SlideShare una empresa de Scribd logo
1 de 2
Descargar para leer sin conexión
A NEW WAY OF
                                                                                       MANAGING THE
                                                                                       CONSTRUCTION OF
                                                                                       A SUBSTATION
                                                                                       ISO 9001 : 2008




                                                      THE CHALLENGE
                                                      Northern Ireland Electricity (NIE) had a project of adding a new
                                                      substation to an existing 275 kV double-circuit power line. This project
                                                      included the erection of 2 new terminal towers to serve the new
                                                      substation.

                                                      Since the terminal towers would be erected in-line with the existing
                                                      275 kV power line, the main challenge was to find a cost effective
                                                      way to by-pass the whole 300 metre long construction site with a
                                                      temporary line without affecting the power flow.

                                                      NIE was facing several challenges:
                                                      1. NIE needed to ensure availability of one circuit at all times
                                                         on the existing power line during the construction of the new
                                                         terminal towers.
                                                      2. Down time of the complete power line was not acceptable
                                                         at any time otherwise network security could be at risk.

                                                      3. All materials had to be quickly available,
                                                         easy to install and reliable.
Schematic suggested deviation plan using SBB Towers
THE SOLUTION
The SBB fast mounting aluminum
modular tower, better known as
the Energy Restoration System
(ERS), was bought by NIE with
mostly emergencies in mind. But
David Holmes, NIE Transmission
Overhead Line Project Engineer,
saw other possible applications for
the temporary towers in planned
transmission network projects.        OVERALL BENEFITS
In this particular substation con-
nection project, the use of the SBB    » The terminal tower construction                   » Significant financial and time savings
towers was considered essential          started as scheduled with no delays                 were made using ERS towers instead
to ensure that one power circuit         for civil engineering contractors.                  of conventional towers.
remained available throughout          » One circuit was always available                  » Network security maintained for
the construction of the terminal         throughout the project with no                      the course of the project with no
towers.                                  down time.                                          complaint from network operator or
                                                                                             utility clients for power interruption.

Two SBB ERS towers were erected          The payback on the investment was very short:
                                         a few projects have been completed and NIE is now generating savings each time
to divert one 275kV circuit around       they use SBB’s ERS towers.
the site allowing terminal tower
construction to be carried out
safely. Once the construction was
                                      ADDITIONAL SBB TOWER USAGES
completed, the conductors were
simply reinstalled on to the new       » Temporary line to replace damaged                 » Repositioning a transmission line away
                                         towers following earthquakes or                     from new developments, e.g. a future
terminal towers and the ERS              mudslides.                                          commercial center.
towers were dismantled, stored in
the SBB containers and returned        » Maintenance purposes e.g. deviation               » Expansion of the network due to
                                         to repair tower concrete bases.                     the integration of renewable energy
to the storage depot.                                                                        sources.


Overall the use of the ERS towers     TESTIMONIAL
was a much faster and more
economical solution than having
                                                                  David A. Holmes, Transmission Overhead Lines Project Engineer
to construct and subsequently                                     for NIE on SBB Towers:
dismantle standard lattice steel                                  “The structures use a simple but very effective modular system that
                                                                  allows various different configurations to be designed and erected
towers.                                                           quickly and effectively. Standard SBB designs have been adapted
                                                                  very easily to suit specific voltage levels and local site conditions.
                                                                  In this area the technical backup provided by the engineering team in
                                                                  SBB has been exceptional with new designs being engineered in very
                                                                  short time periods. (…) The instructors who provided this training
                                                                  were very know ledgeable on all aspects of the structures and
                                         had an excellent practical understanding of the erection techniques required.
                                         The SBB emergency restoration structures have proved to be a very valuable company
                                         asset over the last few years in terms of planning work and in ongoing network security. (…)”


                                      3005, des Bâtisseurs
                                      Terrebonne, Québec, Canada J6Y 0A2
                                                                                                                                       SBB01-10/2010




                                      T: +1.450.968.0800 F: +1.450.968.0050
                                      www.sbb.ca | info@sbb.ca                                                        MADE IN CANADA

Más contenido relacionado

Similar a SBB Study Case Northern Ireland Electricity Limited (NIE) - The Challenge

Offshore Substation Design Brochure
Offshore Substation Design BrochureOffshore Substation Design Brochure
Offshore Substation Design Brochurepbnrambollcom
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
2012 Network design
2012 Network design2012 Network design
2012 Network designJohn Snoxell
 
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’sAnalysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’sIRJET Journal
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016Sher Chuhan
 
"Structural probabilistic assessment of offshore wind turbine operation fatig...
"Structural probabilistic assessment of offshore wind turbine operation fatig..."Structural probabilistic assessment of offshore wind turbine operation fatig...
"Structural probabilistic assessment of offshore wind turbine operation fatig...TRUSS ITN
 
title defense.pptx
title defense.pptxtitle defense.pptx
title defense.pptxMayThansin3
 
title defense.pptx
title defense.pptxtitle defense.pptx
title defense.pptxMayThansin3
 
Church College Of New Zealand July 2009 Engineering Report
Church College Of New Zealand July 2009  Engineering ReportChurch College Of New Zealand July 2009  Engineering Report
Church College Of New Zealand July 2009 Engineering Reportkiakaha
 
Presentation PPT.pdf
Presentation PPT.pdfPresentation PPT.pdf
Presentation PPT.pdfMRVOLDEMORT1
 
Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...
Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...
Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...Thorne & Derrick International
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...McKenney's Inc
 

Similar a SBB Study Case Northern Ireland Electricity Limited (NIE) - The Challenge (20)

Offshore Substation Design Brochure
Offshore Substation Design BrochureOffshore Substation Design Brochure
Offshore Substation Design Brochure
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
17.cabling system
17.cabling system17.cabling system
17.cabling system
 
2012 Network design
2012 Network design2012 Network design
2012 Network design
 
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’sAnalysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
Analysis For Retrofitting Of An Existing Failed RC Column Using FEM Software’s
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
"Structural probabilistic assessment of offshore wind turbine operation fatig...
"Structural probabilistic assessment of offshore wind turbine operation fatig..."Structural probabilistic assessment of offshore wind turbine operation fatig...
"Structural probabilistic assessment of offshore wind turbine operation fatig...
 
StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)
 
StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)
 
StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)StanCV1[1][1].dcc (1)
StanCV1[1][1].dcc (1)
 
title defense.pptx
title defense.pptxtitle defense.pptx
title defense.pptx
 
title defense.pptx
title defense.pptxtitle defense.pptx
title defense.pptx
 
Church College Of New Zealand July 2009 Engineering Report
Church College Of New Zealand July 2009  Engineering ReportChurch College Of New Zealand July 2009  Engineering Report
Church College Of New Zealand July 2009 Engineering Report
 
Presentation PPT.pdf
Presentation PPT.pdfPresentation PPT.pdf
Presentation PPT.pdf
 
Khaled(beca)
Khaled(beca)Khaled(beca)
Khaled(beca)
 
Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...
Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...
Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132...
 
CV - Chris Gibbins
CV - Chris GibbinsCV - Chris Gibbins
CV - Chris Gibbins
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
 
MMC Revision Notes
MMC Revision NotesMMC Revision Notes
MMC Revision Notes
 

SBB Study Case Northern Ireland Electricity Limited (NIE) - The Challenge

  • 1. A NEW WAY OF MANAGING THE CONSTRUCTION OF A SUBSTATION ISO 9001 : 2008 THE CHALLENGE Northern Ireland Electricity (NIE) had a project of adding a new substation to an existing 275 kV double-circuit power line. This project included the erection of 2 new terminal towers to serve the new substation. Since the terminal towers would be erected in-line with the existing 275 kV power line, the main challenge was to find a cost effective way to by-pass the whole 300 metre long construction site with a temporary line without affecting the power flow. NIE was facing several challenges: 1. NIE needed to ensure availability of one circuit at all times on the existing power line during the construction of the new terminal towers. 2. Down time of the complete power line was not acceptable at any time otherwise network security could be at risk. 3. All materials had to be quickly available, easy to install and reliable. Schematic suggested deviation plan using SBB Towers
  • 2. THE SOLUTION The SBB fast mounting aluminum modular tower, better known as the Energy Restoration System (ERS), was bought by NIE with mostly emergencies in mind. But David Holmes, NIE Transmission Overhead Line Project Engineer, saw other possible applications for the temporary towers in planned transmission network projects. OVERALL BENEFITS In this particular substation con- nection project, the use of the SBB » The terminal tower construction » Significant financial and time savings towers was considered essential started as scheduled with no delays were made using ERS towers instead to ensure that one power circuit for civil engineering contractors. of conventional towers. remained available throughout » One circuit was always available » Network security maintained for the construction of the terminal throughout the project with no the course of the project with no towers. down time. complaint from network operator or utility clients for power interruption. Two SBB ERS towers were erected The payback on the investment was very short: a few projects have been completed and NIE is now generating savings each time to divert one 275kV circuit around they use SBB’s ERS towers. the site allowing terminal tower construction to be carried out safely. Once the construction was ADDITIONAL SBB TOWER USAGES completed, the conductors were simply reinstalled on to the new » Temporary line to replace damaged » Repositioning a transmission line away towers following earthquakes or from new developments, e.g. a future terminal towers and the ERS mudslides. commercial center. towers were dismantled, stored in the SBB containers and returned » Maintenance purposes e.g. deviation » Expansion of the network due to to repair tower concrete bases. the integration of renewable energy to the storage depot. sources. Overall the use of the ERS towers TESTIMONIAL was a much faster and more economical solution than having David A. Holmes, Transmission Overhead Lines Project Engineer to construct and subsequently for NIE on SBB Towers: dismantle standard lattice steel “The structures use a simple but very effective modular system that allows various different configurations to be designed and erected towers. quickly and effectively. Standard SBB designs have been adapted very easily to suit specific voltage levels and local site conditions. In this area the technical backup provided by the engineering team in SBB has been exceptional with new designs being engineered in very short time periods. (…) The instructors who provided this training were very know ledgeable on all aspects of the structures and had an excellent practical understanding of the erection techniques required. The SBB emergency restoration structures have proved to be a very valuable company asset over the last few years in terms of planning work and in ongoing network security. (…)” 3005, des Bâtisseurs Terrebonne, Québec, Canada J6Y 0A2 SBB01-10/2010 T: +1.450.968.0800 F: +1.450.968.0050 www.sbb.ca | info@sbb.ca MADE IN CANADA