (not grants) to finance surface transportation projects of national and regional significance • USDOT Secretary LaHood departing & accelerated turnaround time for documents • Improved access to capital markets, flexible repayment terms, and potentially more favorable interest rates than can be found in private capital markets for similar instruments • Loan Repayment Deferral Option - 5 years after project completion (2023) • Alternatively – conduct open market bond sale & debt service payments immediately 7
  • 8. Silver Line Cost Allocation – Funding Partners Funding Partner % Share TPE - Baseline $ Share TPE - Baseline Other – Garages Funding Partner Total (TPE Baseline + Garages) Dulles Toll Road* 75% $4,262,763,750 - $4,262,763,750 Fairfax 16.1% 915,073,285 146,721,000 1,061,794,285 Loudoun 4.8% 272,816,880 168,413,000 441,229,880 MWAA – Aviation Funds 4.1% 233,031,085 - 233,031,085 Total 100.00% $5,683,685,000 $315,134,000 $5,998,819,000 * Includes $900m from FTA New Starts (16.1%), $275m from Commonwealth (4.9%). Net to Dulles Toll Road is 54%. Allocation assumes the add’l $150m + $300m for Phase 2 will be used to pay interest on Dulles Toll Road Revenue Bonds, not direct project costs. 8
  • 9. Silver Line Total Project Estimate - Fairfax County Costs 16.1% Phase 1 Phase 2 Total Total Baseline $2,905,685,000 $2,778,000,000 $5,683,685,000 County Share @ 16.1% 467,815,285 447,258,000 915,073,285 Less Tax Districts (400,000,000) (330,000,000) (730,000,000) Net County due $67,815,285 $117,258,000 $185,073,285 Garages Herndon-Monroe $80,959,000* $80,959,000 Route 28 65,762,000* 65,762,000 Total Garages $146,721,000 $146,721,000 TOTAL (Baseline + Garages) $467,815,285 $593,979,000 $1,061,794,285 *Per 100% P/E and consistent with MWAA documents; County believes costs will be lower and in the process of a feasibility study 9
  • 10. TIFIA Allocation: Funding Partner Consensus Funding Partner Funding Partner Total Project Cost TIFIA Allocation Fairfax $1,061,794,285 $475,000,000 Loudoun 441,229,880 200,000,000 MWAA – Aviation Funds 233,031,085 - Dulles Toll Road 4,262,763,750 1,304,610,270 Total $5,998,819,000 $1,979,610,270 • Meets MWAA goal of $1.2-$1.4b for the Toll Road • Counties maintain equity of TIFIA allocation equal to 45% Total Project Cost • December 2012 – Per USDOT Project Will Remain Eligible for 33% TIFIA Loan or $1.9b ($5.9b * 33%) 10
  • 11. TIFIA Premium Projections A B C D E (C * D) Funding Partner USDOT Requested Minimum Credit Rating Anticipated TIFIA Premium TIFIA Allocation* USDOT Premium Subsidy Allocation Fairfax AA Category 2% $475,000,000 $9,500,000 Loudoun AA Category 2% 200,000,000 4,000,000 Dulles Toll Road Investment Grade (BBB Category) 12% 1,304,610,270 156,553,232 Total $1,979,610,270 $170,053,232 Premium allocation evaluated/ reviewed heavily by TIFIA office when awarding project funding * Assumes MWAA Aviation Funds receive no TIFIA Loan 11
  • 12. TIFIA Status Update – Requirements from Funding Partners 12
  • 13. TIFIA Financing • Competitive Interest Rates that correlate to 30-Year Treasury Note • Flexible call options - prepay outstanding principal • Potential future refunding opportunities • USDOT Expected Ratings from Funding Partners • AA Category Rating from Counties • Investment Grade from Dulles Toll Road (MWAA) • Pledge two County sources for Plan of Finance • Commercial and Industrial Tax Fund • Dulles Rail Phase 2 Tax District ($330 million) • May be required to include Moral Obligation of the County General Fund if AA Category Rating is not achieved 13
  • 14. USDOT Information Request – April 2013 • Complete County Plan of Finance for TIFIA • Commercial and Industrial Tax Fund • Dulles Rail Phase 2 Tax District ($330 million) • Indicative Rating Letter on the TIFIA Loan • USDOT EXPECTS Counties to achieve rating in the AA Category • Initial review from the Credit Rating Agencies ($90,000) • Feasibility Study for Each Source of Credit Pledged • MWAA Toll Road Study • Counties expected to submit standard information: tax assessment, economic, and demographic information • Credit Processing Down Payment of $100,000 from each funding partner 14
  • 15. County Plan of Finance for TIFIA - Commercial & Industrial Tax Fund • Tax Rate of 12.5 cents per $100 of AV & generates approximately $51m revenue annually • Previously recommended to finance County project costs outside of the two tax districts: Phase 1 ($67.8m) & Phase 2 ($117.3m) • Planning Guideline for Long Term Forecasting: • 50% of expenses for Tysons / Silver Line • 50% of expenses for Remainder Countywide Projects • Loan Repayment Deferral Option - 5 years after project completion (2023) • Redirect previously forecasted monies required for debt service to fund other Countywide projects (equates to approximately $70m total from 2014-2023) 15
  • 16. County Plan of Finance for TIFIA - Phase 2 Tax District $330 million • Estimated stand alone current rating of this district likely “A” Category, thus enhancement necessary • Comparative Assessed Value 1/1/13: Phase 1 $11.4b vs. Phase 2 $7.5b • Allow for growth district tax base / assessed value, similar to Phase 1 Tax District • Phase 2 Tax Rate – 20 cents for FY 2014 • Initially began at 5 Cents in FY 2011, with 5 cent laddered increases • Remain at this rate until rail service begins 2018, then ability to increase to 25 cents per Petition • Accumulation of tax collections to provide for early repayment of outstanding principal at regular intervals • Staff recommendation that C & I Fund be used back this Tax District for credit enhancement • General Fund Moral Obligation may be needed to reach AA Category if C & I Fund insufficient 16
  • 17. Financing Dulles Rail - Alternate Options Public Sector Sources Private Sector Sources State/Feder al Funding General Fund (Pay Go) G.O. Bonds C&I Funds Meals Tax (Pay Go) 100% TIF Capped TIF Service District /CDA Developer Contributions Cost of Financing / Carrying Cost (Lowest to High) ■ ■ ■  ■    ■ Length of Time to Accrue Funds (Sooner to Later)   ■       General Fund Impact (Low to High) ■  ■ ■ ■   ■ ■ Impact on Redevelopment (Low to High)  ■ ■  ■ ■ ■   Impact to G.O. Debt (Low to High) ■ ■  ■ ■ ■ ■ ■ ■ Ability to Meet Capital Requirements (High to Low)     ■ ■  ■  Requires Third Party Concurrence (Degree of Difficulty)  ■    ■ ■   ■ Low Impact and/or Most Beneficial  Medium Impact and/or of Concern  High Impact and/or Most Difficult 17 Other Potential Funding Options: NVTA & Federal TIGER Grants
  • 18. Fairfax County Portion Remaining Dulles Rail Financing Phase 1 Phase 2 Total Total Project Estimate (TPE) $2,905,685,000 $2,778,000,000 $5,683,685,000 County Share @ 16.1% 467,815,285 447,258,000 915,073,285 Less Tax Districts (400,000,000*) (330,000,000) (730,000,000) Net County due $67,815,285 $117,258,000 $185,073,285 Total County Remaining Financing Needed $67,815,285 $447,258,000 $515,073,285 *paid to date to MWAA 18
  • 19. Fairfax County Cashflow Remaining Dulles Rail Financing Source Funds Amount Source Debt Service Comment TIFIA $67.8m C & I Fund Balance Phase 1 costs beyond $400m from Phase 1 Tax District; TIFIA may be used to repay short term financing (2013) TIFIA $117.3m C & I Fund Phase 2 costs beyond $330m from Phase 2 Tax District (2013-2018) TIFIA $289.9m Phase 2 Tax District 88% of Phase 2 Tax District’s $330m (2013-2018) Total TIFIA $475.0m 45% Total County Project Cost Phase 2 Tax District Bond Sale or Cash $40.1m Phase 2 Tax District Phase 2 Tax District Bond Sale or Cash Contribution (2018) Total Remaining Financing $515.1m 19
  • 20. County Phase 1 Cost - $467m • Phase 1 Tax District fulfilled $400 million obligation • Establish a plan of finance to cover remaining $67m to close out the County’s Phase 1 contributions • TIFIA Funds are not expected until end of the Calendar Year 2013 at the earliest • County Staff and Financial Advisor review of short term financing options to address the $67m: • Use portion of County’s current $100m Line of Credit • Bond Anticipation Note (BAN) • Staff recommendation: Utilize the Line of Credit & then pay off from receipt of TIFIA funds. 20
  • 21. Recommendations – Consistent with May 14th Board Item • Approve the Preliminary TIFIA Allocation of $1.9b amongst the Funding Partners, with County to receive $475m • Approve the County Credit Pledge of the C & I Fund and the Phase 2 Tax District to TIFIA • Goal to receive AA Category Rating and assumes no Moral Obligation • Phase 2 Tax District to utilize $290m of Preliminary TIFIA & seeking Moral Obligation (e.g. Credit Enhancement) from C & I Fund • Request Credit Ratings from the bond rating agencies to comply with TIFIA Credit Review ($90,000) • Approve the $100,000 down payment required from the County to move forward in the TIFIA LOI review process • Review short term financing options to cover the $67m for balance of County contributions for Phase 1. This will be paid off with receipt of TIFIA funds 21
  • 22. Timeline Date Item October 2012 MAP-21 Revised TIFIA Loan Notification (33% to 49%) October 2012 Funding Partners Submits LOI USDOT TIFIA (@ 49%) December 2012 TIFIA request to Funding Partners for more information January 2013 Funding Partners discussion on TIFIA Allocation April / May 2013 MWAA Awards Phase 2 Design-Build Contract May 2013 Board Discussion on TIFIA Allocation May 2013 Discussion with Bond Rating Agencies on County Credit for TIFIA May 2013 Submit County materials to TIFIA Summer 2013 County Interim Financing to cover balance of Phase 1 costs December 2013 Targeted Closing on TIFIA Loan for Funding Partners December 2013 Begin Service for Phase 1 Spring 2014 Refinance Interim Financing for balance Phase 1 costs December 2018 Begin Service for Phase 2 22