Rennes International School of Business


                     ESC RENNES


       Executive Master of Business Administration
                         EMBA


               COHORT 1 (2003 - 2004)


               HR & Change Management
                     Conducted by:
                  Dr. Donald MINDAY




Changing and standardize the Cleaning operation
                    For Menatel


                          By
                  Magdy A. Sattar



                    March, 2004
                    Cairo, Egypt
EXECUTEVE SUMMARY .................................................................................................................. II
1-     REPORT OBJECTIVE. ............................................................................................................... 1
2-     MENATEL PROFILE.................................................................................................................. 1
3-     CURRENT SITUATION ANALYSIS & IDINTIFING THE PROBLEM. ............................. 2
4-     THE PROPOSED NEW CLEANING OPERATION STANDRALIZATION ....................... 3
5-     CONCLUSION ........................................................................................................................... 11
6-     RECOMMENDATION .............................................................................................................. 11




EMBA Cairo
Rennes International School of Business                                                                                                  I
EXECUTEVE SUMMARY


In this report, we analyze, evaluate and then recommend a method through which
Menatel and the sub-contractors assigned to the cleaning operation satisfy their
business needs and achieve effective and efficient communication.
First, we will analysis the current situation (figures and performance) to identify the
problem.
Second, we shall go through explanation and description of          the proposed new
cleaning operation by its three phase’s unfreeze –movement –refreeze, describing the
job duties assigned to the concerned parties and the expected output of their
communication, the new basis of Menatel checking methodology for both cleaning
quality and invoice checking. How we are going to communicate and explain the new
process. Illustrate the sources of resistances, the movement phase strategies, and the
refreezing techniques.
Third, the conclusion and recommended decision that we think it should be taken.




EMBA Cairo
Rennes International School of Business                                            II
1- Report Objective.
The purpose of this report is to allow me to demonstrate my understanding of the
principles and techniques covered during the HR and change management course. I
will submit a business report that will address a proposed new cleaning operation
process showing how Menatel will manage the changing process. I will analyze
Menatel cleaning sub contractor situation through evaluating their performance
quality compared to Menatel needs and quality standard, also revise all the contracts
in order to present the new cleaning operation process by which both parties are
satisfied and Menatel’s image is maintained.


   2- Menatel profile
Late in 1998 Menatel was born as a joint stock company, under investment low
number 8/1997 registered in 1998 under number 314030. Menatel is granted a ten
years; renewable license, to install, operate, and manage a telecommunication
network of at least 30,000 public payphone. Egyptian shares are 53 % and foreign
shares are 47 %. By the end of 2003 Menatel has been operating a payphone network
with near to 30,000 payphones in operation, and work force of more than 400
employees. Thanks to our customers love, appreciation, and trust Menatel’s two
colors (green and yellow) are now a trend, they can be seen every where, not only
Menatel payphones but also kiosks, bill-boards or sometimes even buildings are
painted in those two colors. This proves the fact that Menatel has succeeded to
become an integral part of people’s daily life in Egypt.


           2.1     Menatel Vision
To be the leaders in the field of telecommunication services, as well as the leader in
creating a national base of accumulated expertise of high Egyptian telecom engineers.


           2.2     Menatel Goals
                Exceptional Customer Satisfaction.
                Inspired, innovative and empowered Employees.
                Depending on local sourcing whenever possible.
                Superior Financial Results.



EMBA Cairo
Rennes International School of Business                                           1
2.3      Menatel Values
                       Customer First.
                       Integrity in All we do.
                       Excellence through Total Quality.
                        Respect for others.
                       Respect for our environment.
                       Growth through change.


         3- Current Situation Analysis & Idintifing the problem.
                  3.2      Current situation figures analysis.
                                                          Sub-              Price (LE)          Contract   Contract
Branch     Zone            Area (Governorates)
                                                       contractors   PD2      PD1        WM      Start       End
                                                         Alpha,
                        Giza, El-Fayoum, Baniswef
Cairo        1                                         Pyramids,     0.40     0.25       0.20   24/12/01   31/12/03
                                   Gov.
                                                         United
                                                         Alpha,
Cairo        2              East & south Cairo         Pyramids,     0.40     0.25       0.20   24/12/01   31/12/03
                                                         United
                        West & north Cairo, 10th of      Alpha,
Cairo        3        Ramadan, shoubra el khaima,      Pyramids,     0.40     0.25       0.20   24/12/01   31/12/03
                      kanater , kalubia, and khanka      United
Alex         4            East Alex., and Behera         Alpha       0.40     0.25       0.20   24/12/01   31/12/03
                      West Alex., north coast, and
Alex         5                                           Alpha       0.40     0.25       0.20   24/12/01   31/12/03
                              Marsa matroh
                        Port said, Damiatta, north
Canal        6                                         Adam Siag     0.40     0.25       0.20   24/12/01   31/12/03
                                   Sina
Canal        7        Suze, Ismailia, and south Sina   Adam Siag     0.40     0.25       0.20   24/12/01   31/12/03
                      Kafer el sheikh, Dakhlia, and
Delta        8                                          El Kods      0.40     0.25       0.20    7/3/02    31/12/03
                                 Sharkia
                        Monofia, Gharbia, banha,
Delta        9        tokh, Kafer shoker, shebeen el     Alpha       0.40     0.25       0.20   24/12/01   31/12/03
                                 kanater
MUE         10                   El-Minia                Alpha       0.45     0.27       0.25   24/12/01   31/12/03
MUE         11            Assiut, and New valley       High care     0.49     0.29       0.24   24/12/02   31/12/03
MUE         12                    Sohag                High care     0.49     0.29       0.24   24/12/02   31/12/03
 SUE        13              Quena, and Louxer            Alpha       0.45     0.27       0.25   24/12/01   31/12/03
 SUE        14                    Aswan                  Alpha       0.45     0.27       0.25   24/12/01   31/12/03
 SUE        15                   Red Sea                 Alpha       0.45     0.27       0.25   24/12/01   31/12/03




  EMBA Cairo
  Rennes International School of Business                                                            2
The table above shows the following
                 A total of six sub-contractors assigned to clean Menatel booths
                  distributed over 15 different zones.
                 All contracts ended 31/12/2003.
                 There are three different prices.


            3.3     Current situation performances analysis.
The table below shows the average cleaning quality per branch for the year 2003,
from which we can see the big gap in the performance from branch to another, which
indicates different methodology of evaluating the cleaning quality which of course
generates a lot of conflicts.


 Branch           Cairo         Alex         Canal       Delta       MUE          SUE
 Average        91.5 %          94 %         65 %        83 %        97 %         96 %


            3.4     Problem Identification
By the above analysis the problem can be stated as a vague understanding or conflict
among the partners (Menatel, and the cleaning contractors). This poor environment of
work, in additional to the economical situation drop in 2003, forces Menatel to revise
the whole cleaning operation and try to find or adapt a planned change that will match
the new environment and new strategies of Menatel to optimize our resources. For
that I was assigned as a change agent to propose and plan the change process for the
cleaning operation. My objectives are:
                 To plan a clear, controlled and standard cleaning quality operation
                 To plan standard invoice checking process
                 To revise old contracts and plan a new contract to fit the new change


    4- The proposed new cleaning operation standralization
Based on Lewin’s change model I divided the change process to three phases
            4.1     The unfreeze phase
This phase where we unfreeze the old operation and plan the new one which is
composed of:



EMBA Cairo
Rennes International School of Business                                                 3
4.1.1 Operation partners and job descriptions
                Contractors field labor tasks
                               Daily tasks
In additional to his daily cleaning tasks, for urgent notes to be reported the field labor
contacts Menatel directly in cases of any fault or problem that would make the
payphone not available to the customer to use. for example, a cut handset, an out of
order payphone, an inserted card, an open PP’s case shell, or the phone is ripped of
the booth.
In such cases the field labor has to make an immediate contact with the technician
assigned to the area or the maintenance Eng. if either of them is not available to reach
for any reason he should call the customer service center and report the case.
For cases that might cause the payphone to be out of order in one to three days, for
example, the booth is not fixed tight to the ground which can be a threat to the
customers, lack of U-guard or cables are not fixed. In such cases the field labor must
report these cases to his direct field supervisor.
                               Weekly tasks
Cases that affect the image of Menatel (booth or payphone status) such as, ribbed off
sides, broken or scratched display, broken fibers or lack of boosters. These notes
should be reported first to the contractor field supervisor, then, it should be put into a
detailed weekly report that to be sent to Menatel


                Contractors field supervisor
                               Daily tasks
Each for his assigned area contact Menatel assigned supervisor to report any cases
that might affect directly the efficiency of the payphones service quality or cause it to
be out of order within the next 48hours.
                               Weekly tasks
Represent a weekly report in which all the notes and the needs of booth maintenance
operation might need to maintain the image of Menatel. The accuracy and on time
commitment of delivering this report is to be considered in evaluating the cleaning
quality.




EMBA Cairo
Rennes International School of Business                                              4
   Contractors project manager
He is to be in touch with Menatel CCs. Supervisor to make sure that the operation is
working in smooth way and all the resources are available to do the assigned tasks in
the field (tools, equipments).


              Menatel cleaning controller
He is assigned by menatel to implement menatel cleaning quality methodology and to
make sure that the cleaning contractor’s labors are doing what they should be doing
according to Menatel standards.


              Menatel CCs. supervisor
He is the operation controller assigned by menatel to do all the necessary actions to
maintain Menatel image in the field following up closely the quality of the booths and
payphones (cleaning, shaping, conditioning).


           4.1.2 Checking methodology
              Cleaning quality checking
Menatel team of cleaning controllers and their supervisor are assigned to perform this
check through the sampling plan techniques and prepare its plan, daily check list, and
reports needed. Their calculations to the QS of the cleaning (based on the cabinet
body sets values) in their assigned area is the main reference.
The area assigned to the contractor shall be divided into routes on which the CC. Shall
makes his check rounds 2 to 3 rounds per month (or according to the area nature and
the no. of Menatel CCs). In each of these rounds a different random sample -around
10%-of total locations in every City or district in the route shall be taken as a
reference by one member of the team. So that by the end of the month the whole area
assigned to the contractor is checked over three times, each time by a different CC.
Cleaning Controller are checking over 3 main things:
                                Checking the cleaning quality of the booths
                                Contractor commitment to daily cleaning operation
                 (whether or not the city or district is cleaned daily)
                                Contractor   staff   (field   labors     and   supervisors)
                 cooperation and their effective communication

EMBA Cairo
Rennes International School of Business                                                 5
The technician team is involved also in evaluating the contractor's staff cooperation
 and response to the field needs.
                   Sampling plan elements (proposed).


                                                          acceptance        rejection criteria
Branch      lot size   sample size   number of samples
                                                           criteria Cl                Cp
 Cairo      12200      10 % =1220          4/month       5% = 61 Booth      20% = 244 Booth
 Alex        4700       10 % =470          4/month       5% = 23 Booth       20% = 94 Booth
 Delta       4200       10 % =420          4/month       5% = 21 Booth       20% = 84 Booth
Canal        4100       10 % =410          4/month       5% = 20 Booth       20% = 82 Booth
 MUE         2600       10 % =260          4/month       5% = 13 Booth       20% = 52 Booth
 SUE         2200       10 % =220          4/month       5% = 11 Booth       20% = 44 Booth
Menatel     30000      10 % =3000          4/month       5% = 150 Booth     20% = 600 Booth



                   Cabinet body parts



          Set (1) 20%                                              Set (2) 25%




   Set (3) 30%



   Set (4) 15%




         Set (5) 10%




 The contractor should be very careful to use the proper means (water, cleansers,
 ladders and brushes) which does not affect the efficiency of the PP. or distort its
 appearance.

 EMBA Cairo
 Rennes International School of Business                                          6
   Invoice checking
There are 3 factors in the contractors' invoice that conclude the invoice and over
which Menatel is revising
                                 Numbers and type of locations.
                                 Numbers of actual working (cleaning) days.
                                 Cleaning Quality of the assigned area
As for the No. and type of the booths in field, Menatel monthly updated report from
Menaprod (Menatel data base) is the reference in this issue, Meaning that any
deviation from Mantel's report (positive or negative) will be calculated and deducted
from the contractor's total figures. As for the actual working days, Menatel emphasis
that, any National holidays occurring in the month shall be deducted from the invoice.




                            Cleaning Invoices Evaluation



        Field               On Time &              Communication           Cleaning
       Monthly               Accurate              & Co-operation          Checking
        Visit               Reporting
        10 %                  10 %                      10 %                   70 %



    Measurement           Measurement              Measurement            Measurement
       Tool                  Tool                     Tool                   Tool

       Sampling          Data Accuracy &            Global QS per          Sampling
                          No. of Reports             Technician

As for the cleaning quality of the cleaning operations the above chart clarifies the
suggested process of evaluating the Contractor Cleaning Invoices according to the
agreed upon indicators and its weights.
Cleaning Checking Indicator Weight (70%) its measurement tool is sampling its
calculation will be as follows:
Should the Sample result meet the CI (Acceptance criteria (5%) Commented upon
cabinets) the contractor evaluation in this indicator is 100% (70%).


EMBA Cairo
Rennes International School of Business                                                7
Should the sample result meet the CP (Rejection criteria (20%) commented upon
cabinets) the whole sample result is rejected and the contractor evaluation in this
indicator is 0%.
Should the sample result varies between CI and CP (from 6%to 19%) the result of this
sample will be put as it is and the contractor will be evaluated by the average the
whole sample results.
The assigned Menatel Engineer will represent a monthly report of the result of the
samples.
Communication and cooperation indicator Weight (10%) Its Measurement tool is
technicians feed back upon the global QS. Maintenance Engineer will represent a
monthly report of the Technician feed back.
The payphones QS, target is no less than 98% the percentage of negative deviation
from the target is deducted from the weight indicator
On time and Accurate Reporting indicator Weight (10%) its measurement is:
Four weekly reports to be delivered per month to Menatel, and accurate data in the
reports. The commitment of delivering these weekly reports and the accuracy of these
reports will be put in a monthly report.
Field Monthly Visit indicator Weight (10%) its Measurement tool is sampling. The
report of this visit result signed by both parties shall be represented monthly.
There are two final notes that are:
The cover of the invoice presented from the contractor should be unified but the
details inside the invoice could vary from according to the branch or the department
assigned area (Territory, Governorate, and Area).
Each branch or department can decide the sample size, number of samples per month
and the locations in the samples in accord to two main factors the area needs and the
branch resources (transportation, cleaning controller, and technician)


           4.1.3 Communicate & explanation of the new process
The new cleaning process will be communicated to all partners through lectures done
by the change agent to cover and explain the new terminology of the new process and
to clear any misunderstandings or conflict and according to the below table this will
take place all over Menatel branches and some of the contractors locations, and will
address all the key persons of the new cleaning operation.

EMBA Cairo
Rennes International School of Business                                            8
Presentation
          Dates                  Location                       Attendance                Concerned company/branch
                                                     time
 Sunday       15-2-2004            HQ           S-12 am/E-4pm    Menatel                   Directors, and Managers
                                                                   All
Wednesday     18-2-2004            HQ           S-12 am/E-4pm                  The companies owners or the General Managers
                                                                contractors
                              HQ/distribution                                 Cairo branch, Delta branch, accountant dep., alpha,
 Monday       15-3-2004                         S-11am/E-3pm    25 persons
                                   room                                              united group, Pyramids, and Elkods.
 Tuesday      16-3-2004        Asute Branch     S-12am/E-3pm    15 persons            Asute branch, high care, and alpha.
Wednesday     17-3-2004        Luxer Branch     S-12am/E-3pm    15 persons                  Luxer branch and alpha.
Thursday      18-3-2004       Port S. Branch    S-12am/E-3pm    15 persons              Port S. branch, and Adam Siage.
 Sunday       21-3-2004        Alex. Branch     S-12am/E-3pm    15 persons                  Alex. Branch, and alpha
                                                                               Alpha company representatives and the company
 Monday       29-3-2004       Alpha company     S-11am/E-3pm    7 persons
                                                                                                     owner


                          4.1.4 Sources of resistances
          Change resistance is a law of nature also it is an obstacle in the way of the new
          process and stand against the smooth movement of it. This obstacle is generated by
          two main sources, organizational sources or individual sources.
                             Organizational sources
          The main source of resistance we expect it to be the organization structural inertia for
          both Menatel and the cleaning companies. The running mechanism now is geared
          with a group of shaped people doing what seems to be, for them, a satisfying job. The
          resistance will be in breaking this (rusty) old geared system, polish it, newly shaping
          it, and redesign it for the new mechanism. Another source of resistance will be the
          powerful relationships between Menatel technicians and the companies’ labors.
          Redesigning the cleaning quality evaluation decision and reducing the weight of
          Menatel technicians’ evaluation will generate a kind of threat for them. This is why
          they will try to oppose the new process.
                             Individual sources
          Every day routine (habits) is the main source of individual resistance especially for
          the technicians, labors, and even supervisors level as this type of employees have no
          self confidant, it’s hard for them to learn new skills or to do things differently.
          Another source of resistance by the cleaning labors (temporary workers) is their
          feeling of having unsecured jobs, in addition their fear of the unknown new process
          its unknown effects over their income or job security.




          EMBA Cairo
          Rennes International School of Business                                                                 9
4.2     The movement phase
The movement phase is an action plan to overcome the resistance resources, by
increasing the driving forces to change and reduce the restraining forces for change, to
do so we need to be persistence and patience. The action plan strategy is as follows:
                Communicate the new process to all partners (lectures, documents).
                Get all concerned Menatel managers and cleaning companies’ inputs
                 and feedback of the new process, and share the responsibility.
                Negotiate the new process with key contractors (Alpha).
                Facilitate and encourage the new process (price increase).
                Standardize the documentation cycles (reports, invoice).
                Generate new contract to fit with the new process (standard contract).


           4.3     The refreezing phase
The objective of this phase is to balance the driving and restraining forces over the
new cleaning process in order to do so we need to follow and evaluate the movement
of the new process, also to monitor and measure results. The evaluation indicators
techniques are one of the new process measurement tool and they are:
                The cleaning checking indicator
                Effective communication indicator
                The on-time and accurate reporting indicator
                The field monthly random inspection visit indicator
Another measurement tool is the new penalty article that will help differentiates the
accepted and not accepted performance which in away rewarding the good
performing company by adding new locations to its assigned area.




EMBA Cairo
Rennes International School of Business                                             10
5- CONCLUSION
           MEN
           GHR
           SHR
           DAK
           KAL


                 In the process of analyzing and evaluating the Sub-Contractors performance in the
                 assigned tasks, we put in mind two factors. The current economic situation (increase
V /// Ex
V Ex  Ex
                 of inflation rate is affecting our business and their business). The Sub-Contractors`
                 services is indispensable to Menatel. This is mainly why we should change the
                 cleaning process to lead them to the most effective way to perform the assigned tasks
                 efficiently. This is the time to change, the time to do things differently.


                    6- RECOMMENDATION

                 It’s obvious from the above stated that the decision should be going for change and
                 we strongly believe that it is time for change and we for that recommend the
                 following actions:
                               Implement the new cleaning operation (1-4-2004).
                               Apply the new modified contract (1-4-2004).




                 EMBA Cairo
                 Rennes International School of Business                                          11

More Related Content

More from Magdy Abdelsattar Omar

More from Magdy Abdelsattar Omar (20)

Reasons to leave a job
Reasons to leave a jobReasons to leave a job
Reasons to leave a job
 
How to save your job if you're about to be fired
How to save your job if you're about to be firedHow to save your job if you're about to be fired
How to save your job if you're about to be fired
 
Do not apply for this job
Do not apply for this jobDo not apply for this job
Do not apply for this job
 
Can a company cut your pay or hours
Can a company cut your pay or hoursCan a company cut your pay or hours
Can a company cut your pay or hours
 
Why you may not have gotten a raise
Why you may not have gotten a raiseWhy you may not have gotten a raise
Why you may not have gotten a raise
 
10 steps to a successful career change
10 steps to a successful career change10 steps to a successful career change
10 steps to a successful career change
 
Top 10 e commerce builders
Top 10 e commerce buildersTop 10 e commerce builders
Top 10 e commerce builders
 
Sales management
Sales managementSales management
Sales management
 
Push & pull strategy
Push & pull strategyPush & pull strategy
Push & pull strategy
 
Egyptian e commerce market to reach $2.7bn by 2020
Egyptian e commerce market to reach $2.7bn by 2020Egyptian e commerce market to reach $2.7bn by 2020
Egyptian e commerce market to reach $2.7bn by 2020
 
Economy
EconomyEconomy
Economy
 
E commerce in egypt
E commerce in egyptE commerce in egypt
E commerce in egypt
 
B plan ssm
B plan ssmB plan ssm
B plan ssm
 
Distribution strategy
Distribution strategyDistribution strategy
Distribution strategy
 
Cv vs Resume
Cv vs ResumeCv vs Resume
Cv vs Resume
 
Distribution business
Distribution businessDistribution business
Distribution business
 
Telecommunication
TelecommunicationTelecommunication
Telecommunication
 
Career profile
Career profileCareer profile
Career profile
 
The secrets of a trainer
The secrets of a trainerThe secrets of a trainer
The secrets of a trainer
 
How to build a team
How to build a teamHow to build a team
How to build a team
 

Recently uploaded

Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 

Recently uploaded (20)

Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 

Hr and change management report

  • 1. Rennes International School of Business ESC RENNES Executive Master of Business Administration EMBA COHORT 1 (2003 - 2004) HR & Change Management Conducted by: Dr. Donald MINDAY Changing and standardize the Cleaning operation For Menatel By Magdy A. Sattar March, 2004 Cairo, Egypt
  • 2. EXECUTEVE SUMMARY .................................................................................................................. II 1- REPORT OBJECTIVE. ............................................................................................................... 1 2- MENATEL PROFILE.................................................................................................................. 1 3- CURRENT SITUATION ANALYSIS & IDINTIFING THE PROBLEM. ............................. 2 4- THE PROPOSED NEW CLEANING OPERATION STANDRALIZATION ....................... 3 5- CONCLUSION ........................................................................................................................... 11 6- RECOMMENDATION .............................................................................................................. 11 EMBA Cairo Rennes International School of Business I
  • 3. EXECUTEVE SUMMARY In this report, we analyze, evaluate and then recommend a method through which Menatel and the sub-contractors assigned to the cleaning operation satisfy their business needs and achieve effective and efficient communication. First, we will analysis the current situation (figures and performance) to identify the problem. Second, we shall go through explanation and description of the proposed new cleaning operation by its three phase’s unfreeze –movement –refreeze, describing the job duties assigned to the concerned parties and the expected output of their communication, the new basis of Menatel checking methodology for both cleaning quality and invoice checking. How we are going to communicate and explain the new process. Illustrate the sources of resistances, the movement phase strategies, and the refreezing techniques. Third, the conclusion and recommended decision that we think it should be taken. EMBA Cairo Rennes International School of Business II
  • 4. 1- Report Objective. The purpose of this report is to allow me to demonstrate my understanding of the principles and techniques covered during the HR and change management course. I will submit a business report that will address a proposed new cleaning operation process showing how Menatel will manage the changing process. I will analyze Menatel cleaning sub contractor situation through evaluating their performance quality compared to Menatel needs and quality standard, also revise all the contracts in order to present the new cleaning operation process by which both parties are satisfied and Menatel’s image is maintained. 2- Menatel profile Late in 1998 Menatel was born as a joint stock company, under investment low number 8/1997 registered in 1998 under number 314030. Menatel is granted a ten years; renewable license, to install, operate, and manage a telecommunication network of at least 30,000 public payphone. Egyptian shares are 53 % and foreign shares are 47 %. By the end of 2003 Menatel has been operating a payphone network with near to 30,000 payphones in operation, and work force of more than 400 employees. Thanks to our customers love, appreciation, and trust Menatel’s two colors (green and yellow) are now a trend, they can be seen every where, not only Menatel payphones but also kiosks, bill-boards or sometimes even buildings are painted in those two colors. This proves the fact that Menatel has succeeded to become an integral part of people’s daily life in Egypt. 2.1 Menatel Vision To be the leaders in the field of telecommunication services, as well as the leader in creating a national base of accumulated expertise of high Egyptian telecom engineers. 2.2 Menatel Goals  Exceptional Customer Satisfaction.  Inspired, innovative and empowered Employees.  Depending on local sourcing whenever possible.  Superior Financial Results. EMBA Cairo Rennes International School of Business 1
  • 5. 2.3 Menatel Values  Customer First.  Integrity in All we do.  Excellence through Total Quality.  Respect for others.  Respect for our environment.  Growth through change. 3- Current Situation Analysis & Idintifing the problem. 3.2 Current situation figures analysis. Sub- Price (LE) Contract Contract Branch Zone Area (Governorates) contractors PD2 PD1 WM Start End Alpha, Giza, El-Fayoum, Baniswef Cairo 1 Pyramids, 0.40 0.25 0.20 24/12/01 31/12/03 Gov. United Alpha, Cairo 2 East & south Cairo Pyramids, 0.40 0.25 0.20 24/12/01 31/12/03 United West & north Cairo, 10th of Alpha, Cairo 3 Ramadan, shoubra el khaima, Pyramids, 0.40 0.25 0.20 24/12/01 31/12/03 kanater , kalubia, and khanka United Alex 4 East Alex., and Behera Alpha 0.40 0.25 0.20 24/12/01 31/12/03 West Alex., north coast, and Alex 5 Alpha 0.40 0.25 0.20 24/12/01 31/12/03 Marsa matroh Port said, Damiatta, north Canal 6 Adam Siag 0.40 0.25 0.20 24/12/01 31/12/03 Sina Canal 7 Suze, Ismailia, and south Sina Adam Siag 0.40 0.25 0.20 24/12/01 31/12/03 Kafer el sheikh, Dakhlia, and Delta 8 El Kods 0.40 0.25 0.20 7/3/02 31/12/03 Sharkia Monofia, Gharbia, banha, Delta 9 tokh, Kafer shoker, shebeen el Alpha 0.40 0.25 0.20 24/12/01 31/12/03 kanater MUE 10 El-Minia Alpha 0.45 0.27 0.25 24/12/01 31/12/03 MUE 11 Assiut, and New valley High care 0.49 0.29 0.24 24/12/02 31/12/03 MUE 12 Sohag High care 0.49 0.29 0.24 24/12/02 31/12/03 SUE 13 Quena, and Louxer Alpha 0.45 0.27 0.25 24/12/01 31/12/03 SUE 14 Aswan Alpha 0.45 0.27 0.25 24/12/01 31/12/03 SUE 15 Red Sea Alpha 0.45 0.27 0.25 24/12/01 31/12/03 EMBA Cairo Rennes International School of Business 2
  • 6. The table above shows the following  A total of six sub-contractors assigned to clean Menatel booths distributed over 15 different zones.  All contracts ended 31/12/2003.  There are three different prices. 3.3 Current situation performances analysis. The table below shows the average cleaning quality per branch for the year 2003, from which we can see the big gap in the performance from branch to another, which indicates different methodology of evaluating the cleaning quality which of course generates a lot of conflicts. Branch Cairo Alex Canal Delta MUE SUE Average 91.5 % 94 % 65 % 83 % 97 % 96 % 3.4 Problem Identification By the above analysis the problem can be stated as a vague understanding or conflict among the partners (Menatel, and the cleaning contractors). This poor environment of work, in additional to the economical situation drop in 2003, forces Menatel to revise the whole cleaning operation and try to find or adapt a planned change that will match the new environment and new strategies of Menatel to optimize our resources. For that I was assigned as a change agent to propose and plan the change process for the cleaning operation. My objectives are:  To plan a clear, controlled and standard cleaning quality operation  To plan standard invoice checking process  To revise old contracts and plan a new contract to fit the new change 4- The proposed new cleaning operation standralization Based on Lewin’s change model I divided the change process to three phases 4.1 The unfreeze phase This phase where we unfreeze the old operation and plan the new one which is composed of: EMBA Cairo Rennes International School of Business 3
  • 7. 4.1.1 Operation partners and job descriptions  Contractors field labor tasks  Daily tasks In additional to his daily cleaning tasks, for urgent notes to be reported the field labor contacts Menatel directly in cases of any fault or problem that would make the payphone not available to the customer to use. for example, a cut handset, an out of order payphone, an inserted card, an open PP’s case shell, or the phone is ripped of the booth. In such cases the field labor has to make an immediate contact with the technician assigned to the area or the maintenance Eng. if either of them is not available to reach for any reason he should call the customer service center and report the case. For cases that might cause the payphone to be out of order in one to three days, for example, the booth is not fixed tight to the ground which can be a threat to the customers, lack of U-guard or cables are not fixed. In such cases the field labor must report these cases to his direct field supervisor.  Weekly tasks Cases that affect the image of Menatel (booth or payphone status) such as, ribbed off sides, broken or scratched display, broken fibers or lack of boosters. These notes should be reported first to the contractor field supervisor, then, it should be put into a detailed weekly report that to be sent to Menatel  Contractors field supervisor  Daily tasks Each for his assigned area contact Menatel assigned supervisor to report any cases that might affect directly the efficiency of the payphones service quality or cause it to be out of order within the next 48hours.  Weekly tasks Represent a weekly report in which all the notes and the needs of booth maintenance operation might need to maintain the image of Menatel. The accuracy and on time commitment of delivering this report is to be considered in evaluating the cleaning quality. EMBA Cairo Rennes International School of Business 4
  • 8.  Contractors project manager He is to be in touch with Menatel CCs. Supervisor to make sure that the operation is working in smooth way and all the resources are available to do the assigned tasks in the field (tools, equipments).  Menatel cleaning controller He is assigned by menatel to implement menatel cleaning quality methodology and to make sure that the cleaning contractor’s labors are doing what they should be doing according to Menatel standards.  Menatel CCs. supervisor He is the operation controller assigned by menatel to do all the necessary actions to maintain Menatel image in the field following up closely the quality of the booths and payphones (cleaning, shaping, conditioning). 4.1.2 Checking methodology  Cleaning quality checking Menatel team of cleaning controllers and their supervisor are assigned to perform this check through the sampling plan techniques and prepare its plan, daily check list, and reports needed. Their calculations to the QS of the cleaning (based on the cabinet body sets values) in their assigned area is the main reference. The area assigned to the contractor shall be divided into routes on which the CC. Shall makes his check rounds 2 to 3 rounds per month (or according to the area nature and the no. of Menatel CCs). In each of these rounds a different random sample -around 10%-of total locations in every City or district in the route shall be taken as a reference by one member of the team. So that by the end of the month the whole area assigned to the contractor is checked over three times, each time by a different CC. Cleaning Controller are checking over 3 main things:  Checking the cleaning quality of the booths  Contractor commitment to daily cleaning operation (whether or not the city or district is cleaned daily)  Contractor staff (field labors and supervisors) cooperation and their effective communication EMBA Cairo Rennes International School of Business 5
  • 9. The technician team is involved also in evaluating the contractor's staff cooperation and response to the field needs.  Sampling plan elements (proposed). acceptance rejection criteria Branch lot size sample size number of samples criteria Cl Cp Cairo 12200 10 % =1220 4/month 5% = 61 Booth 20% = 244 Booth Alex 4700 10 % =470 4/month 5% = 23 Booth 20% = 94 Booth Delta 4200 10 % =420 4/month 5% = 21 Booth 20% = 84 Booth Canal 4100 10 % =410 4/month 5% = 20 Booth 20% = 82 Booth MUE 2600 10 % =260 4/month 5% = 13 Booth 20% = 52 Booth SUE 2200 10 % =220 4/month 5% = 11 Booth 20% = 44 Booth Menatel 30000 10 % =3000 4/month 5% = 150 Booth 20% = 600 Booth  Cabinet body parts Set (1) 20% Set (2) 25% Set (3) 30% Set (4) 15% Set (5) 10% The contractor should be very careful to use the proper means (water, cleansers, ladders and brushes) which does not affect the efficiency of the PP. or distort its appearance. EMBA Cairo Rennes International School of Business 6
  • 10.  Invoice checking There are 3 factors in the contractors' invoice that conclude the invoice and over which Menatel is revising  Numbers and type of locations.  Numbers of actual working (cleaning) days.  Cleaning Quality of the assigned area As for the No. and type of the booths in field, Menatel monthly updated report from Menaprod (Menatel data base) is the reference in this issue, Meaning that any deviation from Mantel's report (positive or negative) will be calculated and deducted from the contractor's total figures. As for the actual working days, Menatel emphasis that, any National holidays occurring in the month shall be deducted from the invoice. Cleaning Invoices Evaluation Field On Time & Communication Cleaning Monthly Accurate & Co-operation Checking Visit Reporting 10 % 10 % 10 % 70 % Measurement Measurement Measurement Measurement Tool Tool Tool Tool Sampling Data Accuracy & Global QS per Sampling No. of Reports Technician As for the cleaning quality of the cleaning operations the above chart clarifies the suggested process of evaluating the Contractor Cleaning Invoices according to the agreed upon indicators and its weights. Cleaning Checking Indicator Weight (70%) its measurement tool is sampling its calculation will be as follows: Should the Sample result meet the CI (Acceptance criteria (5%) Commented upon cabinets) the contractor evaluation in this indicator is 100% (70%). EMBA Cairo Rennes International School of Business 7
  • 11. Should the sample result meet the CP (Rejection criteria (20%) commented upon cabinets) the whole sample result is rejected and the contractor evaluation in this indicator is 0%. Should the sample result varies between CI and CP (from 6%to 19%) the result of this sample will be put as it is and the contractor will be evaluated by the average the whole sample results. The assigned Menatel Engineer will represent a monthly report of the result of the samples. Communication and cooperation indicator Weight (10%) Its Measurement tool is technicians feed back upon the global QS. Maintenance Engineer will represent a monthly report of the Technician feed back. The payphones QS, target is no less than 98% the percentage of negative deviation from the target is deducted from the weight indicator On time and Accurate Reporting indicator Weight (10%) its measurement is: Four weekly reports to be delivered per month to Menatel, and accurate data in the reports. The commitment of delivering these weekly reports and the accuracy of these reports will be put in a monthly report. Field Monthly Visit indicator Weight (10%) its Measurement tool is sampling. The report of this visit result signed by both parties shall be represented monthly. There are two final notes that are: The cover of the invoice presented from the contractor should be unified but the details inside the invoice could vary from according to the branch or the department assigned area (Territory, Governorate, and Area). Each branch or department can decide the sample size, number of samples per month and the locations in the samples in accord to two main factors the area needs and the branch resources (transportation, cleaning controller, and technician) 4.1.3 Communicate & explanation of the new process The new cleaning process will be communicated to all partners through lectures done by the change agent to cover and explain the new terminology of the new process and to clear any misunderstandings or conflict and according to the below table this will take place all over Menatel branches and some of the contractors locations, and will address all the key persons of the new cleaning operation. EMBA Cairo Rennes International School of Business 8
  • 12. Presentation Dates Location Attendance Concerned company/branch time Sunday 15-2-2004 HQ S-12 am/E-4pm Menatel Directors, and Managers All Wednesday 18-2-2004 HQ S-12 am/E-4pm The companies owners or the General Managers contractors HQ/distribution Cairo branch, Delta branch, accountant dep., alpha, Monday 15-3-2004 S-11am/E-3pm 25 persons room united group, Pyramids, and Elkods. Tuesday 16-3-2004 Asute Branch S-12am/E-3pm 15 persons Asute branch, high care, and alpha. Wednesday 17-3-2004 Luxer Branch S-12am/E-3pm 15 persons Luxer branch and alpha. Thursday 18-3-2004 Port S. Branch S-12am/E-3pm 15 persons Port S. branch, and Adam Siage. Sunday 21-3-2004 Alex. Branch S-12am/E-3pm 15 persons Alex. Branch, and alpha Alpha company representatives and the company Monday 29-3-2004 Alpha company S-11am/E-3pm 7 persons owner 4.1.4 Sources of resistances Change resistance is a law of nature also it is an obstacle in the way of the new process and stand against the smooth movement of it. This obstacle is generated by two main sources, organizational sources or individual sources.  Organizational sources The main source of resistance we expect it to be the organization structural inertia for both Menatel and the cleaning companies. The running mechanism now is geared with a group of shaped people doing what seems to be, for them, a satisfying job. The resistance will be in breaking this (rusty) old geared system, polish it, newly shaping it, and redesign it for the new mechanism. Another source of resistance will be the powerful relationships between Menatel technicians and the companies’ labors. Redesigning the cleaning quality evaluation decision and reducing the weight of Menatel technicians’ evaluation will generate a kind of threat for them. This is why they will try to oppose the new process.  Individual sources Every day routine (habits) is the main source of individual resistance especially for the technicians, labors, and even supervisors level as this type of employees have no self confidant, it’s hard for them to learn new skills or to do things differently. Another source of resistance by the cleaning labors (temporary workers) is their feeling of having unsecured jobs, in addition their fear of the unknown new process its unknown effects over their income or job security. EMBA Cairo Rennes International School of Business 9
  • 13. 4.2 The movement phase The movement phase is an action plan to overcome the resistance resources, by increasing the driving forces to change and reduce the restraining forces for change, to do so we need to be persistence and patience. The action plan strategy is as follows:  Communicate the new process to all partners (lectures, documents).  Get all concerned Menatel managers and cleaning companies’ inputs and feedback of the new process, and share the responsibility.  Negotiate the new process with key contractors (Alpha).  Facilitate and encourage the new process (price increase).  Standardize the documentation cycles (reports, invoice).  Generate new contract to fit with the new process (standard contract). 4.3 The refreezing phase The objective of this phase is to balance the driving and restraining forces over the new cleaning process in order to do so we need to follow and evaluate the movement of the new process, also to monitor and measure results. The evaluation indicators techniques are one of the new process measurement tool and they are:  The cleaning checking indicator  Effective communication indicator  The on-time and accurate reporting indicator  The field monthly random inspection visit indicator Another measurement tool is the new penalty article that will help differentiates the accepted and not accepted performance which in away rewarding the good performing company by adding new locations to its assigned area. EMBA Cairo Rennes International School of Business 10
  • 14. 5- CONCLUSION MEN GHR SHR DAK KAL In the process of analyzing and evaluating the Sub-Contractors performance in the assigned tasks, we put in mind two factors. The current economic situation (increase V /// Ex V Ex Ex of inflation rate is affecting our business and their business). The Sub-Contractors` services is indispensable to Menatel. This is mainly why we should change the cleaning process to lead them to the most effective way to perform the assigned tasks efficiently. This is the time to change, the time to do things differently. 6- RECOMMENDATION It’s obvious from the above stated that the decision should be going for change and we strongly believe that it is time for change and we for that recommend the following actions:  Implement the new cleaning operation (1-4-2004).  Apply the new modified contract (1-4-2004). EMBA Cairo Rennes International School of Business 11