 Background

The brewery has ten Cellars. Each cellar is
divided into different tanks, in which the
fermentation takes place. Glycine is passed
through tubes wound round the tanks to control
the temperature during the brewing process.
A solenoid valve is used to open and close flow
of glycine. Pt100 at the top and bottom of each
tank are used to monitor the temperature. The
temperature is either monitored using the Top/
Bottom PT100 or both PT100s. should any of the
PT100 fail the PLC will switch the control
completely to the healthy one.
Each of the tanks can be in one of the following
modes: Ready, Filling, Fermentation, Chill or
Cleaning in Progress (CIP)

 AGE’s Scope of work to be done –

The plant is divided into three Control systems,
i.e. Cellar 1&2, Cellar 3-8 and Cellar 9&10.
A SCADA (Supervisory Control And Data
Acquisition) system will provide a graphical
overview of the whole control system. An
Ethernet TCP/IP network will link the three
Systems and the SCADA.

 Significant Features of the project –





HMI will provide the operator with status of each
Cellar and Tank
SCADA system will provide a graphical overview
of the plant, with the status of each tank.
A graph of all temperatures and operator
inputted information will be available.
The fermentation manager will be able to change
the operating mode of a tank, and with a login
password he can also change the temperature
set points.








A historical log will also be kept of all tank
batches that have been brewed
Keeping data for each batch is important
for quality purposes.
The Mode of operation of each tank will
be colour coded - determined by its
background Colour in the overview page.
A Siren and alarm lamp will be installed at
each control system to warn the operator
of an alarm condition

Products used –

 Modicon TSX Premium from Schneider
Electric
 PLC software - PL7 Pro for TSX Premium
PLC
 HMI - is an EZTOUCH, Modbus/TCP 8” Slim
panel
 SCADA System - Intouch version 9, with
1000 tag licence
 Spider, 5 port 10/100 Ethernet switches for
each Control system



Duration of the project –

6 months



Total Value –

R 605,906.34

More Related Content

Viewers also liked

Brochure - Slim Boring 2016
Brochure - Slim Boring 2016Brochure - Slim Boring 2016
Brochure - Slim Boring 2016Master Drilling
 
Fx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific BreweriesFx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific BreweriesMeggiePhan
 
The Global Brewery Industry
The Global Brewery IndustryThe Global Brewery Industry
The Global Brewery IndustrySobithan Sekar
 
Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...Cary Institute of Ecosystem Studies
 
PROCESO MONTAJE 03
PROCESO MONTAJE 03PROCESO MONTAJE 03
PROCESO MONTAJE 03cecilia
 
AGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE Technologies
 
Implementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE TechnologiesImplementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE TechnologiesAGE Technologies
 
Heineken Case Study business Analysis
Heineken Case Study business AnalysisHeineken Case Study business Analysis
Heineken Case Study business Analysisjin88lin
 

Viewers also liked (10)

Brochure - Slim Boring 2016
Brochure - Slim Boring 2016Brochure - Slim Boring 2016
Brochure - Slim Boring 2016
 
Kendal power station
Kendal power station Kendal power station
Kendal power station
 
Fx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific BreweriesFx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific Breweries
 
The Global Brewery Industry
The Global Brewery IndustryThe Global Brewery Industry
The Global Brewery Industry
 
Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...
 
Age Catalogue Feb'14
Age Catalogue Feb'14Age Catalogue Feb'14
Age Catalogue Feb'14
 
PROCESO MONTAJE 03
PROCESO MONTAJE 03PROCESO MONTAJE 03
PROCESO MONTAJE 03
 
AGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefs
 
Implementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE TechnologiesImplementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE Technologies
 
Heineken Case Study business Analysis
Heineken Case Study business AnalysisHeineken Case Study business Analysis
Heineken Case Study business Analysis
 

Similar to Brewery Fermentation Control System Project

Similar to Brewery Fermentation Control System Project (20)

I012455457
I012455457I012455457
I012455457
 
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
NEXCOM_APPC_1533T-P20s_Exercise_Strict_Control_Monitoring_over_Steelmaking_Qu...
 
Basic plc
Basic plcBasic plc
Basic plc
 
Basic PLC.ppt
Basic PLC.pptBasic PLC.ppt
Basic PLC.ppt
 
Presentaton on Plc & Scada
Presentaton on Plc & ScadaPresentaton on Plc & Scada
Presentaton on Plc & Scada
 
Dgps control system
Dgps control systemDgps control system
Dgps control system
 
PLC SCADA
PLC SCADAPLC SCADA
PLC SCADA
 
Plc scada-140717081152-phpapp02
Plc scada-140717081152-phpapp02Plc scada-140717081152-phpapp02
Plc scada-140717081152-phpapp02
 
PLC, by Mohamed Al-Emam, Session 1
PLC, by Mohamed Al-Emam, Session 1PLC, by Mohamed Al-Emam, Session 1
PLC, by Mohamed Al-Emam, Session 1
 
Basic plc 1
Basic plc 1Basic plc 1
Basic plc 1
 
Advanced insrumentation lab manual
Advanced insrumentation lab manualAdvanced insrumentation lab manual
Advanced insrumentation lab manual
 
Temperature humidity control cabinets
Temperature humidity control cabinetsTemperature humidity control cabinets
Temperature humidity control cabinets
 
Plc scada(by ankit)2
Plc scada(by ankit)2Plc scada(by ankit)2
Plc scada(by ankit)2
 
Elitech Controls HVAC refrigeration company overview
Elitech Controls HVAC refrigeration company overviewElitech Controls HVAC refrigeration company overview
Elitech Controls HVAC refrigeration company overview
 
Basic plc
Basic plcBasic plc
Basic plc
 
Walk in-seed-germinator
Walk in-seed-germinatorWalk in-seed-germinator
Walk in-seed-germinator
 
Plc
PlcPlc
Plc
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Basic plc
Basic plcBasic plc
Basic plc
 
Basic plc
Basic plcBasic plc
Basic plc
 

Brewery Fermentation Control System Project

  • 1.  Background The brewery has ten Cellars. Each cellar is divided into different tanks, in which the fermentation takes place. Glycine is passed through tubes wound round the tanks to control the temperature during the brewing process. A solenoid valve is used to open and close flow of glycine. Pt100 at the top and bottom of each tank are used to monitor the temperature. The temperature is either monitored using the Top/ Bottom PT100 or both PT100s. should any of the PT100 fail the PLC will switch the control completely to the healthy one. Each of the tanks can be in one of the following modes: Ready, Filling, Fermentation, Chill or Cleaning in Progress (CIP)  AGE’s Scope of work to be done – The plant is divided into three Control systems, i.e. Cellar 1&2, Cellar 3-8 and Cellar 9&10. A SCADA (Supervisory Control And Data Acquisition) system will provide a graphical overview of the whole control system. An Ethernet TCP/IP network will link the three Systems and the SCADA.  Significant Features of the project –     HMI will provide the operator with status of each Cellar and Tank SCADA system will provide a graphical overview of the plant, with the status of each tank. A graph of all temperatures and operator inputted information will be available. The fermentation manager will be able to change the operating mode of a tank, and with a login password he can also change the temperature set points.      A historical log will also be kept of all tank batches that have been brewed Keeping data for each batch is important for quality purposes. The Mode of operation of each tank will be colour coded - determined by its background Colour in the overview page. A Siren and alarm lamp will be installed at each control system to warn the operator of an alarm condition Products used –  Modicon TSX Premium from Schneider Electric  PLC software - PL7 Pro for TSX Premium PLC  HMI - is an EZTOUCH, Modbus/TCP 8” Slim panel  SCADA System - Intouch version 9, with 1000 tag licence  Spider, 5 port 10/100 Ethernet switches for each Control system  Duration of the project – 6 months  Total Value – R 605,906.34