Sathish Bakanagari et al Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086

RESEARCH ARTICLE

www.ijera.com

OPEN ACCESS

Three Phase Fault Analysis with Auto Reset for Temporary Fault
and Trip for Permanent Fault
Sathish Bakanagari1, A. Mahesh Kumar2, M. Cheenya3
12

(Asst.prof in EEE Department) 3(Asst.Prof in ECE Department)
Mahaveer Institute of Science and Technology, bandlaguda, Hyderabad.A.P.

Abstract
This paper to develop an automatic tripping mechanism for the three phase supply system. The project output
resets automatically after a brief interruption in the event temporary fault while it remains in tripped condition in
case of permanent fault. The electrical substation which supply the power to the consumers, have failures due to
some faults which can be temporary or permanent. These faults lead to substantial damage to the power system
equipment. In India it is common, The faults might be LG (Line to Ground), LL (Line to Line), 3L (Three lines)
in the supply systems and these faults in three phase supply system can affect the power system. To overcome
this problem a system is built, which can sense these faults and automatically disconnects the supply to avoid
large scale damage to the control gears in the grid sub-stations. This system is built using three single phase
transformers which are wired in star input and star output, and 3 transformers are connected in delta
connections, having input 220 volt and output at 12 volt. This concept low voltage testing of fault conditions is
followed as it is not advisable to create on mains line. 555 timers are used for handling short duration and long
duration fault conditions. A set of switches are used to create the LL, LG and 3L fault in low voltage side, for
activating the tripping mechanism. Short duration fault returns the supply to the load immediately called as
temporary trip while long duration shall result in permanent trip. The concept in the future can be extended to
developing a mechanism to send message to the authorities via SMS by interfacing a GSM modem.
Keywords—555 Timer, Voltage regulator (LM7805), Relays, Comparator, Transformer (230 V– 12V AC)
I. Introduction
Various studies have shown that anywhere
from 70%, to as high as 90%, of faults on most
overhead lines are transient. A transient fault, such as
an insulator flashover, is a fault which is cleared by
the immediate tripping of one or more circuit breakers
to isolate the fault, and which does not recur when the
line is re-energized. Faults tend to be less transient
(near the 80% range) at lower, distribution voltages
and more transient (near the90% range) at higher, sub
transmission and transmission voltages.
Lightning is the most common cause of transient
faults, partially resulting from insulator flashover
from the high transient voltages induced by the
lightning. Other possible causes are swinging wires
and temporary contact with foreign objects. Thus,
transient faults can be cleared by momentarily deenergizing the line, in order to allow the fault to
clear.Autoreclosing can then restore service to the
line.
The remaining 10 - 30% of faults are semipermanent or permanent in nature. A small branch
falling onto the line can cause a semi-permanent fault.
In this case, however, an immediate de-energizing of
the line and subsequent auto reclosing does not clear
the fault. Instead, a coordinated time-delayed trip
would allow the branch to be burned away without
damage to the system. Semi-permanent faults of this
type are likely to be most prevalent in highly wooded
www.ijera.com

areas and can be substantially controlled by
aggressive line clearance programs.
Permanent faults are those that will not clear
upon tripping and reclosing. An example of a
permanent fault on an overhead line is a broken wire
causing a phase to open, or a broken pole causing the
phases to short together. Faults on underground
cables should be considered permanent. Cable faults
should be cleared without auto reclosing and the
damaged cable repaired before service is restored.
There may be exceptions to this, as in the case of
circuits composed of both underground cables and
overhead lines.
Although auto reclosing success rates vary
from one company to another, it is clear that the
majority of faults can be successfully cleared by the
proper use of tripping and auto reclosing. This deenergizes the line long enough for the fault source to
pass and the fault arc to de-energize, then
automatically recloses the line to restore service.
Thus, autoreclosing can significantly reduce the
outage time due to faults and provide a higher level of
service continuity to the customer. Furthermore,
successful high-speed reclosing auto reclosing. on
transmission circuits can be a major factor when
attempting to maintain system stability. For those
faults that are permanent, auto reclosing will reclose
the circuit into a fault that has not been cleared, which

1082 | P a g e
Sathish Bakanagari et al Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086

www.ijera.com

may have adverse affects on system stability
(particularly at transmission levels).

II. VOLTAGE REGULATOR

III. SCHEMATIC DIAGRAM

The LM78XX/LM78XXA series of threeterminal positive regulators are available in the TO220/D-PAK package and with several fixed output
voltages, making them useful in a Wide range of
applications. Each type employs internal current
limiting, thermal shutdown and safe operating area
protection, making it essentially indestructible. If
adequate heat sinking is provided, they can deliver
over 1A output Current. Although designed primarily
as fixed voltage regulators, these devices can be used
Fig2 (a) Block diagram

with external components to obtain adjustable
voltages and currents.
Fig1 (a) Block diagram of voltage regulator

Fig1 (b) Absolute Maximum Ratings
It has some features:
• Output Current up to 1A.
• Output Voltages of 5, 6, 8, 9, 10, 12, 15, 18, 24V.
• Thermal Overload Protection.
• Short Circuit Protection.
• Output Transistor Safe Operating Area Protection.

www.ijera.com

Fig2 (b) Proposed schematic diagram
Working principle:
The project uses 6numbers step-down
transformers for handling the entire circuit under low
voltage conditions of 12v only to test the 3 phase fault
analysis. The primaries of 3 transformers are
connected to a 3 phase supply in star configuration,
while the secondary of the same is also connected in
star configuration. The other set of 3 transformers
with its primary connected in star to 3 phase have
their secondary’s connected in delta configuration.
The outputs of all the 6 transformers are rectified and
filtered individually and are given to 6 relay coils. 6
push buttons, one each connected across the relay coil
is meant to create a fault condition either at star i.e.
LL Fault or 3L Fault. The NC contacts of all the
relays are made parallel while all the common points
are grounded. The parallel connected point of NC are
given to pin2 through a resistor R5 to a 555 timer i.e.
wired in monostable mode. The output of the same
timer is connected to the reset pin 4 of another 555
timer wired in astable mode. LED’S are connected at
their output to indicate their status. The output of the
U3 555 timer from pin3 is given to an Op-amp
LM358 through wire 11 and d12 to the non inverting
input pin3, while the inverting input is kept at a fixed
voltage by a potential divider RV2. The voltage at
pin2 coming from the potential divider is so held that
it is higher than the pin3 of the Op-amp used as a
comparator so that pin1 develops zero logic that fails
to operate the relay through the driver transistor Q1.
1083 | P a g e
Sathish Bakanagari et al Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086
This relay Q1 is ‘3CO’ relay i.e. is meant for
disconnecting the load to indicate fault conditions.
Operating procedure:
While the board is powered from a 3phase
supply all the 6 relay coils get DC voltage and their
common point disconnects from the NC and moves
on to the NO points there by providing logic high at
pin2 of 555 timer U1 i.e. that is kept on monostable
mode. While any push button across the relay is
pressed it disconnects that relay and in the process in
common contacts moves to the NC position to
provide a logic low at trigger pin of 555 timer to
develop an output that brings the U3 555 timer which
is used in astable mode for its reset pin to high such
that the astable operation takes place at its output
which is also indicated by flashing D11 LED.
If the fault is off temporary in nature i.e. if
the push button pressed is released immediately the
U1 monostable disables U3 the output of which goes
to zero in the event of any push button kept pressed
for a longer duration the monostable output provides
a longer duration active situation for U3 the astable
timer the output of which charges capacitor C13
through R11 such that the output of the comparator
goes high that drives the relay to switch off three
phase load.
The output of Op-amp remains high
indefinitely through a positive feedback provided for
its pin1 to pin3 through a forward biased diode and a
resistor in series. This results in the relay permanently
switched on to disconnect the load connected at its
NC contacts permanently off. In order to maintain the
flow of DC supply the star connected secondary set
DC’S are paralleled through D8, D9 & D10 for
uninterrupted supply to the circuit voltage of 12v DC
and 5v DC derived out of voltage regulator IC 7805.

IV. HARDWARE TESTING
1. Conductivity Test:
In electronics, a continuity test is the
checking of an electric circuit to see if current flows
(that it is in fact a complete circuit). A continuity test
is performed by placing a small voltage (wired in
series with an LED or noise-producing component
such as a piezoelectric speaker) across the chosen
path. If electron flow is inhibited by broken
conductors, damaged components, or excessive
resistance, the circuit is "open".
Devices that can be used to perform
continuity tests include multi meters which measure
current and specialized continuity testers which are
cheaper, more basic devices, generally with a simple
light bulb that lights up when current flows.
An important application is the continuity
test of a bundle of wires so as to find the two ends
belonging to a particular one of these wires; there will
be a negligible resistance between the "right" ends,
and only between the "right" ends.
This test is the performed just after the
hardware soldering and configuration has been
www.ijera.com

www.ijera.com

completed. This test aims at finding any electrical
open paths in the circuit after the soldering. Many a
times, the electrical continuity in the circuit is lost due
to improper soldering, wrong and rough handling of
the PCB, improper usage of the soldering iron,
component failures and presence of bugs in the circuit
diagram. We use a multi meter to perform this test.
We keep the multi meter in buzzer mode and connect
the ground terminal of the multi meter to the ground.
We connect both the terminals across the path that
needs to be checked. If there is continuation then you
will hear the beep sound.
2. Power ON Test:
This test is performed to check whether the
voltage at different terminals is according to the
requirement or not. We take a multi meter and put it
in voltage mode. Remember that this test is performed
without ICs. Firstly, if we are using a transformer we
check the output of the transformer; whether we get
the required 12V AC voltage (depends on the
transformer used in for the circuit). If we use a battery
then we check if the battery is fully charged or not
according to the specified voltage of the battery by
using multimeter.
Then we apply this voltage to the power
supply circuit. Note that we do this test without ICs
because if there is any excessive voltage, this may
lead to damaging the ICs. If a circuit consists of
voltage regulator then we check for the input to the
voltage regulator (like 7805, 7809, 7815, 7915 etc)
i.e., are we getting an input of 12V and a required
output depending on the regulator used in the circuit.
EX: if we are using 7805 we get output of 5V and if
using 7809 we get 9V at output pin and so on.
This output from the voltage regulator is
given to the power supply pin of specific ICs. Hence
we check for the voltage level at those pins whether
we are getting required voltage. Similarly, we check
for the other terminals for the required voltage. In this
way we can assure that the voltage at all the terminals
is as per the requirement.

V. TESTING AND RESULTS

fig 8.1.Practical Circuit of Linear load
1084 | P a g e
Sathish Bakanagari et al Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086

www.ijera.com

Fig.8.5.Output voltage of the 12v dc supply
(monostable)
Fig:8.2. Input voltage of Linear load

Fig.8.6.Output voltage of the 12v dc
supply(astable)

Fig.8.3.Practical Circuit of Non linear load

CALCULATIONS IN THERIOTICALLY:
For L-G:
Pbase=500 mva, vbase=230

Fig.8.4.Input Voltage of Non linear load

For L-L:

www.ijera.com

1085 | P a g e
Sathish Bakanagari et al Int. Journal of Engineering Research and Applications
ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086

www.ijera.com

Systems, Vol. 10, No. 4, pp 1742-1749,
November 1995.

About Authors:

SATHISH BAKANAGARI, he is received
M.Tech(power engg &energy systems) degree from
Mahaveer institute of science & technology in 2009,
now he is working as Asst. Professor in MIST,
Department of Electrical &Electronics Engg,
bandlaguda,Hyderabad,A.P.
Email:satyam2k8@gmail.com

VI. CONCLUSION
This project is designed in the form of
Hardware for three single phase transformers 230v to
12V of output for to develop an automatic tripping
mechanism for the three phase supply system while
temporary fault and permanent fault occurs. Here we
used 555 timer with relay for the fault is temporary or
permanent.
Short duration fault returns the supply to the
load immediately called as temporary trip
while
long duration shall result in permanent trip. The
concept in the future can be extended to developing a
mechanism to send message to the authorities via
SMS by interfacing a GSM modem.

A.Maheshkumar, he is received M.E(power
system& power electronics) degree from Chaitanya
bharathi institute of science& technology in 2011,
now he is working as Asst. Professor in MIST,
Department of Electrical &Electronics Engg,
Hyderabad, A.P. Email:Mahesh.alvala1@gmail.com

M.Cheenya, he is received M.Tech(Digital
electronics&communication systems) degree from
JNTU Hyderabad in 2010, now he is working as Asst.
Professor in MIST, Department of Electronics&
communication Engg, Hyderabad, A.P.
E-mail: cheenya.m@gmail.com

REFERENCES
[1]

[2]

[3]

[4]

[5]

[6]

[7]

Kimbark, Edward Wilson, ScD; Power
System Stability; John Wiley & Sons, Inc.,
N.Y., London
HAVRAN, F.J. 1999. Fault investigation on
power transmission system. ESKOM.
Internaldocument: 38, 96-99KELLER, P.
1998. Correct fault analysis. Eskom internal
document
Turan Gonen, “Electric Power Transmission
System Engineering, Analysis and Design”,
Crc Press Taylor and Francis Group.
Paul M. Anderson, “Analysis of Faulted
Power Systems”, The Institute of Electrical
and Electronics Engineers, Inc., 1995. [
Miroslav D. Markovic, “Fault Analysis in
Power Systems by Using the Fortescue
Method”, TESLA Institute, 2009.
Jun Zhu. “Analysis Of Transmission System
Faults the Phase Domain”, Texas A&M
University. Master Thesis, 2004.
D. C. Yu, D. Chen, S. Ramasamy and D. G.
Flinn, “A Windows Based Graphical
Package for Symmetrical Components
Analysis”, IEEE Transactions on Power

www.ijera.com

1086 | P a g e

Más contenido relacionado

La actualidad más candente

Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Mustafa Ismail
 
Auto selection of any aviliable phase
Auto selection of any aviliable phaseAuto selection of any aviliable phase
Auto selection of any aviliable phasenajeebs10
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedureMustafa Ismail
 
ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionChandrabhan Sharma
 
Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculationsmichaeljmack
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...Jobin Abraham
 
Calculation of short circuit currents
Calculation of short circuit currents Calculation of short circuit currents
Calculation of short circuit currents Maria Romina Angustia
 
Short circuit calculations
Short circuit calculationsShort circuit calculations
Short circuit calculationsMustafa Ismail
 
Transformer protection & maintenance
Transformer protection & maintenanceTransformer protection & maintenance
Transformer protection & maintenancePradeep Avanigadda
 
Synchronization of single phase power converters to grid
Synchronization of single phase power converters to gridSynchronization of single phase power converters to grid
Synchronization of single phase power converters to gridSyed Lateef
 
7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Lines7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Linesashwini reliserv
 
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...IRJET Journal
 
Multilevel inverter fault detectiion classification and diagnosis
Multilevel inverter fault detectiion classification and diagnosisMultilevel inverter fault detectiion classification and diagnosis
Multilevel inverter fault detectiion classification and diagnosissuryakant tripathi
 
Technical presentation on protection distance protection
Technical presentation on protection  distance protectionTechnical presentation on protection  distance protection
Technical presentation on protection distance protectionSujith Mohandas
 
Self powered door-bell watcher
Self powered door-bell watcherSelf powered door-bell watcher
Self powered door-bell watcherabdullahkhalid50
 
Over-current-earth-fault-relay-MC-31
 Over-current-earth-fault-relay-MC-31 Over-current-earth-fault-relay-MC-31
Over-current-earth-fault-relay-MC-31Powerway Systems
 

La actualidad más candente (20)

Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.
 
Auto selection of any aviliable phase
Auto selection of any aviliable phaseAuto selection of any aviliable phase
Auto selection of any aviliable phase
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedure
 
ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent Protection
 
Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculations
 
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
ELECTRICAL POWER SYSTEM - II. symmetrical three phase faults. PREPARED BY : J...
 
Calculation of short circuit currents
Calculation of short circuit currents Calculation of short circuit currents
Calculation of short circuit currents
 
Short circuit calculations
Short circuit calculationsShort circuit calculations
Short circuit calculations
 
Short circuit followup[1]
Short circuit followup[1]Short circuit followup[1]
Short circuit followup[1]
 
Transformer protection & maintenance
Transformer protection & maintenanceTransformer protection & maintenance
Transformer protection & maintenance
 
Synchronization of single phase power converters to grid
Synchronization of single phase power converters to gridSynchronization of single phase power converters to grid
Synchronization of single phase power converters to grid
 
7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Lines7SA522 Distance Protection Relay For Transmission Lines
7SA522 Distance Protection Relay For Transmission Lines
 
Transformers Protection
Transformers ProtectionTransformers Protection
Transformers Protection
 
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
Auto Reset on Temporary Fault Otherwise Permanent Trip in Three Phase Transmi...
 
Multilevel inverter fault detectiion classification and diagnosis
Multilevel inverter fault detectiion classification and diagnosisMultilevel inverter fault detectiion classification and diagnosis
Multilevel inverter fault detectiion classification and diagnosis
 
Technical presentation on protection distance protection
Technical presentation on protection  distance protectionTechnical presentation on protection  distance protection
Technical presentation on protection distance protection
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 
1 7 earth fault relay
1 7 earth fault relay1 7 earth fault relay
1 7 earth fault relay
 
Self powered door-bell watcher
Self powered door-bell watcherSelf powered door-bell watcher
Self powered door-bell watcher
 
Over-current-earth-fault-relay-MC-31
 Over-current-earth-fault-relay-MC-31 Over-current-earth-fault-relay-MC-31
Over-current-earth-fault-relay-MC-31
 

Destacado (20)

Fp3610261032
Fp3610261032Fp3610261032
Fp3610261032
 
Gb3611041110
Gb3611041110Gb3611041110
Gb3611041110
 
Gd3611171122
Gd3611171122Gd3611171122
Gd3611171122
 
Fs3610481053
Fs3610481053Fs3610481053
Fs3610481053
 
Gg3611321138
Gg3611321138Gg3611321138
Gg3611321138
 
Gc3611111116
Gc3611111116Gc3611111116
Gc3611111116
 
Ft3610541057
Ft3610541057Ft3610541057
Ft3610541057
 
Fq3610331039
Fq3610331039Fq3610331039
Fq3610331039
 
Gh3611391145
Gh3611391145Gh3611391145
Gh3611391145
 
Gf3611261131
Gf3611261131Gf3611261131
Gf3611261131
 
Ga3610941103
Ga3610941103Ga3610941103
Ga3610941103
 
Fu3610581067
Fu3610581067Fu3610581067
Fu3610581067
 
Fr3610401047
Fr3610401047Fr3610401047
Fr3610401047
 
Fw3610731076
Fw3610731076Fw3610731076
Fw3610731076
 
Fv3610681072
Fv3610681072Fv3610681072
Fv3610681072
 
Ge3611231125
Ge3611231125Ge3611231125
Ge3611231125
 
Fx3610771081
Fx3610771081Fx3610771081
Fx3610771081
 
Fz3610871093
Fz3610871093Fz3610871093
Fz3610871093
 
Kj uguiktdu
Kj uguiktduKj uguiktdu
Kj uguiktdu
 
How we do it
How we do itHow we do it
How we do it
 

Similar a Fy3610821086

final year project report
final year project reportfinal year project report
final year project reportAnuj Kumar
 
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...IJERA Editor
 
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...IJERA Editor
 
project report on plc based load sharing
project report on plc based load sharingproject report on plc based load sharing
project report on plc based load sharingVivek Arun
 
Report on minor project
Report on minor projectReport on minor project
Report on minor projectAnil Maurya
 
IRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over MechanismIRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over MechanismIRJET Journal
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...Vikram Rawani
 
Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...ijtsrd
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protectionDinesh Sharma
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculationsRonald Santos
 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Samuel Okhuegbe
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORijiert bestjournal
 
IRJET- Auto Selection of any Available Phase, in Three Phase Supply System
IRJET- Auto Selection of any Available Phase, in Three Phase Supply SystemIRJET- Auto Selection of any Available Phase, in Three Phase Supply System
IRJET- Auto Selection of any Available Phase, in Three Phase Supply SystemIRJET Journal
 
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...IRJET Journal
 
Ec Engineering project by Rahul pawar & Gagan prasad
Ec Engineering project by Rahul pawar & Gagan prasadEc Engineering project by Rahul pawar & Gagan prasad
Ec Engineering project by Rahul pawar & Gagan prasadGagan Prasad
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principlesAmmar Al Hakeim
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear johny renoald
 
Analysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time Effect
Analysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time EffectAnalysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time Effect
Analysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time EffectIJERA Editor
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power systemArvind Nathan
 

Similar a Fy3610821086 (20)

final year project report
final year project reportfinal year project report
final year project report
 
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
 
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
Implementationof Single Phasing, Over Voltage, Under Voltage, Protection of T...
 
project report on plc based load sharing
project report on plc based load sharingproject report on plc based load sharing
project report on plc based load sharing
 
Report on minor project
Report on minor projectReport on minor project
Report on minor project
 
IRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over MechanismIRJET- Microcontroller based Automatic Power Change Over Mechanism
IRJET- Microcontroller based Automatic Power Change Over Mechanism
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
 
Electrical basics
Electrical basicsElectrical basics
Electrical basics
 
Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...Consideration of Three Phase Faults on Transmission Line with Distance Protec...
Consideration of Three Phase Faults on Transmission Line with Distance Protec...
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
 
IRJET- Auto Selection of any Available Phase, in Three Phase Supply System
IRJET- Auto Selection of any Available Phase, in Three Phase Supply SystemIRJET- Auto Selection of any Available Phase, in Three Phase Supply System
IRJET- Auto Selection of any Available Phase, in Three Phase Supply System
 
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
Detection of Power Grid Synchronization Failure by Sensing Bad Voltage and Fr...
 
Ec Engineering project by Rahul pawar & Gagan prasad
Ec Engineering project by Rahul pawar & Gagan prasadEc Engineering project by Rahul pawar & Gagan prasad
Ec Engineering project by Rahul pawar & Gagan prasad
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principles
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Analysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time Effect
Analysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time EffectAnalysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time Effect
Analysis of PWM Inverter Fed Induction Motor Drive Based On Dead-Time Effect
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power system
 

Último

SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 

Último (20)

SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 

Fy3610821086

  • 1. Sathish Bakanagari et al Int. Journal of Engineering Research and Applications ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086 RESEARCH ARTICLE www.ijera.com OPEN ACCESS Three Phase Fault Analysis with Auto Reset for Temporary Fault and Trip for Permanent Fault Sathish Bakanagari1, A. Mahesh Kumar2, M. Cheenya3 12 (Asst.prof in EEE Department) 3(Asst.Prof in ECE Department) Mahaveer Institute of Science and Technology, bandlaguda, Hyderabad.A.P. Abstract This paper to develop an automatic tripping mechanism for the three phase supply system. The project output resets automatically after a brief interruption in the event temporary fault while it remains in tripped condition in case of permanent fault. The electrical substation which supply the power to the consumers, have failures due to some faults which can be temporary or permanent. These faults lead to substantial damage to the power system equipment. In India it is common, The faults might be LG (Line to Ground), LL (Line to Line), 3L (Three lines) in the supply systems and these faults in three phase supply system can affect the power system. To overcome this problem a system is built, which can sense these faults and automatically disconnects the supply to avoid large scale damage to the control gears in the grid sub-stations. This system is built using three single phase transformers which are wired in star input and star output, and 3 transformers are connected in delta connections, having input 220 volt and output at 12 volt. This concept low voltage testing of fault conditions is followed as it is not advisable to create on mains line. 555 timers are used for handling short duration and long duration fault conditions. A set of switches are used to create the LL, LG and 3L fault in low voltage side, for activating the tripping mechanism. Short duration fault returns the supply to the load immediately called as temporary trip while long duration shall result in permanent trip. The concept in the future can be extended to developing a mechanism to send message to the authorities via SMS by interfacing a GSM modem. Keywords—555 Timer, Voltage regulator (LM7805), Relays, Comparator, Transformer (230 V– 12V AC) I. Introduction Various studies have shown that anywhere from 70%, to as high as 90%, of faults on most overhead lines are transient. A transient fault, such as an insulator flashover, is a fault which is cleared by the immediate tripping of one or more circuit breakers to isolate the fault, and which does not recur when the line is re-energized. Faults tend to be less transient (near the 80% range) at lower, distribution voltages and more transient (near the90% range) at higher, sub transmission and transmission voltages. Lightning is the most common cause of transient faults, partially resulting from insulator flashover from the high transient voltages induced by the lightning. Other possible causes are swinging wires and temporary contact with foreign objects. Thus, transient faults can be cleared by momentarily deenergizing the line, in order to allow the fault to clear.Autoreclosing can then restore service to the line. The remaining 10 - 30% of faults are semipermanent or permanent in nature. A small branch falling onto the line can cause a semi-permanent fault. In this case, however, an immediate de-energizing of the line and subsequent auto reclosing does not clear the fault. Instead, a coordinated time-delayed trip would allow the branch to be burned away without damage to the system. Semi-permanent faults of this type are likely to be most prevalent in highly wooded www.ijera.com areas and can be substantially controlled by aggressive line clearance programs. Permanent faults are those that will not clear upon tripping and reclosing. An example of a permanent fault on an overhead line is a broken wire causing a phase to open, or a broken pole causing the phases to short together. Faults on underground cables should be considered permanent. Cable faults should be cleared without auto reclosing and the damaged cable repaired before service is restored. There may be exceptions to this, as in the case of circuits composed of both underground cables and overhead lines. Although auto reclosing success rates vary from one company to another, it is clear that the majority of faults can be successfully cleared by the proper use of tripping and auto reclosing. This deenergizes the line long enough for the fault source to pass and the fault arc to de-energize, then automatically recloses the line to restore service. Thus, autoreclosing can significantly reduce the outage time due to faults and provide a higher level of service continuity to the customer. Furthermore, successful high-speed reclosing auto reclosing. on transmission circuits can be a major factor when attempting to maintain system stability. For those faults that are permanent, auto reclosing will reclose the circuit into a fault that has not been cleared, which 1082 | P a g e
  • 2. Sathish Bakanagari et al Int. Journal of Engineering Research and Applications ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086 www.ijera.com may have adverse affects on system stability (particularly at transmission levels). II. VOLTAGE REGULATOR III. SCHEMATIC DIAGRAM The LM78XX/LM78XXA series of threeterminal positive regulators are available in the TO220/D-PAK package and with several fixed output voltages, making them useful in a Wide range of applications. Each type employs internal current limiting, thermal shutdown and safe operating area protection, making it essentially indestructible. If adequate heat sinking is provided, they can deliver over 1A output Current. Although designed primarily as fixed voltage regulators, these devices can be used Fig2 (a) Block diagram with external components to obtain adjustable voltages and currents. Fig1 (a) Block diagram of voltage regulator Fig1 (b) Absolute Maximum Ratings It has some features: • Output Current up to 1A. • Output Voltages of 5, 6, 8, 9, 10, 12, 15, 18, 24V. • Thermal Overload Protection. • Short Circuit Protection. • Output Transistor Safe Operating Area Protection. www.ijera.com Fig2 (b) Proposed schematic diagram Working principle: The project uses 6numbers step-down transformers for handling the entire circuit under low voltage conditions of 12v only to test the 3 phase fault analysis. The primaries of 3 transformers are connected to a 3 phase supply in star configuration, while the secondary of the same is also connected in star configuration. The other set of 3 transformers with its primary connected in star to 3 phase have their secondary’s connected in delta configuration. The outputs of all the 6 transformers are rectified and filtered individually and are given to 6 relay coils. 6 push buttons, one each connected across the relay coil is meant to create a fault condition either at star i.e. LL Fault or 3L Fault. The NC contacts of all the relays are made parallel while all the common points are grounded. The parallel connected point of NC are given to pin2 through a resistor R5 to a 555 timer i.e. wired in monostable mode. The output of the same timer is connected to the reset pin 4 of another 555 timer wired in astable mode. LED’S are connected at their output to indicate their status. The output of the U3 555 timer from pin3 is given to an Op-amp LM358 through wire 11 and d12 to the non inverting input pin3, while the inverting input is kept at a fixed voltage by a potential divider RV2. The voltage at pin2 coming from the potential divider is so held that it is higher than the pin3 of the Op-amp used as a comparator so that pin1 develops zero logic that fails to operate the relay through the driver transistor Q1. 1083 | P a g e
  • 3. Sathish Bakanagari et al Int. Journal of Engineering Research and Applications ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086 This relay Q1 is ‘3CO’ relay i.e. is meant for disconnecting the load to indicate fault conditions. Operating procedure: While the board is powered from a 3phase supply all the 6 relay coils get DC voltage and their common point disconnects from the NC and moves on to the NO points there by providing logic high at pin2 of 555 timer U1 i.e. that is kept on monostable mode. While any push button across the relay is pressed it disconnects that relay and in the process in common contacts moves to the NC position to provide a logic low at trigger pin of 555 timer to develop an output that brings the U3 555 timer which is used in astable mode for its reset pin to high such that the astable operation takes place at its output which is also indicated by flashing D11 LED. If the fault is off temporary in nature i.e. if the push button pressed is released immediately the U1 monostable disables U3 the output of which goes to zero in the event of any push button kept pressed for a longer duration the monostable output provides a longer duration active situation for U3 the astable timer the output of which charges capacitor C13 through R11 such that the output of the comparator goes high that drives the relay to switch off three phase load. The output of Op-amp remains high indefinitely through a positive feedback provided for its pin1 to pin3 through a forward biased diode and a resistor in series. This results in the relay permanently switched on to disconnect the load connected at its NC contacts permanently off. In order to maintain the flow of DC supply the star connected secondary set DC’S are paralleled through D8, D9 & D10 for uninterrupted supply to the circuit voltage of 12v DC and 5v DC derived out of voltage regulator IC 7805. IV. HARDWARE TESTING 1. Conductivity Test: In electronics, a continuity test is the checking of an electric circuit to see if current flows (that it is in fact a complete circuit). A continuity test is performed by placing a small voltage (wired in series with an LED or noise-producing component such as a piezoelectric speaker) across the chosen path. If electron flow is inhibited by broken conductors, damaged components, or excessive resistance, the circuit is "open". Devices that can be used to perform continuity tests include multi meters which measure current and specialized continuity testers which are cheaper, more basic devices, generally with a simple light bulb that lights up when current flows. An important application is the continuity test of a bundle of wires so as to find the two ends belonging to a particular one of these wires; there will be a negligible resistance between the "right" ends, and only between the "right" ends. This test is the performed just after the hardware soldering and configuration has been www.ijera.com www.ijera.com completed. This test aims at finding any electrical open paths in the circuit after the soldering. Many a times, the electrical continuity in the circuit is lost due to improper soldering, wrong and rough handling of the PCB, improper usage of the soldering iron, component failures and presence of bugs in the circuit diagram. We use a multi meter to perform this test. We keep the multi meter in buzzer mode and connect the ground terminal of the multi meter to the ground. We connect both the terminals across the path that needs to be checked. If there is continuation then you will hear the beep sound. 2. Power ON Test: This test is performed to check whether the voltage at different terminals is according to the requirement or not. We take a multi meter and put it in voltage mode. Remember that this test is performed without ICs. Firstly, if we are using a transformer we check the output of the transformer; whether we get the required 12V AC voltage (depends on the transformer used in for the circuit). If we use a battery then we check if the battery is fully charged or not according to the specified voltage of the battery by using multimeter. Then we apply this voltage to the power supply circuit. Note that we do this test without ICs because if there is any excessive voltage, this may lead to damaging the ICs. If a circuit consists of voltage regulator then we check for the input to the voltage regulator (like 7805, 7809, 7815, 7915 etc) i.e., are we getting an input of 12V and a required output depending on the regulator used in the circuit. EX: if we are using 7805 we get output of 5V and if using 7809 we get 9V at output pin and so on. This output from the voltage regulator is given to the power supply pin of specific ICs. Hence we check for the voltage level at those pins whether we are getting required voltage. Similarly, we check for the other terminals for the required voltage. In this way we can assure that the voltage at all the terminals is as per the requirement. V. TESTING AND RESULTS fig 8.1.Practical Circuit of Linear load 1084 | P a g e
  • 4. Sathish Bakanagari et al Int. Journal of Engineering Research and Applications ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086 www.ijera.com Fig.8.5.Output voltage of the 12v dc supply (monostable) Fig:8.2. Input voltage of Linear load Fig.8.6.Output voltage of the 12v dc supply(astable) Fig.8.3.Practical Circuit of Non linear load CALCULATIONS IN THERIOTICALLY: For L-G: Pbase=500 mva, vbase=230 Fig.8.4.Input Voltage of Non linear load For L-L: www.ijera.com 1085 | P a g e
  • 5. Sathish Bakanagari et al Int. Journal of Engineering Research and Applications ISSN : 2248-9622, Vol. 3, Issue 6, Nov-Dec 2013, pp.1082-1086 www.ijera.com Systems, Vol. 10, No. 4, pp 1742-1749, November 1995. About Authors: SATHISH BAKANAGARI, he is received M.Tech(power engg &energy systems) degree from Mahaveer institute of science & technology in 2009, now he is working as Asst. Professor in MIST, Department of Electrical &Electronics Engg, bandlaguda,Hyderabad,A.P. Email:satyam2k8@gmail.com VI. CONCLUSION This project is designed in the form of Hardware for three single phase transformers 230v to 12V of output for to develop an automatic tripping mechanism for the three phase supply system while temporary fault and permanent fault occurs. Here we used 555 timer with relay for the fault is temporary or permanent. Short duration fault returns the supply to the load immediately called as temporary trip while long duration shall result in permanent trip. The concept in the future can be extended to developing a mechanism to send message to the authorities via SMS by interfacing a GSM modem. A.Maheshkumar, he is received M.E(power system& power electronics) degree from Chaitanya bharathi institute of science& technology in 2011, now he is working as Asst. Professor in MIST, Department of Electrical &Electronics Engg, Hyderabad, A.P. Email:Mahesh.alvala1@gmail.com M.Cheenya, he is received M.Tech(Digital electronics&communication systems) degree from JNTU Hyderabad in 2010, now he is working as Asst. Professor in MIST, Department of Electronics& communication Engg, Hyderabad, A.P. E-mail: cheenya.m@gmail.com REFERENCES [1] [2] [3] [4] [5] [6] [7] Kimbark, Edward Wilson, ScD; Power System Stability; John Wiley & Sons, Inc., N.Y., London HAVRAN, F.J. 1999. Fault investigation on power transmission system. ESKOM. Internaldocument: 38, 96-99KELLER, P. 1998. Correct fault analysis. Eskom internal document Turan Gonen, “Electric Power Transmission System Engineering, Analysis and Design”, Crc Press Taylor and Francis Group. Paul M. Anderson, “Analysis of Faulted Power Systems”, The Institute of Electrical and Electronics Engineers, Inc., 1995. [ Miroslav D. Markovic, “Fault Analysis in Power Systems by Using the Fortescue Method”, TESLA Institute, 2009. Jun Zhu. “Analysis Of Transmission System Faults the Phase Domain”, Texas A&M University. Master Thesis, 2004. D. C. Yu, D. Chen, S. Ramasamy and D. G. Flinn, “A Windows Based Graphical Package for Symmetrical Components Analysis”, IEEE Transactions on Power www.ijera.com 1086 | P a g e