DATA CENTER
Computer Room
   Planning


 Jeffrey Lam RCDD
What is a data center?
Data Centers
– “nerve centers” of the
  organisation
– centralize & consolidate IT
  resources
– support critical business
  operations.
– provide uninterrupted service to
  mission critical applications
    •   7 x 24 x 365 availability
    •   Power & network redundancy
    •   Physical & network security
    •   Environmental monitoring
    •   Air-conditioning / thermal mgt
    •   Fire suppression systems
Different Tiers of data centers




 Data center space is precious, use it wisely.
FM200 cylinders
                                            FM200 cylinders
MDA
MDA   Operating Console
      Operating Console




C
C
R
R         Reserved for future racks
          Reserved for future racks
A
A
U
U                                                                     TYPICAL
                racks
                racks                                               Computer Room

C
C               racks
                racks
R
R
A
A
U
U



                                                           Elect.
                                                           Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS


                                               Batteries
                                               Batteries
EIA/TIA 942 recommendations for computer room
  • Minimum height = 2.6m
  • Minimum door = 1m wide, 2.13m high
  • Minimum floor loading = 7.2kPa (distributed)
            • Recommended floor loading = 12kPa (distributed)
  • Dedicated air conditioning
     – temperature 20° to 25 °C
     – relative humidity 40% to 55%


EIA/TIA 569 recommendations for equipment room
  • Lighting
      – 500 lux measured 1 m above finished floor
      – Install light fixtures 2.6 m above floor
  • Local disaster regulations
      – seismic rating
Batteries
    Batteries
Elect.
Elect.               Operating Console
                     Operating Console
                                                                 Group your
                                                                 equipment into
C
C                                                                zones
R
R                    Reserved for future racks
                     Reserved for future racks
A
                                                                 power required
A
U
U                                                                •heat generated
                 LAN /             WAN / routers
                                                                 •amount & type of
                switches            & security                   cables
                                                                 •maintenance
C
C               SAN /              applications/
R
R
A
A               storage               server
U
U



                                                       Elect.
                                                       Elect.
                     UPS
                     UPS          UPS
                                  UPS            UPS
                                                 UPS            Lower power & cooling

                                                                Highest power & cooling
MDA
MDA         Operating Console
            Operating Console
                                                                           Group your
                                                                           equipment into
C
C                                                                          zones
R
R
                SINGAPORE

                            INDONESIA

                                         MALAYSIA
A
      THALAND

A                                                                          Consider ease of
U




                                                    LAN &
U




                                                            WAN
                                                                           operation

                                                                           Spread out the
                                                                           power / cooling
C                                                                          requirements
C
R
R
A
A
U
U



                                                                  Elect.
                                                                  Elect.
                  UPS
                  UPS                   UPS
                                        UPS          UPS
                                                     UPS
MDA
MDA   Operating Console
      Operating Console

                                                     Ramp to bring
                                                     equipment up onto
C
C                                                    raised floors.
R
R         Reserved for future racks
          Reserved for future racks
A
A                                                    Suggested slope 1:12
U
U                                                    Suggested width 1.8m
                racks
                racks                                (but consider the width
                                                     of your largest piece of
                                                     equipment)
C
C               racks
                racks
R
R
A
A
U
U                                                    Barriers / handrails


                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS            for safety purposes.
                                                     Suggested height
                                                     >0.8m
MDA
MDA   Operating Console
      Operating Console


                                                     Allow space for
C
C                                                    expansion
R
R         Reserved for future racks
          Reserved for future racks
A
A
U
U                                                    Near entrance for
                                                     easy install where
                racks
                racks                                possible.


C
C               racks
                racks
R
R
A
A
U
U



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
MDA
MDA      Operating Console
         Operating Console

       Cold aisles                                             Hot & Cold aisles
C
C                                                              •Cold air directed to
R
R            Reserved for future racks
             Reserved for future racks                         cold aisles through
A
A                                                              raised floors.
U
U                                          Hot aisles          •Hot air return through
                    racks
                    racks                                      ceiling space
      Cold aisles                                              •Computer Room Air
                                                               handling units (CRAU)
C
C                   racks
                    racks                                      located along hot aisle.
R
R
A
A                                                              •Under the raised floor,
U
                                         Hot aisles
U                                                              cables are routed along


                                                      Elect.
                                                      Elect.
             UPS
             UPS            UPS
                            UPS          UPS
                                         UPS                   hot aisles to prevent
                                                               obstruction to
                                                               incoming cold air.
MDA
MDA   Operating Console
      Operating Console

                                                        .
                                                     Separate comms
C
C
                                                     and electrical
R
R         Reserved for future racks
          Reserved for future racks                  cables where
A
A                                                    possible
U
U
                racks
                racks
                                                     Opposite ends of
                                                     room
C
C               racks
                racks                                Top and bottom entry
R
R
A
A
U
U



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
MDA
MDA        Operating Console
           Operating Console
                                                               Maintenance space
                                                               Suggested 1m
C
C
                                                               clearance in front &
R
                                                               behind racks
R              Reserved for future racks
               Reserved for future racks
A
A                                                              Suggested 1.5m bend
U
U                  Minimum 1m
                   Minimum 1m                                  radius around access
                                                               corners
                     racks
                     racks
Min.1.5m
Min.1.5m                                                       Consider depth of your
 radius
 radius            Minimum 1m
                   Minimum 1m                    Min.1.5m
                                                               deepest equipment
                                                 Min.1.5m
                                                  radius
                                                  radius
C
C                    racks
                     racks
                                                               Floor loading
R
R                                                              Loading depends on
A
A                    Minimum 1m                                weight of equipment
                     Minimum 1m
U
U
                                                               Recommended for


                                                      Elect.
                                                      Elect.
               UPS
               UPS           UPS
                             UPS           UPS
                                           UPS                 CR = 7.2kPa min.
                                                               High traffic Areas =
                                                               CR loading +50%
MDA
MDA    Operating Console
       Operating Console




C
C                                                     If operating
R
R          Reserved for future racks
           Reserved for future racks                  Console needs to be
A
A            Possible
U
U
                                                      in computer room,
      Maintenance / MAC
             racks
             racks

           Work Area                                  Near entrance for easy
                                                      access & escape
C
C                racks
                 racks                                Not affected by any
R
R
A                                                     maintenance / MAC
A
U
U                                                     work



                                             Elect.
                                             Elect.
           UPS
           UPS           UPS
                         UPS           UPS
                                       UPS
MDA
MDA   Operating Console
      Operating Console


                                                     Vision panel
C
C                                                    •showcase data center.
R
R         Reserved for future racks
          Reserved for future racks
A
A                                                    •Security issue.
U
U
                                                         •Reinforced glass.
                racks
                racks




C
C               racks
                racks
R
R
A
A
U
U



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
FM200 cylinders
                                            FM200 cylinders
MDA
MDA   Operating Console
      Operating Console




C
C
R
R         Reserved for future racks
          Reserved for future racks
                                                                 Minimise items
A
A                                                                inside computer
U
U                                                                room
                racks
                racks


                                                                 FM200 cylinders
C
C               racks
                racks
R
                                                                 UPS batteries
R
A
A                                                                Operating console
U
U



                                                        Elect.
                                                        Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
                                        Batteries
                                        Batteries
MDA
MDA   Operating Console
      Operating Console                              CCTV camera
                                                     At entrance
                                                     •with people counter
C
C                                                    functionality
R
R         Reserved for future racks
          Reserved for future racks
A
A                                                    •complements log
U
U                                                    book
                racks
                racks

                                                     at aisles
C
C               racks
                racks                                •monitor access to
R
R                                                    equipment
A
A
U
U



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
MDA
MDA   Operating Console
      Operating Console




C
C
R
R         Reserved for future racks
          Reserved for future racks
A
A                                                    Access control
U
U
                                                     At least 2 forms of
                racks
                racks
                                                     recognition
                                                     •what you know
C
C               racks
                racks                                •who you are
R
R
A
A                                                    •what you have
U
U



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
                                                     2 levels access control
                                                     prevents tailgating.
MDA
MDA   Operating Console
      Operating Console



                                                     Risers
C
C
R
R         Reserved for future racks
          Reserved for future racks                  •accessible from outside
A
A
U
                                                     •must be locked
U
                racks
                racks
                                                     •remotely monitored
                                                     preferred


C
C               racks
                racks
R
R
A
A
U
U



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS
Structured vs. Unstructured
     Cabling Solutions
MDA.
MDA.   Operating Console
       Operating Console
                                                      Distribution Area
                                                      •Main distribution

C
C                                                     •Top of rack
R
R          Reserved for future racks
           Reserved for future racks
                                                      •central cross connect to
A
A
U
                                                      all cabinets in the
U
                                                      computer room
                 racks
                 racks
                                                      •no. of cables depend on
                                                      equipment housed in the
                                                      racks.
C
C                racks
                 racks
R
R                                                     •24 UTP ports/rack
A
A
U
U                                                     •6 LC fiber ports per



                                             Elect.
                                                      rack


                                             Elect.
           UPS
           UPS           UPS
                         UPS           UPS
                                       UPS
STRUCTURED VS. UNSTRUCTURED
              CABLING SOLUTIONS
               The cabling starts with a few connections . . .
Server            Changes made at active equipment
racks             • adding cables = accidental pulling adjacent cables
                  • pulling of cables = longer installation times
                  • Mess under the floor = poor air flow
                  • Long patchcords = long lead times

                                                     Storage


Switch racks
STRUCTURED VS. UNSTRUCTURED
             CABLING SOLUTIONS
                                   The alternative...
Server rack

               DISTRIBUTION AREA

                   Server Ports



                                       Storage
                   Switch Ports

Switch rack

                   Storage Ports
Typical Data center



                      Backbone
                       cabling




                      Horizontal
                       cabling
MDA
MDA    Operating Console
       Operating Console



                                                       Distribution Area
C
C
R
R           Reserved for future racks
            Reserved for future racks                  •Horizontal distribution
A
A                                                      area
U
U
                                                       •End of Row design


      HDA
      HDA
C
C
R
R
A
A
U
U



                                              Elect.
                                              Elect.
            UPS
            UPS          UPS
                         UPS            UPS
                                        UPS
MDA
MDA   Operating Console
      Operating Console

                                                         Distribution Area
                                                         •Zone distribution area
C
C
R
R         Reserved for future racks
          Reserved for future racks
A
A
U
U                                       Hot aisle

                                                         what’s wrong with this
                  ZDA
                  ZDA                   Cold aisle picture?
C
C
R
R
A
A                                                         Cabling should be
U
U                                                         routed in hot aisle to


                                                Elect.
                                                Elect.
          UPS
          UPS          UPS
                       UPS            UPS
                                      UPS                 prevent obstruction
                                                          to air flow
Zone cabling boxes
Ceiling boxes     Raised floor boxes
MDA
MDA   Operating Console
      Operating Console
                                                     CREMS
                                                     Computer
C
C                                                    Room
R
R         Reserved for future racks
          Reserved for future racks
A
A
                                                     Environmental
U
U                                                    Monitoring
                racks
                racks
                                                     System
                                                     •power
                                                     •humidity
C
C               racks
                racks
R
R                                                    •temperature
A
A
U
U                                                    •airflow



                                            Elect.
                                            Elect.
          UPS
          UPS           UPS
                        UPS           UPS
                                      UPS            •sound
Final design
Comms.
Comms.
                     Cold aisles
C
C            MDA
             MDA         Reserved for future racks
                         Reserved for future racks
R
R
A
A                    Hot aisles




                                                                            Operating Console
                                                                            Operating Console
                                                                            Operating Console
                                                                             Operating Console
U
U
                           racks
                           racks

                      Cold aisles
C
C                          racks
                           racks
R
R




                                                                          FM200 cylinders
                                                                          FM200 cylinders
A
A
U
U                    Hot aisles
                                                              Batteries
                                                              Batteries




                                                     Elect.
                                                     Elect.
                    UPS
                    UPS            UPS
                                   UPS         UPS
                                               UPS


Ramp / Console areas outside CR
Separate support Area.
2 security points before entering CR
Security
  Access Control                       IP CCTV




Card & Numerical pad
    access control
                                      IP CCTV - fixed




Iris scan access control          IP CCTV - Pan/Tilt/Zoom
FINAL DESIGN
Final design
Comms.
Comms.



 C
 C            MDA
              MDA            Reserved for future racks
                             Reserved for future racks
 R
 R
 A
 A




                                                                                Operating Console
                                                                                Operating Console
 U
 U
                             racks
                             racks




C
C                            racks
                             racks
R
R




                                                                              FM200 cylinders
                                                                              FM200 cylinders
A
A
U
U                                                                 Batteries
                                                                  Batteries




                                                         Elect.
                                                         Elect.
                       UPS
                       UPS           UPS
                                     UPS         UPS
                                                 UPS


Separate comms. and electrical cables
Different ends of room.
Top and bottom entry
Final design
Comms.
Comms.



 C
 C            MDA
              MDA            Reserved for future racks
                             Reserved for future racks
 R
 R
 A
 A




                                                                                Operating Console
                                                                                Operating Console
 U
 U
                             racks
                             racks




C
C                            racks
                             racks
R
R




                                                                              FM200 cylinders
                                                                              FM200 cylinders
A
A
U
U                                                                 Batteries
                                                                  Batteries




                                                         Elect.
                                                         Elect.
                       UPS
                       UPS           UPS
                                     UPS         UPS
                                                 UPS


Separate comms. and electrical cables
Different ends of room.
Top and bottom entry
THANK YOU!

  Jeffrey Lam RCDD
Jeffrey.lam@anixter.com
     +65 97849870

Más contenido relacionado

Similar a Computer room design (revised)

Dc power plants for telecom and data
Dc power plants for telecom and dataDc power plants for telecom and data
Dc power plants for telecom and dataAnil Upadhyay
 
3 8 12 Overview Of New Products Pat
3 8 12 Overview Of New Products Pat3 8 12 Overview Of New Products Pat
3 8 12 Overview Of New Products Patcvoproductions
 
Introduction to automation ppt
Introduction to automation pptIntroduction to automation ppt
Introduction to automation pptHimani Harbola
 
Sy tech rios ai mobile command mobile command with workstations
Sy tech rios ai mobile command   mobile command with workstationsSy tech rios ai mobile command   mobile command with workstations
Sy tech rios ai mobile command mobile command with workstationsSyTech Corporation
 
2013 HERCO Corporate Profile
2013 HERCO Corporate Profile2013 HERCO Corporate Profile
2013 HERCO Corporate ProfileRajeev Handa
 
LDIC UNIT-1 2022-23 PART-1.pptx
LDIC UNIT-1 2022-23 PART-1.pptxLDIC UNIT-1 2022-23 PART-1.pptx
LDIC UNIT-1 2022-23 PART-1.pptxAnjaneyulu Naik
 
Essential Guide Power Supply & Transformers 2010
Essential Guide Power Supply & Transformers 2010Essential Guide Power Supply & Transformers 2010
Essential Guide Power Supply & Transformers 2010Gilbert Brault
 
Introduction To Sonalysts Engineering
Introduction To Sonalysts EngineeringIntroduction To Sonalysts Engineering
Introduction To Sonalysts EngineeringArmandHalter
 
FUTURA_CCCORPS_FERMI
FUTURA_CCCORPS_FERMIFUTURA_CCCORPS_FERMI
FUTURA_CCCORPS_FERMIKBR-AMCDE
 
Tank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haulTank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haulAsif Sheriff
 
Tank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haulTank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haulAsif Sheriff
 
9030 rps datasheet_gfk1920
9030 rps datasheet_gfk19209030 rps datasheet_gfk1920
9030 rps datasheet_gfk1920tokamaka
 
Low Power Design and Verification
Low Power Design and VerificationLow Power Design and Verification
Low Power Design and VerificationDVClub
 
Low power design-ver_26_mar08
Low power design-ver_26_mar08Low power design-ver_26_mar08
Low power design-ver_26_mar08Obsidian Software
 

Similar a Computer room design (revised) (20)

Dc power plants for telecom and data
Dc power plants for telecom and dataDc power plants for telecom and data
Dc power plants for telecom and data
 
3 8 12 Overview Of New Products Pat
3 8 12 Overview Of New Products Pat3 8 12 Overview Of New Products Pat
3 8 12 Overview Of New Products Pat
 
Presentation On Ips
Presentation On IpsPresentation On Ips
Presentation On Ips
 
Introduction to automation ppt
Introduction to automation pptIntroduction to automation ppt
Introduction to automation ppt
 
Sy tech rios ai mobile command mobile command with workstations
Sy tech rios ai mobile command   mobile command with workstationsSy tech rios ai mobile command   mobile command with workstations
Sy tech rios ai mobile command mobile command with workstations
 
2013 HERCO Corporate Profile
2013 HERCO Corporate Profile2013 HERCO Corporate Profile
2013 HERCO Corporate Profile
 
LDIC UNIT-1 2022-23 PART-1.pptx
LDIC UNIT-1 2022-23 PART-1.pptxLDIC UNIT-1 2022-23 PART-1.pptx
LDIC UNIT-1 2022-23 PART-1.pptx
 
Essential Guide Power Supply & Transformers 2010
Essential Guide Power Supply & Transformers 2010Essential Guide Power Supply & Transformers 2010
Essential Guide Power Supply & Transformers 2010
 
Introduction To Sonalysts Engineering
Introduction To Sonalysts EngineeringIntroduction To Sonalysts Engineering
Introduction To Sonalysts Engineering
 
How to choose a ups
How to choose a upsHow to choose a ups
How to choose a ups
 
How to choose a ups
How to choose a upsHow to choose a ups
How to choose a ups
 
FUTURA_CCCORPS_FERMI
FUTURA_CCCORPS_FERMIFUTURA_CCCORPS_FERMI
FUTURA_CCCORPS_FERMI
 
Tank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haulTank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haul
 
Tank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haulTank point and continuous level to base radio and back haul
Tank point and continuous level to base radio and back haul
 
Isis
IsisIsis
Isis
 
9030 rps datasheet_gfk1920
9030 rps datasheet_gfk19209030 rps datasheet_gfk1920
9030 rps datasheet_gfk1920
 
Shultz dallas q108
Shultz dallas q108Shultz dallas q108
Shultz dallas q108
 
Schulz dallas q1_2008
Schulz dallas q1_2008Schulz dallas q1_2008
Schulz dallas q1_2008
 
Low Power Design and Verification
Low Power Design and VerificationLow Power Design and Verification
Low Power Design and Verification
 
Low power design-ver_26_mar08
Low power design-ver_26_mar08Low power design-ver_26_mar08
Low power design-ver_26_mar08
 

Último

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 

Último (20)

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 

Computer room design (revised)

  • 1. DATA CENTER Computer Room Planning Jeffrey Lam RCDD
  • 2. What is a data center? Data Centers – “nerve centers” of the organisation – centralize & consolidate IT resources – support critical business operations. – provide uninterrupted service to mission critical applications • 7 x 24 x 365 availability • Power & network redundancy • Physical & network security • Environmental monitoring • Air-conditioning / thermal mgt • Fire suppression systems
  • 3. Different Tiers of data centers Data center space is precious, use it wisely.
  • 4. FM200 cylinders FM200 cylinders MDA MDA Operating Console Operating Console C C R R Reserved for future racks Reserved for future racks A A U U TYPICAL racks racks Computer Room C C racks racks R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS Batteries Batteries
  • 5. EIA/TIA 942 recommendations for computer room • Minimum height = 2.6m • Minimum door = 1m wide, 2.13m high • Minimum floor loading = 7.2kPa (distributed) • Recommended floor loading = 12kPa (distributed) • Dedicated air conditioning – temperature 20° to 25 °C – relative humidity 40% to 55% EIA/TIA 569 recommendations for equipment room • Lighting – 500 lux measured 1 m above finished floor – Install light fixtures 2.6 m above floor • Local disaster regulations – seismic rating
  • 6. Batteries Batteries Elect. Elect. Operating Console Operating Console Group your equipment into C C zones R R Reserved for future racks Reserved for future racks A power required A U U •heat generated LAN / WAN / routers •amount & type of switches & security cables •maintenance C C SAN / applications/ R R A A storage server U U Elect. Elect. UPS UPS UPS UPS UPS UPS Lower power & cooling Highest power & cooling
  • 7. MDA MDA Operating Console Operating Console Group your equipment into C C zones R R SINGAPORE INDONESIA MALAYSIA A THALAND A Consider ease of U LAN & U WAN operation Spread out the power / cooling C requirements C R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 8. MDA MDA Operating Console Operating Console Ramp to bring equipment up onto C C raised floors. R R Reserved for future racks Reserved for future racks A A Suggested slope 1:12 U U Suggested width 1.8m racks racks (but consider the width of your largest piece of equipment) C C racks racks R R A A U U Barriers / handrails Elect. Elect. UPS UPS UPS UPS UPS UPS for safety purposes. Suggested height >0.8m
  • 9. MDA MDA Operating Console Operating Console Allow space for C C expansion R R Reserved for future racks Reserved for future racks A A U U Near entrance for easy install where racks racks possible. C C racks racks R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 10. MDA MDA Operating Console Operating Console Cold aisles Hot & Cold aisles C C •Cold air directed to R R Reserved for future racks Reserved for future racks cold aisles through A A raised floors. U U Hot aisles •Hot air return through racks racks ceiling space Cold aisles •Computer Room Air handling units (CRAU) C C racks racks located along hot aisle. R R A A •Under the raised floor, U Hot aisles U cables are routed along Elect. Elect. UPS UPS UPS UPS UPS UPS hot aisles to prevent obstruction to incoming cold air.
  • 11. MDA MDA Operating Console Operating Console . Separate comms C C and electrical R R Reserved for future racks Reserved for future racks cables where A A possible U U racks racks Opposite ends of room C C racks racks Top and bottom entry R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 12. MDA MDA Operating Console Operating Console Maintenance space Suggested 1m C C clearance in front & R behind racks R Reserved for future racks Reserved for future racks A A Suggested 1.5m bend U U Minimum 1m Minimum 1m radius around access corners racks racks Min.1.5m Min.1.5m Consider depth of your radius radius Minimum 1m Minimum 1m Min.1.5m deepest equipment Min.1.5m radius radius C C racks racks Floor loading R R Loading depends on A A Minimum 1m weight of equipment Minimum 1m U U Recommended for Elect. Elect. UPS UPS UPS UPS UPS UPS CR = 7.2kPa min. High traffic Areas = CR loading +50%
  • 13. MDA MDA Operating Console Operating Console C C If operating R R Reserved for future racks Reserved for future racks Console needs to be A A Possible U U in computer room, Maintenance / MAC racks racks Work Area Near entrance for easy access & escape C C racks racks Not affected by any R R A maintenance / MAC A U U work Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 14. MDA MDA Operating Console Operating Console Vision panel C C •showcase data center. R R Reserved for future racks Reserved for future racks A A •Security issue. U U •Reinforced glass. racks racks C C racks racks R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 15. FM200 cylinders FM200 cylinders MDA MDA Operating Console Operating Console C C R R Reserved for future racks Reserved for future racks Minimise items A A inside computer U U room racks racks FM200 cylinders C C racks racks R UPS batteries R A A Operating console U U Elect. Elect. UPS UPS UPS UPS UPS UPS Batteries Batteries
  • 16. MDA MDA Operating Console Operating Console CCTV camera At entrance •with people counter C C functionality R R Reserved for future racks Reserved for future racks A A •complements log U U book racks racks at aisles C C racks racks •monitor access to R R equipment A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 17. MDA MDA Operating Console Operating Console C C R R Reserved for future racks Reserved for future racks A A Access control U U At least 2 forms of racks racks recognition •what you know C C racks racks •who you are R R A A •what you have U U Elect. Elect. UPS UPS UPS UPS UPS UPS 2 levels access control prevents tailgating.
  • 18. MDA MDA Operating Console Operating Console Risers C C R R Reserved for future racks Reserved for future racks •accessible from outside A A U •must be locked U racks racks •remotely monitored preferred C C racks racks R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 19. Structured vs. Unstructured Cabling Solutions
  • 20. MDA. MDA. Operating Console Operating Console Distribution Area •Main distribution C C •Top of rack R R Reserved for future racks Reserved for future racks •central cross connect to A A U all cabinets in the U computer room racks racks •no. of cables depend on equipment housed in the racks. C C racks racks R R •24 UTP ports/rack A A U U •6 LC fiber ports per Elect. rack Elect. UPS UPS UPS UPS UPS UPS
  • 21. STRUCTURED VS. UNSTRUCTURED CABLING SOLUTIONS The cabling starts with a few connections . . . Server Changes made at active equipment racks • adding cables = accidental pulling adjacent cables • pulling of cables = longer installation times • Mess under the floor = poor air flow • Long patchcords = long lead times Storage Switch racks
  • 22. STRUCTURED VS. UNSTRUCTURED CABLING SOLUTIONS The alternative... Server rack DISTRIBUTION AREA Server Ports Storage Switch Ports Switch rack Storage Ports
  • 23. Typical Data center Backbone cabling Horizontal cabling
  • 24. MDA MDA Operating Console Operating Console Distribution Area C C R R Reserved for future racks Reserved for future racks •Horizontal distribution A A area U U •End of Row design HDA HDA C C R R A A U U Elect. Elect. UPS UPS UPS UPS UPS UPS
  • 25. MDA MDA Operating Console Operating Console Distribution Area •Zone distribution area C C R R Reserved for future racks Reserved for future racks A A U U Hot aisle what’s wrong with this ZDA ZDA Cold aisle picture? C C R R A A Cabling should be U U routed in hot aisle to Elect. Elect. UPS UPS UPS UPS UPS UPS prevent obstruction to air flow
  • 26. Zone cabling boxes Ceiling boxes Raised floor boxes
  • 27. MDA MDA Operating Console Operating Console CREMS Computer C C Room R R Reserved for future racks Reserved for future racks A A Environmental U U Monitoring racks racks System •power •humidity C C racks racks R R •temperature A A U U •airflow Elect. Elect. UPS UPS UPS UPS UPS UPS •sound
  • 28. Final design Comms. Comms. Cold aisles C C MDA MDA Reserved for future racks Reserved for future racks R R A A Hot aisles Operating Console Operating Console Operating Console Operating Console U U racks racks Cold aisles C C racks racks R R FM200 cylinders FM200 cylinders A A U U Hot aisles Batteries Batteries Elect. Elect. UPS UPS UPS UPS UPS UPS Ramp / Console areas outside CR Separate support Area. 2 security points before entering CR
  • 29. Security Access Control IP CCTV Card & Numerical pad access control IP CCTV - fixed Iris scan access control IP CCTV - Pan/Tilt/Zoom
  • 31. Final design Comms. Comms. C C MDA MDA Reserved for future racks Reserved for future racks R R A A Operating Console Operating Console U U racks racks C C racks racks R R FM200 cylinders FM200 cylinders A A U U Batteries Batteries Elect. Elect. UPS UPS UPS UPS UPS UPS Separate comms. and electrical cables Different ends of room. Top and bottom entry
  • 32. Final design Comms. Comms. C C MDA MDA Reserved for future racks Reserved for future racks R R A A Operating Console Operating Console U U racks racks C C racks racks R R FM200 cylinders FM200 cylinders A A U U Batteries Batteries Elect. Elect. UPS UPS UPS UPS UPS UPS Separate comms. and electrical cables Different ends of room. Top and bottom entry
  • 33. THANK YOU! Jeffrey Lam RCDD Jeffrey.lam@anixter.com +65 97849870