1.0     PROJECT BACKGROUND




2.0     SCOPE OF WORKS

The components in this flood mitigation project comprise of two (2) interrelated flood diversion
schemes :

        i)      New diversion channel to divert Sg. Keroh flood flow to Jinjang Detention Ponds.
        ii)     Upgrading Gombak Diversion to allow more discharge diversion from Sg. Gombak to the
                enlarged Batu Detention Pond.
        iii)    Benteng and Puah conceptional detail design.
2.1   GOMBAK DIVERSION’S WORK
Upgrading of the existing Gombak Diversion system:

      i.    Gombak Diversion (3.375 km)
      ii.   Gombak barrage at Gombak River downstream of Gombak Diversion
      iii.  Low overflow weir from Gombak River to Gombak Diversion
      iv.   Inlet gate to Gombak Diversion
      v.    Gombak Diversion outfall structure
      vi.   Ogee weir from regulating pond to Batu Pond
      vii.  Enlargement of Batu Pond capacity to 4.5 million cubic meter
      viii. Control gate for Batu Pond outlet to Batu River
      ix.   Flood walls along Gombak River
2.2   KEROH DIVERSION’S WORK
i.    New diversion scheme from Sungai Keroh to Jinjang Ponds (2.2 km)
         ii.   Keroh barrage at downstream of Seri Segambut Pond
         iii.  Low overflow weir from Keroh river to Seri Segambut Pond
         iv.   Inlet gate to Keroh Diversion
         v.    Keroh Diversion outfall
         vi.   Enlargement of Nanyang pond, Taman Wahyu and Delima Pond capacity to 2.5 million
               cubic meter
         vii.  Control gate at Nanyang Pond outlet
         viii. Deepening of the channel connecting Nanyang and Taman Wahyu Pond
         ix.   Control gate at Taman Wahyu and Delima Pond outlet
         x.    Flood walls along Keroh River
3.0      CONTRACTUAL INFORMATION

i)      Nama Kontrak :                 Projek Mengatasi Masalah Banjir Di Kuala Lumpur
                                       Package B – Batu / Jinjang Ponds And Related Flood
                                       Diversion

ii)     No. Kontrak :                  JPS/IP/S/5/02

iii)    Pemilik Projek :               Kerajaan Malaysia, Kementerian Sumber Asli Dan Alam
                                       Sekitar

iv)     Jabatan Pelaksana :            Jabatan Pengairan dan Saliran, Malaysia

v)      Kontraktor Utama :             PECD Construction Sdn. Bhd.
                                       5th Floor, Block E, Peremba Square
                                       Saujana Resort, Seksyen U2,
                                       40150 Shah Alam
                                       Selangor Darul Ehsan

vi)     Perunding Rekabentuk dan       RPM Engineers Sdn. Bhd.
        Penyeliaan:                    34A, Jalan SS21/39,
                                       Damansara Utama
                                       47400 Petaling Jaya,
                                       Selangor Darul Ehsan

vii)    Perunding Jurukur Bahan :      Perunding Ukur Bahan RB,
                                       Unit G1, Taman Tunku,
                                       Bukit Tunku, 50480 Kuala Lumpur

viii)   Harga Kontrak Asal :           RM 804,993,894.00

ix)     Kos Pembinaan:                 RM 528,880,519.00

x)      Tempoh Kontrak :               45 Bulan (25 Ogos 2003 – 24 Mei 2007)
                                       EOT 1 ( 27 Disember 2007 )
                                       EOT 2 ( 26 Mei 2008 )
                                       EOT 3 ( 25 September 2008 )
                                       EOT 4 ( 24 Disember 2008 )
                                       EOT 5 (24 Ogos 2009)
Project Information 060709[1]

Más contenido relacionado

La actualidad más candente

IRJET- Investigation on Soil Stabilization using Jute Fibre and Glass Powder
IRJET- Investigation on Soil Stabilization using Jute Fibre and Glass PowderIRJET- Investigation on Soil Stabilization using Jute Fibre and Glass Powder
IRJET- Investigation on Soil Stabilization using Jute Fibre and Glass PowderIRJET Journal
 
Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...Subash thangaraj
 
structural software tools.pptx
structural software tools.pptxstructural software tools.pptx
structural software tools.pptxMd Aashu
 
Final Report (Steel Bridge Design)
Final Report (Steel Bridge Design)Final Report (Steel Bridge Design)
Final Report (Steel Bridge Design)Josia Tannos, EIT
 
In situ permeability testing in boreholes
In situ permeability testing in boreholesIn situ permeability testing in boreholes
In situ permeability testing in boreholesMartin Preene
 
Concrete Overlays: A Proven Resurfacing Strategy
Concrete Overlays: A Proven Resurfacing StrategyConcrete Overlays: A Proven Resurfacing Strategy
Concrete Overlays: A Proven Resurfacing StrategyJill Reeves
 
ULCCS - industrial visit report
ULCCS - industrial visit reportULCCS - industrial visit report
ULCCS - industrial visit reportSHAMJITH KM
 
Plate load test observation and calculation Plate load test image (usefulsear...
Plate load test observation and calculation Plate load test image (usefulsear...Plate load test observation and calculation Plate load test image (usefulsear...
Plate load test observation and calculation Plate load test image (usefulsear...Make Mannan
 
Bearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationBearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationLatif Hyder Wadho
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roadsOlukayode Alao
 
training report on pwd
training report on pwdtraining report on pwd
training report on pwdAjay Upadhyay
 
Geotech Engg. Ch#05 bearing capacity
Geotech Engg. Ch#05 bearing capacityGeotech Engg. Ch#05 bearing capacity
Geotech Engg. Ch#05 bearing capacityIrfan Malik
 

La actualidad más candente (19)

cut-off wall
cut-off wallcut-off wall
cut-off wall
 
IRJET- Investigation on Soil Stabilization using Jute Fibre and Glass Powder
IRJET- Investigation on Soil Stabilization using Jute Fibre and Glass PowderIRJET- Investigation on Soil Stabilization using Jute Fibre and Glass Powder
IRJET- Investigation on Soil Stabilization using Jute Fibre and Glass Powder
 
Spine and wing method for box girders
Spine and wing method for box girdersSpine and wing method for box girders
Spine and wing method for box girders
 
5878 5
5878 55878 5
5878 5
 
Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...Planning analysis design the overhead circular water tank in seerapalayam pan...
Planning analysis design the overhead circular water tank in seerapalayam pan...
 
Manual de-diseno-de-carreteras
Manual de-diseno-de-carreterasManual de-diseno-de-carreteras
Manual de-diseno-de-carreteras
 
structural software tools.pptx
structural software tools.pptxstructural software tools.pptx
structural software tools.pptx
 
Final Report (Steel Bridge Design)
Final Report (Steel Bridge Design)Final Report (Steel Bridge Design)
Final Report (Steel Bridge Design)
 
In situ permeability testing in boreholes
In situ permeability testing in boreholesIn situ permeability testing in boreholes
In situ permeability testing in boreholes
 
Concrete Overlays: A Proven Resurfacing Strategy
Concrete Overlays: A Proven Resurfacing StrategyConcrete Overlays: A Proven Resurfacing Strategy
Concrete Overlays: A Proven Resurfacing Strategy
 
Geotechnical site investigation
Geotechnical site investigationGeotechnical site investigation
Geotechnical site investigation
 
ULCCS - industrial visit report
ULCCS - industrial visit reportULCCS - industrial visit report
ULCCS - industrial visit report
 
Plate load test observation and calculation Plate load test image (usefulsear...
Plate load test observation and calculation Plate load test image (usefulsear...Plate load test observation and calculation Plate load test image (usefulsear...
Plate load test observation and calculation Plate load test image (usefulsear...
 
Powerful parbati
Powerful parbatiPowerful parbati
Powerful parbati
 
Bearing Capacity of Shallow Foundation
Bearing Capacity of Shallow FoundationBearing Capacity of Shallow Foundation
Bearing Capacity of Shallow Foundation
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roads
 
Final report
Final reportFinal report
Final report
 
training report on pwd
training report on pwdtraining report on pwd
training report on pwd
 
Geotech Engg. Ch#05 bearing capacity
Geotech Engg. Ch#05 bearing capacityGeotech Engg. Ch#05 bearing capacity
Geotech Engg. Ch#05 bearing capacity
 

Similar a Project Information 060709[1]

Musi Bridge Visitation Report.pptx
Musi Bridge Visitation Report.pptxMusi Bridge Visitation Report.pptx
Musi Bridge Visitation Report.pptxIkhwanAlAmin1
 
Saravanan CV 2015.1
Saravanan CV 2015.1Saravanan CV 2015.1
Saravanan CV 2015.1Bob Vanan
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & mariaMaria Archana
 
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power PlantZerry Antro
 
South east kowloon development kai tak approach channel reclamation.
South east kowloon development   kai tak approach channel reclamation.South east kowloon development   kai tak approach channel reclamation.
South east kowloon development kai tak approach channel reclamation.FelixGao
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam JunaidAshraf31
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)engineeringwatch
 
Full of Paper CAFEO 31
Full of Paper  CAFEO 31Full of Paper  CAFEO 31
Full of Paper CAFEO 31Rahmat Muallim
 
1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptx1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptxosiinterwerks
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...IRJET Journal
 
Internship Report
Internship ReportInternship Report
Internship ReportBala Murali
 

Similar a Project Information 060709[1] (20)

CV_Hazwan Updated
CV_Hazwan UpdatedCV_Hazwan Updated
CV_Hazwan Updated
 
CV Latest Rosdi PL381
CV Latest Rosdi PL381CV Latest Rosdi PL381
CV Latest Rosdi PL381
 
Musi Bridge Visitation Report.pptx
Musi Bridge Visitation Report.pptxMusi Bridge Visitation Report.pptx
Musi Bridge Visitation Report.pptx
 
Saravanan CV 2015.1
Saravanan CV 2015.1Saravanan CV 2015.1
Saravanan CV 2015.1
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & maria
 
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
 
South east kowloon development kai tak approach channel reclamation.
South east kowloon development   kai tak approach channel reclamation.South east kowloon development   kai tak approach channel reclamation.
South east kowloon development kai tak approach channel reclamation.
 
report draft
report draftreport draft
report draft
 
20srm davinjaniceleemadhavi
20srm davinjaniceleemadhavi20srm davinjaniceleemadhavi
20srm davinjaniceleemadhavi
 
Presentation-Nilantha
Presentation-NilanthaPresentation-Nilantha
Presentation-Nilantha
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
 
Full of Paper CAFEO 31
Full of Paper  CAFEO 31Full of Paper  CAFEO 31
Full of Paper CAFEO 31
 
1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptx1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptx
 
Project
Project Project
Project
 
JAGMOC RESUME
JAGMOC RESUMEJAGMOC RESUME
JAGMOC RESUME
 
Hassby's CV 2015
Hassby's CV 2015Hassby's CV 2015
Hassby's CV 2015
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
 
Internship Report
Internship ReportInternship Report
Internship Report
 

Project Information 060709[1]

  • 1. 1.0 PROJECT BACKGROUND 2.0 SCOPE OF WORKS The components in this flood mitigation project comprise of two (2) interrelated flood diversion schemes : i) New diversion channel to divert Sg. Keroh flood flow to Jinjang Detention Ponds. ii) Upgrading Gombak Diversion to allow more discharge diversion from Sg. Gombak to the enlarged Batu Detention Pond. iii) Benteng and Puah conceptional detail design.
  • 2. 2.1 GOMBAK DIVERSION’S WORK
  • 3. Upgrading of the existing Gombak Diversion system: i. Gombak Diversion (3.375 km) ii. Gombak barrage at Gombak River downstream of Gombak Diversion iii. Low overflow weir from Gombak River to Gombak Diversion iv. Inlet gate to Gombak Diversion v. Gombak Diversion outfall structure vi. Ogee weir from regulating pond to Batu Pond vii. Enlargement of Batu Pond capacity to 4.5 million cubic meter viii. Control gate for Batu Pond outlet to Batu River ix. Flood walls along Gombak River 2.2 KEROH DIVERSION’S WORK
  • 4. i. New diversion scheme from Sungai Keroh to Jinjang Ponds (2.2 km) ii. Keroh barrage at downstream of Seri Segambut Pond iii. Low overflow weir from Keroh river to Seri Segambut Pond iv. Inlet gate to Keroh Diversion v. Keroh Diversion outfall vi. Enlargement of Nanyang pond, Taman Wahyu and Delima Pond capacity to 2.5 million cubic meter vii. Control gate at Nanyang Pond outlet viii. Deepening of the channel connecting Nanyang and Taman Wahyu Pond ix. Control gate at Taman Wahyu and Delima Pond outlet x. Flood walls along Keroh River 3.0 CONTRACTUAL INFORMATION i) Nama Kontrak : Projek Mengatasi Masalah Banjir Di Kuala Lumpur Package B – Batu / Jinjang Ponds And Related Flood Diversion ii) No. Kontrak : JPS/IP/S/5/02 iii) Pemilik Projek : Kerajaan Malaysia, Kementerian Sumber Asli Dan Alam Sekitar iv) Jabatan Pelaksana : Jabatan Pengairan dan Saliran, Malaysia v) Kontraktor Utama : PECD Construction Sdn. Bhd. 5th Floor, Block E, Peremba Square Saujana Resort, Seksyen U2, 40150 Shah Alam Selangor Darul Ehsan vi) Perunding Rekabentuk dan RPM Engineers Sdn. Bhd. Penyeliaan: 34A, Jalan SS21/39, Damansara Utama 47400 Petaling Jaya, Selangor Darul Ehsan vii) Perunding Jurukur Bahan : Perunding Ukur Bahan RB, Unit G1, Taman Tunku, Bukit Tunku, 50480 Kuala Lumpur viii) Harga Kontrak Asal : RM 804,993,894.00 ix) Kos Pembinaan: RM 528,880,519.00 x) Tempoh Kontrak : 45 Bulan (25 Ogos 2003 – 24 Mei 2007) EOT 1 ( 27 Disember 2007 ) EOT 2 ( 26 Mei 2008 ) EOT 3 ( 25 September 2008 ) EOT 4 ( 24 Disember 2008 ) EOT 5 (24 Ogos 2009)