SlideShare una empresa de Scribd logo
1 de 29
Descargar para leer sin conexión
Achieving the Unachievable
  A Case Study on Aligning a
  Project with Stakeholder
  Objectives

                       enterprise project analysis



Dr. Dan Patterson PMP | CEO & Founder Acumen
Introductions
!      Acumen: Project Management Software Company
!      Market leader in Analytics; 20 year legacy
!      Oracle Primavera & Microsoft partner



       S1 > S5™ Framework                                    Acumen Core Offerings
                                                  S5:             Acumen Fuse®
                                                  Validate
                                       S4:
                                       Optimize
                           S3: Risk-
                S2:
                           Adjust                            Risk Assessment Workshops
                Critique
    S1: Build


                                                                 Software Training
3




Case Study Introduction
!   Case study: GasCom
      !    LNG Pipeline & Facility Owner
      !    Early FEED stage
!   Project readying for sanction approval
      !    Investment board Dec 2013 P75 First Gas
      !    Gas Sales contract already established
!   GasCom adopted Acumen S1>S5
      !   Required contractors to achieve Fuse Schedule
          Index™ of 75%
!   Schedule developed in Primavera P6
!   All analytics conducted using Acumen Fuse

    February 10, 2012
4




GasCom S1 > S5 Approach
       •  Schedule Basis
S1     •  Reflects latest scope/contractor updates

       •  Critiqued Schedule
S2     •  Structurally sound, no contingency, sound logic

       •  Risk-Adjusted Schedule
S3     •  Estimate uncertainty, risk events

       •  Optimized Target Scenarios
S4     •  Reduced hot spots, higher confidence

       •  Team Validated Scenario
S5     •  Buy-in on mitigation plans



 February 10, 2012
5




S1 > S2 Schedule Review
!   Deterministic date of Dec 2013
!   Bidding contractors submitted their
    schedules to GasCom
!   GasCom needed to ensure sufficient
    realism in the schedules
!   Looked for means of compressing the
    schedule to show that an earlier First Gas
    was achievable

    February 10, 2012
6




Schedule Critique
!   Metric Analysis
      !    Quality of logic
      !    Float analysis
      !    Realism of durations
      !    Contractor maturity/realism
!   Based on the Fuse metric library



    February 10, 2012         [demo of standard Schedule analysis]
Fuse Schedule Index™     7




Analysis by Contractor




 February 10, 2012
8




Schedule Analysis Results
!   Bidder B failed Schedule Quality review
      !    Quality was less than 75% threshold
      !    Had to re-submit resolved schedule
      !    Used Fuse Schedule Assistant™ to fix
          shortcomings




    February 10, 2012
9




GasCom Schedule Cleanse




                     Lags converted
                       to activities
 February 10, 2012
Impact of Schedule                      10




Cleanse




                     5 month slippage




 February 10, 2012
11




Logic Integrity
!   Use of FS, FF, SF, SS links
!   SS links don’t account for durations
!   Lags hide schedule detail                   redundant

!   Leads cause reverse dates            A	

!   Circular logic between projects
                                                   B	

!   Out of sequence updates
!   Open start/finish: hidden open ends                      C	

!   Logic Density™
!   Logic Hotspot™
!   Redundancy Index™

    February 10, 2012
12




GasCom Logic Density™
!   Measure of complexity & soundness
!   Dual-band threshold: 2 to 6…
!   Determine Logic Hotspots™ in schedule
!   GasCom the level of detail was lacking towards the end
    of the project – mainly around interfaces & integration


                                                  More definition
                                                     needed




    February 10, 2012
13




Driving Logic Analysis
!   Test to ensure true path to First Gas
!   Analysis showed that there was an error in
    the schedule with a break in the path
    around Early Works
!   As a result of fixing this missing path, First
    Gas moved to the right by 2 months



    February 10, 2012
Removal of Logic                                                14




Redundancy




                                      8% redundancy




 Removal of redundancy led to a cleaner, more robust schedule
15




GasCom Float Analysis
!   S1 showed high float in early stage of project
!   S2 resolved schedule showed the opposite
!   Sanction acceleration opportunity went away
                                                    Originally percieved
                                                opportunity for making up            Resolved schedule not
    60                                            lost time through float        offering early stage schedule
                                                absorbtion in early stage of              acceleration
    40                                                    project

    20
      0
          Q1   Q2   Q3   Q4
         2011 2011            Q1   Q2
                   2011 2011
                             2012 2012 Q3    Q4               Q1
                                       2012 2012                       Q2       Q3
                                                             2013     2013             Q4
                                                                               2013             Q1        Q2
                                                                                      2013     2014               Q3
                                                                                                         2014            Q4
          S1 Average Float   S2 Average Float                                                                    2014
                                                                                                                        2014




    February 10, 2012
16




S1 > S2 Summary
!     Bidder schedules all passed the Schedule
      Quality Index™ Assessment
!     Missing logic was added
!     Lags converted to activities
!     Opportunity for schedule acceleration was
      understood (back-end loaded)

    S1: Dec 2013         5 months      S2: May 2014




     February 10, 2012
17




S2 > S3 Risk Analysis
!    Objective: to determine a risk-adjusted P75 First Gas
!    Risk workshop conducted
!    True risk exposure was actually at end of project
    70%
                                       Team Perception
    60%
                                       Actual Risk Hotspots
    50%

    40%

    30%

    20%

    10%

    0%
           Q1     Q2      Q3     Q4     Q1     Q2     Q3       Q4     Q1     Q2     Q3     Q4     Q1     Q2     Q3     Q4
          2011   2011    2011   2011   2012   2012   2012     2012   2013   2013   2013   2013   2014   2014   2014   2014




     February 10, 2012
18




Risk Insight
!   Hidden critical paths
!   Risk hot Spots™
!   Determined that Land acquisition activities were
    extremely critical yet weren’t identified in the
    schedule


                         Land acquisition




    February 10, 2012
19




S3 Summary
!     P75 risk-adjusted First Gas: Oct 2014
       !    10 months later than board expectations
!     Key risk hot spots in schedule identified
       !    Long Lead procurement items
!     Hidden path identified
       !   Driven by land acquisition delaying pipeline early
           works

    S1: Dec 2013         5   S2: May 2014   10        S3: Oct 2014



     February 10, 2012
S4: Getting back to                                         20




December 2013…
Risk Mitigation Plan            Schedule Acceleration

!   Response plan identified     !   LNG pipeline ready for
    for each key risk               hookup: Feb 2013
!   These plans became part     !   LNG Facility ready to
    of the overall schedule         receive gas: Nov 2013
                                !   Focus needed to be on
!   Enabled cost/benefit of
                                    accelerating the LNG
    the mitigation plan to be       facility
    assessed                    !   Could even afford to slow
!   $100MM investment to            down pipeline/field work
    save 1 month                    by a couple of months…


    February 10, 2012
LNG Facility Acceleration
Criteria Set
    Drive acceleration
!
                                           LNG Facility
    !   Reduce duration
                                         Script Objective
         !   More resources           “accelerate Facility by 6
                                             months”
    !   Changed calendars
                                       Step 1         Step 2          Step 3
                                    Accelerate     Delay Train    Introduce 6
         !   Contractor incentive   Jetty          2 activities   day working
                                    construction                  week/larger
                                                                  camp
    !   Delay Train 2
22




How Did This Work?
!   CPM simulation
!   Critical path focus
!   Incremental push
!   Prioritize
      !    Earliest/latest
      !    Longest durations
      !    Least resistance

    February 10, 2012
23




S4 Summary
!   LNG Facility was able to be accelerated
    sufficiently so as to not be the driving path in
    the schedule
!   Deterministic First Gas of August 2013
!   4 months earlier than Dec 2013 but not a
    valid comparison!
!   Sanction board wanted a P75 date not a
    deterministic
!   Risk-adjusted S4 date of February 2014
!   Only 2 months later than target…

    February 10, 2012
24




S5 Team Buy-in
!   A further 2 months acceleration was still required…
!   New mitigation plans developed based on the
    updated risk analysis after the schedule compression
!   Model showed that if the board would sanction a
    further $500MM spend to sponsor the more
    aggressive mitigation plan, then P75 could be brought
    back to Dec 2013.
!   Project team went to the board with both options and
    were duly granted the green-light for the more
    aggressive plan so as to achieve earlier production…


    February 10, 2012
25




GasCom First Gas Dates
 P75 Schedule Delay From Dec 2013 1st Gas (months)




                                                     10

                                                      9

                                                      8

                                                      7

                                                      6
                                                                                           10               Resolved, risk-
                                                      5
                                                                                                              adjusted,
                                                      4
                                                                                                             accelerated,
                                                                                                              mitigated
                                                      3                      5

                                                      2
                                                                                                            2                       0
                                                      1
                                                               0
                                                      0
                                                          S1 - base   S2 - resolved   S3 - risk-   S4 - accelerated    S5 - mitigated
                                                                                      adjusted
                                                                                      Scenario




     February 10, 2012
26




The End Result
!   Fully vetted, bought-into schedule
!   Risk-adjusted
!   LNG Facility accelerated to align with pipeline
!   Mitigation plan sponsored by board
!   Sanction awarded!




    February 10, 2012
Better Planning Drives                                                                                      27




Project Success
                                    100%
Probability of On-Time Completion




                                    90%

                                    80%

                                    70%

                                    60%

                                    50%

                                    40%

                                    30%

                                    20%

                                    10%

                                     0%
                                           0%   10%   20%   30%     40%   50%   60%     70%   80%   90%   100%

                                                                  Fuse Quality Index™


                          February 10, 2012
Sample of Completed                           28



S1>S5 Projects
    Top of bar represents sanctioned
         target completion date



              Vertical bar represents
               forecasted risk range



              Diamond represents actual/
             final forecast completion date
More information:
White papers: www.projectacumen.com
Software Trial: www.projectacumen.com/trial
Twitter: @projectacumen
Email: info@projectacumen.com

Más contenido relacionado

Similar a Achieving the Unachievable: Aligning a Project with Stakeholder Expectations

Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success ppt
p6academy
 
Prince 2 + XLPM - Semcon - Bert Hedeman
Prince 2 + XLPM - Semcon - Bert HedemanPrince 2 + XLPM - Semcon - Bert Hedeman
Prince 2 + XLPM - Semcon - Bert Hedeman
Svenskt Projektforum
 
At bruxelles scaling agile - v1.5 slideshare
At bruxelles   scaling agile - v1.5 slideshareAt bruxelles   scaling agile - v1.5 slideshare
At bruxelles scaling agile - v1.5 slideshare
Herve Lourdin
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
NASAPMC
 
Controlling project costs
Controlling project costsControlling project costs
Controlling project costs
James Sutter
 
Global samhandling i Aker Solutions
Global samhandling i Aker SolutionsGlobal samhandling i Aker Solutions
Global samhandling i Aker Solutions
Avanade Norway
 

Similar a Achieving the Unachievable: Aligning a Project with Stakeholder Expectations (20)

Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success ppt
 
Prince 2 + XLPM - Semcon - Bert Hedeman
Prince 2 + XLPM - Semcon - Bert HedemanPrince 2 + XLPM - Semcon - Bert Hedeman
Prince 2 + XLPM - Semcon - Bert Hedeman
 
Rawsthorne dan - scrum the big picture
Rawsthorne dan - scrum the big pictureRawsthorne dan - scrum the big picture
Rawsthorne dan - scrum the big picture
 
SAB4113 Intro to Planning & Scheduling
SAB4113 Intro to Planning & SchedulingSAB4113 Intro to Planning & Scheduling
SAB4113 Intro to Planning & Scheduling
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
At bruxelles scaling agile - v1.5 slideshare
At bruxelles   scaling agile - v1.5 slideshareAt bruxelles   scaling agile - v1.5 slideshare
At bruxelles scaling agile - v1.5 slideshare
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Prince2 and agile happy bedfellows
Prince2 and agile happy bedfellowsPrince2 and agile happy bedfellows
Prince2 and agile happy bedfellows
 
Controlling project costs
Controlling project costsControlling project costs
Controlling project costs
 
PRINCE2 and Agile
PRINCE2 and AgilePRINCE2 and Agile
PRINCE2 and Agile
 
DMC Event Presentation for 4 26-2012
DMC Event Presentation for 4 26-2012DMC Event Presentation for 4 26-2012
DMC Event Presentation for 4 26-2012
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 
Projects in less time; 3 secrets to reducing project lead time, on time
Projects in less time; 3 secrets to reducing project lead time, on timeProjects in less time; 3 secrets to reducing project lead time, on time
Projects in less time; 3 secrets to reducing project lead time, on time
 
Global samhandling i Aker Solutions
Global samhandling i Aker SolutionsGlobal samhandling i Aker Solutions
Global samhandling i Aker Solutions
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 

Más de Acumen

Más de Acumen (19)

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPC
 
Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project Compliance
 
Acumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen Risk Workshops Overview
Acumen Risk Workshops Overview
 
Fuse Information Sheet
Fuse Information SheetFuse Information Sheet
Fuse Information Sheet
 
Improved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentImproved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric Assessment
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Project Simplification through Metric Analysis
Project Simplification through Metric AnalysisProject Simplification through Metric Analysis
Project Simplification through Metric Analysis
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range Certainty
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
 

Último

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 

Último (20)

Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 

Achieving the Unachievable: Aligning a Project with Stakeholder Expectations

  • 1. Achieving the Unachievable A Case Study on Aligning a Project with Stakeholder Objectives enterprise project analysis Dr. Dan Patterson PMP | CEO & Founder Acumen
  • 2. Introductions ! Acumen: Project Management Software Company ! Market leader in Analytics; 20 year legacy ! Oracle Primavera & Microsoft partner S1 > S5™ Framework Acumen Core Offerings S5: Acumen Fuse® Validate S4: Optimize S3: Risk- S2: Adjust Risk Assessment Workshops Critique S1: Build Software Training
  • 3. 3 Case Study Introduction ! Case study: GasCom ! LNG Pipeline & Facility Owner ! Early FEED stage ! Project readying for sanction approval ! Investment board Dec 2013 P75 First Gas ! Gas Sales contract already established ! GasCom adopted Acumen S1>S5 ! Required contractors to achieve Fuse Schedule Index™ of 75% ! Schedule developed in Primavera P6 ! All analytics conducted using Acumen Fuse February 10, 2012
  • 4. 4 GasCom S1 > S5 Approach •  Schedule Basis S1 •  Reflects latest scope/contractor updates •  Critiqued Schedule S2 •  Structurally sound, no contingency, sound logic •  Risk-Adjusted Schedule S3 •  Estimate uncertainty, risk events •  Optimized Target Scenarios S4 •  Reduced hot spots, higher confidence •  Team Validated Scenario S5 •  Buy-in on mitigation plans February 10, 2012
  • 5. 5 S1 > S2 Schedule Review ! Deterministic date of Dec 2013 ! Bidding contractors submitted their schedules to GasCom ! GasCom needed to ensure sufficient realism in the schedules ! Looked for means of compressing the schedule to show that an earlier First Gas was achievable February 10, 2012
  • 6. 6 Schedule Critique ! Metric Analysis ! Quality of logic ! Float analysis ! Realism of durations ! Contractor maturity/realism ! Based on the Fuse metric library February 10, 2012 [demo of standard Schedule analysis]
  • 7. Fuse Schedule Index™ 7 Analysis by Contractor February 10, 2012
  • 8. 8 Schedule Analysis Results ! Bidder B failed Schedule Quality review ! Quality was less than 75% threshold ! Had to re-submit resolved schedule ! Used Fuse Schedule Assistant™ to fix shortcomings February 10, 2012
  • 9. 9 GasCom Schedule Cleanse Lags converted to activities February 10, 2012
  • 10. Impact of Schedule 10 Cleanse 5 month slippage February 10, 2012
  • 11. 11 Logic Integrity ! Use of FS, FF, SF, SS links ! SS links don’t account for durations ! Lags hide schedule detail redundant ! Leads cause reverse dates A ! Circular logic between projects B ! Out of sequence updates ! Open start/finish: hidden open ends C ! Logic Density™ ! Logic Hotspot™ ! Redundancy Index™ February 10, 2012
  • 12. 12 GasCom Logic Density™ ! Measure of complexity & soundness ! Dual-band threshold: 2 to 6… ! Determine Logic Hotspots™ in schedule ! GasCom the level of detail was lacking towards the end of the project – mainly around interfaces & integration More definition needed February 10, 2012
  • 13. 13 Driving Logic Analysis ! Test to ensure true path to First Gas ! Analysis showed that there was an error in the schedule with a break in the path around Early Works ! As a result of fixing this missing path, First Gas moved to the right by 2 months February 10, 2012
  • 14. Removal of Logic 14 Redundancy 8% redundancy Removal of redundancy led to a cleaner, more robust schedule
  • 15. 15 GasCom Float Analysis ! S1 showed high float in early stage of project ! S2 resolved schedule showed the opposite ! Sanction acceleration opportunity went away Originally percieved opportunity for making up Resolved schedule not 60 lost time through float offering early stage schedule absorbtion in early stage of acceleration 40 project 20 0 Q1 Q2 Q3 Q4 2011 2011 Q1 Q2 2011 2011 2012 2012 Q3 Q4 Q1 2012 2012 Q2 Q3 2013 2013 Q4 2013 Q1 Q2 2013 2014 Q3 2014 Q4 S1 Average Float S2 Average Float 2014 2014 February 10, 2012
  • 16. 16 S1 > S2 Summary ! Bidder schedules all passed the Schedule Quality Index™ Assessment ! Missing logic was added ! Lags converted to activities ! Opportunity for schedule acceleration was understood (back-end loaded) S1: Dec 2013 5 months S2: May 2014 February 10, 2012
  • 17. 17 S2 > S3 Risk Analysis ! Objective: to determine a risk-adjusted P75 First Gas ! Risk workshop conducted ! True risk exposure was actually at end of project 70% Team Perception 60% Actual Risk Hotspots 50% 40% 30% 20% 10% 0% Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2011 2011 2011 2011 2012 2012 2012 2012 2013 2013 2013 2013 2014 2014 2014 2014 February 10, 2012
  • 18. 18 Risk Insight ! Hidden critical paths ! Risk hot Spots™ ! Determined that Land acquisition activities were extremely critical yet weren’t identified in the schedule Land acquisition February 10, 2012
  • 19. 19 S3 Summary ! P75 risk-adjusted First Gas: Oct 2014 ! 10 months later than board expectations ! Key risk hot spots in schedule identified ! Long Lead procurement items ! Hidden path identified ! Driven by land acquisition delaying pipeline early works S1: Dec 2013 5 S2: May 2014 10 S3: Oct 2014 February 10, 2012
  • 20. S4: Getting back to 20 December 2013… Risk Mitigation Plan Schedule Acceleration ! Response plan identified ! LNG pipeline ready for for each key risk hookup: Feb 2013 ! These plans became part ! LNG Facility ready to of the overall schedule receive gas: Nov 2013 ! Focus needed to be on ! Enabled cost/benefit of accelerating the LNG the mitigation plan to be facility assessed ! Could even afford to slow ! $100MM investment to down pipeline/field work save 1 month by a couple of months… February 10, 2012
  • 21. LNG Facility Acceleration Criteria Set Drive acceleration ! LNG Facility ! Reduce duration Script Objective ! More resources “accelerate Facility by 6 months” ! Changed calendars Step 1 Step 2 Step 3 Accelerate Delay Train Introduce 6 ! Contractor incentive Jetty 2 activities day working construction week/larger camp ! Delay Train 2
  • 22. 22 How Did This Work? ! CPM simulation ! Critical path focus ! Incremental push ! Prioritize ! Earliest/latest ! Longest durations ! Least resistance February 10, 2012
  • 23. 23 S4 Summary ! LNG Facility was able to be accelerated sufficiently so as to not be the driving path in the schedule ! Deterministic First Gas of August 2013 ! 4 months earlier than Dec 2013 but not a valid comparison! ! Sanction board wanted a P75 date not a deterministic ! Risk-adjusted S4 date of February 2014 ! Only 2 months later than target… February 10, 2012
  • 24. 24 S5 Team Buy-in ! A further 2 months acceleration was still required… ! New mitigation plans developed based on the updated risk analysis after the schedule compression ! Model showed that if the board would sanction a further $500MM spend to sponsor the more aggressive mitigation plan, then P75 could be brought back to Dec 2013. ! Project team went to the board with both options and were duly granted the green-light for the more aggressive plan so as to achieve earlier production… February 10, 2012
  • 25. 25 GasCom First Gas Dates P75 Schedule Delay From Dec 2013 1st Gas (months) 10 9 8 7 6 10 Resolved, risk- 5 adjusted, 4 accelerated, mitigated 3 5 2 2 0 1 0 0 S1 - base S2 - resolved S3 - risk- S4 - accelerated S5 - mitigated adjusted Scenario February 10, 2012
  • 26. 26 The End Result ! Fully vetted, bought-into schedule ! Risk-adjusted ! LNG Facility accelerated to align with pipeline ! Mitigation plan sponsored by board ! Sanction awarded! February 10, 2012
  • 27. Better Planning Drives 27 Project Success 100% Probability of On-Time Completion 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Fuse Quality Index™ February 10, 2012
  • 28. Sample of Completed 28 S1>S5 Projects Top of bar represents sanctioned target completion date Vertical bar represents forecasted risk range Diamond represents actual/ final forecast completion date
  • 29. More information: White papers: www.projectacumen.com Software Trial: www.projectacumen.com/trial Twitter: @projectacumen Email: info@projectacumen.com