12. Performance comparison with peer group Power Journal -Journal entry addressing work done, questions, arrangements, & updates ETC. Overall performance Direct monitoring
18. Time Development & Testing M1 I= 30 Development & Testing M2 Start Discussing different ideas C= 20 D= 20 Development & Testing M3 J= 30 A0 = 35 B = 6 A1 = 63 E = 20 K= 25 Development & Testing M4 Finalise Idea Closure Approval Initiation & Planning F = 20 L= 35 Development & Testing M5 M= 45 G = 20 N= 45 Development & Testing M6 H = 20 Development & Testing M7 Note: All the durations are in days. A0 =35 means activity A0 has duration of 35 days Critical path – A0- A-B-G-M and A0-A-B-H-N