1. Free PMP® Exam Sample
Question
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and
did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation,
expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented
in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal
responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material.
Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties
are implied or expressed by OSP International LLC.
2. The following PMP® Exam Sample Question is
taken from the Free PMP Exam Simulator:
2
3. PMP® Exam Sample Question
You
are
managing
a
software
development project. You want to create
the basis that will be used later on for
estimating,
scheduling,
executing,
monitoring, and controlling the project
work. Which process performs this
activity?
a) Create WBS
b) Define Scope
c) Define Activities
d) Create Project Management Plan
3
4. Hint:
Estimating is performed when the activities are defined
and the schedule is prepared.
All our questions are updated to the latest PMBOK® Guide
standard. Stop by at
http://free.pm-exam-simulator.com
and try the PMP® Exam Simulator free for 3 days. We also
offer 110 free questions at
http://www.free-pm-examquestions.com. We are a PMI® Registered Education Provider.
4
5. Answer and Explanation:
The correct answer is C.
Explanation:
Activities
form
a
basis
for
estimating, scheduling, executing,
and monitoring and controlling the
project work. This is performed in
the Define Activities process.
5