SlideShare una empresa de Scribd logo
1 de 57
Descargar para leer sin conexión
Adoption of Best Practices for Cable Testing and
Condition Monitoring in the Offshore Renewables Market
Presented by:
Dr Lee Renforth
Managing Director, HVPD Ltd
CONTENTS
• Why do we need improved commissioning testing and
condition monitoring for subsea cables?
• Exploring the options for diagnostic testing as part of the
field acceptance/commissioning tests for subsea cables.
• What options are available for the condition monitoring
(CM) of in-service subsea cables?
• Diagnostic testing and condition monitoring Case Studies
from the Oil and Gas industry.
• How can condition monitoring technology support
condition based management (CBM) of these assets.
Introduction to HVPD Ltd
• HVPD are experts in the field of on-line partial discharge (OLPD) condition monitoring
technology with specific expertise in MV and HV cable monitoring.
• We have over 20 years of experience in testing of in-service MV and HV cables, switchgear,
transformers and motors/generators.
• We supply portable and permanent OLPD diagnostic test and continuous monitoring solutions,
and a complimentary range of on-site test services and training.
• Five main market sectors: Oil & Gas, Renewables, Transmission & Distribution, Shipping and
Generation.
Introduction to HVPD Ltd
HVPD’s Subsea Cable Clients
HVDC & HVAC Interconnector Owners – Manx 90kV 108km HVAC Interconnector
© Google
HVPD’s Subsea Cable Clients
Oil and Gas Operators – 33kV Cables from Deepwater Offshore Wind Turbines
HVPD’s Subsea Cable Clients
Offshore Wind Farm (OWF) HVAC Export Cables & 33kV Inter-array Cables
Subsea MV and HV Cable Faults
Common Causes
• Incorrect workmanship of the cable accessories leading to partial discharge,
electrical tracking and finally complete insulation failure.
• Mechanical damage caused by poor installation practices including damage to
the cable (from jack-up vessels, anchors, etc.) and/or poor quality cable
mechanical protection of cable joints leading to scour and mechanical stressing.
• Thermal damage caused by poor bonding of cable earthing system and/or
water ingress that leads to localised heating and thermal breakdown.
‘TEAM’ Stresses for Subsea Power Cables
THERMAL
‘Thermal runaway’ problems can occur in
cables where there are high circulating
currents and local high resistance points.
ELECTRICAL
This is the No.1 cause of cable faults
occurring within the first 3 years of service,
typically due to incorrect installation of the
cable accessories.
AMBIENT
The effects of mechanical ‘wear and tear’
including ‘scour’ caused by movement of the
subsea cables with tidal and current changes.
MECHANICAL
Many subsea cable failures are caused by
mechanical damage caused by poor practice
when installing and ‘pulling-in’ the cables.
Introduction to Partial Discharge
Why test for partial discharge?
PD activity is an indication of an ‘incipient fault’ in HV
insulation and is widely regarded as the best ‘early
warning’ indicator of insulation deterioration.
The detection of PD at an early stage enables preventative
maintenance action to avoid unplanned outages.
What is partial discharge?
“A localised electrical discharge that only partially
bridges the insulation between conductors and which
can or can not occur adjacent to a conductor”
IEC60270 Definition
Most Likely Sites of PD Activity in Subsea Cables
132 kV Onshore Cable Termination
Failed and Exploded Outdoor Porcelain Cable Sealing End
33 kV OWF Export Cable Joint – this joint had been exhibiting
high levels of PD and was replaced and removed from service
110kV Transformer Cable Terminations
Left – photo showing PD ‘scorching’, Right – photo of a failed termination
Tracking and ‘scorching’ on a 110 kV Termination
(PD detected before failure)
A Failed 110 kV Termination
(Same type as opposite)
Reliability Centred Maintenance (RCM) ‘Bathtub Curve’
Steady State
Failure
‘Infant Mortality’
Phase
3 Years 20-50 Years
Infant Mortality Steady State Failure
End of Life
‘Wear-out’
Time
FailureRate
Why and When to Perform PD Testing
New Equipment
At Manufacture
• Quality Assurance
• Type/routine tests, e.g. IEEE/IEC
standards – test to less than 5pC on the
cables
At Commissioning
• To check for transport damage
• To ensure the installation of the cable
accessories have made to a good
standard (these are the weak points in
the cable system)
VLF and Soak Test Commissioning Tests for 33 kV Cables
• To detect any poor workmanship and/or
installation damage with a particular
focus on the cable accessories.
• Partial Discharge (PD) and Tan Delta
(TD) diagnostic acceptance tests should
be made in combination with the VLF
voltage withstand test (from 2.0 to 3.0 U0
i.e. 38.2–57.3 kVrms for 33 kV cables).
• This test is combined with an off-line,
electrical Time Domain Reflectometry
(TDR) testing to support both future ‘PD
Mapping’ (PD site localisation) and/or
rapid fault location in the event of a cable
fault.
Factory Testing of Cable Systems
• Cable components tested individually.
• Cable cores should be tested both
before and then after their assembly
into the 3-core subsea cable.
• High sensitivity measurements in a
‘low-noise’ environment are required,
typically to accuracies of <5pC.
• This requires a Faraday Cage,
electromagnetically screened test room
to achieve this sensitivity.
• The Faraday Cage HV test facility
shown opposite can measure PD
activity down to 1pC.
Cable HV Withstand Voltage Field Acceptance Test Options
VLF (Very Low Frequency) (0.05–0.1 Hz)
example supplier: Baur - Austria, b2hv - Austria
Variable Frequency Resonant Test
Systems (RTS) (20-300Hz)
example supplier: High-Volt – Germany
Damped AC / Oscillating Wave (OWTS)
example suppliers: Seitz, SEBAkmt - Germany
24 Hour Soak Test (at U0)
No external power supply is required although
extended, continuous 24-hour OLPD monitoring is
necessary during the duration of the soak test.
Manufacturing
Damage
Mistake
Repair
Aging
Acceptance
Testing
Continuous
Monitoring
Transportation Installation
Factory
Testing
Power
frequency
50/60 Hz
Operation
Power frequency 50/60
Hz
From ‘Cradle to Grave’ PD Testing and Monitoring Philosophy
Partial Discharge Cable Mapping – PD Site Location along the cable
All
PD Map of Circuit Meols Drive - Graham Road
Location (% along cable)
10510095908580757065605550454035302520151050-5
AllPhasesPD
7,000
6,500
6,000
5,500
5,000
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
The locations of any defects that exhibit PD activity will be detected along the length of
the cable using the technique of time domain reflectometery (TDR).
The PD Map of the cable below shows three (3) main sites of PD activity along the cable.
On-line PD Testing & Monitoring to Support
Planned Maintenance Interventions
Repeat testing before the cable
supplier/jointer warranty runs out!
• It is highly recommended that an on-line
PD test is carried out before the warranty
period expires (typically only 12 months).
Continuous On-line PD (OLPD) monitoring
throughout the service life
• To detect whether PD activity has
initiated during the service life of the
cable/plant
• To support maintenance and operation
decisions, by detecting and localising any
PD activity in in-service cables
• To direct preventative maintenance
interventions.
CONDITION MONITORING OF IN-SERVICE
SUBSEA MV AND HV CABLES
On-line Condition Monitoring Options for Subsea Power Cables
THERMAL
Distributed Temperature Sensing (DTS)
using fibre optic detection technology.
ELECTRICAL
On-line Partial Discharge (OLPD), plus
sheath current and power quality monitoring .
AMBIENT
Vibration monitoring using fibre optic
detection technology.
MECHANICAL
Mechanical strain monitoring using fibre
optic detection technology.
Fibre-Optic Strain, Vibration and Temperature Sensing Solution
• Optoelectronic devices which measure
temperature and strain by means of optical
fibres functioning as linear sensors
• Provides real-time, dynamic temperature and
strain information along the complete length of
power cable for health monitoring.
• Can identify small hot spot locations and
localised mechanical damage without prior
installation knowledge.
• Provides accurate temperature data input for
dynamic cable rating based on actual
“installed” conditions to monitor higher power
flows through the cable.
Fibre optic
monitoring
cable
DTS/Strain
Monitoring
unit
Field
splice
box
Local
splice
box
Subsea 3-core Cable with Built-in Fibre-Optics
• Subsea cables can include up to 4 fibre-optic cables that can be
utilised for distributed temperature, strain and vibration sensing.
• The example below shows a fibre along the cable centreline, and 3
fibres laid up and located in the interstices between the phases.
Offshore High Voltage Network Monitoring System
• OHVMS – ‘holistic’ HV/MV network condition monitoring (CM) system for offshore
cable networks and connected plant (switchgear and transformers).
• The Condition Monitoring (CM) data is used to provide predictive, ‘early warnings’
against ‘incipient’ insulation faults.
• The system helps to avoid unplanned outages, supports preventative
maintenance and reduces the high O&M costs of the OWF electrical networks.
Offshore High Voltage Network Monitoring System
OHVMS Cable Condition Monitoring
Features and Benefits
OHVMS
HOLISTIC
MONITORING
SYSTEM
Power
Quality
Partial
Discharge
Earth
Faults
Loading
Sheath
Currents
Ambient
Conditions
Intelligent
Diagnosis
System Health
Alarms
System
Stability
Alarms
Condition-
Based
Maintenance
SMART Grid
Integration
Dynamic
De-Rating
OHVMS ‘Holistic’ MV/HV Cable Condition Monitoring System
Example – 80 x 3.6MW Turbine Array
An OHVMS monitoring hub (MH1) is
located at the offshore substation
platform (OSP) to monitor:
• 33 kV switchgear
• 33/132 kV transformers
• 33 kV incoming cable ‘strings’
from the turbine arrays
Turbine Monitor Nodes (TMN01–
TMN21) are positioned at strategic
locations (every 3rd turbine) across
the turbine array, to provide complete
network coverage.
OHVMS SMART-Quadplex™ Sensor Location In the Turbine Base
OHVMS SMART-Quadplex™ Sensor Location In the Turbine Nacelle
• A combined electrical state and condition assessment of the health of the
network is provided using SMART-Quadplex™ sensors.
• The sensors and OHVMS monitor can be installed either at the base of the
turbine or in the nacelle, depending on the turbine design.
CASE STUDY 1: ON-LINE PARTIAL DISCHARGE
(OLPD) TESTING, LOCATION, MONITORING WITH
PREVENTATIVE MAINTENANCE ON A 33 KV
OFFSHORE WIND FARM EXPORT CABLE
Case Study 1: Export Cable Circuit Details
• 1.7 km single core XLPE land cable
• 9.6/11.5 km 3-core XLPE subsea cable
OLPD Test and Mapping Data
L1 L2 L3
Cable PD
Phase of Pow er Cycle (deg)
360270180900
PDMagnitude(pC)
0
Cable PD
Phase of Pow er Cycle (deg)
360270180900
PDMagnitude(pC)
0
Cable PD
Phase of Pow er Cycle (deg)
360270180900
PDMagnitude(pC)
10,000
5,000
0
-5,000
-10,000
High levels of PD (of up to 10,000 pC / 10 nC) were
measured from the onshore substation on Circuit
B, Phase L3.
Location (meters)
1,6001,4001,2001,0008006004002000
PDMap© Graph Showing PD Location
Land-sea
Transition
Joint
Joint Pit 7
Switching
Substation
PD Signals Before and After Joint Replacement
Joint 7 with PD
removed and
replacement cable
section installed
Location (meters)
1,6001,4001,2001,0008006004002000
High PD detected on L3
PD Located
Lower-level sporadic PD
signals from different site
after joint replacement
BEFORE
AFTER
Circuit B – Evidence of Surface Tracking and Degradation due
to Poorly-Fitted Heatshrink Stress Control
CASE STUDY 2: INSTALLATION OF AN OLPD
CONDITION MONITORING SYSTEM FOR A 400 KV
ONSHORE GRID CONNECTION CABLE
Continuous OLPD Insulation Condition Monitoring
In-service Equipment
Condition Monitoring throughout the
service life of the cable.
• Continuous OLPD monitoring of the
insulation condition of the cable
network throughout it’s service life.
• Data from the technology supports
Condition-Based Management
(CBM) of critical cable networks.
• Provides increased security and
reliability of electricity supply from
offshore renewables generation.
• Helps to reduce O&M costs through
the avoidance of faults and
unplanned outages.
Sensor Locations at 400 kV Transformer Terminations
HV Cable OLPD Monitor System Drawing
CASE STUDY 3: OLPD TESTING AND
LOCATION ON A DEEPWATER OFFSHORE
WIND TURBINE CONNECTED TO AN OIL &
GAS PLATFORM
Case Study 2: OLPD Testing and Location on a Deepwater
Offshore Wind Turbine connected to an Oil & Gas Platform
Background
• Two deep-water wind turbines supply power exclusively to an oil production platform
situated around 2km away.
• Two on-line PD tests were performed to assess the condition of the 33kV cables from
two turbines to the oil & gas platform.
Test 1 – OLPD Test at 33 kV Switchgear on Platform
Results from Test 1 at 33 kV Switchgear on the Platform
• High PD activity (in excess
of 6,000pC+) was detected
on the Turbine A Feeder.
• Analysis of the PD pulse
data suggested that the
source of the PD activity
was at the far end of the
Turbine A feeder cable.
• OLPD Cable Mapping was
recommended.
Test 2 – PD Test at the Wind Turbine’s 33 kV Switchgear
PD Location at Wind Turbine A
• Test identified the PD source to the cable joint at the top of the
tower close to the 33 kV transformer.
• Measurement of PD pulses showed the source of the PD being
at 52m from the switchgear at Test Point 2.
• The cause of the discharge was meachanical stress due to
insufficient support of the cable joint from the weight of the free-
hanging cable.
CASE STUDY 4: A COMPLETE 33 KV CABLE
NETWORK OLPD SURVEY AND ANALYSIS TO
SUPPORT CONDITION BASED MAINTENANCE (CBM)
DUBAI METRO, DUBAI, UAE
On-line Partial Discharge (OLPD) test and cable
mapping survey of the customer’s 33 kV cable
network was carried out by HVPD engineers
using the HVPD Longshot™ diagnostic test
system.
This testing was carried out in response to a
number catastrophic failures of 33 kV cable joints
within their network which had led to disruption of
the power supply to the Metropolitan rail system.
The purpose of the testing was to measure and locate any PD activity within the
cables with particular focus on the cable joints.
It can be noted that this was a recently installed cable system that had been in-
service for just over 12 months before the faults started to occur.
After four 33kV cable joint faults in 2 months, the client requested a complete
OLPD survey of the network to detect any ‘incipient’ faults on the network.
Background
• On-line Cable PD Mapping using the HVPD Longshot™ test unit and Portable
Transponder technology was used to carry out an on-line condition assessment of
complete 33kV cable network.
• Tests started with calibration testing with pulse injection HFCTs, followed by OLPD
measurements and then cable mapping tests.
OLPD Testing to Support CBM of a 33kV Cable Network
• Cable PD signals of
6,000pC+ were detected on
the Blue Phase with some
‘cross-talk’ (lower magnitude)
on the Red and Yellow
phases.
• The source of PD was
located to Joint Number 2
(Jt2) using the cable
mapping test technique.
• The faulty joint on this cable
was replaced and re-tested
using the HVPD Longshot™
test unit to verify the repair
was good.
33kV Cable Network Test Results I
33kV Cable Network Test Results II
Examples of PD located on two 33kV circuits
Left – PD Located on Red Phase Joint No.1, Right – PD located on Red Phase, Joint No.2
• The network consisted of 104x 33kV that were circuits tested
• High Levels of PD were detected in cable joints on the six of the circuits (6%) as shown in
RED in the Table below, Condition Category, “Major concern, locate PD and then repair”.
• A further five circuits (5%) were in the Orange/Yellow Categor, these were also repaired.
Top 20 ‘Worst Performing 33kV Circuits’
Criticality
Number
Circuit Comments
Peak Cable
PD Level
(pC)
Local PD
Level
(dB)
Cumulative Cable
PD Level
(nC/cycle)
OLPD
Criticality (%)
Maintenance
Action
1. DUB to MPS1 C2 B Phase 25888 <10 247 97.4
Major concern,
locate PD and
then repair or
replace.
2. ABS to AH C2 B / Y Phase 9729 <10 120 90.3
3. BUR to HCC C2 B / Y Phase 3781 <10 12.3 78.7
4. BUR to HCC C1 B / Y Phase 3245 <10 7.9 78.1
5. ABS to AH C1 B / Y Phase 2920 <10 14.4 77.4
6. NHD to QYD C2 R Phase 2849 <10 15.0 76.2
7. ALQ to AHS C2 B Phase 1733 <10 4.6 70.6 Some concern,
repeat test and
regular
monitoring
recommended.
8. MPS3 to BNS C2 R / B Phase 1337 <10 6.4 65.5
9. NHD to QYD C1 R Phase 887 <10 8.8 47.8
10. HCC to CRK C1 Y / B Phase 759 <10 2.5 39.2
11. AHS to SLD Y / R Phase 705 <10 3.1 38.5
12. STD to ABH Y Phase 238 <10 1.0 24.1
Re-test in 12
months.
13. ALR to BNS C1 B Phase 184 <10 0.9 18.6
14. ALR to BRJ No PD detected 0 <10 0 0
15. ALG to PMD No PD detected 0 <10 0 0
16. ALG to KBW No PD detected 0 <10 0 0
17. AQD to AQ2 No PD detected 0 <10 0 0
18. JDD to CRK No PD detected 0 <10 0 0
19. ODM to JDF C1 No PD detected 0 <10 0 0
20. ODM to JDF C2 No PD detected 0 <10 0 0
CONCLUSIONS
Conclusions
• The increasing installation rate of installation of offshore wind farms (OWFs)
in Europe, combined with the high MV and HV cable fault rates reported to
date, has led to a ‘market need’ for better MV/HV cable condition
monitoring (CM) technology.
• Offshore wind farm subsea cable owners need to also consider the use of
diagnostic testing during cable HV withstand/commissioning tests.
• It is proposed that any CM system employed should combine thermal,
electrical, ambient and mechanical monitoring to cover all four of the ‘TEAM’
stresses that effect the reliable operation of the cables.
• The purpose of any CM system is to provide an ‘early warning’ of ‘incipient’
cable insulation faults to enable preventative maintenance interventions to
avoid unplanned outages.
• A move towards Condition Based Management (CBM) of the cable
networks (using data from ‘holistic’ CM technologies) is seen as the key to
reducing the presently high O&M costs to achieve DECC’s target of a 25%
reduction in Levelised Cost of Electricity (LCOE) by 2020.
End of Presentation
Thank you for your time
Q&A?

Más contenido relacionado

La actualidad más candente

Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
Seminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsSeminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsHarshit Bhandari
 
Splicing theory & products
Splicing theory & productsSplicing theory & products
Splicing theory & productsmichaeljmack
 
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)AHMED MOHAMED HEGAB
 
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...Living Online
 
Integrated Earthing Systems
Integrated Earthing SystemsIntegrated Earthing Systems
Integrated Earthing SystemsLeonardo ENERGY
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableLeonardo ENERGY
 
Electrical Substation and Switchyard Design
Electrical Substation and Switchyard DesignElectrical Substation and Switchyard Design
Electrical Substation and Switchyard DesignLiving Online
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2Himmelstern
 
Lightning Arrester Working Principle & Types
Lightning Arrester Working Principle & TypesLightning Arrester Working Principle & Types
Lightning Arrester Working Principle & TypesPower System Operation
 
Cable fault location methods (Megger)
Cable fault location methods (Megger)Cable fault location methods (Megger)
Cable fault location methods (Megger)AHMED MOHAMED HEGAB
 
High voltage technology &amp; insulation testing
High voltage technology &amp; insulation testingHigh voltage technology &amp; insulation testing
High voltage technology &amp; insulation testingZeeshan Akhtar
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-systemAdeoye Okunoye
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 

La actualidad más candente (20)

Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
Seminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsSeminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methods
 
Splicing theory & products
Splicing theory & productsSplicing theory & products
Splicing theory & products
 
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
 
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High voltage Testing of Electrical Equipment for Enginee...
 
Integrated Earthing Systems
Integrated Earthing SystemsIntegrated Earthing Systems
Integrated Earthing Systems
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power Cable
 
Electrical Substation and Switchyard Design
Electrical Substation and Switchyard DesignElectrical Substation and Switchyard Design
Electrical Substation and Switchyard Design
 
Testing
TestingTesting
Testing
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
High voltage underground cables
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
 
IEEE-std80.pdf
IEEE-std80.pdfIEEE-std80.pdf
IEEE-std80.pdf
 
Lightning Arrester Working Principle & Types
Lightning Arrester Working Principle & TypesLightning Arrester Working Principle & Types
Lightning Arrester Working Principle & Types
 
Cable fault location methods (Megger)
Cable fault location methods (Megger)Cable fault location methods (Megger)
Cable fault location methods (Megger)
 
High voltage technology &amp; insulation testing
High voltage technology &amp; insulation testingHigh voltage technology &amp; insulation testing
High voltage technology &amp; insulation testing
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system
 
auto-reclosure
auto-reclosureauto-reclosure
auto-reclosure
 
PARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERSPARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERS
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 

Similar a Offshore Renewables Cable Testing

2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...vutnm94
 
IEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdfIEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdfNitinPandya14
 
Heinputter 2
Heinputter 2Heinputter 2
Heinputter 2Thang Nd
 
Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...HighVoltageDUT
 
P D Measurements On H V Joints
P D  Measurements On  H V JointsP D  Measurements On  H V Joints
P D Measurements On H V JointsAol_Amil
 
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Thorne & Derrick International
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Thorne & Derrick International
 
Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systemsmichaeljmack
 
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Thorne & Derrick International
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTranscat
 
Lightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationLightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationRekaNext Capital
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................hiiarindam
 

Similar a Offshore Renewables Cable Testing (20)

Procedure cable testing
Procedure cable testingProcedure cable testing
Procedure cable testing
 
Deis talk-nov-2014-revised
Deis talk-nov-2014-revisedDeis talk-nov-2014-revised
Deis talk-nov-2014-revised
 
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
2-HVPD-Night-2-On-line-Partial-Discharge-OLPD-Monitoring-of-Complete-HV-Netwo...
 
SebKMT Cable Sheath testers & Fault Locators
SebKMT Cable Sheath testers & Fault LocatorsSebKMT Cable Sheath testers & Fault Locators
SebKMT Cable Sheath testers & Fault Locators
 
IEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdfIEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdf
 
Heinputter 2
Heinputter 2Heinputter 2
Heinputter 2
 
Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...
 
P D Measurements On H V Joints
P D  Measurements On  H V JointsP D  Measurements On  H V Joints
P D Measurements On H V Joints
 
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
 
Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
 
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV Systems
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
ESDEMC CDE IEEE Symposium 2014
ESDEMC CDE IEEE Symposium 2014ESDEMC CDE IEEE Symposium 2014
ESDEMC CDE IEEE Symposium 2014
 
New cv jithesh
New cv jitheshNew cv jithesh
New cv jithesh
 
Lightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationLightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for Instrumentation
 
Time current curves
Time current curvesTime current curves
Time current curves
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................
 

Más de Thorne & Derrick International

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Thorne & Derrick International
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptThorne & Derrick International
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018Thorne & Derrick International
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick InternationalThorne & Derrick International
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-AThorne & Derrick International
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...Thorne & Derrick International
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Thorne & Derrick International
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RoweThorne & Derrick International
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandThorne & Derrick International
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DThorne & Derrick International
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...Thorne & Derrick International
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetThorne & Derrick International
 

Más de Thorne & Derrick International (20)

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
Itron Fact Sheet
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
 

Último

Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 

Último (20)

Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 

Offshore Renewables Cable Testing

  • 1. Adoption of Best Practices for Cable Testing and Condition Monitoring in the Offshore Renewables Market Presented by: Dr Lee Renforth Managing Director, HVPD Ltd
  • 2. CONTENTS • Why do we need improved commissioning testing and condition monitoring for subsea cables? • Exploring the options for diagnostic testing as part of the field acceptance/commissioning tests for subsea cables. • What options are available for the condition monitoring (CM) of in-service subsea cables? • Diagnostic testing and condition monitoring Case Studies from the Oil and Gas industry. • How can condition monitoring technology support condition based management (CBM) of these assets.
  • 3. Introduction to HVPD Ltd • HVPD are experts in the field of on-line partial discharge (OLPD) condition monitoring technology with specific expertise in MV and HV cable monitoring. • We have over 20 years of experience in testing of in-service MV and HV cables, switchgear, transformers and motors/generators. • We supply portable and permanent OLPD diagnostic test and continuous monitoring solutions, and a complimentary range of on-site test services and training. • Five main market sectors: Oil & Gas, Renewables, Transmission & Distribution, Shipping and Generation. Introduction to HVPD Ltd
  • 4. HVPD’s Subsea Cable Clients HVDC & HVAC Interconnector Owners – Manx 90kV 108km HVAC Interconnector © Google
  • 5. HVPD’s Subsea Cable Clients Oil and Gas Operators – 33kV Cables from Deepwater Offshore Wind Turbines
  • 6. HVPD’s Subsea Cable Clients Offshore Wind Farm (OWF) HVAC Export Cables & 33kV Inter-array Cables
  • 7. Subsea MV and HV Cable Faults Common Causes • Incorrect workmanship of the cable accessories leading to partial discharge, electrical tracking and finally complete insulation failure. • Mechanical damage caused by poor installation practices including damage to the cable (from jack-up vessels, anchors, etc.) and/or poor quality cable mechanical protection of cable joints leading to scour and mechanical stressing. • Thermal damage caused by poor bonding of cable earthing system and/or water ingress that leads to localised heating and thermal breakdown.
  • 8. ‘TEAM’ Stresses for Subsea Power Cables THERMAL ‘Thermal runaway’ problems can occur in cables where there are high circulating currents and local high resistance points. ELECTRICAL This is the No.1 cause of cable faults occurring within the first 3 years of service, typically due to incorrect installation of the cable accessories. AMBIENT The effects of mechanical ‘wear and tear’ including ‘scour’ caused by movement of the subsea cables with tidal and current changes. MECHANICAL Many subsea cable failures are caused by mechanical damage caused by poor practice when installing and ‘pulling-in’ the cables.
  • 9. Introduction to Partial Discharge Why test for partial discharge? PD activity is an indication of an ‘incipient fault’ in HV insulation and is widely regarded as the best ‘early warning’ indicator of insulation deterioration. The detection of PD at an early stage enables preventative maintenance action to avoid unplanned outages. What is partial discharge? “A localised electrical discharge that only partially bridges the insulation between conductors and which can or can not occur adjacent to a conductor” IEC60270 Definition
  • 10. Most Likely Sites of PD Activity in Subsea Cables
  • 11. 132 kV Onshore Cable Termination Failed and Exploded Outdoor Porcelain Cable Sealing End
  • 12. 33 kV OWF Export Cable Joint – this joint had been exhibiting high levels of PD and was replaced and removed from service
  • 13. 110kV Transformer Cable Terminations Left – photo showing PD ‘scorching’, Right – photo of a failed termination Tracking and ‘scorching’ on a 110 kV Termination (PD detected before failure) A Failed 110 kV Termination (Same type as opposite)
  • 14. Reliability Centred Maintenance (RCM) ‘Bathtub Curve’ Steady State Failure ‘Infant Mortality’ Phase 3 Years 20-50 Years Infant Mortality Steady State Failure End of Life ‘Wear-out’ Time FailureRate
  • 15. Why and When to Perform PD Testing New Equipment At Manufacture • Quality Assurance • Type/routine tests, e.g. IEEE/IEC standards – test to less than 5pC on the cables At Commissioning • To check for transport damage • To ensure the installation of the cable accessories have made to a good standard (these are the weak points in the cable system)
  • 16. VLF and Soak Test Commissioning Tests for 33 kV Cables • To detect any poor workmanship and/or installation damage with a particular focus on the cable accessories. • Partial Discharge (PD) and Tan Delta (TD) diagnostic acceptance tests should be made in combination with the VLF voltage withstand test (from 2.0 to 3.0 U0 i.e. 38.2–57.3 kVrms for 33 kV cables). • This test is combined with an off-line, electrical Time Domain Reflectometry (TDR) testing to support both future ‘PD Mapping’ (PD site localisation) and/or rapid fault location in the event of a cable fault.
  • 17. Factory Testing of Cable Systems • Cable components tested individually. • Cable cores should be tested both before and then after their assembly into the 3-core subsea cable. • High sensitivity measurements in a ‘low-noise’ environment are required, typically to accuracies of <5pC. • This requires a Faraday Cage, electromagnetically screened test room to achieve this sensitivity. • The Faraday Cage HV test facility shown opposite can measure PD activity down to 1pC.
  • 18. Cable HV Withstand Voltage Field Acceptance Test Options VLF (Very Low Frequency) (0.05–0.1 Hz) example supplier: Baur - Austria, b2hv - Austria Variable Frequency Resonant Test Systems (RTS) (20-300Hz) example supplier: High-Volt – Germany Damped AC / Oscillating Wave (OWTS) example suppliers: Seitz, SEBAkmt - Germany 24 Hour Soak Test (at U0) No external power supply is required although extended, continuous 24-hour OLPD monitoring is necessary during the duration of the soak test.
  • 20. Partial Discharge Cable Mapping – PD Site Location along the cable All PD Map of Circuit Meols Drive - Graham Road Location (% along cable) 10510095908580757065605550454035302520151050-5 AllPhasesPD 7,000 6,500 6,000 5,500 5,000 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 0 The locations of any defects that exhibit PD activity will be detected along the length of the cable using the technique of time domain reflectometery (TDR). The PD Map of the cable below shows three (3) main sites of PD activity along the cable.
  • 21. On-line PD Testing & Monitoring to Support Planned Maintenance Interventions Repeat testing before the cable supplier/jointer warranty runs out! • It is highly recommended that an on-line PD test is carried out before the warranty period expires (typically only 12 months). Continuous On-line PD (OLPD) monitoring throughout the service life • To detect whether PD activity has initiated during the service life of the cable/plant • To support maintenance and operation decisions, by detecting and localising any PD activity in in-service cables • To direct preventative maintenance interventions.
  • 22. CONDITION MONITORING OF IN-SERVICE SUBSEA MV AND HV CABLES
  • 23. On-line Condition Monitoring Options for Subsea Power Cables THERMAL Distributed Temperature Sensing (DTS) using fibre optic detection technology. ELECTRICAL On-line Partial Discharge (OLPD), plus sheath current and power quality monitoring . AMBIENT Vibration monitoring using fibre optic detection technology. MECHANICAL Mechanical strain monitoring using fibre optic detection technology.
  • 24. Fibre-Optic Strain, Vibration and Temperature Sensing Solution • Optoelectronic devices which measure temperature and strain by means of optical fibres functioning as linear sensors • Provides real-time, dynamic temperature and strain information along the complete length of power cable for health monitoring. • Can identify small hot spot locations and localised mechanical damage without prior installation knowledge. • Provides accurate temperature data input for dynamic cable rating based on actual “installed” conditions to monitor higher power flows through the cable. Fibre optic monitoring cable DTS/Strain Monitoring unit Field splice box Local splice box
  • 25. Subsea 3-core Cable with Built-in Fibre-Optics • Subsea cables can include up to 4 fibre-optic cables that can be utilised for distributed temperature, strain and vibration sensing. • The example below shows a fibre along the cable centreline, and 3 fibres laid up and located in the interstices between the phases.
  • 26. Offshore High Voltage Network Monitoring System • OHVMS – ‘holistic’ HV/MV network condition monitoring (CM) system for offshore cable networks and connected plant (switchgear and transformers). • The Condition Monitoring (CM) data is used to provide predictive, ‘early warnings’ against ‘incipient’ insulation faults. • The system helps to avoid unplanned outages, supports preventative maintenance and reduces the high O&M costs of the OWF electrical networks.
  • 27. Offshore High Voltage Network Monitoring System
  • 28. OHVMS Cable Condition Monitoring Features and Benefits OHVMS HOLISTIC MONITORING SYSTEM Power Quality Partial Discharge Earth Faults Loading Sheath Currents Ambient Conditions Intelligent Diagnosis System Health Alarms System Stability Alarms Condition- Based Maintenance SMART Grid Integration Dynamic De-Rating
  • 29. OHVMS ‘Holistic’ MV/HV Cable Condition Monitoring System Example – 80 x 3.6MW Turbine Array An OHVMS monitoring hub (MH1) is located at the offshore substation platform (OSP) to monitor: • 33 kV switchgear • 33/132 kV transformers • 33 kV incoming cable ‘strings’ from the turbine arrays Turbine Monitor Nodes (TMN01– TMN21) are positioned at strategic locations (every 3rd turbine) across the turbine array, to provide complete network coverage.
  • 30. OHVMS SMART-Quadplex™ Sensor Location In the Turbine Base
  • 31. OHVMS SMART-Quadplex™ Sensor Location In the Turbine Nacelle • A combined electrical state and condition assessment of the health of the network is provided using SMART-Quadplex™ sensors. • The sensors and OHVMS monitor can be installed either at the base of the turbine or in the nacelle, depending on the turbine design.
  • 32. CASE STUDY 1: ON-LINE PARTIAL DISCHARGE (OLPD) TESTING, LOCATION, MONITORING WITH PREVENTATIVE MAINTENANCE ON A 33 KV OFFSHORE WIND FARM EXPORT CABLE
  • 33. Case Study 1: Export Cable Circuit Details • 1.7 km single core XLPE land cable • 9.6/11.5 km 3-core XLPE subsea cable
  • 34. OLPD Test and Mapping Data L1 L2 L3 Cable PD Phase of Pow er Cycle (deg) 360270180900 PDMagnitude(pC) 0 Cable PD Phase of Pow er Cycle (deg) 360270180900 PDMagnitude(pC) 0 Cable PD Phase of Pow er Cycle (deg) 360270180900 PDMagnitude(pC) 10,000 5,000 0 -5,000 -10,000 High levels of PD (of up to 10,000 pC / 10 nC) were measured from the onshore substation on Circuit B, Phase L3.
  • 35. Location (meters) 1,6001,4001,2001,0008006004002000 PDMap© Graph Showing PD Location Land-sea Transition Joint Joint Pit 7 Switching Substation
  • 36. PD Signals Before and After Joint Replacement Joint 7 with PD removed and replacement cable section installed Location (meters) 1,6001,4001,2001,0008006004002000 High PD detected on L3 PD Located Lower-level sporadic PD signals from different site after joint replacement BEFORE AFTER
  • 37. Circuit B – Evidence of Surface Tracking and Degradation due to Poorly-Fitted Heatshrink Stress Control
  • 38. CASE STUDY 2: INSTALLATION OF AN OLPD CONDITION MONITORING SYSTEM FOR A 400 KV ONSHORE GRID CONNECTION CABLE
  • 39. Continuous OLPD Insulation Condition Monitoring In-service Equipment Condition Monitoring throughout the service life of the cable. • Continuous OLPD monitoring of the insulation condition of the cable network throughout it’s service life. • Data from the technology supports Condition-Based Management (CBM) of critical cable networks. • Provides increased security and reliability of electricity supply from offshore renewables generation. • Helps to reduce O&M costs through the avoidance of faults and unplanned outages.
  • 40. Sensor Locations at 400 kV Transformer Terminations
  • 41. HV Cable OLPD Monitor System Drawing
  • 42. CASE STUDY 3: OLPD TESTING AND LOCATION ON A DEEPWATER OFFSHORE WIND TURBINE CONNECTED TO AN OIL & GAS PLATFORM
  • 43. Case Study 2: OLPD Testing and Location on a Deepwater Offshore Wind Turbine connected to an Oil & Gas Platform
  • 44. Background • Two deep-water wind turbines supply power exclusively to an oil production platform situated around 2km away. • Two on-line PD tests were performed to assess the condition of the 33kV cables from two turbines to the oil & gas platform.
  • 45. Test 1 – OLPD Test at 33 kV Switchgear on Platform
  • 46. Results from Test 1 at 33 kV Switchgear on the Platform • High PD activity (in excess of 6,000pC+) was detected on the Turbine A Feeder. • Analysis of the PD pulse data suggested that the source of the PD activity was at the far end of the Turbine A feeder cable. • OLPD Cable Mapping was recommended.
  • 47. Test 2 – PD Test at the Wind Turbine’s 33 kV Switchgear
  • 48. PD Location at Wind Turbine A • Test identified the PD source to the cable joint at the top of the tower close to the 33 kV transformer. • Measurement of PD pulses showed the source of the PD being at 52m from the switchgear at Test Point 2. • The cause of the discharge was meachanical stress due to insufficient support of the cable joint from the weight of the free- hanging cable.
  • 49. CASE STUDY 4: A COMPLETE 33 KV CABLE NETWORK OLPD SURVEY AND ANALYSIS TO SUPPORT CONDITION BASED MAINTENANCE (CBM) DUBAI METRO, DUBAI, UAE
  • 50. On-line Partial Discharge (OLPD) test and cable mapping survey of the customer’s 33 kV cable network was carried out by HVPD engineers using the HVPD Longshot™ diagnostic test system. This testing was carried out in response to a number catastrophic failures of 33 kV cable joints within their network which had led to disruption of the power supply to the Metropolitan rail system. The purpose of the testing was to measure and locate any PD activity within the cables with particular focus on the cable joints. It can be noted that this was a recently installed cable system that had been in- service for just over 12 months before the faults started to occur. After four 33kV cable joint faults in 2 months, the client requested a complete OLPD survey of the network to detect any ‘incipient’ faults on the network. Background
  • 51. • On-line Cable PD Mapping using the HVPD Longshot™ test unit and Portable Transponder technology was used to carry out an on-line condition assessment of complete 33kV cable network. • Tests started with calibration testing with pulse injection HFCTs, followed by OLPD measurements and then cable mapping tests. OLPD Testing to Support CBM of a 33kV Cable Network
  • 52. • Cable PD signals of 6,000pC+ were detected on the Blue Phase with some ‘cross-talk’ (lower magnitude) on the Red and Yellow phases. • The source of PD was located to Joint Number 2 (Jt2) using the cable mapping test technique. • The faulty joint on this cable was replaced and re-tested using the HVPD Longshot™ test unit to verify the repair was good. 33kV Cable Network Test Results I
  • 53. 33kV Cable Network Test Results II Examples of PD located on two 33kV circuits Left – PD Located on Red Phase Joint No.1, Right – PD located on Red Phase, Joint No.2
  • 54. • The network consisted of 104x 33kV that were circuits tested • High Levels of PD were detected in cable joints on the six of the circuits (6%) as shown in RED in the Table below, Condition Category, “Major concern, locate PD and then repair”. • A further five circuits (5%) were in the Orange/Yellow Categor, these were also repaired. Top 20 ‘Worst Performing 33kV Circuits’ Criticality Number Circuit Comments Peak Cable PD Level (pC) Local PD Level (dB) Cumulative Cable PD Level (nC/cycle) OLPD Criticality (%) Maintenance Action 1. DUB to MPS1 C2 B Phase 25888 <10 247 97.4 Major concern, locate PD and then repair or replace. 2. ABS to AH C2 B / Y Phase 9729 <10 120 90.3 3. BUR to HCC C2 B / Y Phase 3781 <10 12.3 78.7 4. BUR to HCC C1 B / Y Phase 3245 <10 7.9 78.1 5. ABS to AH C1 B / Y Phase 2920 <10 14.4 77.4 6. NHD to QYD C2 R Phase 2849 <10 15.0 76.2 7. ALQ to AHS C2 B Phase 1733 <10 4.6 70.6 Some concern, repeat test and regular monitoring recommended. 8. MPS3 to BNS C2 R / B Phase 1337 <10 6.4 65.5 9. NHD to QYD C1 R Phase 887 <10 8.8 47.8 10. HCC to CRK C1 Y / B Phase 759 <10 2.5 39.2 11. AHS to SLD Y / R Phase 705 <10 3.1 38.5 12. STD to ABH Y Phase 238 <10 1.0 24.1 Re-test in 12 months. 13. ALR to BNS C1 B Phase 184 <10 0.9 18.6 14. ALR to BRJ No PD detected 0 <10 0 0 15. ALG to PMD No PD detected 0 <10 0 0 16. ALG to KBW No PD detected 0 <10 0 0 17. AQD to AQ2 No PD detected 0 <10 0 0 18. JDD to CRK No PD detected 0 <10 0 0 19. ODM to JDF C1 No PD detected 0 <10 0 0 20. ODM to JDF C2 No PD detected 0 <10 0 0
  • 56. Conclusions • The increasing installation rate of installation of offshore wind farms (OWFs) in Europe, combined with the high MV and HV cable fault rates reported to date, has led to a ‘market need’ for better MV/HV cable condition monitoring (CM) technology. • Offshore wind farm subsea cable owners need to also consider the use of diagnostic testing during cable HV withstand/commissioning tests. • It is proposed that any CM system employed should combine thermal, electrical, ambient and mechanical monitoring to cover all four of the ‘TEAM’ stresses that effect the reliable operation of the cables. • The purpose of any CM system is to provide an ‘early warning’ of ‘incipient’ cable insulation faults to enable preventative maintenance interventions to avoid unplanned outages. • A move towards Condition Based Management (CBM) of the cable networks (using data from ‘holistic’ CM technologies) is seen as the key to reducing the presently high O&M costs to achieve DECC’s target of a 25% reduction in Levelised Cost of Electricity (LCOE) by 2020.
  • 57. End of Presentation Thank you for your time Q&A?