Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design

    Paul Erickson, LEED AP, Sustainable Practice Leader

  ASHRAE | Chicago Energy Modeling Conference | February 14, 2012
Slide 2


Costs Over Time
Slide 3


Cost Compression
Slide 4


The Operational Savings Opportunity
Slide 5


Agenda



   1.   Why the universal drive to reduce operating costs now?
   2.   Getting more from the Integrated Design Process
   3.   The impact of BIM
   4.   Robust decision making process
   5.   The Learning Objectives
   6.   Questions
Slide 6




Why the Drive to Reduce Operating
           Costs Now?

          FIVE DRIVERS
Slide 7


Driver 1              42 States Have Projected Shortfalls for Fiscal Year 2012
                       Short of Money




  Source: Center on Budget and Policy Priorities | CBPP survey
Slide 8


Driver 2                 Endowment Data
                          Short of Money




 1Institutions ranked by size of endowment in 2009.
 NOTE: Degree-granting institutions grant associate's or higher degrees and participate in Title IV federal financial aid programs.
 SOURCE: U.S. Department of Education, National Center for Education Statistics. (2011). Digest of Education Statistics, 2010 (NCES 2011-015), Table 372.
Slide 9


Driver 3   Energy Prices Going Up; Operational Costs Going Up




               24 Years




                                                       24 Years


     Compounds difficulties of budget reductions
Slide 10


Driver 4               Recent Building Boom on Campuses = Greater Demand on
                        Operating Budgets

  HISTORY OF COLLEGE CONSTRUCTION
  COLLEGE CONSTRUCTION COMPLETED ($000’S), 1995 THROUGH 2010


    $16B                          Total Construction
    $14B

    $12B

    $10B

     $8B

     $6B

     $4B

     $2B

      $0
                1995             1997               1999   2001   2003   2005   2007   2009



  Source: College Planning & Management/Feb. 2011
Slide 11


Driver 5    Reducing Energy – Bar Raising Codes for New & Renovated
             Construction
Progression of the ASHRAE 90.1 Energy Standard
Slide 12


The Result   The Need for an Integrated Solution
Slide 13


Integrated Design Efforts to Date

     If Traditional Design Effort has been this…

       Traditional
Slide 14


Integrated Design Efforts to Date

       Integrated Effort has been…




   •   Goal: Construction Cost Savings to Owners
   •   Result: Limited Realization of Cost Savings to Owners
Slide 15


How Do We Get More from the Integrated Delivery Process?



   1.   Harness the Industry’s Dynamically Developing Tools
           BIM
           Energy Modeling
   2.   Improve the Design Decision Making Process
           Timing of Team Engagement
           Decision Making Process (tools and metrics)
   3.   Amplify Owner’s Expectations
           The Project Champion
           Day to Day : Project Manager
Slide 16


BIM: One Tool, Uneven Development
Slide 17


BIM’s Promise
Slide 18


BIM’s Pending Architecture: The Anticipated Path to Reduce Operating Costs
Slide 19


BIM’s Pending Architecture: Continuous Retro-Commissioning

    Real-time evaluation of performance
    Near real-time adjustment of operation parameters
    Maintaining the original design savings
Slide 20


BIM’s Pending Architecture: Facilities ManagementTools

    Real-time evaluation of performance
    Calculation of avoided maintenance cost impact
    Prioritization of maintenance tasks
    Intuitive data and product information access
    Single interface and point of content update
Slide 21


Effective Decision Making Potential
Slide 22




Our Experience . . .
• Typical Integrated Design alone will not deliver operations savings
• A clear financial metric alone will not deliver operations savings


Our Position
The complexity and contagious rate of change requires:

       An Effective and Nimble Decision Making Process
Slide 23




An Effective and Nimble Decision Making Process
• Driven by:
    • Accelerated Team Engagement
    • Financial Metrics which consider operating costs
    • Decision Making Tools that can accommodate competing and changing goals
        •   operating costs,
        •   LEED,
        •   Simple Payback
        •   etc.
Slide 24


Timing of Team Engagement

   •   Typical Integrated Design process generally produces:
        • More coordinated drawings
        • Fewer RFIs and change orders
        • More User/FM interaction and input during design
        • Some energy savings
   •   Earlier engagement is necessary for early decision making
Slide 25


Decision Making Metrics are Not Equally Useful
Slide 26


Decision Making Metrics are Not Equally Useful
Slide 27


Decision Making Process
Slide 28


Decision Making Process
Slide 29


Analysis and Decision Making

 Questions to Consider
 •   How does this analysis happen soon enough to inform the Charrette or early
     budgeting?
 •   How do the consultants know what the goals are prior to the charrette?
 •   Doesn’t the design team just default to “same-old” design early on?
 •   What happens when the input/experience seems to be counterproductive to
     the goals?
 •   How can the energy modeling be “detailed” if the building architecture
     isn’t set?
 •   How can the modeling keep up with the timeline? Who should do it?
 •   How do we determine if some strategies are worth tabling?
 •   How does the LCCA get good first cost numbers? Maintenance cost
     numbers?
 •   How does the estimating fit into the timeline? Who should do it?
 •   Whose responsibility is it to identify/pursue alternative funding?
 •   How do we navigate the VE exercise? A menu would be nice…
 •   Are the LCCA results meaningless if we mix and match strategies?
 •   What if we don’t believe the results?
 •   How do we accommodate items that are difficult to price?
 •   How can the design team support the Decision Maker?
 •   What are some examples of the type of support?
Slide 30


Energy Performance Modeling



                   Sustainability Charrette
Slide 31


Energy Performance Modeling


                  End of Concepts (inform estimate)




                          CODE    20%      40%         Net-Zero
                                                      Net-Zero
                                 Better   Better
Slide 32


Energy Performance Modeling - Takeaways



                • Appropriate level of detail
                • Modeling output only as good as the inputs
                • A/E vs third-party modeler
                • Models best at deltas, not absolutes
Slide 33


Goals and Metrics


                Design Goals   Life Cycle Cost   University Decision Maker
Slide 34


Goals and Metrics - Takeaways



                 •   Clear definition of metrics and goals
                 •   Stakeholder input is essential
                 •   Sensitivity analyses can accommodate uncertainties
Slide 35


Cost Hurdles: First Cost AND Operating Cost
Slide 36


Navigating the VE Sea



               Capitalizing on LCCA data
Slide 37


Navigating the VE Sea




                 • Multiple project goals must be addressed
                 • Richness of LCCA data allows for adaptation
                 • The modeling and LCCA provide a foundation throughout
Slide 38


Summary
Slide 39


Summary
Slide 40


Strategies     Energy Recovery Wheel




    • Typical Energy Savings: 15-20%
    • Typical Energy Cost Savings: 10-15%
    • Simple payback range: 3-7 yrs
Slide 41


Strategies     Active Chilled Beams




    • Typical Energy Savings: 5-10%
    • Typical Energy Cost Savings: 3-7%
    • Simple payback range: 0-4 yrs
Slide 42


Strategies     Heat Recovery Chiller (HRC)




                   HRC RECOVERED ENERGY




      • Typical Energy Savings: 10-20%
      • Typical Energy Cost Savings: 10-15 %
      • Simple payback range: 3-7 yrs
Slide 43


Strategies     Demand Control Ventilation




    • Typical Energy Savings: 5-15%
    • Typical Energy Cost Savings: 3-12%
    • Simple payback range: 1-4 yrs
Slide 44


Example Results: Integrated Design for Reducing Operating Costs
Slide 45


Today’s Takeaways



   1.   Unprecedented Drive to Reduce Operating Costs
   2.   Preliminary Modeling and Life Cycle Costing are the Right Tools to
        Reduce Operating Costs
   3.   Amplified Client Commitment will lead to Reduced Operating Costs
Slide 46
Slide 47


Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design

    Paul Erickson, LEED AP, Sustainable Practice Leader

  ASHRAE | Chicago Energy Modeling Conference | February 14, 2012

Más contenido relacionado

La actualidad más candente

IES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L ClinicIES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L ClinicIES VE
 
Modelling Natural Ventilation in IES-VE: Case studies & Research Outlook
Modelling Natural Ventilation in IES-VE: Case studies & Research OutlookModelling Natural Ventilation in IES-VE: Case studies & Research Outlook
Modelling Natural Ventilation in IES-VE: Case studies & Research OutlookIES VE
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWmelanie_bissonnette
 
REBNY NYC Benchmarking Seminar: EnergyStar Portfolio Managerr
REBNY NYC Benchmarking Seminar: EnergyStar Portfolio ManagerrREBNY NYC Benchmarking Seminar: EnergyStar Portfolio Managerr
REBNY NYC Benchmarking Seminar: EnergyStar Portfolio ManagerrREBNY
 
Building Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuestBuilding Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuestAsadullah Malik
 
IES Faculty - Big Data in Building Services
IES Faculty - Big Data in Building ServicesIES Faculty - Big Data in Building Services
IES Faculty - Big Data in Building ServicesIES VE
 
04.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 204.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 2melanie_bissonnette
 
Development of calibrated operational models of existing buildings for real-t...
Development of calibrated operational models of existing buildings for real-t...Development of calibrated operational models of existing buildings for real-t...
Development of calibrated operational models of existing buildings for real-t...IES VE
 
Integrating Energy Efficiency into the Emerging Off-site modular Construction...
Integrating Energy Efficiency into the Emerging Off-site modular Construction...Integrating Energy Efficiency into the Emerging Off-site modular Construction...
Integrating Energy Efficiency into the Emerging Off-site modular Construction...Shanti Pless
 
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...Shanti Pless
 
150312 updating history_deep_retrofits
150312 updating history_deep_retrofits150312 updating history_deep_retrofits
150312 updating history_deep_retrofitsmelanie_bissonnette
 
Net Zero - TSA presentation
Net Zero - TSA presentationNet Zero - TSA presentation
Net Zero - TSA presentationPeter Hoffmann
 
Benchmark the Relative Performance of Your Data Center
Benchmark the Relative Performance of Your Data CenterBenchmark the Relative Performance of Your Data Center
Benchmark the Relative Performance of Your Data CenterAFCOM
 

La actualidad más candente (20)

IES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L ClinicIES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L Clinic
 
Modelling Natural Ventilation in IES-VE: Case studies & Research Outlook
Modelling Natural Ventilation in IES-VE: Case studies & Research OutlookModelling Natural Ventilation in IES-VE: Case studies & Research Outlook
Modelling Natural Ventilation in IES-VE: Case studies & Research Outlook
 
Bim adoption
Bim adoptionBim adoption
Bim adoption
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
Energy simulation & analysis
Energy simulation & analysisEnergy simulation & analysis
Energy simulation & analysis
 
Besf building renewal_021815
Besf building renewal_021815Besf building renewal_021815
Besf building renewal_021815
 
Building Performance Modeling
Building Performance ModelingBuilding Performance Modeling
Building Performance Modeling
 
REBNY NYC Benchmarking Seminar: EnergyStar Portfolio Managerr
REBNY NYC Benchmarking Seminar: EnergyStar Portfolio ManagerrREBNY NYC Benchmarking Seminar: EnergyStar Portfolio Managerr
REBNY NYC Benchmarking Seminar: EnergyStar Portfolio Managerr
 
Building Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuestBuilding Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuest
 
Efficiency Valuation: Fine Tuning M&V for Business Transactions
Efficiency Valuation: Fine Tuning M&V for Business TransactionsEfficiency Valuation: Fine Tuning M&V for Business Transactions
Efficiency Valuation: Fine Tuning M&V for Business Transactions
 
IES Faculty - Big Data in Building Services
IES Faculty - Big Data in Building ServicesIES Faculty - Big Data in Building Services
IES Faculty - Big Data in Building Services
 
04.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 204.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 2
 
Development of calibrated operational models of existing buildings for real-t...
Development of calibrated operational models of existing buildings for real-t...Development of calibrated operational models of existing buildings for real-t...
Development of calibrated operational models of existing buildings for real-t...
 
Integrating Energy Efficiency into the Emerging Off-site modular Construction...
Integrating Energy Efficiency into the Emerging Off-site modular Construction...Integrating Energy Efficiency into the Emerging Off-site modular Construction...
Integrating Energy Efficiency into the Emerging Off-site modular Construction...
 
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
 
150312 updating history_deep_retrofits
150312 updating history_deep_retrofits150312 updating history_deep_retrofits
150312 updating history_deep_retrofits
 
Net Zero - TSA presentation
Net Zero - TSA presentationNet Zero - TSA presentation
Net Zero - TSA presentation
 
EnergyPlus
EnergyPlusEnergyPlus
EnergyPlus
 
ECBC Training_08-Compliance
ECBC Training_08-ComplianceECBC Training_08-Compliance
ECBC Training_08-Compliance
 
Benchmark the Relative Performance of Your Data Center
Benchmark the Relative Performance of Your Data CenterBenchmark the Relative Performance of Your Data Center
Benchmark the Relative Performance of Your Data Center
 

Destacado

Chicago Energy Modeling Conference Key Note
Chicago Energy Modeling Conference Key NoteChicago Energy Modeling Conference Key Note
Chicago Energy Modeling Conference Key NoteIllinois ASHRAE
 
Chicago Energy Modeling Conference Welcome Address
Chicago Energy Modeling Conference Welcome AddressChicago Energy Modeling Conference Welcome Address
Chicago Energy Modeling Conference Welcome AddressIllinois ASHRAE
 
Nicor Gas Non-Residential Energy Efficiency Programs
Nicor Gas Non-Residential Energy Efficiency ProgramsNicor Gas Non-Residential Energy Efficiency Programs
Nicor Gas Non-Residential Energy Efficiency ProgramsIllinois ASHRAE
 
Measurement & Verification
Measurement & VerificationMeasurement & Verification
Measurement & VerificationIllinois ASHRAE
 
Net Zero Energy Buildings
Net Zero Energy BuildingsNet Zero Energy Buildings
Net Zero Energy BuildingsIllinois ASHRAE
 
Illinois ASHRAE 2011 Technology Awards
Illinois ASHRAE 2011 Technology AwardsIllinois ASHRAE 2011 Technology Awards
Illinois ASHRAE 2011 Technology AwardsIllinois ASHRAE
 
Illinois ASHRAE Research Promotion
Illinois ASHRAE Research PromotionIllinois ASHRAE Research Promotion
Illinois ASHRAE Research PromotionIllinois ASHRAE
 
YEA ASHRAE Kick-Off Meeting 2011
YEA ASHRAE Kick-Off Meeting 2011YEA ASHRAE Kick-Off Meeting 2011
YEA ASHRAE Kick-Off Meeting 2011Illinois ASHRAE
 
Smart Ideas for Your Business
Smart Ideas for Your BusinessSmart Ideas for Your Business
Smart Ideas for Your BusinessIllinois ASHRAE
 
Illinois ASHRAE Kick-Off Meeting 2011
Illinois ASHRAE Kick-Off Meeting 2011Illinois ASHRAE Kick-Off Meeting 2011
Illinois ASHRAE Kick-Off Meeting 2011Illinois ASHRAE
 
ComEd Retro-Commissioning Program
ComEd Retro-Commissioning ProgramComEd Retro-Commissioning Program
ComEd Retro-Commissioning ProgramIllinois ASHRAE
 
Waterside energy-recovery hourlong-chicago_ashrae
Waterside energy-recovery hourlong-chicago_ashraeWaterside energy-recovery hourlong-chicago_ashrae
Waterside energy-recovery hourlong-chicago_ashraeIllinois ASHRAE
 
High performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoHigh performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoIllinois ASHRAE
 
ASHRAE - Applying Air-to-Air Energy Recovery Ventilators
ASHRAE -  Applying Air-to-Air Energy Recovery VentilatorsASHRAE -  Applying Air-to-Air Energy Recovery Ventilators
ASHRAE - Applying Air-to-Air Energy Recovery VentilatorsJohn Chavez
 
You Might Need Commissioning if...
You Might Need Commissioning if...You Might Need Commissioning if...
You Might Need Commissioning if...Illinois ASHRAE
 
Sequences & Control Schemes for Air & Water Systems
Sequences & Control Schemes for Air & Water SystemsSequences & Control Schemes for Air & Water Systems
Sequences & Control Schemes for Air & Water SystemsIllinois ASHRAE
 
Standard 90.1-2010 Update
Standard 90.1-2010 UpdateStandard 90.1-2010 Update
Standard 90.1-2010 UpdateIllinois ASHRAE
 
Smoke Control in Buildings
Smoke Control in BuildingsSmoke Control in Buildings
Smoke Control in BuildingsIllinois ASHRAE
 
Kinetic Energy Recovery System (KERS)
Kinetic Energy Recovery System (KERS)Kinetic Energy Recovery System (KERS)
Kinetic Energy Recovery System (KERS)Harsh Gupta
 

Destacado (20)

Chicago Energy Modeling Conference Key Note
Chicago Energy Modeling Conference Key NoteChicago Energy Modeling Conference Key Note
Chicago Energy Modeling Conference Key Note
 
Chicago Energy Modeling Conference Welcome Address
Chicago Energy Modeling Conference Welcome AddressChicago Energy Modeling Conference Welcome Address
Chicago Energy Modeling Conference Welcome Address
 
Nicor Gas Non-Residential Energy Efficiency Programs
Nicor Gas Non-Residential Energy Efficiency ProgramsNicor Gas Non-Residential Energy Efficiency Programs
Nicor Gas Non-Residential Energy Efficiency Programs
 
Measurement & Verification
Measurement & VerificationMeasurement & Verification
Measurement & Verification
 
Net Zero Energy Buildings
Net Zero Energy BuildingsNet Zero Energy Buildings
Net Zero Energy Buildings
 
Illinois ASHRAE 2011 Technology Awards
Illinois ASHRAE 2011 Technology AwardsIllinois ASHRAE 2011 Technology Awards
Illinois ASHRAE 2011 Technology Awards
 
Illinois ASHRAE Research Promotion
Illinois ASHRAE Research PromotionIllinois ASHRAE Research Promotion
Illinois ASHRAE Research Promotion
 
YEA ASHRAE Kick-Off Meeting 2011
YEA ASHRAE Kick-Off Meeting 2011YEA ASHRAE Kick-Off Meeting 2011
YEA ASHRAE Kick-Off Meeting 2011
 
Smart Ideas for Your Business
Smart Ideas for Your BusinessSmart Ideas for Your Business
Smart Ideas for Your Business
 
Illinois ASHRAE Kick-Off Meeting 2011
Illinois ASHRAE Kick-Off Meeting 2011Illinois ASHRAE Kick-Off Meeting 2011
Illinois ASHRAE Kick-Off Meeting 2011
 
ComEd Retro-Commissioning Program
ComEd Retro-Commissioning ProgramComEd Retro-Commissioning Program
ComEd Retro-Commissioning Program
 
Waterside energy-recovery hourlong-chicago_ashrae
Waterside energy-recovery hourlong-chicago_ashraeWaterside energy-recovery hourlong-chicago_ashrae
Waterside energy-recovery hourlong-chicago_ashrae
 
High performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoHigh performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicago
 
ASHRAE Standard 100
ASHRAE Standard 100ASHRAE Standard 100
ASHRAE Standard 100
 
ASHRAE - Applying Air-to-Air Energy Recovery Ventilators
ASHRAE -  Applying Air-to-Air Energy Recovery VentilatorsASHRAE -  Applying Air-to-Air Energy Recovery Ventilators
ASHRAE - Applying Air-to-Air Energy Recovery Ventilators
 
You Might Need Commissioning if...
You Might Need Commissioning if...You Might Need Commissioning if...
You Might Need Commissioning if...
 
Sequences & Control Schemes for Air & Water Systems
Sequences & Control Schemes for Air & Water SystemsSequences & Control Schemes for Air & Water Systems
Sequences & Control Schemes for Air & Water Systems
 
Standard 90.1-2010 Update
Standard 90.1-2010 UpdateStandard 90.1-2010 Update
Standard 90.1-2010 Update
 
Smoke Control in Buildings
Smoke Control in BuildingsSmoke Control in Buildings
Smoke Control in Buildings
 
Kinetic Energy Recovery System (KERS)
Kinetic Energy Recovery System (KERS)Kinetic Energy Recovery System (KERS)
Kinetic Energy Recovery System (KERS)
 

Similar a Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design.

A Guide to Effective Benchmarking of Applications Development
A Guide to Effective Benchmarking of Applications DevelopmentA Guide to Effective Benchmarking of Applications Development
A Guide to Effective Benchmarking of Applications DevelopmentComputer Aid, Inc
 
The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9led4lgus
 
ITSM Conference, Dubai, UAE 2009
ITSM Conference, Dubai, UAE   2009ITSM Conference, Dubai, UAE   2009
ITSM Conference, Dubai, UAE 2009Tariq Elsadik
 
Using Dashboards to Monitor Project Performance - Is there a Practical Approach?
Using Dashboards to Monitor Project Performance - Is there a Practical Approach?Using Dashboards to Monitor Project Performance - Is there a Practical Approach?
Using Dashboards to Monitor Project Performance - Is there a Practical Approach?New Mexico Technology Council
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleAnnsstand
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayneNASAPMC
 
Energy Efficiency & Industrial Productivity: Gaining through Saving
Energy Efficiency & Industrial Productivity: Gaining through SavingEnergy Efficiency & Industrial Productivity: Gaining through Saving
Energy Efficiency & Industrial Productivity: Gaining through SavingInternational Energy Agency
 
Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10friscozephyr
 
Linda maleki
Linda malekiLinda maleki
Linda malekiNASAPMC
 
Leed green associate vi. stakeholder involvement in innovation answer
Leed green associate vi. stakeholder involvement in innovation   answer Leed green associate vi. stakeholder involvement in innovation   answer
Leed green associate vi. stakeholder involvement in innovation answer Bilal Mohamed
 
Bim and project management
Bim and project managementBim and project management
Bim and project managementOmar Selim
 
Bim and project management
Bim and project managementBim and project management
Bim and project managementOmar Selim
 
Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...
Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...
Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...Institute for Industrial Productivity
 
Competing with IT 15 March 13
Competing with IT 15 March 13Competing with IT 15 March 13
Competing with IT 15 March 13Lead & Transform
 
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire  20th JanContractor Lead BIM: Baxall Construction: CE Lancashire  20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th JanMartin Brown
 
KPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics FrameworkKPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics FrameworkKPI Partners
 

Similar a Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design. (20)

EA Benefits
EA BenefitsEA Benefits
EA Benefits
 
A Guide to Effective Benchmarking of Applications Development
A Guide to Effective Benchmarking of Applications DevelopmentA Guide to Effective Benchmarking of Applications Development
A Guide to Effective Benchmarking of Applications Development
 
The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9The Compass of Local Competitiveness v0.9
The Compass of Local Competitiveness v0.9
 
ITSM Conference, Dubai, UAE 2009
ITSM Conference, Dubai, UAE   2009ITSM Conference, Dubai, UAE   2009
ITSM Conference, Dubai, UAE 2009
 
Using Dashboards to Monitor Project Performance - Is there a Practical Approach?
Using Dashboards to Monitor Project Performance - Is there a Practical Approach?Using Dashboards to Monitor Project Performance - Is there a Practical Approach?
Using Dashboards to Monitor Project Performance - Is there a Practical Approach?
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Ricci Piper
Ricci PiperRicci Piper
Ricci Piper
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 
Energy Efficiency & Industrial Productivity: Gaining through Saving
Energy Efficiency & Industrial Productivity: Gaining through SavingEnergy Efficiency & Industrial Productivity: Gaining through Saving
Energy Efficiency & Industrial Productivity: Gaining through Saving
 
Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10Au2010 Autodesk Deliberations11.28.10
Au2010 Autodesk Deliberations11.28.10
 
Linda maleki
Linda malekiLinda maleki
Linda maleki
 
AMI Presentation
AMI PresentationAMI Presentation
AMI Presentation
 
Leed green associate vi. stakeholder involvement in innovation answer
Leed green associate vi. stakeholder involvement in innovation   answer Leed green associate vi. stakeholder involvement in innovation   answer
Leed green associate vi. stakeholder involvement in innovation answer
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
 
Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...
Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...
Energy Efficiency & Industrial Productivity - Gaining through Saving, Julia R...
 
Competing with IT 15 March 13
Competing with IT 15 March 13Competing with IT 15 March 13
Competing with IT 15 March 13
 
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire  20th JanContractor Lead BIM: Baxall Construction: CE Lancashire  20th Jan
Contractor Lead BIM: Baxall Construction: CE Lancashire 20th Jan
 
KPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics FrameworkKPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics Framework
 
#TFT12: Mark Kawasaki & Farah Remtulla
#TFT12: Mark Kawasaki & Farah Remtulla#TFT12: Mark Kawasaki & Farah Remtulla
#TFT12: Mark Kawasaki & Farah Remtulla
 

Más de Illinois ASHRAE

Solar Project Risk from the Developer’s Point of View
Solar Project Risk from the Developer’s Point of ViewSolar Project Risk from the Developer’s Point of View
Solar Project Risk from the Developer’s Point of ViewIllinois ASHRAE
 
Illinois Chapter of ASHRAE April 2011 Student Night
Illinois Chapter of ASHRAE April 2011 Student NightIllinois Chapter of ASHRAE April 2011 Student Night
Illinois Chapter of ASHRAE April 2011 Student NightIllinois ASHRAE
 
Rock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedRock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedIllinois ASHRAE
 
Active Chilled Beam Technology
Active Chilled Beam TechnologyActive Chilled Beam Technology
Active Chilled Beam TechnologyIllinois ASHRAE
 
Enhancing the Healing Environment with Geothermal Energy - Sherman Hospital
Enhancing the Healing Environment with Geothermal Energy - Sherman HospitalEnhancing the Healing Environment with Geothermal Energy - Sherman Hospital
Enhancing the Healing Environment with Geothermal Energy - Sherman HospitalIllinois ASHRAE
 
Hydronic Basics / Primary-Secondary Pumping
Hydronic Basics / Primary-Secondary PumpingHydronic Basics / Primary-Secondary Pumping
Hydronic Basics / Primary-Secondary PumpingIllinois ASHRAE
 
Natural Gas Rebate Programs
Natural Gas Rebate ProgramsNatural Gas Rebate Programs
Natural Gas Rebate ProgramsIllinois ASHRAE
 

Más de Illinois ASHRAE (11)

ASHRAE Standard 189.1
ASHRAE Standard 189.1ASHRAE Standard 189.1
ASHRAE Standard 189.1
 
Solar Project Risk from the Developer’s Point of View
Solar Project Risk from the Developer’s Point of ViewSolar Project Risk from the Developer’s Point of View
Solar Project Risk from the Developer’s Point of View
 
Illinois Chapter of ASHRAE April 2011 Student Night
Illinois Chapter of ASHRAE April 2011 Student NightIllinois Chapter of ASHRAE April 2011 Student Night
Illinois Chapter of ASHRAE April 2011 Student Night
 
Solar Thermal Cooling
Solar Thermal CoolingSolar Thermal Cooling
Solar Thermal Cooling
 
Life Safety Products
Life Safety ProductsLife Safety Products
Life Safety Products
 
Control Dampers
Control DampersControl Dampers
Control Dampers
 
Rock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedRock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson Learned
 
Active Chilled Beam Technology
Active Chilled Beam TechnologyActive Chilled Beam Technology
Active Chilled Beam Technology
 
Enhancing the Healing Environment with Geothermal Energy - Sherman Hospital
Enhancing the Healing Environment with Geothermal Energy - Sherman HospitalEnhancing the Healing Environment with Geothermal Energy - Sherman Hospital
Enhancing the Healing Environment with Geothermal Energy - Sherman Hospital
 
Hydronic Basics / Primary-Secondary Pumping
Hydronic Basics / Primary-Secondary PumpingHydronic Basics / Primary-Secondary Pumping
Hydronic Basics / Primary-Secondary Pumping
 
Natural Gas Rebate Programs
Natural Gas Rebate ProgramsNatural Gas Rebate Programs
Natural Gas Rebate Programs
 

Último

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsRoshan Dwivedi
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 

Último (20)

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 

Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design.

  • 1. Slide 1 Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design Paul Erickson, LEED AP, Sustainable Practice Leader ASHRAE | Chicago Energy Modeling Conference | February 14, 2012
  • 4. Slide 4 The Operational Savings Opportunity
  • 5. Slide 5 Agenda 1. Why the universal drive to reduce operating costs now? 2. Getting more from the Integrated Design Process 3. The impact of BIM 4. Robust decision making process 5. The Learning Objectives 6. Questions
  • 6. Slide 6 Why the Drive to Reduce Operating Costs Now? FIVE DRIVERS
  • 7. Slide 7 Driver 1 42 States Have Projected Shortfalls for Fiscal Year 2012 Short of Money Source: Center on Budget and Policy Priorities | CBPP survey
  • 8. Slide 8 Driver 2 Endowment Data Short of Money 1Institutions ranked by size of endowment in 2009. NOTE: Degree-granting institutions grant associate's or higher degrees and participate in Title IV federal financial aid programs. SOURCE: U.S. Department of Education, National Center for Education Statistics. (2011). Digest of Education Statistics, 2010 (NCES 2011-015), Table 372.
  • 9. Slide 9 Driver 3 Energy Prices Going Up; Operational Costs Going Up 24 Years 24 Years Compounds difficulties of budget reductions
  • 10. Slide 10 Driver 4 Recent Building Boom on Campuses = Greater Demand on Operating Budgets HISTORY OF COLLEGE CONSTRUCTION COLLEGE CONSTRUCTION COMPLETED ($000’S), 1995 THROUGH 2010 $16B Total Construction $14B $12B $10B $8B $6B $4B $2B $0 1995 1997 1999 2001 2003 2005 2007 2009 Source: College Planning & Management/Feb. 2011
  • 11. Slide 11 Driver 5 Reducing Energy – Bar Raising Codes for New & Renovated Construction Progression of the ASHRAE 90.1 Energy Standard
  • 12. Slide 12 The Result The Need for an Integrated Solution
  • 13. Slide 13 Integrated Design Efforts to Date If Traditional Design Effort has been this… Traditional
  • 14. Slide 14 Integrated Design Efforts to Date Integrated Effort has been… • Goal: Construction Cost Savings to Owners • Result: Limited Realization of Cost Savings to Owners
  • 15. Slide 15 How Do We Get More from the Integrated Delivery Process? 1. Harness the Industry’s Dynamically Developing Tools BIM Energy Modeling 2. Improve the Design Decision Making Process Timing of Team Engagement Decision Making Process (tools and metrics) 3. Amplify Owner’s Expectations The Project Champion Day to Day : Project Manager
  • 16. Slide 16 BIM: One Tool, Uneven Development
  • 18. Slide 18 BIM’s Pending Architecture: The Anticipated Path to Reduce Operating Costs
  • 19. Slide 19 BIM’s Pending Architecture: Continuous Retro-Commissioning Real-time evaluation of performance Near real-time adjustment of operation parameters Maintaining the original design savings
  • 20. Slide 20 BIM’s Pending Architecture: Facilities ManagementTools Real-time evaluation of performance Calculation of avoided maintenance cost impact Prioritization of maintenance tasks Intuitive data and product information access Single interface and point of content update
  • 21. Slide 21 Effective Decision Making Potential
  • 22. Slide 22 Our Experience . . . • Typical Integrated Design alone will not deliver operations savings • A clear financial metric alone will not deliver operations savings Our Position The complexity and contagious rate of change requires: An Effective and Nimble Decision Making Process
  • 23. Slide 23 An Effective and Nimble Decision Making Process • Driven by: • Accelerated Team Engagement • Financial Metrics which consider operating costs • Decision Making Tools that can accommodate competing and changing goals • operating costs, • LEED, • Simple Payback • etc.
  • 24. Slide 24 Timing of Team Engagement • Typical Integrated Design process generally produces: • More coordinated drawings • Fewer RFIs and change orders • More User/FM interaction and input during design • Some energy savings • Earlier engagement is necessary for early decision making
  • 25. Slide 25 Decision Making Metrics are Not Equally Useful
  • 26. Slide 26 Decision Making Metrics are Not Equally Useful
  • 29. Slide 29 Analysis and Decision Making Questions to Consider • How does this analysis happen soon enough to inform the Charrette or early budgeting? • How do the consultants know what the goals are prior to the charrette? • Doesn’t the design team just default to “same-old” design early on? • What happens when the input/experience seems to be counterproductive to the goals? • How can the energy modeling be “detailed” if the building architecture isn’t set? • How can the modeling keep up with the timeline? Who should do it? • How do we determine if some strategies are worth tabling? • How does the LCCA get good first cost numbers? Maintenance cost numbers? • How does the estimating fit into the timeline? Who should do it? • Whose responsibility is it to identify/pursue alternative funding? • How do we navigate the VE exercise? A menu would be nice… • Are the LCCA results meaningless if we mix and match strategies? • What if we don’t believe the results? • How do we accommodate items that are difficult to price? • How can the design team support the Decision Maker? • What are some examples of the type of support?
  • 30. Slide 30 Energy Performance Modeling Sustainability Charrette
  • 31. Slide 31 Energy Performance Modeling End of Concepts (inform estimate) CODE 20% 40% Net-Zero Net-Zero Better Better
  • 32. Slide 32 Energy Performance Modeling - Takeaways • Appropriate level of detail • Modeling output only as good as the inputs • A/E vs third-party modeler • Models best at deltas, not absolutes
  • 33. Slide 33 Goals and Metrics Design Goals Life Cycle Cost University Decision Maker
  • 34. Slide 34 Goals and Metrics - Takeaways • Clear definition of metrics and goals • Stakeholder input is essential • Sensitivity analyses can accommodate uncertainties
  • 35. Slide 35 Cost Hurdles: First Cost AND Operating Cost
  • 36. Slide 36 Navigating the VE Sea Capitalizing on LCCA data
  • 37. Slide 37 Navigating the VE Sea • Multiple project goals must be addressed • Richness of LCCA data allows for adaptation • The modeling and LCCA provide a foundation throughout
  • 40. Slide 40 Strategies Energy Recovery Wheel • Typical Energy Savings: 15-20% • Typical Energy Cost Savings: 10-15% • Simple payback range: 3-7 yrs
  • 41. Slide 41 Strategies Active Chilled Beams • Typical Energy Savings: 5-10% • Typical Energy Cost Savings: 3-7% • Simple payback range: 0-4 yrs
  • 42. Slide 42 Strategies Heat Recovery Chiller (HRC) HRC RECOVERED ENERGY • Typical Energy Savings: 10-20% • Typical Energy Cost Savings: 10-15 % • Simple payback range: 3-7 yrs
  • 43. Slide 43 Strategies Demand Control Ventilation • Typical Energy Savings: 5-15% • Typical Energy Cost Savings: 3-12% • Simple payback range: 1-4 yrs
  • 44. Slide 44 Example Results: Integrated Design for Reducing Operating Costs
  • 45. Slide 45 Today’s Takeaways 1. Unprecedented Drive to Reduce Operating Costs 2. Preliminary Modeling and Life Cycle Costing are the Right Tools to Reduce Operating Costs 3. Amplified Client Commitment will lead to Reduced Operating Costs
  • 47. Slide 47 Preliminary Modeling & Life Cycle Costing: Underpinnings of Integrated Design Paul Erickson, LEED AP, Sustainable Practice Leader ASHRAE | Chicago Energy Modeling Conference | February 14, 2012