SlideShare una empresa de Scribd logo
1 de 31
Descargar para leer sin conexión
Woodglen Lake Dredging and Restoration
Department of Public Works and Environmental Services
Woodglen Lake Facts

 Lake Surface Area = 12.5 acres
 Sediment Pool Capacity =
  160,000 cubic yards (CY)
 Current sediment in lake =
  32,500 CY
 Estimated annual sediment load   17 feet
  = 1,244 CY
                                   32,500 CY
Watershed

 Drainage Area = 740
  acres (1.15 square
  miles)
 Pohick Creek
  Watershed
 Sideburn Branch
Woodglen Lake
Woodglen Lake: Sediment Thickness
Woodglen Lake: Water Depth
Woodglen Lake: Dewatering Basin




         Inactive
      Dewatering Basin




                                  Available Exclusively by DigitalGlobe
                                  ©2013 Microsoft Corporation © 2012 Nokia
Lake Restoration and Dredging Project

 Project Goals
 Restore sediment pool capacity
    Downstream water quality benefits
    Lake water quality
    Esthetics
 Improve lake water quality and habitat
 Stabilize stream segment
 Provide long term maintenance improvements
Dredging Alternatives


1. Mechanically dredge deposited
   sediment and haul wet




2. Drain lake and dry deposited
   sediment in place before hauling
Lake Barton Example

PRE-DREDGING:
An estimated
35,000 cubic yards
of sediment had
accumulated in
the lake, forming
islands and
reducing water
levels to less than
three feet in most
areas.
Lake Barton Example: Pre-Dredging
Lake Barton Example: Dredging in Progress

DREDGING:
Dredging took
place without
draining the lake.
Lake Barton Example: Dredging in Progress
Lake Barton Example: Completed Project
Lake Needwood Example

                               Lake Needwood:
                               Montgomery County, MD




Dredging:
The lake was drained and the
sediment was dried in-place.
Lake Needwood Example: Dredging
Dredge Alternative – In the Wet

 General Sequence
    Establish access and staging areas
    Conduct dredging utilizing barges
    Haul wet sediment to disposal site
     for drying
 Benefits
    Less weather dependent
    Quicker initial start to dredging
    Less potential for schedule extensions or delay
 Concerns
    Increased sediment handling effort at disposal area
    Potentially higher cost
Dredge Alternative – In the Dry

 General Sequence
      Initiate drawdown of lake
      Establish access and staging areas
      Establish diversion channels within lake
      Conduct dredging
 Benefits
    Higher daily sediment removal rates
    Minimal sediment handling effort at disposal area
    Potentially lower cost
 Concerns
      Very weather dependent
      Higher potential for delays due to weather
      Typically more odor from entire lake bottom being exposed
      Need to relocate/salvage fish
Woodglen Lake

Dredging:
32,500 Cubic
                        Staging Area
Yards
Lake Restoration

     In-lake forebay
     Wetland planting
     Shoreline stabilization
     Fish habitat
     Fish stocking


Fish habitat created from
      salvaged trees




                                                                   Lake Barton:
                                               Fish stocking by Virginia Game and Inland Fisheries
Chesapeake Bay Preservation Areas

 Buffer Restoration
Woodglen Lake: Shoreline Restoration
Woodglen Lake: Shoreline Restoration

Woodglen
Lake Existing
Conditions
Shoreline Protection Options
Fish Habitat Structures
Stream Stabilization
Woodglen Lake: Site Access & Staging
Access During Construction

 Lake Barton
Huntsman Lake
Woodglen Lake




                       Available Exclusively by DigitalGlobe
                       ©2013 Microsoft Corporation © 2012 Nokia




                                       2011
Woodglen Lake Dredging and Restoration
              Project Timeline and Coordination

   Community coordination at Design and Construction phase
   June 2013: Final Design
   July 2013: Construction bid advertisement
   September/October 2013: Begin dredging
   Project duration: 6 - 7 months
   Lake may be drained for entire project (dredging method
    depends on project bidding)
     Partial lake drawdown alternative to be evaluated
Woodglen Lake Dredging and Restoration

Contacts
 Dipmani Kumar, Project
  Manager
    703-324-4612
    Dipmani.kumar@fairfaxcounty.gov

 Matt Meyers, Branch Chief
    703-324-5651
    Matthew.meyers@fairfaxcounty.gov

 Partners:

Más contenido relacionado

La actualidad más candente

Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Fairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Fairfax County
 
Tripps Run Stream Improvement
Tripps Run Stream ImprovementTripps Run Stream Improvement
Tripps Run Stream ImprovementFairfax County
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Fairfax County
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Fairfax County
 
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization ProjectScotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization ProjectFairfax County
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Fairfax County
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Fairfax County
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectFairfax County
 
Habitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterHabitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterFairfax County
 
Sequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectSequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectFairfax County
 
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Fairfax County
 
Autumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectAutumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectFairfax County
 
Lake Development Authority_CEO
Lake Development Authority_CEOLake Development Authority_CEO
Lake Development Authority_CEOEkonnect
 
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectColvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectFairfax County
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFairfax County
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaFairfax County
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Fairfax County
 

La actualidad más candente (20)

Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
Tripps Run Stream Improvement
Tripps Run Stream ImprovementTripps Run Stream Improvement
Tripps Run Stream Improvement
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014
 
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization ProjectScotts Run Tributary at Windy Hill Road: Stream Stabilization Project
Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
Habitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterHabitat Improvement for Cleaner Water
Habitat Improvement for Cleaner Water
 
Sequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectSequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit Project
 
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
 
Autumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectAutumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit Project
 
Lake Development Authority_CEO
Lake Development Authority_CEOLake Development Authority_CEO
Lake Development Authority_CEO
 
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectColvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly Drive
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, China
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 

Similar a Woodglen Lake Dredging and Restoration

Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall RestorationFairfax County
 
8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock
8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock
8. CaBA Conference 2017 Eurasian Beaver - Alan PuttockCaBASupport
 
Impacts of hydel dam projects in world
Impacts of hydel dam projects in worldImpacts of hydel dam projects in world
Impacts of hydel dam projects in worldSoubhagya Tripathy
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Alastair Driver Multiple Benefits
Alastair Driver Multiple BenefitsAlastair Driver Multiple Benefits
Alastair Driver Multiple Benefitsobjectiveassociates
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meetingMCDEP
 
Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting showMCDEP
 
Piney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter WayPiney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter WayFairfax County
 
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNECAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNEGeorge Dumitrache
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead HavenSWCNabi
 
Weather Hazards 2
Weather Hazards 2Weather Hazards 2
Weather Hazards 2total
 

Similar a Woodglen Lake Dredging and Restoration (20)

Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
 
Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall Restoration
 
The Dee HELP Basin
The Dee HELP BasinThe Dee HELP Basin
The Dee HELP Basin
 
8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock
8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock
8. CaBA Conference 2017 Eurasian Beaver - Alan Puttock
 
Impacts of hydel dam projects in world
Impacts of hydel dam projects in worldImpacts of hydel dam projects in world
Impacts of hydel dam projects in world
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Alastair Driver Multiple Benefits
Alastair Driver Multiple BenefitsAlastair Driver Multiple Benefits
Alastair Driver Multiple Benefits
 
Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meeting
 
Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting show
 
Natural Flood Management Strategic Development
Natural Flood Management Strategic DevelopmentNatural Flood Management Strategic Development
Natural Flood Management Strategic Development
 
Piney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter WayPiney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter Way
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNECAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE
CAMBRIDGE AS GEOGRAPHY - CASE STUDY: RIVER HARBOURNE
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Weather Hazards 2
Weather Hazards 2Weather Hazards 2
Weather Hazards 2
 
Alastair Driver's drivers for better catchment management
Alastair Driver's drivers for better catchment management Alastair Driver's drivers for better catchment management
Alastair Driver's drivers for better catchment management
 

Más de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Último

Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...Faga1939
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPsychicRuben LoveSpells
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...IT Industry
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)Delhi Call girls
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdflambardar420420
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhbhavenpr
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Delhi Call girls
 
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...srinuseo15
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...anjanibaddipudi1
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Delhi Call girls
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...Andy (Avraham) Blumenthal
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsVoterMood
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...hyt3577
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfssuser5750e1
 

Último (20)

Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 

Woodglen Lake Dredging and Restoration

  • 1. Woodglen Lake Dredging and Restoration Department of Public Works and Environmental Services
  • 2. Woodglen Lake Facts  Lake Surface Area = 12.5 acres  Sediment Pool Capacity = 160,000 cubic yards (CY)  Current sediment in lake = 32,500 CY  Estimated annual sediment load 17 feet = 1,244 CY 32,500 CY
  • 3. Watershed  Drainage Area = 740 acres (1.15 square miles)  Pohick Creek Watershed  Sideburn Branch
  • 7. Woodglen Lake: Dewatering Basin Inactive Dewatering Basin Available Exclusively by DigitalGlobe ©2013 Microsoft Corporation © 2012 Nokia
  • 8. Lake Restoration and Dredging Project  Project Goals  Restore sediment pool capacity  Downstream water quality benefits  Lake water quality  Esthetics  Improve lake water quality and habitat  Stabilize stream segment  Provide long term maintenance improvements
  • 9. Dredging Alternatives 1. Mechanically dredge deposited sediment and haul wet 2. Drain lake and dry deposited sediment in place before hauling
  • 10. Lake Barton Example PRE-DREDGING: An estimated 35,000 cubic yards of sediment had accumulated in the lake, forming islands and reducing water levels to less than three feet in most areas.
  • 11. Lake Barton Example: Pre-Dredging
  • 12. Lake Barton Example: Dredging in Progress DREDGING: Dredging took place without draining the lake.
  • 13. Lake Barton Example: Dredging in Progress
  • 14. Lake Barton Example: Completed Project
  • 15. Lake Needwood Example Lake Needwood: Montgomery County, MD Dredging: The lake was drained and the sediment was dried in-place.
  • 17. Dredge Alternative – In the Wet  General Sequence  Establish access and staging areas  Conduct dredging utilizing barges  Haul wet sediment to disposal site for drying  Benefits  Less weather dependent  Quicker initial start to dredging  Less potential for schedule extensions or delay  Concerns  Increased sediment handling effort at disposal area  Potentially higher cost
  • 18. Dredge Alternative – In the Dry  General Sequence  Initiate drawdown of lake  Establish access and staging areas  Establish diversion channels within lake  Conduct dredging  Benefits  Higher daily sediment removal rates  Minimal sediment handling effort at disposal area  Potentially lower cost  Concerns  Very weather dependent  Higher potential for delays due to weather  Typically more odor from entire lake bottom being exposed  Need to relocate/salvage fish
  • 20. Lake Restoration  In-lake forebay  Wetland planting  Shoreline stabilization  Fish habitat  Fish stocking Fish habitat created from salvaged trees Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
  • 21. Chesapeake Bay Preservation Areas  Buffer Restoration
  • 23. Woodglen Lake: Shoreline Restoration Woodglen Lake Existing Conditions
  • 27. Woodglen Lake: Site Access & Staging
  • 29. Huntsman Lake Woodglen Lake Available Exclusively by DigitalGlobe ©2013 Microsoft Corporation © 2012 Nokia 2011
  • 30. Woodglen Lake Dredging and Restoration Project Timeline and Coordination  Community coordination at Design and Construction phase  June 2013: Final Design  July 2013: Construction bid advertisement  September/October 2013: Begin dredging  Project duration: 6 - 7 months  Lake may be drained for entire project (dredging method depends on project bidding)  Partial lake drawdown alternative to be evaluated
  • 31. Woodglen Lake Dredging and Restoration Contacts  Dipmani Kumar, Project Manager  703-324-4612  Dipmani.kumar@fairfaxcounty.gov  Matt Meyers, Branch Chief  703-324-5651  Matthew.meyers@fairfaxcounty.gov  Partners: