SCHOOL OF ARCHITECTURE, BUILDING & DESIGN
Modern Architecture Studies in Southeast Asia (MASSA) ResearchUnit
Bachelor of Science (Honours) (Architecture)
BUILDING CONSTRUCTION 1 [ARC 1523]
Assignment 2:
Construction Activities and Process of
A Three Storey Bungalow
Name: Toh Chee Cheng
Student ID: 0311122
Tutor: Ms. Suja
Week 1
Construction Activity 1: Earthwork
Duration: 6 Days
Skilled worker: Land surveyor (1), land surveyor assistant (1), civil engineer (1), civil engineer
assistant (1)
Technical information: Survey topography for measurement of earthwork quantities.
Week 2
Construction Activity 1: Earthwork
Duration: 6 Days
Equipment: Backhoe (1), excavator (1), dumper (1)
Skilled worker: Backhoe operator (1), dumper operator (1), general worker (1)
Technical information: Site is cleared of trees, topsoil, shrubs and rubbish.
Week 3 & 4
Construction Activity 1: Earthwork
Duration: 12 Days
Equipment: Portable penetrometer (1)
Skilled worker: Geotechnical engineer (1), geotechnical engineer assistant (1), civil engineer (1),
civil engineer assistant (1)
Technical information: Mackintosh Probe (MP) test carried out for testing soft soils and
determining suitable materials.
Week 5
Construction Activity 1: Earthwork
Duration: 6 Days
Equipment: Vibrating plate compactor (1), backhoe (1), excavator (1), paver (1), dumper (1)
Skilled worker: Backhoe operator (1), excavator operator (1), paver (1), dumper operator (1),
general worker (1)
Technical information: Site is excavated to required lengths, depths, breadths, inclinations and
curvatures
Week 6
Construction Activity 1: Earthwork
Duration: 6 Days
Materials: Timber formwork, gravel
Equipment: Table saw (2), shovel (2), long tape measurer, steel tape, strong threads, wire nails,
theodolite, wooden pegs, drill hammer
Skilled worker: Carpenter (2), general worker (1)
Technical information: Filling materials to lines, levels and grades required to complete
permanent construction.
Construction activity 2: Transporting piles
Duration: 2 days
Materials: piles
Equipment: Lorry (2), Crane (1)
Skilled worker: Lorry driver (4), Crane Operator (1)
Technical information: Transporting piles from factory, lift the piles by using crane from
lorry after reaching the site.
Week 7 – 8
Construction activity 1: Pile driving process
Duration: 14 days
Materials: piles, pile cushion, bituminous paint
Equipment: Hydraulic drop hammer (1)
Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (3)
Technical information: Mobilize the hydraulic drop hammer to the intended pile position
after marking penetration of the piles, set out the position of drop hammer above the pile
point, pile driving, weld the joints between the piles, apply bituminous paint around the joints
of welded piles to prevent rusting.
Construction activity 2: Cut off process
Duration: During Pilling Process
Material: -
Equipment: Multipurpose excavator (1), Pneumatic hammer (1), Oxy-cutter (1)
Skilled worker: Excavator operator (1), General worker (2)
Technical information: Excavate 1m to 1.5m depth by using Multi-purpose excavator, cut the
piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in
the pile is cut by oxy-cutter.
Week 9
Construction activity 1: Set up formwork for pile cap
Duration: 2 days
Material: Plywood, nails, reinforcement
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general worker (3)
Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and
set up the reinforcement for column stump before pouring the concrete.
Construction activity 2: Pour concrete into the formwork
Duration: 2 days
Material: Concrete
Equipment: Concrete mixer truck, Skip, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (3)
Technical information: Pour the concrete into the formwork through skip from concrete
mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its
strength by preventing air pockets.
Week 10
Construction activity 1: Pile cap harden process
Duration: 7 days
Material: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete pile cap harden for 7 days to wait it mature and
sufficient strength, open formwork after completed.
Week 11
Construction activity 1: Set up formwork for column stump
Duration: 2 days
Material: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker:
Technical information: Set up formwork for column stump before pouring the concrete.
Construction activity 2: Pour concrete into the formwork
Duration: 2 days
Material: Concrete
Equipment: Concrete mixer truck, Skip, Concrete vibrator
Skilled worker:
Technical information: Pour the concrete into the formwork through skip from concrete
mixer truck, vibrate the concrete to increase its strength.
Week 12
Construction activity 1: Column stump harden process
Duration: 7 days
Material: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column stump harden for 7 days to wait it mature and
sufficient strength, open formwork after completed
Construction activity 2: Back filling the pile foundation
Duration: 1 day
Material: soil
Equipment: Multipurpose excavator (1)
Skilled worker: Multipurpose excavator Operator
Technical information: After the harden process, fill up the excavated part around the
foundation to move on to the next process.
Week 13
Construction activity 1: Plumbing Sub-Slab
Duration: 3 days
Material: -
Equipment: -
Skilled worker: -
Technical information: -
Week 14
Construction Activity 1: Ground beam
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete
(1)
Skilled worker: Carpenter (4) , bar bender (2), general worker (1)
Technical information: Determine material, mark the number of form panels, amount of
falsework, place reinforcement bar, erecting the formwork and falsework, propping and
centering, shuttling, provision a camber, brace the wood with stringer and support by struts
and cleat, ensure a grout-tight seal, cleaning and surface treatment, slump test for concrete,
pour cement concrete
Construction Activity 2: Columns
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: Erection sequence for a column, place reinforcement bar as
instructed, position formwork for the column from predetermined grids, securely support
using adjustable steel props,
safely secured to the column formwork and the floor, and that adjustment for pushing and pul
ling is operational, set up and transfer
column clamp positions from the storey rod onto column formwork,
use nails to support the arms of column clamps while wedging,
check the formwork at the top for square
Week 14
Construction Activity 1: Ground Floor Slab
Duration: 6 Days
Materials: Plywood formwork
Equipment: Dip-galvanised nails,hammer, measuring tape, table saw
Skilledworker: General worker (2), carpenter (1),
Technical information: Determine the plan to place slab, constructing slab formwork, propping
and centering, fixingplywood to timber frames, side and bottom shutter of RCC members are
fixed,give an upward camber in the horizontal member of concrete, surface treatment, fixed
the reinforced steel inside.
Thickness range of plywood: 7mm - 32mm
Week 15
Construction Activity 1: Ground Floor Slab
Duration: 6 Days
Materials: Reinforced steel,service pipes, concrete Grade 20
Equipment: Mixer truck (2), concrete vibrator (1), tipper, wheelbarrow
Skilledworker: General worker (2), carpenter (2), bar bender (2)
Technical information: Install service pipes,fixedthe reinforced steel,slump test for concrete,
pour cement concrete, striking and dismantling, remove formwork
Week 16
Construction Activity 1: Ground beam
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete(1)
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: pour cement concrete, striking and dismantling, remove forming
vertical faces, remove shuttling forming soffit
Construction Activity 2: Columns
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete(1)
Skilled worker: Carpenter (3) , bar bender (2), general worker (1)
Technical information: Position and wedge the remainder of the column clamps,
using a plumb bob suspended from a gauge block plumb the column,
securely propped a final check for plumb and column, provision of camber, ensure a grout-
tight seal, cleaning and surface treatment, slump test for concrete, concrete has been poured
and vibrated
Week 17
Construction Activity 1: Columns
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: striking and dismantling, remove forming vertical sides of column
Week 18
Construction Activity 1: First Floor Slab
Duration: 6 Days
Materials: Plywood formwork
Equipment: Dip-galvanised nails,hammer, measuring tape, table saw
Skilledworker: General worker (2), carpenter (1),
Technical information: Determine the plan to place slab, constructing slab formwork, propping
and centering, fixingplywood to timber frames, side and bottom shutter of RCC members are
fixed,give an upward camber in the horizontal member of concrete, surface treatment, fixed
the reinforced steel inside.
Thickness range of plywood: 7mm - 32mm
Week 19
Construction Activity 1: First Floor Slab
Duration: 6 Days
Materials: Reinforced steel,service pipes, concrete Grade 20
Equipment: Mixer truck (2), concrete vibrator (1), tipper, wheelbarrom
Skilledworker: General worker (2), carpenter (2), bar bender (2)
Technical information: Install service pipes,fixedthe reinforced steel,slump test for concrete,
pour cement concrete, striking and dismantling, remove formwork
Week 20
Construction Activity 1: Beam First floor
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete
(1)
Skilled worker: Carpenter (4) , bar bender (2), general worker (1)
Technical information: Determine material, mark the number of form panels, amount of
falsework, place reinforcement bar, erecting the formwork and falsework, propping and
centering, shuttling, provision a camber, brace the wood with stringer and support by struts
and cleat, ensure a grout-tight seal, cleaning and surface treatment, slump test for concrete,
pour cement concrete
Construction Activity 2: Columns (Grid 11-13)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: Erection sequence for a column, place reinforcement bar as
instructed, position formwork for the column from predetermined grids, securely support
using adjustable steel props,
safely secured to the column formwork and the floor, and that adjustment for pushing and pul
ling is operational, set up and transfer
column clamp positions from the storey rod onto column formwork,
use nails to support the arms of column clamps while wedging,
check the formwork at the top for square
Week 21
Construction Activity 1: Beam (Grid 8-10)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete(1)
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: pour cement concrete, striking and dismantling, remove forming
vertical faces, remove shuttling forming soffit
Construction Activity 2: Columns (Grid 11-13)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete(1)
Skilled worker: Carpenter (3) , bar bender (2), general worker (1)
Technical information: Position and wedge the remainder of the column clamps,
using a plumb bob suspended from a gauge block plumb the column,
securely propped a final check for plumb and column, provision of camber, ensure a grout-
tight seal, cleaning and surface treatment, slump test for concrete, concrete has been poured
and vibrated
Week 22
Construction Activity 2: Columns (Grid 11-13)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: striking and dismantling, remove forming vertical sides of column
Week 23
Construction Activity 1: Second Floor Slab
Duration: 6 Days
Materials: Plywood formwork
Equipment: Dip-galvanised nails,hammer, measuring tape, table saw
Skilledworker: General worker (2), carpenter (1),
Technical information: Determine the plan to place slab, constructing slab formwork, propping
and centering, fixingplywood to timber frames, side and bottom shutter of RCC members are
fixed,give an upward camber in the horizontal member of concrete, surface treatment, fixed
the reinforced steel inside.
Thickness range of plywood: 7mm - 32mm
Week 24
Construction Activity 1: Second Floor Slab (Grid 7-14)
Duration: 6 Days
Materials: Reinforced steel,service pipes, concrete Grade 20
Equipment: Mixer truck (2), concrete vibrator (1), tipper, wheelbarrom
Skilledworker: General worker (2), carpenter (2), bar bender (2)
Technical information: Install service pipes,fixedthe reinforced steel,slump test for concrete,
pour cement concrete, striking and dismantling, remove formwork
Week 25
Construction Activity 1: Beam second floor
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete
(1)
Skilled worker: Carpenter (4) , bar bender (2), general worker (1)
Technical information: Determine material, mark the number of form panels, amount of
falsework, place reinforcement bar, erecting the formwork and falsework, propping and
centering, shuttling, provision a camber, brace the wood with stringer and support by struts
and cleat, ensure a grout-tight seal, cleaning and surface treatment, slump test for concrete,
pour cement concrete
Construction Activity 2: Columns (Grid 11-13)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: Erection sequence for a column, place reinforcement bar as
instructed, position formwork for the column from predetermined grids, securely support
using adjustable steel props,
safely secured to the column formwork and the floor, and that adjustment for pushing and pul
ling is operational, set up and transfer
column clamp positions from the storey rod onto column formwork,
use nails to support the arms of column clamps while wedging,
check the formwork at the top for square
Week 26
Construction Activity 1: Beam (Grid 8-10)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete(1)
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: pour cement concrete, striking and dismantling, remove forming
vertical faces, remove shuttling forming soffit
Construction Activity 2: Columns (Grid 11-13)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete(1)
Skilled worker: Carpenter (3) , bar bender (2), general worker (1)
Technical information: Position and wedge the remainder of the column clamps,
using a plumb bob suspended from a gauge block plumb the column,
securely propped a final check for plumb and column, provision of camber, ensure a grout-
tight seal, cleaning and surface treatment, slump test for concrete, concrete has been poured
and vibrated
Week 27
Construction Activity 2: Columns (Grid 11-13)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (1)
Technical information: striking and dismantling, remove forming vertical sides of column
WEEK 28
Construction Activity 1: Staircase (Grid 7-14) Ground floor
Duration: 3 Days
Materials: Ply Woods, Timber Battens
Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
Skilled worker: Carpenter (1), Joinery (1)
Technical information: Make a pitch board with the angle of 30°. Hold pitch board on
the side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (Grid 7-14)
Duration: 3 Days
Materials: Timber, Metal or Prefabricated Formwork
Equipment: Drill, Hammer, Hand Saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from
boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats.
WEEK 29
Construction Activity 1: Staircase (Grid 7-14) ground floor
Duration: 2 Days
Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place
sleeve
Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: To create strong grid of rebar, two or more pieces of rebar
cross are joined together. Secure riser form board with cleats attached about an inch
above the stairs layout to the slide form.
Construction Activity 2: Staircase (Grid 7-14)
Duration: 4 Days
Materials: Concrete, Long screws, Nails
Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
Skilled worker: Carpenters (2)
Technical information: Concrete ceiling and stairs pour in the same day to create
strong bond between the components. Use long screws and nails to lock together
the wooden formwork. After filling the formwork with concrete, mix evenly with
concrete vibrator to prevent air pockets. Use straight edge to spread the concrete
and circular moves to create even finish. Keep the concrete wet or damp to prevent
cracks for up to one week while it cures.
WEEK 30
Construction Activity 1: Staircase (Grid 7-14)first floor
Duration: 3 Days
Materials: Ply Woods, Timber Battens
Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
Skilled worker: Carpenter (1), Joinery (1)
Technical information: Make a pitch board with the angle of 30°. Hold pitch board on
the side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (Grid 7-14)
Duration: 3 Days
Materials: Timber, Metal or Prefabricated Formwork
Equipment: Drill, Hammer, Hand Saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from
boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats.
WEEK 31
Construction Activity 1: Staircase (Grid 7-14)first floor
Duration: 2 Days
Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place
sleeve
Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: To create strong grid of rebar, two or more pieces of rebar
cross are joined together. Secure riser form board with cleats attached about an inch
above the stairs layout to the slide form.
Construction Activity 2: Staircase (Grid 7-14)
Duration: 4 Days
Materials: Concrete, Long screws, Nails
Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
Skilled worker: Carpenters (2)
Technical information: Concrete ceiling and stairs pour in the same day to create
strong bond between the components. Use long screws and nails to lock together
the wooden formwork. After filling the formwork with concrete, mix evenly with
concrete vibrator to prevent air pockets. Use straight edge to spread the concrete
and circular moves to create even finish. Keep the concrete wet or damp to prevent
cracks for up to one week while it cures.
Week 32
Construction Activity 1: Brickwork (Grid 7-14) –ground floor
Duration: 5 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1)
Technical information:
Brickwork process including bricks, beds and perpends. The bed is made up with mortar
with brick is laid. Perpends is a vertical joint between two bricks filled with mortar.
 Bricks of dimensions 215 mm x 102.5 mm × 65 mm;
 Mortar beds and perpends of a uniform 10 mm.
Wire are usedevery3 layersof brickslaidto control mortar shrinkage andcrack control due to
temperature andpressure extremes,andbondintersectingwalls.
Brickwork needs to be supported over openings the opening are often supporting by
reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all
the support, or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred. Supporting windows and doors.
Week 33
Construction Activity 1: Brickwork (Grid 7-14) –first floor
Duration: 5 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1)
Technical information:
Brickwork process including bricks, beds and perpends. The bed is made up with mortar
with brick is laid. Perpends is a vertical joint between two bricks filled with mortar.
 Bricks of dimensions 215 mm x 102.5 mm × 65 mm;
 Mortar beds and perpends of a uniform 10 mm.
Wire are usedevery3 layersof brickslaidto control mortar shrinkage andcrack control due to
temperature andpressure extremes,andbondintersectingwalls.
Brickwork needs to be supported over openings the opening are often supporting by
reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all
the support, or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred. Supporting windows and doors.
Week 34
Construction Activity 2: Brickwork (Grid 7-14) –second floor
Duration: 3 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1)
Technical information:
Brickwork process including brick laying, reinforcement of the wall and reinforcement of
openings. The bed is made up with mortar with brick is laid. Perpends is a vertical joint
between two bricks filled with mortar.
 Bricks of dimensions 215 mm x 102.5 mm × 65 mm;
 Mortar beds and perpends of a uniform 10 mm.
Wire are usedevery3 layersof brickslaidto control mortar shrinkage andcrack control due to
temperature andpressure extremes,andbondintersectingwalls.
Brickwork needs to be supported over openings the opening are often supporting by
reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all
the support, or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred. Supporting windows and doors.
WEEK 35
Construction Activity 1: Staircase (Grid 7-14)
Duration: 3 Days
Materials: Ply Woods, Timber Battens
Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
Skilled worker: Carpenter (1), Joinery (1)
Technical information: Make a pitch board with the angle of 30°. Hold pitch board on
the side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (Grid 7-14)
Duration: 3 Days
Materials: Timber, Metal or Prefabricated Formwork
Equipment: Drill, Hammer, Hand Saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from
boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats.
WEEK 36
Construction Activity 1: Staircase (Grid 7-14)
Duration: 2 Days
Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place
sleeve
Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: To create strong grid of rebar, two or more pieces of rebar
cross are joined together. Secure riser form board with cleats attached about an inch
above the stairs layout to the slide form.
Construction Activity 2: Staircase (Grid 7-14)
Duration: 4 Days
Materials: Concrete, Long screws, Nails
Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
Skilled worker: Carpenters (2)
Technical information: Concrete ceiling and stairs pour in the same day to create
strong bond between the components. Use long screws and nails to lock together
the wooden formwork. After filling the formwork with concrete, mix evenly with
concrete vibrator to prevent air pockets. Use straight edge to spread the concrete
and circular moves to create even finish. Keep the concrete wet or damp to prevent
cracks for up to one week while it cures.
Week 37
Construction Activity 1: Roof (Grid 7-14)
Duration: 6 Days
Materials: Metal trusses
Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape
Skilledworker: Roofer (1), general worker (1), truss erector (1), crane operator (1)
Technical information: Install permanent lateral bracing to truss.
Construction Activity 2: Roof (Grid 1-7)
Duration: 6 Days
Materials: Ridge metal (aluminium),ridge bracket, ridge vent
Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender
Skilledworker: Roofer (1), general worker (1), bar bender (1)
Construction Activity 3: Brickwork – Rendering (Grid 7-14)—ground floor
Duration: 3 Days
Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
Skilled worker: Pointing, cleaning, and caulking workers (2) and plasterer (2)
Technical information:
Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Construction Activity 4: Brickwork – Rendering (Grid 7-14)—first floor
Duration: 3 Days
Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
Skilled worker: Pointing, cleaning, and caulking workers (2) and plasterer (2)
Technical information:
Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Technical information: Install ridge block.
Week 38
Construction Activity 1: Roof (Grid 7-14)
Duration: 6 Days
Materials: Ridge metal (aluminium),ridge bracket, ridge vent
Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender
Skilledworker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install ridge block.
Construction Activity 2: Roof (Grid 1-7)
Duration: 6 Days
Materials: Fascia board ribbon, fascia board bracket
Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender
Skilledworker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install fascia board.
Construction Activity 3: Brickwork – Rendering (Grid 7-14)—second floor
Duration: 3 Days
Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
Skilled worker: Pointing, cleaning, and caulking workers(2) and plasterer (2)
Technical information:
Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Week 39
Construction Activity 1: Roof (Grid 7-14)
Duration: 6 Days
Materials: Fascia board ribbon, fascia board bracket
Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender
Skilledworker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install fascia board.
Construction Activity 2: Roof (Grid 1-14)
Duration: 6 Days
Materials: Metal anchor sling,roof anchor bracket
Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender
Skilledworker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install anchor slings.
Week 40
Construction Activity 1: Roof (Grid 1-7)
Duration: 3 Days
Materials: Chicken netting
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install chicken netting.
Week 41
Construction Activity 1: Roof (Grid 7-14)
Duration: 3 Days
Materials: Chicken netting
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install chicken netting.
Construction Activity 2: Roof (Grid 1-7)
Duration: 3 Days
Materials: Aluminiumsheet
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install aluminium flashing.
Week 42
Construction Activity 1: Roof (Grid 7-14)
Duration: 3 Days
Materials: Chicken netting
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install aluminium flashing.
Week 43
Construction Activity 1: Roof (Grid 1-7)
Duration: 6 Days
Materials: Metal batten strips (aluminium)
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install batten.
Construction Activity 2: Roof (Grid 7-14)
Duration: 6 Days
Materials: Metal batten strips (aluminium)
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install batten.
Week 44
Construction Activity 1: Roof (Grid 1-7)
Duration: 6 Days
Materials: Cement tiles
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install batten.
Construction Activity 2: Roof (Grid 7-14)
Duration: 6 Days
Materials: Metal batten strips (aluminium)
Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter
Skilledworker: Roofer (1), general worker (1)
Technical information: Install batten.
Week 45
Construction Activity 1: Roof (Grid 1-7)
Duration: 6 Days
Materials: Cement tiles
Equipment: Measuring tape, dip-galvanised nails,hammer
Skilledworker: Roofer (1), general worker (1), roof tiler(1)
Technical information: Place cement tilesand nail every third row.
Construction Activity 2: Roof (Grid 7-14)
Duration: 6 Days
Materials: Cement tiles
Equipment: Measuring tape, dip-galvanised nails,hammer
Skilledworker: Roofer (1), general worker (1), roof tiler(1)
Technical information: Place cement tilesand nail every third row.

Más contenido relacionado

Destacado

Theories and Urbanism Synopsis
Theories and Urbanism SynopsisTheories and Urbanism Synopsis
Theories and Urbanism SynopsisQing Cheng
 
Special moments
Special momentsSpecial moments
Special moments0633419707
 
Guid tour george, miiko, lucia & mette
Guid tour   george, miiko, lucia & metteGuid tour   george, miiko, lucia & mette
Guid tour george, miiko, lucia & metteMette Frandsen
 
приколы 01
приколы 01приколы 01
приколы 010633419707
 
Edited journal
Edited journalEdited journal
Edited journalQing Cheng
 
Compare movies essay
Compare movies essayCompare movies essay
Compare movies essayQing Cheng
 

Destacado (10)

Epc ass 1
Epc ass 1Epc ass 1
Epc ass 1
 
Theories and Urbanism Synopsis
Theories and Urbanism SynopsisTheories and Urbanism Synopsis
Theories and Urbanism Synopsis
 
Special moments
Special momentsSpecial moments
Special moments
 
Cach su dung may xong khi dung
Cach su dung may xong khi dungCach su dung may xong khi dung
Cach su dung may xong khi dung
 
Guid tour george, miiko, lucia & mette
Guid tour   george, miiko, lucia & metteGuid tour   george, miiko, lucia & mette
Guid tour george, miiko, lucia & mette
 
Fotki funny
Fotki funnyFotki funny
Fotki funny
 
приколы 01
приколы 01приколы 01
приколы 01
 
Vocabulary
VocabularyVocabulary
Vocabulary
 
Edited journal
Edited journalEdited journal
Edited journal
 
Compare movies essay
Compare movies essayCompare movies essay
Compare movies essay
 

Similar a Bcon final report

Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final ProjectEvelyn Paul
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1Jing Chuang
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 ReportappleManiac
 
Construction maintenance
Construction maintenanceConstruction maintenance
Construction maintenanceDeepsonJohn1
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)Jia Hong Mui
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite reportxennechau
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1Zi Shan
 
Site visit report
Site visit reportSite visit report
Site visit reportJıa Yıı
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visitPui San
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit ReportZIyeeTan
 

Similar a Bcon final report (20)

MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final Project
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 Report
 
Construction maintenance
Construction maintenanceConstruction maintenance
Construction maintenance
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite report
 
SITE REPORT
SITE REPORTSITE REPORT
SITE REPORT
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
Site report 1
Site report 1Site report 1
Site report 1
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 

Último

8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 

Último (20)

8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 

Bcon final report

  • 1. SCHOOL OF ARCHITECTURE, BUILDING & DESIGN Modern Architecture Studies in Southeast Asia (MASSA) ResearchUnit Bachelor of Science (Honours) (Architecture) BUILDING CONSTRUCTION 1 [ARC 1523] Assignment 2: Construction Activities and Process of A Three Storey Bungalow Name: Toh Chee Cheng Student ID: 0311122 Tutor: Ms. Suja
  • 2. Week 1 Construction Activity 1: Earthwork Duration: 6 Days Skilled worker: Land surveyor (1), land surveyor assistant (1), civil engineer (1), civil engineer assistant (1) Technical information: Survey topography for measurement of earthwork quantities. Week 2 Construction Activity 1: Earthwork Duration: 6 Days Equipment: Backhoe (1), excavator (1), dumper (1) Skilled worker: Backhoe operator (1), dumper operator (1), general worker (1) Technical information: Site is cleared of trees, topsoil, shrubs and rubbish.
  • 3. Week 3 & 4 Construction Activity 1: Earthwork Duration: 12 Days Equipment: Portable penetrometer (1) Skilled worker: Geotechnical engineer (1), geotechnical engineer assistant (1), civil engineer (1), civil engineer assistant (1) Technical information: Mackintosh Probe (MP) test carried out for testing soft soils and determining suitable materials. Week 5 Construction Activity 1: Earthwork Duration: 6 Days Equipment: Vibrating plate compactor (1), backhoe (1), excavator (1), paver (1), dumper (1) Skilled worker: Backhoe operator (1), excavator operator (1), paver (1), dumper operator (1), general worker (1) Technical information: Site is excavated to required lengths, depths, breadths, inclinations and curvatures
  • 4. Week 6 Construction Activity 1: Earthwork Duration: 6 Days Materials: Timber formwork, gravel Equipment: Table saw (2), shovel (2), long tape measurer, steel tape, strong threads, wire nails, theodolite, wooden pegs, drill hammer Skilled worker: Carpenter (2), general worker (1) Technical information: Filling materials to lines, levels and grades required to complete permanent construction. Construction activity 2: Transporting piles Duration: 2 days Materials: piles Equipment: Lorry (2), Crane (1) Skilled worker: Lorry driver (4), Crane Operator (1) Technical information: Transporting piles from factory, lift the piles by using crane from lorry after reaching the site.
  • 5. Week 7 – 8 Construction activity 1: Pile driving process Duration: 14 days Materials: piles, pile cushion, bituminous paint Equipment: Hydraulic drop hammer (1) Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (3) Technical information: Mobilize the hydraulic drop hammer to the intended pile position after marking penetration of the piles, set out the position of drop hammer above the pile point, pile driving, weld the joints between the piles, apply bituminous paint around the joints of welded piles to prevent rusting. Construction activity 2: Cut off process Duration: During Pilling Process Material: - Equipment: Multipurpose excavator (1), Pneumatic hammer (1), Oxy-cutter (1) Skilled worker: Excavator operator (1), General worker (2) Technical information: Excavate 1m to 1.5m depth by using Multi-purpose excavator, cut the piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in the pile is cut by oxy-cutter.
  • 6. Week 9 Construction activity 1: Set up formwork for pile cap Duration: 2 days Material: Plywood, nails, reinforcement Equipment: hammer, measuring tape, drill, handsaw Skilled worker: general worker (3) Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and set up the reinforcement for column stump before pouring the concrete. Construction activity 2: Pour concrete into the formwork Duration: 2 days Material: Concrete Equipment: Concrete mixer truck, Skip, Concrete vibrator Skilled worker: Concrete mixer truck operator (1), general worker (3) Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its strength by preventing air pockets.
  • 7. Week 10 Construction activity 1: Pile cap harden process Duration: 7 days Material: - Equipment: - Skilled worker: - Technical information: Let the concrete pile cap harden for 7 days to wait it mature and sufficient strength, open formwork after completed. Week 11 Construction activity 1: Set up formwork for column stump Duration: 2 days Material: Plywood, nails Equipment: hammer, measuring tape, drill, handsaw Skilled worker: Technical information: Set up formwork for column stump before pouring the concrete.
  • 8. Construction activity 2: Pour concrete into the formwork Duration: 2 days Material: Concrete Equipment: Concrete mixer truck, Skip, Concrete vibrator Skilled worker: Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate the concrete to increase its strength. Week 12 Construction activity 1: Column stump harden process Duration: 7 days Material: - Equipment: - Skilled worker: - Technical information: Let the concrete column stump harden for 7 days to wait it mature and sufficient strength, open formwork after completed Construction activity 2: Back filling the pile foundation Duration: 1 day Material: soil Equipment: Multipurpose excavator (1) Skilled worker: Multipurpose excavator Operator Technical information: After the harden process, fill up the excavated part around the foundation to move on to the next process.
  • 9. Week 13 Construction activity 1: Plumbing Sub-Slab Duration: 3 days Material: - Equipment: - Skilled worker: - Technical information: - Week 14 Construction Activity 1: Ground beam Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete (1) Skilled worker: Carpenter (4) , bar bender (2), general worker (1) Technical information: Determine material, mark the number of form panels, amount of falsework, place reinforcement bar, erecting the formwork and falsework, propping and centering, shuttling, provision a camber, brace the wood with stringer and support by struts and cleat, ensure a grout-tight seal, cleaning and surface treatment, slump test for concrete, pour cement concrete Construction Activity 2: Columns Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork
  • 10. Equipment: Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: Erection sequence for a column, place reinforcement bar as instructed, position formwork for the column from predetermined grids, securely support using adjustable steel props, safely secured to the column formwork and the floor, and that adjustment for pushing and pul ling is operational, set up and transfer column clamp positions from the storey rod onto column formwork, use nails to support the arms of column clamps while wedging, check the formwork at the top for square Week 14 Construction Activity 1: Ground Floor Slab Duration: 6 Days Materials: Plywood formwork Equipment: Dip-galvanised nails,hammer, measuring tape, table saw Skilledworker: General worker (2), carpenter (1), Technical information: Determine the plan to place slab, constructing slab formwork, propping and centering, fixingplywood to timber frames, side and bottom shutter of RCC members are fixed,give an upward camber in the horizontal member of concrete, surface treatment, fixed the reinforced steel inside. Thickness range of plywood: 7mm - 32mm Week 15 Construction Activity 1: Ground Floor Slab Duration: 6 Days Materials: Reinforced steel,service pipes, concrete Grade 20 Equipment: Mixer truck (2), concrete vibrator (1), tipper, wheelbarrow Skilledworker: General worker (2), carpenter (2), bar bender (2) Technical information: Install service pipes,fixedthe reinforced steel,slump test for concrete, pour cement concrete, striking and dismantling, remove formwork Week 16 Construction Activity 1: Ground beam Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete(1) Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: pour cement concrete, striking and dismantling, remove forming vertical faces, remove shuttling forming soffit
  • 11. Construction Activity 2: Columns Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete(1) Skilled worker: Carpenter (3) , bar bender (2), general worker (1) Technical information: Position and wedge the remainder of the column clamps, using a plumb bob suspended from a gauge block plumb the column, securely propped a final check for plumb and column, provision of camber, ensure a grout- tight seal, cleaning and surface treatment, slump test for concrete, concrete has been poured and vibrated Week 17 Construction Activity 1: Columns Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: striking and dismantling, remove forming vertical sides of column
  • 12. Week 18 Construction Activity 1: First Floor Slab Duration: 6 Days Materials: Plywood formwork Equipment: Dip-galvanised nails,hammer, measuring tape, table saw Skilledworker: General worker (2), carpenter (1), Technical information: Determine the plan to place slab, constructing slab formwork, propping and centering, fixingplywood to timber frames, side and bottom shutter of RCC members are fixed,give an upward camber in the horizontal member of concrete, surface treatment, fixed the reinforced steel inside. Thickness range of plywood: 7mm - 32mm Week 19 Construction Activity 1: First Floor Slab Duration: 6 Days Materials: Reinforced steel,service pipes, concrete Grade 20 Equipment: Mixer truck (2), concrete vibrator (1), tipper, wheelbarrom Skilledworker: General worker (2), carpenter (2), bar bender (2) Technical information: Install service pipes,fixedthe reinforced steel,slump test for concrete, pour cement concrete, striking and dismantling, remove formwork Week 20 Construction Activity 1: Beam First floor
  • 13. Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete (1) Skilled worker: Carpenter (4) , bar bender (2), general worker (1) Technical information: Determine material, mark the number of form panels, amount of falsework, place reinforcement bar, erecting the formwork and falsework, propping and centering, shuttling, provision a camber, brace the wood with stringer and support by struts and cleat, ensure a grout-tight seal, cleaning and surface treatment, slump test for concrete, pour cement concrete Construction Activity 2: Columns (Grid 11-13) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: Erection sequence for a column, place reinforcement bar as instructed, position formwork for the column from predetermined grids, securely support using adjustable steel props, safely secured to the column formwork and the floor, and that adjustment for pushing and pul ling is operational, set up and transfer column clamp positions from the storey rod onto column formwork, use nails to support the arms of column clamps while wedging, check the formwork at the top for square Week 21 Construction Activity 1: Beam (Grid 8-10) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete(1) Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: pour cement concrete, striking and dismantling, remove forming vertical faces, remove shuttling forming soffit
  • 14. Construction Activity 2: Columns (Grid 11-13) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete(1) Skilled worker: Carpenter (3) , bar bender (2), general worker (1) Technical information: Position and wedge the remainder of the column clamps, using a plumb bob suspended from a gauge block plumb the column, securely propped a final check for plumb and column, provision of camber, ensure a grout- tight seal, cleaning and surface treatment, slump test for concrete, concrete has been poured and vibrated Week 22 Construction Activity 2: Columns (Grid 11-13) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: striking and dismantling, remove forming vertical sides of column
  • 15. Week 23 Construction Activity 1: Second Floor Slab Duration: 6 Days Materials: Plywood formwork Equipment: Dip-galvanised nails,hammer, measuring tape, table saw Skilledworker: General worker (2), carpenter (1), Technical information: Determine the plan to place slab, constructing slab formwork, propping and centering, fixingplywood to timber frames, side and bottom shutter of RCC members are fixed,give an upward camber in the horizontal member of concrete, surface treatment, fixed the reinforced steel inside. Thickness range of plywood: 7mm - 32mm Week 24 Construction Activity 1: Second Floor Slab (Grid 7-14) Duration: 6 Days Materials: Reinforced steel,service pipes, concrete Grade 20 Equipment: Mixer truck (2), concrete vibrator (1), tipper, wheelbarrom Skilledworker: General worker (2), carpenter (2), bar bender (2) Technical information: Install service pipes,fixedthe reinforced steel,slump test for concrete, pour cement concrete, striking and dismantling, remove formwork Week 25
  • 16. Construction Activity 1: Beam second floor Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete (1) Skilled worker: Carpenter (4) , bar bender (2), general worker (1) Technical information: Determine material, mark the number of form panels, amount of falsework, place reinforcement bar, erecting the formwork and falsework, propping and centering, shuttling, provision a camber, brace the wood with stringer and support by struts and cleat, ensure a grout-tight seal, cleaning and surface treatment, slump test for concrete, pour cement concrete
  • 17. Construction Activity 2: Columns (Grid 11-13) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: Erection sequence for a column, place reinforcement bar as instructed, position formwork for the column from predetermined grids, securely support using adjustable steel props, safely secured to the column formwork and the floor, and that adjustment for pushing and pul ling is operational, set up and transfer column clamp positions from the storey rod onto column formwork, use nails to support the arms of column clamps while wedging, check the formwork at the top for square Week 26 Construction Activity 1: Beam (Grid 8-10) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete(1) Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: pour cement concrete, striking and dismantling, remove forming vertical faces, remove shuttling forming soffit Construction Activity 2: Columns (Grid 11-13) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete(1) Skilled worker: Carpenter (3) , bar bender (2), general worker (1) Technical information: Position and wedge the remainder of the column clamps, using a plumb bob suspended from a gauge block plumb the column, securely propped a final check for plumb and column, provision of camber, ensure a grout- tight seal, cleaning and surface treatment, slump test for concrete, concrete has been poured and vibrated
  • 18. Week 27 Construction Activity 2: Columns (Grid 11-13) Duration: 6 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (1) Technical information: striking and dismantling, remove forming vertical sides of column WEEK 28 Construction Activity 1: Staircase (Grid 7-14) Ground floor Duration: 3 Days Materials: Ply Woods, Timber Battens Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw Skilled worker: Carpenter (1), Joinery (1) Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the side to represent the top of the stair slab and mark the riser and tread Construction Activity 2: Staircase (Grid 7-14) Duration: 3 Days Materials: Timber, Metal or Prefabricated Formwork Equipment: Drill, Hammer, Hand Saw Skilled worker: Bar Benders (1), Formwork Carpenters (1) Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats. WEEK 29 Construction Activity 1: Staircase (Grid 7-14) ground floor Duration: 2 Days Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve Equipment: Measuring Tape, chalk line, drill, hammer, hand saw Skilled worker: Bar Benders (1), Formwork Carpenters (1) Technical information: To create strong grid of rebar, two or more pieces of rebar cross are joined together. Secure riser form board with cleats attached about an inch above the stairs layout to the slide form. Construction Activity 2: Staircase (Grid 7-14) Duration: 4 Days Materials: Concrete, Long screws, Nails Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
  • 19. Skilled worker: Carpenters (2) Technical information: Concrete ceiling and stairs pour in the same day to create strong bond between the components. Use long screws and nails to lock together the wooden formwork. After filling the formwork with concrete, mix evenly with concrete vibrator to prevent air pockets. Use straight edge to spread the concrete and circular moves to create even finish. Keep the concrete wet or damp to prevent cracks for up to one week while it cures. WEEK 30 Construction Activity 1: Staircase (Grid 7-14)first floor Duration: 3 Days Materials: Ply Woods, Timber Battens Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw Skilled worker: Carpenter (1), Joinery (1) Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the side to represent the top of the stair slab and mark the riser and tread Construction Activity 2: Staircase (Grid 7-14) Duration: 3 Days Materials: Timber, Metal or Prefabricated Formwork Equipment: Drill, Hammer, Hand Saw Skilled worker: Bar Benders (1), Formwork Carpenters (1) Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats. WEEK 31 Construction Activity 1: Staircase (Grid 7-14)first floor Duration: 2 Days Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve Equipment: Measuring Tape, chalk line, drill, hammer, hand saw Skilled worker: Bar Benders (1), Formwork Carpenters (1)
  • 20. Technical information: To create strong grid of rebar, two or more pieces of rebar cross are joined together. Secure riser form board with cleats attached about an inch above the stairs layout to the slide form. Construction Activity 2: Staircase (Grid 7-14) Duration: 4 Days Materials: Concrete, Long screws, Nails Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board Skilled worker: Carpenters (2) Technical information: Concrete ceiling and stairs pour in the same day to create strong bond between the components. Use long screws and nails to lock together the wooden formwork. After filling the formwork with concrete, mix evenly with concrete vibrator to prevent air pockets. Use straight edge to spread the concrete and circular moves to create even finish. Keep the concrete wet or damp to prevent cracks for up to one week while it cures. Week 32 Construction Activity 1: Brickwork (Grid 7-14) –ground floor Duration: 5 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled with mortar.  Bricks of dimensions 215 mm x 102.5 mm × 65 mm;  Mortar beds and perpends of a uniform 10 mm. Wire are usedevery3 layersof brickslaidto control mortar shrinkage andcrack control due to temperature andpressure extremes,andbondintersectingwalls.
  • 21. Brickwork needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Supporting windows and doors.
  • 22. Week 33 Construction Activity 1: Brickwork (Grid 7-14) –first floor Duration: 5 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1) Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled with mortar.  Bricks of dimensions 215 mm x 102.5 mm × 65 mm;  Mortar beds and perpends of a uniform 10 mm. Wire are usedevery3 layersof brickslaidto control mortar shrinkage andcrack control due to temperature andpressure extremes,andbondintersectingwalls. Brickwork needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Supporting windows and doors.
  • 23. Week 34 Construction Activity 2: Brickwork (Grid 7-14) –second floor Duration: 3 days Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh Equipment: Rose Brick Trowels, carpenter level, brick jointer Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1) Technical information: Brickwork process including brick laying, reinforcement of the wall and reinforcement of openings. The bed is made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled with mortar.  Bricks of dimensions 215 mm x 102.5 mm × 65 mm;  Mortar beds and perpends of a uniform 10 mm. Wire are usedevery3 layersof brickslaidto control mortar shrinkage andcrack control due to temperature andpressure extremes,andbondintersectingwalls. Brickwork needs to be supported over openings the opening are often supporting by reinforcing steel fully embedded in Portland cement grout. The steel angles, can provide all the support, or be attached to the primary structure such as a reinforced concrete frame, to which the load is transferred. Supporting windows and doors. WEEK 35 Construction Activity 1: Staircase (Grid 7-14) Duration: 3 Days Materials: Ply Woods, Timber Battens Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw Skilled worker: Carpenter (1), Joinery (1)
  • 24. Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the side to represent the top of the stair slab and mark the riser and tread Construction Activity 2: Staircase (Grid 7-14) Duration: 3 Days Materials: Timber, Metal or Prefabricated Formwork Equipment: Drill, Hammer, Hand Saw Skilled worker: Bar Benders (1), Formwork Carpenters (1) Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats. WEEK 36 Construction Activity 1: Staircase (Grid 7-14) Duration: 2 Days Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve Equipment: Measuring Tape, chalk line, drill, hammer, hand saw Skilled worker: Bar Benders (1), Formwork Carpenters (1) Technical information: To create strong grid of rebar, two or more pieces of rebar cross are joined together. Secure riser form board with cleats attached about an inch above the stairs layout to the slide form. Construction Activity 2: Staircase (Grid 7-14) Duration: 4 Days Materials: Concrete, Long screws, Nails Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board Skilled worker: Carpenters (2) Technical information: Concrete ceiling and stairs pour in the same day to create strong bond between the components. Use long screws and nails to lock together the wooden formwork. After filling the formwork with concrete, mix evenly with concrete vibrator to prevent air pockets. Use straight edge to spread the concrete and circular moves to create even finish. Keep the concrete wet or damp to prevent cracks for up to one week while it cures. Week 37 Construction Activity 1: Roof (Grid 7-14) Duration: 6 Days Materials: Metal trusses Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape Skilledworker: Roofer (1), general worker (1), truss erector (1), crane operator (1) Technical information: Install permanent lateral bracing to truss. Construction Activity 2: Roof (Grid 1-7) Duration: 6 Days Materials: Ridge metal (aluminium),ridge bracket, ridge vent Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender Skilledworker: Roofer (1), general worker (1), bar bender (1)
  • 25. Construction Activity 3: Brickwork – Rendering (Grid 7-14)—ground floor Duration: 3 Days Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White Cement Equipment: Masonry Brushes, Sled Runners, Skilled worker: Pointing, cleaning, and caulking workers (2) and plasterer (2) Technical information: Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Skim coat mixed blended white cement on it. Construction Activity 4: Brickwork – Rendering (Grid 7-14)—first floor Duration: 3 Days Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White Cement Equipment: Masonry Brushes, Sled Runners, Skilled worker: Pointing, cleaning, and caulking workers (2) and plasterer (2) Technical information: Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Skim coat mixed blended white cement on it. Technical information: Install ridge block. Week 38 Construction Activity 1: Roof (Grid 7-14) Duration: 6 Days Materials: Ridge metal (aluminium),ridge bracket, ridge vent Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender Skilledworker: Roofer (1), general worker (1), bar bender (1) Technical information: Install ridge block. Construction Activity 2: Roof (Grid 1-7) Duration: 6 Days Materials: Fascia board ribbon, fascia board bracket Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender Skilledworker: Roofer (1), general worker (1), bar bender (1) Technical information: Install fascia board.
  • 26. Construction Activity 3: Brickwork – Rendering (Grid 7-14)—second floor Duration: 3 Days Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White Cement Equipment: Masonry Brushes, Sled Runners, Skilled worker: Pointing, cleaning, and caulking workers(2) and plasterer (2) Technical information: Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Skim coat mixed blended white cement on it. Week 39 Construction Activity 1: Roof (Grid 7-14) Duration: 6 Days Materials: Fascia board ribbon, fascia board bracket Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender Skilledworker: Roofer (1), general worker (1), bar bender (1) Technical information: Install fascia board. Construction Activity 2: Roof (Grid 1-14) Duration: 6 Days Materials: Metal anchor sling,roof anchor bracket Equipment: Driller,screw driver, spiral screw, measuring tape, metal bender Skilledworker: Roofer (1), general worker (1), bar bender (1) Technical information: Install anchor slings. Week 40 Construction Activity 1: Roof (Grid 1-7) Duration: 3 Days Materials: Chicken netting Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install chicken netting. Week 41 Construction Activity 1: Roof (Grid 7-14) Duration: 3 Days
  • 27. Materials: Chicken netting Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install chicken netting. Construction Activity 2: Roof (Grid 1-7) Duration: 3 Days Materials: Aluminiumsheet Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install aluminium flashing. Week 42 Construction Activity 1: Roof (Grid 7-14) Duration: 3 Days Materials: Chicken netting Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install aluminium flashing. Week 43 Construction Activity 1: Roof (Grid 1-7) Duration: 6 Days Materials: Metal batten strips (aluminium) Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install batten. Construction Activity 2: Roof (Grid 7-14) Duration: 6 Days Materials: Metal batten strips (aluminium) Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install batten. Week 44 Construction Activity 1: Roof (Grid 1-7) Duration: 6 Days Materials: Cement tiles Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install batten. Construction Activity 2: Roof (Grid 7-14) Duration: 6 Days Materials: Metal batten strips (aluminium) Equipment: Measuring tape, metal bender, dip-galvanisednails, hammer, metal cutter Skilledworker: Roofer (1), general worker (1) Technical information: Install batten.
  • 28. Week 45 Construction Activity 1: Roof (Grid 1-7) Duration: 6 Days Materials: Cement tiles Equipment: Measuring tape, dip-galvanised nails,hammer Skilledworker: Roofer (1), general worker (1), roof tiler(1) Technical information: Place cement tilesand nail every third row. Construction Activity 2: Roof (Grid 7-14) Duration: 6 Days Materials: Cement tiles Equipment: Measuring tape, dip-galvanised nails,hammer Skilledworker: Roofer (1), general worker (1), roof tiler(1) Technical information: Place cement tilesand nail every third row.