Best Practices on Contract Design in
          PPPs: Checklist
         Report prepared for the World Bank




                        BY

                 Elisabetta Iossa
               Giancarlo Spagnolo
                 Mercedes Vellez




                  FIRST DRAFT
                  September, 2007
Contents

                      I.      Transparency
                      II.     Risk allocation
                      III.    Payment mechanism
                      IV.     Price variations
                      V.      Flexibility and Renegotiation
                      VI.     Contract duration
                      VII.    Other contractual issues
                      VIII.   Subcontracting




Best Practices on Contract Design: CHECKLIST

The following checklist takes stock of a number of issues that should be addressed in assessing the
contract design of Public-Private Partnerships for infrastructure projects, with particular emphasis to
Governance issues. Its structure and content are based on the accompanying best practices on
contract design in order to minimize the likelihood of poor performance of a PPP, but the order is
slightly modified to focus them on governance issues. Questions in bold are particularly important
for the Governance of PPPs, and should therefore have higher weight in the evaluation.
I. TRANSPARENCY                                                                                       Yes/No   Comments
 1. Are the final contract and all other documents publicly disclosed in a proactive way?
 2. If part of the contractual documentation is not disclosed, did it pass a tight test that
 evaluates that it is truly ‘commercially sensitive’ information, or that there is a public
 interest in keeping it confidential, against the presumption that they are not?
 3. Are output specifications, performance targets, and payment mechanism (including
 deductions or fines for low performance) put in the public domain?
 4. Does the contract require to proactively disclose measurements contractor performance
 along the development of the project, and payment changes connected to the measured
 performance?
 5. Does the contract require to proactively disclose motivation and cost assessment of any
 change in output or in other terms of the contract before approval?
 6. Does the contract require to proactively disclose methodology and results of all
 benchmarking and market testing exercises the contract requires?
 7. Is the above information disclosed in an electronic form in the main page of the project?
 8. Is the above information disclosed within a pre-determined and short time from its
 emergence?
 9. Are the disclosure requirements compulsory?
 10. Does the contract itself specify such disclosure rules?
II. RISK ALLOCATION                                                                                   Yes/No   Comments
 11. Have the main risks of the project been identified?
 12. Does the contract transfer risks to the private-sector party that it can control?
 13. Does the public-sector party bear risks that the private-sector cannot control?
 14. Are the risks properly allocated in order to give appropriate incentives to the private-sector
 party?
III. PAYMENT MECHANISM                                                                                Yes/No   Comments
 15. Are the required service standards based on output specifications?
 16. Are all these service standards easily monitorable and verifiable?
17. If not, are other objective measures of performance specified?
18. Are customer satisfaction surveys used to monitor performance of the private-sector party?
19. If yes, are customer satisfaction surveys carried out by an independent third party?
20. Does the contract exhibit a consistent link between output specifications, risk allocation and
incentives, and the payment mechanism?
21. Is the payment mechanism consistent with the allocation of risks between the public and
private parties, and hence with the incentives given to the private-sector party?
22. Is the payment due to the private-sector party conditional on service provision?
23. Does the contract specify a service commencement day after which the first payment is
made?
24. Does the public-sector party impose sufficient contractual protections from delays in
service commencement, like robust deductions and liquidated damages?
25. If the payment mechanism is based on user charges, does the tariff level ensure the bankability
of the project?
26. Does the level of tariff discourage demand, particularity if there is an alternative free-available
service?
27. Are there provisions to combine user charges with any form of subvention from the
public-sector party?
28. Do these subventions depend on the private-sector performance, like subventions based
on the number of users?
29. Is the private-sector party allowed to collect secondary revenues, like advertisement, food
services, etc.?
30. If the revenues collected by the private-sector party turn out to be higher than expected, are
there mechanisms to limit the private sector profits, like sharing surplus revenues?
31. If the payment mechanism is based on usage, is the definition of service usage measurable and
observable, like traffic volumes?
32. Is the usage payment capped for high levels of usage?
33. Does the payment mechanism include bonuses or deductions according to availability of the
service and/or performance targets?
34. Do deductions vary according to the severity of the availability/performance failure?
 35. Does the contract include clear rectification periods providing the private-sector party with
 clear deadlines within which to rectify the failures to avoid additional and increasing deductions?
 36. Do deduction payments use a ratchet mechanism where deductions increase with the duration
 and frequency of the failure?
IV. PRICE VARIATIONS                                                                                   Yes/No   Comments
 37. Does the contract include provisions allowing tariffs or usage payments to vary according to
 the evolution of costs that are independent of contractor’s performance?
 38. Does the contract include indexation clauses?
 39. Does the contract specify the price index to be applied?
 40. Does indexation apply to the proportion of tariffs or usage payments that matches the
 proportion of the private-sector party variable costs in total costs?
 41. Does the contract specify the frequency of tariffs or usage payments indexation?
 42. Does the contract require and detail market testing or benchmarking procedures?
 43. Is the market competitive enough to apply market testing procedures?
 44. Does the contract specify the frequency of the market testing or benchmarking
 procedures?
V. FLEXIBILITY AND RENEGOTIATION                                                                       Yes/No   Comments
 45. Are all anticipated (foreseen) changes in service provision pre-specified in the contract,
 so they can be part of the initial bid?
 46. Does the contract include provisions allowing the public-sector party to require other likely
 small changes that cannot be pre-specified exactly and therefore cannot be priced at the
 competitive tendering stage?
 47. If yes, does the contract pre-specify exactly how compensation to the private-sector party for
 the extra costs arising from these required small changes should be calculated?
 48. In particular, is any cost reimbursement compensation backed by benchmarking or
 market testing procedures before changes are approved and implemented?
49. Is there a third party (e.g. panel of experts) involved in approving the cost
 reimbursement before changes are implemented?
 50. For completely unanticipated large change needs, does the contract precisely specify a
 transparent change protocol through which proposed changes are requested, assessed,
 approved, and implemented?
 51. Are independent third parties involved in such a change protocol and in particular at the
 approval stage?
 52. Does the change protocol require and detail benchmarking or market testing procedures
 before these larger unanticipated changes are approved and implemented?
 53. Does the contract specify a freeze period at the beginning of the contract life within
 which no change can be requested by any party?
 54. Is this freeze period proportional to the construction phase period of the project?
 55. Is this freeze period longer for contract changes required by the private-sector party
 than for those required by the public-sector party?
 56. Does the contract specify fees to accompany the private-sector demand for contract
 changes to be withheld by the public-sector party if the change requested is rejected?
VI. CONTRACT DURATION                                                                                   Yes/No   Comments
 57. Does the contract specify its duration?
 58. Do the contract length and the payment profile ensure the bankability of the project?
 59. Does contract duration encourage non-contractible investments?
 60. Does contract duration include review periods (recurrent possibilities to stop or renew the
 contract to the incumbent contractor) to be used as an in-kind reward for the private-sector party’s
 good performance?
 61. Are contract renewals contractually conditioned on reaching pre-specified target levels of
 performance?
 62. Does contract duration allow the private-sector party to exploit economies of scale?
 63. If the project involves the provision of soft and hard services by the private-sector party, do
 these services have different contract duration (shorter the former, much longer the latter)?
VII. OTHER CONTRACTUAL ISSUES                                                                          Yes/No   Comments
 64. Does the contract include a dispute resolution mechanism?
 65. If yes, does the procedure involve different stages for resolving disputes?
 66. Does the dispute resolution mechanism envisage appointing of PPP experts or arbiter among
 distinguished professionals?
 67. Are there strict deadlines specified for the PPP experts/arbiter to make decisions and reach
 resolution?
 68. Are the decisions made by experts/arbiter enforceable?
 69. Does the contract include provisions allowing the public-sector party to step-in?
 70. Doest the contract specify the circumstances under which the public-sector party is entitled to
 step-in?
 71. Does the contract specify who should bear the costs arising from the public sector’s step-in
 actions?
 72. Does the contract include provisions allowing the lenders of the project to step-in?
 73. Doest the contract specify the circumstances under which the lenders are entitled to step-in?
 74. Does the contract include early termination clauses?
 75. Does the contract specify the circumstances under which the private-sector party has the right
 to terminate the contract before the contract expires because of a public-sector party default?
 76. Does the contract specify the circumstances under which the public-sector party has the right
 to terminate the contract before the contract expires because of a private-sector party default?
 77. Does the contract specify the circumstances under which the public-sector party has the right
 to voluntarily terminate the contract?
 78. Does the contract specify the compensation payable to the private-sector party in the above
 cases?
 79. Does the contract include provisions for early contract termination because of force majeure
 events?
 80. Does the contract specify these force majeure events?
 81. Does the contract consider corrupt gifts and fraud as causes for early contract termination?
VIII. SUBCONTRACTING                                                                                   Yes/No   Comments
 82. Does the contract impose any restriction on subcontractors in order to avoid conflicts of
 interest?
 83. Does the contract entitle the public-sector party to approve the replacement of subcontractors?
 84. Does the contract impose liquidated damages on non-performing subcontractors?
 85. Does the contract specify that the employment of subcontractors will terminate whenever the
 contractual relationship between the public and private parties terminate?

Más contenido relacionado

Similar a Best practices checklist copy

OECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEY
OECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEYOECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEY
OECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEYOECD Governance
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure developmentsakariya88
 
Construction Contract Review Checklist
Construction Contract Review ChecklistConstruction Contract Review Checklist
Construction Contract Review ChecklistSarah Fox
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsAM Publications
 
Learn Past Exp
Learn Past ExpLearn Past Exp
Learn Past Expeuwebsc01
 
Learn Past Exp
Learn Past ExpLearn Past Exp
Learn Past Expeuwebtc01
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsIRJET Journal
 
NEC4 Toolkit presentation for contractss
NEC4 Toolkit presentation for contractssNEC4 Toolkit presentation for contractss
NEC4 Toolkit presentation for contractssSheila282031
 
Action For Client,Contractors ...
Action For Client,Contractors ...Action For Client,Contractors ...
Action For Client,Contractors ...ali nematollah
 
Action For Client,Ontractors ...
Action For Client,Ontractors ...Action For Client,Ontractors ...
Action For Client,Ontractors ...caspian refinery
 
AVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAM Publications
 
Ppp Guide 2008
Ppp Guide 2008Ppp Guide 2008
Ppp Guide 2008euweben01
 
Ppp Guide 2008
Ppp Guide 2008Ppp Guide 2008
Ppp Guide 2008euwebsc01
 
Ppp Guide 2008
Ppp Guide 2008Ppp Guide 2008
Ppp Guide 2008euwebtc01
 
2d Acli Paper Presentation 12 2010 V2
2d Acli Paper Presentation 12 2010 V22d Acli Paper Presentation 12 2010 V2
2d Acli Paper Presentation 12 2010 V2Doug Barnert
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSProf Handley Mpoki Mafwenga
 

Similar a Best practices checklist copy (20)

OECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEY
OECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEYOECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEY
OECD, 7th Meeting on Public-Private Partnerships - Peter LIVESEY
 
Pgpm14 infrastructure development
Pgpm14 infrastructure developmentPgpm14 infrastructure development
Pgpm14 infrastructure development
 
Construction Contract Review Checklist
Construction Contract Review ChecklistConstruction Contract Review Checklist
Construction Contract Review Checklist
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
 
Learn Past Exp
Learn Past ExpLearn Past Exp
Learn Past Exp
 
Learn Past Exp
Learn Past ExpLearn Past Exp
Learn Past Exp
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
 
NEC4 Toolkit presentation for contractss
NEC4 Toolkit presentation for contractssNEC4 Toolkit presentation for contractss
NEC4 Toolkit presentation for contractss
 
Action For Client,Contractors ...
Action For Client,Contractors ...Action For Client,Contractors ...
Action For Client,Contractors ...
 
Action For Client,Ontractors ...
Action For Client,Ontractors ...Action For Client,Ontractors ...
Action For Client,Ontractors ...
 
AVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTE
 
Ppp Guide 2008
Ppp Guide 2008Ppp Guide 2008
Ppp Guide 2008
 
Ppp Guide 2008
Ppp Guide 2008Ppp Guide 2008
Ppp Guide 2008
 
Ppp Guide 2008
Ppp Guide 2008Ppp Guide 2008
Ppp Guide 2008
 
2d Acli Paper Presentation 12 2010 V2
2d Acli Paper Presentation 12 2010 V22d Acli Paper Presentation 12 2010 V2
2d Acli Paper Presentation 12 2010 V2
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Audit of contracts version 2
Audit of contracts version 2Audit of contracts version 2
Audit of contracts version 2
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 

Más de Confidential

Wisdom for-managers
Wisdom for-managersWisdom for-managers
Wisdom for-managersConfidential
 
Hossam hussein revised final draft 3
Hossam hussein revised final draft 3Hossam hussein revised final draft 3
Hossam hussein revised final draft 3Confidential
 
I095456 acceptance certificate (1)
I095456 acceptance certificate (1)I095456 acceptance certificate (1)
I095456 acceptance certificate (1)Confidential
 
I095456 acceptance certificate
I095456 acceptance certificate I095456 acceptance certificate
I095456 acceptance certificate Confidential
 
Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Confidential
 
Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Confidential
 
Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Confidential
 
Recession reformation
Recession reformationRecession reformation
Recession reformationConfidential
 
101 powerfulwaystousethelawofattraction (1)
101 powerfulwaystousethelawofattraction (1)101 powerfulwaystousethelawofattraction (1)
101 powerfulwaystousethelawofattraction (1)Confidential
 
4 leadership messages your talent needs to hear forbes
4 leadership messages your talent needs to hear   forbes4 leadership messages your talent needs to hear   forbes
4 leadership messages your talent needs to hear forbesConfidential
 
Job interview mistakes 2
Job interview mistakes  2Job interview mistakes  2
Job interview mistakes 2Confidential
 
Job interview mistakes 1
Job interview mistakes 1Job interview mistakes 1
Job interview mistakes 1Confidential
 
Wisdom for-managers
Wisdom for-managersWisdom for-managers
Wisdom for-managersConfidential
 
Finding jobs through craigslist
Finding jobs through craigslistFinding jobs through craigslist
Finding jobs through craigslistConfidential
 
Acquire power through self development
Acquire power through self developmentAcquire power through self development
Acquire power through self developmentConfidential
 
25 simple-strategies-to-boost-your-creativity (1)
25 simple-strategies-to-boost-your-creativity (1)25 simple-strategies-to-boost-your-creativity (1)
25 simple-strategies-to-boost-your-creativity (1)Confidential
 
Start a local produce business
Start a local produce businessStart a local produce business
Start a local produce businessConfidential
 
How to start a green housecleaning business
How to start a green housecleaning businessHow to start a green housecleaning business
How to start a green housecleaning businessConfidential
 

Más de Confidential (20)

Wisdom for-managers
Wisdom for-managersWisdom for-managers
Wisdom for-managers
 
Hossam hussein revised final draft 3
Hossam hussein revised final draft 3Hossam hussein revised final draft 3
Hossam hussein revised final draft 3
 
I095456 acceptance certificate (1)
I095456 acceptance certificate (1)I095456 acceptance certificate (1)
I095456 acceptance certificate (1)
 
I095456 acceptance certificate
I095456 acceptance certificate I095456 acceptance certificate
I095456 acceptance certificate
 
Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)
 
Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)
 
Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)Certified NLP Practitioner ( UAE)
Certified NLP Practitioner ( UAE)
 
Recession reformation
Recession reformationRecession reformation
Recession reformation
 
101 powerfulwaystousethelawofattraction (1)
101 powerfulwaystousethelawofattraction (1)101 powerfulwaystousethelawofattraction (1)
101 powerfulwaystousethelawofattraction (1)
 
4 leadership messages your talent needs to hear forbes
4 leadership messages your talent needs to hear   forbes4 leadership messages your talent needs to hear   forbes
4 leadership messages your talent needs to hear forbes
 
Job interview mistakes 2
Job interview mistakes  2Job interview mistakes  2
Job interview mistakes 2
 
Job interview mistakes 1
Job interview mistakes 1Job interview mistakes 1
Job interview mistakes 1
 
Achieving self
Achieving selfAchieving self
Achieving self
 
Skills summary
Skills summarySkills summary
Skills summary
 
Wisdom for-managers
Wisdom for-managersWisdom for-managers
Wisdom for-managers
 
Finding jobs through craigslist
Finding jobs through craigslistFinding jobs through craigslist
Finding jobs through craigslist
 
Acquire power through self development
Acquire power through self developmentAcquire power through self development
Acquire power through self development
 
25 simple-strategies-to-boost-your-creativity (1)
25 simple-strategies-to-boost-your-creativity (1)25 simple-strategies-to-boost-your-creativity (1)
25 simple-strategies-to-boost-your-creativity (1)
 
Start a local produce business
Start a local produce businessStart a local produce business
Start a local produce business
 
How to start a green housecleaning business
How to start a green housecleaning businessHow to start a green housecleaning business
How to start a green housecleaning business
 

Best practices checklist copy

  • 1. Best Practices on Contract Design in PPPs: Checklist Report prepared for the World Bank BY Elisabetta Iossa Giancarlo Spagnolo Mercedes Vellez FIRST DRAFT September, 2007
  • 2. Contents I. Transparency II. Risk allocation III. Payment mechanism IV. Price variations V. Flexibility and Renegotiation VI. Contract duration VII. Other contractual issues VIII. Subcontracting Best Practices on Contract Design: CHECKLIST The following checklist takes stock of a number of issues that should be addressed in assessing the contract design of Public-Private Partnerships for infrastructure projects, with particular emphasis to Governance issues. Its structure and content are based on the accompanying best practices on contract design in order to minimize the likelihood of poor performance of a PPP, but the order is slightly modified to focus them on governance issues. Questions in bold are particularly important for the Governance of PPPs, and should therefore have higher weight in the evaluation.
  • 3. I. TRANSPARENCY Yes/No Comments 1. Are the final contract and all other documents publicly disclosed in a proactive way? 2. If part of the contractual documentation is not disclosed, did it pass a tight test that evaluates that it is truly ‘commercially sensitive’ information, or that there is a public interest in keeping it confidential, against the presumption that they are not? 3. Are output specifications, performance targets, and payment mechanism (including deductions or fines for low performance) put in the public domain? 4. Does the contract require to proactively disclose measurements contractor performance along the development of the project, and payment changes connected to the measured performance? 5. Does the contract require to proactively disclose motivation and cost assessment of any change in output or in other terms of the contract before approval? 6. Does the contract require to proactively disclose methodology and results of all benchmarking and market testing exercises the contract requires? 7. Is the above information disclosed in an electronic form in the main page of the project? 8. Is the above information disclosed within a pre-determined and short time from its emergence? 9. Are the disclosure requirements compulsory? 10. Does the contract itself specify such disclosure rules? II. RISK ALLOCATION Yes/No Comments 11. Have the main risks of the project been identified? 12. Does the contract transfer risks to the private-sector party that it can control? 13. Does the public-sector party bear risks that the private-sector cannot control? 14. Are the risks properly allocated in order to give appropriate incentives to the private-sector party? III. PAYMENT MECHANISM Yes/No Comments 15. Are the required service standards based on output specifications? 16. Are all these service standards easily monitorable and verifiable?
  • 4. 17. If not, are other objective measures of performance specified? 18. Are customer satisfaction surveys used to monitor performance of the private-sector party? 19. If yes, are customer satisfaction surveys carried out by an independent third party? 20. Does the contract exhibit a consistent link between output specifications, risk allocation and incentives, and the payment mechanism? 21. Is the payment mechanism consistent with the allocation of risks between the public and private parties, and hence with the incentives given to the private-sector party? 22. Is the payment due to the private-sector party conditional on service provision? 23. Does the contract specify a service commencement day after which the first payment is made? 24. Does the public-sector party impose sufficient contractual protections from delays in service commencement, like robust deductions and liquidated damages? 25. If the payment mechanism is based on user charges, does the tariff level ensure the bankability of the project? 26. Does the level of tariff discourage demand, particularity if there is an alternative free-available service? 27. Are there provisions to combine user charges with any form of subvention from the public-sector party? 28. Do these subventions depend on the private-sector performance, like subventions based on the number of users? 29. Is the private-sector party allowed to collect secondary revenues, like advertisement, food services, etc.? 30. If the revenues collected by the private-sector party turn out to be higher than expected, are there mechanisms to limit the private sector profits, like sharing surplus revenues? 31. If the payment mechanism is based on usage, is the definition of service usage measurable and observable, like traffic volumes? 32. Is the usage payment capped for high levels of usage? 33. Does the payment mechanism include bonuses or deductions according to availability of the service and/or performance targets?
  • 5. 34. Do deductions vary according to the severity of the availability/performance failure? 35. Does the contract include clear rectification periods providing the private-sector party with clear deadlines within which to rectify the failures to avoid additional and increasing deductions? 36. Do deduction payments use a ratchet mechanism where deductions increase with the duration and frequency of the failure? IV. PRICE VARIATIONS Yes/No Comments 37. Does the contract include provisions allowing tariffs or usage payments to vary according to the evolution of costs that are independent of contractor’s performance? 38. Does the contract include indexation clauses? 39. Does the contract specify the price index to be applied? 40. Does indexation apply to the proportion of tariffs or usage payments that matches the proportion of the private-sector party variable costs in total costs? 41. Does the contract specify the frequency of tariffs or usage payments indexation? 42. Does the contract require and detail market testing or benchmarking procedures? 43. Is the market competitive enough to apply market testing procedures? 44. Does the contract specify the frequency of the market testing or benchmarking procedures? V. FLEXIBILITY AND RENEGOTIATION Yes/No Comments 45. Are all anticipated (foreseen) changes in service provision pre-specified in the contract, so they can be part of the initial bid? 46. Does the contract include provisions allowing the public-sector party to require other likely small changes that cannot be pre-specified exactly and therefore cannot be priced at the competitive tendering stage? 47. If yes, does the contract pre-specify exactly how compensation to the private-sector party for the extra costs arising from these required small changes should be calculated? 48. In particular, is any cost reimbursement compensation backed by benchmarking or market testing procedures before changes are approved and implemented?
  • 6. 49. Is there a third party (e.g. panel of experts) involved in approving the cost reimbursement before changes are implemented? 50. For completely unanticipated large change needs, does the contract precisely specify a transparent change protocol through which proposed changes are requested, assessed, approved, and implemented? 51. Are independent third parties involved in such a change protocol and in particular at the approval stage? 52. Does the change protocol require and detail benchmarking or market testing procedures before these larger unanticipated changes are approved and implemented? 53. Does the contract specify a freeze period at the beginning of the contract life within which no change can be requested by any party? 54. Is this freeze period proportional to the construction phase period of the project? 55. Is this freeze period longer for contract changes required by the private-sector party than for those required by the public-sector party? 56. Does the contract specify fees to accompany the private-sector demand for contract changes to be withheld by the public-sector party if the change requested is rejected? VI. CONTRACT DURATION Yes/No Comments 57. Does the contract specify its duration? 58. Do the contract length and the payment profile ensure the bankability of the project? 59. Does contract duration encourage non-contractible investments? 60. Does contract duration include review periods (recurrent possibilities to stop or renew the contract to the incumbent contractor) to be used as an in-kind reward for the private-sector party’s good performance? 61. Are contract renewals contractually conditioned on reaching pre-specified target levels of performance? 62. Does contract duration allow the private-sector party to exploit economies of scale? 63. If the project involves the provision of soft and hard services by the private-sector party, do these services have different contract duration (shorter the former, much longer the latter)?
  • 7. VII. OTHER CONTRACTUAL ISSUES Yes/No Comments 64. Does the contract include a dispute resolution mechanism? 65. If yes, does the procedure involve different stages for resolving disputes? 66. Does the dispute resolution mechanism envisage appointing of PPP experts or arbiter among distinguished professionals? 67. Are there strict deadlines specified for the PPP experts/arbiter to make decisions and reach resolution? 68. Are the decisions made by experts/arbiter enforceable? 69. Does the contract include provisions allowing the public-sector party to step-in? 70. Doest the contract specify the circumstances under which the public-sector party is entitled to step-in? 71. Does the contract specify who should bear the costs arising from the public sector’s step-in actions? 72. Does the contract include provisions allowing the lenders of the project to step-in? 73. Doest the contract specify the circumstances under which the lenders are entitled to step-in? 74. Does the contract include early termination clauses? 75. Does the contract specify the circumstances under which the private-sector party has the right to terminate the contract before the contract expires because of a public-sector party default? 76. Does the contract specify the circumstances under which the public-sector party has the right to terminate the contract before the contract expires because of a private-sector party default? 77. Does the contract specify the circumstances under which the public-sector party has the right to voluntarily terminate the contract? 78. Does the contract specify the compensation payable to the private-sector party in the above cases? 79. Does the contract include provisions for early contract termination because of force majeure events? 80. Does the contract specify these force majeure events? 81. Does the contract consider corrupt gifts and fraud as causes for early contract termination?
  • 8. VIII. SUBCONTRACTING Yes/No Comments 82. Does the contract impose any restriction on subcontractors in order to avoid conflicts of interest? 83. Does the contract entitle the public-sector party to approve the replacement of subcontractors? 84. Does the contract impose liquidated damages on non-performing subcontractors? 85. Does the contract specify that the employment of subcontractors will terminate whenever the contractual relationship between the public and private parties terminate?