SlideShare una empresa de Scribd logo
1 de 7
Descargar para leer sin conexión
Doc No: DPD074.GN
Revision: March-09
© 2009
This document has copyright, which is owned by Sonneville International Corporation (SIC) and may not be reproduced, in whole, in part, or in any form whatsoever without
prior written authority from SIC. This document has been submitted on the understanding that it will not be used in any way against the interest of SIC.
LOW VIBRATION TRACK (LVT)
Track renewal
SONNEVILLE INTERNATIONAL CORPORATION
8109 Tis Well Drive, Suite 513
Alexandria, VA 22306, USA
Tel. +1 703 619 1530
Fax +1 703 619 1534
E-mail mail@sonneville.com
www.sonneville.com
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 2 of 7
A) Special cavity LVT
Substitution of old wooden ties or blocks embedded in
concrete with special cavity LVT supports
Track geometry re-adjustment
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 3 of 7
Grout placement
Special cavity LVT supports, first installed on Amtrak in early 2000, were primarily designed to replace existing ties or blocks
encased in concrete. Their relatively smaller size allows them to be retrofitted in the cavities left by the removed ties or blocks,
adjusted and sealed in place with flowable cementitious grout. The trapezoidal shape of the concrete blocks, resilient pads and
rubber boots equalizes the pressure per area on the field and gauge sides under combined vertical and lateral loads and further
prevents long term migration towards the gauge side when the LVT supports are installed adjacent to an existing central trough.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 4 of 7
B) Renewal of ballasted track under traffic
The following procedure was successfully implemented in 1974 in Denmark to renew 6 km (3.8 miles) of ballasted track with the
earlier non-ballasted track system comprising tie bars.
The work was restricted to 4 ½ hours per night with traffic operating normally at all other times, except for a temporary 35 km/h
(22 mph) speed restriction.
The same procedure is applicable to LVT with the only addition of insulated temporary gauge bars between the rails.
Advanced ballast removal
An advance crew excavated the ballast cribs up to the ends of
the existing ties.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 5 of 7
Old track removal
The first trackwork crew removed three 15-metre panels
[45 metres (150 ft) of track] per night, excavated the remaining
ballast and placed roller compacted concrete on the
foundation while restoring the drainage system.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 6 of 7
Track restoration
New track panels were then installed directly on the roller compacted concrete, the rails connected and ramps shimmed at both
ends, the track temporarily resting slightly below its final level.
Traffic immediately resumed.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 7 of 7
Final adjustment and concreting
The second trackwork crew adjusted the track, verified its geometry and secured it in place with shims inserted between the rail
base and the now fully cured roller compacted concrete before placing and finishing the track concrete.
The loads generated by the traffic that resumed immediately thereafter were transferred directly from the rails to the roller
compacted concrete through the shims without any measurable relative movement between the rubber boots and the green
track concrete below.
The upper portion of the shims was later removed and recycled forwards.

Más contenido relacionado

La actualidad más candente

Product Data Sheet - ACO Passavant
Product Data Sheet - ACO PassavantProduct Data Sheet - ACO Passavant
Product Data Sheet - ACO PassavantACO Passavant
 
Cc channel lining aberdeen western peripheral route - transport scotland (1)
Cc channel lining   aberdeen western peripheral route - transport scotland (1)Cc channel lining   aberdeen western peripheral route - transport scotland (1)
Cc channel lining aberdeen western peripheral route - transport scotland (1)Oscar044
 
Expansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalExpansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalRailways and Harbours
 
Intro to oil well drilling ops pt 2
Intro to oil well drilling ops pt 2 Intro to oil well drilling ops pt 2
Intro to oil well drilling ops pt 2 amrhaggag
 
Proj ref lrg_anzacbridge
Proj ref lrg_anzacbridgeProj ref lrg_anzacbridge
Proj ref lrg_anzacbridgeBrett Finucane
 
Tw Rcc Dams Display
Tw Rcc Dams DisplayTw Rcc Dams Display
Tw Rcc Dams DisplayTed Warren
 
TfI Marine - Mooring Load Reduction - FOWT 2018
TfI Marine - Mooring Load Reduction - FOWT 2018TfI Marine - Mooring Load Reduction - FOWT 2018
TfI Marine - Mooring Load Reduction - FOWT 2018Noel Halloran
 
Chad Irvine's CV
Chad Irvine's CVChad Irvine's CV
Chad Irvine's CVChad Irvine
 
Manitowoc press-presentation final
Manitowoc press-presentation finalManitowoc press-presentation final
Manitowoc press-presentation finalManitowocCompany
 
Project Management of M&E works at a WwTW
Project Management of M&E works at a WwTWProject Management of M&E works at a WwTW
Project Management of M&E works at a WwTWftwg
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbourFHRahman1
 
We are TSC-Rev1-small
We are TSC-Rev1-smallWe are TSC-Rev1-small
We are TSC-Rev1-smallSophia Wang
 
Emin SG Proyecto Rehabilitacion Vias Ferreas ST Charles Avenue
Emin SG Proyecto Rehabilitacion Vias Ferreas ST Charles AvenueEmin SG Proyecto Rehabilitacion Vias Ferreas ST Charles Avenue
Emin SG Proyecto Rehabilitacion Vias Ferreas ST Charles AvenueEMIN Sistemas Geotecnicos
 

La actualidad más candente (20)

Product Data Sheet - ACO Passavant
Product Data Sheet - ACO PassavantProduct Data Sheet - ACO Passavant
Product Data Sheet - ACO Passavant
 
Mobile crusher
Mobile crusherMobile crusher
Mobile crusher
 
LVT
LVTLVT
LVT
 
Cc channel lining aberdeen western peripheral route - transport scotland (1)
Cc channel lining   aberdeen western peripheral route - transport scotland (1)Cc channel lining   aberdeen western peripheral route - transport scotland (1)
Cc channel lining aberdeen western peripheral route - transport scotland (1)
 
Expansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container TerminalExpansion Of The Cape Town Container Terminal
Expansion Of The Cape Town Container Terminal
 
Intro to oil well drilling ops pt 2
Intro to oil well drilling ops pt 2 Intro to oil well drilling ops pt 2
Intro to oil well drilling ops pt 2
 
Sobre los Desvios
Sobre los DesviosSobre los Desvios
Sobre los Desvios
 
Proj ref lrg_anzacbridge
Proj ref lrg_anzacbridgeProj ref lrg_anzacbridge
Proj ref lrg_anzacbridge
 
Tw Rcc Dams Display
Tw Rcc Dams DisplayTw Rcc Dams Display
Tw Rcc Dams Display
 
TfI Marine - Mooring Load Reduction - FOWT 2018
TfI Marine - Mooring Load Reduction - FOWT 2018TfI Marine - Mooring Load Reduction - FOWT 2018
TfI Marine - Mooring Load Reduction - FOWT 2018
 
KMOC ASIA Ltd.
KMOC ASIA Ltd.KMOC ASIA Ltd.
KMOC ASIA Ltd.
 
Rock anchored wind turbine
Rock anchored wind turbineRock anchored wind turbine
Rock anchored wind turbine
 
Chad Irvine's CV
Chad Irvine's CVChad Irvine's CV
Chad Irvine's CV
 
Portfolio
PortfolioPortfolio
Portfolio
 
Manitowoc press-presentation final
Manitowoc press-presentation finalManitowoc press-presentation final
Manitowoc press-presentation final
 
Project Management of M&E works at a WwTW
Project Management of M&E works at a WwTWProject Management of M&E works at a WwTW
Project Management of M&E works at a WwTW
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
We are TSC-Rev1-small
We are TSC-Rev1-smallWe are TSC-Rev1-small
We are TSC-Rev1-small
 
Emin SG Proyecto Rehabilitacion Vias Ferreas ST Charles Avenue
Emin SG Proyecto Rehabilitacion Vias Ferreas ST Charles AvenueEmin SG Proyecto Rehabilitacion Vias Ferreas ST Charles Avenue
Emin SG Proyecto Rehabilitacion Vias Ferreas ST Charles Avenue
 
Narrow Pavement Widening - Atlanta District
Narrow Pavement Widening - Atlanta DistrictNarrow Pavement Widening - Atlanta District
Narrow Pavement Widening - Atlanta District
 

Destacado

Indian Railways
Indian RailwaysIndian Railways
Indian RailwaysAnand Dube
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)sharda university
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Railssrinivas2036
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.ashrafdgrt
 

Destacado (6)

Indian Railways
Indian RailwaysIndian Railways
Indian Railways
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.
 

Similar a Renovación de Vías

Reporte de Atenuacion de Vibraciones
Reporte de Atenuacion de VibracionesReporte de Atenuacion de Vibraciones
Reporte de Atenuacion de VibracionesManuel Huaringa Leon
 
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepersEtd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepersNECB
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnelAratiSavant
 
Etd 02-02 - resilient rail fastenings for concrete sleepers
Etd 02-02 - resilient rail fastenings for  concrete sleepersEtd 02-02 - resilient rail fastenings for  concrete sleepers
Etd 02-02 - resilient rail fastenings for concrete sleepersNECB
 
Evermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectEvermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectFairfax County
 
Submerged floating tunnel ppt
Submerged floating tunnel pptSubmerged floating tunnel ppt
Submerged floating tunnel pptjishnukpkp
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-enTeresa Elliott
 
Infographic Line 10 WSRP SEPT 2015
Infographic Line 10 WSRP SEPT 2015Infographic Line 10 WSRP SEPT 2015
Infographic Line 10 WSRP SEPT 2015David Coll
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster PresentationPaul Trofimov
 
WH Scott - Load Securing (V1)
WH Scott - Load Securing (V1)WH Scott - Load Securing (V1)
WH Scott - Load Securing (V1)Leighton Glynn
 
WH Scott - Load Securing
WH Scott - Load SecuringWH Scott - Load Securing
WH Scott - Load SecuringPatrick Doyle
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slidesWaqas Javaid
 
November 2015 - G-Tech
November 2015 - G-TechNovember 2015 - G-Tech
November 2015 - G-TechAaron Chapman
 

Similar a Renovación de Vías (20)

Reporte de Atenuacion de Vibraciones
Reporte de Atenuacion de VibracionesReporte de Atenuacion de Vibraciones
Reporte de Atenuacion de Vibraciones
 
Site Design Labs
Site Design LabsSite Design Labs
Site Design Labs
 
Sobre Mantenimiento
Sobre MantenimientoSobre Mantenimiento
Sobre Mantenimiento
 
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepersEtd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
 
Etd 02-02 - resilient rail fastenings for concrete sleepers
Etd 02-02 - resilient rail fastenings for  concrete sleepersEtd 02-02 - resilient rail fastenings for  concrete sleepers
Etd 02-02 - resilient rail fastenings for concrete sleepers
 
Evermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectEvermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement Project
 
Submerged floating tunnel ppt
Submerged floating tunnel pptSubmerged floating tunnel ppt
Submerged floating tunnel ppt
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
 
2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en
 
Infographic Line 10 WSRP SEPT 2015
Infographic Line 10 WSRP SEPT 2015Infographic Line 10 WSRP SEPT 2015
Infographic Line 10 WSRP SEPT 2015
 
Thesis Poster Presentation
Thesis Poster PresentationThesis Poster Presentation
Thesis Poster Presentation
 
Work Term Overview
Work Term OverviewWork Term Overview
Work Term Overview
 
WH Scott - Load Securing (V1)
WH Scott - Load Securing (V1)WH Scott - Load Securing (V1)
WH Scott - Load Securing (V1)
 
WH Scott - Load Securing
WH Scott - Load SecuringWH Scott - Load Securing
WH Scott - Load Securing
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slides
 
316b Booklet for S&L
316b Booklet for S&L316b Booklet for S&L
316b Booklet for S&L
 
November 2015 - G-Tech
November 2015 - G-TechNovember 2015 - G-Tech
November 2015 - G-Tech
 

Más de Manuel Huaringa Leon (17)

TRABAJO ESCALONADO-FINAL
TRABAJO ESCALONADO-FINALTRABAJO ESCALONADO-FINAL
TRABAJO ESCALONADO-FINAL
 
Transmilenio fase III
Transmilenio fase IIITransmilenio fase III
Transmilenio fase III
 
Informe de gestion 2009
Informe de gestion 2009Informe de gestion 2009
Informe de gestion 2009
 
Transmilenio
TransmilenioTransmilenio
Transmilenio
 
Referencias
ReferenciasReferencias
Referencias
 
Experiencia en Viaductos
Experiencia en ViaductosExperiencia en Viaductos
Experiencia en Viaductos
 
Rutas
RutasRutas
Rutas
 
EL METRO DE LIMA
EL METRO DE LIMAEL METRO DE LIMA
EL METRO DE LIMA
 
Arq cesar lama
Arq cesar lamaArq cesar lama
Arq cesar lama
 
Consorcio Tren Electrico - Megaevento Ferroviario
Consorcio Tren Electrico - Megaevento FerroviarioConsorcio Tren Electrico - Megaevento Ferroviario
Consorcio Tren Electrico - Megaevento Ferroviario
 
Plan de viaje descripcion de rutas
Plan de viaje   descripcion de rutasPlan de viaje   descripcion de rutas
Plan de viaje descripcion de rutas
 
Low Vibration Track
Low Vibration TrackLow Vibration Track
Low Vibration Track
 
Primer trabajo
Primer trabajoPrimer trabajo
Primer trabajo
 
Primer trabajo
Primer trabajoPrimer trabajo
Primer trabajo
 
Tema de tesis
Tema de tesisTema de tesis
Tema de tesis
 
Trans milenio wikipedia
Trans milenio wikipediaTrans milenio wikipedia
Trans milenio wikipedia
 
Transmilenio bogota
Transmilenio bogotaTransmilenio bogota
Transmilenio bogota
 

Último

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 

Último (20)

Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 

Renovación de Vías

  • 1. Doc No: DPD074.GN Revision: March-09 © 2009 This document has copyright, which is owned by Sonneville International Corporation (SIC) and may not be reproduced, in whole, in part, or in any form whatsoever without prior written authority from SIC. This document has been submitted on the understanding that it will not be used in any way against the interest of SIC. LOW VIBRATION TRACK (LVT) Track renewal SONNEVILLE INTERNATIONAL CORPORATION 8109 Tis Well Drive, Suite 513 Alexandria, VA 22306, USA Tel. +1 703 619 1530 Fax +1 703 619 1534 E-mail mail@sonneville.com www.sonneville.com
  • 2. Doc No: DPD074.GN Revision: March-09 Low Vibration Track (LVT) – Track renewal Page 2 of 7 A) Special cavity LVT Substitution of old wooden ties or blocks embedded in concrete with special cavity LVT supports Track geometry re-adjustment
  • 3. Doc No: DPD074.GN Revision: March-09 Low Vibration Track (LVT) – Track renewal Page 3 of 7 Grout placement Special cavity LVT supports, first installed on Amtrak in early 2000, were primarily designed to replace existing ties or blocks encased in concrete. Their relatively smaller size allows them to be retrofitted in the cavities left by the removed ties or blocks, adjusted and sealed in place with flowable cementitious grout. The trapezoidal shape of the concrete blocks, resilient pads and rubber boots equalizes the pressure per area on the field and gauge sides under combined vertical and lateral loads and further prevents long term migration towards the gauge side when the LVT supports are installed adjacent to an existing central trough.
  • 4. Doc No: DPD074.GN Revision: March-09 Low Vibration Track (LVT) – Track renewal Page 4 of 7 B) Renewal of ballasted track under traffic The following procedure was successfully implemented in 1974 in Denmark to renew 6 km (3.8 miles) of ballasted track with the earlier non-ballasted track system comprising tie bars. The work was restricted to 4 ½ hours per night with traffic operating normally at all other times, except for a temporary 35 km/h (22 mph) speed restriction. The same procedure is applicable to LVT with the only addition of insulated temporary gauge bars between the rails. Advanced ballast removal An advance crew excavated the ballast cribs up to the ends of the existing ties.
  • 5. Doc No: DPD074.GN Revision: March-09 Low Vibration Track (LVT) – Track renewal Page 5 of 7 Old track removal The first trackwork crew removed three 15-metre panels [45 metres (150 ft) of track] per night, excavated the remaining ballast and placed roller compacted concrete on the foundation while restoring the drainage system.
  • 6. Doc No: DPD074.GN Revision: March-09 Low Vibration Track (LVT) – Track renewal Page 6 of 7 Track restoration New track panels were then installed directly on the roller compacted concrete, the rails connected and ramps shimmed at both ends, the track temporarily resting slightly below its final level. Traffic immediately resumed.
  • 7. Doc No: DPD074.GN Revision: March-09 Low Vibration Track (LVT) – Track renewal Page 7 of 7 Final adjustment and concreting The second trackwork crew adjusted the track, verified its geometry and secured it in place with shims inserted between the rail base and the now fully cured roller compacted concrete before placing and finishing the track concrete. The loads generated by the traffic that resumed immediately thereafter were transferred directly from the rails to the roller compacted concrete through the shims without any measurable relative movement between the rubber boots and the green track concrete below. The upper portion of the shims was later removed and recycled forwards.