Project Surveying



              20/01/2013   1
Electronic Distance Measurement
(EDM)




                     20/01/2013   2
• 1950s.
• Large, heavy, complicated and expensive (old EDM).
• Lighter, simpler and less expensive (new EDM).
• EDM Instruments use infrared light, laser light or
microwaves.
• Receiver/Transmitter at one end and Prism at the other end.
• EDM Instruments come in long range (10 – 20) km, medium
range (3 – 10) km and short range (0.5 – 3) km.


• Some laser EDM Instruments measure short distances (100
– 350) m without reflecting prism.


•Microwave instruments are often used in hydrographic
surveys 50 km. Currently GPS.



                               20/01/2013                       3
Electronic Angle Measurement
             (Total Stations)
Combine the function of Theodolite and EDM




                    20/01/2013               4
Principles of EDM
            y



                                              x
            



   = c/f             c = 299,792.458 km/s (in vacuum)

: wavelength (m)
c: velocity (km/s)
f: frequency (Hz, hertz; one cycle per second)


                                 20/01/2013              5
Principles of EDM

                               
             1
                     2
                               3     4

                                                      2L = (n + )


                        n     n-1



c, the velocity of light through the atmosphere can be affected by:
• Temperature
• Atmospheric Pressure
• Water Vapour Content




                                         20/01/2013                   6
EDM Characteristics
    • The more expensive EDM instruments have longer distance range
    and higher precision.


Distance Range:
•   800 m – 1 km (single prism).
•   Short-range EDM can be extended to 1,300 m using 3 prisms.
•   Long-range EDM can be extended to 15 km using 11 prisms.


Accuracy Range:
 (5 mm + 5 ppm) for short-range EDM.
 (2 mm + 1 ppm) for long-range EDM.


                                    20/01/2013                        7
EDM Characteristics

Measuring Time:
1.5 seconds for short-range EDM.
3.5 seconds for long-range EDM.

 Battery Capability:
 1,400 – 4200 measurements depending on the size and
 condition of battery and the temperature.

  Temperature Range:
  - 20c + 50c

  Non-prism measurements: 100 – 350 m

                                  20/01/2013           8
Prisms

Prisms are surveying tools used with EDM and Total Stations to
reflect the transmitted signals.


 • Prisms must be tribrach-mounted if a higher level of accuracy is
 required (Control Surveys).


 • Prisms mounted on adjustable-length prism poles are portable and
 suited particularly for (Stakeout and Topographic Surveys)




                                    20/01/2013                        9
EDM Instrument Accuracies


Accuracy Range:
 (2 mm + 1 ppm) to  (10 mm + 10 ppm)


Constant Instrumental Error e.g. 5 mm represents an accuracy of
1/2,000 at 10 m, 1/20,000 at 100 m, 1/200,000 at 1,000 m.


Measuring error is proportional to the distance being measured
e.g. 10 ppm.




                                  20/01/2013                      10
Field Method for

    Determining the Instrument-Reflector Constant




A                                 B                     C




           AC – AB – BC = Instrument/Present Constant




                                20/01/2013                  11
EDM Operation
• Set Up
• Aim
• Measure
• Record



               20/01/2013   12
Geometry of EDM
• Optical target and reflecting prism
  are at the same height
• EDM (S), theodolite ()
• Adjustable-length prism pole
  (HR = hi)
• Elev. (B) = Elev. (A) +hi  h - HR
                    20/01/2013          13
Problem 1
Refer to Figure below. A top-mounted EDM instrument
is set up at station A, its elevation, (HA = 650.000 m).
Using the following values, compute the horizontal
distance from A to B and the elevation of B, (HB). The
optical centre of the theodolite is hi = 1.601 m above
station and a vertical angle of + 4◦ 18 30 is measured
to the target, which is 1.915 m (HR) above station B.
The EDM instrument centre is 0.100 m (hi) above the
theodolite and the reflecting prism is 0.150 m (HR)
above the target. The slope distance is measured to
be 387.603 m.


                            20/01/2013                     14
Prism
                        S
                                                            HR
                                                Target
          
   EDM                                                   2.065 m

                                                          HR
 hi


 hi
                                            B
1.701 m
                                                            X cos 
                              S                   X

   A                                   S

                   
                                  k
               




                        20/01/2013                                    15
Solution

         X cos 
sin  
            S


X  HR  hi



                   20/01/2013   16
X = 0.15 – 0.10 = 0.05 m

 = 4◦ 18 30 = 4◦.308

S = 387.603 m

 = 26.53

k =  +   =

4◦ 18 30 + 26.53 = 4◦ 18 56.53 = 4◦.3157

                          20/01/2013            17
Computation of the horizontal distance from A to B (H):


H = S cos (k) = 386.504 m




                             20/01/2013                   18
Computation of the elevation of B, (HB):


 H B  H A  hi  h  HR

              ,




                        20/01/2013         19
HA = 650.000 m

h = S sin (k) = 29.168 m

HB = 650.000 + (1.601 + 0.10) + 29.168 – (1.915 + 0.15)

   = 678.804 m

HB = 678.804 m
                 ,




                               20/01/2013                 20
Problem 2
A line AB is measured at both ends as follows:
At A, slope distance = 1458.777 m,
zenith angle = 91 26 50.
At B, slope distance = 1458.757 m,
zenith angle = 88 33 22.
The heights of the instrument, reflector and target are
    equal for each observation.

•   Compute the horizontal distance AB.

•   If the elevation at A is 590.825 m, what is the
    elevation at B?

•   Calculate the gradient between A and B.

                            20/01/2013                    21
H = S cos 

    -1 26 44
                                            h = S sin 

    - 2.5%
                  S = 1458.767 m
A


                                                B




                                   20/01/2013              22
Solution
S1 = 1458.777 m, S2 = 1458.757 m

S = (S1 + S2)/2 = 1458.767 m

1 = 90 00 00 - 91 26 50 = - 1 26 50

2 = 90 00 00 - 88 33 22 = 1 26 38

 = (1 + 2)/2 = 1 26 44




                        20/01/2013              23
Solution
H = S cos  = 1458.303 m


HA = 590.825 m,

h = S sin  = 36.800 m.

HB = HA - h = 590.825 - 36.800 = 554.025 m.

Gradient between A and B

= (h/H)  100 = - 2.5%


                           20/01/2013          24
Problem 3
Refer to Figure below; angles 1, 2,…....8 of a
   quadrilateral of a triangulation network were
   adjusted. If, DA = 213.36 m, XD = 171,719.32 m, YD =
   114,056.00 m and the bearing of the line DA is
   equal to N 25 00 00 W.

•   Calculate the distances AB, BC and CD.

•   Calculate the bearings of the lines AB, BC and CD.

•   Calculate the coordinates of points A, B and C.




                          20/01/2013                  25
Quadrilateral Adjustment

    A


        1       2




                                             B
                            3

                                     4




    8
            7
                                 5
D
                        6
                                         C




                    20/01/2013                   26
Quadrilateral Adjustment

  Angles i   Adjusted values
     1         38 44 08
     2         23 44 33
     3         42 19 08
     4         44 51 57
     5         69 04 22
     6         39 37 47
     7         26 25 54
     8         75 12 11


                      20/01/2013   27
Solution

• Distances:

Applying the law of sines by solving triangles:
ABD for AB, ABC for BC, ACD for DC:

AB = AD sin8/sin3 = 306.40 m

BC = AB sin2/sin5 = 132.07 m

CD = AD sin1/sin6 = 209.31 m



                       20/01/2013                 28
Solution

Bearings:

If you redraw the figure below, you can calculate
the bearings of the lines AB, BC and CD as follows:




                          20/01/2013                  29
Solution

Bearings:
    W           E

        A

            S


                                      B




    D
                                  C




                     20/01/2013           30
Solution
Bearings:

 Brg of AB = (1 + 2) – Brg of AD
          = (38 44 08 + 23 44 33) - 25 00 00 = 37 28 41
 The complete bearing of line AB is S37 28 41E

 Brg of BC = 180 00 00 - (3 + 4 + Brg of BA)
           = 179 59 60 - (42 19 08 + 44 51 57 +37 28 41)
           = 55 20 14
 The complete bearing of line BC is S55 20 14W

 Brg of CD = (5 + 6) – Brg of CB
           = (69 04 22 + 39 37 47) - 55 20 14 = 53 21 55
 The complete bearing of line CD is N53 21 55W



                                20/01/2013                             31
Coordinates:
                  Solution
XD = 171,719.32 m, YD = 114,056.00 m
 XA = XD + DA sin (25 00 00) = 171,809.49 m

 YA = YD + DA cos (25 00 00) = 114,249.37 m


 XB = XA + AB sin (37 28 41) = 171,995.92 m

 YB = YA - AB cos (37 28 41) = 114,006.22 m


 XC = XB - BC sin (55 20 14) = 171,887.29 m

 YC = YB - BC cos (55 20 14) = 113,931.10 m


                              20/01/2013         32
Total Stations



• Background
• Main Characteristics
• Applications




                 20/01/2013   33
Main Characteristics
•   Parameter Input
1. Angle Units: degrees or gon.
2. Distance Units: ft or m.
3. Pressure Units: inches HG or mm HG.
4. Temperature Units: F or C.
5. Prism constant (- 0.03 m).

                       20/01/2013        34
Main Characteristics
•   Parameter Input
6. Offset distance.
7. Face 1 or face 2 selection.
8. Automatic point no. incrementation.
9. Hi
10. HR

                      20/01/2013         35
Main Characteristics
•   Parameter Input
11. Point numbers and code numbers
  for occupied and sighted stations.
12. Date and time settings.




                      20/01/2013       36
Main Characteristics
•   Capabilities
1. Monitor: battery status, signal attenuation,
   horizontal and vertical axes status, collimation
   factors.
2. Compute coordinates (N, E, Z).
3. Traverse closure and adjustment, and areas.
4. Topography reductions.
5. Object heights.
6. Distances between remote points.


                             20/01/2013               37
Main Characteristics
•   Capabilities
7. Inversing.
8. Resection.
9. Layout (Setting out).
10. Horizontal and vertical collimation corrections.
11. Vertical circle indexing.
12. Records search and review.
13. Loading external programmes.
14. Downloading and uploading.

                                20/01/2013             38
Applications
•     Point Location
                                            New Point
                                               B




                                      d2
    Reference Control Point

             P                


                                    A       Station
                              20/01/2013                39
Applications
•     Point Location

    • Known:
    N, E and Z of A,
    N, E and Z of P/Azimuth of AP.
    • Measured:
    Angles or azimuths from the control point () and d.
    • Computed:
    N, E and Z of B and azimuth of AB and d.

                               20/01/2013                  40

Más contenido relacionado

La actualidad más candente (20)

Curves
CurvesCurves
Curves
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Tacheometric survey
Tacheometric surveyTacheometric survey
Tacheometric survey
 
Surveying by using Digital Theodolite
Surveying by using Digital TheodoliteSurveying by using Digital Theodolite
Surveying by using Digital Theodolite
 
Total station
Total stationTotal station
Total station
 
Total station surveying
Total station surveyingTotal station surveying
Total station surveying
 
EDM ( Electronic distance meter)
EDM ( Electronic distance meter)EDM ( Electronic distance meter)
EDM ( Electronic distance meter)
 
Total station Surveying
Total station SurveyingTotal station Surveying
Total station Surveying
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
 
5. AREAS AND VOLUMES (SUR) 3140601 GTU
5. AREAS AND VOLUMES (SUR) 3140601 GTU5. AREAS AND VOLUMES (SUR) 3140601 GTU
5. AREAS AND VOLUMES (SUR) 3140601 GTU
 
tacheometry surveying
tacheometry surveyingtacheometry surveying
tacheometry surveying
 
Total station
Total stationTotal station
Total station
 
Theodolite survey
Theodolite surveyTheodolite survey
Theodolite survey
 
Total Station surveying
Total Station surveyingTotal Station surveying
Total Station surveying
 
EDM
EDMEDM
EDM
 
Trigonometric levelling
Trigonometric levellingTrigonometric levelling
Trigonometric levelling
 
Lecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryLecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetry
 
MODERN SURVEYING TECHNIQUES
MODERN SURVEYING TECHNIQUESMODERN SURVEYING TECHNIQUES
MODERN SURVEYING TECHNIQUES
 
Types of level
Types of levelTypes of level
Types of level
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
 

Similar a EDM and Total Stations

Radiacion poligonal abierta
Radiacion   poligonal abiertaRadiacion   poligonal abierta
Radiacion poligonal abiertaJeanCordova7
 
OE Instrumentation_03_Interferometry_2.pdf
OE Instrumentation_03_Interferometry_2.pdfOE Instrumentation_03_Interferometry_2.pdf
OE Instrumentation_03_Interferometry_2.pdfJamesWalter40
 
Project 2- traversing
Project 2- traversingProject 2- traversing
Project 2- traversingseenyee
 
Project 2- traversing
Project 2- traversingProject 2- traversing
Project 2- traversingseenyee
 
TACHYMETRY lesson 1 introduction
TACHYMETRY lesson 1   introduction TACHYMETRY lesson 1   introduction
TACHYMETRY lesson 1 introduction kmasz kamal
 
SatCom_Numerical Probloms.pptx
SatCom_Numerical Probloms.pptxSatCom_Numerical Probloms.pptx
SatCom_Numerical Probloms.pptxEshP1
 
Site survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversingSite survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversingSheng Zhe
 
Assignment 2 - Traverse
Assignment 2 - TraverseAssignment 2 - Traverse
Assignment 2 - TraverseKai Yun Pang
 
S2 6 theodolites
S2 6 theodolitesS2 6 theodolites
S2 6 theodolitesEst
 
'Documents.mx dynamics solucionario-riley.pdf'
'Documents.mx dynamics solucionario-riley.pdf''Documents.mx dynamics solucionario-riley.pdf'
'Documents.mx dynamics solucionario-riley.pdf'jhameschiqui
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2Doreen Yeo
 
OE Instrumentation_02_Interferometry_1.pdf
OE Instrumentation_02_Interferometry_1.pdfOE Instrumentation_02_Interferometry_1.pdf
OE Instrumentation_02_Interferometry_1.pdfJamesWalter40
 
Topic 4 curve lesson 2
Topic 4   curve lesson 2Topic 4   curve lesson 2
Topic 4 curve lesson 2kmasz kamal
 
Site Surveying Traversing
Site Surveying TraversingSite Surveying Traversing
Site Surveying TraversingDarren Lee
 

Similar a EDM and Total Stations (20)

Route Surveys
Route SurveysRoute Surveys
Route Surveys
 
Radiacion poligonal abierta
Radiacion   poligonal abiertaRadiacion   poligonal abierta
Radiacion poligonal abierta
 
OE Instrumentation_03_Interferometry_2.pdf
OE Instrumentation_03_Interferometry_2.pdfOE Instrumentation_03_Interferometry_2.pdf
OE Instrumentation_03_Interferometry_2.pdf
 
Project 2- traversing
Project 2- traversingProject 2- traversing
Project 2- traversing
 
Project 2- traversing
Project 2- traversingProject 2- traversing
Project 2- traversing
 
TACHYMETRY lesson 1 introduction
TACHYMETRY lesson 1   introduction TACHYMETRY lesson 1   introduction
TACHYMETRY lesson 1 introduction
 
SatCom_Numerical Probloms.pptx
SatCom_Numerical Probloms.pptxSatCom_Numerical Probloms.pptx
SatCom_Numerical Probloms.pptx
 
Site survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversingSite survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversing
 
Assignment 2 - Traverse
Assignment 2 - TraverseAssignment 2 - Traverse
Assignment 2 - Traverse
 
Math12 (week 1)
Math12 (week 1)Math12 (week 1)
Math12 (week 1)
 
PresentationSAR
PresentationSARPresentationSAR
PresentationSAR
 
M010327985
M010327985M010327985
M010327985
 
S2 6 theodolites
S2 6 theodolitesS2 6 theodolites
S2 6 theodolites
 
Antenna Design Course work
Antenna Design Course workAntenna Design Course work
Antenna Design Course work
 
'Documents.mx dynamics solucionario-riley.pdf'
'Documents.mx dynamics solucionario-riley.pdf''Documents.mx dynamics solucionario-riley.pdf'
'Documents.mx dynamics solucionario-riley.pdf'
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2
 
OE Instrumentation_02_Interferometry_1.pdf
OE Instrumentation_02_Interferometry_1.pdfOE Instrumentation_02_Interferometry_1.pdf
OE Instrumentation_02_Interferometry_1.pdf
 
UNIT 1.pptx
UNIT 1.pptxUNIT 1.pptx
UNIT 1.pptx
 
Topic 4 curve lesson 2
Topic 4   curve lesson 2Topic 4   curve lesson 2
Topic 4 curve lesson 2
 
Site Surveying Traversing
Site Surveying TraversingSite Surveying Traversing
Site Surveying Traversing
 

Más de haroldtaylor1113

Design Coordinates Incorporated
Design Coordinates IncorporatedDesign Coordinates Incorporated
Design Coordinates Incorporatedharoldtaylor1113
 
Case Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater ManagementCase Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater Managementharoldtaylor1113
 
Case Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in LagunaCase Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in Lagunaharoldtaylor1113
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Provinceharoldtaylor1113
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manilaharoldtaylor1113
 
Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067haroldtaylor1113
 
Case Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the PhilippinesCase Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the Philippinesharoldtaylor1113
 
Case Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the PhilippinesCase Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the Philippinesharoldtaylor1113
 
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan CityCase Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan Cityharoldtaylor1113
 
Case Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in AquacultureCase Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in Aquacultureharoldtaylor1113
 
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...haroldtaylor1113
 
Case Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, CaviteCase Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, Caviteharoldtaylor1113
 
Case Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of SuccessCase Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of Successharoldtaylor1113
 
Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen  Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen haroldtaylor1113
 
Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine haroldtaylor1113
 
Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection haroldtaylor1113
 
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...haroldtaylor1113
 
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...haroldtaylor1113
 
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...haroldtaylor1113
 
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...haroldtaylor1113
 

Más de haroldtaylor1113 (20)

Design Coordinates Incorporated
Design Coordinates IncorporatedDesign Coordinates Incorporated
Design Coordinates Incorporated
 
Case Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater ManagementCase Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater Management
 
Case Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in LagunaCase Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in Laguna
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Province
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manila
 
Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067
 
Case Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the PhilippinesCase Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the Philippines
 
Case Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the PhilippinesCase Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the Philippines
 
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan CityCase Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
 
Case Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in AquacultureCase Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in Aquaculture
 
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
 
Case Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, CaviteCase Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, Cavite
 
Case Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of SuccessCase Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of Success
 
Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen  Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen
 
Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine
 
Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection
 
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
 
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
 
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
 
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
 

Último

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 

Último (20)

DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 

EDM and Total Stations

  • 1. Project Surveying 20/01/2013 1
  • 3. • 1950s. • Large, heavy, complicated and expensive (old EDM). • Lighter, simpler and less expensive (new EDM). • EDM Instruments use infrared light, laser light or microwaves. • Receiver/Transmitter at one end and Prism at the other end. • EDM Instruments come in long range (10 – 20) km, medium range (3 – 10) km and short range (0.5 – 3) km. • Some laser EDM Instruments measure short distances (100 – 350) m without reflecting prism. •Microwave instruments are often used in hydrographic surveys 50 km. Currently GPS. 20/01/2013 3
  • 4. Electronic Angle Measurement (Total Stations) Combine the function of Theodolite and EDM 20/01/2013 4
  • 5. Principles of EDM y x   = c/f c = 299,792.458 km/s (in vacuum) : wavelength (m) c: velocity (km/s) f: frequency (Hz, hertz; one cycle per second) 20/01/2013 5
  • 6. Principles of EDM  1 2 3 4 2L = (n + )  n n-1 c, the velocity of light through the atmosphere can be affected by: • Temperature • Atmospheric Pressure • Water Vapour Content 20/01/2013 6
  • 7. EDM Characteristics • The more expensive EDM instruments have longer distance range and higher precision. Distance Range: • 800 m – 1 km (single prism). • Short-range EDM can be extended to 1,300 m using 3 prisms. • Long-range EDM can be extended to 15 km using 11 prisms. Accuracy Range:  (5 mm + 5 ppm) for short-range EDM.  (2 mm + 1 ppm) for long-range EDM. 20/01/2013 7
  • 8. EDM Characteristics Measuring Time: 1.5 seconds for short-range EDM. 3.5 seconds for long-range EDM. Battery Capability: 1,400 – 4200 measurements depending on the size and condition of battery and the temperature. Temperature Range: - 20c + 50c Non-prism measurements: 100 – 350 m 20/01/2013 8
  • 9. Prisms Prisms are surveying tools used with EDM and Total Stations to reflect the transmitted signals. • Prisms must be tribrach-mounted if a higher level of accuracy is required (Control Surveys). • Prisms mounted on adjustable-length prism poles are portable and suited particularly for (Stakeout and Topographic Surveys) 20/01/2013 9
  • 10. EDM Instrument Accuracies Accuracy Range:  (2 mm + 1 ppm) to  (10 mm + 10 ppm) Constant Instrumental Error e.g. 5 mm represents an accuracy of 1/2,000 at 10 m, 1/20,000 at 100 m, 1/200,000 at 1,000 m. Measuring error is proportional to the distance being measured e.g. 10 ppm. 20/01/2013 10
  • 11. Field Method for Determining the Instrument-Reflector Constant A B C AC – AB – BC = Instrument/Present Constant 20/01/2013 11
  • 12. EDM Operation • Set Up • Aim • Measure • Record 20/01/2013 12
  • 13. Geometry of EDM • Optical target and reflecting prism are at the same height • EDM (S), theodolite () • Adjustable-length prism pole (HR = hi) • Elev. (B) = Elev. (A) +hi  h - HR 20/01/2013 13
  • 14. Problem 1 Refer to Figure below. A top-mounted EDM instrument is set up at station A, its elevation, (HA = 650.000 m). Using the following values, compute the horizontal distance from A to B and the elevation of B, (HB). The optical centre of the theodolite is hi = 1.601 m above station and a vertical angle of + 4◦ 18 30 is measured to the target, which is 1.915 m (HR) above station B. The EDM instrument centre is 0.100 m (hi) above the theodolite and the reflecting prism is 0.150 m (HR) above the target. The slope distance is measured to be 387.603 m. 20/01/2013 14
  • 15. Prism S HR Target  EDM 2.065 m  HR hi hi B 1.701 m X cos  S X A S  k  20/01/2013 15
  • 16. Solution X cos  sin   S X  HR  hi 20/01/2013 16
  • 17. X = 0.15 – 0.10 = 0.05 m  = 4◦ 18 30 = 4◦.308 S = 387.603 m  = 26.53 k =  +   = 4◦ 18 30 + 26.53 = 4◦ 18 56.53 = 4◦.3157 20/01/2013 17
  • 18. Computation of the horizontal distance from A to B (H): H = S cos (k) = 386.504 m 20/01/2013 18
  • 19. Computation of the elevation of B, (HB): H B  H A  hi  h  HR , 20/01/2013 19
  • 20. HA = 650.000 m h = S sin (k) = 29.168 m HB = 650.000 + (1.601 + 0.10) + 29.168 – (1.915 + 0.15) = 678.804 m HB = 678.804 m , 20/01/2013 20
  • 21. Problem 2 A line AB is measured at both ends as follows: At A, slope distance = 1458.777 m, zenith angle = 91 26 50. At B, slope distance = 1458.757 m, zenith angle = 88 33 22. The heights of the instrument, reflector and target are equal for each observation. • Compute the horizontal distance AB. • If the elevation at A is 590.825 m, what is the elevation at B? • Calculate the gradient between A and B. 20/01/2013 21
  • 22. H = S cos  -1 26 44 h = S sin  - 2.5% S = 1458.767 m A B 20/01/2013 22
  • 23. Solution S1 = 1458.777 m, S2 = 1458.757 m S = (S1 + S2)/2 = 1458.767 m 1 = 90 00 00 - 91 26 50 = - 1 26 50 2 = 90 00 00 - 88 33 22 = 1 26 38  = (1 + 2)/2 = 1 26 44 20/01/2013 23
  • 24. Solution H = S cos  = 1458.303 m HA = 590.825 m, h = S sin  = 36.800 m. HB = HA - h = 590.825 - 36.800 = 554.025 m. Gradient between A and B = (h/H)  100 = - 2.5% 20/01/2013 24
  • 25. Problem 3 Refer to Figure below; angles 1, 2,…....8 of a quadrilateral of a triangulation network were adjusted. If, DA = 213.36 m, XD = 171,719.32 m, YD = 114,056.00 m and the bearing of the line DA is equal to N 25 00 00 W. • Calculate the distances AB, BC and CD. • Calculate the bearings of the lines AB, BC and CD. • Calculate the coordinates of points A, B and C. 20/01/2013 25
  • 26. Quadrilateral Adjustment A 1 2 B 3 4 8 7 5 D 6 C 20/01/2013 26
  • 27. Quadrilateral Adjustment Angles i Adjusted values 1 38 44 08 2 23 44 33 3 42 19 08 4 44 51 57 5 69 04 22 6 39 37 47 7 26 25 54 8 75 12 11 20/01/2013 27
  • 28. Solution • Distances: Applying the law of sines by solving triangles: ABD for AB, ABC for BC, ACD for DC: AB = AD sin8/sin3 = 306.40 m BC = AB sin2/sin5 = 132.07 m CD = AD sin1/sin6 = 209.31 m 20/01/2013 28
  • 29. Solution Bearings: If you redraw the figure below, you can calculate the bearings of the lines AB, BC and CD as follows: 20/01/2013 29
  • 30. Solution Bearings: W E A S B D C 20/01/2013 30
  • 31. Solution Bearings: Brg of AB = (1 + 2) – Brg of AD = (38 44 08 + 23 44 33) - 25 00 00 = 37 28 41 The complete bearing of line AB is S37 28 41E Brg of BC = 180 00 00 - (3 + 4 + Brg of BA) = 179 59 60 - (42 19 08 + 44 51 57 +37 28 41) = 55 20 14 The complete bearing of line BC is S55 20 14W Brg of CD = (5 + 6) – Brg of CB = (69 04 22 + 39 37 47) - 55 20 14 = 53 21 55 The complete bearing of line CD is N53 21 55W 20/01/2013 31
  • 32. Coordinates: Solution XD = 171,719.32 m, YD = 114,056.00 m XA = XD + DA sin (25 00 00) = 171,809.49 m YA = YD + DA cos (25 00 00) = 114,249.37 m XB = XA + AB sin (37 28 41) = 171,995.92 m YB = YA - AB cos (37 28 41) = 114,006.22 m XC = XB - BC sin (55 20 14) = 171,887.29 m YC = YB - BC cos (55 20 14) = 113,931.10 m 20/01/2013 32
  • 33. Total Stations • Background • Main Characteristics • Applications 20/01/2013 33
  • 34. Main Characteristics • Parameter Input 1. Angle Units: degrees or gon. 2. Distance Units: ft or m. 3. Pressure Units: inches HG or mm HG. 4. Temperature Units: F or C. 5. Prism constant (- 0.03 m). 20/01/2013 34
  • 35. Main Characteristics • Parameter Input 6. Offset distance. 7. Face 1 or face 2 selection. 8. Automatic point no. incrementation. 9. Hi 10. HR 20/01/2013 35
  • 36. Main Characteristics • Parameter Input 11. Point numbers and code numbers for occupied and sighted stations. 12. Date and time settings. 20/01/2013 36
  • 37. Main Characteristics • Capabilities 1. Monitor: battery status, signal attenuation, horizontal and vertical axes status, collimation factors. 2. Compute coordinates (N, E, Z). 3. Traverse closure and adjustment, and areas. 4. Topography reductions. 5. Object heights. 6. Distances between remote points. 20/01/2013 37
  • 38. Main Characteristics • Capabilities 7. Inversing. 8. Resection. 9. Layout (Setting out). 10. Horizontal and vertical collimation corrections. 11. Vertical circle indexing. 12. Records search and review. 13. Loading external programmes. 14. Downloading and uploading. 20/01/2013 38
  • 39. Applications • Point Location New Point B d2 Reference Control Point P  A  Station 20/01/2013 39
  • 40. Applications • Point Location • Known: N, E and Z of A, N, E and Z of P/Azimuth of AP. • Measured: Angles or azimuths from the control point () and d. • Computed: N, E and Z of B and azimuth of AB and d. 20/01/2013 40