SlideShare una empresa de Scribd logo
1 de 18
Descargar para leer sin conexión
KLIA2
- Some Salient Facts
Source: Masters Thesis of Mr Sivabalan Naidu of IPE
Management School, Paris
1st June 2014
The Regional Hub to be?
Is KLIA 2 sinking now?
• Why was a new master plan drawn up in 2008 for
the expansion of the low-cost carrier airport
(KLIA2), resulting in the airport being built on soft
soil, when an earlier plan circumvented (avoided)
this problem?
• This question lies at the heart of the current
outcry over the ballooned cost of the airport
from an estimated RM1.7 billion to up to over
RM4 billion today and the question of safety.
• Refer to the International Airport Masterplan
1992
Why we continue to faulter in our
projects?
Klia2 facts
Executive summary
• The purpose of this report was to undertake a thorough investigation
into the various causative factors which may have contributed to the
failure of KLIA 2 by Malaysia Airports Holdings Berhad (MAHB)
• The cost overrun was from RM 1.9 Billion to RM 4.0 Billion and with
more than 2 years of delay in its completion.
• One of the major factors which may have contributed to the cost
overrun and delayed completion is the inability to manage change.
• As we know, managing the changes in a project is a part of project
management life cycle.
Executive summary
• Based on the report, given by CEO & Managing Director of
Malaysia Airports Holdings Berhad (MAHB) Tan Sri Bashir
Ahmad, the new terminal was delayed three times from its
original completion date of September 2011
• It is because of the new requirements.
• If only the additional or new requirements had been managed
with a scope which is a major factor in having a balanced
project management these cost overruns and delays would not
have occurred.
Executive summary
• After taking all the project success and failure factors into
consideration, it is recommended that the Chairperson of the
MAHB Board of Directors should use Statement of Work
(SOW) as a yardstick of progress and success.
• Plan the purpose of the project by taking into consideration,
the risk management and scope in this case is to finish the
KLIA 2 as per the initial project planning without running
away from the schedule and cost.….
Executive summary
• ….and to clearly outline the possible risks, and
management of the risk so that when a change or new
requirements arises we could manage it without
interrupting the iron triangle, where the main
components are quality, scope, cost and schedule.
• This is the key being the co-ordination between all the
sectors working in building KLIA 2
Klia2 facts
Scope Variation
Klia2 facts
Klia2 facts
- Air
Asia
Conclusion & Recommendations
• We have discussed the various relevant factors which
may have contributed to the failure of KLIA 2 by
Malaysia Airports Holdings Berhad (MAHB).
• The key factors being lack of anticipation to the
project plan changes and a poor risk management.
• Thus, I would recommend to the chairperson of
MAHB in the future projects have a change
management team where they help execute and
manage change to ensure, you not only meet your
business objectives but new processes are adopted
and sustained.
Conclusion& Recommendations
• Other than that it’s crucial to follow the four
phases of project management life cycle and not
skipping any of these phases will ensure the
success of the project.
• It is also important to create statement of work
(SOW) for the business case to identify the
purpose, scope, project deliverables, goals and
objectives and cost and schedule estimates. These
ensure we do not run out of the planning we
initially made thus preventing mishaps such as cost
overrun or delays..
Conclusion & Recommendations
• Adding to that the risk management team
should calculate the possible risks with the
help of risk impact / probability chart. This
gives a quick and clear view of the priority we
need to give each, and help us to decide what
resource to allocate in managing the
particular risk
Conclusion & Recommendations
• Therefore as conclusion project management
skills should be incorporated with the theories
and models I have presented in my study
above should be followed to attain project
success, as these are the models proven by
researches and trials. I hope these
recommendations will help to elevate the
project success in future business cases

Más contenido relacionado

La actualidad más candente

Architecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation ReportArchitecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation ReportNaqiuddin Johari
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Hamza Waheed
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1Afiq Knick
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectNekumi Kida
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Tan Jaden
 
pihak yang terlibat dalam projek pembinaan
pihak yang terlibat dalam projek pembinaanpihak yang terlibat dalam projek pembinaan
pihak yang terlibat dalam projek pembinaanFiQahh AmiNn
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in ConstructionSamsonFemiAdesope
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)Pang Khai Shuen
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 

La actualidad más candente (20)

Architecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation ReportArchitecture Museum Malacca Dilapidation Report
Architecture Museum Malacca Dilapidation Report
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
BS Role
BS RoleBS Role
BS Role
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Tender
TenderTender
Tender
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Project brief
Project briefProject brief
Project brief
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...
 
pihak yang terlibat dalam projek pembinaan
pihak yang terlibat dalam projek pembinaanpihak yang terlibat dalam projek pembinaan
pihak yang terlibat dalam projek pembinaan
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 

Destacado

Kuala lumpur international air port
Kuala lumpur international air portKuala lumpur international air port
Kuala lumpur international air portYuwita Killua
 
introduction to klia
introduction to kliaintroduction to klia
introduction to kliaAiDY
 
KLIA v.02 presentation aznan
KLIA v.02 presentation aznanKLIA v.02 presentation aznan
KLIA v.02 presentation aznanAiDY
 
Pm certifications & accreditations
Pm certifications & accreditationsPm certifications & accreditations
Pm certifications & accreditationsmasilamani ramasamy
 
Basics of sSpply Chain Management
Basics of sSpply Chain ManagementBasics of sSpply Chain Management
Basics of sSpply Chain Managementmasilamani ramasamy
 
Malaysia airport management
Malaysia airport managementMalaysia airport management
Malaysia airport managementgracenis44
 
Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...
Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...
Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...BC Chew
 
Malaysia airlines ppt
Malaysia airlines pptMalaysia airlines ppt
Malaysia airlines pptKotee Swaran
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartAnand Bobade
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasksAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 

Destacado (20)

Kuala lumpur international air port
Kuala lumpur international air portKuala lumpur international air port
Kuala lumpur international air port
 
introduction to klia
introduction to kliaintroduction to klia
introduction to klia
 
Unique of klia2
Unique of klia2Unique of klia2
Unique of klia2
 
KLIA v.02 presentation aznan
KLIA v.02 presentation aznanKLIA v.02 presentation aznan
KLIA v.02 presentation aznan
 
Presentation on pmp exam
Presentation on pmp examPresentation on pmp exam
Presentation on pmp exam
 
Successful project
Successful projectSuccessful project
Successful project
 
Pm certifications & accreditations
Pm certifications & accreditationsPm certifications & accreditations
Pm certifications & accreditations
 
Basics of sSpply Chain Management
Basics of sSpply Chain ManagementBasics of sSpply Chain Management
Basics of sSpply Chain Management
 
Procurement lecture
Procurement lectureProcurement lecture
Procurement lecture
 
KLIA 2
KLIA 2KLIA 2
KLIA 2
 
Malaysia airport management
Malaysia airport managementMalaysia airport management
Malaysia airport management
 
Essentialsof Project Management
Essentialsof Project ManagementEssentialsof Project Management
Essentialsof Project Management
 
Developing Facilitation Skills
Developing Facilitation Skills Developing Facilitation Skills
Developing Facilitation Skills
 
Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...
Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...
Adoption of Piezoelectric Tiles as an Alternative Energy Source: A Feasibili...
 
Malaysia airlines ppt
Malaysia airlines pptMalaysia airlines ppt
Malaysia airlines ppt
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes Chart
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Cost management
Cost managementCost management
Cost management
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasks
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 

Similar a Klia2 facts

Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsIbrahim Al-Hudhaif
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project managementprakashnachnani
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxmalikshanii458
 
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...REDceo.net
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxkiranroy6777
 
Unit viii preparation of project report
Unit viii preparation of project reportUnit viii preparation of project report
Unit viii preparation of project reporttaruian
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...Dr Rupert Booth
 

Similar a Klia2 facts (20)

Lec#1
Lec#1Lec#1
Lec#1
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
 
VM Guide - Final
VM Guide - FinalVM Guide - Final
VM Guide - Final
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
 
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
Unit viii preparation of project report
Unit viii preparation of project reportUnit viii preparation of project report
Unit viii preparation of project report
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Project Management
Project ManagementProject Management
Project Management
 
Managing project (snowball)
Managing project (snowball)Managing project (snowball)
Managing project (snowball)
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Pmo
PmoPmo
Pmo
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...
 

Más de masilamani ramasamy (20)

Leadership exercises 4
Leadership exercises 4Leadership exercises 4
Leadership exercises 4
 
Leadership
LeadershipLeadership
Leadership
 
MH370 & The Bayes Theory [autosaved]
MH370 & The Bayes Theory [autosaved]MH370 & The Bayes Theory [autosaved]
MH370 & The Bayes Theory [autosaved]
 
MH370 & The Bayes Theory [autosaved]
MH370 & The Bayes Theory [autosaved]MH370 & The Bayes Theory [autosaved]
MH370 & The Bayes Theory [autosaved]
 
The bayes theory [autosaved]
The bayes theory [autosaved]The bayes theory [autosaved]
The bayes theory [autosaved]
 
MH370 & The Bayes theory [autosaved]
MH370 & The Bayes theory [autosaved]MH370 & The Bayes theory [autosaved]
MH370 & The Bayes theory [autosaved]
 
MH 370 & the Bayes theory
MH 370 & the Bayes theoryMH 370 & the Bayes theory
MH 370 & the Bayes theory
 
Nine Things-in-the-PMBoK
Nine Things-in-the-PMBoKNine Things-in-the-PMBoK
Nine Things-in-the-PMBoK
 
Black belt vs PMP Friend
Black belt vs PMP FriendBlack belt vs PMP Friend
Black belt vs PMP Friend
 
Business+Leaders-quotes worth cosidering
Business+Leaders-quotes worth cosideringBusiness+Leaders-quotes worth cosidering
Business+Leaders-quotes worth cosidering
 
The Hospitality Industry-the trends,
The Hospitality Industry-the trends, The Hospitality Industry-the trends,
The Hospitality Industry-the trends,
 
Basic Facilitation Skills
Basic Facilitation SkillsBasic Facilitation Skills
Basic Facilitation Skills
 
Presentation1
Presentation1Presentation1
Presentation1
 
Leaders develop leaders
Leaders develop leadersLeaders develop leaders
Leaders develop leaders
 
First marketing workshopr of sridaya
First marketing workshopr of sridayaFirst marketing workshopr of sridaya
First marketing workshopr of sridaya
 
Bpm overview
Bpm overviewBpm overview
Bpm overview
 
Marketing management-ppt
Marketing management-pptMarketing management-ppt
Marketing management-ppt
 
Abilitities of leaders
Abilitities of leadersAbilitities of leaders
Abilitities of leaders
 
Manage risks
Manage risksManage risks
Manage risks
 
Pmce presentation slides
Pmce presentation slidesPmce presentation slides
Pmce presentation slides
 

Último

Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...sahb78428
 
Guardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSecGuardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSecTrupti Shiralkar, CISSP
 
Dev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingDev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingMarian Marinov
 
Landsman converter for power factor improvement
Landsman converter for power factor improvementLandsman converter for power factor improvement
Landsman converter for power factor improvementVijayMuni2
 
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchrohitcse52
 
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfSummer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfNaveenVerma126
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Apollo Techno Industries Pvt Ltd
 
Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...soginsider
 
The relationship between iot and communication technology
The relationship between iot and communication technologyThe relationship between iot and communication technology
The relationship between iot and communication technologyabdulkadirmukarram03
 
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...amrabdallah9
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderjuancarlos286641
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptxSaiGouthamSunkara
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide LaboratoryBahzad5
 
Graphics Primitives and CG Display Devices
Graphics Primitives and CG Display DevicesGraphics Primitives and CG Display Devices
Graphics Primitives and CG Display DevicesDIPIKA83
 
Test of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptxTest of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptxHome
 
cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabusViolet Violet
 

Último (20)

Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...
 
Guardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSecGuardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSec
 
Dev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & LoggingDev.bg DevOps March 2024 Monitoring & Logging
Dev.bg DevOps March 2024 Monitoring & Logging
 
Landsman converter for power factor improvement
Landsman converter for power factor improvementLandsman converter for power factor improvement
Landsman converter for power factor improvement
 
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
 
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdfSummer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
Summer training report on BUILDING CONSTRUCTION for DIPLOMA Students.pdf
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
Litature Review: Research Paper work for Engineering
Litature Review: Research Paper work for EngineeringLitature Review: Research Paper work for Engineering
Litature Review: Research Paper work for Engineering
 
Lecture 4 .pdf
Lecture 4                              .pdfLecture 4                              .pdf
Lecture 4 .pdf
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
 
Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...
 
The relationship between iot and communication technology
The relationship between iot and communication technologyThe relationship between iot and communication technology
The relationship between iot and communication technology
 
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entender
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptx
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
Graphics Primitives and CG Display Devices
Graphics Primitives and CG Display DevicesGraphics Primitives and CG Display Devices
Graphics Primitives and CG Display Devices
 
Test of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptxTest of Significance of Large Samples for Mean = µ.pptx
Test of Significance of Large Samples for Mean = µ.pptx
 
cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabus
 

Klia2 facts

  • 1. KLIA2 - Some Salient Facts Source: Masters Thesis of Mr Sivabalan Naidu of IPE Management School, Paris 1st June 2014
  • 3. Is KLIA 2 sinking now? • Why was a new master plan drawn up in 2008 for the expansion of the low-cost carrier airport (KLIA2), resulting in the airport being built on soft soil, when an earlier plan circumvented (avoided) this problem? • This question lies at the heart of the current outcry over the ballooned cost of the airport from an estimated RM1.7 billion to up to over RM4 billion today and the question of safety. • Refer to the International Airport Masterplan 1992
  • 4. Why we continue to faulter in our projects?
  • 6. Executive summary • The purpose of this report was to undertake a thorough investigation into the various causative factors which may have contributed to the failure of KLIA 2 by Malaysia Airports Holdings Berhad (MAHB) • The cost overrun was from RM 1.9 Billion to RM 4.0 Billion and with more than 2 years of delay in its completion. • One of the major factors which may have contributed to the cost overrun and delayed completion is the inability to manage change. • As we know, managing the changes in a project is a part of project management life cycle.
  • 7. Executive summary • Based on the report, given by CEO & Managing Director of Malaysia Airports Holdings Berhad (MAHB) Tan Sri Bashir Ahmad, the new terminal was delayed three times from its original completion date of September 2011 • It is because of the new requirements. • If only the additional or new requirements had been managed with a scope which is a major factor in having a balanced project management these cost overruns and delays would not have occurred.
  • 8. Executive summary • After taking all the project success and failure factors into consideration, it is recommended that the Chairperson of the MAHB Board of Directors should use Statement of Work (SOW) as a yardstick of progress and success. • Plan the purpose of the project by taking into consideration, the risk management and scope in this case is to finish the KLIA 2 as per the initial project planning without running away from the schedule and cost.….
  • 9. Executive summary • ….and to clearly outline the possible risks, and management of the risk so that when a change or new requirements arises we could manage it without interrupting the iron triangle, where the main components are quality, scope, cost and schedule. • This is the key being the co-ordination between all the sectors working in building KLIA 2
  • 15. Conclusion & Recommendations • We have discussed the various relevant factors which may have contributed to the failure of KLIA 2 by Malaysia Airports Holdings Berhad (MAHB). • The key factors being lack of anticipation to the project plan changes and a poor risk management. • Thus, I would recommend to the chairperson of MAHB in the future projects have a change management team where they help execute and manage change to ensure, you not only meet your business objectives but new processes are adopted and sustained.
  • 16. Conclusion& Recommendations • Other than that it’s crucial to follow the four phases of project management life cycle and not skipping any of these phases will ensure the success of the project. • It is also important to create statement of work (SOW) for the business case to identify the purpose, scope, project deliverables, goals and objectives and cost and schedule estimates. These ensure we do not run out of the planning we initially made thus preventing mishaps such as cost overrun or delays..
  • 17. Conclusion & Recommendations • Adding to that the risk management team should calculate the possible risks with the help of risk impact / probability chart. This gives a quick and clear view of the priority we need to give each, and help us to decide what resource to allocate in managing the particular risk
  • 18. Conclusion & Recommendations • Therefore as conclusion project management skills should be incorporated with the theories and models I have presented in my study above should be followed to attain project success, as these are the models proven by researches and trials. I hope these recommendations will help to elevate the project success in future business cases