Introduction to Lean and Agile Software
         Development




©2008 Protegra Inc. All rights reserved.
Agenda
•   What is the problem?
•   What is Agile?
     -   Agile Manifesto
     -   Agile Principles
•   Agile Methodologies
•   Agile Software Development Standards
     -   Iteration Planning and Estimating
     -   Key Meetings
     -   Role of Project Management
     -   Role of Requirements Management
     -   Tools to assist Project and Requirements Management
     -   Role of Software Development
     -   Role of Testing
•   Is it Working?
•   Customize the Process
•   FAQ/Q&A

                ©2009 Protegra Inc. All rights reserved.
What is the problem?

•       Standish Group – CHAOS Study of IT project success

60

50

40
                                                                                 Succeeded
30
                                                                                 Challenged
20                                                                               Failed

10

    0
          1994         1996              1998               2000   2002   2004

                 ©2009 Protegra Inc. All rights reserved.
What is the problem?

  Cost overruns
+ Schedule overruns
+ Failed or Cancelled projects
+ Rigid processes
+ Change Management (that acts like Change Restriction)
+ Late Learning process
+ Building the wrong thing

= Lack of Trust in IT




            ©2009 Protegra Inc. All rights reserved.
Agile Manifesto
         Snowbird ski resort - Feb 2001

   We are uncovering better ways of developing
   software by doing it and helping others do it.
    Through this work we have come to value:

Individuals and interactions over processes and tools
Working software over comprehensive documentation
  Customer collaboration over contract negotiation
     Responding to change over following a plan

 That is, while there is value in the items on the
   right, we value the items on the left more.
 Reference: http://www.agilemanifesto.org


                         ©2009 Protegra Inc. All rights reserved.
Agile Manifesto: 12 Principles

  1.      Satisfy the customer through early and continuous delivery
         -      Shorten the distance between requirements gathering and customer
                feedback
  2.      Welcome changing requirements, even late in development
         -      Shorten the distance between conceiving and implementing an
                important change
  3.      Deliver working software frequently
         -      Shorten the distance between system-as-desired and system-as-
                built
  4. Business people and developers work together daily
         -      Shorten the distance (time) between a question and its
                answer


Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html


                          ©2009 Protegra Inc. All rights reserved.
Agile Manifesto: 12 Principles
  4. Build projects around motivated individuals
         -      Shorten the distance between intent and action, issue &
                resolution
  5. Convey information via face-to-face information
         -      Shorten the distance (space) between a question and its
                answer




Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html


                          ©2009 Protegra Inc. All rights reserved.
Agile Manifesto: 12 Principles

    7.     Working software is the primary measure of
           progress
           -      Shorten the distance between thinking we‟re done and
                  knowing we‟re done
    8.     Maintain a constant pace indefinitely
           -      Shorten the distance between the amount of
                  unproductive time spent building software and a
                  satisfying work day
    9.     Give continuous attention to technical excellence
           -      Shorten the distance between implementation and ideal




Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html


                          ©2009 Protegra Inc. All rights reserved.
Agile Manifesto: 12 Principles

  10. Simplify: maximize the amount of work not done
         -      Shorten the distance between comprehension and completion




  11. Teams self-organize
         -      Shorten the distance between need and action
  12. Teams retrospect and tune their behaviour
         -      Shorten the distance between introspection and adaptation

Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html



                          ©2009 Protegra Inc. All rights reserved.
Agile Methodologies

  •     Scrum
          -     founded by Ken Schwaber & Jeff Sutherland
  •     Extreme Programming (XP)
          -     founded by Kent Beck, Ward Cunningham, Ron Jeffries
  •     Crystal
          -     founded by Alistair Cockburn
  •     Lean Software Development
          -     founded by Tom & Mary Poppendieck
  •     Others…
          -     FDD
          -     DSDM

Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html


                          ©2009 Protegra Inc. All rights reserved.
Top Three Methodologies

•   Lets look at the characteristics of the top three Agile
    Methodologies
     -   Scrum
     -   Extreme Programming
     -   Lean Software Development




               ©2009 Protegra Inc. All rights reserved.       11
Scrum

•   Scrum is a process skeleton that includes a set of practices
    and predefined roles.
     -   Pigs
     -   Chickens
•   The main roles in Scrum are the ScrumMaster who
    maintains the processes and works similarly to a project
    manager, the Product Owner who represents the
    stakeholders, and the Team which includes the developers.




               ©2009 Protegra Inc. All rights reserved.
Scrum

•   During each sprint, a 15-30 day period, the team creates an
    increment of usable software.
•   The set of user stories that go into a sprint come from the
    product backlog, which is a prioritized set of high level
    requirements of work to be done.
•   Which backlog user stories go into the sprint is determined
    during the sprint planning meeting.
•   During a sprint, no one is able to change the sprint backlog,
    which means that the requirements are frozen for that sprint.
    After a sprint is completed, the team demonstrates the use
    of the software.




             ©2009 Protegra Inc. All rights reserved.               13
Scrum

•   Scrum enables the creation of self-organizing teams by
    encouraging co-location of all team members, and verbal
    communication across all team members and disciplines
    that are involved in the project.
•   A key principle of Scrum is its recognition that during a
    project the customers can change their minds about what
    they want and need (often called requirements churn), and
    that unpredicted challenges cannot be easily addressed in a
    traditional predictive or planned manner.




             ©2009 Protegra Inc. All rights reserved.
Extreme Programming

•   A discipline of software development that follows a specific
    structure that is designed to simplify and expedite the
    process of developing new software. Kent Beck developed
    Extreme Programming to be used with small teams of
    developers who need to develop software quickly in an
    environment of rapidly-changing requirements.
     -   Interesting note: Kent Beck‟s first book proposed a rigid form of XP.
         This has since been changed and the result is a more Agile XP. 




                ©2009 Protegra Inc. All rights reserved.
Extreme Programming

•   Extreme Programming is based on 12 principles:
     -   The Planning Process -- The desired features of the software,
         which are communicated by the customer, are combined with cost
         estimates provided by the programmers to determine what the most
         important factors of the software are.
     -   Small Releases -- The software is developed in small stages that
         are updated frequently, typically every two weeks.
     -   Metaphor -- All members on an XP team use common names and
         descriptions to guide development and communicate.
     -   Simple Design -- The software should include only the code that is
         necessary to achieve the desired results.
     -   Testing -- Programmers design the tests first and then write the
         software to fulfill the requirements of the test. The customer also
         provides tests at each stage to ensure the desired results are
         achieved.



               ©2009 Protegra Inc. All rights reserved.
Extreme Programming
    -   Refactoring -- XP programmers improve the design of the software
        through every stage of development instead of waiting until the end of the
        development and going back to correct flaws.
    -   Pair Programming -- All code is written by a pair of programmers working
        at the same machine.
    -   Collective Ownership -- Every line of code belongs to every programmer
        working on the project, so there are no issues of proprietary authorship to
        slow the project down
    -   Continuous Integration -- The XP team integrates and builds the
        software system multiple times per day to keep all the programmers at the
        same stage of the development process at once.
    -   40-Hour Week -- The XP team does not work excessive overtime to
        ensure that the team remains well-rested, alert and effective.
    -   On-Site Customer -- The XP project is directed by the customer who is
        available all the time to answer questions, set priorities and determine
        requirements of the project.
    -   Coding Standard -- The programmers all write code in the same way.
        This allows them to work in pairs and to share ownership of the code.

           ©2009 Protegra Inc. All rights reserved.
Extreme Programming Technical
Practices

•   Extreme Programming is essentially Scrum with additional
    Technical Practices
     - keep it simple and never add functionality early
       (YAGNI, Last Responsible Moment),
     - choose a system metaphor (Domain-Driven
       Design),
     - use CRC cards,
     - create a spike solution (proof of concept),
     - create acceptance tests,
     - establish coding standards,



             ©2009 Protegra Inc. All rights reserved.          18
Extreme Programming Technical
Practices

   - code the unit test first and ensure that all code
     has and passes all unit tests (Test-Driven
     Development),
   - program in pairs,
   - integrate sequentially and often,
   - own the code collectively,
   - measure and optimize last, and
   - create tests to detect bugs.




          ©2009 Protegra Inc. All rights reserved.       19
Lean Software Development

•   Lean Software Development is the application of lean
    principles to the craft of software development. So what is
    Lean? According to the National Institute of Standards and
    Technology Manufacturing Extensions Partnership’s Lean
    Network, Lean is:
     -   “A systematic approach to identifying and eliminating waste through
         continuous improvement, flowing the product at the pull of the
         customer in pursuit of perfection.” [1]
     -   “Lean Software Development reduces defects and cycle times while
         delivering a steady stream of incremental business value.” [2]




               ©2009 Protegra Inc. All rights reserved.
Lean Software Development

•   Lean Software development is a style of software
    development that emphasizes customer satisfaction through
    continuous delivery of functional software. In contrast to
    traditional software development methods, lean developers
    liaise continuously with business clients.
•   Their objective is to deliver working software as frequently
    as every two weeks during a project, and welcome changes
    to the requirements in response to evolving business needs.




             ©2009 Protegra Inc. All rights reserved.
Lean Software Development

•   The most crucial aspect of Lean LifeCycle is the execution
    of the project in iterations and quick feedback loops
    possible because of these iterations. It is essential to note
    that these iterations to not just apply to construction, they
    also apply to the following tasks:
     -   Project Management and Planning
     -   Analysis
     -   Technical Design
     -   Testing
     -   Deployment




               ©2009 Protegra Inc. All rights reserved.             22
Lean Principles

 1. Eliminate Waste

 The three biggest wastes in software development are:

       a)     Extra Features
       b)     Churn                                                Client received:
       c)     Crossing Boundaries




                                                                   Client needed:
Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com



                        ©2009 Protegra Inc. All rights reserved.
Lean Principles

   2. Create Knowledge

   Planning is useful. Learning is essential

         a)     Use the Scientific Method
         b)     Standards exist to be Challenged and Improved
         c)     Predictable performance is Driven by Feedback




Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com


                        ©2009 Protegra Inc. All rights reserved.
Lean Principles

   3. Build Quality In

   If you routinely find defects in your verification process,
        your process is defective.

         a)     Mistake-Proof Code with Test-Driven Development
         b)     Stop Building Legacy Code
         c)     The Big Bang is Obsolete




Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com


                        ©2009 Protegra Inc. All rights reserved.
Lean Principles

   4. Defer Commitment

   Abolish the idea that it is a good idea to start
      development with a complete specification.

         a)     Break Dependencies
         b)     Maintain Options
         c)     Schedule Irreversible Decisions at the Last Responsible
                Moment




Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com


                        ©2009 Protegra Inc. All rights reserved.
Lean Principles

     5. Deliver Fast

     Lists and queues are buffers between
         organizations that simply slow things
         down.

           a)    Rapid Delivery, High Quality, and Low Cost
                 are Fully Compatible
           b)    Queuing Theory applies to Development, not
                 just Servers
           c)    Limit Work to Capacity




Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com



                        ©2009 Protegra Inc. All rights reserved.
Lean Principles

   6. Respect People

   Engaged, thinking people provide the most sustainable
      competitive advantage.

         a)     Teams Thrive on Pride, Commitment, Trust, Applause
         b)     Provide Effective Leadership
         c)     Respect Partners




Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com


                        ©2009 Protegra Inc. All rights reserved.
Lean Principles

   7. Improve the System

   Brilliant products emerge from a unique combination of
       opportunity and technology.

         a)     Focus on the Entire Value Stream
         b)     Deliver a Complete Product
         c)     Measure UP




Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com



                        ©2009 Protegra Inc. All rights reserved.
Agile Software Development Standards


•   The following roles and activities are done in a standard way
    in all Agile Methodologies:
     -   Iteration Planning and Estimating
     -   Key Meetings
     -   Role of Project Management
     -   Role of Requirements Management
     -   Tools to assist Project and Requirements Management
     -   Role of Software Development
     -   Role of Testing




               ©2009 Protegra Inc. All rights reserved.             30
Iteration Planning and Estimating

•   Iteration planning is ‘the’ key planning initiative.
    Iterations need to be planned in conjunction with
    the client to accomplish the following:
         •   Deliver functionality to define the pace of the project
         •   Deliver functionality to deliver value to the client
         •   Deliver functionality to reduce and minimize risk for the entire project
         •   Lessons learned from one iteration must feed into subsequent iterations
             so that we don‟t execute the project in iterations with similar results, but
             that we execute the project in iterations with better results.




               ©2009 Protegra Inc. All rights reserved.
Initial Planning and Estimating

•   Initial Planning and estimating needs to be done
     -   Need detailed deliverable or task levels estimates
     -   Resource planning
     -   Milestone based
     -   Sometimes even a WBS structure based on project reporting
         requirements
•   This should be required for Agile or Lean projects.
•   Agile or Lean should not be an open cheque where
    estimates and milestones are not planned and approved up
    front
     -   Some proponents promote that agile estimates should only be given
         after team „Velocity‟ is determined




               ©2009 Protegra Inc. All rights reserved.                      32
What is this ‘Team Velocity’ I hear about?

•   Team Velocity is the sustainable pace that the team can do
    work
     -   This will change based upon the project and team composition
•   Velocity should not replace detailed estimating and Project
    Planning
     -   Detailed Estimating and Project Planning are to plan the project
     -   Velocity measurement and refinement are used to manage an
         executing project
     -   BOTH are required for a successful project.




               ©2009 Protegra Inc. All rights reserved.                     33
Estimation Levels

•   Estimating should be done at multiple levels to gain
    confidence and increase estimate reliability
•   There are 5 levels of estimating
     -   Task Level
     -   Deliverable Level
     -   Schedule Level
     -   Monte Carlo Simulation
     -   Planning Poker Sessions (Wide Band Delphi)




               ©2009 Protegra Inc. All rights reserved.    34
What is this ‘Planning Poker ’ I hear about?

•   Planning Poker is a process whereby the entire team
    estimate objects using card decks.
•   Planning Poker sessions should be held for each iteration.
•   A baseline is first established estimating an item that there
    is high estimating confidence in. (i.e. a simple CRUD screen)
     -   Subsequent items are then estimated in increments of that first
         baseline. (i.e. This screen would take the effort of 3 base screens to
         develop)
     -   Everyone chooses a card and then flips it over the same time.
     -   The team then discusses the difference in opinions why people
         estimated differently. The team then has to come to consensus on
         the estimate to be used.
     -   While time consuming, it addresses one of the main issues for
         project success. Proper estimating.
           •   Planning Poker enables the sharing of estimating expertise and
               knowledge

                 ©2009 Protegra Inc. All rights reserved.                         35
Key Meetings

•   The following key meetings are required:

     -   Project Kick off
     -   Iteration kick off
     -   Daily scrums or huddles
           •   What did you do yesterday
           •   What are you doing today
           •   What issues do you have
           •   2 minute limit per person
     -   Iteration Retrospectives
     -   Iteration Planning and Estimating




                ©2009 Protegra Inc. All rights reserved.   36
Role of Project Management
•   Iteration Planning
•   Issue Management
•   Risk Management
•   Change Management is required even more
     -   Different focus. The focus is how I can get the client the MOST
         functionality by following the Change Management process. May
         involve:
           •   Trading requirements
           •   Eliminating Requirements
           •   Change Requests for new budget or schedule if required
•   Sometimes the perception exists that Agile or Lean projects
    do not require the same level of Change Management. This
    is an incorrect perception.
     -   Sometimes Iterative projects actually have less Change
         Management than water fall projects.
     -   Projects that are doing less Change Management than required are
         not „being lean‟, they are being misguided.

                 ©2009 Protegra Inc. All rights reserved.                   37
Role of Project Management


•   Increased communication and visibility
     -   Visual Project Management
     -   Visual Project Dashboards
     -   Visual Status Reporting




               ©2009 Protegra Inc. All rights reserved.   38
Requirements Management

•   Business Analysts are the liaison to the business needs and
    desires.
•   Requirements Management and traceability is even more
    important for agile projects as there is the possibility of
    increased change
•   This makes the role of business and systems analysis
    critical to the success of the projects
•   The focus is on the ‘right’ amount of documentation.
•   Sometimes the perception exists that Agile or Lean projects
    do not document requirements. This is an incorrect
    perception.
     -   Projects should define what the appropriate level of documentation
         is on a case by case basis. (within required guidelines)
     -   Projects that are doing less documentation than required are not
         „being lean‟, they are being misguided.

               ©2009 Protegra Inc. All rights reserved.                       39
Requirements Management

•   Requirements must be Test Case Driven.
     -   Instead of descriptions as to what the software needs to do, the
         requirements should first list what test cases will ensure the software
         is operating correctly.
     -   This should be the first section in every specification or use case
     -   This will then feed into automated test cases and be a living
         document that will define the software
     -   There is less ambiguity in test cases than textual descriptions




                ©2009 Protegra Inc. All rights reserved.                           40
Tools to assist Project and Requirements Management


•   Many free or affordable tools are available to assist Agile or
    Lean Projects.

     -   www.rallydev.com
     -   www.targetprocess.com
     -   www.versionone.com
     -   www.thoughtworks.com/mingle


•   This is due to the fact that MS Project is an ok project
    planning tool, but not a great tool to manage a project while
    it is executing. (especially Agile or Lean Projects)




               ©2009 Protegra Inc. All rights reserved.              41
Role of Software Development

•   The following are important aspects of software
    development in an Agile or Lean Project:
     -   Team-Based Design
     -   Resources are multi-disciplined
     -   Pull system for task assignment
     -   Iterative Development
           •   Each development should be able to be implemented in Production. If
               not, it is not Iterative Development.
     -   Automated Unit Testing
           •   NUnit/Junit
     -   Continuous Builds/Continuous Build Servers




                 ©2009 Protegra Inc. All rights reserved.                            42
Role of Testing
•   Testing is a critical component in Agile or Lean project. (like all
    Waterfall Projects)
•   The Test Phase should be planned very diligently and in a very
    detailed manner.
     -   Resist the urge to have the iterations tested in an unstructured way. This
         only delays the discovery of defects.
     -   A Test Charter, Test Strategy, and Test Plans are all required.
     -   Automated System Integration Tests and User Acceptance Tests are
         mandatory
•   Continuous Integration is mandatory. This is distinct from
    Continuous builds.
     -   Continuous builds are the daily builds and execution of unit test cases to
         ensure ongoing development has not introduced new development
         issues
     -   Continuous integrations are the daily builds and execution of regression
         test cases to ensure no major application functionality issues exist.


                ©2009 Protegra Inc. All rights reserved.                              43
Is it working?
    Dr. Dobb‟s Journal – Agile Adoption Survey in 2008
    • Effectiveness of agile software development compared
      with traditional approaches:
                Cost of System
                 Development
      Business Stakeholder
           Satisfaction                                                                                     Higher
                                                                                                            No Change
                             Quality                                                                        Lower

                     Productivity

                                           0%         20% 40% 60% 80% 100%
Reference: Dr. Dobb‟s Journal 2008 Agile Adoption Survey. Retrieved from http://www.ambysoft.com/surveys/agileFebruary2008.html


                        ©2009 Protegra Inc. All rights reserved.
Customize the process

•   The most important advice I could provide is to not take any
    of these methodologies as correct.
•   Instead I would encourage you to read about the different
    methodologies and evaluate which components make sense
    for your company and for the particular project in question.




             ©2009 Protegra Inc. All rights reserved.              45
FAQ
 Q. Silver Bullet?
   A. No

 Q. Cowboy Coding?
   A. No

 Q. How much documentation?
   A. Only what adds value

 Q. Isn’t this just a blank cheque with no controls?
   A. No – disciplined approach

 Q. How do you deal with constant change to the code?
   A. Technical Excellence. TDD, SOLID

 Q. How do you estimate up front?
   A. Same as waterfall, but at a higher level
             ©2009 Protegra Inc. All rights reserved.
FAQ
 Q. Is there a place for analysts?
   A. Yes

 Q. Isn’t Agile unpredictable?
   A. Final outcome is not predictable, but value is

 Q. Is this just mini-waterfall in phases?
  A. No. The team performs all tasks in one day in parallel, not in
     sequence

 Q. What project sizes is this appropriate for?
   A. Survey says…. all sizes

 Q. Is this for Greenfield projects only?
   A. No.
 Q. Can I use Agile practices on waterfall projects?
   A. Yes. Example: Once requirements & design are complete, execute
     the development in iterations
             ©2009 Protegra Inc. All rights reserved.
FAQ
Q. Where to start?
   A.
    - Pick/Customize a methodology
    - Learn it
         • Read, listen, research, ask questions
         • Talk to someone who has done it
    - Try it
         • It won‟t likely be smooth on your first try
         • Don‟t ignore practices without understanding the why
    - Learn a few more methodologies
    - Incorporate your learning into a hybrid that
      works for your company, your teams, your
      projects

             ©2009 Protegra Inc. All rights reserved.
Further Reading
•   Books
     -      Lean Software Development. Tom and Mary Poppendieck (2003)
     -      User Stories Applied. Mike Cohn (2004)
     -      The Art of Agile Development. James Shore and Shane Warden (2008)
     -      The Art of Lean Software Development. Curt Hibbs, Steve Jewett, Mike Sullivan (2009)
•   Sites
     -      www.poppendieck.com
     -      www.leanprimer.com
     -      www.agilemanifesto.org
•   Podcast Sites
     -      http://www.hanselminutes.com/
     -      http://blog.agiletoolkit.com/
•   Newsgroups
     -      leanagile@yahoogroups.com
•   Other links to articles, blogs, videos
     -      www.martinfowler.com/articles/newMethodology.html
     -      http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html
     -      www.infoq.com/Agile2009 (Videos from Agile 2009)
     -      http://www.netobjectives.com/files/BusinessCaseForAgility.pdf (requires account registration)
     -      http://groups.google.com/group/agile-developer-skills/web/draft-summary-of-chicago-meeting?hl=en&pli=1
     -      http://www.agilemanifesto.org/history.html - History of the Manifesto
     -      http://www.devx.com/architect/Article/32836/0/page/4 - comparison of seven popular agile methodologies



                   ©2009 Protegra Inc. All rights reserved.
Q&A




      ©2009 Protegra Inc. All rights reserved.
Thank You!

Name: Terry Bunio
Role: Principal Consultant

E-mail: terry.bunio@protegra.com
Main: 204-956-2727

www.protegra.com




       ©2009 Protegra Inc. All rights reserved.      51

Más contenido relacionado

La actualidad más candente

Agile and the Seven Sins of Project Management
Agile and the Seven Sins of Project ManagementAgile and the Seven Sins of Project Management
Agile and the Seven Sins of Project ManagementMike Cohn
 
Building an Agile framework that fits your organisation
Building an Agile framework that fits your organisationBuilding an Agile framework that fits your organisation
Building an Agile framework that fits your organisationKurt Solarte
 
Thezenofscrum1 090221154550-phpapp01
Thezenofscrum1 090221154550-phpapp01Thezenofscrum1 090221154550-phpapp01
Thezenofscrum1 090221154550-phpapp01Dani Llamazares
 
Starting out with Scrum
Starting out with ScrumStarting out with Scrum
Starting out with ScrumJoshua Partogi
 
Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts Yuval Yeret
 
Copenhagen 121127 - Lars Irenius
Copenhagen 121127 - Lars IreniusCopenhagen 121127 - Lars Irenius
Copenhagen 121127 - Lars IreniusKnowit_TM
 
Agile Practices - eXtreme Programming
Agile Practices - eXtreme ProgrammingAgile Practices - eXtreme Programming
Agile Practices - eXtreme ProgrammingAniruddha Chakrabarti
 
extreme Programming
extreme Programmingextreme Programming
extreme ProgrammingBilal Shah
 
Primer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUMPrimer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUMJoe Riego
 
Agile Software Development with Scrum – Introduction
Agile Software Development with Scrum – IntroductionAgile Software Development with Scrum – Introduction
Agile Software Development with Scrum – IntroductionBlackvard
 
Introduction to Extreme Programming
Introduction to Extreme ProgrammingIntroduction to Extreme Programming
Introduction to Extreme ProgrammingNaresh Jain
 
Learn Scrum Engineering in 5 minutes
Learn Scrum Engineering in 5 minutesLearn Scrum Engineering in 5 minutes
Learn Scrum Engineering in 5 minutesguest035e0d
 
Adm Initial Proposal
Adm Initial ProposalAdm Initial Proposal
Adm Initial Proposalcfry
 
PRINCE2 + AGILE = SUCCESS
PRINCE2 + AGILE = SUCCESSPRINCE2 + AGILE = SUCCESS
PRINCE2 + AGILE = SUCCESSJens Hoffmann
 
Agile software development
Agile software developmentAgile software development
Agile software developmentRajesh Piryani
 

La actualidad más candente (20)

Agile and the Seven Sins of Project Management
Agile and the Seven Sins of Project ManagementAgile and the Seven Sins of Project Management
Agile and the Seven Sins of Project Management
 
Building an Agile framework that fits your organisation
Building an Agile framework that fits your organisationBuilding an Agile framework that fits your organisation
Building an Agile framework that fits your organisation
 
Thezenofscrum1 090221154550-phpapp01
Thezenofscrum1 090221154550-phpapp01Thezenofscrum1 090221154550-phpapp01
Thezenofscrum1 090221154550-phpapp01
 
Starting out with Scrum
Starting out with ScrumStarting out with Scrum
Starting out with Scrum
 
Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts Crossing the Chasm & Pull-based change interactive workshop handouts
Crossing the Chasm & Pull-based change interactive workshop handouts
 
Copenhagen 121127 - Lars Irenius
Copenhagen 121127 - Lars IreniusCopenhagen 121127 - Lars Irenius
Copenhagen 121127 - Lars Irenius
 
Agile & Scrum Training
Agile & Scrum TrainingAgile & Scrum Training
Agile & Scrum Training
 
Agile Practices - eXtreme Programming
Agile Practices - eXtreme ProgrammingAgile Practices - eXtreme Programming
Agile Practices - eXtreme Programming
 
extreme Programming
extreme Programmingextreme Programming
extreme Programming
 
why agile?
why agile?why agile?
why agile?
 
Primer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUMPrimer on Agile Project Management and SCRUM
Primer on Agile Project Management and SCRUM
 
Agile Software Development with Scrum – Introduction
Agile Software Development with Scrum – IntroductionAgile Software Development with Scrum – Introduction
Agile Software Development with Scrum – Introduction
 
Agile Methodologies
Agile MethodologiesAgile Methodologies
Agile Methodologies
 
Scrum checklist
Scrum checklistScrum checklist
Scrum checklist
 
Introduction to Extreme Programming
Introduction to Extreme ProgrammingIntroduction to Extreme Programming
Introduction to Extreme Programming
 
India Agile Week 2015
India Agile Week 2015India Agile Week 2015
India Agile Week 2015
 
Learn Scrum Engineering in 5 minutes
Learn Scrum Engineering in 5 minutesLearn Scrum Engineering in 5 minutes
Learn Scrum Engineering in 5 minutes
 
Adm Initial Proposal
Adm Initial ProposalAdm Initial Proposal
Adm Initial Proposal
 
PRINCE2 + AGILE = SUCCESS
PRINCE2 + AGILE = SUCCESSPRINCE2 + AGILE = SUCCESS
PRINCE2 + AGILE = SUCCESS
 
Agile software development
Agile software developmentAgile software development
Agile software development
 

Similar a Introduction to lean and agile

PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-i
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-iPMI-ACP Lesson 01 Nugget 2 Agile Methodologies-i
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-iThanh Nguyen
 
Scaled Professional Srum and Nexus on the Scrum User Group Berlin
Scaled Professional Srum and Nexus on the Scrum User Group BerlinScaled Professional Srum and Nexus on the Scrum User Group Berlin
Scaled Professional Srum and Nexus on the Scrum User Group BerlinJerónimo Palacios
 
The Extreme Programming (XP) Model
The Extreme Programming (XP) ModelThe Extreme Programming (XP) Model
The Extreme Programming (XP) ModelDamian T. Gordon
 
Scrum Day Europe 2015 - Scaled Professional Scrum
Scrum Day Europe 2015 - Scaled Professional ScrumScrum Day Europe 2015 - Scaled Professional Scrum
Scrum Day Europe 2015 - Scaled Professional ScrumGunther Verheyen
 
Spira plan overview presentation
Spira plan overview presentationSpira plan overview presentation
Spira plan overview presentationTrabalistra Bagaz
 
Getting Agile with Srum
Getting Agile with SrumGetting Agile with Srum
Getting Agile with SrumMike Cohn
 
Agile & SCRUM basics
Agile & SCRUM basicsAgile & SCRUM basics
Agile & SCRUM basicsArun R
 
Scaled Professional Scrum - Scrum Days Poland 2015
Scaled Professional Scrum - Scrum Days Poland 2015Scaled Professional Scrum - Scrum Days Poland 2015
Scaled Professional Scrum - Scrum Days Poland 2015Gunther Verheyen
 
eXtreme programming (XP) - An Overview
eXtreme programming (XP) - An OvervieweXtreme programming (XP) - An Overview
eXtreme programming (XP) - An OverviewGurtej Pal Singh
 
Agile development
Agile developmentAgile development
Agile developmentJoshuaU1
 
Introduction To Agile Refresh Savannah July20 2010 V1 4
Introduction To Agile Refresh Savannah July20 2010 V1 4Introduction To Agile Refresh Savannah July20 2010 V1 4
Introduction To Agile Refresh Savannah July20 2010 V1 4Marvin Heery
 
Getting agile-with-scrum-ndc-2104
Getting agile-with-scrum-ndc-2104Getting agile-with-scrum-ndc-2104
Getting agile-with-scrum-ndc-2104somyaadwan
 
Getting Agile with Srum
Getting Agile with SrumGetting Agile with Srum
Getting Agile with SrumMike Cohn
 

Similar a Introduction to lean and agile (20)

PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-i
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-iPMI-ACP Lesson 01 Nugget 2 Agile Methodologies-i
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-i
 
Scaled Professional Srum and Nexus on the Scrum User Group Berlin
Scaled Professional Srum and Nexus on the Scrum User Group BerlinScaled Professional Srum and Nexus on the Scrum User Group Berlin
Scaled Professional Srum and Nexus on the Scrum User Group Berlin
 
4. ch 3-agile process
4. ch 3-agile process4. ch 3-agile process
4. ch 3-agile process
 
The Extreme Programming (XP) Model
The Extreme Programming (XP) ModelThe Extreme Programming (XP) Model
The Extreme Programming (XP) Model
 
Extreme programming
Extreme programmingExtreme programming
Extreme programming
 
module I.pptx
module I.pptxmodule I.pptx
module I.pptx
 
Scrum Day Europe 2015 - Scaled Professional Scrum
Scrum Day Europe 2015 - Scaled Professional ScrumScrum Day Europe 2015 - Scaled Professional Scrum
Scrum Day Europe 2015 - Scaled Professional Scrum
 
Spira plan overview presentation
Spira plan overview presentationSpira plan overview presentation
Spira plan overview presentation
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 
Scrum and Agile SDLC 101
Scrum and Agile SDLC 101Scrum and Agile SDLC 101
Scrum and Agile SDLC 101
 
Getting Agile with Srum
Getting Agile with SrumGetting Agile with Srum
Getting Agile with Srum
 
Introduction to Software Engineering
Introduction to Software EngineeringIntroduction to Software Engineering
Introduction to Software Engineering
 
Agile & SCRUM basics
Agile & SCRUM basicsAgile & SCRUM basics
Agile & SCRUM basics
 
Scaled Professional Scrum - Scrum Days Poland 2015
Scaled Professional Scrum - Scrum Days Poland 2015Scaled Professional Scrum - Scrum Days Poland 2015
Scaled Professional Scrum - Scrum Days Poland 2015
 
eXtreme programming (XP) - An Overview
eXtreme programming (XP) - An OvervieweXtreme programming (XP) - An Overview
eXtreme programming (XP) - An Overview
 
Agile development
Agile developmentAgile development
Agile development
 
Scrum and DevOps training
Scrum and DevOps trainingScrum and DevOps training
Scrum and DevOps training
 
Introduction To Agile Refresh Savannah July20 2010 V1 4
Introduction To Agile Refresh Savannah July20 2010 V1 4Introduction To Agile Refresh Savannah July20 2010 V1 4
Introduction To Agile Refresh Savannah July20 2010 V1 4
 
Getting agile-with-scrum-ndc-2104
Getting agile-with-scrum-ndc-2104Getting agile-with-scrum-ndc-2104
Getting agile-with-scrum-ndc-2104
 
Getting Agile with Srum
Getting Agile with SrumGetting Agile with Srum
Getting Agile with Srum
 

Más de Terry Bunio

Uof m empathys role
Uof m empathys roleUof m empathys role
Uof m empathys roleTerry Bunio
 
Data modeling tips from the trenches
Data modeling tips from the trenchesData modeling tips from the trenches
Data modeling tips from the trenchesTerry Bunio
 
Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015
Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015
Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015Terry Bunio
 
Pr dc 2015 sql server is cheaper than open source
Pr dc 2015 sql server is cheaper than open sourcePr dc 2015 sql server is cheaper than open source
Pr dc 2015 sql server is cheaper than open sourceTerry Bunio
 
Asper database presentation - Data Modeling Topics
Asper database presentation - Data Modeling TopicsAsper database presentation - Data Modeling Topics
Asper database presentation - Data Modeling TopicsTerry Bunio
 
The final frontier v3
The final frontier v3The final frontier v3
The final frontier v3Terry Bunio
 
Ssrs and sharepoint there and back again - SQL SAT Fargo
Ssrs and sharepoint   there and back again - SQL SAT FargoSsrs and sharepoint   there and back again - SQL SAT Fargo
Ssrs and sharepoint there and back again - SQL SAT FargoTerry Bunio
 
A data driven etl test framework sqlsat madison
A data driven etl test framework sqlsat madisonA data driven etl test framework sqlsat madison
A data driven etl test framework sqlsat madisonTerry Bunio
 
Dimensional modeling primer
Dimensional modeling primerDimensional modeling primer
Dimensional modeling primerTerry Bunio
 
SSRS and Sharepoint there and back again
SSRS and Sharepoint   there and back againSSRS and Sharepoint   there and back again
SSRS and Sharepoint there and back againTerry Bunio
 
The final frontier
The final frontierThe final frontier
The final frontierTerry Bunio
 
Role of an agile pm
Role of an agile pmRole of an agile pm
Role of an agile pmTerry Bunio
 
Pmi june 5th 2007
Pmi june 5th 2007Pmi june 5th 2007
Pmi june 5th 2007Terry Bunio
 
Pmi sac november 20
Pmi sac november 20Pmi sac november 20
Pmi sac november 20Terry Bunio
 
Iiba.november.09
Iiba.november.09Iiba.november.09
Iiba.november.09Terry Bunio
 
Sdec11 when user stories are not enough
Sdec11 when user stories are not enoughSdec11 when user stories are not enough
Sdec11 when user stories are not enoughTerry Bunio
 

Más de Terry Bunio (20)

Uof m empathys role
Uof m empathys roleUof m empathys role
Uof m empathys role
 
Ictam big data
Ictam big dataIctam big data
Ictam big data
 
Data modeling tips from the trenches
Data modeling tips from the trenchesData modeling tips from the trenches
Data modeling tips from the trenches
 
#YesEstimates
#YesEstimates#YesEstimates
#YesEstimates
 
Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015
Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015
Dimensional modeling primer - SQL Saturday Madison - April 11th, 2015
 
Pr dc 2015 sql server is cheaper than open source
Pr dc 2015 sql server is cheaper than open sourcePr dc 2015 sql server is cheaper than open source
Pr dc 2015 sql server is cheaper than open source
 
Breaking data
Breaking dataBreaking data
Breaking data
 
Asper database presentation - Data Modeling Topics
Asper database presentation - Data Modeling TopicsAsper database presentation - Data Modeling Topics
Asper database presentation - Data Modeling Topics
 
The final frontier v3
The final frontier v3The final frontier v3
The final frontier v3
 
Ssrs and sharepoint there and back again - SQL SAT Fargo
Ssrs and sharepoint   there and back again - SQL SAT FargoSsrs and sharepoint   there and back again - SQL SAT Fargo
Ssrs and sharepoint there and back again - SQL SAT Fargo
 
A data driven etl test framework sqlsat madison
A data driven etl test framework sqlsat madisonA data driven etl test framework sqlsat madison
A data driven etl test framework sqlsat madison
 
Dimensional modeling primer
Dimensional modeling primerDimensional modeling primer
Dimensional modeling primer
 
SSRS and Sharepoint there and back again
SSRS and Sharepoint   there and back againSSRS and Sharepoint   there and back again
SSRS and Sharepoint there and back again
 
The final frontier
The final frontierThe final frontier
The final frontier
 
Role of an agile pm
Role of an agile pmRole of an agile pm
Role of an agile pm
 
Estimating 101
Estimating 101Estimating 101
Estimating 101
 
Pmi june 5th 2007
Pmi june 5th 2007Pmi june 5th 2007
Pmi june 5th 2007
 
Pmi sac november 20
Pmi sac november 20Pmi sac november 20
Pmi sac november 20
 
Iiba.november.09
Iiba.november.09Iiba.november.09
Iiba.november.09
 
Sdec11 when user stories are not enough
Sdec11 when user stories are not enoughSdec11 when user stories are not enough
Sdec11 when user stories are not enough
 

Último

A Glance At The Java Performance Toolbox
A Glance At The Java Performance ToolboxA Glance At The Java Performance Toolbox
A Glance At The Java Performance ToolboxAna-Maria Mihalceanu
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Nikki Chapple
 
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...BookNet Canada
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Mark Goldstein
 
React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...Karmanjay Verma
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...itnewsafrica
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observabilityitnewsafrica
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructureitnewsafrica
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 

Último (20)

A Glance At The Java Performance Toolbox
A Glance At The Java Performance ToolboxA Glance At The Java Performance Toolbox
A Glance At The Java Performance Toolbox
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
 
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
 
React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 

Introduction to lean and agile

  • 1. Introduction to Lean and Agile Software Development ©2008 Protegra Inc. All rights reserved.
  • 2. Agenda • What is the problem? • What is Agile? - Agile Manifesto - Agile Principles • Agile Methodologies • Agile Software Development Standards - Iteration Planning and Estimating - Key Meetings - Role of Project Management - Role of Requirements Management - Tools to assist Project and Requirements Management - Role of Software Development - Role of Testing • Is it Working? • Customize the Process • FAQ/Q&A ©2009 Protegra Inc. All rights reserved.
  • 3. What is the problem? • Standish Group – CHAOS Study of IT project success 60 50 40 Succeeded 30 Challenged 20 Failed 10 0 1994 1996 1998 2000 2002 2004 ©2009 Protegra Inc. All rights reserved.
  • 4. What is the problem? Cost overruns + Schedule overruns + Failed or Cancelled projects + Rigid processes + Change Management (that acts like Change Restriction) + Late Learning process + Building the wrong thing = Lack of Trust in IT ©2009 Protegra Inc. All rights reserved.
  • 5. Agile Manifesto Snowbird ski resort - Feb 2001 We are uncovering better ways of developing software by doing it and helping others do it. Through this work we have come to value: Individuals and interactions over processes and tools Working software over comprehensive documentation Customer collaboration over contract negotiation Responding to change over following a plan That is, while there is value in the items on the right, we value the items on the left more. Reference: http://www.agilemanifesto.org ©2009 Protegra Inc. All rights reserved.
  • 6. Agile Manifesto: 12 Principles 1. Satisfy the customer through early and continuous delivery - Shorten the distance between requirements gathering and customer feedback 2. Welcome changing requirements, even late in development - Shorten the distance between conceiving and implementing an important change 3. Deliver working software frequently - Shorten the distance between system-as-desired and system-as- built 4. Business people and developers work together daily - Shorten the distance (time) between a question and its answer Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html ©2009 Protegra Inc. All rights reserved.
  • 7. Agile Manifesto: 12 Principles 4. Build projects around motivated individuals - Shorten the distance between intent and action, issue & resolution 5. Convey information via face-to-face information - Shorten the distance (space) between a question and its answer Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html ©2009 Protegra Inc. All rights reserved.
  • 8. Agile Manifesto: 12 Principles 7. Working software is the primary measure of progress - Shorten the distance between thinking we‟re done and knowing we‟re done 8. Maintain a constant pace indefinitely - Shorten the distance between the amount of unproductive time spent building software and a satisfying work day 9. Give continuous attention to technical excellence - Shorten the distance between implementation and ideal Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html ©2009 Protegra Inc. All rights reserved.
  • 9. Agile Manifesto: 12 Principles 10. Simplify: maximize the amount of work not done - Shorten the distance between comprehension and completion 11. Teams self-organize - Shorten the distance between need and action 12. Teams retrospect and tune their behaviour - Shorten the distance between introspection and adaptation Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html ©2009 Protegra Inc. All rights reserved.
  • 10. Agile Methodologies • Scrum - founded by Ken Schwaber & Jeff Sutherland • Extreme Programming (XP) - founded by Kent Beck, Ward Cunningham, Ron Jeffries • Crystal - founded by Alistair Cockburn • Lean Software Development - founded by Tom & Mary Poppendieck • Others… - FDD - DSDM Reference: Agile in a Flash. Retrieved Sept 2009 from http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html ©2009 Protegra Inc. All rights reserved.
  • 11. Top Three Methodologies • Lets look at the characteristics of the top three Agile Methodologies - Scrum - Extreme Programming - Lean Software Development ©2009 Protegra Inc. All rights reserved. 11
  • 12. Scrum • Scrum is a process skeleton that includes a set of practices and predefined roles. - Pigs - Chickens • The main roles in Scrum are the ScrumMaster who maintains the processes and works similarly to a project manager, the Product Owner who represents the stakeholders, and the Team which includes the developers. ©2009 Protegra Inc. All rights reserved.
  • 13. Scrum • During each sprint, a 15-30 day period, the team creates an increment of usable software. • The set of user stories that go into a sprint come from the product backlog, which is a prioritized set of high level requirements of work to be done. • Which backlog user stories go into the sprint is determined during the sprint planning meeting. • During a sprint, no one is able to change the sprint backlog, which means that the requirements are frozen for that sprint. After a sprint is completed, the team demonstrates the use of the software. ©2009 Protegra Inc. All rights reserved. 13
  • 14. Scrum • Scrum enables the creation of self-organizing teams by encouraging co-location of all team members, and verbal communication across all team members and disciplines that are involved in the project. • A key principle of Scrum is its recognition that during a project the customers can change their minds about what they want and need (often called requirements churn), and that unpredicted challenges cannot be easily addressed in a traditional predictive or planned manner. ©2009 Protegra Inc. All rights reserved.
  • 15. Extreme Programming • A discipline of software development that follows a specific structure that is designed to simplify and expedite the process of developing new software. Kent Beck developed Extreme Programming to be used with small teams of developers who need to develop software quickly in an environment of rapidly-changing requirements. - Interesting note: Kent Beck‟s first book proposed a rigid form of XP. This has since been changed and the result is a more Agile XP.  ©2009 Protegra Inc. All rights reserved.
  • 16. Extreme Programming • Extreme Programming is based on 12 principles: - The Planning Process -- The desired features of the software, which are communicated by the customer, are combined with cost estimates provided by the programmers to determine what the most important factors of the software are. - Small Releases -- The software is developed in small stages that are updated frequently, typically every two weeks. - Metaphor -- All members on an XP team use common names and descriptions to guide development and communicate. - Simple Design -- The software should include only the code that is necessary to achieve the desired results. - Testing -- Programmers design the tests first and then write the software to fulfill the requirements of the test. The customer also provides tests at each stage to ensure the desired results are achieved. ©2009 Protegra Inc. All rights reserved.
  • 17. Extreme Programming - Refactoring -- XP programmers improve the design of the software through every stage of development instead of waiting until the end of the development and going back to correct flaws. - Pair Programming -- All code is written by a pair of programmers working at the same machine. - Collective Ownership -- Every line of code belongs to every programmer working on the project, so there are no issues of proprietary authorship to slow the project down - Continuous Integration -- The XP team integrates and builds the software system multiple times per day to keep all the programmers at the same stage of the development process at once. - 40-Hour Week -- The XP team does not work excessive overtime to ensure that the team remains well-rested, alert and effective. - On-Site Customer -- The XP project is directed by the customer who is available all the time to answer questions, set priorities and determine requirements of the project. - Coding Standard -- The programmers all write code in the same way. This allows them to work in pairs and to share ownership of the code. ©2009 Protegra Inc. All rights reserved.
  • 18. Extreme Programming Technical Practices • Extreme Programming is essentially Scrum with additional Technical Practices - keep it simple and never add functionality early (YAGNI, Last Responsible Moment), - choose a system metaphor (Domain-Driven Design), - use CRC cards, - create a spike solution (proof of concept), - create acceptance tests, - establish coding standards, ©2009 Protegra Inc. All rights reserved. 18
  • 19. Extreme Programming Technical Practices - code the unit test first and ensure that all code has and passes all unit tests (Test-Driven Development), - program in pairs, - integrate sequentially and often, - own the code collectively, - measure and optimize last, and - create tests to detect bugs. ©2009 Protegra Inc. All rights reserved. 19
  • 20. Lean Software Development • Lean Software Development is the application of lean principles to the craft of software development. So what is Lean? According to the National Institute of Standards and Technology Manufacturing Extensions Partnership’s Lean Network, Lean is: - “A systematic approach to identifying and eliminating waste through continuous improvement, flowing the product at the pull of the customer in pursuit of perfection.” [1] - “Lean Software Development reduces defects and cycle times while delivering a steady stream of incremental business value.” [2] ©2009 Protegra Inc. All rights reserved.
  • 21. Lean Software Development • Lean Software development is a style of software development that emphasizes customer satisfaction through continuous delivery of functional software. In contrast to traditional software development methods, lean developers liaise continuously with business clients. • Their objective is to deliver working software as frequently as every two weeks during a project, and welcome changes to the requirements in response to evolving business needs. ©2009 Protegra Inc. All rights reserved.
  • 22. Lean Software Development • The most crucial aspect of Lean LifeCycle is the execution of the project in iterations and quick feedback loops possible because of these iterations. It is essential to note that these iterations to not just apply to construction, they also apply to the following tasks: - Project Management and Planning - Analysis - Technical Design - Testing - Deployment ©2009 Protegra Inc. All rights reserved. 22
  • 23. Lean Principles 1. Eliminate Waste The three biggest wastes in software development are: a) Extra Features b) Churn Client received: c) Crossing Boundaries Client needed: Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 24. Lean Principles 2. Create Knowledge Planning is useful. Learning is essential a) Use the Scientific Method b) Standards exist to be Challenged and Improved c) Predictable performance is Driven by Feedback Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 25. Lean Principles 3. Build Quality In If you routinely find defects in your verification process, your process is defective. a) Mistake-Proof Code with Test-Driven Development b) Stop Building Legacy Code c) The Big Bang is Obsolete Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 26. Lean Principles 4. Defer Commitment Abolish the idea that it is a good idea to start development with a complete specification. a) Break Dependencies b) Maintain Options c) Schedule Irreversible Decisions at the Last Responsible Moment Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 27. Lean Principles 5. Deliver Fast Lists and queues are buffers between organizations that simply slow things down. a) Rapid Delivery, High Quality, and Low Cost are Fully Compatible b) Queuing Theory applies to Development, not just Servers c) Limit Work to Capacity Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 28. Lean Principles 6. Respect People Engaged, thinking people provide the most sustainable competitive advantage. a) Teams Thrive on Pride, Commitment, Trust, Applause b) Provide Effective Leadership c) Respect Partners Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 29. Lean Principles 7. Improve the System Brilliant products emerge from a unique combination of opportunity and technology. a) Focus on the Entire Value Stream b) Deliver a Complete Product c) Measure UP Reference: Lean Software Development Principles. Retrieved Sept 2009 from http://www.poppendieck.com ©2009 Protegra Inc. All rights reserved.
  • 30. Agile Software Development Standards • The following roles and activities are done in a standard way in all Agile Methodologies: - Iteration Planning and Estimating - Key Meetings - Role of Project Management - Role of Requirements Management - Tools to assist Project and Requirements Management - Role of Software Development - Role of Testing ©2009 Protegra Inc. All rights reserved. 30
  • 31. Iteration Planning and Estimating • Iteration planning is ‘the’ key planning initiative. Iterations need to be planned in conjunction with the client to accomplish the following: • Deliver functionality to define the pace of the project • Deliver functionality to deliver value to the client • Deliver functionality to reduce and minimize risk for the entire project • Lessons learned from one iteration must feed into subsequent iterations so that we don‟t execute the project in iterations with similar results, but that we execute the project in iterations with better results. ©2009 Protegra Inc. All rights reserved.
  • 32. Initial Planning and Estimating • Initial Planning and estimating needs to be done - Need detailed deliverable or task levels estimates - Resource planning - Milestone based - Sometimes even a WBS structure based on project reporting requirements • This should be required for Agile or Lean projects. • Agile or Lean should not be an open cheque where estimates and milestones are not planned and approved up front - Some proponents promote that agile estimates should only be given after team „Velocity‟ is determined ©2009 Protegra Inc. All rights reserved. 32
  • 33. What is this ‘Team Velocity’ I hear about? • Team Velocity is the sustainable pace that the team can do work - This will change based upon the project and team composition • Velocity should not replace detailed estimating and Project Planning - Detailed Estimating and Project Planning are to plan the project - Velocity measurement and refinement are used to manage an executing project - BOTH are required for a successful project. ©2009 Protegra Inc. All rights reserved. 33
  • 34. Estimation Levels • Estimating should be done at multiple levels to gain confidence and increase estimate reliability • There are 5 levels of estimating - Task Level - Deliverable Level - Schedule Level - Monte Carlo Simulation - Planning Poker Sessions (Wide Band Delphi) ©2009 Protegra Inc. All rights reserved. 34
  • 35. What is this ‘Planning Poker ’ I hear about? • Planning Poker is a process whereby the entire team estimate objects using card decks. • Planning Poker sessions should be held for each iteration. • A baseline is first established estimating an item that there is high estimating confidence in. (i.e. a simple CRUD screen) - Subsequent items are then estimated in increments of that first baseline. (i.e. This screen would take the effort of 3 base screens to develop) - Everyone chooses a card and then flips it over the same time. - The team then discusses the difference in opinions why people estimated differently. The team then has to come to consensus on the estimate to be used. - While time consuming, it addresses one of the main issues for project success. Proper estimating. • Planning Poker enables the sharing of estimating expertise and knowledge ©2009 Protegra Inc. All rights reserved. 35
  • 36. Key Meetings • The following key meetings are required: - Project Kick off - Iteration kick off - Daily scrums or huddles • What did you do yesterday • What are you doing today • What issues do you have • 2 minute limit per person - Iteration Retrospectives - Iteration Planning and Estimating ©2009 Protegra Inc. All rights reserved. 36
  • 37. Role of Project Management • Iteration Planning • Issue Management • Risk Management • Change Management is required even more - Different focus. The focus is how I can get the client the MOST functionality by following the Change Management process. May involve: • Trading requirements • Eliminating Requirements • Change Requests for new budget or schedule if required • Sometimes the perception exists that Agile or Lean projects do not require the same level of Change Management. This is an incorrect perception. - Sometimes Iterative projects actually have less Change Management than water fall projects. - Projects that are doing less Change Management than required are not „being lean‟, they are being misguided. ©2009 Protegra Inc. All rights reserved. 37
  • 38. Role of Project Management • Increased communication and visibility - Visual Project Management - Visual Project Dashboards - Visual Status Reporting ©2009 Protegra Inc. All rights reserved. 38
  • 39. Requirements Management • Business Analysts are the liaison to the business needs and desires. • Requirements Management and traceability is even more important for agile projects as there is the possibility of increased change • This makes the role of business and systems analysis critical to the success of the projects • The focus is on the ‘right’ amount of documentation. • Sometimes the perception exists that Agile or Lean projects do not document requirements. This is an incorrect perception. - Projects should define what the appropriate level of documentation is on a case by case basis. (within required guidelines) - Projects that are doing less documentation than required are not „being lean‟, they are being misguided. ©2009 Protegra Inc. All rights reserved. 39
  • 40. Requirements Management • Requirements must be Test Case Driven. - Instead of descriptions as to what the software needs to do, the requirements should first list what test cases will ensure the software is operating correctly. - This should be the first section in every specification or use case - This will then feed into automated test cases and be a living document that will define the software - There is less ambiguity in test cases than textual descriptions ©2009 Protegra Inc. All rights reserved. 40
  • 41. Tools to assist Project and Requirements Management • Many free or affordable tools are available to assist Agile or Lean Projects. - www.rallydev.com - www.targetprocess.com - www.versionone.com - www.thoughtworks.com/mingle • This is due to the fact that MS Project is an ok project planning tool, but not a great tool to manage a project while it is executing. (especially Agile or Lean Projects) ©2009 Protegra Inc. All rights reserved. 41
  • 42. Role of Software Development • The following are important aspects of software development in an Agile or Lean Project: - Team-Based Design - Resources are multi-disciplined - Pull system for task assignment - Iterative Development • Each development should be able to be implemented in Production. If not, it is not Iterative Development. - Automated Unit Testing • NUnit/Junit - Continuous Builds/Continuous Build Servers ©2009 Protegra Inc. All rights reserved. 42
  • 43. Role of Testing • Testing is a critical component in Agile or Lean project. (like all Waterfall Projects) • The Test Phase should be planned very diligently and in a very detailed manner. - Resist the urge to have the iterations tested in an unstructured way. This only delays the discovery of defects. - A Test Charter, Test Strategy, and Test Plans are all required. - Automated System Integration Tests and User Acceptance Tests are mandatory • Continuous Integration is mandatory. This is distinct from Continuous builds. - Continuous builds are the daily builds and execution of unit test cases to ensure ongoing development has not introduced new development issues - Continuous integrations are the daily builds and execution of regression test cases to ensure no major application functionality issues exist. ©2009 Protegra Inc. All rights reserved. 43
  • 44. Is it working? Dr. Dobb‟s Journal – Agile Adoption Survey in 2008 • Effectiveness of agile software development compared with traditional approaches: Cost of System Development Business Stakeholder Satisfaction Higher No Change Quality Lower Productivity 0% 20% 40% 60% 80% 100% Reference: Dr. Dobb‟s Journal 2008 Agile Adoption Survey. Retrieved from http://www.ambysoft.com/surveys/agileFebruary2008.html ©2009 Protegra Inc. All rights reserved.
  • 45. Customize the process • The most important advice I could provide is to not take any of these methodologies as correct. • Instead I would encourage you to read about the different methodologies and evaluate which components make sense for your company and for the particular project in question. ©2009 Protegra Inc. All rights reserved. 45
  • 46. FAQ Q. Silver Bullet? A. No Q. Cowboy Coding? A. No Q. How much documentation? A. Only what adds value Q. Isn’t this just a blank cheque with no controls? A. No – disciplined approach Q. How do you deal with constant change to the code? A. Technical Excellence. TDD, SOLID Q. How do you estimate up front? A. Same as waterfall, but at a higher level ©2009 Protegra Inc. All rights reserved.
  • 47. FAQ Q. Is there a place for analysts? A. Yes Q. Isn’t Agile unpredictable? A. Final outcome is not predictable, but value is Q. Is this just mini-waterfall in phases? A. No. The team performs all tasks in one day in parallel, not in sequence Q. What project sizes is this appropriate for? A. Survey says…. all sizes Q. Is this for Greenfield projects only? A. No. Q. Can I use Agile practices on waterfall projects? A. Yes. Example: Once requirements & design are complete, execute the development in iterations ©2009 Protegra Inc. All rights reserved.
  • 48. FAQ Q. Where to start? A. - Pick/Customize a methodology - Learn it • Read, listen, research, ask questions • Talk to someone who has done it - Try it • It won‟t likely be smooth on your first try • Don‟t ignore practices without understanding the why - Learn a few more methodologies - Incorporate your learning into a hybrid that works for your company, your teams, your projects ©2009 Protegra Inc. All rights reserved.
  • 49. Further Reading • Books - Lean Software Development. Tom and Mary Poppendieck (2003) - User Stories Applied. Mike Cohn (2004) - The Art of Agile Development. James Shore and Shane Warden (2008) - The Art of Lean Software Development. Curt Hibbs, Steve Jewett, Mike Sullivan (2009) • Sites - www.poppendieck.com - www.leanprimer.com - www.agilemanifesto.org • Podcast Sites - http://www.hanselminutes.com/ - http://blog.agiletoolkit.com/ • Newsgroups - leanagile@yahoogroups.com • Other links to articles, blogs, videos - www.martinfowler.com/articles/newMethodology.html - http://agileinaflash.blogspot.com/2009/08/12-principles-for-agile-software.html - www.infoq.com/Agile2009 (Videos from Agile 2009) - http://www.netobjectives.com/files/BusinessCaseForAgility.pdf (requires account registration) - http://groups.google.com/group/agile-developer-skills/web/draft-summary-of-chicago-meeting?hl=en&pli=1 - http://www.agilemanifesto.org/history.html - History of the Manifesto - http://www.devx.com/architect/Article/32836/0/page/4 - comparison of seven popular agile methodologies ©2009 Protegra Inc. All rights reserved.
  • 50. Q&A ©2009 Protegra Inc. All rights reserved.
  • 51. Thank You! Name: Terry Bunio Role: Principal Consultant E-mail: terry.bunio@protegra.com Main: 204-956-2727 www.protegra.com ©2009 Protegra Inc. All rights reserved. 51