SlideShare a Scribd company logo
1 of 14
Cost Estimation Cost Budgetting Work Authorization
Cost Budgetting The output of the budgeting process is an approved project budget that is allocated to different control accounts within a distributed budget The total project budget is flowed down from the contract negotiation Management and the PM divide up this budget to create a budget structure that defines the total funding available to be spent in the program as the distributed budget. A control account structure is developed based on the work breakdown and organizational breakdown structures. The distributed budget is “rationally” allocated to the control accounts.
The Budget The budget is the amount of funding authorized to complete a “chunk” of the project scope This “chunk” may be the entire project scope in the SOW and estimate, or a subset of this – for example: customer funding may be negotiated in phases A customer may solicit a proposal for both the R&D and production costs for an innovative, risky product, but only fund the R&D portion until it is evident it will work. management may wish to control the funds “at risk” at any one time For the same project, the customer may fund both phases, but management may only release the R&D portion in order to ensure that the product developed is profitable before authorizing production.   The budget is therefore related to the original estimates provided, but not necessarily the same, and usually less.  Budget review is essential to: Understand the scope approved Highlight differences between funds authorized and funds estimated
Budget Sources and Structure The Budget is provided by company management via the Sponsor team It is authorized initially in the Project Charter, with changes introduced via the Integrated Change Control process (Changing the Plan) The budget amount authorized is usually: For customer funded activity, related to the amount agreed to within the proposal/contract negotiation, the Contract Price For internally funded activity, an amount provided by management based on the original estimates provided and available company financing In both cases, the total budget amount will be allocated for various purposes, among which is covering the costs of performing the project work This allocation creates a number of budget “baselines” that comprise the budget “structure”
Typical Budget Structure Fee & Profit Authorized/ Non-priced Work(non-negotiated) Management Reserve Undistributed Budget  Control Accounts	Planning WBS Work Packages	Planning Packages Contract Price ,[object Object]
Different “layers” of management remove the pieces of the budget “pie”       for which they are     responsible, and            measure lower layers       based on what is leftContract “Baselines” Contract Budget  Base (CBB) Negotiated  Contract Cost Performance  Measurement Baseline (PMB) Distributed  Budget
Who’s budget? Who gets measured at what baseline? Fee & Profit Authorized/ Non-priced Work(non-negotiated) Management Reserve Undistributed Budget  Control Accounts	Planning WBS Work Packages	Planning Packages Contract Price Business Management –  Corporate (“P&L”) Contract “Baselines” Contract Budget  Base (CBB) “Resource” Management -  Sponsor (“Cost Centre”) Negotiated  Contract Cost Performance  Measurement Baseline (PMB) Project Management  Control Account  Management  Distributed  Budget
The “Corporate” budget Fee & Profit Authorized/ Non-priced Work(non-negotiated) Management Reserve Undistributed Budget  Control Accounts	Planning WBS Work Packages	Planning Packages ,[object Object]
The total anticipated project cost or Contract Budget Base (CBB) is determined after negotiations by removing the profit.”
Occasionally, some details remain un-negotiated, but have some “provisional” funding allocated to   allow the project to proceed.Contract Price Contract Budget  Base (CBB) ,[object Object]
This is the Negotiated Contract Cost, and what the “organization” calls “the budget Negotiated  Contract Cost Performance  Measurement Baseline (PMB) Distributed  Budget
The “Sponsor’s” budget Fee & Profit Authorized/ Non-priced Work(non-negotiated) Management Reserve Undistributed Budget  Control Accounts	Planning WBS Work Packages	Planning Packages Contract Price ,[object Object],Contract Budget  Base (CBB) Negotiated  Contract Cost Performance  Measurement Baseline (PMB) Distributed  Budget
The “Project Manager’s” Budget Fee & Profit Authorized/ Non-priced Work(non-negotiated) Management Reserve Undistributed Budget  Control Accounts	Planning WBS Work Packages	Planning Packages Contract Price ,[object Object]
The Project Manager will decide how much of the PMB to retain as Undistributed Budget to deal with short term issues and performance variation, and how much to distribute

More Related Content

What's hot

Budget and Budgetary Control
Budget and Budgetary ControlBudget and Budgetary Control
Budget and Budgetary ControlAshish Nangla
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costsharwoodr
 
Chapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspectsChapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspectsAKSHAYA0000
 
Zero based budgeting: Zero or Hero?
Zero based budgeting: Zero or Hero?Zero based budgeting: Zero or Hero?
Zero based budgeting: Zero or Hero?Mark S. Hopkins
 
Power Point For Cmgt 410
Power Point For Cmgt 410Power Point For Cmgt 410
Power Point For Cmgt 410steffiann88
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
WBS Structure –Essential Element In Project Management
WBS Structure –Essential Element In Project ManagementWBS Structure –Essential Element In Project Management
WBS Structure –Essential Element In Project ManagementAnjali Rao
 
Myrtle 2016 zero based budgeting
Myrtle 2016 zero based budgetingMyrtle 2016 zero based budgeting
Myrtle 2016 zero based budgetingJames Fitzgerald
 
Budgets 1222199522318591-8
Budgets 1222199522318591-8Budgets 1222199522318591-8
Budgets 1222199522318591-8Mishal Sunbul
 

What's hot (20)

Budget and Budgetary Control
Budget and Budgetary ControlBudget and Budgetary Control
Budget and Budgetary Control
 
Project controls outlined
Project controls outlinedProject controls outlined
Project controls outlined
 
Project controls
Project controlsProject controls
Project controls
 
Project control
Project controlProject control
Project control
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Budgeting
BudgetingBudgeting
Budgeting
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
Chapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspectsChapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspects
 
project planning
project planningproject planning
project planning
 
Zero based budgeting: Zero or Hero?
Zero based budgeting: Zero or Hero?Zero based budgeting: Zero or Hero?
Zero based budgeting: Zero or Hero?
 
Power Point For Cmgt 410
Power Point For Cmgt 410Power Point For Cmgt 410
Power Point For Cmgt 410
 
ACH 216 Lecture 07 (Project Funding)
ACH 216 Lecture 07 (Project Funding)ACH 216 Lecture 07 (Project Funding)
ACH 216 Lecture 07 (Project Funding)
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Budgeting
BudgetingBudgeting
Budgeting
 
WBS Structure –Essential Element In Project Management
WBS Structure –Essential Element In Project ManagementWBS Structure –Essential Element In Project Management
WBS Structure –Essential Element In Project Management
 
Myrtle 2016 zero based budgeting
Myrtle 2016 zero based budgetingMyrtle 2016 zero based budgeting
Myrtle 2016 zero based budgeting
 
Project cost management
Project cost management Project cost management
Project cost management
 
Budgets 1222199522318591-8
Budgets 1222199522318591-8Budgets 1222199522318591-8
Budgets 1222199522318591-8
 

Similar to 3 pm3 c_3%20-%20the%20program%20budget

CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20planharwoodr
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.pptDejeneTsegaye6
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIMudassir Iqbal
 
Bugetory Control.pptx
Bugetory Control.pptxBugetory Control.pptx
Bugetory Control.pptxKPiano
 
Budget and budgetary control
Budget and budgetary controlBudget and budgetary control
Budget and budgetary controlUmeshJain27
 
Budget control and budget making techniques in a hospital
Budget control and budget making techniques in a hospitalBudget control and budget making techniques in a hospital
Budget control and budget making techniques in a hospitalmeghadevgan3
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxDr. ABEER KHALID MANSOUR
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Budgetary control
Budgetary controlBudgetary control
Budgetary controlVenusRana3
 
Cost Benefit Analysis- CBA
Cost Benefit Analysis- CBACost Benefit Analysis- CBA
Cost Benefit Analysis- CBASerje Ekmekjian
 
Project Budget And Accounting (BOND)
Project Budget And Accounting (BOND)Project Budget And Accounting (BOND)
Project Budget And Accounting (BOND)rexcris
 
Budget and cost controll unit 2
Budget and cost controll unit 2Budget and cost controll unit 2
Budget and cost controll unit 2Sowjanya
 
Financial & profit planning
Financial & profit planningFinancial & profit planning
Financial & profit planningAnamika Santhosh
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital BudgetingPranab Bain
 

Similar to 3 pm3 c_3%20-%20the%20program%20budget (20)

CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.ppt
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Bugetory Control.pptx
Bugetory Control.pptxBugetory Control.pptx
Bugetory Control.pptx
 
Budget and budgetary control
Budget and budgetary controlBudget and budgetary control
Budget and budgetary control
 
Budget control and budget making techniques in a hospital
Budget control and budget making techniques in a hospitalBudget control and budget making techniques in a hospital
Budget control and budget making techniques in a hospital
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Management Reserve
Management ReserveManagement Reserve
Management Reserve
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Budget
BudgetBudget
Budget
 
Budgetary control
Budgetary controlBudgetary control
Budgetary control
 
Cost Benefit Analysis- CBA
Cost Benefit Analysis- CBACost Benefit Analysis- CBA
Cost Benefit Analysis- CBA
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Budget And Accounting (BOND)
Project Budget And Accounting (BOND)Project Budget And Accounting (BOND)
Project Budget And Accounting (BOND)
 
Budget and cost controll unit 2
Budget and cost controll unit 2Budget and cost controll unit 2
Budget and cost controll unit 2
 
Financial & profit planning
Financial & profit planningFinancial & profit planning
Financial & profit planning
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 

More from harwoodr

3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structureharwoodr
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20networkharwoodr
 
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20worksharwoodr
 
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20scheduleharwoodr
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20developmentharwoodr
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimatingharwoodr
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencingharwoodr
 
3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorizationharwoodr
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budgetharwoodr
 

More from harwoodr (11)

3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network
 
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
 
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing
 
3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
PHP games
PHP gamesPHP games
PHP games
 

Recently uploaded

Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 

Recently uploaded (20)

Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 

3 pm3 c_3%20-%20the%20program%20budget

  • 1. Cost Estimation Cost Budgetting Work Authorization
  • 2. Cost Budgetting The output of the budgeting process is an approved project budget that is allocated to different control accounts within a distributed budget The total project budget is flowed down from the contract negotiation Management and the PM divide up this budget to create a budget structure that defines the total funding available to be spent in the program as the distributed budget. A control account structure is developed based on the work breakdown and organizational breakdown structures. The distributed budget is “rationally” allocated to the control accounts.
  • 3. The Budget The budget is the amount of funding authorized to complete a “chunk” of the project scope This “chunk” may be the entire project scope in the SOW and estimate, or a subset of this – for example: customer funding may be negotiated in phases A customer may solicit a proposal for both the R&D and production costs for an innovative, risky product, but only fund the R&D portion until it is evident it will work. management may wish to control the funds “at risk” at any one time For the same project, the customer may fund both phases, but management may only release the R&D portion in order to ensure that the product developed is profitable before authorizing production. The budget is therefore related to the original estimates provided, but not necessarily the same, and usually less. Budget review is essential to: Understand the scope approved Highlight differences between funds authorized and funds estimated
  • 4. Budget Sources and Structure The Budget is provided by company management via the Sponsor team It is authorized initially in the Project Charter, with changes introduced via the Integrated Change Control process (Changing the Plan) The budget amount authorized is usually: For customer funded activity, related to the amount agreed to within the proposal/contract negotiation, the Contract Price For internally funded activity, an amount provided by management based on the original estimates provided and available company financing In both cases, the total budget amount will be allocated for various purposes, among which is covering the costs of performing the project work This allocation creates a number of budget “baselines” that comprise the budget “structure”
  • 5.
  • 6. Different “layers” of management remove the pieces of the budget “pie” for which they are responsible, and measure lower layers based on what is leftContract “Baselines” Contract Budget Base (CBB) Negotiated Contract Cost Performance Measurement Baseline (PMB) Distributed Budget
  • 7. Who’s budget? Who gets measured at what baseline? Fee & Profit Authorized/ Non-priced Work(non-negotiated) Management Reserve Undistributed Budget Control Accounts Planning WBS Work Packages Planning Packages Contract Price Business Management – Corporate (“P&L”) Contract “Baselines” Contract Budget Base (CBB) “Resource” Management - Sponsor (“Cost Centre”) Negotiated Contract Cost Performance Measurement Baseline (PMB) Project Management Control Account Management Distributed Budget
  • 8.
  • 9. The total anticipated project cost or Contract Budget Base (CBB) is determined after negotiations by removing the profit.”
  • 10.
  • 11. This is the Negotiated Contract Cost, and what the “organization” calls “the budget Negotiated Contract Cost Performance Measurement Baseline (PMB) Distributed Budget
  • 12.
  • 13.
  • 14. The Project Manager will decide how much of the PMB to retain as Undistributed Budget to deal with short term issues and performance variation, and how much to distribute
  • 15. Of the distributed amount, some will be distributed to the team to perform work against Work Packages, and some will be allocated to future work that is not yet authorized, but is kept in Planning PackagesContract Budget Base (CBB) Negotiated Contract Cost Performance Measurement Baseline (PMB) Distributed Budget
  • 16.
  • 17. Undistributed budget is to mitigate “Known Unknowns”
  • 18.
  • 19. to Control Accounts for the near term execution of Work Packages
  • 20. Planning Packages for purposes of long term planning and resource forecasting
  • 21. At the Control Accounts, control over the budget passes to the Control Account Managers (CAMs)Contract Budget Base (CBB) Negotiated Contract Cost Performance Measurement Baseline (PMB) Distributed Budget
  • 22. Work vs. Planning Packages Control Account No. 1 Control Account No. 6 Work Packages Planning Package Control Account No. 2 Control Account No. 8 Work Packages Planning Package Planning Package Control Account No. 3 Control Account No. 5 Work Packages Planning Package Time Now Time 6 Months
  • 23.
  • 25. Establish who controls budgets at each level
  • 26.