SlideShare una empresa de Scribd logo
1 de 23
 The Calcutta Electric Supply Corporation or CESC supplies 
electricity to area under the Kolkata municipal corporation in the 
city of Kolkata, India, mainly but also few areas of Howrah, 
Hooghly, 24 Parganas (North) and 24 Parganas (South) districts of 
West Bengal, India. 
 The CESC limited supplies electricity to approximately 2.4 millon 
consumers. The total generation capacity stands out at 1025 MW 
from the four generating power plants. It has four generating 
stations namely 
1. New Cossipore, commissioned at 1949 with an installed capacity of 
100 MW. 
2. Titagarh, commissioned at 1983 with an installed capacity of 240 
MW. 
3. Southern, commissioned at 1991 with an installed capacity of 135 
MW. 
4. BBGS, commissioned at 1997 with an installed capacity of 750 MW.
 The Budge Budge generating 
station(BBGS) is a state of the 
art facility which has won 
several awards and 
accolades for its 
environmental friendly way 
of producing current. It is 
located in Pujali,Budge 
Budge,24 PGS(S),West 
Bengal. The Budge Budge 
generating station is a state 
of the art facility which has 
won several awards and 
accolades for its 
environmental friendly way 
of producing current.
 The capacity stands out at 750 MW out of three 
units of 250 MW each .Power is generated at 
16.5 kV and is stepped up to a voltage of 132 
kV(unit 1&2) and 220 Kv(unit 3) in a generator 
transformer for onward transmission to the 
system.
The following two departments give us the technical details 
about budge budge generating station. 
OPERATIONS DEPARTMENT- The Department of operations at 
the Budge Budge generating station is responsible for 
monitoring and issuing remote commands in case of manual 
mode of operation to various components like 
boiler,turbine,condensors etc for a smooth running of the power 
plant. 
FUEL AND ASH DEPARTMENT- The department of fuel and ash 
operations oversees the entire process of coal unloading, 
moving it to the stack yard and as well as the effective 
elimination of fly as well as bottom ash. A majority of the fly ash 
is at present exported to Bangladesh though barges for use in 
their cement plants.
 A boiler (or steam generator, as it is commonly 
called) is a closed vessel in which water, under 
pressure, is transformed into steam by the 
application of heat.In BBGS,vertical down shot 
boilers are used.
 A heat engine is one that 
converts heat energy into 
mechanical energy. Steam 
turbines are used as are in 
industry for several 
critical purposes: to 
generate electricity by 
driving an electric 
generator and to drive 
equipment such as 
compressors, fans, and 
pumps. The main turbine 
used in BBGS is a tandem 
compounded,three 
cylinder one.
 The condenser is a major component of the 
power plant system. It receives exhaust steam 
from the last stage of a turbine and condenses 
it to water for reuse as feed water in the boiler 
system. For large utility turbines that have a 
design incorporating high-, intermediate-, and 
low-pressure sections, the exhaust steam comes 
from the low-pressure section of the turbine.
1. A direct contact type of condenser, where the cooling 
water is sprayed directly into the exhaust steam from 
the turbine, and the mixture of the water with the 
steam condenses the steam. 
2. A surface condenser, in which the cooling water and 
exhaust steam remain separate. The vast majority of 
power plants use the water cooled surface condenser.
 3.Air-cooled condensers are used primarily when 
water availability is a problem. They are also used to 
meet the requirements for the discharge of water 
where so-called zero-discharge facilities are necessary. 
They also are used in areas where vapor plumes 
associated with cooling towers are to be eliminated.
 In BBGS,closed loop system is used for heat 
rejecton. Heat is rejected to the atmosphere 
through the use of a cooling tower .
 In wet cooling tower systems, 
cooling water is circulated 
through the condenser and 
absorbs heat from the exhaust 
steam from the turbine. The 
heated cooling water is then 
circulated through a cooling 
tower, where the absorbed heat 
is rejected to the atmosphere by 
the evaporation of some of the 
circulating water. The cooled 
water is then returned to the 
condenser by a circulating water 
pump.Makeup water must be 
provided to replace the water 
lost during evaporation and 
during blowdown, where 
contaminants are controlled.
The cooling tower therefore performs the 
following major functions: 
1. Removes the heat that the cooling water 
absorbed in the condenser. 
2. Minimizes the use of cooling water. 
3. Provides cooling water to the condenser to 
obtain high plant thermal efficiency.
 The Coal Handling Plant has been designed for 
supplying coal to both the units of 250 MW each. 
Two (2) parallel conveyor streams, one working 
and one standby, each of 960 MTPH design 
capacity have been provided in the Coal Handling 
System. 
 Arrangements have been made for unloading of 
wagons in the yard either in Wagon Tippler 
Hoppers thru' Wagon Tipplers or In the Track 
Hoppers thru' bottom discharge wagons.
 For a coal fired unit the ash generated after 
burning of coal is broadly divided into three types. 
The heaviest part, clinker etc. are collected in 
Furnace bottom that is at Bottom Ash Furnace 
Hopper. Rest of the ash, called Fly ash, is carried 
away by flue gas, of which the coarser ash is 
collected in Economiser Hoppers and Air Heater 
Hoppers. Finer ash is further carried by flue gas to 
Electrostatic Precipitator, where Ash is separated 
from flue gas by imparting negative electrical 
charge to ash particles and then collecting at 
positive plate. Subsequently this ash is dislodged 
from positive plate by wrapping the plate 
Dislodged ash is collected in ESP Hoppers.
 This huge ash thus collected at various hoppers needs a 
system for disposal. The system incorporated here is 
wet system for Bottom-Ash removal & dry system for 
Fly-Ash collection & removal. In other words the 
bottom ash is to be hydraulically conveyed in the form 
of slurry from the bottom ash hopper directly upto the 
Dewatering Bins the Ash Tank while the Fly Ash is to 
be pneumatically conveyed in dry state upto the 
intermediate Surge Hoppers and there from to Final 
Storage Silos. Ultimate disposal of both types of ash is 
to be by means of road trucks.
 The vacational training has been organized by the 
CESC limited and has been undertaken at the BUDGE 
BUDGE GENERATING STATION. The purpose of the 
vacational training is to get an industrial exposure in 
our engineering career. 
 Students can learn a lot from different books about 
various subjects such as operations of a plant, various 
constituents of a plant, power production, power 
distribution etc. but a practical experience helps in 
better understanding and enhancement of knowledge 
in various subjects. I am grateful to CESC limited for 
organizing this vacational training.
project

Más contenido relacionado

La actualidad más candente

TENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIA
TENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIATENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIA
TENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIA
Avinash Kumar
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
AKHILESH KUMAR
 

La actualidad más candente (20)

GANESH KUMAR RAM PPT ON TTPS LALPANIA
GANESH KUMAR RAM PPT ON TTPS LALPANIAGANESH KUMAR RAM PPT ON TTPS LALPANIA
GANESH KUMAR RAM PPT ON TTPS LALPANIA
 
TENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIA
TENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIATENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIA
TENUGHAT THERMAL POWER STATION, T.T.P.S. LALPANIA
 
TTPS
TTPSTTPS
TTPS
 
thermal power station
thermal power stationthermal power station
thermal power station
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
 
NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
 
Dev
DevDev
Dev
 
project -2
project -2project -2
project -2
 
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHARKBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Overview of ntpc power plant
Overview of ntpc power plantOverview of ntpc power plant
Overview of ntpc power plant
 
Kota Super Thermal Power Plant
Kota Super Thermal Power PlantKota Super Thermal Power Plant
Kota Super Thermal Power Plant
 
ppt by amit 5 from iet lko
ppt by amit 5 from iet lkoppt by amit 5 from iet lko
ppt by amit 5 from iet lko
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivank
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
 
K.s.t.p.s. ppt
K.s.t.p.s.  pptK.s.t.p.s.  ppt
K.s.t.p.s. ppt
 

Destacado (9)

CESC_cert
CESC_certCESC_cert
CESC_cert
 
UNMESH 2015 modified Presentation
UNMESH 2015 modified PresentationUNMESH 2015 modified Presentation
UNMESH 2015 modified Presentation
 
Cesc Intro English
Cesc Intro   EnglishCesc Intro   English
Cesc Intro English
 
CESC Report
CESC ReportCESC Report
CESC Report
 
Cesc
CescCesc
Cesc
 
Cesc limited
Cesc limitedCesc limited
Cesc limited
 
CESC LTD PPT ON STRATEGIC MANAGEMENT
CESC LTD PPT ON STRATEGIC MANAGEMENTCESC LTD PPT ON STRATEGIC MANAGEMENT
CESC LTD PPT ON STRATEGIC MANAGEMENT
 
ProjectReport
ProjectReportProjectReport
ProjectReport
 
Training and development ppt
Training and development pptTraining and development ppt
Training and development ppt
 

Similar a project

A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical only
Shobhan Biswas
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-report
Anil Saharan
 
Introduction
IntroductionIntroduction
Introduction
mittal434
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power station
Ashish Agarwal
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
arvind singh rathore
 
power plant. engineering for btech mechanical
power plant. engineering for btech mechanicalpower plant. engineering for btech mechanical
power plant. engineering for btech mechanical
ashokpradhan23
 
Coal power plant
Coal power plantCoal power plant
Coal power plant
Anum Mairaj
 

Similar a project (20)

MEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORTMEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORT
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVC
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical only
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-report
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
Identification of fuel pipe and steam pipe(Thermal Power plant Muzafarghar )
 
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
Identification of fuel pipe and steam pipe(thermal power plant Muzafargha)
 
Kota super thermal power plant training report
Kota super thermal power plant training reportKota super thermal power plant training report
Kota super thermal power plant training report
 
Introduction
IntroductionIntroduction
Introduction
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training report
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2Principles of Power Systems V.K Mehta Complete Book - Chapter 2
Principles of Power Systems V.K Mehta Complete Book - Chapter 2
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power station
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
power plant. engineering for btech mechanical
power plant. engineering for btech mechanicalpower plant. engineering for btech mechanical
power plant. engineering for btech mechanical
 
DPL Vocational Training Report
DPL Vocational Training ReportDPL Vocational Training Report
DPL Vocational Training Report
 
Mejia Thermal power Station(Seminar)
Mejia Thermal power Station(Seminar)Mejia Thermal power Station(Seminar)
Mejia Thermal power Station(Seminar)
 
Pm ppt
Pm pptPm ppt
Pm ppt
 
Coal power plant
Coal power plantCoal power plant
Coal power plant
 

project

  • 1.
  • 2.
  • 3.  The Calcutta Electric Supply Corporation or CESC supplies electricity to area under the Kolkata municipal corporation in the city of Kolkata, India, mainly but also few areas of Howrah, Hooghly, 24 Parganas (North) and 24 Parganas (South) districts of West Bengal, India.  The CESC limited supplies electricity to approximately 2.4 millon consumers. The total generation capacity stands out at 1025 MW from the four generating power plants. It has four generating stations namely 1. New Cossipore, commissioned at 1949 with an installed capacity of 100 MW. 2. Titagarh, commissioned at 1983 with an installed capacity of 240 MW. 3. Southern, commissioned at 1991 with an installed capacity of 135 MW. 4. BBGS, commissioned at 1997 with an installed capacity of 750 MW.
  • 4.  The Budge Budge generating station(BBGS) is a state of the art facility which has won several awards and accolades for its environmental friendly way of producing current. It is located in Pujali,Budge Budge,24 PGS(S),West Bengal. The Budge Budge generating station is a state of the art facility which has won several awards and accolades for its environmental friendly way of producing current.
  • 5.  The capacity stands out at 750 MW out of three units of 250 MW each .Power is generated at 16.5 kV and is stepped up to a voltage of 132 kV(unit 1&2) and 220 Kv(unit 3) in a generator transformer for onward transmission to the system.
  • 6.
  • 7. The following two departments give us the technical details about budge budge generating station. OPERATIONS DEPARTMENT- The Department of operations at the Budge Budge generating station is responsible for monitoring and issuing remote commands in case of manual mode of operation to various components like boiler,turbine,condensors etc for a smooth running of the power plant. FUEL AND ASH DEPARTMENT- The department of fuel and ash operations oversees the entire process of coal unloading, moving it to the stack yard and as well as the effective elimination of fly as well as bottom ash. A majority of the fly ash is at present exported to Bangladesh though barges for use in their cement plants.
  • 8.
  • 9.  A boiler (or steam generator, as it is commonly called) is a closed vessel in which water, under pressure, is transformed into steam by the application of heat.In BBGS,vertical down shot boilers are used.
  • 10.  A heat engine is one that converts heat energy into mechanical energy. Steam turbines are used as are in industry for several critical purposes: to generate electricity by driving an electric generator and to drive equipment such as compressors, fans, and pumps. The main turbine used in BBGS is a tandem compounded,three cylinder one.
  • 11.  The condenser is a major component of the power plant system. It receives exhaust steam from the last stage of a turbine and condenses it to water for reuse as feed water in the boiler system. For large utility turbines that have a design incorporating high-, intermediate-, and low-pressure sections, the exhaust steam comes from the low-pressure section of the turbine.
  • 12. 1. A direct contact type of condenser, where the cooling water is sprayed directly into the exhaust steam from the turbine, and the mixture of the water with the steam condenses the steam. 2. A surface condenser, in which the cooling water and exhaust steam remain separate. The vast majority of power plants use the water cooled surface condenser.
  • 13.  3.Air-cooled condensers are used primarily when water availability is a problem. They are also used to meet the requirements for the discharge of water where so-called zero-discharge facilities are necessary. They also are used in areas where vapor plumes associated with cooling towers are to be eliminated.
  • 14.  In BBGS,closed loop system is used for heat rejecton. Heat is rejected to the atmosphere through the use of a cooling tower .
  • 15.  In wet cooling tower systems, cooling water is circulated through the condenser and absorbs heat from the exhaust steam from the turbine. The heated cooling water is then circulated through a cooling tower, where the absorbed heat is rejected to the atmosphere by the evaporation of some of the circulating water. The cooled water is then returned to the condenser by a circulating water pump.Makeup water must be provided to replace the water lost during evaporation and during blowdown, where contaminants are controlled.
  • 16. The cooling tower therefore performs the following major functions: 1. Removes the heat that the cooling water absorbed in the condenser. 2. Minimizes the use of cooling water. 3. Provides cooling water to the condenser to obtain high plant thermal efficiency.
  • 17.
  • 18.  The Coal Handling Plant has been designed for supplying coal to both the units of 250 MW each. Two (2) parallel conveyor streams, one working and one standby, each of 960 MTPH design capacity have been provided in the Coal Handling System.  Arrangements have been made for unloading of wagons in the yard either in Wagon Tippler Hoppers thru' Wagon Tipplers or In the Track Hoppers thru' bottom discharge wagons.
  • 19.
  • 20.  For a coal fired unit the ash generated after burning of coal is broadly divided into three types. The heaviest part, clinker etc. are collected in Furnace bottom that is at Bottom Ash Furnace Hopper. Rest of the ash, called Fly ash, is carried away by flue gas, of which the coarser ash is collected in Economiser Hoppers and Air Heater Hoppers. Finer ash is further carried by flue gas to Electrostatic Precipitator, where Ash is separated from flue gas by imparting negative electrical charge to ash particles and then collecting at positive plate. Subsequently this ash is dislodged from positive plate by wrapping the plate Dislodged ash is collected in ESP Hoppers.
  • 21.  This huge ash thus collected at various hoppers needs a system for disposal. The system incorporated here is wet system for Bottom-Ash removal & dry system for Fly-Ash collection & removal. In other words the bottom ash is to be hydraulically conveyed in the form of slurry from the bottom ash hopper directly upto the Dewatering Bins the Ash Tank while the Fly Ash is to be pneumatically conveyed in dry state upto the intermediate Surge Hoppers and there from to Final Storage Silos. Ultimate disposal of both types of ash is to be by means of road trucks.
  • 22.  The vacational training has been organized by the CESC limited and has been undertaken at the BUDGE BUDGE GENERATING STATION. The purpose of the vacational training is to get an industrial exposure in our engineering career.  Students can learn a lot from different books about various subjects such as operations of a plant, various constituents of a plant, power production, power distribution etc. but a practical experience helps in better understanding and enhancement of knowledge in various subjects. I am grateful to CESC limited for organizing this vacational training.