6. Policy and Strategy for CCS in Korea
q Commitment of the 30% GHG reduction below BAU
by 2020 (Nov.’09)
q Framework Act on Low Carbon, Green Growth (14
April 2010)
Ø Presidential Committee on Green Growth: Major Policies
and Plans including CCS
Ø Announcement of Korean CCS Master Plan (July 13 2010)
§
§
Two large-scale integrated CCS demonstrations by 2020
Established Korea CCS Association in MOTIE, leading by
KEPCO (Nov. 2010)
q Korean ETS is slated on Jan 1, 2015
KEPCOP’s CCS Projects in Action
6
7. Korea CCS Demonstration Plans
q Two Large-scale integrated CCS demonstrations by 2020
Stage 1. Pilot demo
(10-30 MW)
1st
Demonstration Project
(KCCS-1)
2nd
Demonstration Project
(KCCS-2)
2010
Post-Combustion
(Dry or Wet)
Pilot Plant
Stage 2. Large-scale demo
(100-300 MW)
2014
FEED
2012
2016
Oxy-fuel or IGCC
Pilot Plant
FEED
2014
2018
Demonstration
(Link to Storage)
2016
2020
Demonstration
(Link to Storage)
q Allocated about US $1.74 billion
Ø Government: $ 0.74 billion (43%), Private: $ 1 billion (57%)
q New coal-fired power plant with CCS will take about 10-15%
share in CO2 reduction by 2030
q KEPCO is leading the development of large scale CCS
commercialization technologies
KEPCOP’s CCS Projects in Action
7
8. KEPCO’s CCS R&DD Strategies
KEPCO 2020 Target Tech
Coal/Gas
Power Plant
Post-combustion
- Solid sorbent
Post-combustion
- Adv. amine
CO2 Capture
Oxy-fuel
combustion
Pre-combustion
- Wet scrubbing
IGCC
Pre-combustion
- Solid sorbent
CCUS
Chemical Looping
Combustion
KEPCO 2025 Target Tech
CO2 Storage
KEPCOP’s CCS Projects in Action
CO2 Utilization
8
9. PostPost-combustion CO2 capture
- Solid sorbent technology
CO2 free flue gas
MHCO3
MHCO3
MHCO3
Regenerator
Carbonator
CO2
H2O
Solid sorbent
Steam
M2CO3
Flue gas
Schematic of Dry Post-Combustion
Technology
KEPCOP’s CCS Projects in Action
9
10. PostPost-Combustion CO2 Capture: Solid Sorbent
q Dry Regenerable Sorbent Technology
Ø KEPCO RI’s Solid Sorbent
Ø KIER’s Fluidized-Bed (FB) CO2 Capture Process
Ø Process scale-up: 0.5 kW(‘03)→25 kW(‘06)→0.5 MW (‘10)→10 MW(‘13)
q
0.5 MW Test-Bed (’02.10~’11.03), MEST (CDRS), US$ 11.2 M
Ø Achieved 85% CO2 capture rate from 25 kW BSU (2008)
Ø Commissioning 0.5 MW test-bed facility at KOSPO’s Hadong
Thermal Power Station (Unit # 3) on March 2010.
Ø Completed Phase 3 with 80% CO2 capture rate from 0.5 MW test-bed
with KEP-CO2P1 sorbent (1600 h)
q 10 MW Pilot Plant (’10.10~’14.09), MOTIE (KETEP), US$ 40 M
Ø 85±5% removal from 0. 5 MW test-bed with modified sorbent (1200 h)
Ø 10 MW site: KOSPO’s Hadong Thermal Power Station (Unit #8)
ü 2012.08.24: Ground-breaking ceremony
ü 2013. 3Q: Completing construction
ü 2013. 4Q~2014.3Q: Commissioning and long-term operation
KEPCOP’s CCS Projects in Action
10
11. 0.5 MW test-bed: Dry regenerable sorbent
q Scale: 0.5 MW slip-streamed
from 500 MW coal-fired power
plant(SC)
q Capacity: 10 tCO2/d
q Flue gas: coal-fired boiler
q Process: KIER’s Fluidized-bed
Process
q Sorbent: KEP-CO2P2 or P3
Ø 85±5% CO2 capture rate
Ø > 90% CO2 product purity
0.5 MW test-bed at KOSPO’s Hadong
coal-fired power plant,
KEPCOP’s CCS Projects in Action
q Startup: 2010.03.
q Pilot plant area: 10 x 6 x 24(H) m
q Location: Hadong, Korea.
KOSPO’s Hadong Thermal Power
Station (unit #3)
11
12. 10 MW Pilot plant: Dry regenerable sorbent
10MW Pilot Plant
H adong Power Plant, unit #8
q Scale: 10 MW slip-streamed from 500 MW
coal-fired power plant(SC)
q Capacity: 200 tCO2/d
q Flue gas: coal-fired boiler
q 0.5 MW Test-Bed
3D-view
H adong Power Plant, unit #3
Algae fond
q Sorbent: KEP-CO2P2
q Targets:
Ø
> 80% CO2 capture rate
Ø
> 95% CO2 purity
Ø
> 1000 h continuous operation
Ø
US$ 30/tCO2
q Startup: October, 2013
q Main plot area: 34 m(L)x15 m(W)x59 m(H)
q Location: Hadong, Korea. KOSPO’s
Hadong Thermal Power Station (unit #8)
KEPCOP’s CCS Projects in Action
12
14. PostPost-Combustion CO2 Capture:
Advanced Solvent
q Advanced Amine Solvent Technology
Ø KEPCO’s Wet Solvent (KoSol)
Ø KEPCO’s KoSol Solvent CO2 Capture Process
q 0.1 MW Test-Bed, (`08. 11 ~`11. 10) MOTIE (KETEP), US$ 8 M
Ø Commissioning 0.1 MW test bed facility at KOMIPO’s Boryeong Thermal
Power Station(Unit#8) on Oct. 2010
Ø Completed Campaign#1~#5 with KoSol-4 solvent (3,000 h)
Ø Achieved over 90% CO2 capture rate and 3.0~3.1 GJ/ton-CO2 regeneration
energy
q 10 MW Pilot Plant, (`10. 10~`14. 9) MOVIE (KETEP), US$ 42 M
Ø
Ø
Ø
Ø
Ø
10 MW site : KOMIPO’s Boryeong Thermal Power Station(Unit #8)
2013. 5. 24 : Completing construction
2013. 9. : Achieved > 90% CO2 capture rate in the early test-run
2013. 10. ~ 12. : Variable tests for optimum operation condition
2013. 12. ~ : Long-term operation
KEPCOP’s CCS Projects in Action
14
15. 0.1 MW Test bed, Advanced amine
q Scale: 0.1 MW slip-streamed from
500 MW coal-fired power plant(SC)
q Capacity: 2 tCO2/d
q Flue gas: coal-fired boiler
Absorber
Stripper
q Solvent: KoSol-4 *
· > 90% CO2 capture
· > 99% CO2 product purity
· 3.0~3.1 GJ/tCO2 regeneration energy
Reboiler
(on conventional wet scrubbing process)
q Plot area: LxWxH =12m x 7m x 25m
q Startup: Oct, 2010
q Location: city of Boryeong, Korea.
KOMIPO’s Boryeong Thermal Power
Station (unit #8)
0.1MW Test-bed at Boryeong coal-fired
power plant
KEPCOP’s CCS Projects in Action
* KoSol: KEPCO’s proprietary solvent
15/26
15
16. 10 MW Pilot Plant,
Advanced amine
q Scale: 10 MW slip-streamed from 500 MW
coal-fired power plant(SC)
q Capacity: 200 tCO2/d
q Flue gas: coal-fired boiler
q Solvent: KoSol-4 *
•
> 90% CO2 capture rate
•
> 99% CO2 product purity
•
3.0~3.1 GJ/tCO2 regeneration energy
(early test results)
•
Target of regen. energy: <2.8 GJ/tCO2
q Startup: May, 2013
q Plot area: LxWxH = 31m x 31m x 48m
q Location: City of Boryeong, Korea.
KOMIPO’s Boryeong Thermal Power
Station (unit #8)
KEPCOP’s CCS Projects in Action
16/26
16
17. PrePre-combustion CO2 capture
- Dry sorbent technology
S free Syngas
CO2
SO2
H2
MS
Regenerator
Desulfurizer
MS
Air
MO
Raw Syngas
Warm Gas Clean-up
SEWGS
KEPCOP’s CCS Projects in Action
17
18. Pre-Combustion CO2 Capture
Solid Sorbent
q Solid Sorbent Pre-Combustion CO2 Capture Technology
Ø Strategic Approach
• Minimize energy penalty and cost for CO2 capture
– Maintain high T & P through the whole process
CO2
Compression
Coal
CO2 Storage
H2S
Sorbent
WGS
Catalyst
HCl
sorbent
CO2
Sorbent
Oxygen
Gasifier
가스화기
Warm Gas
Cleanup
SEWGS
By One Loop Process
Combined
Cycle
Ø Warm Gas Clean-up
• Solid sorbent (KEPCO RI) & FB Process (KIER)
Ø One Loop Process for Pre-combustion CO2 Capture
• Solid Sorbents (KEPCO RI) & One-loop FB Process (KIER)
Ø Scale-up Schedule of Process Development
• 0.1 MW ('11) → 1~10 MW (‘18) → 300 MW (’18~)
Ø 2nd Phase Fund: US$ 30 M, Oct. 2011~ Sep. 2015
KEPCOP’s CCS Projects in Action
18
19. Chemical Looping Combustion
q
q
q
q
Intrinsic CO2 separation w/o ASU and CO2 Capture Facility
2nd Phase fund: US$ 5.6 M (Sep. 2006-Aug. 2011)
CO2 capture cost: <10~20 $/tCO2 (‘20)
Scale-up
Ø 50 kWth (‘09)→200 kWth (‘11)→1 MWth (‘18)→100 MW (‘18~)
q Participants: Process (KIER, Daegu City Gas Co., MEPS, NEXCOM)
Oxygen carrier (KEPCO & its 5 Thermal Power Co.)
Fuel + Air
CO2 + H2O
HXR
N2
N 2+MeO
Steam
Power
발전
Air
공기반응기
Air
(금속연소)
Reactor
HXR
HXR
Oxygen Carrier
CO2
H 2O
연료반응기
Fuel
(연료연소)
Reactor
Fuel
(CH4, Syngas)
Me
KEPCOP’s CCS Projects in Action
19
20. 200 kW CLC BSU
•
•
•
•
Oxidizer
•
Reducer
•
•
•
KEPCOP’s CCS Projects in Action
20
Scale: 200 kWth slip-streamed
from local H&P
Capacity: 1 tCO2/d (CO2 20 Nm3/h)
Fuel gas: Natural gas
Process: Dual fluidized-bed process
(KIER)
Oxygen carrier (KEPCO RI): batch test
– Fuel conversion >99.7%
– CO2 selectivity >99%
– 99% CO2 product purity
– NOx emission < 10 ppm
– CO + H2+CH4 <0.3 %
– O2 transfer capacity >12
wt% (AI <15%)
Startup: 2011.03 (100 h)
Pilot plant area: 5 x 5 x 6(H) m
Location: City of Daegu, Korea. Joo-kok
CES H & P plant
22. Summary
q For energy security and climate change, KEPCO offers the
comprehensible portfolio of CO2 capture technology.
q Two 10 MW pilot plants (dry sorbent and adv. amine) scaled-up
based on the results from 0.1- 0.5 MW test-bed runs are under
shakedown test, aiming to bring at least one commercial demo
project online by 2015~2017.
q The FEED study of the 100 MW oxyfuel combustion project was
completed in 2012 and MOTIE was putting the 100 MW prject on
hold recently.
q KEPCO RI with others also develops the key technologies of
pre-combustion and CLC with solid sorbents for advanced
power generation.
q KEPCOs with MOTIE’s support is moving big steps forwarding
to commercialize CCS technology by 2020.
q Looking for funding, strategic partners and opportunities to
demonstrate our technologies in Korea
KEPCOP’s CCS Projects in Action
22
24. CO2 Storage in Korea
• MOF: Korea Offshore CO2 Geological Storage Project (‘05-’15) (US$ 66M, 2 Phase ‘11-’15)
• MOTIE: Small-scale CO2 injection demonstration project, Phohang Basin (US$ 16.7 M, ‘13-’16)
24
25. Thank you for your attention!
KEPCOP’s CCS Projects in Action
25