POWER GENERATION
  PROCESS BASICS
BOILER / STEAM TURBO-GENERATOR
                          UTILITY PLANT
                                                                                       40%
                                     Steam Condenser




                20%




                   Stack

                                                                                Lake
                      Steam
                                                       6% Aux. Power + Losses
                                                                                       34% Electricity


100%
Fuel


Air



       Boiler                   Steam Turbine                  Generator               Transmission



                              THERMAL EFFICIENCY - 34%
BOILER / STEAM TURBINE-GENERATOR
                    INDUSTRIAL CO-GENERATION
                                                 Process Steam
                                                 65%

                  15%


                                                                             Process Plant


                     Stack



                        Steam                             5% Aux. Power + Losses

                                                                                             15% Electricity


Fuel
100%


 Air



       Boiler                    Steam Turbine                   Generator                   Transmission


                                THERMAL EFFICIENCY - 80%
SIMPLE CYCLE COMBUSTION (GAS) TURBINE


                                    57-62%




 100% Fuel                               Stack


                   Combuster
                                                       3% Aux Power + Losses


                                                                               35-40% Electricity
Air




      Compressor          Turbine                Generator                     Transmission


                          THERMAL EFFICIENCY - 35-40%
GAS TURBINE
                   INDUSTRIAL CO-GENERATION PLANT
                                                   20%


                         Stack                           Stack

            Supplementary/
            Auxiliary
            Fuel (Optional)                              Process Steam
                                                                         Process Plant
 100% Fuel


                                 Combuster            Exhaust Gas




Air




      Compressor                         Turbine             Generator              Transmission
GAS TURBINE                                                                 28%
                        COMBINED CYCLE POWER PLANT
                                                                         Steam Condenser
                                                       20%

                                                             Stack
                              Stack
                                                             Steam                               Lake
                   Supplementary
                   Fuel (Optional)


 100% Fuel

                                                                       Steam Turbine       Generator
                                                                                                            Transmission
                                 Combuster                Exhaust Gas                                   12-15% Electricity



Air                                                                  6% Aux. Power + Losses             35-40% Electricity




      Compressor                             Turbine                 Generator                           Transmission


                                             Thermal Efficiency - 45-55%
UTILITY PLANT - FUNCTIONAL BLOCK DIAGRAM
   Switch Yard System                 Ash Handling System          Station Electrical System


                   Boiler Steam & Water System

                    Air & Flue Gas System

    BOILER          Fuel Preparation System

                    Fuel Firing System

                   Boiler Miscellaneous Systems

                        Boiler Feed Pumps &
                                                               UNIT#2
                        Deaerator System


                    Turbine Steam System
   TURBINE-
                    HP & LP Heaters System
   GENERATOR
                    Turbine Supervisory & Control
                    System
                   Generator & Electrical System

                   Turbine Miscellaneous Systems


                          Turbine Bypass System



                                        Fuel Handling System
               DM Plant                                        Station Miscellaneous Systems
CAPTIVE POWER PLANT - FUNCTIONAL BLOCK
               DIAGRAM
         Switch Yard System              Ash Handling System              Station Electrical System



             Steam & Water

             Air & Flue Gas
BOILER

            Fuel Preparation

             Fuel Firing


             Steam                             UNIT#2                       UNIT#3
TG           HP & LP Heaters


              Supervisory & Control

            Generator & Electrical


            Miscellaneous Systems


                                      BFP’s & Deaerator System


                                      Fuel Handling System
               DM Plant                                          Station Miscellaneous Systems
BOILER FUNDAMENTALS
BASIC DIAGRAM OF A BOILER

                                                             Steam
Water



                     Steam / Water System                   Blowdown




Fuel
                                                            Flue Gas
        Mixing of                           Heat Transfer
        Fuel & Air                          Surface
                         Furnace


Air                                                          Ash
SALIENT FEATURES OF MODERN INDUSTRIAL
& UTILITY BOILER

• STEAM BOILER
• WATER TUBE

• SUPERHEATED STEAM

• HIGH PRESSURE

• WATER COOLED FURNACE

• WATER CIRCULATION
COMBUSTION REQUIREMENTS




           Sufficient
           Combustion Air




                                            Temperature
Fuel                                                         Combustion
                            Mixing within   above
is                                                           Time
                            Flammable       Ignition
Gasified                                                     Temperature
                            Range           Point            Turbulence


                                                          3 T’s of Combustion
BASIC COMBUSTION CHEMISTRY

                                              Complete      Heat

(Air) Oxygen                 Fuel                            Flue Gas

                                                            Products
                                H2                          H2O
       O2            +          C                           CO2




                                              Incomplete
                                                            Heat

  Oxygen                       Fuel
                                                             Flue Gas
                                                            Products
                                 H2
                                                            H2O
      O2              +          C
                                                            CO2
                                                            CO
                                                            H2
                                                            C

  • Other Combustibles - Sulphur to Sulphur Oxides
  • Non-combustible - Nitrogen to Nitrogen+Nitrous Oxides
  • Ash
BOILER WATER & STEAM SYSTEM                                                        Hot Reheat
                                                                                               Steam
                    Spray
                    Water                                                                       Main Steam
         Drum
                                                 Attemperator

                                                                                      Attemperator
                                                                                                       Cold
                                        Final       Primary     Final                                  Reheat
                             Platen                                        Primary
                                        Re          Re          Super                                  Steam
                             Super                                         Super
                                        Heater      Heater      Heater                        Spray
                             Heater                                        Heater
                                                                                              Water

Down
Comers           Flue Gas
                                                                         Economiser
                                                                                              Feed Water


                   Furnace


                                                                         Flue Gas
                Water Wall                                               Out to
                Risers                                                   Air Heater




                                      Bottom Ring Header



                        Simplified Process Diagram
BOILER WATER & STEAM SYSTEM

Process Performance Highlights

• Heat Transfer by Radiation and Convection

• Boiler Water Circulation - Natural or Controlled

• Heat Transfer depends on Heat Transfer Area & Time

• Heat Transfer is affected by Fouling, Boiler Pressure, Boiler Water Quality
  and % MCR Load
BOILER WATER & STEAM SYSTEM

Major Equipment

• Economiser - Pre-heats Boiler Feed water

• Boiler Drum - Separates water from steam and reduce solids in steam

• Water Walls - Absorb heat from flue gas to evaporate boiler water

• Superheaters - Heat up steam coming from boiler drum

• Reheaters - Heat up steam coming from High Pressure turbine

• Attemperators - Reduce superheat from steam
BOILER WATER & STEAM SYSTEM


Process Regulation

• Drum Level - Regulation of Feed Water flow

• Drum Water Quality - Blow down / Chemical Dozing

• Fouling of Heat Transfer Surfaces - Blowdown / Soot Blowing

• Main Steam Temperature - Attemperation / Burner Tilt

• Hot Reheat Steam Temperature - Burner Tilt / Attemperation

• Main Steam Pressure - Regulation of Combustion
AIR & FLUE GAS SYSTEM
To Air Cooled                                                                  PA FAN A
                                                   To Hot      To Cold
Guns                                               PA Header   PA Header
                                 From
          Scanner Air Fans       FD Fans
                                                                               PA FAN B




     WINDOX A
                                                        AH A        ESP A
                             P         F   L
                                  R            E
                             T         I   T                                 ID Fan A
      FURNACE                     H            C
                             N         N   S                                                Chimney
                                               O
                             S         S   H
                             H         H                                      ID Fan B
                                                                     ESP B
                                                        AH B
      WINDBOX B


                                                                                FD FAN A




                                                                                 FD FAN B




                             Simplified Process Diagram
AIR & FLUE GAS SYSTEM


Process Performance Highlights

• Generation of Draft - Natural / Induced / Forced / Balanced

• Supply of Air for Transport of Pulverised Coal

• Pre-heating of Air

• Distribution of Air in Combustion Chamber

• Recirculation of Gas

• Fan capacity depends on Flow, Density & System Resistance

• Fan performance is affected by temperature, density, barometric pressure
          and speed

• Flue Gas Cleaning

• Gas flow is restricted by ash deposits on boiler surfaces
AIR & FLUE GAS SYSTEM


Major Equipment

• Air Path - Forced Draft Fans, Steam Coil Air Pre-heater,
             Regenerative Air Pre-heater & Wind-box

• Gas Path - Induced Draft Fans and Stack

• Gas Recirculation - Gas Recirculating Fans

• Flue Gas Cleaning - Mechanical Precipitator, Electrostatic
             Precipitator and Gas Scrubber

• Dampers
AIR & FLUE GAS SYSTEM


Process Regulation

• Furnace Draft - ID Fan Inlet Vane Control and/or Variable Speed

• Secondary Air Flow - FD Fan Variable Pitch Control

• PA Header Pressure - PA Fan Inlet Vane Control

• RAPH Cold End Temperature - SCAPH Control

• Gas Recirculation - Damper Control
FUEL PREPARATION SYSTEM - COAL
             Raw Coal Bunker                        To Mill Discharge
                                                    Valves

                                                                         To           Hot PA
                                                                         Other
                Coal Feeder                                              Mills

Coal+Air
to Burners




                   Mill A                                                             Cold PA
                                                                              To
                                                                              Other
                                                                              Mills




                                   To Other Mills             Seal Air Fans




                               Simplified Process Diagram
FUEL PREPARATION SYSTEM - GAS/OIL
Fuel Gas
Supply                                                               To Burners
                                                     FCV      FGTV

                         PRV’s
                                                FUEL GAS

 Atomising
 Steam/Air

                                     PCV


 Fuel Oil
 Return
                                                 Short     Long
                                                 Recirc    Recirc
               PCV


 Fuel Oil
                                   Oil Heater                            To Burners
 Supply
                                                   FCV     FOTV


                                   Steam
             Fuel Oil Pumps
                                                FUEL OIL


                              Simplified Process Diagram
FUEL PREPARATION SYSTEM


Process Performance Highlights

• Coal Pulverizing - Direct / Indirect Firing

• Coal Transport and Drying

• Fuel Gas Pressure Regulation

• Fuel Oil Pumping & Filtering

• Fuel Oil Pressure & Viscosity Regulation

• Gas Pressure & Oil Pressure/Temperature affect Boiler
  Load
FUEL PREPARATION SYSTEM

Major Equipment

• Coal Mills - Tube Ball / Bowl / Impact

• Raw Coal Feeders - Chain / Belt / Rotary / Gravimetric

• Coal / Air Dampers, Gates & Discharge Valves

• Fuel Oil Pumps & Heaters

• Seal Air Fans

• Coal Bunkers

• Vapour Fans
FUEL PREPARATION SYSTEM

Process Regulation

• Coal Flow - Raw Coal Feeder Speed

• Coal/Air Temperature & Flow - Cold & Hot PA Flows
FUEL FIRING SYSTEM
         OFA
         OFA

    FF   EA

    F    FA
               (2)                        (3)             Air Damper
    EF   AA

    E                                               OFA   Over Fire Air
                                                    EA    End Air
    DE
                                                    FA     Fuel Air

    D                                               AA     Aux. Air
                      Front Wall
                                                          Coal Burner
CD                                            (4)
                (1)
                       Plan                               Fire Ball Scanner
C
                       (Corner Designation)               LFO?HFO Burner
BC
B                                                         HFO Burner
                                                          Oil Flame Scanner
AB
A                                                         HEA Igniter

AA

          Typical Corner Arrangement
         for a Tangentially Fired System
FUEL FIRING SYSTEM

Process Performance Highlights

• Fuel Firing - Front / Tangential

• Fuel Oil Atomisation - Mechanical / Air / Steam

• Flame Ignition

• Air Distribution

• Fuel Combustion
FUEL FIRING SYSTEM


Major Equipment

• Burners

• Ignitors

• Flame Scanners

• Burner Tilt Mechanism

• Wind Box

• Dampers
FUEL FIRING SYSTEM


Process Regulation

• Furnace to Wind Box Differential Pressure

• Fuel Air Flows

• Fuel Firing

• Emergency Shutdown

• Flame Monitoring

• Oil Support for Coal Flame Stability
BOILER MISCELLANEOUS SYSTEMS



Boiler Auxiliary Cooling Water System

• Ensures continuous supply of cooling water to Boiler & it’s auxiliaries

• Consists of Overhead Tank, Pumps & Heat Exchangers

Chemical Dosing System

• Prepares & supplies chemicals for treatment of Boiler Water

• Consists of Preparation Tanks, Mixers & Metering Pumps
DEAERATION & FEED PUMPING SYSTEM
                    Condensate from LP Heater

                                                                             To HP
   HP Heater Drains
                                                           Aux. Steam        Heaters

                                                           CRH Steam
                     Deaerator
                                                           IPT Extraction
Aux. Steam                                                 Steam
for               Feed Storage Tank
Pegging                                                                                To HP Bypass
                                                                                       Spray

      Hydrazine                                                                         T o APRDS
      Dosing                                                                            Spray
      Ammonia                                        Recirculation
      Dosing                                         Valve
                                                                     M



                                                           Discharge Valve




                                 Boiler Feed Pumps




                                  Simplified Process Diagram
DEAERATION & FEED PUMPING SYSTEM


Process Performance Highlights

• Boiler Water pre-heating & air removal

• Maintain positive Suction Pressure for Feed Pumps

• Feed Water Pumping to Boiler
DEAERATION & FEED PUMPING SYSTEM

Major Equipment

• Boiler Feed Pumps

• Hydraulic Coupling

• Deaerator
DEAERATION & FEED PUMPING SYSTEM


Process Regulation

• Deaerator Pressure

• Deaerator Level

• BFP Minimum Recirculation

• Feed Pump Speed
STEAM TURBINE FUNDAMENTALS
LAWS OF THERMODYNAMICS



• Conservation of Energy - Heat may be converted in to work and
  work may be converted in to heat,
  in accordance with a certain natural proportionality constant
  (ENERGY CAN NOT BE DESTROYED)

• Not all of a given quantity of Heat can be converted in to useful Work,
  because of irreversbility in the process
  (ENTROPY OF THE UNIVERSE IS INCREASING)
BASIC RANKINE CYCLE




T

              Heat Available
              for Work



          Unavailable Heat




                S
IMPROVING RANKINE CYCLE

• Superheating

• Increased Pressure

• Decreased Exhaust Pressure

• Regenerative Feed Heating

• Reheating
STEAM TURBINE TYPES


• Condensing Turbine

• Back Pressure Turbine

• Regenerative Turbine

•Controlled Extraction

• No. of Cylinders

• Speed - Constant / Variable

• Single / Double Flow
TURBINE STEAM SYSTEM
Main
Steam

          ESV   CV    HP                  IP
                      Turbine             Turbine                LP           Turbine



Cold
Reheat
Steam

                                                                      Condenser

 Hot
 Reheat
 Steam
                                IV   CV
                                                    Extraction
                                                    Steam




                     Simplified Process Diagram
TURBINE STEAM SYSTEM


Major Equipment

• Turbine - Casing, Rotor & Blades

• Emergency Stop Valves

• Control Valves

• Condenser
TURBINE STEAM SYSTEM


Process Regulation

• Steam Admission

• Emergency Shutdown
REGENERATIVE FEED HEATING SYSTEM
                     To     From BFP                To
                     Boiler Discharge               Deaerator    LPT
   CRH                                                           Extraction Steam
   Steam

To
Deaerator                                                       LP
            HP
                                                                HTR
            HTR



                                           LPT                                                         Condenser
                    IPT                    Extraction Steam               Gland
                    Extrn.                                                Leakoff
                    Steam                                       LP        Steam
            HP                                                  HTR                 Minimum                          Makeup
            HTR                                                                     Recirculation        Hotwell



                                     To                                         LPT Extraction
                                     Condenser
                                                                           LP        Drain
                         To                                      GSC       HTR       CLR
            HP           Condenser      LP
            Flash                       Flash
            Tank                        Tank
                                                                                                 Condensate Extraction
                                                                                                 Pump


                                Simplified Process Diagram
REGENERATIVE FEED HEATING SYSTEM


Process Performance Highlights

• Pumping of Condensate from Hotwell to Deaerator

•Gradual Heating of Feed Water Temperature

• Minimise Heat Loss from the Cycle
REGENERATIVE FEED HEATING SYSTEM


Major Equipment

• HP Heaters

• LP Heaters

• Drain Cooler

• Condensate Extraction Pumps
REGENERATIVE FEED HEATING SYSTEM

Process Regulation

• Hotwell Level

• Heater Level

• Minimum Flow through CEP & GSC
TURBINE GOVERNING & CONTROL SYSTEM



    Governing
    Oil
    System


     Turning
     Gear



     Jacking            Condenser
     Oil                Vacuum
     System             System



     Lubricating         Gland           Turbine
         Oil             Steam           Drain
       System                            System
                         System

   OIL SYSTEMS
                       VACUUM SYSTEM   WARM UP SYSTEM



                Functional Block Diagram
TURBINE GOVERNING & CONTROL SYSTEM

Process Performance Highlights

• Shaft & Bearing Protection

• Electro-hydraulic Governing

• Maintain Vacuum in Condenser

• Supply Steam to Turbine Glands

• Warming up of Turbines and their Valves

• Emergency Shutdown in case of Unsafe Conditions
TURBINE GOVERNING & CONTROL SYSTEM

Major Equipment

• Oil Pumps, Turning Gear & Jacking Oil Pump

• Hydraulic Actuators for Turbine Valves

• Vacuum Pumps

• Gland Steam Pressure Regulator

• Oil Coolers & Temperature Regulator
TURBINE GOVERNING & CONTROL SYSTEM


Process Regulation

• Speed / Load / Frequency Control

• Gland Steam Pressure Control
TURBINE MISCELLANEOUS SYSTEMS



Condenser Cooling Water System

• Supplies Cooling Water Condensation of Turbine Exhaust Steam

Turbine Auxiliary Cooling Water System

• Ensures continuous supply of cooling water to Turbine & it’s auxiliaries

• Consists of Overhead Tank, Pumps & Heat Exchangers

Chemical Dosing System

• Prepares & supplies chemicals for treatment of Condensate

• Consists of Preparation Tanks, Mixers & Metering Pumps
TURBINE MISCELLANEOUS SYSTEMS
     Condenser Cooling Water System
                    CW Return Header




Cooling                                                   Condenser Waterbox
Tower
                                       To                     A        B
                                       Unit#2
                   CW
                   Sump




    CW
    Makeup
    Water
                                       CW Supply Header


                            Circulating
                            Water Pumps

             Simplified Process Diagram
TURBINE MISCELLANEOUS SYSTEMS
   Condenser Cooling Water System

Major Equipment

• Cooling Towers
• CW Pumps


Process Performance Highlights

• Steam Condensation
• Cooling of Condenser CW - Cooling Tower / Lake


Process Regulation

• Condenser Tube Cleaning - Online / Back flushing
TURBINE BYPASS SYSTEM
Main
Steam
                                                       To HPT

           Feed
           Water                     PRV

                   Block   Spray
                   Valve   Control
                           Valve
CRH
                                                        From HPT




 HRH                                         To IPT



  Condensate


                                                      Condenser




                       Simplified Process Diagram
TURBINE BYPASS SYSTEM

Process Performance Highlights

• Enable Boiler Operation for Quick Re-start after Boiler Trip and
  during Turbine Start-up

• Control MS Pressure after Turbine Trip or Sudden Load Throw-off
TURBINE BYPASS SYSTEM

Process Regulation

• MS Pressure Reduction & Desuperheating

• HRH Steam Pressure Reduction & Desuperheating
GENERATOR FUNDAMENTALS
WORKING PRINCIPLE

• Converts Mechanical Energy in to Electrical Energy

• Based on Electro-magnetic Induction

   E = 4.44 O FN volts

   E - e. m. f.
   O - Strength of Magnetic Field
   F - Frequency
   N - No. of Turns in a Stator Winding Coil

    F = Pn/120

    P - No. of Poles
    n - Revolution per second of Rotor
GENERATOR EFFICIENCY & LOSSES


• Efficiency = Output Electrical Energy
               Input Mechanical Energy


• Losses - Bearing Loss, Copper Loss & Iron Loss

• Typically Efficiency is 90-97%
GENERATOR & UNIT ELECTRICAL SYSTEM



                 Metering &
                 Protective
                 Relays



                 Generator            Seal
                 Transformer          Oil
                                      System


                 Generator           Hydrogen
                 Synchronising       Cooling
                 Sceme               System


   Unit          Field              Stator
   Auxiliary     Excitation         Cooling Water
   Transformer   System             System



    ELECTRICAL SYSTEMS           MECHANICAL SYSTEMS



     Generator Functional Block Diagram
GENERATOR & UNIT ELECTRICAL SYSTEM

    Isolator                                     132 KV Bus I




                                                  132 KV Bus II


                       Circuit Breaker




                                                             Unit
                        GT
                                                             Auxiliary
                                                             Transformer

                                                                              From
               11 kV                  From
                                                                              Station
                                      Station
                                                                              Bus
                                      Bus
                          Generator
                                         6.6 kV Unit Bus A      6.6 kV Unit Bus B




               Key One Line Diagram
GENERATOR & UNIT ELECTRICAL SYSTEM

Process Performance Highlights

• Conversion of Mechanical Energy in to Electrical Energy

• Field Excitation

• Stator Winding Cooling by Distillate / Air

• Rotor Winding Cooling by Hydrogen / Air

• Hydrogen Sealing by Oil

• Synchronisation & Voltage Transformation

• Emergency Shutdown in case of Unsafe Conditions
GENERATOR & UNIT ELECTRICAL SYSTEM

Major Equipment

• Generator - Stator, Rotor, Armature Windings, Field Windings

• Field Excitation - Exciter (DC/AC), Static Rectifying Unit & AVR

• Bus Ducts & Transformers

• Circuit Breakers & Protective Relays

• H2 Cooling - Fans, Dryers & Coolers

• Stator Water Cooling - Pumps, Coolers & Overhead Tank

• Seal Oil - Pumps, Coolers & Differential Pressure Regulator
GENERATOR & UNIT ELECTRICAL SYSTEM

Process Regulation

• Field Excitation

• Generator Synchrinisation

• Voltage Regulation
POWER PLANT
OPERATION & MAINTENANCE
OPERATION & MAINTENANCE

Efficiency Calculations

• Boiler Efficiency - Direct / Heat Loss Method

• Turbine Heat Rate - Total Heat Supplied/ KWHR

• Plant Heat Rate - Heat Supplied/ KWHR
OPERATION & MAINTENANCE

Factors Affecting Plant Performance
• Flue Gas Exit Temperature

• Excess Air

• Unburnt Fuel

• Steam Temperature

• Condenser Back Pressure

• FW Temperature at Eco Inlet

• Auxiliary Power Consumption

• Make up Water Flow

• Optimum Loading
OPERATION & MAINTENANCE

• Start-up & Shutdown Monitoring

• Trip Analysis - Boiler / Turbine / Generator

• Equipment Run-Hour Monitoring

• History Trending

• Alarm Management

• Division of Operational Responsibilities

• Economic Load Allocation & Load Shedding (CPP)
POWER PLANT
AUTOMATION &
   CONTROL
POWER PLANT AUTOMATION & CONTROL

Burner Management System

• Furnace Purge Supervision

• Secondary Air Damper Modulation, On/Off Control and Supervision

• Light/Heavy Oil On/Off Control and Supervision

• Pulveriser and Feeder On/Off Control and Supervision

• Flame Scanning

• Overall Boiler Flame Failure Protection

• Boiler Trip Protection
POWER PLANT AUTOMATION & CONTROL


Soot Blower Sequential Control

• Wall Blowers

• Long Retractable Blowers

• Air Heater Blowers
POWER PLANT AUTOMATION & CONTROL


Automatic Turbine Run-up System

• Oil Supply Control - Turning Gear, Auxiliary Oil Pumps, Emergency Oil Pump,
  Jacking Oil Pump and Lube Oil Temperature

• Condensate & Evacuation Control - Condensate Extraction Pumps, Gland Steam
   Pressure, Vacuum Pumps and Vacuum Breaker Valve

• Turbine Control - Steam & Metal Temperature Matching, Warming up of HP
  ESV & CV, Steam Rolling & Acceleration and Auto Synchroniser
POWER PLANT AUTOMATION & CONTROL

Turbine Stress Evaluator

• Calculation of Actual and Permissible Thermal Stress Values

• Comparison of Actual with Permissible Stress Values and Computation
  of Available Margin

• Optimize Start up, Operation and Shut down
POWER PLANT AUTOMATION & CONTROL

Automatic Turbine Tester

• Safety Devices - Remote Trip, Over-speed, Low Vacuum and
  Thrust Bearing

• HP/IP Valves - HP Stop and Control Valves, and IP Stop and
  Control Valves
POWER PLANT AUTOMATION & CONTROL

Electro-hydraulic Governing System

• Speed Control

• Load Control

• Load Shedding

• Initial Pressure Control
AUTOMATION & CONTROL

CRITICAL CLOSED LOOPS

• CMC - Boiler Follow / Turbine follow / Coordinated (Utility)

• Header Pressure Control (CPP)

• Combustion - Fuel / Air Flow

• Steam Temperature

• Drum Level

• Furnace Draft
AUTOMATION & CONTROL

OPEN LOOP CONTROL

• Interlocking - Safe Startup / Shutdown

• Protection - Emergency Shutdown (Trip)

• Sequencial Control - Efficient Startup / Shutdown


CRITICAL OPEN LOOPS

• ID/FD /PA Fans

• BFP
POWER PLANT
INSTRUMENTATION
POWER PLANT INSTRUMENTATION

• Temperature - T/C & RTD

• Pressure

• Level - DP / Displacement / Hydra Step Drum Level Indicator

• Flow - DP / Annubar / Mag-flow

• Turbine Supervisory - Vibration/ Expansion/ Axial Shift/ Eccentricity

• Steam & Water Analysers - Conductivity/ pH/ DO2/ Silica

• Gas Analysers - O2/ CO2/ CO (in Flue Gas)
                  Pollution Monitor
                  H2 Purity (in Generator)

Más contenido relacionado

La actualidad más candente

Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing systemAshvani Shukla
 
SOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxSOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxanujgupta862927
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protectionanujkumarsingh79
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingTahoor Alam Khan
 
Drum level measurement
Drum level measurementDrum level measurement
Drum level measurementLalit_943240
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineRAVI PAL SINGH
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
Condenser in thermal power plants
Condenser in thermal power plantsCondenser in thermal power plants
Condenser in thermal power plantsSHIVAJI CHOUDHURY
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Jigyasa Singh
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Generator cooling and sealing system 2
Generator cooling and sealing system 2Generator cooling and sealing system 2
Generator cooling and sealing system 2Mohammad Basid
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Manohar Tatwawadi
 

La actualidad más candente (20)

Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
SOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxSOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptx
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Boiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & WorkingBoiler Purging-Logic, Importance & Working
Boiler Purging-Logic, Importance & Working
 
Drum level measurement
Drum level measurementDrum level measurement
Drum level measurement
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Condenser in thermal power plants
Condenser in thermal power plantsCondenser in thermal power plants
Condenser in thermal power plants
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
200 mw FSSS
200 mw FSSS200 mw FSSS
200 mw FSSS
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Generator cooling and sealing system 2
Generator cooling and sealing system 2Generator cooling and sealing system 2
Generator cooling and sealing system 2
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
 

Similar a Power plant-basics

power-plant-basics
power-plant-basicspower-plant-basics
power-plant-basicskulanji Siva
 
Flownex In Coal Energy
Flownex In Coal EnergyFlownex In Coal Energy
Flownex In Coal EnergySanthosh N L
 
Cogeneration assesment
Cogeneration assesmentCogeneration assesment
Cogeneration assesmentHabudin Hassan
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applicationsmirfanm
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applicationsmirfanm
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power PlantsHarshad Desai
 
Energy saving audit project( mgtc)
Energy saving audit project( mgtc)Energy saving audit project( mgtc)
Energy saving audit project( mgtc)moffaz
 
Schneider process automation power industry solutions
Schneider process automation power industry solutionsSchneider process automation power industry solutions
Schneider process automation power industry solutionsRodney Berg
 
Apex Microturbine Powerpoint
Apex Microturbine PowerpointApex Microturbine Powerpoint
Apex Microturbine PowerpointMario Viscovich
 
Thermal power-plant
Thermal power-plantThermal power-plant
Thermal power-plantjsoni332
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutionsHemant Sharma
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE Manohar Tatwawadi
 
Energyes division ener termopac line 2015 ev v02
Energyes division ener termopac line 2015 ev v02Energyes division ener termopac line 2015 ev v02
Energyes division ener termopac line 2015 ev v02Christian Moreau
 
Energyes Division EnerTermoPac Line 2015 EV V02
Energyes Division EnerTermoPac Line 2015 EV V02Energyes Division EnerTermoPac Line 2015 EV V02
Energyes Division EnerTermoPac Line 2015 EV V02Christian Moreau
 

Similar a Power plant-basics (20)

power-plant-basics
power-plant-basicspower-plant-basics
power-plant-basics
 
Flownex In Coal Energy
Flownex In Coal EnergyFlownex In Coal Energy
Flownex In Coal Energy
 
Cogeneration assesment
Cogeneration assesmentCogeneration assesment
Cogeneration assesment
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applications
 
Ge Combined Cycle
Ge Combined CycleGe Combined Cycle
Ge Combined Cycle
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plants
 
Energy saving audit project( mgtc)
Energy saving audit project( mgtc)Energy saving audit project( mgtc)
Energy saving audit project( mgtc)
 
utilzing wasted flared gas
utilzing wasted flared gasutilzing wasted flared gas
utilzing wasted flared gas
 
Schneider process automation power industry solutions
Schneider process automation power industry solutionsSchneider process automation power industry solutions
Schneider process automation power industry solutions
 
6 ltaa8.9 g2(英文版)
6 ltaa8.9 g2(英文版)6 ltaa8.9 g2(英文版)
6 ltaa8.9 g2(英文版)
 
Apex Microturbine Powerpoint
Apex Microturbine PowerpointApex Microturbine Powerpoint
Apex Microturbine Powerpoint
 
Variable Speed Pumping in Condensing Boiler Systems
Variable Speed Pumping in Condensing Boiler SystemsVariable Speed Pumping in Condensing Boiler Systems
Variable Speed Pumping in Condensing Boiler Systems
 
Thermal power-plant
Thermal power-plantThermal power-plant
Thermal power-plant
 
Cogeneration Concept
Cogeneration ConceptCogeneration Concept
Cogeneration Concept
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutions
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE
 
Energyes division ener termopac line 2015 ev v02
Energyes division ener termopac line 2015 ev v02Energyes division ener termopac line 2015 ev v02
Energyes division ener termopac line 2015 ev v02
 
Energyes Division EnerTermoPac Line 2015 EV V02
Energyes Division EnerTermoPac Line 2015 EV V02Energyes Division EnerTermoPac Line 2015 EV V02
Energyes Division EnerTermoPac Line 2015 EV V02
 

Último

Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja Nehwal
 
infant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptxinfant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptxsuhanimunjal27
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxmirandajeremy200221
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfParomita Roy
 
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...Delhi Call girls
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdftbatkhuu1
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfAmirYakdi
 
SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxjanettecruzeiro1
 
VVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts Service
VVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts ServiceVVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts Service
VVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts Servicearoranaina404
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)amitlee9823
 
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵anilsa9823
 
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...amitlee9823
 
2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptxsuhanimunjal27
 
Pastel Portfolio _ by Slidesgo.pptx. Xxx
Pastel Portfolio _ by Slidesgo.pptx. XxxPastel Portfolio _ by Slidesgo.pptx. Xxx
Pastel Portfolio _ by Slidesgo.pptx. XxxSegundoManuelFaichin1
 
Tapestry Clothing Brands: Collapsing the Funnel
Tapestry Clothing Brands: Collapsing the FunnelTapestry Clothing Brands: Collapsing the Funnel
Tapestry Clothing Brands: Collapsing the Funneljen_giacalone
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...home
 
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...Delhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceanilsa9823
 

Último (20)

Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
 
infant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptxinfant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptx
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptx
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
 
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Vasundhra (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
Editorial design Magazine design project.pdf
Editorial design Magazine design project.pdfEditorial design Magazine design project.pdf
Editorial design Magazine design project.pdf
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
 
SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptx
 
VVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts Service
VVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts ServiceVVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts Service
VVIP CALL GIRLS Lucknow 💓 Lucknow < Renuka Sharma > 7877925207 Escorts Service
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Escorts Service Nagavara ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Brookefield Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
 
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
RT Nagar Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bang...
 
2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx
 
Pastel Portfolio _ by Slidesgo.pptx. Xxx
Pastel Portfolio _ by Slidesgo.pptx. XxxPastel Portfolio _ by Slidesgo.pptx. Xxx
Pastel Portfolio _ by Slidesgo.pptx. Xxx
 
Tapestry Clothing Brands: Collapsing the Funnel
Tapestry Clothing Brands: Collapsing the FunnelTapestry Clothing Brands: Collapsing the Funnel
Tapestry Clothing Brands: Collapsing the Funnel
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
 
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
call girls in Kaushambi (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝...
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
 

Power plant-basics

  • 1. POWER GENERATION PROCESS BASICS
  • 2. BOILER / STEAM TURBO-GENERATOR UTILITY PLANT 40% Steam Condenser 20% Stack Lake Steam 6% Aux. Power + Losses 34% Electricity 100% Fuel Air Boiler Steam Turbine Generator Transmission THERMAL EFFICIENCY - 34%
  • 3. BOILER / STEAM TURBINE-GENERATOR INDUSTRIAL CO-GENERATION Process Steam 65% 15% Process Plant Stack Steam 5% Aux. Power + Losses 15% Electricity Fuel 100% Air Boiler Steam Turbine Generator Transmission THERMAL EFFICIENCY - 80%
  • 4. SIMPLE CYCLE COMBUSTION (GAS) TURBINE 57-62% 100% Fuel Stack Combuster 3% Aux Power + Losses 35-40% Electricity Air Compressor Turbine Generator Transmission THERMAL EFFICIENCY - 35-40%
  • 5. GAS TURBINE INDUSTRIAL CO-GENERATION PLANT 20% Stack Stack Supplementary/ Auxiliary Fuel (Optional) Process Steam Process Plant 100% Fuel Combuster Exhaust Gas Air Compressor Turbine Generator Transmission
  • 6. GAS TURBINE 28% COMBINED CYCLE POWER PLANT Steam Condenser 20% Stack Stack Steam Lake Supplementary Fuel (Optional) 100% Fuel Steam Turbine Generator Transmission Combuster Exhaust Gas 12-15% Electricity Air 6% Aux. Power + Losses 35-40% Electricity Compressor Turbine Generator Transmission Thermal Efficiency - 45-55%
  • 7. UTILITY PLANT - FUNCTIONAL BLOCK DIAGRAM Switch Yard System Ash Handling System Station Electrical System Boiler Steam & Water System Air & Flue Gas System BOILER Fuel Preparation System Fuel Firing System Boiler Miscellaneous Systems Boiler Feed Pumps & UNIT#2 Deaerator System Turbine Steam System TURBINE- HP & LP Heaters System GENERATOR Turbine Supervisory & Control System Generator & Electrical System Turbine Miscellaneous Systems Turbine Bypass System Fuel Handling System DM Plant Station Miscellaneous Systems
  • 8. CAPTIVE POWER PLANT - FUNCTIONAL BLOCK DIAGRAM Switch Yard System Ash Handling System Station Electrical System Steam & Water Air & Flue Gas BOILER Fuel Preparation Fuel Firing Steam UNIT#2 UNIT#3 TG HP & LP Heaters Supervisory & Control Generator & Electrical Miscellaneous Systems BFP’s & Deaerator System Fuel Handling System DM Plant Station Miscellaneous Systems
  • 10. BASIC DIAGRAM OF A BOILER Steam Water Steam / Water System Blowdown Fuel Flue Gas Mixing of Heat Transfer Fuel & Air Surface Furnace Air Ash
  • 11. SALIENT FEATURES OF MODERN INDUSTRIAL & UTILITY BOILER • STEAM BOILER • WATER TUBE • SUPERHEATED STEAM • HIGH PRESSURE • WATER COOLED FURNACE • WATER CIRCULATION
  • 12. COMBUSTION REQUIREMENTS Sufficient Combustion Air Temperature Fuel Combustion Mixing within above is Time Flammable Ignition Gasified Temperature Range Point Turbulence 3 T’s of Combustion
  • 13. BASIC COMBUSTION CHEMISTRY Complete Heat (Air) Oxygen Fuel Flue Gas Products H2 H2O O2 + C CO2 Incomplete Heat Oxygen Fuel Flue Gas Products H2 H2O O2 + C CO2 CO H2 C • Other Combustibles - Sulphur to Sulphur Oxides • Non-combustible - Nitrogen to Nitrogen+Nitrous Oxides • Ash
  • 14. BOILER WATER & STEAM SYSTEM Hot Reheat Steam Spray Water Main Steam Drum Attemperator Attemperator Cold Final Primary Final Reheat Platen Primary Re Re Super Steam Super Super Heater Heater Heater Spray Heater Heater Water Down Comers Flue Gas Economiser Feed Water Furnace Flue Gas Water Wall Out to Risers Air Heater Bottom Ring Header Simplified Process Diagram
  • 15. BOILER WATER & STEAM SYSTEM Process Performance Highlights • Heat Transfer by Radiation and Convection • Boiler Water Circulation - Natural or Controlled • Heat Transfer depends on Heat Transfer Area & Time • Heat Transfer is affected by Fouling, Boiler Pressure, Boiler Water Quality and % MCR Load
  • 16. BOILER WATER & STEAM SYSTEM Major Equipment • Economiser - Pre-heats Boiler Feed water • Boiler Drum - Separates water from steam and reduce solids in steam • Water Walls - Absorb heat from flue gas to evaporate boiler water • Superheaters - Heat up steam coming from boiler drum • Reheaters - Heat up steam coming from High Pressure turbine • Attemperators - Reduce superheat from steam
  • 17. BOILER WATER & STEAM SYSTEM Process Regulation • Drum Level - Regulation of Feed Water flow • Drum Water Quality - Blow down / Chemical Dozing • Fouling of Heat Transfer Surfaces - Blowdown / Soot Blowing • Main Steam Temperature - Attemperation / Burner Tilt • Hot Reheat Steam Temperature - Burner Tilt / Attemperation • Main Steam Pressure - Regulation of Combustion
  • 18. AIR & FLUE GAS SYSTEM To Air Cooled PA FAN A To Hot To Cold Guns PA Header PA Header From Scanner Air Fans FD Fans PA FAN B WINDOX A AH A ESP A P F L R E T I T ID Fan A FURNACE H C N N S Chimney O S S H H H ID Fan B ESP B AH B WINDBOX B FD FAN A FD FAN B Simplified Process Diagram
  • 19. AIR & FLUE GAS SYSTEM Process Performance Highlights • Generation of Draft - Natural / Induced / Forced / Balanced • Supply of Air for Transport of Pulverised Coal • Pre-heating of Air • Distribution of Air in Combustion Chamber • Recirculation of Gas • Fan capacity depends on Flow, Density & System Resistance • Fan performance is affected by temperature, density, barometric pressure and speed • Flue Gas Cleaning • Gas flow is restricted by ash deposits on boiler surfaces
  • 20. AIR & FLUE GAS SYSTEM Major Equipment • Air Path - Forced Draft Fans, Steam Coil Air Pre-heater, Regenerative Air Pre-heater & Wind-box • Gas Path - Induced Draft Fans and Stack • Gas Recirculation - Gas Recirculating Fans • Flue Gas Cleaning - Mechanical Precipitator, Electrostatic Precipitator and Gas Scrubber • Dampers
  • 21. AIR & FLUE GAS SYSTEM Process Regulation • Furnace Draft - ID Fan Inlet Vane Control and/or Variable Speed • Secondary Air Flow - FD Fan Variable Pitch Control • PA Header Pressure - PA Fan Inlet Vane Control • RAPH Cold End Temperature - SCAPH Control • Gas Recirculation - Damper Control
  • 22. FUEL PREPARATION SYSTEM - COAL Raw Coal Bunker To Mill Discharge Valves To Hot PA Other Coal Feeder Mills Coal+Air to Burners Mill A Cold PA To Other Mills To Other Mills Seal Air Fans Simplified Process Diagram
  • 23. FUEL PREPARATION SYSTEM - GAS/OIL Fuel Gas Supply To Burners FCV FGTV PRV’s FUEL GAS Atomising Steam/Air PCV Fuel Oil Return Short Long Recirc Recirc PCV Fuel Oil Oil Heater To Burners Supply FCV FOTV Steam Fuel Oil Pumps FUEL OIL Simplified Process Diagram
  • 24. FUEL PREPARATION SYSTEM Process Performance Highlights • Coal Pulverizing - Direct / Indirect Firing • Coal Transport and Drying • Fuel Gas Pressure Regulation • Fuel Oil Pumping & Filtering • Fuel Oil Pressure & Viscosity Regulation • Gas Pressure & Oil Pressure/Temperature affect Boiler Load
  • 25. FUEL PREPARATION SYSTEM Major Equipment • Coal Mills - Tube Ball / Bowl / Impact • Raw Coal Feeders - Chain / Belt / Rotary / Gravimetric • Coal / Air Dampers, Gates & Discharge Valves • Fuel Oil Pumps & Heaters • Seal Air Fans • Coal Bunkers • Vapour Fans
  • 26. FUEL PREPARATION SYSTEM Process Regulation • Coal Flow - Raw Coal Feeder Speed • Coal/Air Temperature & Flow - Cold & Hot PA Flows
  • 27. FUEL FIRING SYSTEM OFA OFA FF EA F FA (2) (3) Air Damper EF AA E OFA Over Fire Air EA End Air DE FA Fuel Air D AA Aux. Air Front Wall Coal Burner CD (4) (1) Plan Fire Ball Scanner C (Corner Designation) LFO?HFO Burner BC B HFO Burner Oil Flame Scanner AB A HEA Igniter AA Typical Corner Arrangement for a Tangentially Fired System
  • 28. FUEL FIRING SYSTEM Process Performance Highlights • Fuel Firing - Front / Tangential • Fuel Oil Atomisation - Mechanical / Air / Steam • Flame Ignition • Air Distribution • Fuel Combustion
  • 29. FUEL FIRING SYSTEM Major Equipment • Burners • Ignitors • Flame Scanners • Burner Tilt Mechanism • Wind Box • Dampers
  • 30. FUEL FIRING SYSTEM Process Regulation • Furnace to Wind Box Differential Pressure • Fuel Air Flows • Fuel Firing • Emergency Shutdown • Flame Monitoring • Oil Support for Coal Flame Stability
  • 31. BOILER MISCELLANEOUS SYSTEMS Boiler Auxiliary Cooling Water System • Ensures continuous supply of cooling water to Boiler & it’s auxiliaries • Consists of Overhead Tank, Pumps & Heat Exchangers Chemical Dosing System • Prepares & supplies chemicals for treatment of Boiler Water • Consists of Preparation Tanks, Mixers & Metering Pumps
  • 32. DEAERATION & FEED PUMPING SYSTEM Condensate from LP Heater To HP HP Heater Drains Aux. Steam Heaters CRH Steam Deaerator IPT Extraction Aux. Steam Steam for Feed Storage Tank Pegging To HP Bypass Spray Hydrazine T o APRDS Dosing Spray Ammonia Recirculation Dosing Valve M Discharge Valve Boiler Feed Pumps Simplified Process Diagram
  • 33. DEAERATION & FEED PUMPING SYSTEM Process Performance Highlights • Boiler Water pre-heating & air removal • Maintain positive Suction Pressure for Feed Pumps • Feed Water Pumping to Boiler
  • 34. DEAERATION & FEED PUMPING SYSTEM Major Equipment • Boiler Feed Pumps • Hydraulic Coupling • Deaerator
  • 35. DEAERATION & FEED PUMPING SYSTEM Process Regulation • Deaerator Pressure • Deaerator Level • BFP Minimum Recirculation • Feed Pump Speed
  • 37. LAWS OF THERMODYNAMICS • Conservation of Energy - Heat may be converted in to work and work may be converted in to heat, in accordance with a certain natural proportionality constant (ENERGY CAN NOT BE DESTROYED) • Not all of a given quantity of Heat can be converted in to useful Work, because of irreversbility in the process (ENTROPY OF THE UNIVERSE IS INCREASING)
  • 38. BASIC RANKINE CYCLE T Heat Available for Work Unavailable Heat S
  • 39. IMPROVING RANKINE CYCLE • Superheating • Increased Pressure • Decreased Exhaust Pressure • Regenerative Feed Heating • Reheating
  • 40. STEAM TURBINE TYPES • Condensing Turbine • Back Pressure Turbine • Regenerative Turbine •Controlled Extraction • No. of Cylinders • Speed - Constant / Variable • Single / Double Flow
  • 41. TURBINE STEAM SYSTEM Main Steam ESV CV HP IP Turbine Turbine LP Turbine Cold Reheat Steam Condenser Hot Reheat Steam IV CV Extraction Steam Simplified Process Diagram
  • 42. TURBINE STEAM SYSTEM Major Equipment • Turbine - Casing, Rotor & Blades • Emergency Stop Valves • Control Valves • Condenser
  • 43. TURBINE STEAM SYSTEM Process Regulation • Steam Admission • Emergency Shutdown
  • 44. REGENERATIVE FEED HEATING SYSTEM To From BFP To Boiler Discharge Deaerator LPT CRH Extraction Steam Steam To Deaerator LP HP HTR HTR LPT Condenser IPT Extraction Steam Gland Extrn. Leakoff Steam LP Steam HP HTR Minimum Makeup HTR Recirculation Hotwell To LPT Extraction Condenser LP Drain To GSC HTR CLR HP Condenser LP Flash Flash Tank Tank Condensate Extraction Pump Simplified Process Diagram
  • 45. REGENERATIVE FEED HEATING SYSTEM Process Performance Highlights • Pumping of Condensate from Hotwell to Deaerator •Gradual Heating of Feed Water Temperature • Minimise Heat Loss from the Cycle
  • 46. REGENERATIVE FEED HEATING SYSTEM Major Equipment • HP Heaters • LP Heaters • Drain Cooler • Condensate Extraction Pumps
  • 47. REGENERATIVE FEED HEATING SYSTEM Process Regulation • Hotwell Level • Heater Level • Minimum Flow through CEP & GSC
  • 48. TURBINE GOVERNING & CONTROL SYSTEM Governing Oil System Turning Gear Jacking Condenser Oil Vacuum System System Lubricating Gland Turbine Oil Steam Drain System System System OIL SYSTEMS VACUUM SYSTEM WARM UP SYSTEM Functional Block Diagram
  • 49. TURBINE GOVERNING & CONTROL SYSTEM Process Performance Highlights • Shaft & Bearing Protection • Electro-hydraulic Governing • Maintain Vacuum in Condenser • Supply Steam to Turbine Glands • Warming up of Turbines and their Valves • Emergency Shutdown in case of Unsafe Conditions
  • 50. TURBINE GOVERNING & CONTROL SYSTEM Major Equipment • Oil Pumps, Turning Gear & Jacking Oil Pump • Hydraulic Actuators for Turbine Valves • Vacuum Pumps • Gland Steam Pressure Regulator • Oil Coolers & Temperature Regulator
  • 51. TURBINE GOVERNING & CONTROL SYSTEM Process Regulation • Speed / Load / Frequency Control • Gland Steam Pressure Control
  • 52. TURBINE MISCELLANEOUS SYSTEMS Condenser Cooling Water System • Supplies Cooling Water Condensation of Turbine Exhaust Steam Turbine Auxiliary Cooling Water System • Ensures continuous supply of cooling water to Turbine & it’s auxiliaries • Consists of Overhead Tank, Pumps & Heat Exchangers Chemical Dosing System • Prepares & supplies chemicals for treatment of Condensate • Consists of Preparation Tanks, Mixers & Metering Pumps
  • 53. TURBINE MISCELLANEOUS SYSTEMS Condenser Cooling Water System CW Return Header Cooling Condenser Waterbox Tower To A B Unit#2 CW Sump CW Makeup Water CW Supply Header Circulating Water Pumps Simplified Process Diagram
  • 54. TURBINE MISCELLANEOUS SYSTEMS Condenser Cooling Water System Major Equipment • Cooling Towers • CW Pumps Process Performance Highlights • Steam Condensation • Cooling of Condenser CW - Cooling Tower / Lake Process Regulation • Condenser Tube Cleaning - Online / Back flushing
  • 55. TURBINE BYPASS SYSTEM Main Steam To HPT Feed Water PRV Block Spray Valve Control Valve CRH From HPT HRH To IPT Condensate Condenser Simplified Process Diagram
  • 56. TURBINE BYPASS SYSTEM Process Performance Highlights • Enable Boiler Operation for Quick Re-start after Boiler Trip and during Turbine Start-up • Control MS Pressure after Turbine Trip or Sudden Load Throw-off
  • 57. TURBINE BYPASS SYSTEM Process Regulation • MS Pressure Reduction & Desuperheating • HRH Steam Pressure Reduction & Desuperheating
  • 59. WORKING PRINCIPLE • Converts Mechanical Energy in to Electrical Energy • Based on Electro-magnetic Induction E = 4.44 O FN volts E - e. m. f. O - Strength of Magnetic Field F - Frequency N - No. of Turns in a Stator Winding Coil F = Pn/120 P - No. of Poles n - Revolution per second of Rotor
  • 60. GENERATOR EFFICIENCY & LOSSES • Efficiency = Output Electrical Energy Input Mechanical Energy • Losses - Bearing Loss, Copper Loss & Iron Loss • Typically Efficiency is 90-97%
  • 61. GENERATOR & UNIT ELECTRICAL SYSTEM Metering & Protective Relays Generator Seal Transformer Oil System Generator Hydrogen Synchronising Cooling Sceme System Unit Field Stator Auxiliary Excitation Cooling Water Transformer System System ELECTRICAL SYSTEMS MECHANICAL SYSTEMS Generator Functional Block Diagram
  • 62. GENERATOR & UNIT ELECTRICAL SYSTEM Isolator 132 KV Bus I 132 KV Bus II Circuit Breaker Unit GT Auxiliary Transformer From 11 kV From Station Station Bus Bus Generator 6.6 kV Unit Bus A 6.6 kV Unit Bus B Key One Line Diagram
  • 63. GENERATOR & UNIT ELECTRICAL SYSTEM Process Performance Highlights • Conversion of Mechanical Energy in to Electrical Energy • Field Excitation • Stator Winding Cooling by Distillate / Air • Rotor Winding Cooling by Hydrogen / Air • Hydrogen Sealing by Oil • Synchronisation & Voltage Transformation • Emergency Shutdown in case of Unsafe Conditions
  • 64. GENERATOR & UNIT ELECTRICAL SYSTEM Major Equipment • Generator - Stator, Rotor, Armature Windings, Field Windings • Field Excitation - Exciter (DC/AC), Static Rectifying Unit & AVR • Bus Ducts & Transformers • Circuit Breakers & Protective Relays • H2 Cooling - Fans, Dryers & Coolers • Stator Water Cooling - Pumps, Coolers & Overhead Tank • Seal Oil - Pumps, Coolers & Differential Pressure Regulator
  • 65. GENERATOR & UNIT ELECTRICAL SYSTEM Process Regulation • Field Excitation • Generator Synchrinisation • Voltage Regulation
  • 66. POWER PLANT OPERATION & MAINTENANCE
  • 67. OPERATION & MAINTENANCE Efficiency Calculations • Boiler Efficiency - Direct / Heat Loss Method • Turbine Heat Rate - Total Heat Supplied/ KWHR • Plant Heat Rate - Heat Supplied/ KWHR
  • 68. OPERATION & MAINTENANCE Factors Affecting Plant Performance • Flue Gas Exit Temperature • Excess Air • Unburnt Fuel • Steam Temperature • Condenser Back Pressure • FW Temperature at Eco Inlet • Auxiliary Power Consumption • Make up Water Flow • Optimum Loading
  • 69. OPERATION & MAINTENANCE • Start-up & Shutdown Monitoring • Trip Analysis - Boiler / Turbine / Generator • Equipment Run-Hour Monitoring • History Trending • Alarm Management • Division of Operational Responsibilities • Economic Load Allocation & Load Shedding (CPP)
  • 71. POWER PLANT AUTOMATION & CONTROL Burner Management System • Furnace Purge Supervision • Secondary Air Damper Modulation, On/Off Control and Supervision • Light/Heavy Oil On/Off Control and Supervision • Pulveriser and Feeder On/Off Control and Supervision • Flame Scanning • Overall Boiler Flame Failure Protection • Boiler Trip Protection
  • 72. POWER PLANT AUTOMATION & CONTROL Soot Blower Sequential Control • Wall Blowers • Long Retractable Blowers • Air Heater Blowers
  • 73. POWER PLANT AUTOMATION & CONTROL Automatic Turbine Run-up System • Oil Supply Control - Turning Gear, Auxiliary Oil Pumps, Emergency Oil Pump, Jacking Oil Pump and Lube Oil Temperature • Condensate & Evacuation Control - Condensate Extraction Pumps, Gland Steam Pressure, Vacuum Pumps and Vacuum Breaker Valve • Turbine Control - Steam & Metal Temperature Matching, Warming up of HP ESV & CV, Steam Rolling & Acceleration and Auto Synchroniser
  • 74. POWER PLANT AUTOMATION & CONTROL Turbine Stress Evaluator • Calculation of Actual and Permissible Thermal Stress Values • Comparison of Actual with Permissible Stress Values and Computation of Available Margin • Optimize Start up, Operation and Shut down
  • 75. POWER PLANT AUTOMATION & CONTROL Automatic Turbine Tester • Safety Devices - Remote Trip, Over-speed, Low Vacuum and Thrust Bearing • HP/IP Valves - HP Stop and Control Valves, and IP Stop and Control Valves
  • 76. POWER PLANT AUTOMATION & CONTROL Electro-hydraulic Governing System • Speed Control • Load Control • Load Shedding • Initial Pressure Control
  • 77. AUTOMATION & CONTROL CRITICAL CLOSED LOOPS • CMC - Boiler Follow / Turbine follow / Coordinated (Utility) • Header Pressure Control (CPP) • Combustion - Fuel / Air Flow • Steam Temperature • Drum Level • Furnace Draft
  • 78. AUTOMATION & CONTROL OPEN LOOP CONTROL • Interlocking - Safe Startup / Shutdown • Protection - Emergency Shutdown (Trip) • Sequencial Control - Efficient Startup / Shutdown CRITICAL OPEN LOOPS • ID/FD /PA Fans • BFP
  • 80. POWER PLANT INSTRUMENTATION • Temperature - T/C & RTD • Pressure • Level - DP / Displacement / Hydra Step Drum Level Indicator • Flow - DP / Annubar / Mag-flow • Turbine Supervisory - Vibration/ Expansion/ Axial Shift/ Eccentricity • Steam & Water Analysers - Conductivity/ pH/ DO2/ Silica • Gas Analysers - O2/ CO2/ CO (in Flue Gas) Pollution Monitor H2 Purity (in Generator)