International Burch university               Course : Building Construction Technology I
Architecture department                                              Date : xx / xx / xxxx
Sarajevo




              LECTURE NO.3
     RESPONSIBILITIES OF PARTICIPANTS

                         Building Construction Technology I


  Professor : Prof.dr.Nerman Rustempasic
  Assistant : M.Sc. Ahmed El Sayed
INTRODUCTION
   Today we will define the responsibilities of Construction
    participants.

   Participants in the Construction process are:
       investor
       Contractor
       Engineer of construction site
       Chief engineer of construction site
       Designer (Architect or Civil Engineer )
       The supervisory authority
       Reviser
THE INVESTOR - DEFINITION

   Investor is a legal or physical            person   in   whose
    name is built (the building structures).



   Design, control and validation projects, construction and
    technical supervision over building investor must entrust
    parties eligible to perform these activities prescribed by The
    Law.
THE INVESTOR – RESPONSIBILITIES
   Design, control, validation of projects, construction and technical
    supervision over Construction must entrusted to persons
    registered for performing these activities.

   Appointing    a chief designer (when there are two or more
    designers).

   for Revising projects to authorized an reviser, if necessary.

   Obtain evidence of the right to construct at a particular property

   Obtain decision on constructing conditions / location / building
    permit
THE INVESTOR – RESPONSIBILITIES
   Appointing a contractor responsible to harmonization of
    work when participating in the construction two or more
    contractors.

   Before the start of construction to obtain an act authorizing
    the construction and report the start construction (the survey
    project + (un) approved major project); report the start of
    building to constructing body and a building inspection not
    later than 8 days before the start / continuation of work after
    a break longer than three months.
THE INVESTOR – RESPONSIBILITIES
   Provide technical     supervision    over   of   construction   or
    reconstruction.

   Appoint a chief supervisor (if there is more than adequate
    supervisory engineers waist for individual papers).

   investor who is also the contractor must entrust technical
    supervision over construction to another person who is
    registered for technical supervision.

   Person that is investor for residential or residential-commercial
    building whose construction (brutto) area does not exceed 400
    m2 , for its own purposes can design it by himself and perform
    construction supervision, if has the appropriate professional
    qualifications.
THE INVESTOR – RESPONSIBILITIES
   Must allow timely review of the work, on the demand of the
    designer.

   If the realization/execution project has not made by the engineer
    of the main project, the investor is required before the start of
    construction or performance of specific components to provide
    realization project or its parts to obtain opinions on the
    realization Project and its compliance with the main project.

   Also is required to enable The Reviser timely control of works.

   To obtain Survey project of the building until the start of
    construction works.

   To ensure building, the neighboring buildings and areas in the
    case of interruption of works
THE INVESTOR – RESPONSIBILITIES
   Obtain technical amendment documentation (or new), if the
    changes in structure affect the technical properties essential to
    building.

   Obtain usage permit for the building, which is issued after
    successful completion of technical inspection on the building by
    the construction body.

   Permanently preserve relevant documents and projects for the
    construction of with the amendments marked and changes as
    long as the building exists

   Must act in accordance with the decisions of inspection
    during construction
THE INVESTOR – ACTIVITIES DURING THE
PREPARATION WORKS
   Securing sources for investment

   Definition and assignment of research works

   Assignment of making investment studies

   Rating investment study and make a final investment decision

   Obtain building land

   Defining the project task for the preparation of project
    documentation

   Assignment of project documentation
THE INVESTOR – ACTIVITIES DURING
CONSTUCTION WORKS
   Assignment of construction, installation and finishing works

   Supply (taking over) and installation of plant, equipment and
    devices

   Organize monitoring and directing the realization of investment
    project

   The execution of contractual obligations undertaken towards
    contractors

   The final calculation of the Construction Contract

   Obtaining the use permit
THE INVESTOR – ACTIVITIES DURING THE USAGE
OF THE BUILDING

   The building can only be used in a manner compliant to its
    purpose

   The organization of the test operation (testing functioning of
    the building, plant, equipment and devices)

   Development of current and investment maintenance of the
    building

   Investment maintenance of the building
THE CONTRACTOR - DEFINITONS

   The contractor is a person who builds or performing works
    on buildings.

   Building or performing individual works in the building can
    do a person registered for performing this activity.

   Contractor shall appoint site engineer or manager of
    works as a responsible person who leads all or some of the
    works on construction.
THE CONTRACTOR – RESPONSIBILITIES

   Must build in accordance with the act which authorized the
    construction

   Build with quality in accordance with the main and detailed design on the
    way to meet the essential requirements for building

   Must draw up a written declaration of executed works and the building
    maintenance conditions

   Apply the material, equipment and products with the proven quality
    (with document from the manufacturer or a certificate of product
    conformity)

   Provide evidence of the quality of construction, embedded products
    and equipment (under the provisions of the laws and requirements of the
    main project)
THE CONTRACTOR – RESPONSIBILITIES

   Properly dispose the construction waste generated during the works on
    the site

   investor shall appoint main contractor responsible for the harmonization
    of work if you participate in the construction a several contractors

   Contractor shall appoint the site engineer (graduated engineer with 5
    years of work experience and passed the professional exam), site
    engineer (graduated engineer with five years experience or an engineer
    with 5 years experience, all with professional exam), or site manager
    (High School Diploma with 5 years experience working with professional
    exam), which lead the construction
THE CONTRACTOR – RESPONSIBILITIES

   Make a study of safety at work and organize the construction site

   Enclose the site and prevent uncontrolled access for the unemployed

   Mark the construction site with prescribed markings and traffic
    signs

   For temporary occupation of public traffic area he must obtain prior
    approval of the competent authorities and enterprises

   For temporary occupation of the neighboring ground he must obtain a
    prior approval from the owner, according to special laws
THE CONTRACTOR – RESPONSIBILITIES

   Temporary facilities to be constructed in accordance with the
    regulations on protection measures against fire and explosion, health
    and safety and all other measures to protect human health and the
    environment

   Remove all temporary structures before obtaining the use permit

   Make plan of common temporary and temporary work sites

   Inform the labor inspection authorities about the start of works (8
    days before the start of works), i.e.: type of the intended works, staff and
    schedule, and responsible persons
THE ENGINEER OF CONSTUCTION SITE

   Site engineer and work manager are               responsible   for   the
    implementation of obligations under the Act.

   If participate in the construction two or more contractors, the investor
    determines the contractor responsible for the harmonization of work and
    who appoints the site engineer.

   The main contractor must perform at least half the work necessary for
    construction and the building.

   The main site engineer is responsible for the completeness and
    harmonization of works, for the harmonization of the implementation of
    obligations under the Act, and also coordinates the implementation of
    regulations which regulate safety and health of workers during
    construction works.
THE CHIEF ENGINEER OF CONSTUCTION SITE



   ... can be both engineer of the site and one of the contractors or
    manager of work for a particular type of work.




   The main site engineer, site engineer and head of work may be persons
    who are eligible for performing these tasks under a special law.
THE DESIGNER


   ... a natural person who under a special law has the right to use
    professional title licensed architect or engineer.



   The designer is responsible to design a projects that fulfill the prescribed
    conditions, in particular, to design a project to comply with the building
    location permit, to meets the essential requirements for the
    building and to comply with the provisions of this Law and special
    regulations.
THE DESIGNER - RESPONSIBILITIES

   The designer is responsible that the projects are to meet the
    requirements made by the Law on spatial Planning and Building Act and
    special laws and regulations

   If participate in the design of a several designers, investor appoints the
    designer who is responsible for the completeness and interconnection
    compliance of projects.

   The right to perform the design under the Law on spatial Planning and
    Construction has just the person with the professional title “licensed
    architect” or “licensed engineer”.
THE DESIGNER - RESPONSIBILITIES

   The designer can not be an employee of the person who is the
    contractor on the same construction

   The designer has to Correspond to that the preliminary/Conceptual and
    main, and all other projects are made according to the requirements of
    building regulations, respecting:

       Essential requirements for the building

       Regional planning solutions for construction work

       The conditions of special regulations that affect the design solutions

       Technical requirements (technical regulations and standards)
THE SUPERVISOR AUTHORITY
   investor is obliged to provide professional construction supervision
    according to the Law
   If the investor does not have authorized engineers for the supervision,
    he must contract with supervision organization that has a licensed
    engineer.
   This organization will appoint a supervisor (s)
   supervising engineer is an individual who under a special law has the
    right to use professional title of licensed architect or licensed
    Engineer      and    implement      on    behalf of     the   investor
    an expert supervision of construction if it meets the requirements
    of construction who under a special law and regulations adopted
    pursuant to that Act.
   The supervising engineer can not be an employee of person who is the
    contractor on the same building.
THE SUPERVISOR AUTHORITY - RESPONSIBILITIES

   In carrying out supervision of construction works supervising
    engineer shall:

       Supervise the construction to be in accordance with the decision on
        building conditions, confirmed main project, and building permit, the
        Act and special regulations,

       Determine whether the survey of the building done by the person
        authorized to conduct tasks of state survey and Real Property
        Cadastre under a special law,

       Determine whether the contractor meets the requirements for
        performing construction activities that are regulated by special law,
THE SUPERVISOR AUTHORITY - RESPONSIBILITIES

     Define the implementation of control procedures in respect of
      conformity assessment and quality evidence of certain parts the
      building by an authorized person who is not involved in the
      implementation process of issuing the documents and evidence to all
      parts of the building and performed for the works that are in progress
      in certain cases when such an obligation,

     Without delay to supply investors with all information about the
      defects and irregularities before the construction phase, while
      investors and building inspections and other inspections about the
      measures undertaken,

     Make a final report on the performance of the building.
THE REVISER

   Reviser is a natural person authorized to control the project.



   Reviser is responsible for the project or part of the project for
    which he spent his control and gave a positive report that
    meets the requirements of the Law, special laws and
    regulations made under the law, technical specifications and
    rules of profession regarding controlled properties.
THANK YOU

Más contenido relacionado

La actualidad más candente

Sustainable Construction
Sustainable ConstructionSustainable Construction
Sustainable ConstructionMohsen, S Ab
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_SpecificationAkash Bharti
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementAditi Shah
 
Specifications 101
Specifications 101Specifications 101
Specifications 101Andrej_M
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 
Building maintenance
Building maintenance Building maintenance
Building maintenance Janki Patel
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Construction practices
Construction practicesConstruction practices
Construction practicesArun Kurali
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 

La actualidad más candente (20)

Sustainable Construction
Sustainable ConstructionSustainable Construction
Sustainable Construction
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Construction contract
Construction contract Construction contract
Construction contract
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_Specification
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Specifications 101
Specifications 101Specifications 101
Specifications 101
 
Formwork
FormworkFormwork
Formwork
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Building maintenance
Building maintenance Building maintenance
Building maintenance
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 

Destacado

Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction siteHamdija Velagic
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
construction tech startup scene - companies
construction tech startup scene - companiesconstruction tech startup scene - companies
construction tech startup scene - companiesIan Beckett
 
Construction Tech Trends: Going Paperless in Construction
Construction Tech Trends: Going Paperless in ConstructionConstruction Tech Trends: Going Paperless in Construction
Construction Tech Trends: Going Paperless in ConstructionBridgit
 
Construction Tech Trends: Connected Jobsite and Automation
Construction Tech Trends: Connected Jobsite and AutomationConstruction Tech Trends: Connected Jobsite and Automation
Construction Tech Trends: Connected Jobsite and AutomationBridgit
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - siteHamdija Velagic
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldingsHamdija Velagic
 
Introduction to Arch Week 14
Introduction to Arch Week 14Introduction to Arch Week 14
Introduction to Arch Week 14Hamdija Velagic
 
Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Hamdija Velagic
 
Building Construction Class 2. definitions
Building Construction Class 2. definitionsBuilding Construction Class 2. definitions
Building Construction Class 2. definitionsHamdija Velagic
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materialsHamdija Velagic
 
Building Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsBuilding Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsHamdija Velagic
 
Climate change and Architects role and resposibilities
Climate change and Architects role and resposibilitiesClimate change and Architects role and resposibilities
Climate change and Architects role and resposibilitiesShereen Khashaba
 
Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Hamdija Velagic
 
Building Construction 4. tender offer
Building Construction 4. tender offerBuilding Construction 4. tender offer
Building Construction 4. tender offerHamdija Velagic
 

Destacado (20)

Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction site
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
construction tech startup scene - companies
construction tech startup scene - companiesconstruction tech startup scene - companies
construction tech startup scene - companies
 
Construction Tech Trends: Going Paperless in Construction
Construction Tech Trends: Going Paperless in ConstructionConstruction Tech Trends: Going Paperless in Construction
Construction Tech Trends: Going Paperless in Construction
 
Construction Tech Trends: Connected Jobsite and Automation
Construction Tech Trends: Connected Jobsite and AutomationConstruction Tech Trends: Connected Jobsite and Automation
Construction Tech Trends: Connected Jobsite and Automation
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldings
 
Introduction to Arch Week 14
Introduction to Arch Week 14Introduction to Arch Week 14
Introduction to Arch Week 14
 
Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]Intro to Architecture Week 5 [compatibility mode]
Intro to Architecture Week 5 [compatibility mode]
 
Building Construction Class 2. definitions
Building Construction Class 2. definitionsBuilding Construction Class 2. definitions
Building Construction Class 2. definitions
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
Building Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsBuilding Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participants
 
Climate change and Architects role and resposibilities
Climate change and Architects role and resposibilitiesClimate change and Architects role and resposibilities
Climate change and Architects role and resposibilities
 
Into. to Arch Week 2
Into. to Arch Week 2Into. to Arch Week 2
Into. to Arch Week 2
 
Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]Intro to Arch Week 4 [compatibility mode]
Intro to Arch Week 4 [compatibility mode]
 
Building Construction 4. tender offer
Building Construction 4. tender offerBuilding Construction 4. tender offer
Building Construction 4. tender offer
 
Into. to Arch Week 3
Into. to Arch Week 3Into. to Arch Week 3
Into. to Arch Week 3
 
Role of an architect
Role of an architectRole of an architect
Role of an architect
 

Similar a Building Construction and Tech. 3. Responsibilities of participants

Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionHamdija Velagic
 
Single Proprietorship JD
Single Proprietorship JDSingle Proprietorship JD
Single Proprietorship JDDean Apao
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionHamdija Velagic
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 RegulationsKhalida Suleymanova
 
UNIT 3 - Building Trades.docx
UNIT 3  - Building Trades.docxUNIT 3  - Building Trades.docx
UNIT 3 - Building Trades.docxTenbytenGraphics
 
Civil Construction Engineer
Civil Construction EngineerCivil Construction Engineer
Civil Construction EngineerMatt Tudge
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxSudas Duddey
 
Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Stephen Findlay
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016ssuserfa2cfd
 
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...Vipin Bakiwala
 

Similar a Building Construction and Tech. 3. Responsibilities of participants (20)

Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
 
Single Proprietorship JD
Single Proprietorship JDSingle Proprietorship JD
Single Proprietorship JD
 
Building Construction 2. rules and definition in construction
Building Construction 2. rules and definition in constructionBuilding Construction 2. rules and definition in construction
Building Construction 2. rules and definition in construction
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 Regulations
 
2014-2015
2014-20152014-2015
2014-2015
 
Final building-team
Final building-teamFinal building-team
Final building-team
 
Final building-team
Final building-teamFinal building-team
Final building-team
 
UNIT 3 - Building Trades.docx
UNIT 3  - Building Trades.docxUNIT 3  - Building Trades.docx
UNIT 3 - Building Trades.docx
 
Engr. Sikandar_resume
Engr. Sikandar_resumeEngr. Sikandar_resume
Engr. Sikandar_resume
 
Civil Construction Engineer
Civil Construction EngineerCivil Construction Engineer
Civil Construction Engineer
 
C4 - Scope of Work.pdf
C4 - Scope of Work.pdfC4 - Scope of Work.pdf
C4 - Scope of Work.pdf
 
Ici individual
Ici individualIci individual
Ici individual
 
Engr ilyas cv new
Engr ilyas cv newEngr ilyas cv new
Engr ilyas cv new
 
Ici individual
Ici individualIci individual
Ici individual
 
HSE Temporary works management plan
HSE Temporary works management planHSE Temporary works management plan
HSE Temporary works management plan
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
 
Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Managing Contractors Effectively 2011
Managing Contractors Effectively 2011
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016
 
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
'DRISHTI' Chapter 16: Checklist for Contract Document (कॉन्ट्रैक्ट डॉक्युमेंट...
 
LastNew CV
LastNew CVLastNew CV
LastNew CV
 

Más de Hamdija Velagic

Introduction to Arch Week 13
Introduction to Arch Week 13Introduction to Arch Week 13
Introduction to Arch Week 13Hamdija Velagic
 
Introduction to Arch Week 11
Introduction to Arch Week 11Introduction to Arch Week 11
Introduction to Arch Week 11Hamdija Velagic
 
Introduction to Arch List of potential questions
Introduction to Arch List of potential questionsIntroduction to Arch List of potential questions
Introduction to Arch List of potential questionsHamdija Velagic
 
Architecture form space order
Architecture form space orderArchitecture form space order
Architecture form space orderHamdija Velagic
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffoldingHamdija Velagic
 
Building Construction 6. intro to building materials
Building Construction 6. intro to building materialsBuilding Construction 6. intro to building materials
Building Construction 6. intro to building materialsHamdija Velagic
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 
New Intro to Architecture Week 4
New Intro to Architecture Week 4New Intro to Architecture Week 4
New Intro to Architecture Week 4Hamdija Velagic
 
1. Introduction to Project Management
1. Introduction to Project Management1. Introduction to Project Management
1. Introduction to Project ManagementHamdija Velagic
 

Más de Hamdija Velagic (9)

Introduction to Arch Week 13
Introduction to Arch Week 13Introduction to Arch Week 13
Introduction to Arch Week 13
 
Introduction to Arch Week 11
Introduction to Arch Week 11Introduction to Arch Week 11
Introduction to Arch Week 11
 
Introduction to Arch List of potential questions
Introduction to Arch List of potential questionsIntroduction to Arch List of potential questions
Introduction to Arch List of potential questions
 
Architecture form space order
Architecture form space orderArchitecture form space order
Architecture form space order
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffolding
 
Building Construction 6. intro to building materials
Building Construction 6. intro to building materialsBuilding Construction 6. intro to building materials
Building Construction 6. intro to building materials
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
New Intro to Architecture Week 4
New Intro to Architecture Week 4New Intro to Architecture Week 4
New Intro to Architecture Week 4
 
1. Introduction to Project Management
1. Introduction to Project Management1. Introduction to Project Management
1. Introduction to Project Management
 

Último

Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 

Último (20)

Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 

Building Construction and Tech. 3. Responsibilities of participants

  • 1. International Burch university Course : Building Construction Technology I Architecture department Date : xx / xx / xxxx Sarajevo LECTURE NO.3 RESPONSIBILITIES OF PARTICIPANTS Building Construction Technology I Professor : Prof.dr.Nerman Rustempasic Assistant : M.Sc. Ahmed El Sayed
  • 2. INTRODUCTION  Today we will define the responsibilities of Construction participants.  Participants in the Construction process are:  investor  Contractor  Engineer of construction site  Chief engineer of construction site  Designer (Architect or Civil Engineer )  The supervisory authority  Reviser
  • 3. THE INVESTOR - DEFINITION  Investor is a legal or physical person in whose name is built (the building structures).  Design, control and validation projects, construction and technical supervision over building investor must entrust parties eligible to perform these activities prescribed by The Law.
  • 4. THE INVESTOR – RESPONSIBILITIES  Design, control, validation of projects, construction and technical supervision over Construction must entrusted to persons registered for performing these activities.  Appointing a chief designer (when there are two or more designers).  for Revising projects to authorized an reviser, if necessary.  Obtain evidence of the right to construct at a particular property  Obtain decision on constructing conditions / location / building permit
  • 5. THE INVESTOR – RESPONSIBILITIES  Appointing a contractor responsible to harmonization of work when participating in the construction two or more contractors.  Before the start of construction to obtain an act authorizing the construction and report the start construction (the survey project + (un) approved major project); report the start of building to constructing body and a building inspection not later than 8 days before the start / continuation of work after a break longer than three months.
  • 6. THE INVESTOR – RESPONSIBILITIES  Provide technical supervision over of construction or reconstruction.  Appoint a chief supervisor (if there is more than adequate supervisory engineers waist for individual papers).  investor who is also the contractor must entrust technical supervision over construction to another person who is registered for technical supervision.  Person that is investor for residential or residential-commercial building whose construction (brutto) area does not exceed 400 m2 , for its own purposes can design it by himself and perform construction supervision, if has the appropriate professional qualifications.
  • 7. THE INVESTOR – RESPONSIBILITIES  Must allow timely review of the work, on the demand of the designer.  If the realization/execution project has not made by the engineer of the main project, the investor is required before the start of construction or performance of specific components to provide realization project or its parts to obtain opinions on the realization Project and its compliance with the main project.  Also is required to enable The Reviser timely control of works.  To obtain Survey project of the building until the start of construction works.  To ensure building, the neighboring buildings and areas in the case of interruption of works
  • 8. THE INVESTOR – RESPONSIBILITIES  Obtain technical amendment documentation (or new), if the changes in structure affect the technical properties essential to building.  Obtain usage permit for the building, which is issued after successful completion of technical inspection on the building by the construction body.  Permanently preserve relevant documents and projects for the construction of with the amendments marked and changes as long as the building exists  Must act in accordance with the decisions of inspection during construction
  • 9. THE INVESTOR – ACTIVITIES DURING THE PREPARATION WORKS  Securing sources for investment  Definition and assignment of research works  Assignment of making investment studies  Rating investment study and make a final investment decision  Obtain building land  Defining the project task for the preparation of project documentation  Assignment of project documentation
  • 10. THE INVESTOR – ACTIVITIES DURING CONSTUCTION WORKS  Assignment of construction, installation and finishing works  Supply (taking over) and installation of plant, equipment and devices  Organize monitoring and directing the realization of investment project  The execution of contractual obligations undertaken towards contractors  The final calculation of the Construction Contract  Obtaining the use permit
  • 11. THE INVESTOR – ACTIVITIES DURING THE USAGE OF THE BUILDING  The building can only be used in a manner compliant to its purpose  The organization of the test operation (testing functioning of the building, plant, equipment and devices)  Development of current and investment maintenance of the building  Investment maintenance of the building
  • 12. THE CONTRACTOR - DEFINITONS  The contractor is a person who builds or performing works on buildings.  Building or performing individual works in the building can do a person registered for performing this activity.  Contractor shall appoint site engineer or manager of works as a responsible person who leads all or some of the works on construction.
  • 13. THE CONTRACTOR – RESPONSIBILITIES  Must build in accordance with the act which authorized the construction  Build with quality in accordance with the main and detailed design on the way to meet the essential requirements for building  Must draw up a written declaration of executed works and the building maintenance conditions  Apply the material, equipment and products with the proven quality (with document from the manufacturer or a certificate of product conformity)  Provide evidence of the quality of construction, embedded products and equipment (under the provisions of the laws and requirements of the main project)
  • 14. THE CONTRACTOR – RESPONSIBILITIES  Properly dispose the construction waste generated during the works on the site  investor shall appoint main contractor responsible for the harmonization of work if you participate in the construction a several contractors  Contractor shall appoint the site engineer (graduated engineer with 5 years of work experience and passed the professional exam), site engineer (graduated engineer with five years experience or an engineer with 5 years experience, all with professional exam), or site manager (High School Diploma with 5 years experience working with professional exam), which lead the construction
  • 15. THE CONTRACTOR – RESPONSIBILITIES  Make a study of safety at work and organize the construction site  Enclose the site and prevent uncontrolled access for the unemployed  Mark the construction site with prescribed markings and traffic signs  For temporary occupation of public traffic area he must obtain prior approval of the competent authorities and enterprises  For temporary occupation of the neighboring ground he must obtain a prior approval from the owner, according to special laws
  • 16. THE CONTRACTOR – RESPONSIBILITIES  Temporary facilities to be constructed in accordance with the regulations on protection measures against fire and explosion, health and safety and all other measures to protect human health and the environment  Remove all temporary structures before obtaining the use permit  Make plan of common temporary and temporary work sites  Inform the labor inspection authorities about the start of works (8 days before the start of works), i.e.: type of the intended works, staff and schedule, and responsible persons
  • 17. THE ENGINEER OF CONSTUCTION SITE  Site engineer and work manager are responsible for the implementation of obligations under the Act.  If participate in the construction two or more contractors, the investor determines the contractor responsible for the harmonization of work and who appoints the site engineer.  The main contractor must perform at least half the work necessary for construction and the building.  The main site engineer is responsible for the completeness and harmonization of works, for the harmonization of the implementation of obligations under the Act, and also coordinates the implementation of regulations which regulate safety and health of workers during construction works.
  • 18. THE CHIEF ENGINEER OF CONSTUCTION SITE  ... can be both engineer of the site and one of the contractors or manager of work for a particular type of work.  The main site engineer, site engineer and head of work may be persons who are eligible for performing these tasks under a special law.
  • 19. THE DESIGNER  ... a natural person who under a special law has the right to use professional title licensed architect or engineer.  The designer is responsible to design a projects that fulfill the prescribed conditions, in particular, to design a project to comply with the building location permit, to meets the essential requirements for the building and to comply with the provisions of this Law and special regulations.
  • 20. THE DESIGNER - RESPONSIBILITIES  The designer is responsible that the projects are to meet the requirements made by the Law on spatial Planning and Building Act and special laws and regulations  If participate in the design of a several designers, investor appoints the designer who is responsible for the completeness and interconnection compliance of projects.  The right to perform the design under the Law on spatial Planning and Construction has just the person with the professional title “licensed architect” or “licensed engineer”.
  • 21. THE DESIGNER - RESPONSIBILITIES  The designer can not be an employee of the person who is the contractor on the same construction  The designer has to Correspond to that the preliminary/Conceptual and main, and all other projects are made according to the requirements of building regulations, respecting:  Essential requirements for the building  Regional planning solutions for construction work  The conditions of special regulations that affect the design solutions  Technical requirements (technical regulations and standards)
  • 22. THE SUPERVISOR AUTHORITY  investor is obliged to provide professional construction supervision according to the Law  If the investor does not have authorized engineers for the supervision, he must contract with supervision organization that has a licensed engineer.  This organization will appoint a supervisor (s)  supervising engineer is an individual who under a special law has the right to use professional title of licensed architect or licensed Engineer and implement on behalf of the investor an expert supervision of construction if it meets the requirements of construction who under a special law and regulations adopted pursuant to that Act.  The supervising engineer can not be an employee of person who is the contractor on the same building.
  • 23. THE SUPERVISOR AUTHORITY - RESPONSIBILITIES  In carrying out supervision of construction works supervising engineer shall:  Supervise the construction to be in accordance with the decision on building conditions, confirmed main project, and building permit, the Act and special regulations,  Determine whether the survey of the building done by the person authorized to conduct tasks of state survey and Real Property Cadastre under a special law,  Determine whether the contractor meets the requirements for performing construction activities that are regulated by special law,
  • 24. THE SUPERVISOR AUTHORITY - RESPONSIBILITIES  Define the implementation of control procedures in respect of conformity assessment and quality evidence of certain parts the building by an authorized person who is not involved in the implementation process of issuing the documents and evidence to all parts of the building and performed for the works that are in progress in certain cases when such an obligation,  Without delay to supply investors with all information about the defects and irregularities before the construction phase, while investors and building inspections and other inspections about the measures undertaken,  Make a final report on the performance of the building.
  • 25. THE REVISER  Reviser is a natural person authorized to control the project.  Reviser is responsible for the project or part of the project for which he spent his control and gave a positive report that meets the requirements of the Law, special laws and regulations made under the law, technical specifications and rules of profession regarding controlled properties.