SlideShare a Scribd company logo
1 of 25
Download to read offline
L Di t R i B i i H d R kLarge Diameter Raise Boring in Hard Rock
An overview, its application and considerations
Author & Presenter: Patrick Hudd
Co‐author: Dennis Martin
Date: Tuesday 26th October, 2010
Location: Room  C205 at 9am
MeMO 2010 – Large Diameter Raiseboring in Hard Rock: An overview, its application and considerations
C t tContents
I t d ti• Introduction
• Large diameter raiseboring, now and then
• Considerations for incorporating large 
diameter raiseboring
• Project execution
• Summary and questions• Summary and questions
Raise Boring is
using machinery to effect a raise by drilling ausing machinery to effect a raise by drilling a 
hole in either a one step or two step process.
d h l h d b h d bReamed holes had been achieved by engineers 
such as Bade in 1949 but it was the development 
of the Cannon‐Robbins raise drills in the late 
1950s that gave us the forerunners of today’s1950s that gave us the forerunners of today s 
raise drills. 
HISTORY OF RAISE BORING
Th R i b i PThe Raiseboring Process
Pilot Ream Pilot Blindrill Ream ReamPilot 
down
Ream 
Up
Pilot 
Up
Blindrill 
Up
Ream 
Up 
Ream 
Down
The Large Diameter RaiseboringThe Large Diameter Raiseboring
Process
Wh R i B i ?Why Raise Boring?
For most applications of non‐
horizontal development in rock raise 
boring provides time and cost saving 
benefits:
– Faster advance rates
– Less disturbance to the rock 
structure
– Reduced labour costs
– Greater safety for operating 
lpersonnel
L Di t N d ThLarge Diameter, Now and Then
• Traditionally in hard rock (>150• Traditionally in hard rock (>150 
MPa) mining large diameter raise 
boring was thought of as 3 to 4 m in 
diameter and over 300 m in lengthdiameter and over 300 m in length
• Mine and ventilation engineers 
were challenged to design systems 
either incorporating such holes, or 
slashing and modifying to suit
• Now single pass bored shafts of 6 m 
in diameter and 1000 m in length 
are being excavated
0 C l d Si l d Sh f10 Largest Completed Single Pass Bored Shafts
Length Ground
Year Location m Dia. Machine Type MPa
1986 Deelkraal – RSA 1036 6.1 HG330 Norite 220
2010 Cadia Shaft – AUS 930 6.0 HG330 Volcanics 210
1988 Frank Shaft – RSA 1033 5.8 HG330 Norite 220
1997 Phalaborwa ‐ RSA 923 5.7 HG330 ? ?
1998 Amandulbult ‐ RSA 877 5.52 HG330 Norite 2201998 Amandulbult RSA 877 5.52 HG330 Norite 220
1999 Impala 11 – RSA 784 5.8 HG330 Norite 220
1998 Impala 1 – RSA 965 5.1 HG330 Norite 220
2008 Gwalia – AUS 800 5.52 HG330 Basalt 200
1993 Turffontein – RSA 1102 4.5 HG330 Norite 220
2007 Red Lake ‐ CAD 694 5.52 123R Basalt 180
Th t d T R i tThrust and Torque Requirements
• Consider a 1,000m long raise of 6 metre diameter  through rock of 150 MPa UCS
• Thrust – required to overcome the dead weight of the drill string, plus the reamer and 
cutter loading required to fracture the rock
• Weight of drill string over 1,000m @ 500kg per m 500tWeight of drill string over 1,000m @ 500kg per m 500t
• Weight of reamer and derrick 45t
• Cutter loading with 36# cutters @ 10t each 360t (3,530kN)
• Thrust required 905t
• Torque – rotational force to overcome the torsion in the drill string and components to 
allow the cutters on the reamer to traverse the face and cut the rock 
• Historical data and the Tamrock torque formula:• Historical data and the Tamrock torque formula:
– M = C x f x T x (D/2) x √P
• Torque required 509kNm
Currently Available Large DiameterCurrently Available Large Diameter
Machines
Machines
Thrust
(Tonne)
Torque
(kNm)
Rod Diameter
mm Available
Wirth HG380 1180 710 353 1Wirth HG380 1180 710 353 1
Wirth HG330 900 610 333 4
Atlas Copco 123RH 810 540 333 1
Atl C 123DC 810 540 333 1Atlas Copco 123DC 810 540 333 1
Strata 950RH 950 1000 333 and 356 5
Strata 850RH 850 1000 333 and 356 1
Redbore 100AC 1440 1000 368 1
Example Standard OperatingExample Standard Operating
Capability
6 5
5.5
6
6.5
4.5
5
ameter(m)
Robbins 97R
Robbins 123R
3
3.5
4
Raisedi
Strata 950
2
2.5
3
0 200 400 600 800 10000 200 400 600 800 1000
Length of raise (m)
Considerations for IncorporatingConsiderations for Incorporating
Large Diameter Raiseboring
• Blind Sink• Blind Sink
– When there is no access at the bottom
– When ground conditions are unstable
– When ground water is an issue– When ground water is an issue
– When the length and diameter rule out pilot and slash and raise boring
• Pilot and Slash (Pilot with Alimak or Raise Drill)
When there is access at the bottom– When there is access at the bottom
– When ground conditions are unstable
– When ground water is not an issue
– When finished diameter is greater than raise boring capabilitiesg g p
• Raise Boring
– When there is access at the bottom
– When ground conditions are stableWhen ground conditions are stable
– When ground water is not an issue
Four key questions that make large diameter raiseboring an option:
Information and technicalInformation and technical
considerations
•Geotechnical Information
–Ground conditions dictate what you can 
and cannot do and planning for those 
ground conditions is fundamental for a 
successful project
Responsibility for the ground 
conditions before, during and after 
construction is with the Ownerconstruction is with the Owner.
G t h i l i k tGeotechnical risk assessment
Based upon McCracken & Stacey, Geotechnical risk assessment for large dimater raise‐bored shafts, 1989
A f d d dAccess – surface and underground
•Shift schedules, blast windowsShift schedules, blast windows
•Raise collars incl. location
Excavations required to enable theExcavations required to enable the
work
Excavations required to enable theExcavations required to enable the
work
Services and logisticsServices and logistics
•Electrical power
•Water
•Sumps
•Rods
•Waste handlingWaste handling
Safety, cost & schedule, riskSafety, cost & schedule, risk
•Safety
•Operator exposure to hazards is reduced, but not eliminatedp p ,
•Bottom horizon work
•Rod handling
•High voltage electrics high pressure hydraulics•High voltage electrics, high pressure hydraulics
•Cost & Schedule
•Early planning and scoping around four key questions
•Actual status and forecast of enabling works and machine availability
•Budget price and schedule, incl. why hole is required
•Risk and Mitigationg
•If risk is unacceptable, relocate, amend specification or method
•Probability of failure, end use of hole and service life
Project ExecutionProject Execution
•Procurement Strategy
•Client or contractor?
•Three main reasons to engage a contractor:
1 Can be done more expertly cheaply and quickly than with client1. Can be done more expertly , cheaply and quickly than with client 
resources
2. Does not warrant the capital expenditure on equipment and 
establishment of a team to carry out a one off job in aestablishment of a team to carry out a one‐off job in a 
specialized field
3. May allow development to be undertaken concurrently with 
existing operations for expansion or transitionexisting operations for expansion or transition
(after JAA James – Underground Mining Construction By Contract – Getting the Best For Principal and Contractor, 1985)
C t t S l tiContractor Selection
•Soundness of 
reputation
•Competence of key 
personnel
•Back‐up resources, 
technical and
administrative
•Financial resources
•Current activities
•Safety track records•Safety track records
•Dependence on sub‐
contractors
T i l C i l F tTypical Commercial Format
NSW Guideline for Raiseboring Operations:NSW Guideline for Raiseboring Operations:
“A negotiated contract that is accurately scoped and includes systems that
h id tifi d d i k k d t ti l h d ith i t tihave identified and risk ranked potential hazards with appropriate actions
to control them. A contract which is fully scoped and completed prior to
project commencement, and is auditable throughout the contract term. A
contract which minimises the likelihood of surprises which may adverselycontract which minimises the likelihood of surprises which may adversely
affect the safety performance of either party.”
O ti C id tiOperating Considerations
• Replacement equipment availability in case of catastrophic failure• Replacement equipment availability in case of catastrophic failure
– Damage or loss of drill string
• Mobilization setup and demobilization require detailed planning• Mobilization, setup and demobilization require detailed planning
– A clear definition of Client and Contractor responsibilities
• Ideally long, large diameter bored shafts are verticalIdeally long, large diameter bored shafts are vertical
– If a vertical shaft is critical then special tooling is need for drilling the pilot hole
• Removal of the cuttings to avoid interruptions during the reaming cycle is g p g g y
extremely important and tends to be where delays and operating issues 
arise
– Capital required to successfully bore a 1000 m long, 6 m shaft is >$12 million USD
– With a crew of six the delay cost is >$500 USD/h
Summary
Questions?Questions?

More Related Content

What's hot

Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020Pomcert
 
Geo-Tech Studies for Longwall
Geo-Tech Studies for LongwallGeo-Tech Studies for Longwall
Geo-Tech Studies for LongwallVR M
 
Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...
Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...
Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...pvisoftware
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...MD.Suresh Kumar
 
Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3pakmek
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingTim Leung
 
Horizontal drilling
Horizontal drillingHorizontal drilling
Horizontal drillingMubarik Rao
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersVR M
 
Report steffones
Report steffonesReport steffones
Report steffonesSteffones K
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case studyMD.Suresh Kumar
 
1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issues1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issuesMD.Suresh Kumar
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operationsElsayed Amer
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 
introduction to directional drilling
introduction to directional drillingintroduction to directional drilling
introduction to directional drillingyoucef benferdi
 

What's hot (20)

Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
 
Strike dip rise longwall panels
Strike dip rise longwall panelsStrike dip rise longwall panels
Strike dip rise longwall panels
 
Chap9 anrep1314
Chap9 anrep1314Chap9 anrep1314
Chap9 anrep1314
 
Geo-Tech Studies for Longwall
Geo-Tech Studies for LongwallGeo-Tech Studies for Longwall
Geo-Tech Studies for Longwall
 
Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...
Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...
Torque and Drag: Concepts that Every Drilling and Completion Engineer Should ...
 
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
Longwall Mining- An experience of Longwall mining in Padmavathikhani Chinese ...
 
Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional Drilling
 
Surface miner
Surface minerSurface miner
Surface miner
 
rig types and its components
rig types and its componentsrig types and its components
rig types and its components
 
Horizontal drilling
Horizontal drillingHorizontal drilling
Horizontal drilling
 
DISCOVERY DRILLING EQUIPMENT
DISCOVERY DRILLING EQUIPMENTDISCOVERY DRILLING EQUIPMENT
DISCOVERY DRILLING EQUIPMENT
 
Mine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of PapersMine Tech Seminar '10 - Gist of Papers
Mine Tech Seminar '10 - Gist of Papers
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Report steffones
Report steffonesReport steffones
Report steffones
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case study
 
1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issues1.5MT Longwall faces in SCCL-Few planning issues
1.5MT Longwall faces in SCCL-Few planning issues
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 
introduction to directional drilling
introduction to directional drillingintroduction to directional drilling
introduction to directional drilling
 

Similar to Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1

Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...muralikrishna317515
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdfRaviNobleseas
 
Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016Mohamed _el_shora
 
Re - Entry Drilling Project
Re - Entry Drilling ProjectRe - Entry Drilling Project
Re - Entry Drilling ProjectAndika Mahardika
 
Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentationZiad el-Balbisi
 
Ripper production
Ripper productionRipper production
Ripper productionVIJAY KUMAR
 
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nick Vukovich
 
Construction techniques
Construction techniquesConstruction techniques
Construction techniquessunilighare
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationKyle Beaudry, P.Eng
 
d_walsh_directional.pdf
d_walsh_directional.pdfd_walsh_directional.pdf
d_walsh_directional.pdfpeter877754
 
03 drilling recent development ui 17 sep 2007
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007yudi05
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
GWDC business-brochure-green PDF
GWDC business-brochure-green PDFGWDC business-brochure-green PDF
GWDC business-brochure-green PDFMiguel Roberg
 

Similar to Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1 (20)

Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
 
Tunneling
TunnelingTunneling
Tunneling
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf
 
Dam focus
Dam focusDam focus
Dam focus
 
Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016Operation and Well Setting GTI SEG-SUSC 08-10-2016
Operation and Well Setting GTI SEG-SUSC 08-10-2016
 
Re - Entry Drilling Project
Re - Entry Drilling ProjectRe - Entry Drilling Project
Re - Entry Drilling Project
 
Riser Design Overview
Riser Design  OverviewRiser Design  Overview
Riser Design Overview
 
Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentation
 
Ripper production
Ripper productionRipper production
Ripper production
 
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!Nippon Dragon Resources Inc. Hard rock revolution has arrived!
Nippon Dragon Resources Inc. Hard rock revolution has arrived!
 
Construction techniques
Construction techniquesConstruction techniques
Construction techniques
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
 
Presentation on Highwall Mining
Presentation on Highwall MiningPresentation on Highwall Mining
Presentation on Highwall Mining
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall Presentation
 
d_walsh_directional.pdf
d_walsh_directional.pdfd_walsh_directional.pdf
d_walsh_directional.pdf
 
03 drilling recent development ui 17 sep 2007
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Deep Lake Water Cooling
Deep Lake Water CoolingDeep Lake Water Cooling
Deep Lake Water Cooling
 
Keynote_Jonny_S_Sevilla_2018.pdf
Keynote_Jonny_S_Sevilla_2018.pdfKeynote_Jonny_S_Sevilla_2018.pdf
Keynote_Jonny_S_Sevilla_2018.pdf
 
GWDC business-brochure-green PDF
GWDC business-brochure-green PDFGWDC business-brochure-green PDF
GWDC business-brochure-green PDF
 

Patrick Hudd Me Mo October 2010 Raise Boring Presentation Rev 1

  • 1. L Di t R i B i i H d R kLarge Diameter Raise Boring in Hard Rock An overview, its application and considerations Author & Presenter: Patrick Hudd Co‐author: Dennis Martin Date: Tuesday 26th October, 2010 Location: Room  C205 at 9am MeMO 2010 – Large Diameter Raiseboring in Hard Rock: An overview, its application and considerations
  • 2. C t tContents I t d ti• Introduction • Large diameter raiseboring, now and then • Considerations for incorporating large  diameter raiseboring • Project execution • Summary and questions• Summary and questions
  • 3. Raise Boring is using machinery to effect a raise by drilling ausing machinery to effect a raise by drilling a  hole in either a one step or two step process. d h l h d b h d bReamed holes had been achieved by engineers  such as Bade in 1949 but it was the development  of the Cannon‐Robbins raise drills in the late  1950s that gave us the forerunners of today’s1950s that gave us the forerunners of today s  raise drills.  HISTORY OF RAISE BORING
  • 4. Th R i b i PThe Raiseboring Process Pilot Ream Pilot Blindrill Ream ReamPilot  down Ream  Up Pilot  Up Blindrill  Up Ream  Up  Ream  Down
  • 5. The Large Diameter RaiseboringThe Large Diameter Raiseboring Process
  • 6. Wh R i B i ?Why Raise Boring? For most applications of non‐ horizontal development in rock raise  boring provides time and cost saving  benefits: – Faster advance rates – Less disturbance to the rock  structure – Reduced labour costs – Greater safety for operating  lpersonnel
  • 7. L Di t N d ThLarge Diameter, Now and Then • Traditionally in hard rock (>150• Traditionally in hard rock (>150  MPa) mining large diameter raise  boring was thought of as 3 to 4 m in  diameter and over 300 m in lengthdiameter and over 300 m in length • Mine and ventilation engineers  were challenged to design systems  either incorporating such holes, or  slashing and modifying to suit • Now single pass bored shafts of 6 m  in diameter and 1000 m in length  are being excavated
  • 8. 0 C l d Si l d Sh f10 Largest Completed Single Pass Bored Shafts Length Ground Year Location m Dia. Machine Type MPa 1986 Deelkraal – RSA 1036 6.1 HG330 Norite 220 2010 Cadia Shaft – AUS 930 6.0 HG330 Volcanics 210 1988 Frank Shaft – RSA 1033 5.8 HG330 Norite 220 1997 Phalaborwa ‐ RSA 923 5.7 HG330 ? ? 1998 Amandulbult ‐ RSA 877 5.52 HG330 Norite 2201998 Amandulbult RSA 877 5.52 HG330 Norite 220 1999 Impala 11 – RSA 784 5.8 HG330 Norite 220 1998 Impala 1 – RSA 965 5.1 HG330 Norite 220 2008 Gwalia – AUS 800 5.52 HG330 Basalt 200 1993 Turffontein – RSA 1102 4.5 HG330 Norite 220 2007 Red Lake ‐ CAD 694 5.52 123R Basalt 180
  • 9. Th t d T R i tThrust and Torque Requirements • Consider a 1,000m long raise of 6 metre diameter  through rock of 150 MPa UCS • Thrust – required to overcome the dead weight of the drill string, plus the reamer and  cutter loading required to fracture the rock • Weight of drill string over 1,000m @ 500kg per m 500tWeight of drill string over 1,000m @ 500kg per m 500t • Weight of reamer and derrick 45t • Cutter loading with 36# cutters @ 10t each 360t (3,530kN) • Thrust required 905t • Torque – rotational force to overcome the torsion in the drill string and components to  allow the cutters on the reamer to traverse the face and cut the rock  • Historical data and the Tamrock torque formula:• Historical data and the Tamrock torque formula: – M = C x f x T x (D/2) x √P • Torque required 509kNm
  • 10. Currently Available Large DiameterCurrently Available Large Diameter Machines Machines Thrust (Tonne) Torque (kNm) Rod Diameter mm Available Wirth HG380 1180 710 353 1Wirth HG380 1180 710 353 1 Wirth HG330 900 610 333 4 Atlas Copco 123RH 810 540 333 1 Atl C 123DC 810 540 333 1Atlas Copco 123DC 810 540 333 1 Strata 950RH 950 1000 333 and 356 5 Strata 850RH 850 1000 333 and 356 1 Redbore 100AC 1440 1000 368 1
  • 11. Example Standard OperatingExample Standard Operating Capability 6 5 5.5 6 6.5 4.5 5 ameter(m) Robbins 97R Robbins 123R 3 3.5 4 Raisedi Strata 950 2 2.5 3 0 200 400 600 800 10000 200 400 600 800 1000 Length of raise (m)
  • 12. Considerations for IncorporatingConsiderations for Incorporating Large Diameter Raiseboring • Blind Sink• Blind Sink – When there is no access at the bottom – When ground conditions are unstable – When ground water is an issue– When ground water is an issue – When the length and diameter rule out pilot and slash and raise boring • Pilot and Slash (Pilot with Alimak or Raise Drill) When there is access at the bottom– When there is access at the bottom – When ground conditions are unstable – When ground water is not an issue – When finished diameter is greater than raise boring capabilitiesg g p • Raise Boring – When there is access at the bottom – When ground conditions are stableWhen ground conditions are stable – When ground water is not an issue
  • 13. Four key questions that make large diameter raiseboring an option:
  • 14. Information and technicalInformation and technical considerations •Geotechnical Information –Ground conditions dictate what you can  and cannot do and planning for those  ground conditions is fundamental for a  successful project Responsibility for the ground  conditions before, during and after  construction is with the Ownerconstruction is with the Owner.
  • 15. G t h i l i k tGeotechnical risk assessment Based upon McCracken & Stacey, Geotechnical risk assessment for large dimater raise‐bored shafts, 1989
  • 16. A f d d dAccess – surface and underground •Shift schedules, blast windowsShift schedules, blast windows •Raise collars incl. location
  • 17. Excavations required to enable theExcavations required to enable the work
  • 18. Excavations required to enable theExcavations required to enable the work
  • 19. Services and logisticsServices and logistics •Electrical power •Water •Sumps •Rods •Waste handlingWaste handling
  • 20. Safety, cost & schedule, riskSafety, cost & schedule, risk •Safety •Operator exposure to hazards is reduced, but not eliminatedp p , •Bottom horizon work •Rod handling •High voltage electrics high pressure hydraulics•High voltage electrics, high pressure hydraulics •Cost & Schedule •Early planning and scoping around four key questions •Actual status and forecast of enabling works and machine availability •Budget price and schedule, incl. why hole is required •Risk and Mitigationg •If risk is unacceptable, relocate, amend specification or method •Probability of failure, end use of hole and service life
  • 21. Project ExecutionProject Execution •Procurement Strategy •Client or contractor? •Three main reasons to engage a contractor: 1 Can be done more expertly cheaply and quickly than with client1. Can be done more expertly , cheaply and quickly than with client  resources 2. Does not warrant the capital expenditure on equipment and  establishment of a team to carry out a one off job in aestablishment of a team to carry out a one‐off job in a  specialized field 3. May allow development to be undertaken concurrently with  existing operations for expansion or transitionexisting operations for expansion or transition (after JAA James – Underground Mining Construction By Contract – Getting the Best For Principal and Contractor, 1985)
  • 22. C t t S l tiContractor Selection •Soundness of  reputation •Competence of key  personnel •Back‐up resources,  technical and administrative •Financial resources •Current activities •Safety track records•Safety track records •Dependence on sub‐ contractors
  • 23. T i l C i l F tTypical Commercial Format NSW Guideline for Raiseboring Operations:NSW Guideline for Raiseboring Operations: “A negotiated contract that is accurately scoped and includes systems that h id tifi d d i k k d t ti l h d ith i t tihave identified and risk ranked potential hazards with appropriate actions to control them. A contract which is fully scoped and completed prior to project commencement, and is auditable throughout the contract term. A contract which minimises the likelihood of surprises which may adverselycontract which minimises the likelihood of surprises which may adversely affect the safety performance of either party.”
  • 24. O ti C id tiOperating Considerations • Replacement equipment availability in case of catastrophic failure• Replacement equipment availability in case of catastrophic failure – Damage or loss of drill string • Mobilization setup and demobilization require detailed planning• Mobilization, setup and demobilization require detailed planning – A clear definition of Client and Contractor responsibilities • Ideally long, large diameter bored shafts are verticalIdeally long, large diameter bored shafts are vertical – If a vertical shaft is critical then special tooling is need for drilling the pilot hole • Removal of the cuttings to avoid interruptions during the reaming cycle is g p g g y extremely important and tends to be where delays and operating issues  arise – Capital required to successfully bore a 1000 m long, 6 m shaft is >$12 million USD – With a crew of six the delay cost is >$500 USD/h