Ministerie van Binnenlandse Zaken en Koninkrijksrelaties Workshop Safety-Chain   Rotterdam, 8-9 November 1999 A case study...
C.O.M. Foligno A brief history about the management style adopted in the  emergency following the earthquake in 1997 G. Ro...
<ul><li>The 26 th  of september 1997 an earthquake with two major shakes has devastated large areas of the Regions Umbria ...
<ul><li>The rescue of victims and assistance to the population  trying to save as much persons as possible   </li></ul><ul...
The national  Chain of Command  in big emergencies National Level Regional / Provincial Level Local Level
The C.O.M. of Foligno in 1997 organized in compliancewith the civil protection guideline called “ Augustus”
C.O.M. -  Management <ul><li>Operation Center: main entrance/parking </li></ul>Foligno 1997
<ul><li>Operation Center: Multi Agency Room </li></ul>C.O.M. -  Management Foligno 1997
<ul><li>Operation Center: Director/Chief Office </li></ul>C.O.M. -  Management Foligno 1997
The “numbers” of the Foligno’sCOM <ul><li>12  Municipalities  </li></ul><ul><li>90.000  inhabitants </li></ul><ul><li>14.0...
C.O.M. Strategic activity in Foligno <ul><li>General Strategy : To operate mainly in a role of support and coordination of...
C.O.M. -   Resources <ul><li>National Fire Corp:  Nocera Umbra  Base Camp </li></ul>Foligno 1997
<ul><li>National Fire Corp:  Polylogistic Fire Truck </li></ul>C.O.M. -   Resources Foligno 1997
<ul><li>National Fire Corp:  Polylogistic Fire Truck </li></ul>C.O.M. -   Resources Foligno 1997
C.O.M. -   Resources National Fire Corp:  Foligno  Base Camp Foligno 1997
<ul><li>National Fire Corp:  Foligno  Base Camp </li></ul><ul><li>Helicopters’ Mobile Hangar </li></ul>C.O.M. -   Resource...
<ul><li>National Fire Corp:  Foligno  Base Camp </li></ul><ul><li>Helicopters’ Mobile Hangar </li></ul>C.O.M. -   Resource...
<ul><li>National Fire Corp:  Foligno  Base Camp Heliport </li></ul>C.O.M. -   Resources Foligno 1997
<ul><li>Red Cross:  Foligno  Base Camp </li></ul>C.O.M. -   Resources Foligno 1997
<ul><li>Red Cross:  Colfiorito  Base Camp </li></ul>C.O.M. -   Resources Foligno 1997
<ul><li>Red Cross: Mobile Hospital  </li></ul>C.O.M. -   Resources Foligno 1997
<ul><li>Volunteers  </li></ul>C.O.M. -   Resources Foligno 1997
C.O.M. -  Operations <ul><li>MITIGATION: Building Stabilization </li></ul>Foligno 1997
C.O.M. -  Operations <ul><li>MITIGATION: Building Stabilization </li></ul>Foligno 1997
C.O.M. -   Assistance <ul><li>First recovery in tents or caravans </li></ul>Foligno 1997
C.O.M. -   Assistance <ul><li>First recovery in tents or caravans </li></ul>Foligno 1997
C.O.M. -   Assistance <ul><li>Temporary villages in prefab homes </li></ul>Foligno 1997
C.O.M. -   Assistance Temporary sheltering in prefab homes Foligno 1997
C.O.M. -   Assistance <ul><li>Temporary sheltering in prefab homes </li></ul>Foligno 1997
C.O.M. -   Assistance <ul><li>Temporary sheltering in prefab homes </li></ul>Foligno 1997
C.O.M. -   Assistance <ul><li>Temporary sheltering in prefab homes </li></ul>Foligno 1997
<ul><li>Aspects that caused difficulties in managing the emergency: </li></ul><ul><li>Continuous shaking that lasted for s...
Thank You for Your kind Attention Giuseppe Romano Gianmario Gnecchi
Próxima SlideShare
Cargando en...5
×

Com Foligno Umbria Earthquake sept 1997

923

Published on

Brief description of the activities of COM-Foligno during the earthquake of september 1997 in Umbria ITALY

Published in: Tecnología
0 comentarios
0 Me gusta
Estadísticas
Notas
  • Sea el primero en comentar

  • Be the first to like this

Sin descargas
reproducciones
reproducciones totales
923
En SlideShare
0
De insertados
0
Número de insertados
0
Acciones
Compartido
0
Descargas
8
Comentarios
0
Me gusta
0
Insertados 0
No embeds

No notes for slide

Transcript of "Com Foligno Umbria Earthquake sept 1997"

  1. 1. Ministerie van Binnenlandse Zaken en Koninkrijksrelaties Workshop Safety-Chain Rotterdam, 8-9 November 1999 A case study - The 1997 Earthquake in Central Italy Giuseppe Romano & Gianmario Gnecchi
  2. 2. C.O.M. Foligno A brief history about the management style adopted in the emergency following the earthquake in 1997 G. Romano G. Gnecchi
  3. 3. <ul><li>The 26 th of september 1997 an earthquake with two major shakes has devastated large areas of the Regions Umbria and Marche in Central Italy: - at 02:33 ( magnitude 5.5, VIII° degree M.C.S. ) - at 11:40 ( magnitude 5.8, VIII°-IX° degree M.C.S. ) </li></ul>The event
  4. 4. <ul><li>The rescue of victims and assistance to the population trying to save as much persons as possible </li></ul><ul><li>The immediate sheltering , protection and feeding of the population </li></ul><ul><li>The control of the operativity and functionality of infrastructures and “essential services” with first urgent interventions </li></ul>The main objectives were: <ul><li>The stabilization of dangerous buildings and the control of efficiency of the civil buildings </li></ul><ul><li>The realization of temporary villages with mobile prefab homes </li></ul><ul><li>The safety and the security in the temporary villages (heating systems, electric appliances, traffic control, checks for undesidered persons) </li></ul><ul><li>The recovery of the material used as first response (tents, caravans) </li></ul><ul><li>The progressive return to the normal activities: social / economical / productive </li></ul>
  5. 5. The national Chain of Command in big emergencies National Level Regional / Provincial Level Local Level
  6. 6. The C.O.M. of Foligno in 1997 organized in compliancewith the civil protection guideline called “ Augustus”
  7. 7. C.O.M. - Management <ul><li>Operation Center: main entrance/parking </li></ul>Foligno 1997
  8. 8. <ul><li>Operation Center: Multi Agency Room </li></ul>C.O.M. - Management Foligno 1997
  9. 9. <ul><li>Operation Center: Director/Chief Office </li></ul>C.O.M. - Management Foligno 1997
  10. 10. The “numbers” of the Foligno’sCOM <ul><li>12 Municipalities </li></ul><ul><li>90.000 inhabitants </li></ul><ul><li>14.000 evacuees hosted in the temporary villages/areas </li></ul><ul><li>111 sheltering areas with tents and/or roulottes </li></ul><ul><li>14 full operating “camp kitchen” </li></ul><ul><li>11 base-camps of the different emergency organizations </li></ul><ul><li>60 temporary villages with prefab homes </li></ul>Foligno 1997
  11. 11. C.O.M. Strategic activity in Foligno <ul><li>General Strategy : To operate mainly in a role of support and coordination of the Majors </li></ul><ul><li>Operational Activities : by mean of the Multiagency Operational Room </li></ul><ul><li>Management Activities : with the technical and administrative staff and the 13 Funcions </li></ul>
  12. 12. C.O.M. - Resources <ul><li>National Fire Corp: Nocera Umbra Base Camp </li></ul>Foligno 1997
  13. 13. <ul><li>National Fire Corp: Polylogistic Fire Truck </li></ul>C.O.M. - Resources Foligno 1997
  14. 14. <ul><li>National Fire Corp: Polylogistic Fire Truck </li></ul>C.O.M. - Resources Foligno 1997
  15. 15. C.O.M. - Resources National Fire Corp: Foligno Base Camp Foligno 1997
  16. 16. <ul><li>National Fire Corp: Foligno Base Camp </li></ul><ul><li>Helicopters’ Mobile Hangar </li></ul>C.O.M. - Resources Foligno 1997
  17. 17. <ul><li>National Fire Corp: Foligno Base Camp </li></ul><ul><li>Helicopters’ Mobile Hangar </li></ul>C.O.M. - Resources Foligno 1997
  18. 18. <ul><li>National Fire Corp: Foligno Base Camp Heliport </li></ul>C.O.M. - Resources Foligno 1997
  19. 19. <ul><li>Red Cross: Foligno Base Camp </li></ul>C.O.M. - Resources Foligno 1997
  20. 20. <ul><li>Red Cross: Colfiorito Base Camp </li></ul>C.O.M. - Resources Foligno 1997
  21. 21. <ul><li>Red Cross: Mobile Hospital </li></ul>C.O.M. - Resources Foligno 1997
  22. 22. <ul><li>Volunteers </li></ul>C.O.M. - Resources Foligno 1997
  23. 23. C.O.M. - Operations <ul><li>MITIGATION: Building Stabilization </li></ul>Foligno 1997
  24. 24. C.O.M. - Operations <ul><li>MITIGATION: Building Stabilization </li></ul>Foligno 1997
  25. 25. C.O.M. - Assistance <ul><li>First recovery in tents or caravans </li></ul>Foligno 1997
  26. 26. C.O.M. - Assistance <ul><li>First recovery in tents or caravans </li></ul>Foligno 1997
  27. 27. C.O.M. - Assistance <ul><li>Temporary villages in prefab homes </li></ul>Foligno 1997
  28. 28. C.O.M. - Assistance Temporary sheltering in prefab homes Foligno 1997
  29. 29. C.O.M. - Assistance <ul><li>Temporary sheltering in prefab homes </li></ul>Foligno 1997
  30. 30. C.O.M. - Assistance <ul><li>Temporary sheltering in prefab homes </li></ul>Foligno 1997
  31. 31. C.O.M. - Assistance <ul><li>Temporary sheltering in prefab homes </li></ul>Foligno 1997
  32. 32. <ul><li>Aspects that caused difficulties in managing the emergency: </li></ul><ul><li>Continuous shaking that lasted for several months </li></ul><ul><li>Extension of the territory involved </li></ul><ul><li>Distribution of popoulation in small villages spread out on the territory </li></ul><ul><li>Huge amount of storical, cultural and artistical sites and buildings </li></ul><ul><li>Aspects that helped to reduce the difficutlies in managing the emergency : </li></ul><ul><li>Few damage to the persons (only 12 deaths) </li></ul><ul><li>Few damages to animals (very lttle or limited problems in public health and hygiene </li></ul><ul><li>the network of communications structures with only minor damages (roads, bridges, …) </li></ul><ul><li>Public utilities services fully operating (electric power, gas, water, telephone and telecommunication </li></ul><ul><li>Immediate response of the civil protection structures </li></ul><ul><li>central position of the area compared with the rest of Italy </li></ul><ul><li>this helped the arrival of the resources. </li></ul><ul><li>Enough resources still available on site </li></ul>Key factors of the earthquake emergency in 1997
  33. 33. Thank You for Your kind Attention Giuseppe Romano Gianmario Gnecchi
  1. ¿Le ha llamado la atención una diapositiva en particular?

    Recortar diapositivas es una manera útil de recopilar información importante para consultarla más tarde.

×