Utility Infrastructure of Lahore City
(Stormwater Drainage)
Engr. Wasif Ali
B.Sc. (Civil Engineering)
M.Sc. (Environmental Engineering)
The Lahore Project
Working Session
Presentation Outline
 Existing Scenario
 Stormwater Management Techniques
 Case Study…… Mohlanwal Area
 Design & Analysis of Stormwater Systems
 Conclusions & Recommendations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Existing Scenario
 Frequent and Widespread Stormwater Flooding
 Unplanned Development Pattern
 Water Table Decline
 Limited Space & Funds for Drainage
 Poor Assessment of Existing Drainage facilities
 Authorities are in mode of crisis
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Existing Scenario
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Existing Scenario
 Groundwater Decline
Sr.
No
Location
Water Level below NSL (ft) Avg.
Decline
(ft/yr)Year Feet Year Feet
1 A-Block Gulberg 1977 40.75 2000 87.74 2.04
2 Nawan Kot Police Station 1981 30.83 2000 66.22 1.86
3 Takkia Lehri Shah 1978 33.75 2000 86.92 2.41
4 Singh Pura 1981 45.40 2000 86.59 2.16
5 Rehman Pura 1987 58.71 2000 94.46 2.75
6 Masti gate 1987 46.08 2000 85.11 3.00
8 Masoom Gunj 1987 26.57 2000 70.81 3.40
9 Avari Hotel 1987 70.68 2000 107.45 2.83
10 Jia Musa 1987 25.65 2000 37.72 0.93
Source: Integrated Master Plan of Lahore for 2021, NESPAKThe Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Existing Scenario
 Design Rainfall Distribution Curve for Lahore (1953-2005)
Source: Pilot Balloon Observatory (PBO) LahoreThe Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Existing Scenario
 Rainfall Distribution
Source: Pilot Balloon Observatory (PBO) LahoreThe Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Stormwater Management Techniques
 Conventional Techniques
☼ Rapid Removal of Water
☼ Reactive Approach
☼ Increased Flooding
☼ Increased Erosion and Pollution
☼ Reduced Aquifer Recharge
☼ Complex Pipe Network
☼ Expensive
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Stormwater Management Techniques
 Alternative Techniques
☼ Nomenclature
☼ BMPs… Best Management Practices
☼ SUDS… Sustainable Urban Drainage Systems
☼ USM… Urban Stormwater Management
☼ Localized Stagnation
☼ Lesser Erosion & Pollutant Loads
☼ Aquifer Recharging
☼ Flexible Network
☼ Proactive Approach
☼ Economical
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Best Management Practices (BMPs)
 Green Roofs
 Rooftop Runoff Controls
 Bioretention / Recharge Garden
 Dry Well / Seepage Pit
 Pervious Pavements
 Vegetated Swale
 Infiltration Trench
 Infiltration basin
 Wet Pond / Retention Basin
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Green Roofs
 Reduced & Delayed Runoff
 (up to 70% peak reduction)
 Insulation of Buildings
 Lower Energy Consumption
 Habitat for Birds and Insects
 Reduced Carbon Dioxide levels
 Higher Cost
 Leakage
 Harsh Conditions for Vegetation
 Higher Maintenance
Benefits
Limitations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Rooftop Runoff Control
Benefits
Limitations  Limited Suitability for small houses
 Requires Proper Maintenance
 Pumping Cost may involve if sub surface storage
is provided
 Irrigation of Landscaped areas & Gardens
 Firefighting Storage
 (Building like WAPDA house, School etc)
 Reduced Peak Volume of Stormwater
 Reuse for Grey Water….i.e. flushing toilets.
 Reuse for Athletic Field Irrigation
 Cost Savings during Summer
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Rooftop Runoff Control
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Bioretention/Rain Garden
Limitations  Regular Inspection
 Rain Gardens may Require Watering in dry season
 Reduce Runoff Volume
 Filter Pollutants
 Recharge Groundwater
 Enhance Aesthetics
 Provide Habitat
Benefits
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Bioretention/Rain Garden
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Dry Well/Seepage Pit
 2’ Separation to Bedrock and Water Table
 Min. 10’ distance from Foundation
 Overflow Outlet for Large Storms
 Min. One Observation Well.
 Maximum Drain-Down Time is 72 hours
Imp.
Features
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Pervious Pavements
Limitations
 Higher Construction and
Maintenance Costs
 Depends on Infiltration Rates of
Underlying Soils
 Less Durable
 Good for impervious areas
 Reduces runoff
 Increased infiltration
 Healthier vegetation
Benefits
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Pervious Pavements
Variations
1) Pervious Bituminous Asphalt
2) Porous Concrete 3) Pervious Pavers BlocksThe Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Vegetated Swale
Imp.
Features
 Significantly slow the rate of runoff
conveyance compared to pipes
 Attenuation & Infiltration of runoff
 Pollutants Removal
 Longitudinal slope = 1 to 6%
 Check Dams for steeper slopes
 Side slope = 3:1 to 5:1
 Bottom width = 2 to 8 ft
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Vegetated Swale
1) Vegetated Swale with Infiltration Trench
3) Swale with Check Dams2) Grassed SwaleThe Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Infiltration Trench
Benefits
Limitations
 Ground Water Recharging
 Stormwater Treatment
 Good for Small Sites with
Porous Soils
 Groundwater Contamination
 High Clogging Potential
 Significant Setback Requirements
 Geotechnical Testing Required
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Infiltration Basin
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Infiltration Basin
 100% Reduction in the Load Discharged to
Surface Waters
 Approximation of Pre-Development Hydrology
 Channel Erosion Control
 Not Appropriate for Industrial / Spill sites
 Not suitable on Fill-Sites or Steep Slopes
 Infiltration rate ≥ 0.5 and ≤ 2.4 inch/hr
 Difficult to Restore once Clogged.
Benefits
Limitations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Wet Pond/Retention Basin
 Wildlife and Wetlands Habitat
 Aesthetic & Recreational Value
 Public Amenity when integrated
into a Park
 Water Quality Improvement
 Public Safety Concern
 Mosquito Breeding
 Cannot be Placed on steep slopes
Benefits
Limitations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Study Area
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Study Area
Master Plan
of the
Mohlanwal
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Study Area
 Building Bye-Laws
 LDA Land-Use Distribution for New Schemes
Sr.# Land Use Area Requirement
1 Open Spaces / Parks Not less than 7% of Total Scheme Area
2 Graveyard Not less than 2% of Total Scheme Area
3 Commercial Area Not more than 5% of Total Scheme Area
4 Public Buildings 2 to 10 %
 LDA Bye-Laws for Open Areas in Residential Units
Category
Area (Sft) Deduct
Car Porch
& Drive
Way
(Sft)
Net
Open
Area
(Sft)
%age
of
Open
AreaPlot
Open
Front Side Rear Total
2-kanal 9,000 1,500 1,800 750 4,050 600 3,450 38.3
1-Kanal 4,500 500 365 350 1,215 300 915 20.3
10-Marla 2,250 350 235 245 830 300 530 23.6
5-Marla 1,125 125 0 125 250 0 250 22.2The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
☼ Stormwater Systems
 Conventional Techniques
 Partially Combined Sewer System (Model #1)
 Separate Storm Sewer System (Model #2)
 Alternative Techniques
 Storm Sewer System with Park Storage (Model #3)
 Storm Sewer System with Park & Lawn storage (Model #4)
☼ Analysis / Design Tool
 Storm Water management Module (SWMM)
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
Model
#
1 & 2
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
☼ Summary of Node Flooding
Node Type
2-Yrs 5-Yrs 10-Yrs
Total
Flooding
(acre-in)
Total
Minutes
Flooded
Total
Flooding
(acre-in)
Total
Minutes
Flooded
Total
Flooding
(acre-in)
Total
Minutes
Flooded
J1 Junction 15.59 364 34.98 384 48.57 393
J2 Junction 5.05 71 23.68 218 43.85 355
J3 Junction 0.01 0 0.01 0 2.81 48
J4 Junction 0 0 0.01 0 0.70 30
J5 Junction 8.79 372 15.31 393 20.36 402
J6 Junction 29.19 364 57.46 384 76.84 393
J7 Junction 5.04 121 18.61 354 31.39 363
J8 Junction 0.00 1 4.62 63 8.65 83
J9 Junction 10.09 374 18.29 399 25.46 412
J10 Junction 10.95 352 29.65 372 43.84 384
J11 Junction 21.67 362 51.63 380 75.32 387
J12 Junction 0 0 0 0 0.00 1
J13 Junction 0 0 0 0 0.00 0
J14 Junction 0 0 0 0 0 0
O1 Outfall 0 0 0 0 0 0
Model # 1
Partially
Combined
Sewer
System
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
☼ Summary of Links
Link Type
Diameter
(inch)
Link Type
Diameter
(inch)
C1 Circular 9 C8 Circular 9
C2 Circular 15 C9 Circular 12
C3 Circular 24 C10 Circular 18
C4 Circular 24 C11 Circular 12
C5 Circular 9 C12 Circular 24
C6 Circular 12 C13 Circular 24
C7 Circular 15 C14 Circular 27
Model # 1
Partially
Combined
Sewer
System
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
Model # 3
Storm
Sewer
System
With
Park
Storage
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
Model # 4
Storm
Sewer
System
With
Park &
Lawn
Storage
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
☼ Evaluation of different Models
 Flooding
Velocity
%age Peak Domestic flow as Stormwater Allowance
Provided as per
WASA Criteria
Required as per SWMM Analysis
Return Period
fps 2-Yrs 5-Yrs 10-Yrs
2.0 100 345 635 1000
2.5 100 460 825 1275
3.0 100 570 1005 1550
Comparison of Stormwater Allowance for different Frequencies
 Length-weighted Diameter {(D1xL1+D2L2+……..DnLn) / ΣLn}
 Cost of the System
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Design & Analysis
of Stormwater Systems
Type of
Stormwater System
Length-weighted Diameter
(inch)
Cost
(Millions Rs.)
2-Yrs 5-Yrs 10-Yrs 2-Yrs 5-Yrs 10-Yrs
Combined System 16 16 16 2.6 2.6 2.6
Separate System 34 45 52 6.7 11.0 14.7
Storm Sewer with Park
Storage
16 22 26 2.9 4.4 5.5
Storm Sewer with Park
and Lawn Storage
09 16 19 1.5 2.9 3.5
 Summary of the Network Sizing & Cost
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Conclusions & Recommendations
1) Mean average decline in ground water table of Lahore comes to be
2.03 ft/yr which clearly shows the need to implement the alternative
storm water techniques instead of conventional techniques.
2) The “knee of curve” for Lahore is in the range of 0.60 to 1.00 inch of
rainfall hence BMPs will be most efficient and economical in Lahore
if they target the storm event having the value lesser than 1.0 inch.
3) The value of “Storm water Allowance”, as per WASA design criteria
is taken as 100% of peak domestic flow but this study shows that it
varies from 345% to 1000% for 2-yrs and 10-yrs return period
respectively. Hence the value suggested by WASA is of no use if
one is designing combined system for No-flooding condition.
☼ Conclusions
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
4) This study shows that ample reduction in conduit size can be achieved
by utilizing BMPs. For example the ultimate diameter for separate
sewer system are 42, 54 and 66 inch respectively for 2, 5 and 10 year
return period while using only two BMPs (i.e. Lawn Depression and
Park Storage) the ultimate diameters are 12, 21 and 24 inch for 2,5 and
10 year return period respectively.
5) Common misconception about the additional land requirement for any
storage facility can be wrecked by the results of this study that even
using the current open space regulation of LDA, 89% of peak flow
reduction can be achieved through BMPs.
Conclusions & Recommendations
☼ Conclusions
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
1) The rainfall data is a basic requirement for the analysis purposes.
Continuous recording of rainfall is required to develop a shorter time
interval for rain fall intensity curves. Presently most of the data is in 3-hr
interval form and only a limited record of continuous recording rain-
gages is available. It is strongly recommended that meteorological
department should make such arrangements that rainfall can be
recorded up to 5 minutes interval.
2) Main emphasis of the bye-laws in Lahore is on ventilation and sunlight
criteria. No provision is made in these bye-laws to meet the sustainable
drainage. Hence it is needed to develop such guidelines by which
sustainable development can be achieved.
Conclusions & Recommendations
☼ Recommendations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
3) Peak and quantity of the stormwater flow should be reduced by the
application of storage BMPs. Government agencies like WASA should
prepare a master drainage plan for all major drains (natural as well as
man-made) and a specific quantity and peak of flow should be allotted
to each and every section of these drains. A stormwater tax should be
imposed if society discharges any additional flow than that of allotted by
the competent authority like WASA.
4) The LDA should encourage the vertical growth so that more and more
space can be utilized for the BMPs. Constructed wetland, wet ponds
and many other storage facilities require a huge land area. It will not
only increase the ground water recharging but at the same time such
spaces can be utilized as recreational spot, walkways and children’s
play areas.
Conclusions & Recommendations
☼ Recommendations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
5) Most of the BMP techniques can only be implemented by the active
public participation hence educational and awareness campaigns
should be set up for local community groups. Electronic media can play
an important role in this regard.
6) Because of rapid urbanization, extensive and more frequent flooding
has been occurring in recent years and the continued use of
conventional techniques to stormwater management result in
municipalities becoming victims of their municipality’s development
success therefore it makes sense to implement the Alternative
techniques to stormwater management.
Conclusions & Recommendations
☼ Recommendations
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013
Questions & Answers
The Lahore Project
Working Session on
Utility Infrastructure
21 August 2013

Más contenido relacionado

Destacado

Environment Sector by Rafia Kamal for TLP
Environment Sector by Rafia Kamal for TLPEnvironment Sector by Rafia Kamal for TLP
Environment Sector by Rafia Kamal for TLPKKM Architects
 
Mapping for TLP (Land Sector) by Syed Ghulam Muhayyudin
Mapping for TLP (Land Sector) by Syed Ghulam MuhayyudinMapping for TLP (Land Sector) by Syed Ghulam Muhayyudin
Mapping for TLP (Land Sector) by Syed Ghulam MuhayyudinKKM Architects
 
Urban Planning: Mapping & Alternative Scenarios (TLP)
Urban Planning: Mapping & Alternative Scenarios (TLP)Urban Planning: Mapping & Alternative Scenarios (TLP)
Urban Planning: Mapping & Alternative Scenarios (TLP)KKM Architects
 
My museum without render model (1)
My museum without render model (1)My museum without render model (1)
My museum without render model (1)Muhammad Muhyuddin
 
Climate change presentation, department of city & regional planning uet lahor...
Climate change presentation, department of city & regional planning uet lahor...Climate change presentation, department of city & regional planning uet lahor...
Climate change presentation, department of city & regional planning uet lahor...Ammad baig
 
Dining Trends In Lahore
Dining Trends In LahoreDining Trends In Lahore
Dining Trends In LahoreAyesha Batool
 
2015 Strategic Directions: Smart Utility Report
2015 Strategic Directions: Smart Utility Report2015 Strategic Directions: Smart Utility Report
2015 Strategic Directions: Smart Utility ReportBlack & Veatch
 
Gtechnology / GElectric
Gtechnology / GElectricGtechnology / GElectric
Gtechnology / GElectricGilbert Madrid
 
King Edward Medical University KEMU Lahore Merit List 2013
King Edward Medical University KEMU Lahore Merit List 2013King Edward Medical University KEMU Lahore Merit List 2013
King Edward Medical University KEMU Lahore Merit List 2013medicalkidunya
 
Tasseled Cap transformation Technique in ArcGIS
Tasseled Cap transformation Technique in ArcGISTasseled Cap transformation Technique in ArcGIS
Tasseled Cap transformation Technique in ArcGISAtiqa khan
 
Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...Edge Hill University
 
Culture presentation TLP
Culture presentation TLPCulture presentation TLP
Culture presentation TLPKKM Architects
 
Multi-Utility Infrastructure Management
Multi-Utility Infrastructure Management Multi-Utility Infrastructure Management
Multi-Utility Infrastructure Management Gilbert Madrid
 
5th - Block 4 - Climate Factors
5th - Block 4 - Climate Factors5th - Block 4 - Climate Factors
5th - Block 4 - Climate FactorsMister Valverde
 
Shalimar gardens By Kamil Khan Mumtaz
Shalimar gardens By Kamil Khan MumtazShalimar gardens By Kamil Khan Mumtaz
Shalimar gardens By Kamil Khan MumtazKKM Architects
 

Destacado (20)

Environment Sector by Rafia Kamal for TLP
Environment Sector by Rafia Kamal for TLPEnvironment Sector by Rafia Kamal for TLP
Environment Sector by Rafia Kamal for TLP
 
Mapping for TLP (Land Sector) by Syed Ghulam Muhayyudin
Mapping for TLP (Land Sector) by Syed Ghulam MuhayyudinMapping for TLP (Land Sector) by Syed Ghulam Muhayyudin
Mapping for TLP (Land Sector) by Syed Ghulam Muhayyudin
 
Urban Planning: Mapping & Alternative Scenarios (TLP)
Urban Planning: Mapping & Alternative Scenarios (TLP)Urban Planning: Mapping & Alternative Scenarios (TLP)
Urban Planning: Mapping & Alternative Scenarios (TLP)
 
KAS_poster_final
KAS_poster_finalKAS_poster_final
KAS_poster_final
 
My museum without render model (1)
My museum without render model (1)My museum without render model (1)
My museum without render model (1)
 
Climate change presentation, department of city & regional planning uet lahor...
Climate change presentation, department of city & regional planning uet lahor...Climate change presentation, department of city & regional planning uet lahor...
Climate change presentation, department of city & regional planning uet lahor...
 
Dining Trends In Lahore
Dining Trends In LahoreDining Trends In Lahore
Dining Trends In Lahore
 
Portfolio
PortfolioPortfolio
Portfolio
 
2015 Strategic Directions: Smart Utility Report
2015 Strategic Directions: Smart Utility Report2015 Strategic Directions: Smart Utility Report
2015 Strategic Directions: Smart Utility Report
 
Gtechnology / GElectric
Gtechnology / GElectricGtechnology / GElectric
Gtechnology / GElectric
 
King Edward Medical University KEMU Lahore Merit List 2013
King Edward Medical University KEMU Lahore Merit List 2013King Edward Medical University KEMU Lahore Merit List 2013
King Edward Medical University KEMU Lahore Merit List 2013
 
The lahore project
The lahore projectThe lahore project
The lahore project
 
Tasseled Cap transformation Technique in ArcGIS
Tasseled Cap transformation Technique in ArcGISTasseled Cap transformation Technique in ArcGIS
Tasseled Cap transformation Technique in ArcGIS
 
Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...Plan for the Regeneration and Improvement of the area between Lower Mall and ...
Plan for the Regeneration and Improvement of the area between Lower Mall and ...
 
Culture presentation TLP
Culture presentation TLPCulture presentation TLP
Culture presentation TLP
 
Multi-Utility Infrastructure Management
Multi-Utility Infrastructure Management Multi-Utility Infrastructure Management
Multi-Utility Infrastructure Management
 
“Classroom communication Gap”
“Classroom communication  Gap”“Classroom communication  Gap”
“Classroom communication Gap”
 
Sun Shade Calculator for Lahore
Sun Shade Calculator for LahoreSun Shade Calculator for Lahore
Sun Shade Calculator for Lahore
 
5th - Block 4 - Climate Factors
5th - Block 4 - Climate Factors5th - Block 4 - Climate Factors
5th - Block 4 - Climate Factors
 
Shalimar gardens By Kamil Khan Mumtaz
Shalimar gardens By Kamil Khan MumtazShalimar gardens By Kamil Khan Mumtaz
Shalimar gardens By Kamil Khan Mumtaz
 

Similar a Stormwater Drainage Infrastructure of Lahore City

Storm water drainage problem of Surat city & its solutions due to flood in ri...
Storm water drainage problem of Surat city & its solutions due to flood in ri...Storm water drainage problem of Surat city & its solutions due to flood in ri...
Storm water drainage problem of Surat city & its solutions due to flood in ri...Kishan Bhadiyadra
 
Storm Water Drain Network System in Bengaluru
Storm Water Drain Network  System in Bengaluru  Storm Water Drain Network  System in Bengaluru
Storm Water Drain Network System in Bengaluru IRJET Journal
 
IRJET - Application of Water Conservation Technique to Low Income Group H...
IRJET -  	  Application of Water Conservation Technique to Low Income Group H...IRJET -  	  Application of Water Conservation Technique to Low Income Group H...
IRJET - Application of Water Conservation Technique to Low Income Group H...IRJET Journal
 
Synopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMSynopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMAbhinay Saraswat
 
Stormwater Management a Case Study of Gandhinagar City
Stormwater Management a Case Study of Gandhinagar CityStormwater Management a Case Study of Gandhinagar City
Stormwater Management a Case Study of Gandhinagar CityIRJET Journal
 
IRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC WeldingIRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC WeldingIRJET Journal
 
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...IRJET Journal
 
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...IRJET Journal
 
IRJET- Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...
IRJET-  	  Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...IRJET-  	  Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...
IRJET- Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...IRJET Journal
 
IRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla JunctionIRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla JunctionIRJET Journal
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...IRJET Journal
 
1st phase analysis
1st phase analysis1st phase analysis
1st phase analysisRohit Sahai
 
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone AreasGuidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone AreasPhani Mohan K
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET Journal
 
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRIRJET Journal
 
measures to counteract urban floods
measures to counteract urban floodsmeasures to counteract urban floods
measures to counteract urban floodsdontknow288849
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa Nisenson
 
IRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete GirderIRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete GirderIRJET Journal
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET Journal
 

Similar a Stormwater Drainage Infrastructure of Lahore City (20)

Storm water drainage problem of Surat city & its solutions due to flood in ri...
Storm water drainage problem of Surat city & its solutions due to flood in ri...Storm water drainage problem of Surat city & its solutions due to flood in ri...
Storm water drainage problem of Surat city & its solutions due to flood in ri...
 
Storm Water Drain Network System in Bengaluru
Storm Water Drain Network  System in Bengaluru  Storm Water Drain Network  System in Bengaluru
Storm Water Drain Network System in Bengaluru
 
IRJET - Application of Water Conservation Technique to Low Income Group H...
IRJET -  	  Application of Water Conservation Technique to Low Income Group H...IRJET -  	  Application of Water Conservation Technique to Low Income Group H...
IRJET - Application of Water Conservation Technique to Low Income Group H...
 
Synopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMSynopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEM
 
Stormwater Management a Case Study of Gandhinagar City
Stormwater Management a Case Study of Gandhinagar CityStormwater Management a Case Study of Gandhinagar City
Stormwater Management a Case Study of Gandhinagar City
 
IRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC WeldingIRJET- Optimization of Process Parameters of Submerged ARC Welding
IRJET- Optimization of Process Parameters of Submerged ARC Welding
 
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
IRJET- A Review Paper on Study on Strengthening and Drainage of Flexible Pave...
 
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
SUSTAINABLE & COST-EFFECTIVE DRAINAGE DESIGN SOLUTION FOR AN URBAN ROAD SCENA...
 
IRJET- Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...
IRJET-  	  Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...IRJET-  	  Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...
IRJET- Impact Assessment of Hydro Geo-Technical Variation in Parts of Sec...
 
IRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla JunctionIRJET- Effective Surface Drainage for Kurla Junction
IRJET- Effective Surface Drainage for Kurla Junction
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
IRJET- Exprimental Analysis of Permeable Concrete and its Application over Co...
 
1st phase analysis
1st phase analysis1st phase analysis
1st phase analysis
 
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone AreasGuidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
 
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
 
measures to counteract urban floods
measures to counteract urban floodsmeasures to counteract urban floods
measures to counteract urban floods
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one ieca
 
IRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete GirderIRJET- Train Impact Analysis on Prestressed Concrete Girder
IRJET- Train Impact Analysis on Prestressed Concrete Girder
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling Methods
 

Más de KKM Architects

Organic Farming vs Conventional Farming
Organic Farming vs Conventional FarmingOrganic Farming vs Conventional Farming
Organic Farming vs Conventional FarmingKKM Architects
 
The Lahore Project Brochure
The Lahore Project BrochureThe Lahore Project Brochure
The Lahore Project BrochureKKM Architects
 
Memorandum of understanding
Memorandum of understandingMemorandum of understanding
Memorandum of understandingKKM Architects
 
Pictures of the Event & The Signing of the MOU
Pictures of the Event & The Signing of the MOUPictures of the Event & The Signing of the MOU
Pictures of the Event & The Signing of the MOUKKM Architects
 
'Lahore sketches' by Syed Muhammad Latif
'Lahore sketches' by Syed Muhammad Latif 'Lahore sketches' by Syed Muhammad Latif
'Lahore sketches' by Syed Muhammad Latif KKM Architects
 
Ravi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the AnnouncementRavi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the AnnouncementKKM Architects
 
The Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development ProjectThe Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development ProjectKKM Architects
 
Mansooba (urban planning - alternate paradigms) by babar mumtaz
Mansooba (urban planning - alternate paradigms) by babar mumtazMansooba (urban planning - alternate paradigms) by babar mumtaz
Mansooba (urban planning - alternate paradigms) by babar mumtazKKM Architects
 
A vision for Physical Planning
A vision for Physical Planning A vision for Physical Planning
A vision for Physical Planning KKM Architects
 
Heritage Conservation - Gate Bagh e-Mullah Shah
Heritage Conservation - Gate Bagh e-Mullah Shah Heritage Conservation - Gate Bagh e-Mullah Shah
Heritage Conservation - Gate Bagh e-Mullah Shah KKM Architects
 
LDA City presentation by salman Sabir for TLP
LDA City presentation by salman Sabir for TLPLDA City presentation by salman Sabir for TLP
LDA City presentation by salman Sabir for TLPKKM Architects
 
PIFD Hostels Proposal, July 2010
PIFD Hostels Proposal, July 2010PIFD Hostels Proposal, July 2010
PIFD Hostels Proposal, July 2010KKM Architects
 
Vision presentation (Updated)
Vision presentation (Updated)Vision presentation (Updated)
Vision presentation (Updated)KKM Architects
 

Más de KKM Architects (15)

TLP Website Manual
TLP Website ManualTLP Website Manual
TLP Website Manual
 
Organic Farming vs Conventional Farming
Organic Farming vs Conventional FarmingOrganic Farming vs Conventional Farming
Organic Farming vs Conventional Farming
 
The Lahore Project Brochure
The Lahore Project BrochureThe Lahore Project Brochure
The Lahore Project Brochure
 
Memorandum of understanding
Memorandum of understandingMemorandum of understanding
Memorandum of understanding
 
Pictures of the Event & The Signing of the MOU
Pictures of the Event & The Signing of the MOUPictures of the Event & The Signing of the MOU
Pictures of the Event & The Signing of the MOU
 
'Lahore sketches' by Syed Muhammad Latif
'Lahore sketches' by Syed Muhammad Latif 'Lahore sketches' by Syed Muhammad Latif
'Lahore sketches' by Syed Muhammad Latif
 
Ravi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the AnnouncementRavi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the Announcement
 
The Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development ProjectThe Ravi Riverfront Urban Development Project
The Ravi Riverfront Urban Development Project
 
Mansooba (urban planning - alternate paradigms) by babar mumtaz
Mansooba (urban planning - alternate paradigms) by babar mumtazMansooba (urban planning - alternate paradigms) by babar mumtaz
Mansooba (urban planning - alternate paradigms) by babar mumtaz
 
A vision for Physical Planning
A vision for Physical Planning A vision for Physical Planning
A vision for Physical Planning
 
Heritage Conservation - Gate Bagh e-Mullah Shah
Heritage Conservation - Gate Bagh e-Mullah Shah Heritage Conservation - Gate Bagh e-Mullah Shah
Heritage Conservation - Gate Bagh e-Mullah Shah
 
LDA City presentation by salman Sabir for TLP
LDA City presentation by salman Sabir for TLPLDA City presentation by salman Sabir for TLP
LDA City presentation by salman Sabir for TLP
 
Regional plan (TLP)
Regional plan (TLP)Regional plan (TLP)
Regional plan (TLP)
 
PIFD Hostels Proposal, July 2010
PIFD Hostels Proposal, July 2010PIFD Hostels Proposal, July 2010
PIFD Hostels Proposal, July 2010
 
Vision presentation (Updated)
Vision presentation (Updated)Vision presentation (Updated)
Vision presentation (Updated)
 

Último

Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Último (20)

Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 

Stormwater Drainage Infrastructure of Lahore City

  • 1. Utility Infrastructure of Lahore City (Stormwater Drainage) Engr. Wasif Ali B.Sc. (Civil Engineering) M.Sc. (Environmental Engineering) The Lahore Project Working Session
  • 2. Presentation Outline  Existing Scenario  Stormwater Management Techniques  Case Study…… Mohlanwal Area  Design & Analysis of Stormwater Systems  Conclusions & Recommendations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 3. Existing Scenario  Frequent and Widespread Stormwater Flooding  Unplanned Development Pattern  Water Table Decline  Limited Space & Funds for Drainage  Poor Assessment of Existing Drainage facilities  Authorities are in mode of crisis The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 4. Existing Scenario The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 5. Existing Scenario  Groundwater Decline Sr. No Location Water Level below NSL (ft) Avg. Decline (ft/yr)Year Feet Year Feet 1 A-Block Gulberg 1977 40.75 2000 87.74 2.04 2 Nawan Kot Police Station 1981 30.83 2000 66.22 1.86 3 Takkia Lehri Shah 1978 33.75 2000 86.92 2.41 4 Singh Pura 1981 45.40 2000 86.59 2.16 5 Rehman Pura 1987 58.71 2000 94.46 2.75 6 Masti gate 1987 46.08 2000 85.11 3.00 8 Masoom Gunj 1987 26.57 2000 70.81 3.40 9 Avari Hotel 1987 70.68 2000 107.45 2.83 10 Jia Musa 1987 25.65 2000 37.72 0.93 Source: Integrated Master Plan of Lahore for 2021, NESPAKThe Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 6. Existing Scenario  Design Rainfall Distribution Curve for Lahore (1953-2005) Source: Pilot Balloon Observatory (PBO) LahoreThe Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 7. Existing Scenario  Rainfall Distribution Source: Pilot Balloon Observatory (PBO) LahoreThe Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 8. Stormwater Management Techniques  Conventional Techniques ☼ Rapid Removal of Water ☼ Reactive Approach ☼ Increased Flooding ☼ Increased Erosion and Pollution ☼ Reduced Aquifer Recharge ☼ Complex Pipe Network ☼ Expensive The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 9. Stormwater Management Techniques  Alternative Techniques ☼ Nomenclature ☼ BMPs… Best Management Practices ☼ SUDS… Sustainable Urban Drainage Systems ☼ USM… Urban Stormwater Management ☼ Localized Stagnation ☼ Lesser Erosion & Pollutant Loads ☼ Aquifer Recharging ☼ Flexible Network ☼ Proactive Approach ☼ Economical The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 10. Best Management Practices (BMPs)  Green Roofs  Rooftop Runoff Controls  Bioretention / Recharge Garden  Dry Well / Seepage Pit  Pervious Pavements  Vegetated Swale  Infiltration Trench  Infiltration basin  Wet Pond / Retention Basin The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 11. Green Roofs  Reduced & Delayed Runoff  (up to 70% peak reduction)  Insulation of Buildings  Lower Energy Consumption  Habitat for Birds and Insects  Reduced Carbon Dioxide levels  Higher Cost  Leakage  Harsh Conditions for Vegetation  Higher Maintenance Benefits Limitations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 12. Rooftop Runoff Control Benefits Limitations  Limited Suitability for small houses  Requires Proper Maintenance  Pumping Cost may involve if sub surface storage is provided  Irrigation of Landscaped areas & Gardens  Firefighting Storage  (Building like WAPDA house, School etc)  Reduced Peak Volume of Stormwater  Reuse for Grey Water….i.e. flushing toilets.  Reuse for Athletic Field Irrigation  Cost Savings during Summer The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 13. Rooftop Runoff Control The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 14. Bioretention/Rain Garden Limitations  Regular Inspection  Rain Gardens may Require Watering in dry season  Reduce Runoff Volume  Filter Pollutants  Recharge Groundwater  Enhance Aesthetics  Provide Habitat Benefits The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 15. Bioretention/Rain Garden The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 16. Dry Well/Seepage Pit  2’ Separation to Bedrock and Water Table  Min. 10’ distance from Foundation  Overflow Outlet for Large Storms  Min. One Observation Well.  Maximum Drain-Down Time is 72 hours Imp. Features The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 17. Pervious Pavements Limitations  Higher Construction and Maintenance Costs  Depends on Infiltration Rates of Underlying Soils  Less Durable  Good for impervious areas  Reduces runoff  Increased infiltration  Healthier vegetation Benefits The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 18. Pervious Pavements Variations 1) Pervious Bituminous Asphalt 2) Porous Concrete 3) Pervious Pavers BlocksThe Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 19. Vegetated Swale Imp. Features  Significantly slow the rate of runoff conveyance compared to pipes  Attenuation & Infiltration of runoff  Pollutants Removal  Longitudinal slope = 1 to 6%  Check Dams for steeper slopes  Side slope = 3:1 to 5:1  Bottom width = 2 to 8 ft The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 20. Vegetated Swale 1) Vegetated Swale with Infiltration Trench 3) Swale with Check Dams2) Grassed SwaleThe Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 21. Infiltration Trench Benefits Limitations  Ground Water Recharging  Stormwater Treatment  Good for Small Sites with Porous Soils  Groundwater Contamination  High Clogging Potential  Significant Setback Requirements  Geotechnical Testing Required The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 22. Infiltration Basin The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 23. Infiltration Basin  100% Reduction in the Load Discharged to Surface Waters  Approximation of Pre-Development Hydrology  Channel Erosion Control  Not Appropriate for Industrial / Spill sites  Not suitable on Fill-Sites or Steep Slopes  Infiltration rate ≥ 0.5 and ≤ 2.4 inch/hr  Difficult to Restore once Clogged. Benefits Limitations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 24. Wet Pond/Retention Basin  Wildlife and Wetlands Habitat  Aesthetic & Recreational Value  Public Amenity when integrated into a Park  Water Quality Improvement  Public Safety Concern  Mosquito Breeding  Cannot be Placed on steep slopes Benefits Limitations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 25. Study Area The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 26. Study Area Master Plan of the Mohlanwal The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 27. Study Area  Building Bye-Laws  LDA Land-Use Distribution for New Schemes Sr.# Land Use Area Requirement 1 Open Spaces / Parks Not less than 7% of Total Scheme Area 2 Graveyard Not less than 2% of Total Scheme Area 3 Commercial Area Not more than 5% of Total Scheme Area 4 Public Buildings 2 to 10 %  LDA Bye-Laws for Open Areas in Residential Units Category Area (Sft) Deduct Car Porch & Drive Way (Sft) Net Open Area (Sft) %age of Open AreaPlot Open Front Side Rear Total 2-kanal 9,000 1,500 1,800 750 4,050 600 3,450 38.3 1-Kanal 4,500 500 365 350 1,215 300 915 20.3 10-Marla 2,250 350 235 245 830 300 530 23.6 5-Marla 1,125 125 0 125 250 0 250 22.2The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 28. Design & Analysis of Stormwater Systems ☼ Stormwater Systems  Conventional Techniques  Partially Combined Sewer System (Model #1)  Separate Storm Sewer System (Model #2)  Alternative Techniques  Storm Sewer System with Park Storage (Model #3)  Storm Sewer System with Park & Lawn storage (Model #4) ☼ Analysis / Design Tool  Storm Water management Module (SWMM) The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 29. Design & Analysis of Stormwater Systems The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 30. Design & Analysis of Stormwater Systems Model # 1 & 2 The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 31. Design & Analysis of Stormwater Systems ☼ Summary of Node Flooding Node Type 2-Yrs 5-Yrs 10-Yrs Total Flooding (acre-in) Total Minutes Flooded Total Flooding (acre-in) Total Minutes Flooded Total Flooding (acre-in) Total Minutes Flooded J1 Junction 15.59 364 34.98 384 48.57 393 J2 Junction 5.05 71 23.68 218 43.85 355 J3 Junction 0.01 0 0.01 0 2.81 48 J4 Junction 0 0 0.01 0 0.70 30 J5 Junction 8.79 372 15.31 393 20.36 402 J6 Junction 29.19 364 57.46 384 76.84 393 J7 Junction 5.04 121 18.61 354 31.39 363 J8 Junction 0.00 1 4.62 63 8.65 83 J9 Junction 10.09 374 18.29 399 25.46 412 J10 Junction 10.95 352 29.65 372 43.84 384 J11 Junction 21.67 362 51.63 380 75.32 387 J12 Junction 0 0 0 0 0.00 1 J13 Junction 0 0 0 0 0.00 0 J14 Junction 0 0 0 0 0 0 O1 Outfall 0 0 0 0 0 0 Model # 1 Partially Combined Sewer System The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 32. Design & Analysis of Stormwater Systems ☼ Summary of Links Link Type Diameter (inch) Link Type Diameter (inch) C1 Circular 9 C8 Circular 9 C2 Circular 15 C9 Circular 12 C3 Circular 24 C10 Circular 18 C4 Circular 24 C11 Circular 12 C5 Circular 9 C12 Circular 24 C6 Circular 12 C13 Circular 24 C7 Circular 15 C14 Circular 27 Model # 1 Partially Combined Sewer System The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 33. Design & Analysis of Stormwater Systems Model # 3 Storm Sewer System With Park Storage The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 34. Design & Analysis of Stormwater Systems Model # 4 Storm Sewer System With Park & Lawn Storage The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 35. Design & Analysis of Stormwater Systems ☼ Evaluation of different Models  Flooding Velocity %age Peak Domestic flow as Stormwater Allowance Provided as per WASA Criteria Required as per SWMM Analysis Return Period fps 2-Yrs 5-Yrs 10-Yrs 2.0 100 345 635 1000 2.5 100 460 825 1275 3.0 100 570 1005 1550 Comparison of Stormwater Allowance for different Frequencies  Length-weighted Diameter {(D1xL1+D2L2+……..DnLn) / ΣLn}  Cost of the System The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 36. Design & Analysis of Stormwater Systems Type of Stormwater System Length-weighted Diameter (inch) Cost (Millions Rs.) 2-Yrs 5-Yrs 10-Yrs 2-Yrs 5-Yrs 10-Yrs Combined System 16 16 16 2.6 2.6 2.6 Separate System 34 45 52 6.7 11.0 14.7 Storm Sewer with Park Storage 16 22 26 2.9 4.4 5.5 Storm Sewer with Park and Lawn Storage 09 16 19 1.5 2.9 3.5  Summary of the Network Sizing & Cost The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 37. Conclusions & Recommendations 1) Mean average decline in ground water table of Lahore comes to be 2.03 ft/yr which clearly shows the need to implement the alternative storm water techniques instead of conventional techniques. 2) The “knee of curve” for Lahore is in the range of 0.60 to 1.00 inch of rainfall hence BMPs will be most efficient and economical in Lahore if they target the storm event having the value lesser than 1.0 inch. 3) The value of “Storm water Allowance”, as per WASA design criteria is taken as 100% of peak domestic flow but this study shows that it varies from 345% to 1000% for 2-yrs and 10-yrs return period respectively. Hence the value suggested by WASA is of no use if one is designing combined system for No-flooding condition. ☼ Conclusions The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 38. 4) This study shows that ample reduction in conduit size can be achieved by utilizing BMPs. For example the ultimate diameter for separate sewer system are 42, 54 and 66 inch respectively for 2, 5 and 10 year return period while using only two BMPs (i.e. Lawn Depression and Park Storage) the ultimate diameters are 12, 21 and 24 inch for 2,5 and 10 year return period respectively. 5) Common misconception about the additional land requirement for any storage facility can be wrecked by the results of this study that even using the current open space regulation of LDA, 89% of peak flow reduction can be achieved through BMPs. Conclusions & Recommendations ☼ Conclusions The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 39. 1) The rainfall data is a basic requirement for the analysis purposes. Continuous recording of rainfall is required to develop a shorter time interval for rain fall intensity curves. Presently most of the data is in 3-hr interval form and only a limited record of continuous recording rain- gages is available. It is strongly recommended that meteorological department should make such arrangements that rainfall can be recorded up to 5 minutes interval. 2) Main emphasis of the bye-laws in Lahore is on ventilation and sunlight criteria. No provision is made in these bye-laws to meet the sustainable drainage. Hence it is needed to develop such guidelines by which sustainable development can be achieved. Conclusions & Recommendations ☼ Recommendations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 40. 3) Peak and quantity of the stormwater flow should be reduced by the application of storage BMPs. Government agencies like WASA should prepare a master drainage plan for all major drains (natural as well as man-made) and a specific quantity and peak of flow should be allotted to each and every section of these drains. A stormwater tax should be imposed if society discharges any additional flow than that of allotted by the competent authority like WASA. 4) The LDA should encourage the vertical growth so that more and more space can be utilized for the BMPs. Constructed wetland, wet ponds and many other storage facilities require a huge land area. It will not only increase the ground water recharging but at the same time such spaces can be utilized as recreational spot, walkways and children’s play areas. Conclusions & Recommendations ☼ Recommendations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 41. 5) Most of the BMP techniques can only be implemented by the active public participation hence educational and awareness campaigns should be set up for local community groups. Electronic media can play an important role in this regard. 6) Because of rapid urbanization, extensive and more frequent flooding has been occurring in recent years and the continued use of conventional techniques to stormwater management result in municipalities becoming victims of their municipality’s development success therefore it makes sense to implement the Alternative techniques to stormwater management. Conclusions & Recommendations ☼ Recommendations The Lahore Project Working Session on Utility Infrastructure 21 August 2013
  • 42. Questions & Answers The Lahore Project Working Session on Utility Infrastructure 21 August 2013