9th Street Safety & Bicycle Project
         Park Slope, Brooklyn




         Division of Street Management & Safety
                Traffic Operations Bureau
              Presentation to CB 6, Brooklyn
                        March, 2007
DOT 3-Year Bicycle Network
       Expansion Plan
• 200 mile expansion of on-street network
• Targeted to:
  – Increase connectivity
  – Areas with high demand
  – Citywide backbone of routes
9th Street: Bicycle Network Link
Corridor Crashes




                                           2004-2006 Crashes
      Injured:    3rd Ave         4th Ave         5th Ave         6th Ave         7th Ave         8th Ave            PPW
Pedestrian       6         14%   9         12%   14        21%   5         14%   3         16%   7         23%   1        17%
Bicyclist        3         7%    2         3%    3         5%    3         8%    1         5%    1         3%    0         0%
Passenger        6         14%   13        18%   3         5%    8         22%   3         16%   10        33%   0         0%
No Injury        29        67%   50        68%   46        70%   20        56%   12        63%   12        40%   5        83%
Total Crashes         43              74              66              36              19              30              6
Primary 9th Street Issues
 1.   Uncomfortable Cycling Route
 2.   Pedestrian Safety Concerns
 3.   High Speeds
 4.   Interrupted Thru Movements
 5.   Challenging Left Turns

Project Goal: A Safer and More Comfortable 9th
      Street Corridor for ALL Street Users
Proposal Summary
•   4 Lane to 3 Lane “Road Diet”
     – Left Turn Bays
     – Bike Lanes
    Carries existing 3 lane configuration at 4th Ave to Prospect Park
•
•   Fast Implementation: July 2007
                                      Existing




                                       Proposed
Issue 1: Uncomfortable Cycling
                      Environment
     • Cyclist squeezes b/w                         • Cyclist separated from
       moving lane and parked                         travel lanes
       cars, or
     • “Takes” moving lane

                                         CENTER




                                                                                                        CENTER
SIDEWALK




                                                  SIDEWALK
             9’          10’      10’                          8’          5’         11’     Flush
           Parking     Moving   Moving                       Parking Bike Lane w/   Moving   Median
            Lane        Lane     Lane                         Lane     3’ buffer     Lane    (4’ / 2)


                                                                  Proposed Condition
                Existing Condition                                Proposed Condition
                Existing Condition
Issue 2: Pedestrian Safety Concerns

                • 3rd & 9th Fatality
                • Dizzy’s Crash (8th Ave)
                • CB 6 Complaints
Issue 2: Pedestrian Safety Concerns
• Lane Assignments, Speed
  Reduction & Simplified Operations
• Potential Refuge Islands at
  Crossings with One Way Avenues
Issue 3: Speeds
• Excess Capacity
  – Atlantic Ave (at Clinton): 26,000 vehicles per day (vpd)
  – Vanderbilt Ave (at Atlantic): 19,000 vpd
  – 9th St (at 6th Ave): 11,500 vpd

• Thru Lane Removal
  – 1 Lane: lead vehicle sets pace
  – Successful “4 to 3” reductions:
      • Vanderbilt Ave
      • Gerritsen Ave
Issue 4: Interrupted Thru Movement

Existing Condition
Existing Condition
                                  Double-parked auto
                                  Double-parked auto      Autos moving thru
                                                          Autos moving thru
                                     or bicyclist
                                      or bicyclist




                Left-turning vehicle
                Left-turning vehicle
                                             Right lane vehicles
                                             Right lane vehicles
                  waiting for gap
                  waiting for gap
                                             change lanes twice
                                             change lanes twice
Issue 4: Interrupted Thru Movement

Proposed Condition
Proposed Condition

                                       Bicyclist       Double-parked auto
                                       Bicyclist       Double-parked auto




                Left-turning vehicle               No lane changes
                Left-turning vehicle               No lane changes
                  waiting for gap
                  waiting for gap
Issue 5: Challenging Left Turns
                                  Left Turning Motorist Have
 Existing Condition
 Existing Condition
                                          4 Concerns
                                                1) Vehicles Approaching
                                                1) Vehicles Approaching
                                                      from Behind
                                                      from Behind
2) Identifying Gap in Left Lane
2) Identifying Gap in Left Lane




       3) ID’ing Gap in Right
       3) ID’ing Gap in Right
                Lane
                Lane
                                      4) ID’ing Pedestrians in
                                      4) ID’ing Pedestrians in
     (VISIBILITY HINDERED)
     (VISIBILITY HINDERED)
                                             Crosswalk
                                              Crosswalk
Issue 5: Challenging Left Turns
                                   Only 2 Points of Focus and
                                     No Visibility Problem
      Proposed Condition
      Proposed Condition
                                        Vehicles from behind in
                                        Vehicles from behind in
                                             different lane
                                             different lane




 Driver only needs ONE gap to
 Driver only needs ONE gap to
turn; can then look at crosswalk
turn; can then look at crosswalk
Bicycle Network Benefits
Implemented with Brooklyn Waterfront Greenway
    Connection to Columbia Street Promenade




                             t St




                                                     e
                                        t
                              ur




                                                Av
                                          S
                           Co
                Bay

                                      ith




                                              3 rd
                      St
                                    Sm




                                                                e
           St




                                                           Av
       bia




                                                         5 th
   lum




                                                                9 th
                                                                       St
Co
• July 2007 – Center of Brooklyn Connected to
  Prospect Park and Red Hook Waterfront on a
  Continuous Bike Route
Summary
Project Goal: A Safer and More Comfortable 9th
      Street Corridor for ALL Street Users
• Cyclists –
   – Dramatically improved experience
   – Connections to major attractors
• Pedestrians –
   – More Comfortable and Safe with Potential for Capital
     Improvements
• Motorists –
   – Simplified and Safer Operations
   – Center median reduces head on crash risk
• New Street in July
   – “Operational” Design Allows for Rapid Implementation
End of Presentation

Más contenido relacionado

Más de streetsblog

Open Sundays on Prince Street
Open Sundays on Prince StreetOpen Sundays on Prince Street
Open Sundays on Prince Streetstreetsblog
 
NYC Congestion Pricing Scenario Comparisons
NYC Congestion Pricing Scenario ComparisonsNYC Congestion Pricing Scenario Comparisons
NYC Congestion Pricing Scenario Comparisonsstreetsblog
 
Congestion Mitigation Strategies: Alternatives to the City’s plan
Congestion Mitigation Strategies: Alternatives to the City’s planCongestion Mitigation Strategies: Alternatives to the City’s plan
Congestion Mitigation Strategies: Alternatives to the City’s planstreetsblog
 
Decongesting New York
Decongesting New YorkDecongesting New York
Decongesting New Yorkstreetsblog
 
Congestion Pricing Commission
Congestion Pricing CommissionCongestion Pricing Commission
Congestion Pricing Commissionstreetsblog
 
Applying the Road Diet for Livable Communities
Applying the Road Diet for Livable CommunitiesApplying the Road Diet for Livable Communities
Applying the Road Diet for Livable Communitiesstreetsblog
 
Rethinking Grand Army Plaza
Rethinking Grand Army PlazaRethinking Grand Army Plaza
Rethinking Grand Army Plazastreetsblog
 
Grand Army Plaza: Southeastern Improvements
Grand Army Plaza: Southeastern ImprovementsGrand Army Plaza: Southeastern Improvements
Grand Army Plaza: Southeastern Improvementsstreetsblog
 
NYCDOT - 9th Street Proposal
NYCDOT - 9th Street ProposalNYCDOT - 9th Street Proposal
NYCDOT - 9th Street Proposalstreetsblog
 
NYCDOT - Bleecker & Prince Bike Route
NYCDOT - Bleecker & Prince Bike RouteNYCDOT - Bleecker & Prince Bike Route
NYCDOT - Bleecker & Prince Bike Routestreetsblog
 
NYCDOT Proposed Conversions of 6th & 7th Avenues in Brooklyn
NYCDOT Proposed Conversions of 6th & 7th Avenues in BrooklynNYCDOT Proposed Conversions of 6th & 7th Avenues in Brooklyn
NYCDOT Proposed Conversions of 6th & 7th Avenues in Brooklynstreetsblog
 
NYC 2030: Accepting The Challenge
NYC 2030: Accepting The ChallengeNYC 2030: Accepting The Challenge
NYC 2030: Accepting The Challengestreetsblog
 

Más de streetsblog (12)

Open Sundays on Prince Street
Open Sundays on Prince StreetOpen Sundays on Prince Street
Open Sundays on Prince Street
 
NYC Congestion Pricing Scenario Comparisons
NYC Congestion Pricing Scenario ComparisonsNYC Congestion Pricing Scenario Comparisons
NYC Congestion Pricing Scenario Comparisons
 
Congestion Mitigation Strategies: Alternatives to the City’s plan
Congestion Mitigation Strategies: Alternatives to the City’s planCongestion Mitigation Strategies: Alternatives to the City’s plan
Congestion Mitigation Strategies: Alternatives to the City’s plan
 
Decongesting New York
Decongesting New YorkDecongesting New York
Decongesting New York
 
Congestion Pricing Commission
Congestion Pricing CommissionCongestion Pricing Commission
Congestion Pricing Commission
 
Applying the Road Diet for Livable Communities
Applying the Road Diet for Livable CommunitiesApplying the Road Diet for Livable Communities
Applying the Road Diet for Livable Communities
 
Rethinking Grand Army Plaza
Rethinking Grand Army PlazaRethinking Grand Army Plaza
Rethinking Grand Army Plaza
 
Grand Army Plaza: Southeastern Improvements
Grand Army Plaza: Southeastern ImprovementsGrand Army Plaza: Southeastern Improvements
Grand Army Plaza: Southeastern Improvements
 
NYCDOT - 9th Street Proposal
NYCDOT - 9th Street ProposalNYCDOT - 9th Street Proposal
NYCDOT - 9th Street Proposal
 
NYCDOT - Bleecker & Prince Bike Route
NYCDOT - Bleecker & Prince Bike RouteNYCDOT - Bleecker & Prince Bike Route
NYCDOT - Bleecker & Prince Bike Route
 
NYCDOT Proposed Conversions of 6th & 7th Avenues in Brooklyn
NYCDOT Proposed Conversions of 6th & 7th Avenues in BrooklynNYCDOT Proposed Conversions of 6th & 7th Avenues in Brooklyn
NYCDOT Proposed Conversions of 6th & 7th Avenues in Brooklyn
 
NYC 2030: Accepting The Challenge
NYC 2030: Accepting The ChallengeNYC 2030: Accepting The Challenge
NYC 2030: Accepting The Challenge
 

Último

The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 

Último (20)

The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 

9th St Safety & Bicycle Project Makes Park Slope Safer

  • 1. 9th Street Safety & Bicycle Project Park Slope, Brooklyn Division of Street Management & Safety Traffic Operations Bureau Presentation to CB 6, Brooklyn March, 2007
  • 2. DOT 3-Year Bicycle Network Expansion Plan • 200 mile expansion of on-street network • Targeted to: – Increase connectivity – Areas with high demand – Citywide backbone of routes
  • 3. 9th Street: Bicycle Network Link
  • 4. Corridor Crashes 2004-2006 Crashes Injured: 3rd Ave 4th Ave 5th Ave 6th Ave 7th Ave 8th Ave PPW Pedestrian 6 14% 9 12% 14 21% 5 14% 3 16% 7 23% 1 17% Bicyclist 3 7% 2 3% 3 5% 3 8% 1 5% 1 3% 0 0% Passenger 6 14% 13 18% 3 5% 8 22% 3 16% 10 33% 0 0% No Injury 29 67% 50 68% 46 70% 20 56% 12 63% 12 40% 5 83% Total Crashes 43 74 66 36 19 30 6
  • 5. Primary 9th Street Issues 1. Uncomfortable Cycling Route 2. Pedestrian Safety Concerns 3. High Speeds 4. Interrupted Thru Movements 5. Challenging Left Turns Project Goal: A Safer and More Comfortable 9th Street Corridor for ALL Street Users
  • 6. Proposal Summary • 4 Lane to 3 Lane “Road Diet” – Left Turn Bays – Bike Lanes Carries existing 3 lane configuration at 4th Ave to Prospect Park • • Fast Implementation: July 2007 Existing Proposed
  • 7. Issue 1: Uncomfortable Cycling Environment • Cyclist squeezes b/w • Cyclist separated from moving lane and parked travel lanes cars, or • “Takes” moving lane CENTER CENTER SIDEWALK SIDEWALK 9’ 10’ 10’ 8’ 5’ 11’ Flush Parking Moving Moving Parking Bike Lane w/ Moving Median Lane Lane Lane Lane 3’ buffer Lane (4’ / 2) Proposed Condition Existing Condition Proposed Condition Existing Condition
  • 8. Issue 2: Pedestrian Safety Concerns • 3rd & 9th Fatality • Dizzy’s Crash (8th Ave) • CB 6 Complaints
  • 9. Issue 2: Pedestrian Safety Concerns • Lane Assignments, Speed Reduction & Simplified Operations • Potential Refuge Islands at Crossings with One Way Avenues
  • 10. Issue 3: Speeds • Excess Capacity – Atlantic Ave (at Clinton): 26,000 vehicles per day (vpd) – Vanderbilt Ave (at Atlantic): 19,000 vpd – 9th St (at 6th Ave): 11,500 vpd • Thru Lane Removal – 1 Lane: lead vehicle sets pace – Successful “4 to 3” reductions: • Vanderbilt Ave • Gerritsen Ave
  • 11. Issue 4: Interrupted Thru Movement Existing Condition Existing Condition Double-parked auto Double-parked auto Autos moving thru Autos moving thru or bicyclist or bicyclist Left-turning vehicle Left-turning vehicle Right lane vehicles Right lane vehicles waiting for gap waiting for gap change lanes twice change lanes twice
  • 12. Issue 4: Interrupted Thru Movement Proposed Condition Proposed Condition Bicyclist Double-parked auto Bicyclist Double-parked auto Left-turning vehicle No lane changes Left-turning vehicle No lane changes waiting for gap waiting for gap
  • 13. Issue 5: Challenging Left Turns Left Turning Motorist Have Existing Condition Existing Condition 4 Concerns 1) Vehicles Approaching 1) Vehicles Approaching from Behind from Behind 2) Identifying Gap in Left Lane 2) Identifying Gap in Left Lane 3) ID’ing Gap in Right 3) ID’ing Gap in Right Lane Lane 4) ID’ing Pedestrians in 4) ID’ing Pedestrians in (VISIBILITY HINDERED) (VISIBILITY HINDERED) Crosswalk Crosswalk
  • 14. Issue 5: Challenging Left Turns Only 2 Points of Focus and No Visibility Problem Proposed Condition Proposed Condition Vehicles from behind in Vehicles from behind in different lane different lane Driver only needs ONE gap to Driver only needs ONE gap to turn; can then look at crosswalk turn; can then look at crosswalk
  • 16. Implemented with Brooklyn Waterfront Greenway Connection to Columbia Street Promenade t St e t ur Av S Co Bay ith 3 rd St Sm e St Av bia 5 th lum 9 th St Co
  • 17. • July 2007 – Center of Brooklyn Connected to Prospect Park and Red Hook Waterfront on a Continuous Bike Route
  • 18. Summary Project Goal: A Safer and More Comfortable 9th Street Corridor for ALL Street Users • Cyclists – – Dramatically improved experience – Connections to major attractors • Pedestrians – – More Comfortable and Safe with Potential for Capital Improvements • Motorists – – Simplified and Safer Operations – Center median reduces head on crash risk • New Street in July – “Operational” Design Allows for Rapid Implementation