SlideShare una empresa de Scribd logo
1 de 28
Descargar para leer sin conexión
Sub-regional approach and its potential
    for the EUSDR implementation
      - Case of the Sava river basin -




           Dejan Komatina, Ph.D. Civ. Eng.,
                  Secretary, ISRBC
Overview
• Introduction on the Sava River Basin

• Framework Agreement on the Sava River Basin (FASRB) and
  International Sava River Basin Commission (ISRBC)

• Approach of the ISRBC

• ISRBC and the EU Strategy for the Danube Region (EUSDR)

• Summary

• Contact Information




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   2
Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   3
Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   4
Sava River Basin
     – Area: 97 713 km2 (the second largest Danube sub-basin; share: 12%)
     – Average flow at the mouth: 1722 m3/s
       (the largest Danube tributary; contribution: 25%)
     – River length: 940 km (594 km of which is the waterway)
     – Population: approx. 8.5 million

              Country                            Share of the           Share of the
                                                  basin (%)             territory (%)
              Albania                                  0.2                    0.6
              Bosnia & Herzegovina                    39.2                   75.8
              Croatia                                 26.0                   45.2
              Montenegro                               7.1                   49.6
              Serbia                                  15.5                   17.4
              Slovenia                                12.0                   52.8
Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011     5
Sava River Basin
• High environmental and social value
     – Natural beauty




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   6
Sava River Basin
• High environmental and social value
     – High biological and landscape diversity
       (natural wetlands, parks, protected areas)




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   7
Sava River Basin
• High environmental and social value
     – Large retention areas




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   8
Sava River Basin
• High environmental and social value
     – High potential for transport of cargo and passengers




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   9
Sava River Basin
• High environmental and social value
     – High potential for tourism and recreation




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   10
FASRB
• Until 1990’s:
     – Sava river used to be the biggest national river
     – Integrated management of the Sava water resources

• 1990’s to 2000’s:
     – Management of the water resources restricted to the country level
     – Integrated approach accepted on European level

• Since 2000’s:
     – Framework Agreement on the Sava River Basin (signed 2002, ratif. 2004)
     – International Sava River Basin Commission (est. 2005, Secr. 2006)
     – 4 Parties (Bosnia & Herzegovina, Croatia, Serbia, Slovenia)


Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   11
FASRB
• From different priorities to Integrated TWRM approach
     – Rehabilitation and development of navigation
     – Flood protection
     – Utilization of potentials for tourism development
     – Utilization of potentials for energy production
     – Maintenance of water quality and quantity




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   12
FASRB
• Key objective:

                            Transboundary cooperation
                     for sustainable development of the region

• Particular objectives:
     – To establish an international regime of navigation
     – To establish sustainable water management
     – To prevent/limit hazards (floods, droughts, ice and accidents) and
       reduce/eliminate their negative consequences




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   13
FASRB
• Implementation coordinated by the ISRBC (BA, HR, RS, SI)

• Fields of work of the ISRBC
     – Issues of sustainability:
           •   Improvement of water quality
           •   Maintenance of water quantity
           •   Protection of aquatic ecosystem
           •   Protection against the harmful effects of water
               (due to floods, ice, droughts, accidents)
     – Development activities:
           • Different kinds of water use
             (navigation, hydropower generation, water supply, sewerage,
             irrigation and drainage, fishery, tourism and recreation)

• Broadest scope of work among European river commissions


Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   14
ISRBC
• Coordination of:
     – Development of joint / integrated plans for the SRB
           • River Basin Management Plan (in accordance with the EU WFD)
           • Flood Risk Management Plan (in accordance with the EU Flood Directive)

     – Establishment of integrated systems for the SRB
           •   GIS (in accordance with the INSPIRE Directive and WISE)
           •   RIS – River Information Services (in accordance with the EU RIS Directive)
           •   Flood Forecasting and Warning System
           •   Accident Emergency Warning System (use of the ICDPR’s system)

     – Preparation of development programs for the SRB
           • Rehabilitation and development of navigation
           • Development of (nautical) tourism


          All the activities performed through implementation of projects
Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011         15
ISRBC
• Coordination of (cont.):
     – Harmonization of regulation (national  EU)
     – Creation of additional protocols to the FASRB
           •   Navigation regime
           •   Prevention of water pollution caused by navigation
           •   Flood protection
           •   Emergency situations
           •   Sediment management
           •   Transboundary impacts

• Cooperation / stakeholder involvement / public participation




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   16
Example
• Rehabilitation of the Waterway on the Sava River
     – Planning phase (studies, design)
     – Technical standards (rules harmonized with EU and UNECE regulation)
     – Protocol on prevention of water pollution caused by navigation
     – Sava RBM Plan                               Sisak            Bosanski Brod                 Brcko                        Belgrade

     – Climate Adaptation Plan                       3.5 – 9.6 million tonnes   5.8 – 15.5 million tonnes   7.8 – 20.8 million tonnes


     – Sediment Management
       Plan                                                                                  3-8
                                                                                             million

     – Initial phase of the
       RIS development




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011                                                       17
Example
• Rehabilitation of the Waterway on the Sava River
     – Joint Statement
       (ICPDR, DC, ISRBC, and EC)                               Cruiser “Victor Hugo”, Sisak, June 2010

     – Manual on Integrated
       IWT Planning
       (EU FP7 PLATINA Project)

     – WANDA
       (SEE TCP Project)




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011                 18
Added value
• Key features of the approach
     – Cohesive, providing conditions for:
           • Cooperation of the countries after the conflict
           • Implementation of joint, basin-wide projects
           • Harmonization of national regulation, methodologies, procedures …

     – Integrated (whole basin; sustainability and development)
     – Transparent (public participation)
     – Aligned with the EU and UNECE regulation
       (EU Directives, UNECE Water Convention, ...)
     – Subregional (“finer resolution” of results than on a regional scale)
     – Pragmatic and practical (offering concrete “products” to the Parties
       – joint plans, development programs, protocols, harmonized regulation,
       integrated systems)

Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   19
Added value
• Relevance to EU 2020
     – Sustainable growth
           • Programs for sustainable development of the region (navigation, tourism)
           • Climate change adaptation (two ongoing projects)
           • Use of hydropower as a
             renewable energy source

     – Smart growth
           • Involvement of academic
             sector
           • Establishment of information
             systems for the basin
     – Inclusive growth
           • Fostering contribution of
             SMEs to sustainable
             development of the region

Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011     20
Added value
• Indicators
      – Interest in the ISRBC approach
            •   South-Eastern Europe
            •   Mediterranean
            •   Europe
            •   Central Asia

      – Recognition of the Joint Statement
        Process
            • EU (e.g. in the European Parliament
              resolution on EUSDR)
            • Similar processes to be launched in the
              fields of hydropower and agriculture




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   21
ISRBC and EUSDR
• Main activities during the consultation and drafting process
     – Raising awareness that the EUSDR and the FASRB have the identical
       main objective – sustainable development of the region they refer to
     – Presentation of the ISRBC approach to sustainable development of
       the Sava region
     – Presentation of the ISRBC priority projects appropriate to be
       executed within the implementation of the EUSDR




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   22
ISRBC and EUSDR
• Main messages during the consultation and drafting process
     – The ISRBC projects are worth to be taken into account,
       as they are:
           • the projects already agreed upon by the 4 countries
           • complementary to other projects proposed by the countries

     – The sub-regional level is likely to be the most effective level
       from the viewpoint of the EUSDR implementation
     – Implementation of the ISRBC projects in the framework of the
       EUSDR can yield double benefits – contribution to an effective
       implementation of both FASRB and EUSDR




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   23
ISRBC and EUSDR
• ISRBC projects included in the EUSDR Action Plan
     – Completion and adoption of the Sava RBM Plan                                   PA 4
     – Establishment and completion of the Sava GIS                                   PA 4
     – Examination of biodiversity and environmental status of
       sediment, water and biota in the Sava river basin                              PA 4
     – Preparation and implementation of the water and climate
       adaptation plan for the Sava river basin                                       PA 5
     – Preparation and implementation of a water pollution contin-
       gency management plan for the Sava river basin              PA 5




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011          24
ISRBC and EUSDR
• Other priority projects of the ISRBC
     – Rehabilitation and improvement of the Sava river waterway
                                                                                      PA 1
     – Support to preparation of the Flood Risk Management Plan
       for the Sava river basin                                PA 5
     – Hydrological study for the Sava river basin                                    PA 5
     – Support to establishment of the Sava RIS                                       PA 1
     – Support to development of nautical tourism in the Sava river
       basin                                                       PA 3
     – Development of the Hydro-meteorological information and
       flood forecasting and warning system for the Sava river basin
                                                                  PA 5


Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011          25
ISRBC and EUSDR
• 3rd Meeting of the Parties
    (Brdo near Kranj, Slovenia,
    31 May – 1 June 2011)




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   26
Summary
• Identical overall objective of the EUSDR and FASRB

• Conformity of the ISRBC approach and its priority projects with
  the EUSDR priorities

• High potential for synergy – implementation of the ISRBC
  projects within the EUSDR framework can contribute to the
  implementation of both EUSDR and FASRB

• The sub-regional level is likely to be the most effective
  level from the viewpoint of the EUSDR implementation


QUESTION:
Baltic experience with the implementation on a sub-regional level ?

Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   27
Contact Information
International Sava River Basin Commission
Vladimira Nazora 61
10000 Zagreb
Croatia




www.savacommission.org




Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011   28

Más contenido relacionado

Destacado

Water buffer management, 3R – Retention, Recharge and Reuse
Water buffer management, 3R – Retention, Recharge and Reuse Water buffer management, 3R – Retention, Recharge and Reuse
Water buffer management, 3R – Retention, Recharge and Reuse SamSamWater Foundation
 
Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...
Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...
Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...Shay Rosen (שי רוזן)
 
אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...
אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...
אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...Shay Rosen (שי רוזן)
 

Destacado (20)

IDMP CEE 2nd workshop: Activity 5.3 by Tomasz Okruszko
IDMP CEE 2nd workshop: Activity 5.3 by Tomasz OkruszkoIDMP CEE 2nd workshop: Activity 5.3 by Tomasz Okruszko
IDMP CEE 2nd workshop: Activity 5.3 by Tomasz Okruszko
 
Third IDMP CEE workshop: Natural, small water retention measures by Tomasz Ok...
Third IDMP CEE workshop: Natural, small water retention measures by Tomasz Ok...Third IDMP CEE workshop: Natural, small water retention measures by Tomasz Ok...
Third IDMP CEE workshop: Natural, small water retention measures by Tomasz Ok...
 
IDMP CEE Activity 5.3 by Waldemar Mioduszewski
IDMP CEE Activity 5.3 by Waldemar MioduszewskiIDMP CEE Activity 5.3 by Waldemar Mioduszewski
IDMP CEE Activity 5.3 by Waldemar Mioduszewski
 
Water buffer management, 3R – Retention, Recharge and Reuse
Water buffer management, 3R – Retention, Recharge and Reuse Water buffer management, 3R – Retention, Recharge and Reuse
Water buffer management, 3R – Retention, Recharge and Reuse
 
3R Environmental considerations
3R Environmental considerations3R Environmental considerations
3R Environmental considerations
 
09082010 global warming and tree planting
09082010 global warming and tree planting09082010 global warming and tree planting
09082010 global warming and tree planting
 
SustSan workshop: IWRM Toolbox by Danka Thalmeinerova
SustSan workshop: IWRM Toolbox by Danka ThalmeinerovaSustSan workshop: IWRM Toolbox by Danka Thalmeinerova
SustSan workshop: IWRM Toolbox by Danka Thalmeinerova
 
IDMP CEE So far by Sabina Bokal
IDMP CEE So far by Sabina BokalIDMP CEE So far by Sabina Bokal
IDMP CEE So far by Sabina Bokal
 
Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...
Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...
Multi-Screen Digital Strategy 2013 How to plan a successful Multiscreen Digit...
 
6 g wadi network for see-zlatanović&dimkić
6 g wadi network for see-zlatanović&dimkić6 g wadi network for see-zlatanović&dimkić
6 g wadi network for see-zlatanović&dimkić
 
Fourth IDMP CEE workshop: Assessment of drought impact on forests by Galia Ba...
Fourth IDMP CEE workshop: Assessment of drought impact on forests by Galia Ba...Fourth IDMP CEE workshop: Assessment of drought impact on forests by Galia Ba...
Fourth IDMP CEE workshop: Assessment of drought impact on forests by Galia Ba...
 
Fourth IDMP CEE workshop: Compendium of good practices by Tanja Tajnik
Fourth IDMP CEE workshop: Compendium of good practices by Tanja TajnikFourth IDMP CEE workshop: Compendium of good practices by Tanja Tajnik
Fourth IDMP CEE workshop: Compendium of good practices by Tanja Tajnik
 
IDMP CEE Activity 1.3 by Gregor Gregoric
IDMP CEE Activity 1.3 by Gregor GregoricIDMP CEE Activity 1.3 by Gregor Gregoric
IDMP CEE Activity 1.3 by Gregor Gregoric
 
Fourth IDMP CEE workshop: Drought Risk Management Scheme: a decision suppor...
Fourth IDMP CEE workshop: Drought  Risk Management Scheme: a decision suppor...Fourth IDMP CEE workshop: Drought  Risk Management Scheme: a decision suppor...
Fourth IDMP CEE workshop: Drought Risk Management Scheme: a decision suppor...
 
IDMP CEE 2nd workshop: Activity 5.6 by Dumitru Drumea
IDMP CEE 2nd workshop: Activity 5.6 by Dumitru DrumeaIDMP CEE 2nd workshop: Activity 5.6 by Dumitru Drumea
IDMP CEE 2nd workshop: Activity 5.6 by Dumitru Drumea
 
אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...
אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...
אתר נולד - אתר האינטרנט של שילב - כיצד תכננו את חווית המשתמש באתר הסחר החדש ש...
 
Difficulties of involving the stakeholders at the local level: Lessons learne...
Difficulties of involving the stakeholders at the local level: Lessons learne...Difficulties of involving the stakeholders at the local level: Lessons learne...
Difficulties of involving the stakeholders at the local level: Lessons learne...
 
IDMP CEE Activity 5.6 by Anna Tsvietkova and Dumitru Drumea
IDMP CEE Activity 5.6 by Anna Tsvietkova and Dumitru DrumeaIDMP CEE Activity 5.6 by Anna Tsvietkova and Dumitru Drumea
IDMP CEE Activity 5.6 by Anna Tsvietkova and Dumitru Drumea
 
Sustainable Sanitation in Central and Eastern Europe by Richard Muller
Sustainable Sanitation in Central and Eastern Europe by Richard MullerSustainable Sanitation in Central and Eastern Europe by Richard Muller
Sustainable Sanitation in Central and Eastern Europe by Richard Muller
 
Global Water Partnership, Ms. Dana J. Thalmeinerova
Global Water Partnership, Ms. Dana J. ThalmeinerovaGlobal Water Partnership, Ms. Dana J. Thalmeinerova
Global Water Partnership, Ms. Dana J. Thalmeinerova
 

Similar a Sub-regional approach and its potential for the EUSDR implementation: Case of the Sava river basin, Dejan Komatina, Ph.D. Civ. Eng.

Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Iwl Pcu
 
Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Iwl Pcu
 
Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Iwl Pcu
 
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...UNESCO Venice Office
 
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...UNESCO Venice Office
 
MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...
MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...
MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...Pan Baltic Scope / Baltic SCOPE
 
Int. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko Dragan
Int. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko DraganInt. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko Dragan
Int. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko DraganGWP-Mediterranean (GWP-Med)
 
Baltic Landscape Project 
and its Polish prospect 
as a practical contributi...
Baltic Landscape Project 
and its Polish prospect  
as a practical contributi...Baltic Landscape Project 
and its Polish prospect  
as a practical contributi...
Baltic Landscape Project 
and its Polish prospect 
as a practical contributi...CIFOR-ICRAF
 
Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...
Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...
Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...GWP-Mediterranean (GWP-Med)
 
DSD-INT 2017 International collaboration within the Delft-FEWS system for the...
DSD-INT 2017 International collaboration within the Delft-FEWS system for the...DSD-INT 2017 International collaboration within the Delft-FEWS system for the...
DSD-INT 2017 International collaboration within the Delft-FEWS system for the...Deltares
 
International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...Iwl Pcu
 
Future of the Baltic Sea Regional Project
Future of the Baltic Sea Regional ProjectFuture of the Baltic Sea Regional Project
Future of the Baltic Sea Regional ProjectIwl Pcu
 

Similar a Sub-regional approach and its potential for the EUSDR implementation: Case of the Sava river basin, Dejan Komatina, Ph.D. Civ. Eng. (20)

Parallels: Water resources management aspects of the EU Strategies for the Ba...
Parallels: Water resources management aspects of the EU Strategies for the Ba...Parallels: Water resources management aspects of the EU Strategies for the Ba...
Parallels: Water resources management aspects of the EU Strategies for the Ba...
 
Water protecting actions in the Danube Region Strategy: Expectations and fact...
Water protecting actions in the Danube Region Strategy: Expectations and fact...Water protecting actions in the Danube Region Strategy: Expectations and fact...
Water protecting actions in the Danube Region Strategy: Expectations and fact...
 
Joint Statement on Guiding - Principles Development of Inland Navigation and ...
Joint Statement on Guiding - Principles Development of Inland Navigation and ...Joint Statement on Guiding - Principles Development of Inland Navigation and ...
Joint Statement on Guiding - Principles Development of Inland Navigation and ...
 
GWP-Med in action. National Consultation on Drought by Dimitris Faloutsos
GWP-Med in action. National Consultation on Drought by Dimitris FaloutsosGWP-Med in action. National Consultation on Drought by Dimitris Faloutsos
GWP-Med in action. National Consultation on Drought by Dimitris Faloutsos
 
Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...
 
Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...
 
Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...Public participation in the Danube Basin: approaches, activities, challenges ...
Public participation in the Danube Basin: approaches, activities, challenges ...
 
IDMP CEE follow-up workshop: Adriatic Ionic Strategy by Martina Zupan
IDMP CEE follow-up workshop: Adriatic Ionic Strategy by Martina ZupanIDMP CEE follow-up workshop: Adriatic Ionic Strategy by Martina Zupan
IDMP CEE follow-up workshop: Adriatic Ionic Strategy by Martina Zupan
 
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
 
GWP CEE Strategy 2009-2013 Implementation
GWP CEE Strategy 2009-2013 ImplementationGWP CEE Strategy 2009-2013 Implementation
GWP CEE Strategy 2009-2013 Implementation
 
Sava River Commission
Sava River CommissionSava River Commission
Sava River Commission
 
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
MAB-IHP Regional Symposium: Managing Water Resources in Biosphere Reserves in...
 
MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...
MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...
MSP activities in Black sea area and achievements of MARSPLAN-BS project at t...
 
Rio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzerRio danubio europa-wolfgangstaltzer
Rio danubio europa-wolfgangstaltzer
 
Int. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko Dragan
Int. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko DraganInt. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko Dragan
Int. Roundtable on Transboundary Waters Management, 15-16.12.2011, Zeljko Dragan
 
Baltic Landscape Project 
and its Polish prospect 
as a practical contributi...
Baltic Landscape Project 
and its Polish prospect  
as a practical contributi...Baltic Landscape Project 
and its Polish prospect  
as a practical contributi...
Baltic Landscape Project 
and its Polish prospect 
as a practical contributi...
 
Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...
Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...
Workshop on Flood management in a transboundary context, 13-14.12.2011, Dimit...
 
DSD-INT 2017 International collaboration within the Delft-FEWS system for the...
DSD-INT 2017 International collaboration within the Delft-FEWS system for the...DSD-INT 2017 International collaboration within the Delft-FEWS system for the...
DSD-INT 2017 International collaboration within the Delft-FEWS system for the...
 
International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...International Cooperation in Water Management and Pollution Control in the Da...
International Cooperation in Water Management and Pollution Control in the Da...
 
Future of the Baltic Sea Regional Project
Future of the Baltic Sea Regional ProjectFuture of the Baltic Sea Regional Project
Future of the Baltic Sea Regional Project
 

Más de Global Water Partnership Central and Eastern Europe

Más de Global Water Partnership Central and Eastern Europe (20)

Treatment Wetlands for Sustainable Sanitation in Central and Eastern Europe b...
Treatment Wetlands for Sustainable Sanitation in Central and Eastern Europe b...Treatment Wetlands for Sustainable Sanitation in Central and Eastern Europe b...
Treatment Wetlands for Sustainable Sanitation in Central and Eastern Europe b...
 
IDMP CEE follow-up workshop:
IDMP CEE follow-up workshop: IDMP CEE follow-up workshop:
IDMP CEE follow-up workshop:
 
IDMP CEE follow-up workshop: Rresearch needs and vision for follow up program...
IDMP CEE follow-up workshop: Rresearch needs and vision for follow up program...IDMP CEE follow-up workshop: Rresearch needs and vision for follow up program...
IDMP CEE follow-up workshop: Rresearch needs and vision for follow up program...
 
10 eu strategy for the danube region feher
10 eu strategy for the danube region feher10 eu strategy for the danube region feher
10 eu strategy for the danube region feher
 
9 fundraising mapping bokal
9 fundraising mapping bokal9 fundraising mapping bokal
9 fundraising mapping bokal
 
8 eodc status mistelbauer
8 eodc status mistelbauer8 eodc status mistelbauer
8 eodc status mistelbauer
 
7 satida mistelbauer
7 satida mistelbauer7 satida mistelbauer
7 satida mistelbauer
 
5 drought in romania mateescu
5 drought in romania mateescu5 drought in romania mateescu
5 drought in romania mateescu
 
4 intersucho zalud
4 intersucho zalud4 intersucho zalud
4 intersucho zalud
 
3 drought r&spi-van lanen
3 drought r&spi-van lanen3 drought r&spi-van lanen
3 drought r&spi-van lanen
 
2 dmcsee gregorič
2 dmcsee gregorič2 dmcsee gregorič
2 dmcsee gregorič
 
1 idmp help desk stefanski
1 idmp help desk stefanski1 idmp help desk stefanski
1 idmp help desk stefanski
 
Fourth IDMP CEE workshop: Water and Drought Management and in the Adriatic S...
Fourth IDMP CEE workshop: Water and Drought Management and  in the Adriatic S...Fourth IDMP CEE workshop: Water and Drought Management and  in the Adriatic S...
Fourth IDMP CEE workshop: Water and Drought Management and in the Adriatic S...
 
Fourth IDMP CEE workshop: Proposed Follow-up pilot projects in forests by Urs...
Fourth IDMP CEE workshop: Proposed Follow-up pilot projects in forests by Urs...Fourth IDMP CEE workshop: Proposed Follow-up pilot projects in forests by Urs...
Fourth IDMP CEE workshop: Proposed Follow-up pilot projects in forests by Urs...
 
Fourth IDMP CEE workshop: IDMP CEE Communications by Gergana Majercakova
Fourth IDMP CEE workshop: IDMP CEE Communications by Gergana MajercakovaFourth IDMP CEE workshop: IDMP CEE Communications by Gergana Majercakova
Fourth IDMP CEE workshop: IDMP CEE Communications by Gergana Majercakova
 
Fourth IDMP CEE workshop: Natural Small Water Retention Measures by Anja Potokar
Fourth IDMP CEE workshop: Natural Small Water Retention Measures by Anja PotokarFourth IDMP CEE workshop: Natural Small Water Retention Measures by Anja Potokar
Fourth IDMP CEE workshop: Natural Small Water Retention Measures by Anja Potokar
 
Fourth IDMP CEE workshop: Increasing soil water holding capacity by Pavol Bi...
Fourth IDMP CEE workshop: Increasing soil water holding capacity by  Pavol Bi...Fourth IDMP CEE workshop: Increasing soil water holding capacity by  Pavol Bi...
Fourth IDMP CEE workshop: Increasing soil water holding capacity by Pavol Bi...
 
Fourth IDMP CEE workshop: Development of GIS Based Communication Technology P...
Fourth IDMP CEE workshop: Development of GIS Based Communication Technology P...Fourth IDMP CEE workshop: Development of GIS Based Communication Technology P...
Fourth IDMP CEE workshop: Development of GIS Based Communication Technology P...
 
Fourth IDMP CEE workshop: Upgrading agricultural drought monitoring and forec...
Fourth IDMP CEE workshop: Upgrading agricultural drought monitoring and forec...Fourth IDMP CEE workshop: Upgrading agricultural drought monitoring and forec...
Fourth IDMP CEE workshop: Upgrading agricultural drought monitoring and forec...
 
Fourth IDMP CEE workshop: Policy oriented study on remote sensing agricultura...
Fourth IDMP CEE workshop: Policy oriented study on remote sensing agricultura...Fourth IDMP CEE workshop: Policy oriented study on remote sensing agricultura...
Fourth IDMP CEE workshop: Policy oriented study on remote sensing agricultura...
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxAmita Gupta
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxcallscotland1987
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 

Último (20)

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 

Sub-regional approach and its potential for the EUSDR implementation: Case of the Sava river basin, Dejan Komatina, Ph.D. Civ. Eng.

  • 1. Sub-regional approach and its potential for the EUSDR implementation - Case of the Sava river basin - Dejan Komatina, Ph.D. Civ. Eng., Secretary, ISRBC
  • 2. Overview • Introduction on the Sava River Basin • Framework Agreement on the Sava River Basin (FASRB) and International Sava River Basin Commission (ISRBC) • Approach of the ISRBC • ISRBC and the EU Strategy for the Danube Region (EUSDR) • Summary • Contact Information Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 2
  • 3. Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 3
  • 4. Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 4
  • 5. Sava River Basin – Area: 97 713 km2 (the second largest Danube sub-basin; share: 12%) – Average flow at the mouth: 1722 m3/s (the largest Danube tributary; contribution: 25%) – River length: 940 km (594 km of which is the waterway) – Population: approx. 8.5 million Country Share of the Share of the basin (%) territory (%) Albania 0.2 0.6 Bosnia & Herzegovina 39.2 75.8 Croatia 26.0 45.2 Montenegro 7.1 49.6 Serbia 15.5 17.4 Slovenia 12.0 52.8 Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 5
  • 6. Sava River Basin • High environmental and social value – Natural beauty Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 6
  • 7. Sava River Basin • High environmental and social value – High biological and landscape diversity (natural wetlands, parks, protected areas) Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 7
  • 8. Sava River Basin • High environmental and social value – Large retention areas Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 8
  • 9. Sava River Basin • High environmental and social value – High potential for transport of cargo and passengers Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 9
  • 10. Sava River Basin • High environmental and social value – High potential for tourism and recreation Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 10
  • 11. FASRB • Until 1990’s: – Sava river used to be the biggest national river – Integrated management of the Sava water resources • 1990’s to 2000’s: – Management of the water resources restricted to the country level – Integrated approach accepted on European level • Since 2000’s: – Framework Agreement on the Sava River Basin (signed 2002, ratif. 2004) – International Sava River Basin Commission (est. 2005, Secr. 2006) – 4 Parties (Bosnia & Herzegovina, Croatia, Serbia, Slovenia) Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 11
  • 12. FASRB • From different priorities to Integrated TWRM approach – Rehabilitation and development of navigation – Flood protection – Utilization of potentials for tourism development – Utilization of potentials for energy production – Maintenance of water quality and quantity Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 12
  • 13. FASRB • Key objective: Transboundary cooperation for sustainable development of the region • Particular objectives: – To establish an international regime of navigation – To establish sustainable water management – To prevent/limit hazards (floods, droughts, ice and accidents) and reduce/eliminate their negative consequences Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 13
  • 14. FASRB • Implementation coordinated by the ISRBC (BA, HR, RS, SI) • Fields of work of the ISRBC – Issues of sustainability: • Improvement of water quality • Maintenance of water quantity • Protection of aquatic ecosystem • Protection against the harmful effects of water (due to floods, ice, droughts, accidents) – Development activities: • Different kinds of water use (navigation, hydropower generation, water supply, sewerage, irrigation and drainage, fishery, tourism and recreation) • Broadest scope of work among European river commissions Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 14
  • 15. ISRBC • Coordination of: – Development of joint / integrated plans for the SRB • River Basin Management Plan (in accordance with the EU WFD) • Flood Risk Management Plan (in accordance with the EU Flood Directive) – Establishment of integrated systems for the SRB • GIS (in accordance with the INSPIRE Directive and WISE) • RIS – River Information Services (in accordance with the EU RIS Directive) • Flood Forecasting and Warning System • Accident Emergency Warning System (use of the ICDPR’s system) – Preparation of development programs for the SRB • Rehabilitation and development of navigation • Development of (nautical) tourism All the activities performed through implementation of projects Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 15
  • 16. ISRBC • Coordination of (cont.): – Harmonization of regulation (national  EU) – Creation of additional protocols to the FASRB • Navigation regime • Prevention of water pollution caused by navigation • Flood protection • Emergency situations • Sediment management • Transboundary impacts • Cooperation / stakeholder involvement / public participation Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 16
  • 17. Example • Rehabilitation of the Waterway on the Sava River – Planning phase (studies, design) – Technical standards (rules harmonized with EU and UNECE regulation) – Protocol on prevention of water pollution caused by navigation – Sava RBM Plan Sisak Bosanski Brod Brcko Belgrade – Climate Adaptation Plan 3.5 – 9.6 million tonnes 5.8 – 15.5 million tonnes 7.8 – 20.8 million tonnes – Sediment Management Plan 3-8 million – Initial phase of the RIS development Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 17
  • 18. Example • Rehabilitation of the Waterway on the Sava River – Joint Statement (ICPDR, DC, ISRBC, and EC) Cruiser “Victor Hugo”, Sisak, June 2010 – Manual on Integrated IWT Planning (EU FP7 PLATINA Project) – WANDA (SEE TCP Project) Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 18
  • 19. Added value • Key features of the approach – Cohesive, providing conditions for: • Cooperation of the countries after the conflict • Implementation of joint, basin-wide projects • Harmonization of national regulation, methodologies, procedures … – Integrated (whole basin; sustainability and development) – Transparent (public participation) – Aligned with the EU and UNECE regulation (EU Directives, UNECE Water Convention, ...) – Subregional (“finer resolution” of results than on a regional scale) – Pragmatic and practical (offering concrete “products” to the Parties – joint plans, development programs, protocols, harmonized regulation, integrated systems) Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 19
  • 20. Added value • Relevance to EU 2020 – Sustainable growth • Programs for sustainable development of the region (navigation, tourism) • Climate change adaptation (two ongoing projects) • Use of hydropower as a renewable energy source – Smart growth • Involvement of academic sector • Establishment of information systems for the basin – Inclusive growth • Fostering contribution of SMEs to sustainable development of the region Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 20
  • 21. Added value • Indicators – Interest in the ISRBC approach • South-Eastern Europe • Mediterranean • Europe • Central Asia – Recognition of the Joint Statement Process • EU (e.g. in the European Parliament resolution on EUSDR) • Similar processes to be launched in the fields of hydropower and agriculture Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 21
  • 22. ISRBC and EUSDR • Main activities during the consultation and drafting process – Raising awareness that the EUSDR and the FASRB have the identical main objective – sustainable development of the region they refer to – Presentation of the ISRBC approach to sustainable development of the Sava region – Presentation of the ISRBC priority projects appropriate to be executed within the implementation of the EUSDR Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 22
  • 23. ISRBC and EUSDR • Main messages during the consultation and drafting process – The ISRBC projects are worth to be taken into account, as they are: • the projects already agreed upon by the 4 countries • complementary to other projects proposed by the countries – The sub-regional level is likely to be the most effective level from the viewpoint of the EUSDR implementation – Implementation of the ISRBC projects in the framework of the EUSDR can yield double benefits – contribution to an effective implementation of both FASRB and EUSDR Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 23
  • 24. ISRBC and EUSDR • ISRBC projects included in the EUSDR Action Plan – Completion and adoption of the Sava RBM Plan PA 4 – Establishment and completion of the Sava GIS PA 4 – Examination of biodiversity and environmental status of sediment, water and biota in the Sava river basin PA 4 – Preparation and implementation of the water and climate adaptation plan for the Sava river basin PA 5 – Preparation and implementation of a water pollution contin- gency management plan for the Sava river basin PA 5 Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 24
  • 25. ISRBC and EUSDR • Other priority projects of the ISRBC – Rehabilitation and improvement of the Sava river waterway PA 1 – Support to preparation of the Flood Risk Management Plan for the Sava river basin PA 5 – Hydrological study for the Sava river basin PA 5 – Support to establishment of the Sava RIS PA 1 – Support to development of nautical tourism in the Sava river basin PA 3 – Development of the Hydro-meteorological information and flood forecasting and warning system for the Sava river basin PA 5 Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 25
  • 26. ISRBC and EUSDR • 3rd Meeting of the Parties (Brdo near Kranj, Slovenia, 31 May – 1 June 2011) Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 26
  • 27. Summary • Identical overall objective of the EUSDR and FASRB • Conformity of the ISRBC approach and its priority projects with the EUSDR priorities • High potential for synergy – implementation of the ISRBC projects within the EUSDR framework can contribute to the implementation of both EUSDR and FASRB • The sub-regional level is likely to be the most effective level from the viewpoint of the EUSDR implementation QUESTION: Baltic experience with the implementation on a sub-regional level ? Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 27
  • 28. Contact Information International Sava River Basin Commission Vladimira Nazora 61 10000 Zagreb Croatia www.savacommission.org Workshop "WRM aspects of the EU Baltic and Danube strategies", Budapest, 5 Apr 2011 28