SlideShare una empresa de Scribd logo
1 de 4
Descargar para leer sin conexión
Mansoura University                                                     Construction Project Management
Faculty of Engineering                                                                     3rd Year Civil
Structural Eng. Dept.                                                                         2006-2007
                                               Exercise 4
                                    Due date: Wednesday, Nov 2nd 2005

1. The free float is defined as:
    a. The amount of time an activity can be delayed without affecting the following activity.
    b. The amount of time an activity can be delayed without affecting total project duration.

2. Total float equals:
    a. Late finish minus early finish                   c. Late start minus early start
    b. Late finish minus (early start + duration)       d. All of the above

3. State True (T) or False (F):

     a.   The critical activities can be determined easily when using the bar chart.
     b.   The network must have definite points of beginning and end.
     c.   The network must be continuous from start to end.
     d.   There’s no dummy activities in the arrow networks,
     e.   A forward pass is used to determine late start and late finish times.
     f.   The time for completing a project is equal to the sum of the individual activity times.

4. For the Following project data, answer the following questions:

                     Activity                 Duration (days)   Predecessor
                                A             2                          --
                                B             6                          A
                                C             3                          A
                                D             1                          B
                                E             6                          B
                                F             3                         C, D
                                G             2                         E, F

          a)   Draw an AOA network and perform forward and backward pass calculations?
          b)   Draw an AON network and perform forward and backward pass calculations?
          c)   Draw a time-scaled diagram of the project?
          d)   Tabulate activities ES, EF, LS, LF, TF, and FF.
          e)   What is the effect of delaying activity D by 3 days?

5. For the following AOA network, determine the following:

          a. Calculate ES, LF, & TF for all activities. Identify critical ones.
          b. Draw an early Bar Chart for the project.
          c. What is the effect of delaying activity “H” by two days on the total project duration?




Construction Management                             1                                Dr. Emad Elbeltagi
Mansoura University                                                                     Construction Project Management
Faculty of Engineering                                                                                     3rd Year Civil
Structural Eng. Dept.                                                                                         2006-2007

                                          3    D (8)         9
                              A (4)                                    H (4)


                    1           B (6)           E (10)       11      I (8)     15       K (5)    17
                                          5
                          C (2)                       F (16)
                                                                               J (10)
                                          7   G (6)          13



6. Perform PDM calculations for the project below and determine activity times. Durations are
shown on the activities

                                                                                         I
                                                                                        (2)

                                         B              D                G
                                        (4)            (1)              (1)

                         A                                                               J             L
                        (1)                                                             (7)           (2)

                                         C              E                H
                                        (1)            (2)              (1)

                                                        F                                K
                                                       (2)                              (4)



7. A gas station is proposed to be built on an already developed site. It will consist essentially of
a sales outlet and an office block. The sales outlet comprises of cash office and gas pumps. The
manager’s office building, which also houses public washrooms and an air compressor, is called
the office block. Adjacent to pumps will be a concrete pit that will house the gas tanks.

The entire area, excluding the office and pumps site, is covered with a concrete slab, and there is
a low perimeter wall in the rear. The utility company has undertaken to install an electric meter
on the site and connect it to the mains. Gasoline pumps must be obtained from the
manufacturers, and after being installed, they are to be connected to the gasoline tanks and the
power supply. Before use the local authority to ensure safety and compliance with regulations
must inspect them. Gasoline tanks are housed in concrete pits and covered by concrete slabs.
Before they are covered, however, the tanks and the associated pipe work have to be inspected
by the local authority. The sales outlet base is excavated first, the pipe work and tanks second,
the office block third, and the trench for underground services last. After the excavation for the
tanks and pipe work is completed, work can proceed on the construction of the perimeter wall
and air points.

Compressed air for inflated tires will be supplied by an electrically driven compressor, which
must be inspected by a competent person before the compressor is put into use. The air lines to

Construction Management                                          2                                    Dr. Emad Elbeltagi
Mansoura University                                                   Construction Project Management
Faculty of Engineering                                                                   3rd Year Civil
Structural Eng. Dept.                                                                       2006-2007
the “free air” points are installed with the general underground services, and the points
themselves are mounted on the perimeter wall. The air pints can be hooked up after the concrete
slab has been poured. Mobilization to start work comprises, among other preparations, the
moving of a trailer to the site to store tools, furnishings, and any weather prone parts and to serve
as the site office. Similarly, when work at the site is completed, the trailer will be removed, and
all scaffolding and construction equipment taken away. This is known as “demobilization and
clean up of site.”

You are required to determine the project duration, critical path(s), and tabulate activity times
(ES, EF, LS, LF, TF, and FF).

                         No            Activity Description            Duration
                          A   Excavate for sales outlet                     1
                          B   Construct sales outlet base                   1
                          C   Construct cash office                         2
                          D   Obtain pumps                                 16
                          E   Install pumps                                 2
                          F   Connect pumps                                 1
                          G   Inspector approves pumps installation         2
                          H   Paint & furnish office & washrooms            2
                          I   Connect office & toilet lighting              1
                          J   Excavate for office block                     1
                          K   Construct office block                        1
                          L   Build office & washrooms + services          15
                         M    Install electric meter                       14
                          N   Connect main cable to meter                   1
                          O   Install area lighting                         4
                          P   Mobilize site                                 1
                          Q   Set out and level site                        1
                          R   Excavate & lay underground services           1
                          S   Excavate for pipes and tanks                  1
                          T   Construct concrete pit                        2
                          U   Obtain pipes and tanks                        2
                          V   Install pipes and tanks                       3
                         W    Obtain compressor                            10
                          X   Install compressor                            1
                          Y   Connect power to compressor                   1
                          Z   Inspection of compressor                      2
                         AA   Backfill and cover tanks                      1
                         BB   Pour concrete slab                            2
                         CC   Construct perimeter wall + air points         2
                         DD   Connect air points                            1
                         EE   Demobilize and clean site                     1
                         FF   Inspection of pipes and tanks                 2



Construction Management                            3                               Dr. Emad Elbeltagi
Mansoura University                                                       Construction Project Management
 Faculty of Engineering                                                                       3rd Year Civil
 Structural Eng. Dept.                                                                           2006-2007
 8. For the following list of activities, draw a time-scaled diagram and mark the critical path.
 Determine activities ES, EF, LS, LF, FF, and TF.


                          Activity             Duration (days)    Predecessor
                                     A         4                          --
                                     B         10                         A
                                     C         2                          A
                                     D         6                          C
                                     E         15                       B, D
                                     F         4                        B, D
                                     G         3                          F
                                     H         2                        B, D
                                     I         1                       E, G, H
                                     J         3                          I
                                     K         2                          E
                                     L         1                          J
                                     M         2                        K, L


 9. For the following PDM, perform the forward pass and backward pass calculations. Determine
    the project duration and critical path. Tabulate the ES, EF, LS, LF, TF, and FF information for
    each activity.

                                                            E
                                                                            FF7
                                                            7




A         SS3, FF4
                      B        SS2
                                          D                                     F      SS8
                                                                                                       G
10                    8                   12                     FF5            9                      12


                                                                                             SS8

                                                                                                               J
                                                            C                                                  0
                                               SF5
                                                            8



                                         FS6
                                                                             H        FF3
                                                                                                   I
                                                                             10                    8




     Construction Management                            4                               Dr. Emad Elbeltagi

Más contenido relacionado

La actualidad más candente

Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfKarim Ragab
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
319621003 ustek-turap-mempawah
319621003 ustek-turap-mempawah319621003 ustek-turap-mempawah
319621003 ustek-turap-mempawahEmil ..
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
Portfolio Telli ali BIM Architect
Portfolio Telli ali BIM ArchitectPortfolio Telli ali BIM Architect
Portfolio Telli ali BIM ArchitectAli TELLI
 
The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementMilind_jagtap_
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
Modul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek KonstruksiModul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek KonstruksiPPGHybrid1
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني M Maged Hegazy, LLM, MBA, CCP, P3O
 
Reconnaissance satellite or Spy Satellite
Reconnaissance satellite or Spy Satellite Reconnaissance satellite or Spy Satellite
Reconnaissance satellite or Spy Satellite Shakir Memon
 
Time & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project DeliveryTime & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project DeliveryShashank Arun
 
YAPIMDA MALIYET YONETIMI
YAPIMDA MALIYET YONETIMIYAPIMDA MALIYET YONETIMI
YAPIMDA MALIYET YONETIMISafak EBESEK
 
Quantity surveying practise
Quantity surveying practiseQuantity surveying practise
Quantity surveying practiseSasi Cool
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 

La actualidad más candente (20)

Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
319621003 ustek-turap-mempawah
319621003 ustek-turap-mempawah319621003 ustek-turap-mempawah
319621003 ustek-turap-mempawah
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Portfolio Telli ali BIM Architect
Portfolio Telli ali BIM ArchitectPortfolio Telli ali BIM Architect
Portfolio Telli ali BIM Architect
 
The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Modul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek KonstruksiModul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek Konstruksi
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
 
Reconnaissance satellite or Spy Satellite
Reconnaissance satellite or Spy Satellite Reconnaissance satellite or Spy Satellite
Reconnaissance satellite or Spy Satellite
 
Time & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project DeliveryTime & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project Delivery
 
YAPIMDA MALIYET YONETIMI
YAPIMDA MALIYET YONETIMIYAPIMDA MALIYET YONETIMI
YAPIMDA MALIYET YONETIMI
 
Quantity surveying practise
Quantity surveying practiseQuantity surveying practise
Quantity surveying practise
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 

Destacado (14)

Cm exercise 1
Cm exercise 1Cm exercise 1
Cm exercise 1
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
Cm exercise 7
Cm exercise 7Cm exercise 7
Cm exercise 7
 
P introduction
P introductionP introduction
P introduction
 
Cm exercise 2
Cm exercise 2Cm exercise 2
Cm exercise 2
 
Cm exercise 8
Cm exercise 8Cm exercise 8
Cm exercise 8
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Cm exercise 6
Cm exercise 6Cm exercise 6
Cm exercise 6
 
Cm exercise 3
Cm exercise 3Cm exercise 3
Cm exercise 3
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Cm exercise 5
Cm exercise 5Cm exercise 5
Cm exercise 5
 
P contracts
P contractsP contracts
P contracts
 
Strategic cost management
Strategic cost managementStrategic cost management
Strategic cost management
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 

Similar a Cm exercise 4

Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 
Project management activity task
Project management activity taskProject management activity task
Project management activity taskTadele Asmare
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxkenjordan97598
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartVinay Prajapati
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Managementguestac67362
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Managementguestd436758
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project managementShadina Shah
 
Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment iichandraswami
 
Robust Information Exchanges For BIM
Robust Information Exchanges For BIMRobust Information Exchanges For BIM
Robust Information Exchanges For BIMManu Venugopal
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project schedulingTadele Asmare
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problemsSubhra Mishra
 
Response of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsResponse of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsIRJET Journal
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpmahsanrabbani
 
Syallabus Discussion Python.pptx
Syallabus Discussion Python.pptxSyallabus Discussion Python.pptx
Syallabus Discussion Python.pptxSachinHarkal1
 

Similar a Cm exercise 4 (20)

606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Project management activity task
Project management activity taskProject management activity task
Project management activity task
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
 
0102 Building Planning And Construction Management
0102 Building Planning And Construction Management0102 Building Planning And Construction Management
0102 Building Planning And Construction Management
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Ch4 scheduling
Ch4 schedulingCh4 scheduling
Ch4 scheduling
 
Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment ii
 
Robust Information Exchanges For BIM
Robust Information Exchanges For BIMRobust Information Exchanges For BIM
Robust Information Exchanges For BIM
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Project management project scheduling
Project management  project schedulingProject management  project scheduling
Project management project scheduling
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
Response of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using EtabsResponse of RCC Structure under Influence of Earthquake using Etabs
Response of RCC Structure under Influence of Earthquake using Etabs
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpm
 
Syallabus Discussion Python.pptx
Syallabus Discussion Python.pptxSyallabus Discussion Python.pptx
Syallabus Discussion Python.pptx
 

Más de Tu Nguyen, PMP®,PMI-RMP®

Más de Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 

Cm exercise 4

  • 1. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 Exercise 4 Due date: Wednesday, Nov 2nd 2005 1. The free float is defined as: a. The amount of time an activity can be delayed without affecting the following activity. b. The amount of time an activity can be delayed without affecting total project duration. 2. Total float equals: a. Late finish minus early finish c. Late start minus early start b. Late finish minus (early start + duration) d. All of the above 3. State True (T) or False (F): a. The critical activities can be determined easily when using the bar chart. b. The network must have definite points of beginning and end. c. The network must be continuous from start to end. d. There’s no dummy activities in the arrow networks, e. A forward pass is used to determine late start and late finish times. f. The time for completing a project is equal to the sum of the individual activity times. 4. For the Following project data, answer the following questions: Activity Duration (days) Predecessor A 2 -- B 6 A C 3 A D 1 B E 6 B F 3 C, D G 2 E, F a) Draw an AOA network and perform forward and backward pass calculations? b) Draw an AON network and perform forward and backward pass calculations? c) Draw a time-scaled diagram of the project? d) Tabulate activities ES, EF, LS, LF, TF, and FF. e) What is the effect of delaying activity D by 3 days? 5. For the following AOA network, determine the following: a. Calculate ES, LF, & TF for all activities. Identify critical ones. b. Draw an early Bar Chart for the project. c. What is the effect of delaying activity “H” by two days on the total project duration? Construction Management 1 Dr. Emad Elbeltagi
  • 2. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 3 D (8) 9 A (4) H (4) 1 B (6) E (10) 11 I (8) 15 K (5) 17 5 C (2) F (16) J (10) 7 G (6) 13 6. Perform PDM calculations for the project below and determine activity times. Durations are shown on the activities I (2) B D G (4) (1) (1) A J L (1) (7) (2) C E H (1) (2) (1) F K (2) (4) 7. A gas station is proposed to be built on an already developed site. It will consist essentially of a sales outlet and an office block. The sales outlet comprises of cash office and gas pumps. The manager’s office building, which also houses public washrooms and an air compressor, is called the office block. Adjacent to pumps will be a concrete pit that will house the gas tanks. The entire area, excluding the office and pumps site, is covered with a concrete slab, and there is a low perimeter wall in the rear. The utility company has undertaken to install an electric meter on the site and connect it to the mains. Gasoline pumps must be obtained from the manufacturers, and after being installed, they are to be connected to the gasoline tanks and the power supply. Before use the local authority to ensure safety and compliance with regulations must inspect them. Gasoline tanks are housed in concrete pits and covered by concrete slabs. Before they are covered, however, the tanks and the associated pipe work have to be inspected by the local authority. The sales outlet base is excavated first, the pipe work and tanks second, the office block third, and the trench for underground services last. After the excavation for the tanks and pipe work is completed, work can proceed on the construction of the perimeter wall and air points. Compressed air for inflated tires will be supplied by an electrically driven compressor, which must be inspected by a competent person before the compressor is put into use. The air lines to Construction Management 2 Dr. Emad Elbeltagi
  • 3. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 the “free air” points are installed with the general underground services, and the points themselves are mounted on the perimeter wall. The air pints can be hooked up after the concrete slab has been poured. Mobilization to start work comprises, among other preparations, the moving of a trailer to the site to store tools, furnishings, and any weather prone parts and to serve as the site office. Similarly, when work at the site is completed, the trailer will be removed, and all scaffolding and construction equipment taken away. This is known as “demobilization and clean up of site.” You are required to determine the project duration, critical path(s), and tabulate activity times (ES, EF, LS, LF, TF, and FF). No Activity Description Duration A Excavate for sales outlet 1 B Construct sales outlet base 1 C Construct cash office 2 D Obtain pumps 16 E Install pumps 2 F Connect pumps 1 G Inspector approves pumps installation 2 H Paint & furnish office & washrooms 2 I Connect office & toilet lighting 1 J Excavate for office block 1 K Construct office block 1 L Build office & washrooms + services 15 M Install electric meter 14 N Connect main cable to meter 1 O Install area lighting 4 P Mobilize site 1 Q Set out and level site 1 R Excavate & lay underground services 1 S Excavate for pipes and tanks 1 T Construct concrete pit 2 U Obtain pipes and tanks 2 V Install pipes and tanks 3 W Obtain compressor 10 X Install compressor 1 Y Connect power to compressor 1 Z Inspection of compressor 2 AA Backfill and cover tanks 1 BB Pour concrete slab 2 CC Construct perimeter wall + air points 2 DD Connect air points 1 EE Demobilize and clean site 1 FF Inspection of pipes and tanks 2 Construction Management 3 Dr. Emad Elbeltagi
  • 4. Mansoura University Construction Project Management Faculty of Engineering 3rd Year Civil Structural Eng. Dept. 2006-2007 8. For the following list of activities, draw a time-scaled diagram and mark the critical path. Determine activities ES, EF, LS, LF, FF, and TF. Activity Duration (days) Predecessor A 4 -- B 10 A C 2 A D 6 C E 15 B, D F 4 B, D G 3 F H 2 B, D I 1 E, G, H J 3 I K 2 E L 1 J M 2 K, L 9. For the following PDM, perform the forward pass and backward pass calculations. Determine the project duration and critical path. Tabulate the ES, EF, LS, LF, TF, and FF information for each activity. E FF7 7 A SS3, FF4 B SS2 D F SS8 G 10 8 12 FF5 9 12 SS8 J C 0 SF5 8 FS6 H FF3 I 10 8 Construction Management 4 Dr. Emad Elbeltagi