SlideShare una empresa de Scribd logo
1 de 60
CONCEPT OF

OC MINE PLANNING &

      DESIGN
Mining Methods
• Coal is mined by two main methods -
  Surface or ‘opencast’ mining and
  underground mining.
• The choice of method is largely determined
  by the depth,thickness and no. of coal
  seams, geology of the coal deposit and
  other factors.
Mining Methods
Shaft Mine    Incline Mine




                                 Incline




                                 Excavator



Adit Mine        Opencast Mine
Ideal conditions for Opencast Mining

1.   Thickness of coal seams       -      > 5m
1.   Flat gradient                 -      < 1 in 6
1.   Strike length                 -      > 1 km
1.   No.of seams                   -      Less the better, with
                                          higher thickness
5.   Coal without stone bands
6.   Free from surface structures / features.
7.   Preferably non-forest land.
8.   Availability of adequate place for dumping.
9.   Stripping ratio depending on quality of the coal
General planning studies
           No fixed procedure – country-wise differences

1.   Conceptual study, data reliable upto            --   75%

                      Review

2.   Pre-feasibility study - data reliable upto      -    80%
          Additional data, modify
      prepare, management acceptance

3.   Feasibility Report/DPR - data reliable upto     -    85-90%

4.   Detailed designing LTP/MTP - data reliability   -    95%

5.   Operational planning (STP)                      -    -
Basis for the initial study is Geological Report

• There will be some overlap between various studies/reports.

• Every step deals with Mining Technology, equipment, production
scheduling, capital cost, revenue cost, internal rate of return, dispatches etc.
However the degree of accuracy of data on the above aspects increases with
each step.

• Generally After F.R. approval, there is need to go in for long term planning,
medium term planning (about 5 years) and S.T.P. Short-term planning (6
months – one year).

•These reports should adapt circular analysis approach by considering
various aspects like additional information available while operating the mine,
slippages occurred, reserves, pit-slopes, pit-limits, pit scheduling to control
faster rate of extraction from coal inventory which otherwise may lead to
reduction in coal production in subsequent years or more equipment for
higher OB removal to maintain targeted production.
CONCEPTUAL MINE PLANNING / PRE-FEASIBILITY

   Deposit                   Tech-Aspects                   Economic aspects


Resources                                                   Production requirements
GR/MR                         Mining
                              Technology                    Minelife requirements
Mining depth                                                Logistics,
Strata Sequa                  Options and
                              Suggestions                   Roads etc.
Thickness of
- coal                                                      Cash out flow
- waste                       Equipment
                                                            Cash inflow
- inter burden                                              Required rate of
Coal Quality                  Surface
                              Constraints                   Return
Slope stability                                             Cut-off SR
Water


                          Conceptual Mine Plan
                        (Open pit layout, equipment)

                          Modification of concept
                          and or optimization

                           Pre-Feasibility Study
           Accepted –       Management                 Not accepted –
           DPR                                         New attempt
Steps in design of Opencast

A. Study of deposit exploration (GR)
B. Final pit limits.
C. Development sequence.
D. Design of Access Ramp and Haul Roads
E. Pit design
F. Annual production capacity – system availability – Mining
   technology
G. Main Mining Equipment – Matching to Mining Plan
H. Optimizing Dumping strategy and balancing
I. Year-wise / stage – wise plans
J. Financial viability (Capital & Revenue)
K. Coal Washing
L. Environment stipulations
A. Study of GR on the deposit Exploration
    Salient Information
•   Extent of deposit i.e. strike and dip rise widths.
•   Geology – Geological succession, sequence of beds, drilling, logging, no. of
    seams, sequence of coal seams, description.
•   Inter seam partings.
•   Structure – No. of faults, Throws, dip of seams and beds
•   Reserves – Quality wise/seam wise/depth-wise etc. based on Block model,
    Gridded seam model & polygonal Model
•   O.B. volumes & S.R. – Sector-wise, depth-wise etc.
•   Coal seam analysis, proximate and ultimate , Ash etc. & OB strata hardness etc.
•   Drilling details (Lithology)
•   Physiography
•   Climate and Vegetation
•   Preliminary EMP information
A. Contd.
    PLATES

•   Location Map, Top Sheet map, Roads, Lands (Forests), Rivers etc.
•   Topography – Hills, contours, rivers of Flats
•    Geological Map – in crops, Faults
•    Graphic Lithologs
•    Graphic correlation charts
•    Floor/Roof contour plans of all seams
•    Seam folio plans of all seams (seam out cop, floor contours, faults,
    isograde, isochore, iso depth).
•    Geological cross sections
•    Seam structure of all seams
•    ISO parting plans
•    ISO excavation plan for lower seam (surface constraints, boundaries,
    faults at seam level, excavation area)
A. Contd.,

  Additional Data required -
-Geo-technical data – diggability of materials, slope geometry and stability of
                      Working/permanent slopes, spoil pile configuration
                      for outside/inside dump, stability, grainsizes after
                      blasting etc.

-Ground Water        – Dewatering and depressurization
 hydrology            - Impact of dewatering on surrounding areas
                      - Impact on water quality

-Surface hydrology - Water quality
                   - make off water
                   - Mine flood protection
                   - Options for discharge of dirty water and various
                     discharge systems.
B. Final pit limits

 The criteria for delineation of boundaries of an Opencast Project are:

Rise side boundary         - Usually incrop of the bottom most seam

Lateral sides              - Usually by Geological disturbances like faults,
                                       surface structures / features like nalah,
river etc                   or limitation of the strike length of the deposits.

Dip side                   - Depends on the economical stripping ratio,in
                                    absence of natural constraints
B Contd.
B. Final pit limits
 Final Pit limits
 Haul analysis
 Lead,lift increase cost – decides mode of transport
                               Dump area 100m from mine boundary
 Dump limits available are Dump area          50 m from internal access road.
                               Dump area 80-100 m. from mine
                                                           infrastructure
 OB volumes            - Final slopes
 Mineable Reserves – various losses, batter, barrier etc.
                      - dilution etc (0-1 m against Roof,floor)
 Maximum depth increases haul cost (30-40% of total cost at 1 1/2 Km lead.

Boundaries are drawn as above & Coal, OB ,SR are estimated
B. Final pit limits                                             B Contd.

Estimation of Coal, OB & Stripping ratio
Rough assessment is given below
•   Assuming Pit slopes of 450, the Quarry floor and Quarry surface are
   delineated

•    Volume of Coal & OB       = Average area x Average depth           - (A)

•    Average area     = (Quarry surface area + Quarry floor area) / 2

•    Average depth    = (Minimum depth + maximum depth) / 2

•    Volume of Coal=(Quarry floor area x Cumulative thickness of all coal
    seams) - (B)

•    Coal in tonnes            = Volume of coal x Specific gravity – (C)

•    OB Volume        = Coal + OB Volume (A) – Coal Volume (B) - (D)

•    Stripping ratio          = OB Volume (D) / Coal in tones (C)
 For accurate S.R,the volumes of OB and coal are to be made seam wise
B Contd.
 B. Final pit limits
The boundaries are firmed up based on the economic stripping ratio.
  Economic stripping ratio varies with:

      • Average sales realization i.e. higher the quality of coal,
        higher the realization.
      • Capital investment requirements
      • Operating cost.
      • Also surface constraints
 The following thumb rules may be of some Help (with outsourcing OB removal):

   Projects are likely to be economically viable upto a maximum SR indicated
   against the grade of coal
                          Grade       Stripping ratio
                                         (Cum/T)
                            F               6
                            E               7
                            D               8
                            C               10
C. Development Sequence
-Opening the deposit – Access trench
-Box cut – To accommodate all equipment
-Mine phases – Depends on the shape of the property
-Progress of Benches
-Coal production schedules
-OB excavation schedules
Note:- Maximize inventory of coal in the initial years
      -Differ OB stripping requirements as much as possible – Average
      SR versus natural SR
      -Income generated in the first 5 to 10 years but not remote
       economics will either make or break the project.
      -Profits for in the future have practically no impact on the project NPV.
      Each successive phase will be less profitable and the ultimate
      limit will be loss even after ploughing in earlier profits.
D. Design of Access Ramp & Haul roads

    Location of Access ramp is guided by the following:

        1)   Generally located at the minimum depth of incrop of bottom most
             seam – So as to reduce initial waste stripping (unproductive work)

        2)   Should facilitate maximizing of internal dumping and sectional
             working.

        3)   Should be near the External dump / Coal yard / Mine service
             facilities etc.
        4)   Main haul road upto the pit limit should be planned in the
             beginning only.
        5)   Since haul costs constitute about more than 40% and tyre costs
             about 10% of the total mining costs,priority for design,construction
             and maintenance should be given.
        6)   Gradient,width,drainage,curves,super elevation,base,sub
             base,type and thickness of top dressing should be like that of
             national high ways for heavy traffic.
D Contd.
D. Design of Access Ramp & Haul roads
     Haul roads

    Sl.No   Particulars


     1      Width                  Should facilities two way traffic, dozer
                                   movement, formation of drains, lighting
                                   arrangement (Normal width – 30m,but
                                   depends on capacity of dumpers).
     2      Gradient               1 in 16 Short ramps 1 in 10
     3      Lesser number of
            curves
     4      In flat seams of       haul roads can be formed over the floor of
            larger strike length   the seam
     5      In steep seams         Haul road for Coal & OB benches can be
                                   planned along highwall slopes say every
                                   30m. This will also facilitate internal dumping.
E. Pit design.

General design parameters and planning data

• Density of seams, total coal column thickness
•Thickness of partings
• Gradient
• Geological disturbances
• Strike lengths, shape of property
• Geological Reserves
• Surface constraints/adjacent habitat
• Dump yards availability with lead and lift
• Mining system, optimum mining concept
• Depth of operation, mineable reserves after various losses, OB volumes, SR
• Spoil characteristics
• Work practices in the Area
• Diggability characteristics
E Contd.
E. Pit design

    As per Regulation 98 of CMR 1957,

    In alluvial soil etc.    -   Sides shall be sloped at 450 or
                                 Benched – height not more than 1.5m
                                 Width – not less than height

    In hard ground           -   Sides adequately benched/sloped so as
                                 to prevent danger from fall of sides

    Coal                     -   Sides shall be sloped at 450 or
                                 Benched – height not more than 3m

    However, exemption can be sought from Inspectorate.
E Contd.
E. Pit design

      Overall slope of a pit depends on several factors of the pit slope:

      a)   Geological disturbances like faults etc.

      b)   Hydrological condition of strata

      c)   Orientation of slip planes

      d)   Nature of strata – i.e. hardness, material consolidation etc.

      e)   Depth of workings

      f)   Design of haul roads & ramps in the highwall

      g)    Stratigraphy – thickness, spacing of the clay bands or other weak
           layers
E. Pit design                                                      E Contd.
   In general for OC mines upto a depth of 200m, overall slope angle of 450 is
   permitted.
E Contd.
E. Pit design
   For deeper mines flatter highwall slopes will be necessary from safety point of
   view (for 35 T dumpers & above)
E. Pit design                                                        E Contd.

   For deeper mines flatter highwall slopes will be necessary from safety point of
   view (dumpers below 35T capacity)
E Contd.
E. Pit design
      Typical High wall layout
E Contd.
E. Pit design
     Working benches:

     1) General
     Width        - 40 – 45m
     Height       - Generally equal to height of the boom or in some cases
                    upto 3m above the boom height.
                     In case of Backhoe – digging height of machine
     Bench slope - 560 to 700

     2) Dragline:
     Width of the cut   -      60m
     Height of bench    -      maximum digging depth

     3) In order to even out the yearly OB removal quantities and the
          economics sometimes alternative workings and non-working benches
          (around 25 m wide) are proposed.
F. Fixing annual production capacity
After defining the boundaries, the annual production capacity will be fixed
based on the following criteria :

1)   The available mineable coal reserves

2)   Geometry of the deposit -      Strike & dip rise lengths

3)   Structure of the deposit -     Thickness of seams, partings, faults,
                                  gradient etc.

4) Linkage                   -    Basket, Captive use etc.

5) HEMM configuration       -     Capacity of HEMM.

6) Surface structures        -      Limits the material to be blasted.
F Contd.
Excavator machine productivity –
Based on ,
-Dipper cycle time
-Waiting time for truck spotting
-Bad blast factor
-Truck loading time etc.
Annual capacity is based on
-Equipment available hours
-Utilization percentage
Proper fragmentation,less throw off material,bench
height,bench slopes ,avoiding toes and secondary
blasting,improves shovel efficiency
Optimum fragmentation-cost of drilling,blasting vis-
à-vis cost of dozing,loading,hauling and dumping.
F Contd.


                  System availability as a function of individual components
Calendar hours-(365x24)                                (Figures are Indicative only)                                 8760



                                                                                       scheduled working
Holidays and bad weather                                 2.5%-                         hours(SSH)                    8463 / 6140



Operational delays-blasting, relocations,shift
change,Lunch etc                                         1 Hour/Shift(8%)




Preventive maintenance-i.e annual,weekly,daily,shift     15% of SSH                    Scheduled operating time or
wise and unexpected break downs                          Availabilty-       100%       Equipment available hours         6563/4390




Shovel,dumper system                                                            97%    Effective Operating Time          6366/3960
  12% - Crusher + 1 Conveyor                                                    85%    Effective Operating Time         5559/3730



              2% Drop for each Belt




                                                                               73%


                                                                                       System Availability           4804/3160
G. Main mining equipment
For Various Technologies

   1)   Shovel Dumper technology.

   2)   Dragline technology

   3)   Inpit Crusher – conveyor – spreader – technology.

   4)   Continuous Mining technology – Bucket wheel excavators.

   5)   Rock Breaker technology.

   6)   Surface Miner technology.
G Contd.

Note: In seam Mining is always practiced in flat seams while in case of
steep seams Horizon mining, with its disadavntages, may have to be followed.
G Contd.
G. Main mining equipment
1)Shovel dumper technology:

•   This is the most commonly used technology in Opencast mines.

•   Basically two variants – Rope shovels and Hydraulic shovels.

•   Shovel used for excavation & Dumper for transport of material.

•   Bucket capacities vary from 0.9 Cum to 40 Cum with matching
    Trucks/Dumpers of 16 Cum to more than 240 T.

•   Can be deployed for removal of varying thickness of materials.

•   Harder materials require blasting.

•   Can be deployed for removal of steep & thin seams (hydraulic shovels).
G. Main mining equipment                                               G Contd.

2)Draglines:
•    A dragline bucket system consists of a large bucket which is suspended from a
     boom with wire ropes.
•    Draglines are deployed wherever there is scope for side casting overburden
     above coal seam into the de-coaled area.
•    It is very cost effective technology & can be deployed in flatter seams.
3)In pit crusher conveyor technology:
• The drilled & blasted OB is loaded by shovels and transported by dumpers to
Crushers. The crushed OB is then transported by a series of conveyors into a
spreader for dumping.
•Can be used in steep seams where laying of transport roads for the trucks is difficult.
•While S.R indicates volumes,cut off ratio indicates depth and reflects in dumper
haulage cost,which increase with depth and may become prohibitive where in
alternative haulage system may have to thought off.
•Ideally suited where material has to be transported over a large distance & lift.
4)Continuous Miner Technology:- Bucket Wheel Excavators
•Presently being used in Neyvali, Lignite Opencast mines, having soft strata.
•The buck wheel excavates the material without blasting which is transported by a
series of belt conveyors to spreader.
G Contd.
G. Main mining equipment
     5)Rock breaker technology:

 •      Rock breaker technology can be applied for breaking of rock/coal/ore
        even about 500 kg/sq.cm.
 •      It can be used wherever it is not possible to go for blasting – near
        vicinity of structures and habitations.
     6)Surface Miner Technology:
     •Used for selective mining.
     •Larger strike length of about 600 m – 1000 m and widths of around
     300 m are ideally suited for surface miner.
     •Does not need drilling and blasting. The machine cuts the coal &
     loads into trucks for onward transportation to Surface
     Other common mining equipment to all the technologies
     •Drills
     •Dozers ,Graders & Compactors
     •Water Sprinklers
     •Pumps etc.
     •Electrical equipment
     •Crushers & Conveyors for Coal/OB
Rope Shovel & Dumper
Hydraulic Shovel & Dumper
An opencast mine with dragline
IN-PIT CRUSHER CONVEYOR TECHNOLOGY (Spreader in Operation)
Surface Miner
Rock breaker
H. Dumping strategy and balancing
   Internal dumping:

   Depends on the steepness of the seams.
   As the gradient increases, the percentage of dumping reduces.
   Internal dumping can be increased by sectorial working of the pit – which may
   reduce the annual output.
   Toe of the dump generally kept at a distance of 100 m from the working benches.
   Floor of the pit to be roughened by blasting for increasing dump stability.
  General design of dumps:
  • Deck height – 30m
  • Berm width – 30m
  • Deck slope – 37½0
  • Overall slope – 280
  • Swell factor for OB-1.38,for coal –1.40
  • Swell compact after initial settling – 1.20

  Note:-Dump yard management and control is essential for the success of open cast
  mining. In case of more than one External Dump yards, balancing the excavation
  volume to either of the dump yard should be based on lead & lift and size of the
  Dump yards.
H Contd.
H. Dumping strategy




                       1.    Total dump height- 90m
                      1.    Total dump height- 90m
                       2.    Deck height – 30m
                      2.    Deck height – 30m
                       3.    Berm width – 30m
                      3.    Berm width – 30m
                       4.    Deck slope-37 ½ 0
                      4.    Deck slope-37 ½ 0
                       5.    Overall slope-280
                      5.    Overall slope-280
H Contd.
H. Dumping strategy




                       1.    Total dump height- 90m
                      1.    Total dump height- 90m
                       2.    Deck height – 15m
                      2.    Deck height – 15m
                       3.    Berm width – 15m
                      3.    Berm width – 15m
                       4.    Deck slope-37 ½ 0
                      4.    Deck slope-37 ½ 0
                       5.    Overall slope-24.830
                      5.    Overall slope-24.830
H Contd.



Internal Dumping reduces with the increase in the gradient of the seam.


                       Comparison between 1in4 and 1in8 Gradient




         floor dipping at 1in4                              floor dipping at 1in8

      Assumptions:
      Strike Length                :   1000m
      Max. Depth                   :   110m
      Coal Seam thickness          :   15m
      Annual Rated capasity        :   6.0 LTPA



      Project Parameters               1in4          1in8
      Area of Excavation           :   0.59 Sq.km    1.04 Sq.km
      Mineable Reserves            :   90.0 L.T      180.L.T
      Total OB Removal             :   274.0 L.m3    480.5 L.m3
      Stripping Ratio              :   2.74          2.67
      Life of the Project          :   17 Years      32 Years
      Volume of Internal Dumping   :   39.85 L.m3    256.41 L.m3
      Volume of External Dumping   :   234.15 L.m3   134.00 L.m3
      % of Internal Dumping        :   14.54         53.36
      (upto Ground Level)
      Safe distance from coal bench
      to toe of internal dump       : 100m           50m
I. Designing the year-wise / stage – wise plans

    I) Stage plans
         •   Stage plans are prepared based on Year-wise production
             requirements (rated out put)

        •   Stage plans at the end of years – 1, 2, 3, 4, 5 & in intervals of 5
            years are prepared.

        •   Also plans are prepared where any specific land mark like a new
              box-cut, change in layout will take place.
J. Financial Viability

       1)   The requirement of HEMM & its capital is estimated.

       2)  Other capital like developmental works, CHP etc are worked
            out.
       3) Operating expenses are worked out to arrive at cost of
            production.
        4) Financial viability including profit & loss , IRR etc is
             estimated.
        5) Based on required IRR, anticipated selling price is also
             worked out.
K. Coal Washing
Need for Washing

Power Houses consume about 75% of coal.

Power Houses are designed to accept Coal of ‘E’ Grade & above
(UHV>3300).

The percentage of production of coal below ‘E’ Grade is increasing .

MoEF stipulation – Presently the onus of responsibility is on end user for
using Coal of not more than 34% ash if he is located over 1000Km away.

Hence, the need to upgrade coals below ‘E’ Grade so as to suit the
requirements of Power houses.

Cost of washing is around Rs 120-130/T of raw coal.
L. Environment stipulations

As per EP Act 1986


 “Environment”
 includes water, air and land and the inter-relationship
 which exists among and between water, air and land and
 human beings, other living creatures, plants, micro
 organism and property
L Contd.
         Impacts and Mitigative Measures
• Air
  – Impacts: Dust is generated from drilling, blasting,
    excavation, crushing and transportation operations. This
    dust becomes air borne and gets carried away to
    surrounding areas.
  – Mitigative Measures:
        • Extensive water spray arrangements at the Coal
          handling sites.
        • Wet-drilling methods are to be adopted.
        • Water spraying on haul roads and permanent transport
          routes at required frequencies. Provision for mobile
          water sprinklers has to be made for this purpose.
        • Extensive Green Belt development around the quarry
          and OB dump
        • Black topping the transport routes and avenue
          plantation on these roads.
Water spraying on the haul road
Continuous water spraying on the haul road
L Contd.
         Impacts and Mitigative Measures

• Water:
  – Impacts:
     • Pollution of the surface water bodies with the
         mine discharge water and domestic sewage.

  – Mitigative Measures:
    • The Mine Discharge water is to be treated in
         settling tanks before discharging it into the
         surface water bodies.
     •   Effluent from workshop is to be treated in ETPs.
     •   Sewerage treatment plant to be provided for
         treating the domestic sewage from the colony.
Photograph of STP
Treatment plant for Work shop effluent
Impacts and Mitigative Measures                   L Contd.

  Noise Pollution & Vibrations
• Impact
   −   The main sources of noise in the project are electrical and
       diesel-powered machines, compressors, pumps, drilling
       machines, dumpers, etc.
   −   During blasting operations blast vibrations will take place.

• Control Measures
   –   Controlled blasting techniques using NONELs are to be
       adopted .
   –   Creation of green belts of dense foliage in three rows
       between mine areas and residential colonies.
   –   Proper maintenance of machinery including transport
       vehicles.
   –   Protective devices like earplugs and earmuffs are to be
       provided to the needy workers.
   –   Sound and dust proof cabins are to be provided in the
       machines like dozers, shovels, dumpers and feeder
       breakers at CHP etc.
Impacts and Mitigative Measures             L Contd.

 Over Burden Management
 Topsoil excavated from the quarry is to be dumped
   separately at predetermined place and has to be
   subsequently spread on external dumps for plantation.
   Top soil dump is to be kept not more than 10m height.
   Top soil has to be vegetated with grasses and
    leguminous species to maintain its fertility.
   The reclamation of O.B dumps is to be done by using
    Biological Engineering techniques for stability of slopes
    and prevention of soil erosion from O.B dumps.
   Construction of crib structures, Gabion structures,
    forming of staggered Contour trenches are to be
    practiced for stability of slopes.
L Contd.
            Impacts and Mitigative Measures

Over Burden Management
   Raising of seedlings on both top and slopes of the dumps
    in the staggered contour trenches.

   By dibbling seeds of various species like Avisa, Subabool,
    Babul, Neem etc.

   Safe disposal of rainwater by construction of garland
    drains. Garland drains are to be provided around the
    quarry and overburden dumps .
Safe disposal of water from Top of OB
Thank you all,

Más contenido relacionado

La actualidad más candente

Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast mines
Anurag Jha
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2
IDHAMUKI
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
SATYANARAYANA I
 

La actualidad más candente (20)

Blasting Gallery Method
Blasting Gallery MethodBlasting Gallery Method
Blasting Gallery Method
 
Optimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast minesOptimization of Blasting Parameters in open cast mines
Optimization of Blasting Parameters in open cast mines
 
Mine planning
Mine planning Mine planning
Mine planning
 
SLOPE STABILITY AND FAILURE
SLOPE STABILITY AND FAILURESLOPE STABILITY AND FAILURE
SLOPE STABILITY AND FAILURE
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining method
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam mining
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methods
 
Rock blasting for mining
Rock blasting  for miningRock blasting  for mining
Rock blasting for mining
 
Basics of drilling 1
Basics of drilling 1Basics of drilling 1
Basics of drilling 1
 
Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2
 
Shovel and Dumper Combinatio by Auqib Javed.pptx
Shovel and Dumper Combinatio by Auqib Javed.pptxShovel and Dumper Combinatio by Auqib Javed.pptx
Shovel and Dumper Combinatio by Auqib Javed.pptx
 
SURFACE MINERS
SURFACE MINERSSURFACE MINERS
SURFACE MINERS
 
Basics of openpit mining
Basics of openpit miningBasics of openpit mining
Basics of openpit mining
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINEDESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
DESIGN OF SUPPORT SYSTEM IN BORD AND PILLAR MINE
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Basics of drilling 2
Basics of drilling 2Basics of drilling 2
Basics of drilling 2
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Analysing shovel dumper productivity for coal mine
Analysing shovel dumper productivity for coal mineAnalysing shovel dumper productivity for coal mine
Analysing shovel dumper productivity for coal mine
 

Destacado

Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
VR M
 
Coal Sccl
Coal ScclCoal Sccl
Coal Sccl
VR M
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
Tayyab Anwar
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
SATYANARAYANA I
 
Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003
Yogesh Ghule
 

Destacado (20)

Openpit Design Fundas
Openpit Design FundasOpenpit Design Fundas
Openpit Design Fundas
 
Mining ppt 2014
Mining ppt 2014Mining ppt 2014
Mining ppt 2014
 
Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining
 
Mining methods
Mining methodsMining methods
Mining methods
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Coal Sccl
Coal ScclCoal Sccl
Coal Sccl
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
 
2 surface mine planning
2 surface mine planning2 surface mine planning
2 surface mine planning
 
Lecture 4: Underground Mining
Lecture 4: Underground MiningLecture 4: Underground Mining
Lecture 4: Underground Mining
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 
Mining
MiningMining
Mining
 
Open pit mine geometry considerations
Open pit mine geometry considerationsOpen pit mine geometry considerations
Open pit mine geometry considerations
 
Copy of open pit mining
Copy of open pit miningCopy of open pit mining
Copy of open pit mining
 
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground MinesPERUMIN 31: Modern Practices for the Design and Planning Underground Mines
PERUMIN 31: Modern Practices for the Design and Planning Underground Mines
 
Methods of Auxiliary Ventilation in Underground Mine
Methods of Auxiliary Ventilation in Underground MineMethods of Auxiliary Ventilation in Underground Mine
Methods of Auxiliary Ventilation in Underground Mine
 
Surface mining
Surface miningSurface mining
Surface mining
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 
Sublevel stoping..Underground mining methods
Sublevel stoping..Underground mining methodsSublevel stoping..Underground mining methods
Sublevel stoping..Underground mining methods
 
Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003Drilling and blasting powerpoint 2003
Drilling and blasting powerpoint 2003
 

Similar a Concept of oc mine planning & design(final)

Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
Demzy George
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
Benjamin Kramka
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015
ILIAS MICHALIS
 

Similar a Concept of oc mine planning & design(final) (20)

Workshop_on_Mine_Planning_and_Valuation_.pptx
Workshop_on_Mine_Planning_and_Valuation_.pptxWorkshop_on_Mine_Planning_and_Valuation_.pptx
Workshop_on_Mine_Planning_and_Valuation_.pptx
 
Re - Entry Drilling Project
Re - Entry Drilling ProjectRe - Entry Drilling Project
Re - Entry Drilling Project
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
 
Geoscience in Offshore Renewables
Geoscience in Offshore RenewablesGeoscience in Offshore Renewables
Geoscience in Offshore Renewables
 
Introduction to underground mine planning
Introduction to underground mine planningIntroduction to underground mine planning
Introduction to underground mine planning
 
Introduction to underground mine planning
Introduction to underground mine planningIntroduction to underground mine planning
Introduction to underground mine planning
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015
 
Key aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsKey aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirs
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
 
14 aneu applications of technological &amp; engineering solutions edit
14 aneu applications of technological &amp; engineering solutions edit 14 aneu applications of technological &amp; engineering solutions edit
14 aneu applications of technological &amp; engineering solutions edit
 
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
 
The life of an oil and gas field
The life of an oil and gas fieldThe life of an oil and gas field
The life of an oil and gas field
 
01 introduction
01 introduction01 introduction
01 introduction
 
African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006African Diamonds corporate presentation 2006
African Diamonds corporate presentation 2006
 
Geotechnical Study
Geotechnical StudyGeotechnical Study
Geotechnical Study
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
 
TL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.pptTL_Cons_present_Kishanpur_20[1].08.09.ppt
TL_Cons_present_Kishanpur_20[1].08.09.ppt
 

Último

一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
sovco
 
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
xzxvi5zp
 
Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...
Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...
Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...
Klinik kandungan
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
Probe Gold
 

Último (20)

countries with the highest gold reserves in 2024
countries with the highest gold reserves in 2024countries with the highest gold reserves in 2024
countries with the highest gold reserves in 2024
 
SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024
 
Gorakhpur Call Girls 8250092165 Low Price Escorts Service in Your Area
Gorakhpur Call Girls 8250092165 Low Price Escorts Service in Your AreaGorakhpur Call Girls 8250092165 Low Price Escorts Service in Your Area
Gorakhpur Call Girls 8250092165 Low Price Escorts Service in Your Area
 
AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024
 
Camil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdfCamil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdf
 
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
一比一原版(EUR毕业证书)鹿特丹伊拉斯姆斯大学毕业证原件一模一样
 
Premium Call Girls In Kapurthala} 9332606886❤️VVIP Sonya Call Girls
Premium Call Girls In Kapurthala} 9332606886❤️VVIP Sonya Call GirlsPremium Call Girls In Kapurthala} 9332606886❤️VVIP Sonya Call Girls
Premium Call Girls In Kapurthala} 9332606886❤️VVIP Sonya Call Girls
 
Dubai Call Girls/// Hot Afternoon O525547819 Call Girls In Dubai
Dubai Call Girls/// Hot Afternoon O525547819 Call Girls In DubaiDubai Call Girls/// Hot Afternoon O525547819 Call Girls In Dubai
Dubai Call Girls/// Hot Afternoon O525547819 Call Girls In Dubai
 
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
Osisko Gold Royalties Ltd - Corporate Presentation, May 2024
 
Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024
 
Teekay Corporation Q1-24 Earnings Results
Teekay Corporation Q1-24 Earnings ResultsTeekay Corporation Q1-24 Earnings Results
Teekay Corporation Q1-24 Earnings Results
 
Osisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 ResultsOsisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 Results
 
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
一比一原版(Acadia毕业证书)加拿大阿卡迪亚大学毕业证学历认证可查认证
 
The Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results PresentationThe Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results Presentation
 
Camil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdfCamil Institutional Presentation_Mai24.pdf
Camil Institutional Presentation_Mai24.pdf
 
Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...
Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...
Jual obat aborsi Tawangmangu ( 085657271886 ) Cytote pil telat bulan penggugu...
 
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdfITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
 
Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024
 
Western Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 PresentationWestern Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 Presentation
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
 

Concept of oc mine planning & design(final)

  • 1. CONCEPT OF OC MINE PLANNING & DESIGN
  • 2. Mining Methods • Coal is mined by two main methods - Surface or ‘opencast’ mining and underground mining. • The choice of method is largely determined by the depth,thickness and no. of coal seams, geology of the coal deposit and other factors.
  • 3. Mining Methods Shaft Mine Incline Mine Incline Excavator Adit Mine Opencast Mine
  • 4. Ideal conditions for Opencast Mining 1. Thickness of coal seams - > 5m 1. Flat gradient - < 1 in 6 1. Strike length - > 1 km 1. No.of seams - Less the better, with higher thickness 5. Coal without stone bands 6. Free from surface structures / features. 7. Preferably non-forest land. 8. Availability of adequate place for dumping. 9. Stripping ratio depending on quality of the coal
  • 5. General planning studies No fixed procedure – country-wise differences 1. Conceptual study, data reliable upto -- 75% Review 2. Pre-feasibility study - data reliable upto - 80% Additional data, modify prepare, management acceptance 3. Feasibility Report/DPR - data reliable upto - 85-90% 4. Detailed designing LTP/MTP - data reliability - 95% 5. Operational planning (STP) - -
  • 6. Basis for the initial study is Geological Report • There will be some overlap between various studies/reports. • Every step deals with Mining Technology, equipment, production scheduling, capital cost, revenue cost, internal rate of return, dispatches etc. However the degree of accuracy of data on the above aspects increases with each step. • Generally After F.R. approval, there is need to go in for long term planning, medium term planning (about 5 years) and S.T.P. Short-term planning (6 months – one year). •These reports should adapt circular analysis approach by considering various aspects like additional information available while operating the mine, slippages occurred, reserves, pit-slopes, pit-limits, pit scheduling to control faster rate of extraction from coal inventory which otherwise may lead to reduction in coal production in subsequent years or more equipment for higher OB removal to maintain targeted production.
  • 7. CONCEPTUAL MINE PLANNING / PRE-FEASIBILITY Deposit Tech-Aspects Economic aspects Resources Production requirements GR/MR Mining Technology Minelife requirements Mining depth Logistics, Strata Sequa Options and Suggestions Roads etc. Thickness of - coal Cash out flow - waste Equipment Cash inflow - inter burden Required rate of Coal Quality Surface Constraints Return Slope stability Cut-off SR Water Conceptual Mine Plan (Open pit layout, equipment) Modification of concept and or optimization Pre-Feasibility Study Accepted – Management Not accepted – DPR New attempt
  • 8. Steps in design of Opencast A. Study of deposit exploration (GR) B. Final pit limits. C. Development sequence. D. Design of Access Ramp and Haul Roads E. Pit design F. Annual production capacity – system availability – Mining technology G. Main Mining Equipment – Matching to Mining Plan H. Optimizing Dumping strategy and balancing I. Year-wise / stage – wise plans J. Financial viability (Capital & Revenue) K. Coal Washing L. Environment stipulations
  • 9. A. Study of GR on the deposit Exploration Salient Information • Extent of deposit i.e. strike and dip rise widths. • Geology – Geological succession, sequence of beds, drilling, logging, no. of seams, sequence of coal seams, description. • Inter seam partings. • Structure – No. of faults, Throws, dip of seams and beds • Reserves – Quality wise/seam wise/depth-wise etc. based on Block model, Gridded seam model & polygonal Model • O.B. volumes & S.R. – Sector-wise, depth-wise etc. • Coal seam analysis, proximate and ultimate , Ash etc. & OB strata hardness etc. • Drilling details (Lithology) • Physiography • Climate and Vegetation • Preliminary EMP information
  • 10. A. Contd. PLATES • Location Map, Top Sheet map, Roads, Lands (Forests), Rivers etc. • Topography – Hills, contours, rivers of Flats • Geological Map – in crops, Faults • Graphic Lithologs • Graphic correlation charts • Floor/Roof contour plans of all seams • Seam folio plans of all seams (seam out cop, floor contours, faults, isograde, isochore, iso depth). • Geological cross sections • Seam structure of all seams • ISO parting plans • ISO excavation plan for lower seam (surface constraints, boundaries, faults at seam level, excavation area)
  • 11. A. Contd., Additional Data required - -Geo-technical data – diggability of materials, slope geometry and stability of Working/permanent slopes, spoil pile configuration for outside/inside dump, stability, grainsizes after blasting etc. -Ground Water – Dewatering and depressurization hydrology - Impact of dewatering on surrounding areas - Impact on water quality -Surface hydrology - Water quality - make off water - Mine flood protection - Options for discharge of dirty water and various discharge systems.
  • 12. B. Final pit limits The criteria for delineation of boundaries of an Opencast Project are: Rise side boundary - Usually incrop of the bottom most seam Lateral sides - Usually by Geological disturbances like faults, surface structures / features like nalah, river etc or limitation of the strike length of the deposits. Dip side - Depends on the economical stripping ratio,in absence of natural constraints
  • 13. B Contd. B. Final pit limits Final Pit limits Haul analysis Lead,lift increase cost – decides mode of transport Dump area 100m from mine boundary Dump limits available are Dump area 50 m from internal access road. Dump area 80-100 m. from mine infrastructure OB volumes - Final slopes Mineable Reserves – various losses, batter, barrier etc. - dilution etc (0-1 m against Roof,floor) Maximum depth increases haul cost (30-40% of total cost at 1 1/2 Km lead. Boundaries are drawn as above & Coal, OB ,SR are estimated
  • 14. B. Final pit limits B Contd. Estimation of Coal, OB & Stripping ratio Rough assessment is given below • Assuming Pit slopes of 450, the Quarry floor and Quarry surface are delineated • Volume of Coal & OB = Average area x Average depth - (A) • Average area = (Quarry surface area + Quarry floor area) / 2 • Average depth = (Minimum depth + maximum depth) / 2 • Volume of Coal=(Quarry floor area x Cumulative thickness of all coal seams) - (B) • Coal in tonnes = Volume of coal x Specific gravity – (C) • OB Volume = Coal + OB Volume (A) – Coal Volume (B) - (D) • Stripping ratio = OB Volume (D) / Coal in tones (C) For accurate S.R,the volumes of OB and coal are to be made seam wise
  • 15. B Contd. B. Final pit limits The boundaries are firmed up based on the economic stripping ratio. Economic stripping ratio varies with: • Average sales realization i.e. higher the quality of coal, higher the realization. • Capital investment requirements • Operating cost. • Also surface constraints The following thumb rules may be of some Help (with outsourcing OB removal): Projects are likely to be economically viable upto a maximum SR indicated against the grade of coal Grade Stripping ratio (Cum/T) F 6 E 7 D 8 C 10
  • 16. C. Development Sequence -Opening the deposit – Access trench -Box cut – To accommodate all equipment -Mine phases – Depends on the shape of the property -Progress of Benches -Coal production schedules -OB excavation schedules Note:- Maximize inventory of coal in the initial years -Differ OB stripping requirements as much as possible – Average SR versus natural SR -Income generated in the first 5 to 10 years but not remote economics will either make or break the project. -Profits for in the future have practically no impact on the project NPV. Each successive phase will be less profitable and the ultimate limit will be loss even after ploughing in earlier profits.
  • 17. D. Design of Access Ramp & Haul roads Location of Access ramp is guided by the following: 1) Generally located at the minimum depth of incrop of bottom most seam – So as to reduce initial waste stripping (unproductive work) 2) Should facilitate maximizing of internal dumping and sectional working. 3) Should be near the External dump / Coal yard / Mine service facilities etc. 4) Main haul road upto the pit limit should be planned in the beginning only. 5) Since haul costs constitute about more than 40% and tyre costs about 10% of the total mining costs,priority for design,construction and maintenance should be given. 6) Gradient,width,drainage,curves,super elevation,base,sub base,type and thickness of top dressing should be like that of national high ways for heavy traffic.
  • 18. D Contd. D. Design of Access Ramp & Haul roads Haul roads Sl.No Particulars 1 Width Should facilities two way traffic, dozer movement, formation of drains, lighting arrangement (Normal width – 30m,but depends on capacity of dumpers). 2 Gradient 1 in 16 Short ramps 1 in 10 3 Lesser number of curves 4 In flat seams of haul roads can be formed over the floor of larger strike length the seam 5 In steep seams Haul road for Coal & OB benches can be planned along highwall slopes say every 30m. This will also facilitate internal dumping.
  • 19. E. Pit design. General design parameters and planning data • Density of seams, total coal column thickness •Thickness of partings • Gradient • Geological disturbances • Strike lengths, shape of property • Geological Reserves • Surface constraints/adjacent habitat • Dump yards availability with lead and lift • Mining system, optimum mining concept • Depth of operation, mineable reserves after various losses, OB volumes, SR • Spoil characteristics • Work practices in the Area • Diggability characteristics
  • 20. E Contd. E. Pit design As per Regulation 98 of CMR 1957, In alluvial soil etc. - Sides shall be sloped at 450 or Benched – height not more than 1.5m Width – not less than height In hard ground - Sides adequately benched/sloped so as to prevent danger from fall of sides Coal - Sides shall be sloped at 450 or Benched – height not more than 3m However, exemption can be sought from Inspectorate.
  • 21. E Contd. E. Pit design Overall slope of a pit depends on several factors of the pit slope: a) Geological disturbances like faults etc. b) Hydrological condition of strata c) Orientation of slip planes d) Nature of strata – i.e. hardness, material consolidation etc. e) Depth of workings f) Design of haul roads & ramps in the highwall g) Stratigraphy – thickness, spacing of the clay bands or other weak layers
  • 22. E. Pit design E Contd. In general for OC mines upto a depth of 200m, overall slope angle of 450 is permitted.
  • 23. E Contd. E. Pit design For deeper mines flatter highwall slopes will be necessary from safety point of view (for 35 T dumpers & above)
  • 24. E. Pit design E Contd. For deeper mines flatter highwall slopes will be necessary from safety point of view (dumpers below 35T capacity)
  • 25. E Contd. E. Pit design Typical High wall layout
  • 26. E Contd. E. Pit design Working benches: 1) General Width - 40 – 45m Height - Generally equal to height of the boom or in some cases upto 3m above the boom height. In case of Backhoe – digging height of machine Bench slope - 560 to 700 2) Dragline: Width of the cut - 60m Height of bench - maximum digging depth 3) In order to even out the yearly OB removal quantities and the economics sometimes alternative workings and non-working benches (around 25 m wide) are proposed.
  • 27. F. Fixing annual production capacity After defining the boundaries, the annual production capacity will be fixed based on the following criteria : 1) The available mineable coal reserves 2) Geometry of the deposit - Strike & dip rise lengths 3) Structure of the deposit - Thickness of seams, partings, faults, gradient etc. 4) Linkage - Basket, Captive use etc. 5) HEMM configuration - Capacity of HEMM. 6) Surface structures - Limits the material to be blasted.
  • 28. F Contd. Excavator machine productivity – Based on , -Dipper cycle time -Waiting time for truck spotting -Bad blast factor -Truck loading time etc. Annual capacity is based on -Equipment available hours -Utilization percentage Proper fragmentation,less throw off material,bench height,bench slopes ,avoiding toes and secondary blasting,improves shovel efficiency Optimum fragmentation-cost of drilling,blasting vis- à-vis cost of dozing,loading,hauling and dumping.
  • 29. F Contd. System availability as a function of individual components Calendar hours-(365x24) (Figures are Indicative only) 8760 scheduled working Holidays and bad weather 2.5%- hours(SSH) 8463 / 6140 Operational delays-blasting, relocations,shift change,Lunch etc 1 Hour/Shift(8%) Preventive maintenance-i.e annual,weekly,daily,shift 15% of SSH Scheduled operating time or wise and unexpected break downs Availabilty- 100% Equipment available hours 6563/4390 Shovel,dumper system 97% Effective Operating Time 6366/3960 12% - Crusher + 1 Conveyor 85% Effective Operating Time 5559/3730 2% Drop for each Belt 73% System Availability 4804/3160
  • 30. G. Main mining equipment For Various Technologies 1) Shovel Dumper technology. 2) Dragline technology 3) Inpit Crusher – conveyor – spreader – technology. 4) Continuous Mining technology – Bucket wheel excavators. 5) Rock Breaker technology. 6) Surface Miner technology.
  • 31. G Contd. Note: In seam Mining is always practiced in flat seams while in case of steep seams Horizon mining, with its disadavntages, may have to be followed.
  • 32. G Contd. G. Main mining equipment 1)Shovel dumper technology: • This is the most commonly used technology in Opencast mines. • Basically two variants – Rope shovels and Hydraulic shovels. • Shovel used for excavation & Dumper for transport of material. • Bucket capacities vary from 0.9 Cum to 40 Cum with matching Trucks/Dumpers of 16 Cum to more than 240 T. • Can be deployed for removal of varying thickness of materials. • Harder materials require blasting. • Can be deployed for removal of steep & thin seams (hydraulic shovels).
  • 33. G. Main mining equipment G Contd. 2)Draglines: • A dragline bucket system consists of a large bucket which is suspended from a boom with wire ropes. • Draglines are deployed wherever there is scope for side casting overburden above coal seam into the de-coaled area. • It is very cost effective technology & can be deployed in flatter seams. 3)In pit crusher conveyor technology: • The drilled & blasted OB is loaded by shovels and transported by dumpers to Crushers. The crushed OB is then transported by a series of conveyors into a spreader for dumping. •Can be used in steep seams where laying of transport roads for the trucks is difficult. •While S.R indicates volumes,cut off ratio indicates depth and reflects in dumper haulage cost,which increase with depth and may become prohibitive where in alternative haulage system may have to thought off. •Ideally suited where material has to be transported over a large distance & lift. 4)Continuous Miner Technology:- Bucket Wheel Excavators •Presently being used in Neyvali, Lignite Opencast mines, having soft strata. •The buck wheel excavates the material without blasting which is transported by a series of belt conveyors to spreader.
  • 34. G Contd. G. Main mining equipment 5)Rock breaker technology: • Rock breaker technology can be applied for breaking of rock/coal/ore even about 500 kg/sq.cm. • It can be used wherever it is not possible to go for blasting – near vicinity of structures and habitations. 6)Surface Miner Technology: •Used for selective mining. •Larger strike length of about 600 m – 1000 m and widths of around 300 m are ideally suited for surface miner. •Does not need drilling and blasting. The machine cuts the coal & loads into trucks for onward transportation to Surface Other common mining equipment to all the technologies •Drills •Dozers ,Graders & Compactors •Water Sprinklers •Pumps etc. •Electrical equipment •Crushers & Conveyors for Coal/OB
  • 35. Rope Shovel & Dumper
  • 37. An opencast mine with dragline
  • 38. IN-PIT CRUSHER CONVEYOR TECHNOLOGY (Spreader in Operation)
  • 41. H. Dumping strategy and balancing Internal dumping: Depends on the steepness of the seams. As the gradient increases, the percentage of dumping reduces. Internal dumping can be increased by sectorial working of the pit – which may reduce the annual output. Toe of the dump generally kept at a distance of 100 m from the working benches. Floor of the pit to be roughened by blasting for increasing dump stability. General design of dumps: • Deck height – 30m • Berm width – 30m • Deck slope – 37½0 • Overall slope – 280 • Swell factor for OB-1.38,for coal –1.40 • Swell compact after initial settling – 1.20 Note:-Dump yard management and control is essential for the success of open cast mining. In case of more than one External Dump yards, balancing the excavation volume to either of the dump yard should be based on lead & lift and size of the Dump yards.
  • 42. H Contd. H. Dumping strategy 1. Total dump height- 90m 1. Total dump height- 90m 2. Deck height – 30m 2. Deck height – 30m 3. Berm width – 30m 3. Berm width – 30m 4. Deck slope-37 ½ 0 4. Deck slope-37 ½ 0 5. Overall slope-280 5. Overall slope-280
  • 43. H Contd. H. Dumping strategy 1. Total dump height- 90m 1. Total dump height- 90m 2. Deck height – 15m 2. Deck height – 15m 3. Berm width – 15m 3. Berm width – 15m 4. Deck slope-37 ½ 0 4. Deck slope-37 ½ 0 5. Overall slope-24.830 5. Overall slope-24.830
  • 44. H Contd. Internal Dumping reduces with the increase in the gradient of the seam. Comparison between 1in4 and 1in8 Gradient floor dipping at 1in4 floor dipping at 1in8 Assumptions: Strike Length : 1000m Max. Depth : 110m Coal Seam thickness : 15m Annual Rated capasity : 6.0 LTPA Project Parameters 1in4 1in8 Area of Excavation : 0.59 Sq.km 1.04 Sq.km Mineable Reserves : 90.0 L.T 180.L.T Total OB Removal : 274.0 L.m3 480.5 L.m3 Stripping Ratio : 2.74 2.67 Life of the Project : 17 Years 32 Years Volume of Internal Dumping : 39.85 L.m3 256.41 L.m3 Volume of External Dumping : 234.15 L.m3 134.00 L.m3 % of Internal Dumping : 14.54 53.36 (upto Ground Level) Safe distance from coal bench to toe of internal dump : 100m 50m
  • 45. I. Designing the year-wise / stage – wise plans I) Stage plans • Stage plans are prepared based on Year-wise production requirements (rated out put) • Stage plans at the end of years – 1, 2, 3, 4, 5 & in intervals of 5 years are prepared. • Also plans are prepared where any specific land mark like a new box-cut, change in layout will take place.
  • 46. J. Financial Viability 1) The requirement of HEMM & its capital is estimated. 2) Other capital like developmental works, CHP etc are worked out. 3) Operating expenses are worked out to arrive at cost of production. 4) Financial viability including profit & loss , IRR etc is estimated. 5) Based on required IRR, anticipated selling price is also worked out.
  • 47. K. Coal Washing Need for Washing Power Houses consume about 75% of coal. Power Houses are designed to accept Coal of ‘E’ Grade & above (UHV>3300). The percentage of production of coal below ‘E’ Grade is increasing . MoEF stipulation – Presently the onus of responsibility is on end user for using Coal of not more than 34% ash if he is located over 1000Km away. Hence, the need to upgrade coals below ‘E’ Grade so as to suit the requirements of Power houses. Cost of washing is around Rs 120-130/T of raw coal.
  • 48. L. Environment stipulations As per EP Act 1986 “Environment” includes water, air and land and the inter-relationship which exists among and between water, air and land and human beings, other living creatures, plants, micro organism and property
  • 49. L Contd. Impacts and Mitigative Measures • Air – Impacts: Dust is generated from drilling, blasting, excavation, crushing and transportation operations. This dust becomes air borne and gets carried away to surrounding areas. – Mitigative Measures: • Extensive water spray arrangements at the Coal handling sites. • Wet-drilling methods are to be adopted. • Water spraying on haul roads and permanent transport routes at required frequencies. Provision for mobile water sprinklers has to be made for this purpose. • Extensive Green Belt development around the quarry and OB dump • Black topping the transport routes and avenue plantation on these roads.
  • 50. Water spraying on the haul road
  • 51. Continuous water spraying on the haul road
  • 52. L Contd. Impacts and Mitigative Measures • Water: – Impacts: • Pollution of the surface water bodies with the mine discharge water and domestic sewage. – Mitigative Measures: • The Mine Discharge water is to be treated in settling tanks before discharging it into the surface water bodies. • Effluent from workshop is to be treated in ETPs. • Sewerage treatment plant to be provided for treating the domestic sewage from the colony.
  • 54. Treatment plant for Work shop effluent
  • 55. Impacts and Mitigative Measures L Contd. Noise Pollution & Vibrations • Impact − The main sources of noise in the project are electrical and diesel-powered machines, compressors, pumps, drilling machines, dumpers, etc. − During blasting operations blast vibrations will take place. • Control Measures – Controlled blasting techniques using NONELs are to be adopted . – Creation of green belts of dense foliage in three rows between mine areas and residential colonies. – Proper maintenance of machinery including transport vehicles. – Protective devices like earplugs and earmuffs are to be provided to the needy workers. – Sound and dust proof cabins are to be provided in the machines like dozers, shovels, dumpers and feeder breakers at CHP etc.
  • 56. Impacts and Mitigative Measures L Contd. Over Burden Management  Topsoil excavated from the quarry is to be dumped separately at predetermined place and has to be subsequently spread on external dumps for plantation.  Top soil dump is to be kept not more than 10m height.  Top soil has to be vegetated with grasses and leguminous species to maintain its fertility.  The reclamation of O.B dumps is to be done by using Biological Engineering techniques for stability of slopes and prevention of soil erosion from O.B dumps.  Construction of crib structures, Gabion structures, forming of staggered Contour trenches are to be practiced for stability of slopes.
  • 57. L Contd. Impacts and Mitigative Measures Over Burden Management  Raising of seedlings on both top and slopes of the dumps in the staggered contour trenches.  By dibbling seeds of various species like Avisa, Subabool, Babul, Neem etc.  Safe disposal of rainwater by construction of garland drains. Garland drains are to be provided around the quarry and overburden dumps .
  • 58. Safe disposal of water from Top of OB
  • 59.