Study of using solar energy system to supply a data center
ASES WREF 2012 Critical Timeframe of importance for PV from a utility perspective
1. CRITICAL TIMEFRAMES OF IMPORTANCE FOR PV FROM A UTILITY PERSPECTIVE
Obadiah Bartholomy
Yong Cai Pramod Krishnani
Belectric Inc.
Brad Dommer
8076 Central Avenue
Sacramento Municipal Utility District
Newark CA 94560
6201 S St
Sacramento, CA 95817 Email: krishnani.pramod@gmail.com
Email: Obadiah.Bartholomy@smud.org pramod.krishnani@belectric-usa.com
Yong.Cai@smud.org
Brad.Dommer@smud.org
ABSTRACT loads occur during approximately 15% of the 4,200 hours
that PV produces energy during year in Sacramento,
As solar penetrations increase, several resource attributes primarily in the springtime with a second but lower
and timeframes are becoming of increasing importance to concentration during the fall. Within an hour, a few dozen
utility and balancing authority operators. In particular, days a year appear to have high variability, potentially
output and variability of PV systems during summer peak creating issues for distribution system operators with
demand periods, during daytime minimum load changes exceeding 50% of rated capacity of a multi-MW
conditions in the spring and fall, and finally at very high system in a 1-minute period. Finally, over the longer term,
penetrations, during periods of significant load ramps for periods of significant ramps of PV in the morning and
the utility. Using historical solar resource data and load evening are likely to present challenges for existing grid
data, PV output is simulated for different configurations balancing resources during non-summer months.
and capacity levels to evaluate its potential to impact grid
operations during these types of timeframes. In this 1. INTRODUCTION
study, historical SMUD hourly load data is correlated to
validated modeled PV output to determine appropriate on- Anecdotal assessment of PV output and problems can
peak capacity values by orientation, minimum load – tend to receive much of the focus and may leave long-
maximum PV output correlations and frequency, and lasting impressions within a utility. Single events that
diurnal patterns of change on an hourly basis. cause problems for a utility may reinforce perceptions of
the resource as unreliable and problematic. For most
The assessment uses 9 years of SolarAnywhere(c) 10 km utilities, high penetrations of solar are relatively new and
grid hourly data correlated to SMUD system load data. up until recently, high resolution historical datasets were
More recent sub-hourly assessments are done for these not readily available to begin assessing the frequency that
values using recently installed ground-based solar problematic conditions may occur. This paper will begin
monitoring to evaluate sub-hourly variability that may to use these relatively recently available datasets to
significantly impact grid operations during low-load time answer questions related to timeframes that are important
periods of interest. to utility operators during which PV performance is of
heightened importance.
The results show that for SMUD’s service territory, peak
contribution from solar PV can be consistently expected The timeframe of primary importance to utility system
to contribute between 35% and 60% of its peak rating operators generally is during the hot summer months for
depending on orientation during the typical peak hour summer peaking utilities, and in particular, for SMUD,
ending 6PM. Periods of high PV output and low utility during hot afternoons between 2PM and 8PM. PV
1
3. between 5 and 6 PM.
Typically, SMUD meets the majority of its peak demand
needs with internal natural gas and hydro generation, and
imports power from the Northwest and CAISO markets to
supplement our internal generation. However, as PV
penetrations increase, the utility will look to it as a
resource to be counted on during times of peak demand.
Because backup resources are most expensive during peak
demand periods, it will be of significant financial
importance to understand the solar PV resource during
these timeframes. Fig. 3: Comparison of Modeled Output Profiles for PV
systems on SMUD’s Peak Setting Day, 2006
By looking at historical loads and modeled PV output
coinciding with those peak demand periods, a clear 4. MINIMUM LOAD PERIODS WITH COINCIDENT
picture of the relative reliability of the solar resource MAXIMUM PV OUTPUT
during peak demand periods can be attained. For this
analysis, we examined days with peak demand above Beyond peak periods, utility operators and planners are
2,800 MW, which is approximately 500 MW below the most concerned with the operation of both distribution
all time peak. Over the 9 year period, there were only 142 systems and the overall transmission system during low
hours which exceeded 2,800 MW, or roughly 0.18% of demand periods that coincide with high PV output
the hours. Of these hours, the solar resource followed a periods. For SMUD, generally these periods occur during
consistent pattern during the peak hours, contributing spring and fall months, where there is limited need for
between 35% and 40% of rated output for a South facing cooling and/or electric heating, resulting in daytime loads
system during the Hour Ending 6 PM for all of the 37 that may be between 30 and 40% of the peak demand
peak load days examined. This peak load and modeled period. Similarly, at the distribution level, minimum load
generation, along with the curves for SMUD’s all time periods generally occur during these same months, though
peak day set in 2006 are shown in Figure 2. can vary a bit more due to the different types of customers
that may be connected to a given distribution feeder.
Compounding the challenges associated with these time
periods at the transmission level are high variability days
and the availability of the hydro system to serve as a
regulating and balancing resource. It is not uncommon
under certain springtime runoff conditions for the hydro
system to be running at full output to avoid spill
situations. During these times, the system is not able to
provide the regulation services that it is able to provide
Fig. 2: South facing PV Output during top 0.18% of Load during other times of the year. It is not able to ramp up or
Hours ramp down as it is running at full output. During fall
periods, the hydro system may also be constrained in its
One way to increase the amount of PV capacity available ability to provide regulation services, in particular in its
on peak is by orienting it towards the West or ability to reduce output in response to increased PV
implementing tracking PV systems. This can increase on- output. This constraint can occur when there is inadequate
peak capacity available from a given system up to 60-65% water in the reservoirs to support generation that could be
as shown in Figure 3, as compared to the 35-40% ramped downwards. While historically these conditions
available from a South facing system. have not been problematic for SMUD operators, as the
utility adds significant amounts of solar these conditions
are likely to increase in significance.
As PV penetrations increase, it will become increasingly
likely that coincident high PV, hydro, and wind
generation could create conditions conducive to
curtailment of resources during minimum load conditions.
Understanding when these conditions may occur, at what
3
5. perceived by the non-PV resources on SMUD’s system.
The result would be two-fold. First, SMUD could be
forced to either curtail PV generation or sell generation
into what would likely be a low-priced electricity market,
Minimum load as evidenced by what is occurring in Germany currently
as a result of high PV penetrations3. Second, as SMUD
ramped up generation to meet load in the morning,
peaking or simple-cycle load following generation would
be required to be turned on to cope with the short duration
of need. This same type of generation would be looked to
again as the sun set to replace PV in the resource mix and
meet the evening load. Such operation would represent as
significant departure from current utility operations, as it
would rely much more heavily on simple cycle generation
and would incur significantly increased O&M costs
Minimum load
associated with these types of generation, given current
operations rarely require more than one start in a day, and
generally involve operation for 6 to 8 hours rather than a 2
to 3 hour operating mode as indicated in Figure 6.
The intent of this significantly simplified assessment is to
point out the challenges in operations that could occur as
a result of significant penetrations of PV and to begin to
identify mitigation approaches for dealing with these
challenges. It is likely that interaction with the broader
Minimum load
Northwest and California electricity markets may mitigate
some of the concerns with regard to resources, and further
that other resources on SMUD’s system, in particular our
Upper American River System, would be used for
meeting some of the ramping demands, alleviating much
of the concern regarding double-starts of thermal units.
However, as PV penetrations increase statewide,
availability of market units and or hydro assets for early
morning ramps may become increasingly unlikely as
Minimum load
these more flexible resources are deployed to deal with
intermittency issues and firming of solar and wind.
6. CONCLUSIONS
Utility operators have historically been distrustful of the
Fig. 5: Ramp timing implications for solar and load for ability of PV resources to meet their needs from a
March, June, September and December, modeling 1,000 reliability perspective. Concerns about consistency on
MW PV and average loads peak, low-load variability, and implications for
complementary grid resources generally have hamstrung
For this assessment, as described in Figure 6, it was widespread acceptance of PV as a valued grid asset.
assumed that the minimum load threshold in each night However, using tools that have only been recently
represented the minimum turndown for utility resources. developed, utilities today are much more able to model
It was also assumed that SMUD expanded its current output of significant penetrations over longer historical
installed PV capacity from an expected 140 MW at the periods to better understand how these generating units
end of 2012 to 1,000 MW, which is currently beyond perform during time periods of interest.
anything in the 20 year planning horizon, but is certainly
possible if PV prices continued to drop and carbon In this paper, three time periods of interest were explored
constraints drove significant additional renewables that could pose challenges to the utility depending on the
beyond 2020. In this scenario, a new minimum load performance of PV generating units. The first time period,
would be achieved during the daytime, at least as corresponding to times of peak demand, was found
5
6. historically to coincide with highly predictable solar ensure that the utility is best prepared for significant
resources. In fact the primary variables related to increases in solar generation in our mix.
predicting solar output on a peak day relate more to the
orientation of the system than the availability of the solar (1) Porter, K., Rogers, J., Wiser, R. “Update on Wind
resource. Based on examination of 37 days representing Curtailment in Europe and North America” June 16, 2011
the top 0.18% of peak demand hours, the modeled PV http://www.efchina.org/csepupfiles/report/201163041046
generation was found to perform within a very narrow 377.1820833464392.pdf/Update%20on%20Wind%20Cur
band between 35% and 40% capacity factor for a South
Facing system during the peak hour. As a result, it was
determined that PV generation could be counted on for a
consistent amount of output during these time periods, (2) Baldrick, Ross “Wind and Energy Markets: A Case
which will assist in planning for SMUD’s future Load Study of Texas” 2011, US Association for Energy
Serving Capability with large penetrations of solar on the Economics Dialogue
grid. http://dialogue.usaee.org/index.php?option=com_content
&view=article&id=109&Itemid=170
The second timeframe of significance, the coincidence of Accessed 3/2/2012 3:03 PM PST
low utility load and high PV output was also examined
from a macro and micro level. At a macro level, (3) Shahan, Zachary “Solar PV Reducing Price of
uneconomic conditions could occur leading to curtailment Electricity in Germany” February 9, 2012
or sale of generation into markets at rates below the long- CleanTechnica.com
term expected value of that generation. The frequency of http://cleantechnica.com/2012/02/09/solar-pv-reducing-
these types of conditions could represent as much as 7% price-of-electricity-in-germany/ Accessed 3/2/2012 5:37
of the hours of the year, where utility loads were between PM PST
30 and 40% of peak and PV output was greater than 50%
of rated capacity. In addition, at the distribution level,
extreme variability, including ramps of up to 50% of
capacity in a minute is likely to create issues on a few
dozen days of the year. These conditions could potentially
lead to local curtailment, changes in distribution system
design, or the inclusion of new distributed storage or other
grid assets to compensate for these extreme conditions.
Finally, over the longer term, scenarios may develop
similar to those in Germany, where daytime loads net of
PV are as low or lower than nighttime loads. With
significant PV penetrations throughout the state, and the
non-coincidence between load and solar ramps, existing
generation will be less useful in filling in short term needs
for morning and evening generation, leading to a
potentially significantly price differentiated market.
Simple cycle generation, storage, and demand response
will likely be better suited for meeting ramps than
combined cycle generation given the short lengths and
significant ramp magnitudes that may occur.
Understanding these conditions can help guide the types
of grid resources that utilities plan for over the next
decade.
This exercise was an initial attempt to begin to answer
some of the questions around the impacts of PV on
existing utility operations. Further work is expected to
refine these assessments, and develop more realistic long-
term scenarios against which to evaluate complementary
grid resources. However, the exercise has shown the
benefits of beginning to think about these timeframes to
6