Table of Contents
1.0      Introduction............................................................................................................. 3
1.0      Introduction............................................................................................................. 3
   1.1      Why use a batch tank or a day tank?................................................................... 3
   1.2      Benefits of the Chemical Batching System ........................................................ 3
   1.3      Theory of operation............................................................................................. 4
2.0     Specifications.......................................................................................................... 5
   2.1      Electrical ............................................................................................................. 5
   2.2      Mechanical.......................................................................................................... 5
   2.3      Chemical Batching System Program Limits....................................................... 5
      2.3a Water relay (1) ................................................................................................ 5
      2.3b Pump relays (4) ............................................................................................... 5
3.0     Un-Packing & instillation of the ............................................................................. 6
   3.1 Unpacking the unit.................................................................................................... 6
   3.2 Mounting the controller ............................................................................................ 6
   3.3 Electrical Installation ................................................................................................ 6
4.0      System Overview .................................................................................................... 9
   4.1 Front Panel .............................................................................................................. 10
   4.2      Display .............................................................................................................. 10
   4.3      Key Pad............................................................................................................. 10
   4.4      Led indictor lights ............................................................................................. 10
   4.5      Start up Initial ................................................................................................... 11
   4.6      Normal start up ................................................................................................. 11
   4.7      Shutdown .......................................................................................................... 11
5.0      Operating Instructions........................................................................................... 11
8.0 Index ........................................................................................................................... 13




                                                 Table of Figures
Figure 1: Wiring configuration ........................................................................................... 7
Figure 2: The CBS controller within a typical system including pumps and day tank ...... 8
Figure 3: The CBS with the faceplate removed.................................................................. 9
Figure 4: The Features displayed on the CBS Faceplate .................................................. 10




CBS_Manual_R015                                           Page 2 of 13
1.0 Introduction
      Thank you for purchasing the Chemical Batching System. The Chemical Batching
      System was designed to fill a large variety of liquid batch tank needs. The purpose
      of the Chemical Batching System is to aid in the operation of a boiler water
      treatment system. Currently boiler operators using day tanks must manually add
      treatment chemicals by hand to the dilution water in their day tanks. As with any
      manual operation errors can be made resulting in increased costs. Some of these
      incurred costs would be due to overuse or underuse of treatment chemicals,
      inconsistently mixed day tank batches and the potential hazards of hand mixing
      hazardous chemicals. Potential savings would include reducing operator workload,
      consistent chemistry in the boilers, resulting in lower maintenance costs.

        1.1 Why use a batch tank or a day tank?
              The reasons to use a batching tank or day tank in a boiler chemical treatment
              program are many.
                 • A batch tank system is an alternative to using an “all in one”
                     chemical treatment product. These products may or may not meet
                     all the requirements of your system.
                 • This system dilutes concentrated chemical products, avoiding line
                     and nozzle plugging. Generally it is more cost effective in terms of
                     pounds of water treated per unit cost to purchase concentrated
                     chemicals from vendors rather than their water diluted counterparts.
                     Depending on the application, this could create line or nozzle
                     plugging problems. Diluting these concentrated products will reduce
                     plugging problems.
                 • It is advantageous to avoid concentrate chemical corrosion/erosion
                     within the boiler. Some water treatment chemicals have low
                     solubility in water and will not dilute without aggressive mixing.
                     Pre-mixing the chemicals in a day tank will dissolve and dilute these
                     chemicals before they enter the boiler system.
                 • Some boiler treatment chemicals are extremely corrosive in their
                     neet form. By diluting these chemicals in a day tank system you can
                     reduce neet chemical corrosion effects.

        1.2 Benefits of the Chemical Batching System
              The Chemical Batching System provides accurate, hands free, on demand
              chemical blending of boiler treatment chemicals. The same concentration of
              chemicals will be blended for each batch.
                 • Reduced operator involvement. Operators need only to replace
                    empty chemical containers and re-prime chemical pumps.
                 • No hand mixing of chemicals to make up batch tanks.
                 • Consistent blending of chemicals in every batch.
                 • Ability to program several chemical recipes for different operating
                    conditions. (Summer/Winter operations, weekend/weekday
                    operations, etc.)


CBS_Manual_R015                        Page 3 of 13
•   Provides the ability to adjust chemical concentrations in the day
                       tank.

        1.3       Theory of operation.
The chemical batching systems is essentially a sensor driven system. A day/batch tank is
set up with a high water level sensor and a low water level sensor. The tank feeds treated
water to the boiler. The level sensors control the cycles of the chemical batching
systems, which consists of five relays. Relays numbers 1 through 4 turn the chemical
delivery pumps on and off. Relay number 5 turns the water supply on and off.

    1. The dilute boiler chemical solution is fed to the boiler from a batched tank.
    2. The water level decreases below the actuation point of the low water level sensor
       in the day tank.
    3. An LED indicator appears lit on the control interface panel.
    4. Upon actuation of the low level sensor the filling/treatment cycle begins.
    5. The 4 timed relays begin their countdowns and the sensor relay actuates.
           a. The 4 timed relays control up to 4 reagent pumps for adding up to 4 water
                treatment chemicals.
           b. Channels 1 through 4 are to be set with the Safety Timer Feature which
                will not allow for the day tank to overflow, due to the relatively slow rate
                of the pumps in use.
             th
    6. The 5 relay actuates a valve which fills the tank with city water.
    7. The 5th relay terminates upon activation of the high water level sensor.
           a. The volume of city water being added to the tank remains constant. This
                allows the amount of reagent to be added also to remain constant. The
                volume flow rate of the pumps is known; therefore to achieve the correct
                addition of reagent, one can set the amount of time for each pump to run to
                add the correct volume of reagent.
    8. The dilute chemical solution is fed to the boiler




CBS_Manual_R015                          Page 4 of 13
2.0 Specifications
        2.1 Electrical
                  •   Input Power
                              Voltage:                100 – 250VAC
                              Frequency:              47-63Hz
                              Input Current:          10A Max @ 115VAC
                                                      20A Max @ 230VAC

                  •   Output power
                              Max Switched Voltage:           250VAC
                              Max Switched Current:           5A
                              Max Switched Power:             1250VA, 150W

                  •   Level indictors
                               On/Off dry contact type 5 VDC

                  •   Agency Approvals
                              UL               TBD


        2.2 Mechanical

              Enclosure Material               Molded Polystyrene
              NEMA Rating                      NEMA 12/13
              Dimensions                       10.25 X 12 X 5.25
              Display                          LCD 16 X 2 Character backlit liquid crystal
              Operating Temperature            32-120 deg F (0 to 50 deg C)

              Level sensor(s)                  2 Dry contact liquid level sensors


        2.3 Chemical Batching System Program Limits
              2.3a     Water relay (1)
                       0 seconds to 99 minutes
                       Triggered by low liquid level sensor
                       Secured by high liquid level sensor or programmable time out
                       safety function (see section 5.5)

              2.3b     Pump relays (4)
                       0 seconds to 99 minutes
                       Triggered by low liquid level sensor
                       Secured by Program (see section 5.0)


CBS_Manual_R015                       Page 5 of 13
3.0 Un-Packing & instillation of the

        3.1 Unpacking the unit
                  Inspect the unit and the contents of the package. Please notify the carrier
                  immediately if there are any signs of damage to unit. Contact your
                  distributor if there are any missing parts.

        3.2 Mounting the controller
                  The Chemical Batching System should be mounted in close proximately to
                  the batching tank and the chemical storage location ideally the controller
                  will be mounted on a stable horizontal surface at eye level. The chemical
                  pumps are normally located 2 to 5 feet away to allow the chemical pumps
                  to be plugged it to the controller. Please consult chemical pump
                  manufacture for the proper suction and discharge line sizing and length.
                  The controller requires the following clearances:

                         Top:            4”
                         Bottom          10”
                         Left            4”
                         Right           4”
                         Front           24”


        3.3 Electrical Installation
                  CAUTION! There are live circuits inside the controller when the
                  controller is energized. The front panel, or plug access panel must never
                  be opened before power is removed from the controller

                  CAUTION! The electrical installation of the controller must be done by a
                  trained personal only.




CBS_Manual_R015                           Page 6 of 13
Figure 1: Electrical Layout




CBS_Manual_R015         Page 7 of 13
PDK Controller



                                                                                              AC Power In
                                                                                              110 Volts AC




                                                                                                                                        High
                                                                                                                                        Level
                                                                                              Y
                                                                                                                                        Sensor
                                                                                              Strainer            Solenoid
                                                                                 Water                            Valve
                                                                                 Supply

                                                                                                         Water Fill line angled
                                                                                         is
                                                                             eta ry an d                 to promote good
                                                                rd p ro p ro                                                            Low
                                        in g is to b e co n side se s o n ly. It is th e                 mixing in Tank
                            T his dr a w in fo rm a tio n p ru po                                                                       Level
                                          r
                            in tend ed fo o f P D K , In c.                                                                             Sensor
                                            ty
                             so le pro p er                                                                            Pumped to
                                                                                                                       Feed Water
                                                                                                                       Line or Boiler
                                                                                                                       Drum

       PDK                           Chemical Batching System 1
             Incorporated


(401) 294-0012     tech@pdkeng.com
                                     Wiring Schematic


                                                   Figure 2: Typical system installation including pumps and day tank




                 CBS_Manual_R015                                                              Page 8 of 13
4.0     System Overview




Figure 3: The CBS with the faceplate removed




CBS_Manual_R015                            Page 9 of 13
4.1 Front Panel

                                                                            Liquid Level Sensor
                                                                            Indicators




                                                                            LCD Display




                                                                            Up Arrow

                                                                            Back Arrow


                                                                             Key Pad


                                                                              Pump Status Indicators

Figure 4: The Features displayed on the CBS Faceplate



4.2     Display
                  The LCD is a 16x2 backlit module. If the characters are not readable, the
                  contrast can be adjusted using the potentiometer (R3) on the back of the
                  interface printed circuit board.


4.3     Key Pad
                  This is the user interface that is used to enter custom programs, change
                  settings, and review stored programs.


4.4     Led indictor lights

                  The led indicators display the status of the liquid level sensors and relays
                  1-5 (chemical pumps and dilution water fill solenoid).




CBS_Manual_R015                            Page 10 of 13
4.5     Start up Initial
                  After unit is installed plug it in and turn it on you will find pre installed
                  programs in the unit (listed below) you may use them as is, modify them
                  or delete them all


4.6     Normal start up
                  Once unit is programmed the parameters are stores in memory. Simply
                  verify water supply in on, the chemical pumps are primed and there is
                  sufficient chemical the unit will run normally


4.7     Shutdown
                  To secure the controller, turn off the power to the controller. For extended
                  shutdowns, the chemical lines should be flushed with water. Disconnect
                  water supply from the solenoid valve and remove chemicals. Store the
                  chemicals according to the instructions provided by your chemical
                  supplier. Pump lines should be flushed by placing chemical suction lines
                  in fresh water and starting the chemical pumps using the Prime mode on
                  the controller.


5.0 Operating Instructions
When you initialize the Chemical Batching System it will be running the last program
that was running before power down. In the case of factory default settings (ie. new unit)
Program 0 will be the default program running. To exit the current program into the
Main Menu press the back arrow key.

The up and back arrow keys are used to scroll through the Main Menu options. The
Main Menu choices are:

    •   Run
    •   Prime
    •   View Program
    •   Edit Program
    •   Safety Timer
    •   Program Delay
    •   Sensor Settings
    •   Factory Reset




CBS_Manual_R015                           Page 11 of 13
5.1     Run
        Allows user to select a program to run. Options are Programs 0 to 9. Program 0
        is not programmable; the default settings of program 0 are all relays are set to run
        for 00:00 (mm:ss). Program 0 is useful for periods of boiler shut down times.
        Programs 1-9 are programmable and are set at factory defaults of 0 mm:ss.


5.2     Prime
        Allows user to run Relays 1-5 for 10 seconds per quarter second that the button is
        held down. Used when adding or changing reagent containers. For example, if
        the button is depressed for 1 second, the pump will run in manual for 40 seconds
        total.


5.3     View Program
        Allows user to view program settings. Options are to view programs 0-9. This
        setting is useful for verifying controller settings.


5.4     Edit Program
        Allows user to edit custom programs 1-9. User can program times for relays 1-4.
        Relay 5 is strictly level sensor actuated and controls the water supply solenoid
        valve.


5.5     Safety Timer
        This is a safety feature intended to prevent overflow of your day tank in the event
        of a high-level sensor failure. This function limits the amount of time that the
        unit’s program can run. This time is user programmable and is generally set at
        125% of the maximum time it takes to fill the tank to the high level sensor. Fill
        times can vary depending on water supply line pressure. The factory default is 0
        for this function.


5.6     Program Delay
        This is an optional setting to add a delay between when the low level sensor
        actuates, and the fill cycle program begins. The factory default time is set at 0.
        The purpose of this option would be to allow the water supply valve to open
        before the chemical pumps to begin pumping.

5.7     Sensor Settings
        Allows the user to select the configuration of the liquid level sensors. The options
        are either normally open (NO) or normally closed (NC) sensors. The purpose of
        this function is to allow for the possibility of installing an alternative level sensor.
        The factory default settings are normally open.


CBS_Manual_R015                         Page 12 of 13
5.8       Factory Reset
          Resets all programmable functions back to factory settings. All the custom
          programs run times are set to 0, safety timer to 0, program delay to 0 and sensor
          settings to normally open (NO).,




6.0 Index
batching tank................................... 3, 6          program 0 .......................................... 12
contrast............................................... 10     Program Delay ............................ 11, 12
Edit Program............................... 11, 12             programs.......................... 10, 11, 12, 13
Factory Reset............................... 11, 13            Run ..................................................... 11
liquid level sensor................................ 5          Safety Timer ............................ 4, 11, 12
liquid level sensors ...................... 10, 12             Sensor Settings ............................ 11, 12
Main Menu ........................................ 11          Start up Initial ................................... 11
missing parts..........................................        View Program.............................. 11, 12
   ................See 3.1 Unpacking the unit                  Wiring .............................................. 2, 7
Prime ............................................ 11, 12




CBS_Manual_R015                                      Page 13 of 13

Más contenido relacionado

Destacado

Sushi is 何
Sushi is 何Sushi is 何
Sushi is 何31 00
 
The right college for me
The right college for meThe right college for me
The right college for mejsilvan93
 
Kowakae6 pre
Kowakae6 preKowakae6 pre
Kowakae6 pretaka_tako
 
Stroustrup10章雑感
Stroustrup10章雑感Stroustrup10章雑感
Stroustrup10章雑感31 00
 
Stroustrup11章雑感
Stroustrup11章雑感Stroustrup11章雑感
Stroustrup11章雑感31 00
 
How a conflict changes the way how people on Fandoms
How a conflict changes the way how people on FandomsHow a conflict changes the way how people on Fandoms
How a conflict changes the way how people on FandomsCleyton Souza
 
How to improve your memory
How to improve your memoryHow to improve your memory
How to improve your memoryannardiyani
 
Statistics for Class XI (CBSE)
Statistics for Class XI (CBSE)Statistics for Class XI (CBSE)
Statistics for Class XI (CBSE)mini4deb
 

Destacado (11)

Sushi is 何
Sushi is 何Sushi is 何
Sushi is 何
 
The right college for me
The right college for meThe right college for me
The right college for me
 
Kowakae6 pre
Kowakae6 preKowakae6 pre
Kowakae6 pre
 
Trabajo grado1
Trabajo grado1Trabajo grado1
Trabajo grado1
 
Signekursen
SignekursenSignekursen
Signekursen
 
Stroustrup10章雑感
Stroustrup10章雑感Stroustrup10章雑感
Stroustrup10章雑感
 
Local roofing service
Local roofing serviceLocal roofing service
Local roofing service
 
Stroustrup11章雑感
Stroustrup11章雑感Stroustrup11章雑感
Stroustrup11章雑感
 
How a conflict changes the way how people on Fandoms
How a conflict changes the way how people on FandomsHow a conflict changes the way how people on Fandoms
How a conflict changes the way how people on Fandoms
 
How to improve your memory
How to improve your memoryHow to improve your memory
How to improve your memory
 
Statistics for Class XI (CBSE)
Statistics for Class XI (CBSE)Statistics for Class XI (CBSE)
Statistics for Class XI (CBSE)
 

Similar a Chemical Batching System R015

Presentation1
Presentation1Presentation1
Presentation1Fady Punk
 
How to increase crude throughput in desalter applications
How to increase crude throughput in desalter applicationsHow to increase crude throughput in desalter applications
How to increase crude throughput in desalter applicationsHelena Barras (Goy)
 
Concentration monitoring
Concentration monitoringConcentration monitoring
Concentration monitoringKunal Vanjare
 
EDR 201: Advanced Electrodialysis Reversal (EDR)
EDR 201: Advanced Electrodialysis Reversal (EDR)EDR 201: Advanced Electrodialysis Reversal (EDR)
EDR 201: Advanced Electrodialysis Reversal (EDR)Saltworks Technologies Inc.
 
Continuous flow reaction/ Chemistry
Continuous flow reaction/ ChemistryContinuous flow reaction/ Chemistry
Continuous flow reaction/ ChemistryGagangowda58
 
Chemical reaction engineering
Chemical reaction engineeringChemical reaction engineering
Chemical reaction engineeringNurul Ain
 
Programmable logic controller (plc) for polymer mixing tank
Programmable logic controller (plc) for polymer mixing tankProgrammable logic controller (plc) for polymer mixing tank
Programmable logic controller (plc) for polymer mixing tankMohab Osman
 
Importance of three elements boiler drum level control and its installation i...
Importance of three elements boiler drum level control and its installation i...Importance of three elements boiler drum level control and its installation i...
Importance of three elements boiler drum level control and its installation i...ijics
 
Scale up of agitated vessels and static mixer
Scale up of agitated vessels and static mixerScale up of agitated vessels and static mixer
Scale up of agitated vessels and static mixerVivek5103
 
Microcontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation SystemMicrocontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation SystemIJMER
 

Similar a Chemical Batching System R015 (20)

Presentation1
Presentation1Presentation1
Presentation1
 
How to increase crude throughput in desalter applications
How to increase crude throughput in desalter applicationsHow to increase crude throughput in desalter applications
How to increase crude throughput in desalter applications
 
Flow Reactors.pdf
Flow Reactors.pdfFlow Reactors.pdf
Flow Reactors.pdf
 
Flow chemistry
Flow chemistryFlow chemistry
Flow chemistry
 
Concentration monitoring
Concentration monitoringConcentration monitoring
Concentration monitoring
 
Flow chemistry
Flow chemistryFlow chemistry
Flow chemistry
 
EDR 201: Advanced Electrodialysis Reversal (EDR)
EDR 201: Advanced Electrodialysis Reversal (EDR)EDR 201: Advanced Electrodialysis Reversal (EDR)
EDR 201: Advanced Electrodialysis Reversal (EDR)
 
Continuous flow reaction/ Chemistry
Continuous flow reaction/ ChemistryContinuous flow reaction/ Chemistry
Continuous flow reaction/ Chemistry
 
Chemical reaction engineering
Chemical reaction engineeringChemical reaction engineering
Chemical reaction engineering
 
Group 2
Group 2Group 2
Group 2
 
Programmable logic controller (plc) for polymer mixing tank
Programmable logic controller (plc) for polymer mixing tankProgrammable logic controller (plc) for polymer mixing tank
Programmable logic controller (plc) for polymer mixing tank
 
Importance of three elements boiler drum level control and its installation i...
Importance of three elements boiler drum level control and its installation i...Importance of three elements boiler drum level control and its installation i...
Importance of three elements boiler drum level control and its installation i...
 
Chronomite Laboratories, Inc.
Chronomite Laboratories, Inc.Chronomite Laboratories, Inc.
Chronomite Laboratories, Inc.
 
Reactor types.ppt
Reactor types.pptReactor types.ppt
Reactor types.ppt
 
Separatore pa 605
Separatore pa 605Separatore pa 605
Separatore pa 605
 
Scale up of agitated vessels and static mixer
Scale up of agitated vessels and static mixerScale up of agitated vessels and static mixer
Scale up of agitated vessels and static mixer
 
fire fighting System
fire fighting Systemfire fighting System
fire fighting System
 
4 reactors
4 reactors4 reactors
4 reactors
 
Microcontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation SystemMicrocontroller Based Automatic Sprinkler Irrigation System
Microcontroller Based Automatic Sprinkler Irrigation System
 
Control and dosing instruments catalog
Control and dosing instruments catalogControl and dosing instruments catalog
Control and dosing instruments catalog
 

Último

Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubaikojalkojal131
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in designnooreen17
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书zdzoqco
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfAayushChavan5
 
Create Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdfCreate Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdfworkingdev2003
 
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...mrchrns005
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Servicejennyeacort
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...katerynaivanenko1
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造kbdhl05e
 
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degreeyuu sss
 
Apresentação Clamo Cristo -letra música Matheus Rizzo
Apresentação Clamo Cristo -letra música Matheus RizzoApresentação Clamo Cristo -letra música Matheus Rizzo
Apresentação Clamo Cristo -letra música Matheus RizzoCarolTelles6
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一Fi sss
 
办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一F dds
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一z xss
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfShivakumar Viswanathan
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryrioverosanniejoy
 
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...ttt fff
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10uasjlagroup
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptMaryamAfzal41
 

Último (20)

Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in design
 
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
办理卡尔顿大学毕业证成绩单|购买加拿大文凭证书
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdf
 
Create Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdfCreate Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdf
 
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造
 
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
Apresentação Clamo Cristo -letra música Matheus Rizzo
Apresentação Clamo Cristo -letra música Matheus RizzoApresentação Clamo Cristo -letra música Matheus Rizzo
Apresentação Clamo Cristo -letra música Matheus Rizzo
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
 
办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙弗雷泽大学毕业证成绩单原版一比一
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdf
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industry
 
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis ppt
 

Chemical Batching System R015

  • 1. CHEMITROL Chemical Batching System Users Manual Revision 1.5 www.chemitrol.com info@chemitrol.com
  • 2. Table of Contents 1.0 Introduction............................................................................................................. 3 1.0 Introduction............................................................................................................. 3 1.1 Why use a batch tank or a day tank?................................................................... 3 1.2 Benefits of the Chemical Batching System ........................................................ 3 1.3 Theory of operation............................................................................................. 4 2.0 Specifications.......................................................................................................... 5 2.1 Electrical ............................................................................................................. 5 2.2 Mechanical.......................................................................................................... 5 2.3 Chemical Batching System Program Limits....................................................... 5 2.3a Water relay (1) ................................................................................................ 5 2.3b Pump relays (4) ............................................................................................... 5 3.0 Un-Packing & instillation of the ............................................................................. 6 3.1 Unpacking the unit.................................................................................................... 6 3.2 Mounting the controller ............................................................................................ 6 3.3 Electrical Installation ................................................................................................ 6 4.0 System Overview .................................................................................................... 9 4.1 Front Panel .............................................................................................................. 10 4.2 Display .............................................................................................................. 10 4.3 Key Pad............................................................................................................. 10 4.4 Led indictor lights ............................................................................................. 10 4.5 Start up Initial ................................................................................................... 11 4.6 Normal start up ................................................................................................. 11 4.7 Shutdown .......................................................................................................... 11 5.0 Operating Instructions........................................................................................... 11 8.0 Index ........................................................................................................................... 13 Table of Figures Figure 1: Wiring configuration ........................................................................................... 7 Figure 2: The CBS controller within a typical system including pumps and day tank ...... 8 Figure 3: The CBS with the faceplate removed.................................................................. 9 Figure 4: The Features displayed on the CBS Faceplate .................................................. 10 CBS_Manual_R015 Page 2 of 13
  • 3. 1.0 Introduction Thank you for purchasing the Chemical Batching System. The Chemical Batching System was designed to fill a large variety of liquid batch tank needs. The purpose of the Chemical Batching System is to aid in the operation of a boiler water treatment system. Currently boiler operators using day tanks must manually add treatment chemicals by hand to the dilution water in their day tanks. As with any manual operation errors can be made resulting in increased costs. Some of these incurred costs would be due to overuse or underuse of treatment chemicals, inconsistently mixed day tank batches and the potential hazards of hand mixing hazardous chemicals. Potential savings would include reducing operator workload, consistent chemistry in the boilers, resulting in lower maintenance costs. 1.1 Why use a batch tank or a day tank? The reasons to use a batching tank or day tank in a boiler chemical treatment program are many. • A batch tank system is an alternative to using an “all in one” chemical treatment product. These products may or may not meet all the requirements of your system. • This system dilutes concentrated chemical products, avoiding line and nozzle plugging. Generally it is more cost effective in terms of pounds of water treated per unit cost to purchase concentrated chemicals from vendors rather than their water diluted counterparts. Depending on the application, this could create line or nozzle plugging problems. Diluting these concentrated products will reduce plugging problems. • It is advantageous to avoid concentrate chemical corrosion/erosion within the boiler. Some water treatment chemicals have low solubility in water and will not dilute without aggressive mixing. Pre-mixing the chemicals in a day tank will dissolve and dilute these chemicals before they enter the boiler system. • Some boiler treatment chemicals are extremely corrosive in their neet form. By diluting these chemicals in a day tank system you can reduce neet chemical corrosion effects. 1.2 Benefits of the Chemical Batching System The Chemical Batching System provides accurate, hands free, on demand chemical blending of boiler treatment chemicals. The same concentration of chemicals will be blended for each batch. • Reduced operator involvement. Operators need only to replace empty chemical containers and re-prime chemical pumps. • No hand mixing of chemicals to make up batch tanks. • Consistent blending of chemicals in every batch. • Ability to program several chemical recipes for different operating conditions. (Summer/Winter operations, weekend/weekday operations, etc.) CBS_Manual_R015 Page 3 of 13
  • 4. Provides the ability to adjust chemical concentrations in the day tank. 1.3 Theory of operation. The chemical batching systems is essentially a sensor driven system. A day/batch tank is set up with a high water level sensor and a low water level sensor. The tank feeds treated water to the boiler. The level sensors control the cycles of the chemical batching systems, which consists of five relays. Relays numbers 1 through 4 turn the chemical delivery pumps on and off. Relay number 5 turns the water supply on and off. 1. The dilute boiler chemical solution is fed to the boiler from a batched tank. 2. The water level decreases below the actuation point of the low water level sensor in the day tank. 3. An LED indicator appears lit on the control interface panel. 4. Upon actuation of the low level sensor the filling/treatment cycle begins. 5. The 4 timed relays begin their countdowns and the sensor relay actuates. a. The 4 timed relays control up to 4 reagent pumps for adding up to 4 water treatment chemicals. b. Channels 1 through 4 are to be set with the Safety Timer Feature which will not allow for the day tank to overflow, due to the relatively slow rate of the pumps in use. th 6. The 5 relay actuates a valve which fills the tank with city water. 7. The 5th relay terminates upon activation of the high water level sensor. a. The volume of city water being added to the tank remains constant. This allows the amount of reagent to be added also to remain constant. The volume flow rate of the pumps is known; therefore to achieve the correct addition of reagent, one can set the amount of time for each pump to run to add the correct volume of reagent. 8. The dilute chemical solution is fed to the boiler CBS_Manual_R015 Page 4 of 13
  • 5. 2.0 Specifications 2.1 Electrical • Input Power Voltage: 100 – 250VAC Frequency: 47-63Hz Input Current: 10A Max @ 115VAC 20A Max @ 230VAC • Output power Max Switched Voltage: 250VAC Max Switched Current: 5A Max Switched Power: 1250VA, 150W • Level indictors On/Off dry contact type 5 VDC • Agency Approvals UL TBD 2.2 Mechanical Enclosure Material Molded Polystyrene NEMA Rating NEMA 12/13 Dimensions 10.25 X 12 X 5.25 Display LCD 16 X 2 Character backlit liquid crystal Operating Temperature 32-120 deg F (0 to 50 deg C) Level sensor(s) 2 Dry contact liquid level sensors 2.3 Chemical Batching System Program Limits 2.3a Water relay (1) 0 seconds to 99 minutes Triggered by low liquid level sensor Secured by high liquid level sensor or programmable time out safety function (see section 5.5) 2.3b Pump relays (4) 0 seconds to 99 minutes Triggered by low liquid level sensor Secured by Program (see section 5.0) CBS_Manual_R015 Page 5 of 13
  • 6. 3.0 Un-Packing & instillation of the 3.1 Unpacking the unit Inspect the unit and the contents of the package. Please notify the carrier immediately if there are any signs of damage to unit. Contact your distributor if there are any missing parts. 3.2 Mounting the controller The Chemical Batching System should be mounted in close proximately to the batching tank and the chemical storage location ideally the controller will be mounted on a stable horizontal surface at eye level. The chemical pumps are normally located 2 to 5 feet away to allow the chemical pumps to be plugged it to the controller. Please consult chemical pump manufacture for the proper suction and discharge line sizing and length. The controller requires the following clearances: Top: 4” Bottom 10” Left 4” Right 4” Front 24” 3.3 Electrical Installation CAUTION! There are live circuits inside the controller when the controller is energized. The front panel, or plug access panel must never be opened before power is removed from the controller CAUTION! The electrical installation of the controller must be done by a trained personal only. CBS_Manual_R015 Page 6 of 13
  • 7. Figure 1: Electrical Layout CBS_Manual_R015 Page 7 of 13
  • 8. PDK Controller AC Power In 110 Volts AC High Level Y Sensor Strainer Solenoid Water Valve Supply Water Fill line angled is eta ry an d to promote good rd p ro p ro Low in g is to b e co n side se s o n ly. It is th e mixing in Tank T his dr a w in fo rm a tio n p ru po Level r in tend ed fo o f P D K , In c. Sensor ty so le pro p er Pumped to Feed Water Line or Boiler Drum PDK Chemical Batching System 1 Incorporated (401) 294-0012 tech@pdkeng.com Wiring Schematic Figure 2: Typical system installation including pumps and day tank CBS_Manual_R015 Page 8 of 13
  • 9. 4.0 System Overview Figure 3: The CBS with the faceplate removed CBS_Manual_R015 Page 9 of 13
  • 10. 4.1 Front Panel Liquid Level Sensor Indicators LCD Display Up Arrow Back Arrow Key Pad Pump Status Indicators Figure 4: The Features displayed on the CBS Faceplate 4.2 Display The LCD is a 16x2 backlit module. If the characters are not readable, the contrast can be adjusted using the potentiometer (R3) on the back of the interface printed circuit board. 4.3 Key Pad This is the user interface that is used to enter custom programs, change settings, and review stored programs. 4.4 Led indictor lights The led indicators display the status of the liquid level sensors and relays 1-5 (chemical pumps and dilution water fill solenoid). CBS_Manual_R015 Page 10 of 13
  • 11. 4.5 Start up Initial After unit is installed plug it in and turn it on you will find pre installed programs in the unit (listed below) you may use them as is, modify them or delete them all 4.6 Normal start up Once unit is programmed the parameters are stores in memory. Simply verify water supply in on, the chemical pumps are primed and there is sufficient chemical the unit will run normally 4.7 Shutdown To secure the controller, turn off the power to the controller. For extended shutdowns, the chemical lines should be flushed with water. Disconnect water supply from the solenoid valve and remove chemicals. Store the chemicals according to the instructions provided by your chemical supplier. Pump lines should be flushed by placing chemical suction lines in fresh water and starting the chemical pumps using the Prime mode on the controller. 5.0 Operating Instructions When you initialize the Chemical Batching System it will be running the last program that was running before power down. In the case of factory default settings (ie. new unit) Program 0 will be the default program running. To exit the current program into the Main Menu press the back arrow key. The up and back arrow keys are used to scroll through the Main Menu options. The Main Menu choices are: • Run • Prime • View Program • Edit Program • Safety Timer • Program Delay • Sensor Settings • Factory Reset CBS_Manual_R015 Page 11 of 13
  • 12. 5.1 Run Allows user to select a program to run. Options are Programs 0 to 9. Program 0 is not programmable; the default settings of program 0 are all relays are set to run for 00:00 (mm:ss). Program 0 is useful for periods of boiler shut down times. Programs 1-9 are programmable and are set at factory defaults of 0 mm:ss. 5.2 Prime Allows user to run Relays 1-5 for 10 seconds per quarter second that the button is held down. Used when adding or changing reagent containers. For example, if the button is depressed for 1 second, the pump will run in manual for 40 seconds total. 5.3 View Program Allows user to view program settings. Options are to view programs 0-9. This setting is useful for verifying controller settings. 5.4 Edit Program Allows user to edit custom programs 1-9. User can program times for relays 1-4. Relay 5 is strictly level sensor actuated and controls the water supply solenoid valve. 5.5 Safety Timer This is a safety feature intended to prevent overflow of your day tank in the event of a high-level sensor failure. This function limits the amount of time that the unit’s program can run. This time is user programmable and is generally set at 125% of the maximum time it takes to fill the tank to the high level sensor. Fill times can vary depending on water supply line pressure. The factory default is 0 for this function. 5.6 Program Delay This is an optional setting to add a delay between when the low level sensor actuates, and the fill cycle program begins. The factory default time is set at 0. The purpose of this option would be to allow the water supply valve to open before the chemical pumps to begin pumping. 5.7 Sensor Settings Allows the user to select the configuration of the liquid level sensors. The options are either normally open (NO) or normally closed (NC) sensors. The purpose of this function is to allow for the possibility of installing an alternative level sensor. The factory default settings are normally open. CBS_Manual_R015 Page 12 of 13
  • 13. 5.8 Factory Reset Resets all programmable functions back to factory settings. All the custom programs run times are set to 0, safety timer to 0, program delay to 0 and sensor settings to normally open (NO)., 6.0 Index batching tank................................... 3, 6 program 0 .......................................... 12 contrast............................................... 10 Program Delay ............................ 11, 12 Edit Program............................... 11, 12 programs.......................... 10, 11, 12, 13 Factory Reset............................... 11, 13 Run ..................................................... 11 liquid level sensor................................ 5 Safety Timer ............................ 4, 11, 12 liquid level sensors ...................... 10, 12 Sensor Settings ............................ 11, 12 Main Menu ........................................ 11 Start up Initial ................................... 11 missing parts.......................................... View Program.............................. 11, 12 ................See 3.1 Unpacking the unit Wiring .............................................. 2, 7 Prime ............................................ 11, 12 CBS_Manual_R015 Page 13 of 13