SlideShare una empresa de Scribd logo
1 de 25
Descargar para leer sin conexión
Former NAS Moffett Field


Hangar 1 Removal Action Update

        Bryce Bartelma, PG
       Navy BRAC PMO West

        November 3, 2011
          RAB Meeting




               1
Presentation Overview



• Project Objective
• Progress Update
    Continued Monitoring            Roof, Redwood, Siding &
     and Protection                   Window Removal
     Measures                        Coating Inspections &
    Historic Mitigation/CARP         Touch-ups
    Scaffolding Installation        Moving Scaffolding
• Schedule
• Questions



                                2
Project Objective




• Control release of PCBs from Hangar 1 in accordance
  with EE/CA (July 2008) and Action Memorandum
  (December 2008)
    Demolition of interior structures
    Removal of contaminated siding
    Application of weather-resistant coating to steel frame




                             3
Continued Monitoring and
                Protection Measures

• No observed impacts to biological
  activity
• Continued storm water and ground
  surface protection
• Navy and NASA air monitoring data
  demonstrates control of air emissions




                            4
EPA and Water Board Site Inspection




                5
Hangar 1 Interactive CD



• Delay in final production. CD will contain interactive
  history and interviews but not 3-D tour.

• Navy and NASA
  looking into a web
  based version that
  will be hosted by
  NASA website and
  will contain both the
  interactive materials
  and 3-D tour!


                             6
Continued Mansard Panel Removal




              7
Continued Redwood Removal




            8
Continued Silver Siding Removal
  (Robertson Protected Metal)




              9
Window and Door Removal




           10
Zone 1 Exterior Coating & Touch-ups



                     • Use of man lifts for
                       lower level touch-ups




                11
Zone 2 East Progress – September 7




                12
Zone 2 East Progress – September 20




                13
Zone 2 East Progress – October 12




               14
Zone 2 West Progress – September 6




                15
Zone 2 West Progress – October 3




               16
Zone 2 West Progress – October 12




               17
Removing Scaffolding in Zone 1




              18
Interior View




     19
Installing Systems Scaffolding
   & Quick Deck in Zone 6




              20
Clam Shell Door Mechanisms




            21
Fiber Board Removal




• Fiber boards surround
  tracks of Clam Shell doors
• Recently sampled and
  determined to contain
  contamination
• Not structural
• Navy to remove boards
  but keep rails in-place
• NASA to consider
  replacement in re-use


                               22
Special Visitor at Moffett




            23
Schedule




• Fieldwork in zones 1 – 6
  Ongoing
• Complete fieldwork,
  confirmation sampling
  and demobilize
  Spring/Summer 2012
• Submit After Action
  Completion Report
  Summer/Fall 2012



                             24
Questions?




             Point of Contact:

               Scott Anderson
            BRAC Environmental
                  Coordinator
               (619) 532-0938
         scott.d.anderson@navy.mil



    25

Más contenido relacionado

La actualidad más candente

Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportHonolulu Civil Beat
 
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...TRC Companies, Inc.
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress reportHonolulu Civil Beat
 
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...TRC Companies, Inc.
 
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Niels Asjee
 
Remediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM conceptsRemediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM conceptsPeter Gringinger
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 

La actualidad más candente (9)

Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily Report
 
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
 
Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...
Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...
Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress report
 
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
 
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
 
Remediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM conceptsRemediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM concepts
 
The glaciation of the North Sea Basin and its implications for Carbon Capture...
The glaciation of the North Sea Basin and its implications for Carbon Capture...The glaciation of the North Sea Basin and its implications for Carbon Capture...
The glaciation of the North Sea Basin and its implications for Carbon Capture...
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 

Destacado

Navy Updates March Rab
Navy Updates March RabNavy Updates March Rab
Navy Updates March RabSteve Williams
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewSteve Williams
 
NASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldNASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldSteve Williams
 
In Search Of East Internet Company
In Search Of East Internet CompanyIn Search Of East Internet Company
In Search Of East Internet CompanyPrashant Singh
 
EPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationEPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationSteve Williams
 
NASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardNASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardSteve Williams
 
Moffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanMoffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanSteve Williams
 
Moffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateMoffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateSteve Williams
 

Destacado (8)

Navy Updates March Rab
Navy Updates March RabNavy Updates March Rab
Navy Updates March Rab
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year Review
 
NASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldNASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett Field
 
In Search Of East Internet Company
In Search Of East Internet CompanyIn Search Of East Internet Company
In Search Of East Internet Company
 
EPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationEPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source Investigation
 
NASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardNASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory Board
 
Moffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanMoffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management Plan
 
Moffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateMoffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area Update
 

Similar a Moffett Hangar One Removal Action Update

Hangar One Update to Moffett RAB
Hangar One Update to Moffett RABHangar One Update to Moffett RAB
Hangar One Update to Moffett RABSteve Williams
 
Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012Steve Williams
 
Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012Steve Williams
 
Moffett RAB Hangar One Update
Moffett RAB Hangar One UpdateMoffett RAB Hangar One Update
Moffett RAB Hangar One UpdateSteve Williams
 
Hangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RABHangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RABSteve Williams
 
Moffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionMoffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionSteve Williams
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Jacobs Engineering
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6James AH Campbell
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Fairfax County
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)DC Department of General Services
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 UpdateSteve Williams
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityFairfax County
 
Structural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docxStructural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docxcpatriciarpatricia
 
01 jt twisting super tower project
01 jt   twisting super tower project01 jt   twisting super tower project
01 jt twisting super tower projectsucreargentina
 
Soil investigation by AURANGZEB
Soil investigation by AURANGZEBSoil investigation by AURANGZEB
Soil investigation by AURANGZEBAURANGZEB442
 

Similar a Moffett Hangar One Removal Action Update (20)

Hangar One Update to Moffett RAB
Hangar One Update to Moffett RABHangar One Update to Moffett RAB
Hangar One Update to Moffett RAB
 
Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012
 
Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012
 
Moffett RAB Hangar One Update
Moffett RAB Hangar One UpdateMoffett RAB Hangar One Update
Moffett RAB Hangar One Update
 
Hangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RABHangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RAB
 
Moffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionMoffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal Action
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 Update
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 
Structural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docxStructural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docx
 
01 jt twisting super tower project
01 jt   twisting super tower project01 jt   twisting super tower project
01 jt twisting super tower project
 
lecture2 site investigation
lecture2   site investigationlecture2   site investigation
lecture2 site investigation
 
SOTC_2016_RMJ_SurveyingChallenges
SOTC_2016_RMJ_SurveyingChallengesSOTC_2016_RMJ_SurveyingChallenges
SOTC_2016_RMJ_SurveyingChallenges
 
Soil investigation by AURANGZEB
Soil investigation by AURANGZEBSoil investigation by AURANGZEB
Soil investigation by AURANGZEB
 
Aoc sediment update_part2
Aoc sediment update_part2Aoc sediment update_part2
Aoc sediment update_part2
 

Más de Steve Williams

RAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationRAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationSteve Williams
 
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28Steve Williams
 
RAB Community Presentation
RAB Community PresentationRAB Community Presentation
RAB Community PresentationSteve Williams
 
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Steve Williams
 
Orion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentOrion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentSteve Williams
 
Epa vi and source investigation rab mtg update august 7 2014rv1
Epa vi  and source investigation rab mtg update    august 7 2014rv1Epa vi  and source investigation rab mtg update    august 7 2014rv1
Epa vi and source investigation rab mtg update august 7 2014rv1Steve Williams
 
Moffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateMoffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateSteve Williams
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateSteve Williams
 
Moffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesMoffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesSteve Williams
 
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013Steve Williams
 
Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Steve Williams
 
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...Steve Williams
 
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesHazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesSteve Williams
 
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Steve Williams
 
Site 28 Supplemental Investigation
Site 28 Supplemental InvestigationSite 28 Supplemental Investigation
Site 28 Supplemental InvestigationSteve Williams
 
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion UpdateMoffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion UpdateSteve Williams
 
Laser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs MonitoringLaser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs MonitoringSteve Williams
 
Site 25 rab nov 29 2012
Site 25 rab nov 29 2012Site 25 rab nov 29 2012
Site 25 rab nov 29 2012Steve Williams
 
Moffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion UpdateMoffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion UpdateSteve Williams
 

Más de Steve Williams (20)

RAB NASA Update
RAB NASA UpdateRAB NASA Update
RAB NASA Update
 
RAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationRAB Vapor Intrusion Mitigation
RAB Vapor Intrusion Mitigation
 
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
 
RAB Community Presentation
RAB Community PresentationRAB Community Presentation
RAB Community Presentation
 
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
 
Orion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentOrion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume Assessment
 
Epa vi and source investigation rab mtg update august 7 2014rv1
Epa vi  and source investigation rab mtg update    august 7 2014rv1Epa vi  and source investigation rab mtg update    august 7 2014rv1
Epa vi and source investigation rab mtg update august 7 2014rv1
 
Moffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateMoffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion Update
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion Update
 
Moffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesMoffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental Activities
 
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
 
Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013
 
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
 
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesHazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
 
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
 
Site 28 Supplemental Investigation
Site 28 Supplemental InvestigationSite 28 Supplemental Investigation
Site 28 Supplemental Investigation
 
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion UpdateMoffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
 
Laser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs MonitoringLaser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs Monitoring
 
Site 25 rab nov 29 2012
Site 25 rab nov 29 2012Site 25 rab nov 29 2012
Site 25 rab nov 29 2012
 
Moffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion UpdateMoffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion Update
 

Último

Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 

Último (20)

Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 

Moffett Hangar One Removal Action Update

  • 1. Former NAS Moffett Field Hangar 1 Removal Action Update Bryce Bartelma, PG Navy BRAC PMO West November 3, 2011 RAB Meeting 1
  • 2. Presentation Overview • Project Objective • Progress Update  Continued Monitoring  Roof, Redwood, Siding & and Protection Window Removal Measures  Coating Inspections &  Historic Mitigation/CARP Touch-ups  Scaffolding Installation  Moving Scaffolding • Schedule • Questions 2
  • 3. Project Objective • Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)  Demolition of interior structures  Removal of contaminated siding  Application of weather-resistant coating to steel frame 3
  • 4. Continued Monitoring and Protection Measures • No observed impacts to biological activity • Continued storm water and ground surface protection • Navy and NASA air monitoring data demonstrates control of air emissions 4
  • 5. EPA and Water Board Site Inspection 5
  • 6. Hangar 1 Interactive CD • Delay in final production. CD will contain interactive history and interviews but not 3-D tour. • Navy and NASA looking into a web based version that will be hosted by NASA website and will contain both the interactive materials and 3-D tour! 6
  • 9. Continued Silver Siding Removal (Robertson Protected Metal) 9
  • 10. Window and Door Removal 10
  • 11. Zone 1 Exterior Coating & Touch-ups • Use of man lifts for lower level touch-ups 11
  • 12. Zone 2 East Progress – September 7 12
  • 13. Zone 2 East Progress – September 20 13
  • 14. Zone 2 East Progress – October 12 14
  • 15. Zone 2 West Progress – September 6 15
  • 16. Zone 2 West Progress – October 3 16
  • 17. Zone 2 West Progress – October 12 17
  • 20. Installing Systems Scaffolding & Quick Deck in Zone 6 20
  • 21. Clam Shell Door Mechanisms 21
  • 22. Fiber Board Removal • Fiber boards surround tracks of Clam Shell doors • Recently sampled and determined to contain contamination • Not structural • Navy to remove boards but keep rails in-place • NASA to consider replacement in re-use 22
  • 23. Special Visitor at Moffett 23
  • 24. Schedule • Fieldwork in zones 1 – 6 Ongoing • Complete fieldwork, confirmation sampling and demobilize Spring/Summer 2012 • Submit After Action Completion Report Summer/Fall 2012 24
  • 25. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 25