SlideShare una empresa de Scribd logo
1 de 42
Descargar para leer sin conexión
Government & Pvt. Contractor
 Importer, Stockiest & Supplier
 Bridge Expansion Joints
 Bridge Bearing Pads
 Construction rubber Goods
 Construction Chemicals
 Allied Machineries

Address: Plot # 377 Nawab Siddiq Ali Khan Road, Garden West Lasbella,
         Karachi, Pakistan.
Phone # 0092 21 2232834
Cell #   0092 321 8218443
Fax #    0092 21 2259779
Email:   rainbowenterpris.aziz@gmail.com
Webpage: www.azizahmad.com
RAINBOW TRANSFLEX
INSTALLATION METHODOLOGY
Contents

Introduction                                   1

Equipments used in project                     2

Bridge Photographs (Portion A & B)             3-4

Installation Method of rainbow Transflex       5-14

Maintenance of Concrete & Rubber               15

Photographs of successful project              16-18

Accomplished Bridge (Experiment and Testing)   19-21

Premium Products                               23-30

Services                                       32-36

Test Reports                                   38

Conclusion
INTRODUCTION

Rainbow Developer’s is sister consultant firm of Rainbow Enterprises.

Rainbow Enterprises is a well reputed firm in commercial market since last decade, it
offers services in Rubber Chemicals, Construction Chemicals, Allied Machineries,
Industrial Machineries and many other premium products.

After the decent achievement in market arena, therefore managing committee of
Rainbow Enterprises has decided to move on the construction future and they
registered their firm in Pakistan Engineering Council and company imports numerous
construction related products i.e. Bridge Pads, Expansion Joints, Water Stop, Rubber
Fender, Road Studs, Road Paints and many other products and always try to facilitate
their customer their level best under the one roof.

The managing committee has also made joint venture with Rainbow Rubber Industry
which is also well reputed firm and this firm is specialized in Rubber Products since last
four decades and their supply is to all over Pakistan and Afghanistan especially in
bridges and other mega projects with their Customers, Private departments and
Government sector satisfaction.

Rainbow Developers also has introduced so many kinds of expansion joints in rubber
and alloy metal, but company recommendation is Rainbow Transflex.

Regarding Expansion Joints, Rainbow Transflex has very good reputation in the market
due to his physical manifestation and this item is easy to install as well as its easy to
maintain. Due to special design it's highly recommended for old bridges.

In this regard Rainbow Developers achieved successful Project of ICI Bridge Project
from CDGK and complete their successful exercise.

We have attached Material test reports, other necessary documents for your
convenience and Demo installation as mentioned in this book. I hope this catalog
volume will give you best knowledge and satisfaction.

Look forward to hear your comment on this book receptively.

                                                       Sincerely yours



                                                       Aziz Ahmad Siddiqui
                                                                                             1
EQUIPMENTS




Utilization of construction equipment:

In our projects construction equipments have been used intermittently,
utilization of output can be judged using the time and ratio of
equipment use as an index. However, there in few projects which
provided concrete data which on the demand and analyzed by us. As
exercised out put ratio is seven of the ten schemes is reported that
construction equipment was used sufficiently and appropriately.

Equipments:

1. Floor Saw & Diamond Blade       (cutting of the asphalt surfacing)
2. Compressor & Tools              (Surfacing & scabbling)
3. Pan type mixer                  (mixing, screed & transition strip
                                   materials)
4. Heavy duty drill                (drilling holes for anchors)
5. Small drill                     (fixing the anchors)
6. Selection of small hand tools
7. Minimum 8kva Generator
8. Labors

All tools are depend on project




                                                                         2
Bridge (Portion A) Photographs

The level of utilization of project roads and bridges can be judged
using changes in the volume of traffic as an Manifest .

This is best example of this kind of project which we have achieved
recently and was judged as being sufficiently utilized as well as
output is completed as planned.




                                                                      3
Bridge (Portion B)
  Photographs




                     4
1- Marking (Position of the place)


Locate the expansion gap in the
concrete deck and mark its
centre line on barriers, prior to
lying the surfacing.


Working from the centre line and
using a snap chalk line, mark the
positions of the two outer edges
of the recess.


2- Cutting of Asphalt


After the alignment and marking
of place with particular asphalt
cutter     has to cut marked
destination (it is not final asphalt
cutting), its only purpose of
fixing for Rainbow Transflex.




                                       5
3- Removal of old joints (Iron Angle)

After the cutting of marked asphalt, have to remove the old joints and
repaired damaged concrete.




4- Making Surface for Concrete and Restoration of Check
   Edges

After the making Surface of the cemented
bed exercise, have to use           specific
chemicals for making surface to concrete
joints, new concrete joints has to be more
strengthen especially during the high
capacity load and must be strong enough
for heavy loaders .




                                                                         6
5- Making Bed for Level

After the placement for        bed of
Rainbow Transflex, this procedure will
be easy at the time of fixing.


Its also composed for leveling as well
as for other necessary procedures.

6- Curing of Bed

Due to Strength of Cemented
Bed, cemented bed need at
least 7 days for its curing.




                                         7
7- Marking on Bed for Drilling
After the successful completion of
curing period, the next step is marking
for studs; there are 14 studs in one
Rainbow Transflex joint.
Due to Heavy percussion drills has to
use for this purpose, it can be less
intensity of causing hurdles    when
positioning holes.
It is, therefore suggested that small
shallow pilot holes be drilled initially,
with the unit or template still in place.
Using the pilot holes as locators drill the
holes out to the full diameter and
required depth.

 8- Drilling process for holes on bed
 Start drilling on bed, This procedure has to perform very vigilantly. All
 stud has to align and drill on same depth and dia.




                                                                             8
9- Cleaning Holes with use of Air Blower

This procedures also have
essential part; all holes must
maneuver     clean   with  air
pressure, must be remove all
dust and sand.


If this procedure is not performed
well may be the next step
produce some problems.



10- Stud fixing with Special Chemicals


Major part of fixing in rainbow
transflex.


This procedure is taking and
holding of rainbow transflex, we
use all imported stud with
special chemical for giving good
quality of grip in joint and easy
to change in other maintenance
procedure.




                                           9
11- Fixing Bolts (stud) in bed (concrete)

Followed by filling
with chemicals; fix
studs    and    give
healing    time  for
studs to provide
premium quality and
strength on it.




12- Fixing of Rainbow Transflex
                                  Satisfaction of all previous
                                  procedure, start fixing of
                                  Rainbow      Transflex   and
                                  especially ensure about male
                                  female adjustment on joint to
                                  joint.

                                  Do not forget to make upper
                                  (external) surface of the unit
                                  has to aligned with wearing
                                  surface    make    equal   to
                                  passageway from its wearing.

                                  Therefore, its very important to
                                  set the units to levels of
                                  wearing       vigilantly    and
                                  precisely.
                                                                     10
13- Firm With Bolts and Washer

Subsequently fix special designed washer and
screw with examined road level and aligned level
during the design of joint rainbow transflex, ensure
that the wearing surface is as consistent and
smooth as possible from either sides of the joint.

The surface should be properly laid.



14- Masking Tape

 As followed by step 13 (firming with bolts and washer).


 It is a process of using Mask tape for safety of studs, washers as well as
 for concrete and for dust. This step is useful for step 17 which is curing
 process.




                                                                              11
15- Cutting of final Asphalt

After the satisfaction of fixing, alignment and adjustment of male
female. The second step is cutting of asphalt for concrete.




16- Concrete on both sides of Masking tape

Chipping, removing dust and cleaning each surface,
use chemicals on old and new concrete to make
auxiliary intensity/strength, and also use special
chemical for concrete to make premium strength.




                                                                     12
17- Curing for concrete strength


As followed by previous action, this process is for
curing of concrete to make optimum dilution.

Curing process is minimum seven (7) days.




18. Cleaning holes through high compressor



Using high air compressor
to cleaning the dust and
expansion    joints.   This
procedure will help and
make easy for next phase.




                                                      13
19- Filling Holes and Gaps

This process is for filling holes with chemicals, make sure of
examined gaps and other final finishing procedure.




     Mixing Polysulphide Sealant for holes and gaps, for the long
     lasting of bolts, washer and studs.




                                                                    14
Maintenance of
Concrete & Rubber




                    15
Photographs
of successful project




                        16
Photographs
(During Work)




                17
Accomplished Bridge
           (Experiment and Testing)




Analyzed and tested                         Crossing on joints
with heavy Vehicles




          Successful and well secured
         Experiment after concrete curing
                                                                 18
Accomplished Bridge
        (Experiment and Testing)




                      The maximum of 2,000
 Fluent passage
                      vehicles per day was
of loaded trucks
                      achieved    in   Karachi
                      Renovation project for
                      ICI Bridge Keemari.


                                                 19
Accomplished Bridge
(Experiment and Testing)




                           20
After successful accomplishment of the bridge maintenance, road has
been spick and span appropriately before handover to the authority.




                                                                      21
PREMIUM PRODUCTS
National Products


IMPORTED PRODUCTS AND STOCKIEST


Upcoming items (Imported)


Services




                                  22
National Products




                                       Rubber and
  Various sizes of Bridge
                                     PVC water stops
       bearing pads




                            Various Types of Rubber Fender

                                                             23
Bridge Bearing Pads




IMPORTED PRODUCTS
   AND STOCKIEST




    Pot Bearing Pads


                         24
IMPORTED ITEMS




                 Various types of Expansion
Rubber Fenders
                            joints
                                              25
IMPORTED ITEMS




     Other Natural &
Synthetic Rubber Products   Rubber Speed Humps




          Allied
        Machineries


                                                 26
IMPORTED ITEMS




Cat Eyes    SOLAR SIGN BOARD



                               27
IMPORTED ITEMS


Road Safety Barrel’s and Products:

The Products include : Traffic Cones, Delineator Posts, Guide Posts,
Water Filled Barrier Systems, Reflective Vests & Signal Batons and
many more on request.




                                                                       28
IMPORTED ITEMS


SBR Latex Polymer for Bounding And Strength
Today's increasing loads, greater traffic volume and the need for better, longer-
lasting roads demand better service from paving materials. Asphalts modified with
SBR Latex Polymers offer the best method of improving binders for highway, street
and airport paving and maintenance projects. SBR Latex Polymers were created
specifically for modifying asphalt binders. SBR easily blends with the asphalt to
form a homogenous reinforced composite.

SBR Polymers provide:

 Optimized visco-elastic properties
       Increased resistance to rutting and shoving
       Increased resistance to low temperature cracking
       Increased resistance to load-associated fatigue cracking
       Reduced temperature susceptibility
       Reduced reflective cracking
 Minimized aging effects
 Reduced stripping and raveling




                                                                                    29
Futuristic Development on Rainbow items:

Flat Hydraulic Jacks is special lifting system for super structure on bridges and it's
helpful to replace old and Bulging Bridge Bearing Pads and very easy to repair Bridge
Guarder, transom as well as for the other maintenance in inner structure of the Bridge
and other heavy structure.




                 Lifting Jacks for Change Bridge Bearing Pads




                                                                                         30
SERVICES:


        Bridge Maintenance

        Concrete Repair

        Expansion Joint Fixing

        Road Construction

        Road Safety Paints




                                 31
SERVICES:

Bridge Maintenance:
Bridge maintenance is undertaken to extend the life of the structure and to ensure that it
functions as designed, thus ensuring public safety. This Operational Statement applies
only to: deck sweeping and washing to remove traction material (e.g., sand and salt
residue), cleaning of all bridge components (substructure, superstructure and deck), the
removal and application of protective coatings, deck wearing surface replacement, the
removal of debris to protect piers and abutments, and structural repairs involving no
instream work.
Aims of maintenance plan:
• Maintain safe passage for bridge way users.
• Protect the asset value of the bridges.
• Ensure consistent standards of maintenance across relative to road usage.
• Ensure expeditious movement of traffic by complying with the Traffic Management
Act.
• Facilitate technical and financial monitoring in order to establish trends in Bridge
condition.
• Provide a framework for reviewing policies and standards and for developing
strategies.
• Implement the principles outlined in the Code of Practice for Maintenance
Management.




                                                                                             32
Services:

CONCRETE REPAIR:
Concrete repair replaces defective, damaged, or deteriorated concrete;
restores structural function; protects the surface or underlying concrete from
aggressive environments; and restores any lost performance requirements.

Concrete repair problems are diverse in nature. Each condition requires a
clear understanding of what is expected of the repair including appearance,
protection needs, and load carrying requirements.

Critical to successful concrete repair is
proper surface preparation of the area being
repaired. This includes complete removal of
concrete around and below the reinforcing
steel and preparation of the substrate.
Combined,       these     techniques   ensure
maximum bond between the new repair
material and the existing substrate, resulting
in effective, long-lasting repairs.

An effective repair strategy must draw from
a variety of repair materials, each having an
installation technique that best suits both
the material and the strategy.

At Structural Preservation Systems, we have
the    expertise     to  utilize specialized
techniques applicable to surface repair
material installation.




                                                                            33
SERVICES:

Expansion Joint Fixing

Whether you're fixing of expansion joint material, the application method for repair is
always the same. Expansion joints are an integral part of concrete structures. They
are built into deck systems to control the stresses of volume changes in concrete.
Depending on the type of construction (cast-in-place, precast, etc.), joints are
installed to isolate ramps, buildings, and large expanses of deck surface. They may
also be needed to provide free rotation of deflecting members. Most joints open and
close according to daily and seasonal fluctuations in deck surface temperatures.

Joints provide a natural place for water, salts, and debris to collect. They also
present a hazard to pedestrians who may trip over them. To prevent these
problems, joint seals can be installed. Seals must be designed for the intended
movement of the joint, as well as for water tightness, wheel action (traffic,
equipment), pedestrian safety, and reparability.




                                                                                          34
SERVICES:

ROAD CONSTRUCTION

We construct broadly encompasses the issues relevant to the process of road
construction and maintenance, including the design, contracting, implementation,
supervision, and maintenance of roads and related structures, such as bridges and
interchanges.




                                                                                    35
SERVICES:

Road Safety Paints:
Reflective Paints

The light emitting paint is nonconventional source of energy. The light emission is
guaranteed lifelong. These paint may be termed as illumination source with least
installation cost, no operating cost & maintenance free. It is absolutely safe,
nonradioactive & nontoxic.

Other than Paints, Inks, Vinyls & Color
Transfers we also undertake job work of road
marking, lane marking & zone marking for
indoor & outdoor areas. We also offer signage
& hoardings as per customer's specification.
We have our infrastructure with digital cutters,
fabrication & paint shop.

                              Light Emitting Paint for Road

                              We offer light emitting paint for road. There is great scope
                              for this paint in infrastructure projects like road, highways,
                              express highways, bridges, tunnels, etc. Quiet high number
                              of accidents takes place due to poor lighting. The present
                              hot melt plastics & fluorescent paints used for lane marking
                              and road marking are visible only when light fall on it in a
                              particular angle. Whereas light emitting paints offer great
                              visibility in the dark. It avoids many of mishaps and
                              accidents. Also the the fluorescent paint looses its luster
                              within short period.
On the contrary light emitting paints offers illumination for long period. The lane marking
strips, zebra crossings, direction indicator arrows, STOP signs at signal are being
painted with light emitting paints. The anti crash barriers installed at sides of the
highways are painted with black & white strips of light emitting paints, adding safety in
the dark too. Various curves & obstacle at ghat sections & hilly terrains can be easily
indicated in dark with light emitting paints. All these infrastructure projects spend huge
expenditure on street lighting for installation, maintenance & operating cost. Light
emitting paints is maintenance free solution with no operating cost & minimum expense
on installation. Street lights operated by photoelectric switches often malfunction in urban
areas causing collision of vehicles against dividers, side railing, pillars & post.
                                                                                           36
TE
        ST
             RE
               PO
                  RT
                     S




22
TEST REPORTS
Conclusion:
                         Conclusion:

We trust that the above reporting on the status of the
recommendations is useful, and are pleased to see that most of
the recommendations of its initial report are part of current
operations, as reflected in its strategic planning process and
implementation through its operational plan. We believes that as
work with the collaborated organizations reaches finalization, the
continuing long-term operational stability of the organization is
an important part of ensuring its successful global responsibility.




                                                                      37

Más contenido relacionado

La actualidad más candente

1南京 第三代軟式透水管簡報介紹-1040414
1南京 第三代軟式透水管簡報介紹-10404141南京 第三代軟式透水管簡報介紹-1040414
1南京 第三代軟式透水管簡報介紹-1040414
crownswear
 
Micro Piles Soil Nails
Micro Piles Soil NailsMicro Piles Soil Nails
Micro Piles Soil Nails
jamieram
 
Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...
Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...
Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...
Dr.Youssef Hammida
 

La actualidad más candente (20)

Soil nailing
Soil nailing Soil nailing
Soil nailing
 
1南京 第三代軟式透水管簡報介紹-1040414
1南京 第三代軟式透水管簡報介紹-10404141南京 第三代軟式透水管簡報介紹-1040414
1南京 第三代軟式透水管簡報介紹-1040414
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Micro Piles Soil Nails
Micro Piles Soil NailsMicro Piles Soil Nails
Micro Piles Soil Nails
 
SOIL NAILING
SOIL NAILINGSOIL NAILING
SOIL NAILING
 
Allan block Installation guide
Allan block Installation guideAllan block Installation guide
Allan block Installation guide
 
Creation of low cost Housing
Creation of low cost HousingCreation of low cost Housing
Creation of low cost Housing
 
Signature bridge ppt2
Signature bridge ppt2Signature bridge ppt2
Signature bridge ppt2
 
Soil nailing seminar report by ankush choudhury
Soil nailing seminar report by ankush choudhurySoil nailing seminar report by ankush choudhury
Soil nailing seminar report by ankush choudhury
 
Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...
Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...
Soil Nails Reinforcement - Design nails soil stabilization --مسامير قضبان تسل...
 
Soil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhurySoil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhury
 
pavement
pavementpavement
pavement
 
Soil nailing/Soil Reinforcement Technique
Soil nailing/Soil Reinforcement TechniqueSoil nailing/Soil Reinforcement Technique
Soil nailing/Soil Reinforcement Technique
 
Soil nailing
Soil nailingSoil nailing
Soil nailing
 
soil nailing technique using gfrp
soil nailing technique using gfrpsoil nailing technique using gfrp
soil nailing technique using gfrp
 
SOIL NAILING
SOIL NAILINGSOIL NAILING
SOIL NAILING
 
Dishant ppt
Dishant pptDishant ppt
Dishant ppt
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
Soil nailing
Soil nailingSoil nailing
Soil nailing
 

Similar a Rainbow Transflex

Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
Minh Bui Si
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
AJAY SHAHU
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
Raghavendra Raghu
 

Similar a Rainbow Transflex (20)

Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
 
Shib
ShibShib
Shib
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
B.Tech Final Year Internship @ Delhi Metro Rail Corporation
B.Tech Final Year Internship @ Delhi Metro Rail CorporationB.Tech Final Year Internship @ Delhi Metro Rail Corporation
B.Tech Final Year Internship @ Delhi Metro Rail Corporation
 
Presentation on Industrial Training by Mr. Balram
Presentation on Industrial Training by Mr. BalramPresentation on Industrial Training by Mr. Balram
Presentation on Industrial Training by Mr. Balram
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
 
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
Dmrc project
Dmrc projectDmrc project
Dmrc project
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Site report 1
Site report 1Site report 1
Site report 1
 

Último

Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 

Último (20)

Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 

Rainbow Transflex

  • 1. Government & Pvt. Contractor Importer, Stockiest & Supplier Bridge Expansion Joints Bridge Bearing Pads Construction rubber Goods Construction Chemicals Allied Machineries Address: Plot # 377 Nawab Siddiq Ali Khan Road, Garden West Lasbella, Karachi, Pakistan. Phone # 0092 21 2232834 Cell # 0092 321 8218443 Fax # 0092 21 2259779 Email: rainbowenterpris.aziz@gmail.com Webpage: www.azizahmad.com
  • 3. Contents Introduction 1 Equipments used in project 2 Bridge Photographs (Portion A & B) 3-4 Installation Method of rainbow Transflex 5-14 Maintenance of Concrete & Rubber 15 Photographs of successful project 16-18 Accomplished Bridge (Experiment and Testing) 19-21 Premium Products 23-30 Services 32-36 Test Reports 38 Conclusion
  • 4. INTRODUCTION Rainbow Developer’s is sister consultant firm of Rainbow Enterprises. Rainbow Enterprises is a well reputed firm in commercial market since last decade, it offers services in Rubber Chemicals, Construction Chemicals, Allied Machineries, Industrial Machineries and many other premium products. After the decent achievement in market arena, therefore managing committee of Rainbow Enterprises has decided to move on the construction future and they registered their firm in Pakistan Engineering Council and company imports numerous construction related products i.e. Bridge Pads, Expansion Joints, Water Stop, Rubber Fender, Road Studs, Road Paints and many other products and always try to facilitate their customer their level best under the one roof. The managing committee has also made joint venture with Rainbow Rubber Industry which is also well reputed firm and this firm is specialized in Rubber Products since last four decades and their supply is to all over Pakistan and Afghanistan especially in bridges and other mega projects with their Customers, Private departments and Government sector satisfaction. Rainbow Developers also has introduced so many kinds of expansion joints in rubber and alloy metal, but company recommendation is Rainbow Transflex. Regarding Expansion Joints, Rainbow Transflex has very good reputation in the market due to his physical manifestation and this item is easy to install as well as its easy to maintain. Due to special design it's highly recommended for old bridges. In this regard Rainbow Developers achieved successful Project of ICI Bridge Project from CDGK and complete their successful exercise. We have attached Material test reports, other necessary documents for your convenience and Demo installation as mentioned in this book. I hope this catalog volume will give you best knowledge and satisfaction. Look forward to hear your comment on this book receptively. Sincerely yours Aziz Ahmad Siddiqui 1
  • 5. EQUIPMENTS Utilization of construction equipment: In our projects construction equipments have been used intermittently, utilization of output can be judged using the time and ratio of equipment use as an index. However, there in few projects which provided concrete data which on the demand and analyzed by us. As exercised out put ratio is seven of the ten schemes is reported that construction equipment was used sufficiently and appropriately. Equipments: 1. Floor Saw & Diamond Blade (cutting of the asphalt surfacing) 2. Compressor & Tools (Surfacing & scabbling) 3. Pan type mixer (mixing, screed & transition strip materials) 4. Heavy duty drill (drilling holes for anchors) 5. Small drill (fixing the anchors) 6. Selection of small hand tools 7. Minimum 8kva Generator 8. Labors All tools are depend on project 2
  • 6. Bridge (Portion A) Photographs The level of utilization of project roads and bridges can be judged using changes in the volume of traffic as an Manifest . This is best example of this kind of project which we have achieved recently and was judged as being sufficiently utilized as well as output is completed as planned. 3
  • 7. Bridge (Portion B) Photographs 4
  • 8. 1- Marking (Position of the place) Locate the expansion gap in the concrete deck and mark its centre line on barriers, prior to lying the surfacing. Working from the centre line and using a snap chalk line, mark the positions of the two outer edges of the recess. 2- Cutting of Asphalt After the alignment and marking of place with particular asphalt cutter has to cut marked destination (it is not final asphalt cutting), its only purpose of fixing for Rainbow Transflex. 5
  • 9. 3- Removal of old joints (Iron Angle) After the cutting of marked asphalt, have to remove the old joints and repaired damaged concrete. 4- Making Surface for Concrete and Restoration of Check Edges After the making Surface of the cemented bed exercise, have to use specific chemicals for making surface to concrete joints, new concrete joints has to be more strengthen especially during the high capacity load and must be strong enough for heavy loaders . 6
  • 10. 5- Making Bed for Level After the placement for bed of Rainbow Transflex, this procedure will be easy at the time of fixing. Its also composed for leveling as well as for other necessary procedures. 6- Curing of Bed Due to Strength of Cemented Bed, cemented bed need at least 7 days for its curing. 7
  • 11. 7- Marking on Bed for Drilling After the successful completion of curing period, the next step is marking for studs; there are 14 studs in one Rainbow Transflex joint. Due to Heavy percussion drills has to use for this purpose, it can be less intensity of causing hurdles when positioning holes. It is, therefore suggested that small shallow pilot holes be drilled initially, with the unit or template still in place. Using the pilot holes as locators drill the holes out to the full diameter and required depth. 8- Drilling process for holes on bed Start drilling on bed, This procedure has to perform very vigilantly. All stud has to align and drill on same depth and dia. 8
  • 12. 9- Cleaning Holes with use of Air Blower This procedures also have essential part; all holes must maneuver clean with air pressure, must be remove all dust and sand. If this procedure is not performed well may be the next step produce some problems. 10- Stud fixing with Special Chemicals Major part of fixing in rainbow transflex. This procedure is taking and holding of rainbow transflex, we use all imported stud with special chemical for giving good quality of grip in joint and easy to change in other maintenance procedure. 9
  • 13. 11- Fixing Bolts (stud) in bed (concrete) Followed by filling with chemicals; fix studs and give healing time for studs to provide premium quality and strength on it. 12- Fixing of Rainbow Transflex Satisfaction of all previous procedure, start fixing of Rainbow Transflex and especially ensure about male female adjustment on joint to joint. Do not forget to make upper (external) surface of the unit has to aligned with wearing surface make equal to passageway from its wearing. Therefore, its very important to set the units to levels of wearing vigilantly and precisely. 10
  • 14. 13- Firm With Bolts and Washer Subsequently fix special designed washer and screw with examined road level and aligned level during the design of joint rainbow transflex, ensure that the wearing surface is as consistent and smooth as possible from either sides of the joint. The surface should be properly laid. 14- Masking Tape As followed by step 13 (firming with bolts and washer). It is a process of using Mask tape for safety of studs, washers as well as for concrete and for dust. This step is useful for step 17 which is curing process. 11
  • 15. 15- Cutting of final Asphalt After the satisfaction of fixing, alignment and adjustment of male female. The second step is cutting of asphalt for concrete. 16- Concrete on both sides of Masking tape Chipping, removing dust and cleaning each surface, use chemicals on old and new concrete to make auxiliary intensity/strength, and also use special chemical for concrete to make premium strength. 12
  • 16. 17- Curing for concrete strength As followed by previous action, this process is for curing of concrete to make optimum dilution. Curing process is minimum seven (7) days. 18. Cleaning holes through high compressor Using high air compressor to cleaning the dust and expansion joints. This procedure will help and make easy for next phase. 13
  • 17. 19- Filling Holes and Gaps This process is for filling holes with chemicals, make sure of examined gaps and other final finishing procedure. Mixing Polysulphide Sealant for holes and gaps, for the long lasting of bolts, washer and studs. 14
  • 21. Accomplished Bridge (Experiment and Testing) Analyzed and tested Crossing on joints with heavy Vehicles Successful and well secured Experiment after concrete curing 18
  • 22. Accomplished Bridge (Experiment and Testing) The maximum of 2,000 Fluent passage vehicles per day was of loaded trucks achieved in Karachi Renovation project for ICI Bridge Keemari. 19
  • 24. After successful accomplishment of the bridge maintenance, road has been spick and span appropriately before handover to the authority. 21
  • 25. PREMIUM PRODUCTS National Products IMPORTED PRODUCTS AND STOCKIEST Upcoming items (Imported) Services 22
  • 26. National Products Rubber and Various sizes of Bridge PVC water stops bearing pads Various Types of Rubber Fender 23
  • 27. Bridge Bearing Pads IMPORTED PRODUCTS AND STOCKIEST Pot Bearing Pads 24
  • 28. IMPORTED ITEMS Various types of Expansion Rubber Fenders joints 25
  • 29. IMPORTED ITEMS Other Natural & Synthetic Rubber Products Rubber Speed Humps Allied Machineries 26
  • 30. IMPORTED ITEMS Cat Eyes SOLAR SIGN BOARD 27
  • 31. IMPORTED ITEMS Road Safety Barrel’s and Products: The Products include : Traffic Cones, Delineator Posts, Guide Posts, Water Filled Barrier Systems, Reflective Vests & Signal Batons and many more on request. 28
  • 32. IMPORTED ITEMS SBR Latex Polymer for Bounding And Strength Today's increasing loads, greater traffic volume and the need for better, longer- lasting roads demand better service from paving materials. Asphalts modified with SBR Latex Polymers offer the best method of improving binders for highway, street and airport paving and maintenance projects. SBR Latex Polymers were created specifically for modifying asphalt binders. SBR easily blends with the asphalt to form a homogenous reinforced composite. SBR Polymers provide: Optimized visco-elastic properties Increased resistance to rutting and shoving Increased resistance to low temperature cracking Increased resistance to load-associated fatigue cracking Reduced temperature susceptibility Reduced reflective cracking Minimized aging effects Reduced stripping and raveling 29
  • 33. Futuristic Development on Rainbow items: Flat Hydraulic Jacks is special lifting system for super structure on bridges and it's helpful to replace old and Bulging Bridge Bearing Pads and very easy to repair Bridge Guarder, transom as well as for the other maintenance in inner structure of the Bridge and other heavy structure. Lifting Jacks for Change Bridge Bearing Pads 30
  • 34. SERVICES: Bridge Maintenance Concrete Repair Expansion Joint Fixing Road Construction Road Safety Paints 31
  • 35. SERVICES: Bridge Maintenance: Bridge maintenance is undertaken to extend the life of the structure and to ensure that it functions as designed, thus ensuring public safety. This Operational Statement applies only to: deck sweeping and washing to remove traction material (e.g., sand and salt residue), cleaning of all bridge components (substructure, superstructure and deck), the removal and application of protective coatings, deck wearing surface replacement, the removal of debris to protect piers and abutments, and structural repairs involving no instream work. Aims of maintenance plan: • Maintain safe passage for bridge way users. • Protect the asset value of the bridges. • Ensure consistent standards of maintenance across relative to road usage. • Ensure expeditious movement of traffic by complying with the Traffic Management Act. • Facilitate technical and financial monitoring in order to establish trends in Bridge condition. • Provide a framework for reviewing policies and standards and for developing strategies. • Implement the principles outlined in the Code of Practice for Maintenance Management. 32
  • 36. Services: CONCRETE REPAIR: Concrete repair replaces defective, damaged, or deteriorated concrete; restores structural function; protects the surface or underlying concrete from aggressive environments; and restores any lost performance requirements. Concrete repair problems are diverse in nature. Each condition requires a clear understanding of what is expected of the repair including appearance, protection needs, and load carrying requirements. Critical to successful concrete repair is proper surface preparation of the area being repaired. This includes complete removal of concrete around and below the reinforcing steel and preparation of the substrate. Combined, these techniques ensure maximum bond between the new repair material and the existing substrate, resulting in effective, long-lasting repairs. An effective repair strategy must draw from a variety of repair materials, each having an installation technique that best suits both the material and the strategy. At Structural Preservation Systems, we have the expertise to utilize specialized techniques applicable to surface repair material installation. 33
  • 37. SERVICES: Expansion Joint Fixing Whether you're fixing of expansion joint material, the application method for repair is always the same. Expansion joints are an integral part of concrete structures. They are built into deck systems to control the stresses of volume changes in concrete. Depending on the type of construction (cast-in-place, precast, etc.), joints are installed to isolate ramps, buildings, and large expanses of deck surface. They may also be needed to provide free rotation of deflecting members. Most joints open and close according to daily and seasonal fluctuations in deck surface temperatures. Joints provide a natural place for water, salts, and debris to collect. They also present a hazard to pedestrians who may trip over them. To prevent these problems, joint seals can be installed. Seals must be designed for the intended movement of the joint, as well as for water tightness, wheel action (traffic, equipment), pedestrian safety, and reparability. 34
  • 38. SERVICES: ROAD CONSTRUCTION We construct broadly encompasses the issues relevant to the process of road construction and maintenance, including the design, contracting, implementation, supervision, and maintenance of roads and related structures, such as bridges and interchanges. 35
  • 39. SERVICES: Road Safety Paints: Reflective Paints The light emitting paint is nonconventional source of energy. The light emission is guaranteed lifelong. These paint may be termed as illumination source with least installation cost, no operating cost & maintenance free. It is absolutely safe, nonradioactive & nontoxic. Other than Paints, Inks, Vinyls & Color Transfers we also undertake job work of road marking, lane marking & zone marking for indoor & outdoor areas. We also offer signage & hoardings as per customer's specification. We have our infrastructure with digital cutters, fabrication & paint shop. Light Emitting Paint for Road We offer light emitting paint for road. There is great scope for this paint in infrastructure projects like road, highways, express highways, bridges, tunnels, etc. Quiet high number of accidents takes place due to poor lighting. The present hot melt plastics & fluorescent paints used for lane marking and road marking are visible only when light fall on it in a particular angle. Whereas light emitting paints offer great visibility in the dark. It avoids many of mishaps and accidents. Also the the fluorescent paint looses its luster within short period. On the contrary light emitting paints offers illumination for long period. The lane marking strips, zebra crossings, direction indicator arrows, STOP signs at signal are being painted with light emitting paints. The anti crash barriers installed at sides of the highways are painted with black & white strips of light emitting paints, adding safety in the dark too. Various curves & obstacle at ghat sections & hilly terrains can be easily indicated in dark with light emitting paints. All these infrastructure projects spend huge expenditure on street lighting for installation, maintenance & operating cost. Light emitting paints is maintenance free solution with no operating cost & minimum expense on installation. Street lights operated by photoelectric switches often malfunction in urban areas causing collision of vehicles against dividers, side railing, pillars & post. 36
  • 40. TE ST RE PO RT S 22
  • 42. Conclusion: Conclusion: We trust that the above reporting on the status of the recommendations is useful, and are pleased to see that most of the recommendations of its initial report are part of current operations, as reflected in its strategic planning process and implementation through its operational plan. We believes that as work with the collaborated organizations reaches finalization, the continuing long-term operational stability of the organization is an important part of ensuring its successful global responsibility. 37