Odoo Experience 2015
Project Management with the lights on:
Earned Value Management using Odoo
Jordi Ballester Alomar (Eficent)
Project management about Deming’s Cycle
Earned Value Management
2
Identifying patterns and trends…
….is something humans are quite good at.
And patterns and trends in the past can be good predictors of the
future.
Earned Value Management
3
Earned Value Management (EVM) attempts to answer to the
following questions:
...are we ahead or behind schedule?
...how efficiently are we using our time?
...when is the project likely to be completed?
...are we currently over or under our budget?
...how efficiently are we using our resources?
...what is the remaining work likely to cost?
...what is the entire project likely to cost?
...how much will we be under or over budget at the end?
Earned Value Management
4
Patterns and trends will help to identify:
● Where problems are occurring
● Whether problems are critical or not
● What will it take to get the project back on track
Earned Value Management
5
… or go back to the usual
divination techniques.
6
Work Plan
Earned Value Management
7
8
Basic Elements
9
Planned Value
1
Planned Value describes how far along project work is supposed
to be at any given point in the project schedule.
Constitutes the Performance Measurement Baseline
Earned Value Management
10
Budget at
Completion
Planned Value
11
Earned Value
2
Earned Value is a snapshot of the work progress at a given point
of time. Reflects the amount of work that has actually been
accomplished to date, expressed as the planned value for that
work.
Earned Value Management
12
Planned Value
Earned Value
13
Actual Cost
3
Actual Cost is an indication of the level of resources that have
been expended to achieve the actual work performed to date.
Earned Value Management
14
Planned Value
Earned Value
Actual Cost
15
Performance
Measurement
Work performance is measured periodically, such as weekly or
monthly.
Discrete efforts that span one to two periods are often measured
with fixed formula techniques (0-100, 50-50,..)
Discrete efforts of longer duration (greater than two periods) are
measured with other techniques, including those known as
weighted milestone and percent complete.
Earned Value Management
16
Mapping the % complete to project stages allows to implement
fixed formula or percent complete.
Earned Value Management
17
18
Performance
Analysis and
Forecasting
Earned Value Management
19
20
Schedule
1
Schedule Variance determines whether the Project is ahead or
behind schedule.
Earned Value Management
21
Schedule
Variance
Time
now
Time behind
SV = EV - PV
Earned Value Management
22
Schedule Variance (Are we ahead or behind schedule?)
SV = EV - PV
Schedule Performance Index (How efficiently are we using
time?)
Earned Value Management
23
SPI = EV / PV
24
Cost
2
Cost Variance (Are we under or over our budget?)
Earned Value Management
25
Time
now
Cost
Variance
CV = EV - AC
Cost Variance (CV)
Earned Value Management
26
CV = EV - AC
Cost Performance Index (How efficiently are we using our
resources?)
Earned Value Management
27
CPI = EV / AC
To-Complete Performance Index (How efficiently must we
use our remaining resources?)
Earned Value Management
28
TCPI = (BAC - EV) / (BAC - AC)
Estimate at Completion (What is the project likely to cost?)
Earned Value Management
29
EAC = BAC / CPI
Variance at Completion (Will we be under or over budget?)
Earned Value Management
30
VAC = BAC - EAC
Estimate to Complete (What will the remaining work cost?)
Earned Value Management
31
ETC = (BAC - EV) / CPI
32
Guidance for use
of key EVM
Practices
33
Establish a
Performance
Measurement
Baseline
1
● Decompose the work to a manageable level
● Assign unambiguous management responsibility
● Develop time-phased budget for each work task
● Select the appropriate Earned Value Measurement
Technique
● Maintain Integrity of Performance Measurement Baseline
Earned Value Management
34
35
Measure and
analyze
performance
against the
Baseline
2
● Record resource usage during project execution
● Objectively Measure the Physical Work Progress
● Credit Earned Value according to Earned Value
Techniques
● Analyze and Forecast cost/schedule performance
● Report performance problems and/or take action
Earned Value Management
36
Find the module: project_earned_value_task in: https://github.com/Eficent/project-
earned-value
Thanks to
37
Jordi Ballester Alomar
Email: jordi.ballester@eficent.com
Twitter: @jbeficent_erp
Website: www.eficent.com

Más contenido relacionado

La actualidad más candente

Portfolio Schedule Execution Metrics
Portfolio Schedule Execution MetricsPortfolio Schedule Execution Metrics
Portfolio Schedule Execution Metrics
Daniel Castro
 
Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
Mayur Rahangdale
 
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
(New) mkt 571 mkt571 final exam entire answers with questions correct  100%(New) mkt 571 mkt571 final exam entire answers with questions correct  100%
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
twiter343r
 

La actualidad más candente (17)

Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
 
Portfolio Schedule Execution Metrics
Portfolio Schedule Execution MetricsPortfolio Schedule Execution Metrics
Portfolio Schedule Execution Metrics
 
Mg6088 spm unit-3
Mg6088 spm unit-3Mg6088 spm unit-3
Mg6088 spm unit-3
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Value management presentation
Value management presentationValue management presentation
Value management presentation
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Pm0011 project planning and scheduling (1)
Pm0011 project planning and scheduling (1)Pm0011 project planning and scheduling (1)
Pm0011 project planning and scheduling (1)
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Melbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd published
 
Mba semester 2 mb0049
Mba semester 2 mb0049Mba semester 2 mb0049
Mba semester 2 mb0049
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Cost management
Cost managementCost management
Cost management
 
Project monitoring activity
Project monitoring activityProject monitoring activity
Project monitoring activity
 
Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
 
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
(New) mkt 571 mkt571 final exam entire answers with questions correct  100%(New) mkt 571 mkt571 final exam entire answers with questions correct  100%
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
 

Similar a Odoo experience 2015 earned value management

L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
Shraddha PMP
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 

Similar a Odoo experience 2015 earned value management (20)

Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
Earned value
Earned valueEarned value
Earned value
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
formation.docx
formation.docxformation.docx
formation.docx
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
unit_-_3.ppt
unit_-_3.pptunit_-_3.ppt
unit_-_3.ppt
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
CONTROLLING.pptx
CONTROLLING.pptxCONTROLLING.pptx
CONTROLLING.pptx
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Evm power point january 2017
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017
 

Último

Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
vineshkumarsajnani12
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 

Último (20)

SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 

Odoo experience 2015 earned value management

  • 1. 1 Odoo Experience 2015 Project Management with the lights on: Earned Value Management using Odoo Jordi Ballester Alomar (Eficent)
  • 2. Project management about Deming’s Cycle Earned Value Management 2
  • 3. Identifying patterns and trends… ….is something humans are quite good at. And patterns and trends in the past can be good predictors of the future. Earned Value Management 3
  • 4. Earned Value Management (EVM) attempts to answer to the following questions: ...are we ahead or behind schedule? ...how efficiently are we using our time? ...when is the project likely to be completed? ...are we currently over or under our budget? ...how efficiently are we using our resources? ...what is the remaining work likely to cost? ...what is the entire project likely to cost? ...how much will we be under or over budget at the end? Earned Value Management 4
  • 5. Patterns and trends will help to identify: ● Where problems are occurring ● Whether problems are critical or not ● What will it take to get the project back on track Earned Value Management 5 … or go back to the usual divination techniques.
  • 10. Planned Value describes how far along project work is supposed to be at any given point in the project schedule. Constitutes the Performance Measurement Baseline Earned Value Management 10 Budget at Completion Planned Value
  • 12. Earned Value is a snapshot of the work progress at a given point of time. Reflects the amount of work that has actually been accomplished to date, expressed as the planned value for that work. Earned Value Management 12 Planned Value Earned Value
  • 14. Actual Cost is an indication of the level of resources that have been expended to achieve the actual work performed to date. Earned Value Management 14 Planned Value Earned Value Actual Cost
  • 16. Work performance is measured periodically, such as weekly or monthly. Discrete efforts that span one to two periods are often measured with fixed formula techniques (0-100, 50-50,..) Discrete efforts of longer duration (greater than two periods) are measured with other techniques, including those known as weighted milestone and percent complete. Earned Value Management 16
  • 17. Mapping the % complete to project stages allows to implement fixed formula or percent complete. Earned Value Management 17
  • 21. Schedule Variance determines whether the Project is ahead or behind schedule. Earned Value Management 21 Schedule Variance Time now Time behind SV = EV - PV
  • 22. Earned Value Management 22 Schedule Variance (Are we ahead or behind schedule?) SV = EV - PV
  • 23. Schedule Performance Index (How efficiently are we using time?) Earned Value Management 23 SPI = EV / PV
  • 25. Cost Variance (Are we under or over our budget?) Earned Value Management 25 Time now Cost Variance CV = EV - AC
  • 26. Cost Variance (CV) Earned Value Management 26 CV = EV - AC
  • 27. Cost Performance Index (How efficiently are we using our resources?) Earned Value Management 27 CPI = EV / AC
  • 28. To-Complete Performance Index (How efficiently must we use our remaining resources?) Earned Value Management 28 TCPI = (BAC - EV) / (BAC - AC)
  • 29. Estimate at Completion (What is the project likely to cost?) Earned Value Management 29 EAC = BAC / CPI
  • 30. Variance at Completion (Will we be under or over budget?) Earned Value Management 30 VAC = BAC - EAC
  • 31. Estimate to Complete (What will the remaining work cost?) Earned Value Management 31 ETC = (BAC - EV) / CPI
  • 32. 32 Guidance for use of key EVM Practices
  • 34. ● Decompose the work to a manageable level ● Assign unambiguous management responsibility ● Develop time-phased budget for each work task ● Select the appropriate Earned Value Measurement Technique ● Maintain Integrity of Performance Measurement Baseline Earned Value Management 34
  • 36. ● Record resource usage during project execution ● Objectively Measure the Physical Work Progress ● Credit Earned Value according to Earned Value Techniques ● Analyze and Forecast cost/schedule performance ● Report performance problems and/or take action Earned Value Management 36
  • 37. Find the module: project_earned_value_task in: https://github.com/Eficent/project- earned-value Thanks to 37 Jordi Ballester Alomar Email: jordi.ballester@eficent.com Twitter: @jbeficent_erp Website: www.eficent.com