SlideShare una empresa de Scribd logo
1 de 55
Turbo-roundabout design
and examples
Iva Močibob, univ.bacc.ing.aedif
Five types of four
leg intersection :
• The Netherlands – more than 70
• Slovenia - 11
• Germany - 3
• Hungary – 2
• Belgium – 1
• Indiana (USA) – 2
In this moment there are just few
countries with turbo roundabouts:
•the basic turbo roundabout
•the egg roundabout
•the knee roundabout
•the spiral roundabout
•the rotor roundabout
 Basic turbo roundabout and egg roundabout
 Knee roundabout and spiral roundabout
 Rotor roundabout
Three leg roundabouts
 Strached knee and star roundabout
GEOMETRIC DESIGN ELEMENTS OF THE TURBO
ROUNDABOUTS
The geometrical form of the turbo roundabout is formed by
the so-called’’turbo block’’.
This is a block or a formation of all the necessary radii,
which must be rotated in a certain way, thereby obtaining
traffic lanes or driving lines.
The size of radii of the standard roundabout with a spiral
course of the circulatory carriageway and the width of the
circulatory traffic lane must be selected in a way that the
speed of driving through the roundabout does not exceed
or equals 40 km/h!
 A turbo roundabout consists of spirals.
 These spirals are composed of segments of circular
arcs, often semicircles, with each arc having a larger
radius than the previous arc.
 When the radius of the arc changes, the centre of the arc
changes by a corresponding amount so that the curve
remains continuous... curve has to be marked by a
constant step equal to the transversal spacing between the
lanes -> Archimedean spiral
The basic turbo roundabout consists of 2 nested spirals. Each spiral
consists of 3 semicircles with successively larger radii that meet at a
line called the translation axis.
The arcs on the right side of the translation axis have a centre C-right
that is above the overall centre of the roundabout; the arcs on the left
side of the translation axis have a centre C-left that is below the
overall centre.
The distance between the centres of the arc segments is called the
shift along the translation axis. The bias of an arc is the distance
from its centre to the overall centre, and is therefore half the shift. In
order for the spiral to be continuous, the shift must equal the change in
radius.
The best position of the translatory axle is as if the clock hands
pointed the time: “five minutes to five o’clock” in the case of four
– arm Or “ten minutes past eight o’clock” in the case of three-
arm turbo roundabout!
Steps in designing turbo roundabout
Step 1 is to select widths of the
basic elements
 the inner radius
 the inside and outside roadways
 the lane divider
 the offsets between the roadway edges and the lane lines
Step 2 is to determine the shifts that the lane lines make.
The actual geometry of a turbo roundabout’s spirals is complicated.
Instead of a single centre point C-right for the semicircular arcs on
the right side of the translation axis, there are two right-side
centre points, one with a slightly larger bias than the other.
The centre point with the larger bias is used to make the transition
from inside edge to the middle divider; the other centre point is
used for the remainder of the spiral. Likewise, the arcs on the left side of the
translation axis have two centre’s with slightly different biases.
Step 3 is to calculate the radii of the circular arcs, and to sketch
the turbo block. Depending on the need, one can focus on
spirals representing lane lines, whose arcs have radii R1’ to R4’,
or spirals whose arcs represent the roadway edges, with radii R1
to R4.
Step 4 is the global rotation and translation of the turbo block to
match the entering legs.
Step 5 is ‘fine tuning’ the position of the translation axis: tangent
point A, where the inner curve of the entrance lanes connects to
the outer curve of the roundabout’s outer lane, should be
positioned after the translation axis.
Design of other types of turbo roundabouts
The design process for the basic turbo roundabout is also valid for
the egg roundabout. Other roundabout types have different
spiral patterns and require modifications to the geometric design.
The knee and stretched knee roundabouts are based on a
simple, nested spirals.
A spiral type roundabout has a similar geometry to the basic
turbo roundabout, based on two nested spirals. However, its
spirals have an additional semicircle in order to create a third
circulating lane:
Because the shift in lane lines is 5.35 m for the transition from the
inside to the first divider and from the first divider to the second
divider, arcs corresponding to the inside of the roundabout and the
first divider (radii R1, R2 and R3, as well as R1’, R2’ and R3’) are
drawn from a centre with bias equal to 5.35/2; the remaining, outer
arcs are drawn from a centre with smaller bias 5.05/2. Calculation of
the arc radii follows a similar logic to that used for the basic turbo
roundabout.
Rotor roundabout
The rotor roundabout consists of 4 nested spirals; its turbo
block has four translation axes.
Star roundabout
For the star roundabout
which consists of 3
nested spirals, the turbo
block has 3 translation
axes.
Radius
•The key parameters that determine the performance of a turbo
roundabout are the radii for the different circular arcs and the
lane widths. They are all related to each other. According to
experiences in the Netherlands, the speed on the roundabout is
the lowest when the radius of the inner curve of the inner lane is
about 12 m
•Because low speed is the most important goal for safety, in the
Netherlands the standard dimensions are based on a radius of 12
m for the inner edge of the inside lane
Start of the inner lane
In the past they were designed with smooth curves but sometimes
this approach caused confusion, as drivers entering the roundabout
in the right entry lane mistakenly expected continuing traffic on the
roundabout to shift into the inner lane. Therefore, nowadays the
preferred design is for the inner lane to start abruptly.
Turbo roundabout with traffic signals
...a new development in the Netherlands.
It seeks to combine the safety advantages of a turbo
roundabout with traffic flow advantages of traffic signals.
The basic design of a turbo roundabout with traffic signals
is based on the rotor roundabout. One of the main
characteristics of a turbo roundabout with traffic signals is
the fact that each traffic direction has its own
separate lane or lanes. There are no combined lanes to
be used by traffic exiting the roundabout at different exits.
Characteristic of signalised turbo roundabouts
Currently there is no standard design for a signalized turbo roundabout.
So far the lanes on the roundabout have a width of 8 m at the
transition to a double lane exit. The inner lane is 10 m wide and
reduces to 8 m towards the exit.
Inner lanes cuts through the central island and space gained this way is
used to create driving lanes with large widths that allows large truck
combinations to safely use all lanes simultaneously. There are islands
between the directions of roughly 2.50 m width. All other
measurements depend on local conditions.
2 signalized turbo roundabouts operating in the Netherlands (2009): Doenkadeplein
and Tolhekplein
Germany -> Turbo roundabout Baden-Baden
 Opened May 2006.
Roundabout examples
-> Zweibruecken
Slovenia
 First turbo roundabout in
Maribor 2008, “Titova – M5”
 Maribor 2008, “Lackova– M3”, Maribor, Slovenia
 Roundabout K1 “Lesnina”, Koper, Slovenia
 Roundabout K5 Koper, Slovenia
 First idea of roundabout with
depressed lanes –”flower
roundabout”
Belgium
The Province of North
Brabant gives a
sustainably safe design of
the road and realizing a
bicycle connection
between Schijndel and 's-
Hertogenbosch.
Netherlands
 In the Netherlands multi lane roundabouts are no longer built,
and existing multi lane roundabouts will be reconstructed into
turbo roundabouts. The main reason is the disappointing
performances of multi lane roundabouts on both capacity and
road safety.
Roundabout Diependaalselaan / Utrechtseweg
-> Oostereind / Soestdijkerstraatweg, Hilversum
-> Roundabout Kerkelanden
Joost den Draaijer Roundabout at the Media Park
The rumble streep
Planned: Leuwarden, Europe tunnel roundabout
Turbo roundabout at the Duke Janstraat in Waalwijk
Turbo roundabout Roermond -Sittard
-> Weert roundabout
Croatia roundabouts (planned)
before
Designed by Tedi Zgrablić
Project designer at Via ING doo Pula
Phd student at Uni. of Maribor
after
Designed by Tedi Zgrablić
Project designer at Via ING doo Pula
Phd student at Uni. of Maribor
Signalized -> Doenkadeplain, Rotterdam,
Zuid-Holand
USA
Indiana
THANK YOU !!!
Literature:
1. Turbo Roundabouts: Design Principles and Safety Performance, Lambertus G.H. Fortuijn, MSc.,
TRB Annual meeting, 2009
2. Roundabouts - Application and design, A practical manual, Royal Haskoning, Ministry of Transport,
Public Works and Water management Partners for Roads, June 2009
3. D.Sc. Tomaž TOLLAZZI, PLANNING AND DESIGNING OF THE TURBO ROUNDABOUTS, University of
Split, Croatia 2012.
4. Slovenian experiences with „Turbo-Roundabouts”, Tollazzi, Tušelj, Renčelj, 2012.
5. Turborotonde und turboplein, Lambertus G.H. Fortuijn, Thesis series 2013/1
6. TURBO-ROUNDABOUT GENERAL DESIGN CRITERIA AND FUNCTIONAL PRINCIPLES:CASE STUDIES
FROM REAL WORLD, Giuffrè,Granà, Guerrieri, 2009.
7. Turbo-Roundabout- an Experience from Netherlands and Germany, Werner Brilon, Ruhr-Universität
Bochum, Germany
8. Bijlagen bij Turborotonde en turboplein: ontwerp, capaciteit en veiligheid L.G.H. (Bertus) Fortuijn
Special thnx to Tedi Zgrablić, mag.ing.aedif.
phd student at Uni. of Maribor
for letting me use his turbo roundabout designs !!!

Más contenido relacionado

La actualidad más candente

Comparison of PCU for Indian and American conditions
Comparison of PCU for Indian and American conditionsComparison of PCU for Indian and American conditions
Comparison of PCU for Indian and American conditionsRaghupathi Kandiboina
 
Bus terminal redevelopment
Bus terminal redevelopment Bus terminal redevelopment
Bus terminal redevelopment Mohit Gupta
 
Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2Latif Hyder Wadho
 
Introduction to intersection
Introduction to intersectionIntroduction to intersection
Introduction to intersectionYasirKhan357
 
Lutyens delhi2 (nx power lite)
Lutyens delhi2 (nx power lite)Lutyens delhi2 (nx power lite)
Lutyens delhi2 (nx power lite)Prince Pal
 
A3 report sarah
A3 report sarahA3 report sarah
A3 report sarahSarah Esa
 
Pedestrian safety powerpoint
Pedestrian safety powerpointPedestrian safety powerpoint
Pedestrian safety powerpointSarah Parks
 
Project for Public Spaces - Streets as Places
Project for Public Spaces - Streets as PlacesProject for Public Spaces - Streets as Places
Project for Public Spaces - Streets as Placesmetroplanning
 
12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...
12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...
12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...Hossam Shafiq I
 
Traffic circles & roundabouts
Traffic circles & roundaboutsTraffic circles & roundabouts
Traffic circles & roundaboutsTHECITYALLIANCE
 
Architectural Comprehensive Design Report
Architectural Comprehensive Design ReportArchitectural Comprehensive Design Report
Architectural Comprehensive Design ReportLimSiewNi
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination surveyAkash Pandey
 
Improving Walkability, And Pedestrian Safety And Convenience
Improving Walkability, And Pedestrian Safety And ConvenienceImproving Walkability, And Pedestrian Safety And Convenience
Improving Walkability, And Pedestrian Safety And ConvenienceArefeh Nasri
 

La actualidad más candente (20)

Chapter 3 junction design
Chapter 3 junction designChapter 3 junction design
Chapter 3 junction design
 
Comparison of PCU for Indian and American conditions
Comparison of PCU for Indian and American conditionsComparison of PCU for Indian and American conditions
Comparison of PCU for Indian and American conditions
 
Bus terminal redevelopment
Bus terminal redevelopment Bus terminal redevelopment
Bus terminal redevelopment
 
Traffic Engineering
Traffic EngineeringTraffic Engineering
Traffic Engineering
 
1 intro to road safety engineering
1 intro to road safety engineering1 intro to road safety engineering
1 intro to road safety engineering
 
Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2Traffic engineering and traffic control devices 2
Traffic engineering and traffic control devices 2
 
Unit 3
Unit 3Unit 3
Unit 3
 
Introduction to intersection
Introduction to intersectionIntroduction to intersection
Introduction to intersection
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Lutyens delhi2 (nx power lite)
Lutyens delhi2 (nx power lite)Lutyens delhi2 (nx power lite)
Lutyens delhi2 (nx power lite)
 
A3 report sarah
A3 report sarahA3 report sarah
A3 report sarah
 
Pedestrian safety powerpoint
Pedestrian safety powerpointPedestrian safety powerpoint
Pedestrian safety powerpoint
 
Project for Public Spaces - Streets as Places
Project for Public Spaces - Streets as PlacesProject for Public Spaces - Streets as Places
Project for Public Spaces - Streets as Places
 
Urban Design: Streets
Urban Design: StreetsUrban Design: Streets
Urban Design: Streets
 
12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...
12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...
12 Basic Principle Of Intersection Signalization (Traffic Engineering هندسة ا...
 
Traffic circles & roundabouts
Traffic circles & roundaboutsTraffic circles & roundabouts
Traffic circles & roundabouts
 
Architectural Comprehensive Design Report
Architectural Comprehensive Design ReportArchitectural Comprehensive Design Report
Architectural Comprehensive Design Report
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination survey
 
Open Space Strategy
Open Space StrategyOpen Space Strategy
Open Space Strategy
 
Improving Walkability, And Pedestrian Safety And Convenience
Improving Walkability, And Pedestrian Safety And ConvenienceImproving Walkability, And Pedestrian Safety And Convenience
Improving Walkability, And Pedestrian Safety And Convenience
 

Destacado

Roundabouts on the road to sustainability
Roundabouts on the road to sustainabilityRoundabouts on the road to sustainability
Roundabouts on the road to sustainabilityJill Berberich
 
Kružni tokovi- Iva
Kružni tokovi- IvaKružni tokovi- Iva
Kružni tokovi- IvaIva Močibob
 
Planning and designing of the planning and designing of the turbo roundabouts
Planning and designing of the planning and designing of the turbo roundaboutsPlanning and designing of the planning and designing of the turbo roundabouts
Planning and designing of the planning and designing of the turbo roundaboutsSamir Awad Núñez
 
159th Metcalf to Nall Community Concerns
159th Metcalf to Nall Community Concerns159th Metcalf to Nall Community Concerns
159th Metcalf to Nall Community Concernspliekhus
 
Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )
Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )
Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Traffic Intersection Points Of Conflict
Traffic Intersection Points Of ConflictTraffic Intersection Points Of Conflict
Traffic Intersection Points Of ConflictTHECITYALLIANCE
 
Road Junctions and Intersections
Road Junctions and IntersectionsRoad Junctions and Intersections
Road Junctions and IntersectionsOshin Deshmukh
 
Statewide Roundabout Guidance in Virginia
Statewide Roundabout Guidance in VirginiaStatewide Roundabout Guidance in Virginia
Statewide Roundabout Guidance in VirginiaAndy Boenau
 
Progress withroundabouts
Progress withroundaboutsProgress withroundabouts
Progress withroundaboutsSean Merrell
 
New Residential Project in Powai by Lake Riviera
New Residential Project in Powai by Lake RivieraNew Residential Project in Powai by Lake Riviera
New Residential Project in Powai by Lake RivieraJennifer Johner
 
Climate Change by Green Yatra
Climate Change by  Green YatraClimate Change by  Green Yatra
Climate Change by Green YatraGreen Yatra
 
FWHA Roundabout Presentation 8 18 2009
FWHA Roundabout Presentation  8 18 2009FWHA Roundabout Presentation  8 18 2009
FWHA Roundabout Presentation 8 18 2009guest25d44f
 
Roundabout feasibility analysis
Roundabout feasibility analysisRoundabout feasibility analysis
Roundabout feasibility analysisAnna McCreery
 
Evs powai lake ppt
Evs powai lake ppt Evs powai lake ppt
Evs powai lake ppt Anush Shenoy
 

Destacado (20)

Porozni asfalt
Porozni asfaltPorozni asfalt
Porozni asfalt
 
Roundabouts on the road to sustainability
Roundabouts on the road to sustainabilityRoundabouts on the road to sustainability
Roundabouts on the road to sustainability
 
Kružni tokovi- Iva
Kružni tokovi- IvaKružni tokovi- Iva
Kružni tokovi- Iva
 
Planning and designing of the planning and designing of the turbo roundabouts
Planning and designing of the planning and designing of the turbo roundaboutsPlanning and designing of the planning and designing of the turbo roundabouts
Planning and designing of the planning and designing of the turbo roundabouts
 
159th Metcalf to Nall Community Concerns
159th Metcalf to Nall Community Concerns159th Metcalf to Nall Community Concerns
159th Metcalf to Nall Community Concerns
 
Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )
Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )
Intersections & Interchanges ( Highway Engineering Dr. Sherif El-Badawy )
 
Traffic Intersection Points Of Conflict
Traffic Intersection Points Of ConflictTraffic Intersection Points Of Conflict
Traffic Intersection Points Of Conflict
 
Road Junctions and Intersections
Road Junctions and IntersectionsRoad Junctions and Intersections
Road Junctions and Intersections
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Waste management
Waste managementWaste management
Waste management
 
Statewide Roundabout Guidance in Virginia
Statewide Roundabout Guidance in VirginiaStatewide Roundabout Guidance in Virginia
Statewide Roundabout Guidance in Virginia
 
Progress withroundabouts
Progress withroundaboutsProgress withroundabouts
Progress withroundabouts
 
MATC Fall Lecture Series: Eugene Russell
MATC Fall Lecture Series: Eugene RussellMATC Fall Lecture Series: Eugene Russell
MATC Fall Lecture Series: Eugene Russell
 
Park design
Park designPark design
Park design
 
New Residential Project in Powai by Lake Riviera
New Residential Project in Powai by Lake RivieraNew Residential Project in Powai by Lake Riviera
New Residential Project in Powai by Lake Riviera
 
P1
P1P1
P1
 
Climate Change by Green Yatra
Climate Change by  Green YatraClimate Change by  Green Yatra
Climate Change by Green Yatra
 
FWHA Roundabout Presentation 8 18 2009
FWHA Roundabout Presentation  8 18 2009FWHA Roundabout Presentation  8 18 2009
FWHA Roundabout Presentation 8 18 2009
 
Roundabout feasibility analysis
Roundabout feasibility analysisRoundabout feasibility analysis
Roundabout feasibility analysis
 
Evs powai lake ppt
Evs powai lake ppt Evs powai lake ppt
Evs powai lake ppt
 

Similar a Turbo roundabouts (EGE Uni) - Copy

Points and crossings.ppt
Points and crossings.pptPoints and crossings.ppt
Points and crossings.pptsamatha6
 
Curves on highway alignment
Curves on highway alignmentCurves on highway alignment
Curves on highway alignmentVishnuvardhan729
 
Waste disposal system of railway wagon
Waste disposal system of railway wagonWaste disposal system of railway wagon
Waste disposal system of railway wagonRajeshvaliya
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curvesLatif Hyder Wadho
 
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...Malyar Talash
 
Chapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptxChapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptxMamushLeta
 
Project report gearless transmission
Project report gearless transmissionProject report gearless transmission
Project report gearless transmissionOinam Kishan Mijabi
 
Designing for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim PhebyDesigning for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim PhebyTim Pheby
 
Abes engineering college ghaziabad
Abes engineering college  ghaziabadAbes engineering college  ghaziabad
Abes engineering college ghaziabadPalash Awasthi
 
abes engineering college ghaziabad
abes engineering college  ghaziabadabes engineering college  ghaziabad
abes engineering college ghaziabadPalash Awasthi
 

Similar a Turbo roundabouts (EGE Uni) - Copy (20)

Project rolling machine
Project  rolling machineProject  rolling machine
Project rolling machine
 
Lect 29- traffic rotaries
Lect 29- traffic rotariesLect 29- traffic rotaries
Lect 29- traffic rotaries
 
Points and crossings.ppt
Points and crossings.pptPoints and crossings.ppt
Points and crossings.ppt
 
Gears ppt.pptx
Gears ppt.pptxGears ppt.pptx
Gears ppt.pptx
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Curves on highway alignment
Curves on highway alignmentCurves on highway alignment
Curves on highway alignment
 
Waste disposal system of railway wagon
Waste disposal system of railway wagonWaste disposal system of railway wagon
Waste disposal system of railway wagon
 
41.2 baranowskipaperfinal
41.2 baranowskipaperfinal41.2 baranowskipaperfinal
41.2 baranowskipaperfinal
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curves
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
2 Superelevation and Spiral Curve ( by Malyar Talash, Highway Design Manager/...
 
Interchange design
Interchange designInterchange design
Interchange design
 
Design
DesignDesign
Design
 
Chapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptxChapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptx
 
Pipe fittings
Pipe fittingsPipe fittings
Pipe fittings
 
Project report gearless transmission
Project report gearless transmissionProject report gearless transmission
Project report gearless transmission
 
Gear.pptx
Gear.pptxGear.pptx
Gear.pptx
 
Designing for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim PhebyDesigning for Cycling RTPI 15.6.16 Tim Pheby
Designing for Cycling RTPI 15.6.16 Tim Pheby
 
Abes engineering college ghaziabad
Abes engineering college  ghaziabadAbes engineering college  ghaziabad
Abes engineering college ghaziabad
 
abes engineering college ghaziabad
abes engineering college  ghaziabadabes engineering college  ghaziabad
abes engineering college ghaziabad
 

Último

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 

Último (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 

Turbo roundabouts (EGE Uni) - Copy

  • 1. Turbo-roundabout design and examples Iva Močibob, univ.bacc.ing.aedif
  • 2. Five types of four leg intersection : • The Netherlands – more than 70 • Slovenia - 11 • Germany - 3 • Hungary – 2 • Belgium – 1 • Indiana (USA) – 2 In this moment there are just few countries with turbo roundabouts: •the basic turbo roundabout •the egg roundabout •the knee roundabout •the spiral roundabout •the rotor roundabout
  • 3.  Basic turbo roundabout and egg roundabout
  • 4.  Knee roundabout and spiral roundabout
  • 6. Three leg roundabouts  Strached knee and star roundabout
  • 7. GEOMETRIC DESIGN ELEMENTS OF THE TURBO ROUNDABOUTS The geometrical form of the turbo roundabout is formed by the so-called’’turbo block’’. This is a block or a formation of all the necessary radii, which must be rotated in a certain way, thereby obtaining traffic lanes or driving lines. The size of radii of the standard roundabout with a spiral course of the circulatory carriageway and the width of the circulatory traffic lane must be selected in a way that the speed of driving through the roundabout does not exceed or equals 40 km/h!
  • 8.  A turbo roundabout consists of spirals.  These spirals are composed of segments of circular arcs, often semicircles, with each arc having a larger radius than the previous arc.  When the radius of the arc changes, the centre of the arc changes by a corresponding amount so that the curve remains continuous... curve has to be marked by a constant step equal to the transversal spacing between the lanes -> Archimedean spiral
  • 9. The basic turbo roundabout consists of 2 nested spirals. Each spiral consists of 3 semicircles with successively larger radii that meet at a line called the translation axis. The arcs on the right side of the translation axis have a centre C-right that is above the overall centre of the roundabout; the arcs on the left side of the translation axis have a centre C-left that is below the overall centre.
  • 10. The distance between the centres of the arc segments is called the shift along the translation axis. The bias of an arc is the distance from its centre to the overall centre, and is therefore half the shift. In order for the spiral to be continuous, the shift must equal the change in radius.
  • 11. The best position of the translatory axle is as if the clock hands pointed the time: “five minutes to five o’clock” in the case of four – arm Or “ten minutes past eight o’clock” in the case of three- arm turbo roundabout!
  • 12. Steps in designing turbo roundabout Step 1 is to select widths of the basic elements  the inner radius  the inside and outside roadways  the lane divider  the offsets between the roadway edges and the lane lines
  • 13. Step 2 is to determine the shifts that the lane lines make. The actual geometry of a turbo roundabout’s spirals is complicated. Instead of a single centre point C-right for the semicircular arcs on the right side of the translation axis, there are two right-side centre points, one with a slightly larger bias than the other. The centre point with the larger bias is used to make the transition from inside edge to the middle divider; the other centre point is used for the remainder of the spiral. Likewise, the arcs on the left side of the translation axis have two centre’s with slightly different biases.
  • 14. Step 3 is to calculate the radii of the circular arcs, and to sketch the turbo block. Depending on the need, one can focus on spirals representing lane lines, whose arcs have radii R1’ to R4’, or spirals whose arcs represent the roadway edges, with radii R1 to R4.
  • 15.
  • 16. Step 4 is the global rotation and translation of the turbo block to match the entering legs.
  • 17. Step 5 is ‘fine tuning’ the position of the translation axis: tangent point A, where the inner curve of the entrance lanes connects to the outer curve of the roundabout’s outer lane, should be positioned after the translation axis.
  • 18. Design of other types of turbo roundabouts The design process for the basic turbo roundabout is also valid for the egg roundabout. Other roundabout types have different spiral patterns and require modifications to the geometric design. The knee and stretched knee roundabouts are based on a simple, nested spirals. A spiral type roundabout has a similar geometry to the basic turbo roundabout, based on two nested spirals. However, its spirals have an additional semicircle in order to create a third circulating lane:
  • 19. Because the shift in lane lines is 5.35 m for the transition from the inside to the first divider and from the first divider to the second divider, arcs corresponding to the inside of the roundabout and the first divider (radii R1, R2 and R3, as well as R1’, R2’ and R3’) are drawn from a centre with bias equal to 5.35/2; the remaining, outer arcs are drawn from a centre with smaller bias 5.05/2. Calculation of the arc radii follows a similar logic to that used for the basic turbo roundabout.
  • 20. Rotor roundabout The rotor roundabout consists of 4 nested spirals; its turbo block has four translation axes.
  • 21.
  • 22. Star roundabout For the star roundabout which consists of 3 nested spirals, the turbo block has 3 translation axes.
  • 24. •The key parameters that determine the performance of a turbo roundabout are the radii for the different circular arcs and the lane widths. They are all related to each other. According to experiences in the Netherlands, the speed on the roundabout is the lowest when the radius of the inner curve of the inner lane is about 12 m •Because low speed is the most important goal for safety, in the Netherlands the standard dimensions are based on a radius of 12 m for the inner edge of the inside lane
  • 25. Start of the inner lane In the past they were designed with smooth curves but sometimes this approach caused confusion, as drivers entering the roundabout in the right entry lane mistakenly expected continuing traffic on the roundabout to shift into the inner lane. Therefore, nowadays the preferred design is for the inner lane to start abruptly.
  • 26. Turbo roundabout with traffic signals ...a new development in the Netherlands. It seeks to combine the safety advantages of a turbo roundabout with traffic flow advantages of traffic signals. The basic design of a turbo roundabout with traffic signals is based on the rotor roundabout. One of the main characteristics of a turbo roundabout with traffic signals is the fact that each traffic direction has its own separate lane or lanes. There are no combined lanes to be used by traffic exiting the roundabout at different exits.
  • 27. Characteristic of signalised turbo roundabouts
  • 28.
  • 29. Currently there is no standard design for a signalized turbo roundabout. So far the lanes on the roundabout have a width of 8 m at the transition to a double lane exit. The inner lane is 10 m wide and reduces to 8 m towards the exit. Inner lanes cuts through the central island and space gained this way is used to create driving lanes with large widths that allows large truck combinations to safely use all lanes simultaneously. There are islands between the directions of roughly 2.50 m width. All other measurements depend on local conditions. 2 signalized turbo roundabouts operating in the Netherlands (2009): Doenkadeplein and Tolhekplein
  • 30. Germany -> Turbo roundabout Baden-Baden  Opened May 2006. Roundabout examples
  • 32. Slovenia  First turbo roundabout in Maribor 2008, “Titova – M5”
  • 33.  Maribor 2008, “Lackova– M3”, Maribor, Slovenia
  • 34.
  • 35.  Roundabout K1 “Lesnina”, Koper, Slovenia
  • 36.
  • 37.  Roundabout K5 Koper, Slovenia
  • 38.
  • 39.  First idea of roundabout with depressed lanes –”flower roundabout”
  • 40. Belgium The Province of North Brabant gives a sustainably safe design of the road and realizing a bicycle connection between Schijndel and 's- Hertogenbosch.
  • 41. Netherlands  In the Netherlands multi lane roundabouts are no longer built, and existing multi lane roundabouts will be reconstructed into turbo roundabouts. The main reason is the disappointing performances of multi lane roundabouts on both capacity and road safety. Roundabout Diependaalselaan / Utrechtseweg
  • 42. -> Oostereind / Soestdijkerstraatweg, Hilversum
  • 43.
  • 45. Joost den Draaijer Roundabout at the Media Park
  • 47. Planned: Leuwarden, Europe tunnel roundabout
  • 48. Turbo roundabout at the Duke Janstraat in Waalwijk
  • 51. Croatia roundabouts (planned) before Designed by Tedi Zgrablić Project designer at Via ING doo Pula Phd student at Uni. of Maribor
  • 52. after Designed by Tedi Zgrablić Project designer at Via ING doo Pula Phd student at Uni. of Maribor
  • 53. Signalized -> Doenkadeplain, Rotterdam, Zuid-Holand
  • 55. THANK YOU !!! Literature: 1. Turbo Roundabouts: Design Principles and Safety Performance, Lambertus G.H. Fortuijn, MSc., TRB Annual meeting, 2009 2. Roundabouts - Application and design, A practical manual, Royal Haskoning, Ministry of Transport, Public Works and Water management Partners for Roads, June 2009 3. D.Sc. Tomaž TOLLAZZI, PLANNING AND DESIGNING OF THE TURBO ROUNDABOUTS, University of Split, Croatia 2012. 4. Slovenian experiences with „Turbo-Roundabouts”, Tollazzi, Tušelj, Renčelj, 2012. 5. Turborotonde und turboplein, Lambertus G.H. Fortuijn, Thesis series 2013/1 6. TURBO-ROUNDABOUT GENERAL DESIGN CRITERIA AND FUNCTIONAL PRINCIPLES:CASE STUDIES FROM REAL WORLD, Giuffrè,Granà, Guerrieri, 2009. 7. Turbo-Roundabout- an Experience from Netherlands and Germany, Werner Brilon, Ruhr-Universität Bochum, Germany 8. Bijlagen bij Turborotonde en turboplein: ontwerp, capaciteit en veiligheid L.G.H. (Bertus) Fortuijn Special thnx to Tedi Zgrablić, mag.ing.aedif. phd student at Uni. of Maribor for letting me use his turbo roundabout designs !!!

Notas del editor

  1. The Archimedean spiral represents the trajectory of a point P moving with a constant speed along a half-line pivoting with constant speed on the point O.
  2. Lane widths should be determined by analyzing the swept path of the design vehicle.
  3. Shifts can be calculated from a cross section sketch such as in figure 59. There, one can see that the inner lane lines shift 5,35 m when transitioning from the inside of the roundabout to the lane divider. One can also see that the outer lane lines shift 5,05 m as they transition from the lane divider to the outside of the roundabout.
  4. For a correct positioning of the translation axis, the distance between the right edge of each entry leg and the inner curve of the outer lane of the roundabout after ¼ turn should be more or less equal.
  5. The first experiences in Germany are slightly positive. Differences in design details, especially the absence of raised lane dividers, may be the cause of an unexpected high number of accidents at one of the entries.