Compass surveying
Prismatic compass
Compass traversing:
Important Definition
 True meridian: Line or plane passing
through geographical north pole and
geographical south pole
 Magnetic meridian: When the magnetic
needle is suspended freely and balanced
properly, unaffected by magnetic
substances, it indicates a direction. This
direction is known as magnetic meridian.
The angle between the magnetic meridian
and a line is known as magnetic bearing or
simple bearing of the line.
North
pole
True meridian
Magnetic meridian
True bearing
Magnetic bearing
 Arbitrary meridian: Convenient direction is assumed as a meridian.
 Grid meridian: Sometimes for preparing a map some state agencies
assume several lines parallel to the true meridian for a particular
zone these lines are termed as grid meridian.
 Designation of magnetic bearing
 Whole circle bearing (WCB)
 Quadrantal bearing (QB)
 WCB: The magnetic bearing of a line measured clockwise from the North
Pole towards the line is known as WCB. Varies 0-360°
 Quadrantal Bearing: The magnetic bearing of a line measured
clockwise or anticlockwise from NP or SP (whichever is nearer to the
line) towards the east or west is known as QB. This system consists of 4-
quadrants NE, SE, NW, SW. The values lie between 0-90°
 QB of OA = N a E
 Reduced Bearing: When the whole circle bearing of a line is
converted to quadrantal bearing it is termed as reduced bearing.
 Fore and Back Bearing:
 In WCB the difference between FB and BB should be exactly 180°
 BB=FB+/-180°
 Use the +ve sign when FB<180°
 Use the –ve sign when FB> 180°
 Magnetic declination: The horizontal angle between the magnetic meridian and
true meridian is known as magnetic declination.
 Dip of the magnetic needle: If the needle is perfectly balanced before
magnetisation, it does not remain in the balanced position after it is magnetised. This
is due to the magnetic influence of the earth. The needle is found to be inclined
towards the pole. This inclination of the needle with the horizontal is known
as dip of the magnetic needle.
 Local Attraction
 Method of correction for traverse:
 First method: Sum of the interior angle should be equal to (2n-4) x 90. if not
than distribute the total error equally to all interior angles of the traverse. Then
starting from unaffected line the bearings of all the lines are corrected using
corrected interior angles.
 Second method: Unaffected line is first detected. Then, commencing from the
unaffected line, the bearing of other affected lines are corrected by finding the
amount of correction at each station.
Methods of traversing
 Chain traversing:
 Compass traversing: Fore bearings and back bearings between the traverse
leg are measured
 Theodolite traversing: Horizontal angles between the traverse legs are
measured. The length of the traverse legs are measured by chain/tape or by
stadia method
 Plane table traversing: Plane table is set at every traverse station in
clockwise and anticlockwise direction and the circuit is finally closed. During
traversing the sides of the traverse are plotted according to any suitable scale.
15 m
15 m
Checks on traverse: Closed traverse
 Check on closed traverse:
 Sum of the measured interior angles (2n-4) x 90°
 Sum of the measured exterior angles (2n+4) x 90 °
 The algebric sum of the deflection angles should be equal to 360°.
Right hand deflection is considered +ve, left hand deflection –ve
 Check on linear measurement
 The lines should be measured once each on two different days
(along opposite directions). Both measurement should tally.
 Linear measurement should also be taken by the stadia method.
The measurement by chaining and stadia method should tally.
Checks on traverse: Open traverse
 Taking cut-off lines: measured the
bearings and lengths of cut off
lines after plotting and tally with
actual values.
 Taking an auxiliary point: Take P
permanent point as auxiliary point
measured bearings and lengths of
P from each traverse point. If
survey is accurate, while plotting
all the measured bearing of P
should meet at P.
Problems:
 Convert the following WCBs to QBs
 (a) WCB of AB = 45°30’
(Ans 45°30’)
 (b) WCB of BC = 125°45’
(Ans 180- 125°45’ = 54° 15’)
 Fore bearing of the following lines are given. Find back bearing
 AB=S 30°30’ E
 BC=N 40°30’ W
 The magnetic bearing of a line AB is 135°30’ what will be the true
bearing, if the declination is 5°15’ W.
Problems
Contd…
Problems
Included angle at A= 280-180-40=60
=FB of DA-180-FB of AB
Included angle at B= 40+180-70= 150
=FB of AB+180-FB of BC
Included angle at C= 70+180-210
=FB of BC+180-FB of CD
Formula: FB of previous line+/-180-
FB of next line
Compass surveying

Más contenido relacionado

La actualidad más candente

Compass survey part 1
Compass survey part 1Compass survey part 1
Compass survey part 1ArunRavi43
 
Total station
Total stationTotal station
Total stationSumit Jha
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & RangingRakesh Verma
 
Compass Surveying.ppt
Compass Surveying.pptCompass Surveying.ppt
Compass Surveying.pptWaseemUllah71
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveyingShikhar Malhotra
 
types of bearing
types of bearingtypes of bearing
types of bearingankit5597
 
Compass surveying
Compass surveyingCompass surveying
Compass surveyingAhmed Eid
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2Muhammad Zubair
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouringAbdul Majid
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingDolat Ram
 
Theodolite surveying part 1 (I scheme MSBTE)
Theodolite surveying part 1 (I scheme MSBTE)Theodolite surveying part 1 (I scheme MSBTE)
Theodolite surveying part 1 (I scheme MSBTE)Naufil Sayyad
 
Plane table surveying
Plane table surveyingPlane table surveying
Plane table surveyingNishuKumar20
 

La actualidad más candente (20)

Theodolite survey
Theodolite surveyTheodolite survey
Theodolite survey
 
Compass survey part 1
Compass survey part 1Compass survey part 1
Compass survey part 1
 
Unit 1
Unit 1Unit 1
Unit 1
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Total station
Total stationTotal station
Total station
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Compass Surveying.ppt
Compass Surveying.pptCompass Surveying.ppt
Compass Surveying.ppt
 
Levelling
LevellingLevelling
Levelling
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveying
 
types of bearing
types of bearingtypes of bearing
types of bearing
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2
 
Plane Table Surveying PPt
Plane Table Surveying PPtPlane Table Surveying PPt
Plane Table Surveying PPt
 
Engineering survey
Engineering surveyEngineering survey
Engineering survey
 
Surveying 1 lab-manual_syb_tech
Surveying 1 lab-manual_syb_techSurveying 1 lab-manual_syb_tech
Surveying 1 lab-manual_syb_tech
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouring
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 
Theodolite surveying part 1 (I scheme MSBTE)
Theodolite surveying part 1 (I scheme MSBTE)Theodolite surveying part 1 (I scheme MSBTE)
Theodolite surveying part 1 (I scheme MSBTE)
 
Theodolite lecture 1 1
Theodolite lecture 1 1Theodolite lecture 1 1
Theodolite lecture 1 1
 
Plane table surveying
Plane table surveyingPlane table surveying
Plane table surveying
 

Similar a Compass surveying

Compass surveying (1).ppt
Compass surveying (1).pptCompass surveying (1).ppt
Compass surveying (1).pptSrini Vasan
 
Compasssurveying 160050106053
Compasssurveying 160050106053Compasssurveying 160050106053
Compasssurveying 160050106053Sumit Nayani
 
1392741020 traverse survey
1392741020 traverse survey1392741020 traverse survey
1392741020 traverse surveyanjali adabala
 
traversing survey principles.docx
traversing survey principles.docxtraversing survey principles.docx
traversing survey principles.docxalexandermwaura
 
COMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYINGCOMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYINGLavanya Singh
 
Traverse Computations
Traverse ComputationsTraverse Computations
Traverse ComputationsBahzad5
 
Angular measurement
Angular measurementAngular measurement
Angular measurementKarnav Rana
 
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptxUnit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptxOKOKILOUISmefgi
 
CE(PC)403 Surveying & Geomatics
CE(PC)403 Surveying & GeomaticsCE(PC)403 Surveying & Geomatics
CE(PC)403 Surveying & GeomaticsBIKIMALLIK1
 
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabusPrismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabusWarish Khan
 
Chapter No. 04 - Angles and Directions.pptx
Chapter No. 04 - Angles and Directions.pptxChapter No. 04 - Angles and Directions.pptx
Chapter No. 04 - Angles and Directions.pptxSaadtariq82
 
chain and compass traversing.pptx
chain and compass traversing.pptxchain and compass traversing.pptx
chain and compass traversing.pptxAshishJadhav655553
 

Similar a Compass surveying (20)

Compass surveying.ppt
Compass surveying.pptCompass surveying.ppt
Compass surveying.ppt
 
Compass surveying (1).ppt
Compass surveying (1).pptCompass surveying (1).ppt
Compass surveying (1).ppt
 
Compass Survaying
Compass SurvayingCompass Survaying
Compass Survaying
 
Compasssurveying 160050106053
Compasssurveying 160050106053Compasssurveying 160050106053
Compasssurveying 160050106053
 
1392741020 traverse survey
1392741020 traverse survey1392741020 traverse survey
1392741020 traverse survey
 
Traverse surveiying
Traverse surveiyingTraverse surveiying
Traverse surveiying
 
3.compass surveying
3.compass surveying3.compass surveying
3.compass surveying
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
traversing survey principles.docx
traversing survey principles.docxtraversing survey principles.docx
traversing survey principles.docx
 
COMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYINGCOMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYING
 
Traverse Computations
Traverse ComputationsTraverse Computations
Traverse Computations
 
Angular measurement for surveying
Angular measurement for surveyingAngular measurement for surveying
Angular measurement for surveying
 
Angular measurement
Angular measurementAngular measurement
Angular measurement
 
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptxUnit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
 
CE(PC)403 Surveying & Geomatics
CE(PC)403 Surveying & GeomaticsCE(PC)403 Surveying & Geomatics
CE(PC)403 Surveying & Geomatics
 
Variations in Magnetic Declination
Variations in Magnetic DeclinationVariations in Magnetic Declination
Variations in Magnetic Declination
 
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabusPrismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
 
Angular measurement
Angular measurementAngular measurement
Angular measurement
 
Chapter No. 04 - Angles and Directions.pptx
Chapter No. 04 - Angles and Directions.pptxChapter No. 04 - Angles and Directions.pptx
Chapter No. 04 - Angles and Directions.pptx
 
chain and compass traversing.pptx
chain and compass traversing.pptxchain and compass traversing.pptx
chain and compass traversing.pptx
 

Más de Land Surveyors United Community

Más de Land Surveyors United Community (20)

Introduction to Land Surveying
Introduction to Land SurveyingIntroduction to Land Surveying
Introduction to Land Surveying
 
Survey instruments
Survey instrumentsSurvey instruments
Survey instruments
 
Sokkia spectrum survey field reference manual
Sokkia spectrum survey field reference manualSokkia spectrum survey field reference manual
Sokkia spectrum survey field reference manual
 
Sokkia set20 k
Sokkia set20 kSokkia set20 k
Sokkia set20 k
 
Sokkia set6 manual
Sokkia set6 manualSokkia set6 manual
Sokkia set6 manual
 
Sokkia setx10 instruction_manual
Sokkia setx10 instruction_manualSokkia setx10 instruction_manual
Sokkia setx10 instruction_manual
 
Sokkia sdr-8100 operations manual
Sokkia sdr-8100 operations manualSokkia sdr-8100 operations manual
Sokkia sdr-8100 operations manual
 
216 surveying traverse explained
216 surveying traverse explained216 surveying traverse explained
216 surveying traverse explained
 
nikon nivo m-series instruction manual
nikon nivo m-series instruction manualnikon nivo m-series instruction manual
nikon nivo m-series instruction manual
 
Land Surveying Resources Handbook
Land Surveying Resources HandbookLand Surveying Resources Handbook
Land Surveying Resources Handbook
 
Fundamentals hp33s exam-review
Fundamentals hp33s exam-reviewFundamentals hp33s exam-review
Fundamentals hp33s exam-review
 
Using the scientific calculator
Using the scientific calculatorUsing the scientific calculator
Using the scientific calculator
 
Complex numbers & vectors hp35s overview
Complex numbers & vectors hp35s overviewComplex numbers & vectors hp35s overview
Complex numbers & vectors hp35s overview
 
Using the hp35s Calculator
Using the hp35s CalculatorUsing the hp35s Calculator
Using the hp35s Calculator
 
Programming 33s simple
Programming 33s simpleProgramming 33s simple
Programming 33s simple
 
Summing up 33_s
Summing up 33_sSumming up 33_s
Summing up 33_s
 
Hp33s calculator user_guide
Hp33s calculator user_guideHp33s calculator user_guide
Hp33s calculator user_guide
 
Programming Hp33s talk v3
Programming Hp33s talk v3Programming Hp33s talk v3
Programming Hp33s talk v3
 
Trimble R8 gnss r6-5800-364_userguide
Trimble R8 gnss r6-5800-364_userguideTrimble R8 gnss r6-5800-364_userguide
Trimble R8 gnss r6-5800-364_userguide
 
Nikon DTN502 instruction-manual-english
Nikon DTN502 instruction-manual-englishNikon DTN502 instruction-manual-english
Nikon DTN502 instruction-manual-english
 

Último

Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical trainingGladiatorsKasper
 
priority interrupt computer organization
priority interrupt computer organizationpriority interrupt computer organization
priority interrupt computer organizationchnrketan
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
A brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProA brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProRay Yuan Liu
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfShreyas Pandit
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 

Último (20)

Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training
 
priority interrupt computer organization
priority interrupt computer organizationpriority interrupt computer organization
priority interrupt computer organization
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
A brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProA brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision Pro
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdf
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 

Compass surveying

  • 3. Compass traversing: Important Definition  True meridian: Line or plane passing through geographical north pole and geographical south pole  Magnetic meridian: When the magnetic needle is suspended freely and balanced properly, unaffected by magnetic substances, it indicates a direction. This direction is known as magnetic meridian. The angle between the magnetic meridian and a line is known as magnetic bearing or simple bearing of the line. North pole True meridian Magnetic meridian True bearing Magnetic bearing
  • 4.  Arbitrary meridian: Convenient direction is assumed as a meridian.  Grid meridian: Sometimes for preparing a map some state agencies assume several lines parallel to the true meridian for a particular zone these lines are termed as grid meridian.  Designation of magnetic bearing  Whole circle bearing (WCB)  Quadrantal bearing (QB)  WCB: The magnetic bearing of a line measured clockwise from the North Pole towards the line is known as WCB. Varies 0-360°
  • 5.  Quadrantal Bearing: The magnetic bearing of a line measured clockwise or anticlockwise from NP or SP (whichever is nearer to the line) towards the east or west is known as QB. This system consists of 4- quadrants NE, SE, NW, SW. The values lie between 0-90°  QB of OA = N a E  Reduced Bearing: When the whole circle bearing of a line is converted to quadrantal bearing it is termed as reduced bearing.  Fore and Back Bearing:  In WCB the difference between FB and BB should be exactly 180°  BB=FB+/-180°  Use the +ve sign when FB<180°  Use the –ve sign when FB> 180°
  • 6.  Magnetic declination: The horizontal angle between the magnetic meridian and true meridian is known as magnetic declination.  Dip of the magnetic needle: If the needle is perfectly balanced before magnetisation, it does not remain in the balanced position after it is magnetised. This is due to the magnetic influence of the earth. The needle is found to be inclined towards the pole. This inclination of the needle with the horizontal is known as dip of the magnetic needle.  Local Attraction  Method of correction for traverse:  First method: Sum of the interior angle should be equal to (2n-4) x 90. if not than distribute the total error equally to all interior angles of the traverse. Then starting from unaffected line the bearings of all the lines are corrected using corrected interior angles.  Second method: Unaffected line is first detected. Then, commencing from the unaffected line, the bearing of other affected lines are corrected by finding the amount of correction at each station.
  • 7.
  • 8.
  • 9. Methods of traversing  Chain traversing:  Compass traversing: Fore bearings and back bearings between the traverse leg are measured  Theodolite traversing: Horizontal angles between the traverse legs are measured. The length of the traverse legs are measured by chain/tape or by stadia method  Plane table traversing: Plane table is set at every traverse station in clockwise and anticlockwise direction and the circuit is finally closed. During traversing the sides of the traverse are plotted according to any suitable scale. 15 m 15 m
  • 10. Checks on traverse: Closed traverse  Check on closed traverse:  Sum of the measured interior angles (2n-4) x 90°  Sum of the measured exterior angles (2n+4) x 90 °  The algebric sum of the deflection angles should be equal to 360°. Right hand deflection is considered +ve, left hand deflection –ve  Check on linear measurement  The lines should be measured once each on two different days (along opposite directions). Both measurement should tally.  Linear measurement should also be taken by the stadia method. The measurement by chaining and stadia method should tally.
  • 11. Checks on traverse: Open traverse  Taking cut-off lines: measured the bearings and lengths of cut off lines after plotting and tally with actual values.  Taking an auxiliary point: Take P permanent point as auxiliary point measured bearings and lengths of P from each traverse point. If survey is accurate, while plotting all the measured bearing of P should meet at P.
  • 12. Problems:  Convert the following WCBs to QBs  (a) WCB of AB = 45°30’ (Ans 45°30’)  (b) WCB of BC = 125°45’ (Ans 180- 125°45’ = 54° 15’)  Fore bearing of the following lines are given. Find back bearing  AB=S 30°30’ E  BC=N 40°30’ W  The magnetic bearing of a line AB is 135°30’ what will be the true bearing, if the declination is 5°15’ W.
  • 14.
  • 16. Problems Included angle at A= 280-180-40=60 =FB of DA-180-FB of AB Included angle at B= 40+180-70= 150 =FB of AB+180-FB of BC Included angle at C= 70+180-210 =FB of BC+180-FB of CD Formula: FB of previous line+/-180- FB of next line