2. Subject: friday report 4-30-10 Hi all, This week we completed the second roof foam insulation and plywood skin. Also finished the exterior pink foam to mitigate our thermal bridging of the wall assembly, we completed the roof shingles and gutters as well as the front entry framing and roof. On the inside we punched our last hole in the exterior plywood/ air seal and stubbed out for all the second wall connections. There were twelve holes in total including water and waste lines, sprinkler, communications, HRV, solar, PV and electrical. For me it was counter intuitive to drill holes in a E ring assembly. The sound of each hole being drilled or cut set my nervous system on fire. On monday I will finish sealing all the new holes and retest with the blower door to see just how well we sealed up the holes.
5. corner trim and first Hardi Plank siding started. Outlet hole is not in air seal assembly but intentionally infront storage area to prevent puncture in air seal assembly
6. dryer vent raceway. here we used a 4" ABS pipe and fixed it tight and rigidto the framing. Normally one uses a soft and somewhat flexible steel or aluminum exit pipe which would be very hard to seal up at each puncture. Movement of the soft through wall pipe would or could break loose at the seal and leak air as time goes by. Here the intention is to supply a permanent solid conduit for the dryer vent. We have yet to figure out how we are going to attach and or release the dryer vent from this line but we got lots of ideas - TBCthis vent will also get a plywood
7. this vent will also get a plywood shroud around it for air sealing the sheetrock against.
13. Sun First, who are donating their time to CLAM, are installing the support feet forthe solar thermal (hot water) panels. Each foot gets a roof jack covering with a leg poking out to support the panels
14. How much extra does it cost to build a passive house?Here James Bill at left, Andy Blake a solar project manager/ consultant (pro-bono) and Dan Smith of Sebastopol Heat and Cool are finishing up a three hour on site meeting to figure out where and how to install the HRV system with the solar thermal and all the other hardware associated with the mechanical system of the house. There is probably a few hundred emails, debates, discussions, meetings and drawings before this meeting to reach a final design. A standard HVAC system might take two to four hours to reach design. Why is that? We have never done this before. It's like building the first car or the first airplane. These are the pioneers of the first passive house.
15. We have never done this before. It's like building the first car or the first airplane. These are the pioneers of the first passive house.