Presented by : VENUMADHAV.R.YEMUL 
Guided by : MILIND.D.DARADE 
Roll No : 5073 
1
Manpower, equipment, and materials are 
important project resources that require 
management attention. 
The basic objective of resource planning and 
resource allocation is to supply and support 
the field operations. 
The term resource allocation is used in the 
case where required resources are assigned 
such that available resources are not 
exceeded. 
2
Resources are the means of production 
needed to complete a project. 
Most project managers would consider the 
big three resources that will require your 
attention to be: 
• Material 
• Labor 
• Equipment 
3
A. LABOUR 
a. In the limited resource allocation case, there 
are two assumptions: 
(1) There are a fixed number of crews available 
to perform the work and 
(2) The project may be delayed as a result of 
the limitation of crews. 
The objective of the resource allocation 
problem is to determine when the project will 
be completed. 
4
b. In the unlimited resource leveling case, there 
are two assumptions: 
(1) There are an unlimited number of crews 
available to perform the work and 
(2) The project may not be delayed. 
The objective of the resource leveling 
problem is to determine how to limit the 
fluctuation in crews required on the job. 
5
B. MATERIALS 
Materials, for projects with sufficient on-site 
storage, are delivered to the site and assumed 
to be available to workers as needed. 
A material-related concern for sites that have 
sufficient space is that of optimizing the position 
of materials on the site so that they require the 
least travel time from the lay-down yard to the 
work-face. 
6
C. EQUIPMENTS 
There are various types of equipment used on 
construction sites. 
Some of this equipment should be considered in 
the project plan, some need not be included. 
Workers, and their companies, are typically 
required to provide the small tools needed to 
complete their specific features of work. 
There are some types of equipment, however, that 
can affect the overall sequence and duration of the 
project. 
7
Resource allocation is used to assign the 
available resources in an economic way. 
It is part of resource management. 
In project management, resource allocation 
is the scheduling of activities and the 
resources required by those activities while 
taking into consideration both the resource 
availability and the project time. 
8
Resource planning cannot be accomplished 
without four essential resources necessary 
to accomplish the given scope of work: 
• MATERIAL 
• MAN POWER 
• MACHINARY 
• TIME 
9
Human resources for construction planning 
breaks down into three major categories as 
follows: 
• Home office personnel(Administrative 
Persons) 
• Construction personnel (field supervision 
and labor) 
• Construction subcontractors(Electrification, 
Plumbing, etc) 
10
The ideal form of a personnel loading curves 
is a trapezoid. 
The average personnel loading curve is a 
straight line. 
Actual practice loading curves take the 
shape of a bell curve 
11
12
The latter two result when the personnel 
loading curves occur earlier or later than 
planned on a project. 
Front loaded curve- the work started as early 
as possible. 
Normal loaded curve- the work started at 
normal time. 
Back loaded curve- the work started as late 
as possible. 
13
The "S" curve for the ideally loaded project has 
a gradual start and finish, which indicates 
smooth starting and finishing conditions. 
The forward loaded curve shows a rapid project 
start up and an even more gradual than normal 
phase out at the end. 
The backward-loaded project indicates a more 
relaxed start and a very steep finish slope on 
the "S" curve. 
14
15
16
Ensuring that the material resources for the 
project arrive on time involves these 
important planning areas: 
• Long-delivery equipment 
• Special materials and alloys 
• Common materials in short supply 
• Services and system requirements 
• Transportation systems 
17
Resource Limited: The project must be finished as 
soon as possible, but without exceeding some 
specific level of resource usage or some general 
resource constraint 
18
1. When the schedule demands more workers 
per day than are available or if we have 
workers standing around without jobs, we 
have a problem. 
2. When a new hire is trained, there is loss of 
productivity. So, if we can keep the trained 
people and reduce the number of new hires, 
we should be better off. 
19
. As we know, every project suffers from start-up 
problems of some sort. Superintendents and 
project managers are very busy trying to get 
everybody working in a productivity manner. 
Therefore, if we can start with a small crew and 
increase its size gradually, we will eliminate some 
of the start-up problems. 
. Most projects suffer from congestion around 
project completion time because of reduced work 
areas. Thus, if we can gradually reduce the crew 
size as we approach project completion, we can 
improve productivity by reducing congestion. 
20
The leveling procedure are as follows: 
• Scheduling all the critical jobs first. 
• Starting the non-critical jobs whenever there 
is a drop in scheduled man power upto the 
point where the peak is reached. 
• Starting the non-critical jobs whenever there 
is a drop so that no ups and downs occur in 
the resource profile. 
21
› Time Limited: The project must be finished by a 
certain time, using as few resources as possible. 
But it is time, not resource usage, that is critical 
22
Resource Histograms: 
• A bar chart showing the amount of time 
assigned to a resource for the time interval. 
• Resource availability is depicted as a line for 
comparison purposes. 
• Resources assigned more work than 
available hours are considered “over-allocated”. 
23
INTRODUCTION 
ERP is a business management software, 
usually a suite of integrated applications, that a 
company can use to store and manage data 
from every stage of business, including: 
Product planning, cost and development 
Manufacturing 
Marketing and sales 
Inventory management 
Shipping and payment 
24
ERP systems could be used in the construction 
industry for the following general purposes: 
1. To improve responsibilities in relation to 
customers. 
2. To strength supply chain partnerships. 
3. To enhance organizational flexibility. 
4. To improve decision-making capabilities. 
5. To reduce project completion time and cost. 
25
26
27
Without the proper resource allocation, one will 
pay the price for late job completions and cost 
overruns. 
The goal of resource leveling is to assign 
resources to project activities in a manner that 
will improve productivity and efficiency. 
During the last two decades, the construction 
industry has progressed in this trend of 
improving resource allocation it merely out of 
interest but as a means of survival in a more 
competitive world. 
28
29
30

Más contenido relacionado

La actualidad más candente

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)Mayur Rahangdale
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Managementdanieljohn810
 

La actualidad más candente (20)

Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Management
 

Similar a Resource planning and resource allocation

Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptxTecnicoItca
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptTecnicoItca
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
Project typed
Project typedProject typed
Project typedRahul
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptTecnicoItca
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Project Resource Management-Good one.ppt
Project Resource Management-Good one.pptProject Resource Management-Good one.ppt
Project Resource Management-Good one.pptHabibullah Qayumi
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxAditya Mane
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...THULASIMANOHARAN2
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxTecnicoItca
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource ManagementSaqib Raza
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource ManagementSaqib Raza
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource ManagementSaqib Raza
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
10 me667 chap4 project scheduling
10 me667 chap4   project scheduling10 me667 chap4   project scheduling
10 me667 chap4 project schedulingPavan Kumar
 

Similar a Resource planning and resource allocation (20)

Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
Project time management
Project time managementProject time management
Project time management
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Project typed
Project typedProject typed
Project typed
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project Resource Management-Good one.ppt
Project Resource Management-Good one.pptProject Resource Management-Good one.ppt
Project Resource Management-Good one.ppt
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
PART- 2: Engineering Project Management
PART- 2: Engineering Project Management PART- 2: Engineering Project Management
PART- 2: Engineering Project Management
 
10 me667 chap4 project scheduling
10 me667 chap4   project scheduling10 me667 chap4   project scheduling
10 me667 chap4 project scheduling
 

Último

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 

Último (20)

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 

Resource planning and resource allocation

  • 1. Presented by : VENUMADHAV.R.YEMUL Guided by : MILIND.D.DARADE Roll No : 5073 1
  • 2. Manpower, equipment, and materials are important project resources that require management attention. The basic objective of resource planning and resource allocation is to supply and support the field operations. The term resource allocation is used in the case where required resources are assigned such that available resources are not exceeded. 2
  • 3. Resources are the means of production needed to complete a project. Most project managers would consider the big three resources that will require your attention to be: • Material • Labor • Equipment 3
  • 4. A. LABOUR a. In the limited resource allocation case, there are two assumptions: (1) There are a fixed number of crews available to perform the work and (2) The project may be delayed as a result of the limitation of crews. The objective of the resource allocation problem is to determine when the project will be completed. 4
  • 5. b. In the unlimited resource leveling case, there are two assumptions: (1) There are an unlimited number of crews available to perform the work and (2) The project may not be delayed. The objective of the resource leveling problem is to determine how to limit the fluctuation in crews required on the job. 5
  • 6. B. MATERIALS Materials, for projects with sufficient on-site storage, are delivered to the site and assumed to be available to workers as needed. A material-related concern for sites that have sufficient space is that of optimizing the position of materials on the site so that they require the least travel time from the lay-down yard to the work-face. 6
  • 7. C. EQUIPMENTS There are various types of equipment used on construction sites. Some of this equipment should be considered in the project plan, some need not be included. Workers, and their companies, are typically required to provide the small tools needed to complete their specific features of work. There are some types of equipment, however, that can affect the overall sequence and duration of the project. 7
  • 8. Resource allocation is used to assign the available resources in an economic way. It is part of resource management. In project management, resource allocation is the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time. 8
  • 9. Resource planning cannot be accomplished without four essential resources necessary to accomplish the given scope of work: • MATERIAL • MAN POWER • MACHINARY • TIME 9
  • 10. Human resources for construction planning breaks down into three major categories as follows: • Home office personnel(Administrative Persons) • Construction personnel (field supervision and labor) • Construction subcontractors(Electrification, Plumbing, etc) 10
  • 11. The ideal form of a personnel loading curves is a trapezoid. The average personnel loading curve is a straight line. Actual practice loading curves take the shape of a bell curve 11
  • 12. 12
  • 13. The latter two result when the personnel loading curves occur earlier or later than planned on a project. Front loaded curve- the work started as early as possible. Normal loaded curve- the work started at normal time. Back loaded curve- the work started as late as possible. 13
  • 14. The "S" curve for the ideally loaded project has a gradual start and finish, which indicates smooth starting and finishing conditions. The forward loaded curve shows a rapid project start up and an even more gradual than normal phase out at the end. The backward-loaded project indicates a more relaxed start and a very steep finish slope on the "S" curve. 14
  • 15. 15
  • 16. 16
  • 17. Ensuring that the material resources for the project arrive on time involves these important planning areas: • Long-delivery equipment • Special materials and alloys • Common materials in short supply • Services and system requirements • Transportation systems 17
  • 18. Resource Limited: The project must be finished as soon as possible, but without exceeding some specific level of resource usage or some general resource constraint 18
  • 19. 1. When the schedule demands more workers per day than are available or if we have workers standing around without jobs, we have a problem. 2. When a new hire is trained, there is loss of productivity. So, if we can keep the trained people and reduce the number of new hires, we should be better off. 19
  • 20. . As we know, every project suffers from start-up problems of some sort. Superintendents and project managers are very busy trying to get everybody working in a productivity manner. Therefore, if we can start with a small crew and increase its size gradually, we will eliminate some of the start-up problems. . Most projects suffer from congestion around project completion time because of reduced work areas. Thus, if we can gradually reduce the crew size as we approach project completion, we can improve productivity by reducing congestion. 20
  • 21. The leveling procedure are as follows: • Scheduling all the critical jobs first. • Starting the non-critical jobs whenever there is a drop in scheduled man power upto the point where the peak is reached. • Starting the non-critical jobs whenever there is a drop so that no ups and downs occur in the resource profile. 21
  • 22. › Time Limited: The project must be finished by a certain time, using as few resources as possible. But it is time, not resource usage, that is critical 22
  • 23. Resource Histograms: • A bar chart showing the amount of time assigned to a resource for the time interval. • Resource availability is depicted as a line for comparison purposes. • Resources assigned more work than available hours are considered “over-allocated”. 23
  • 24. INTRODUCTION ERP is a business management software, usually a suite of integrated applications, that a company can use to store and manage data from every stage of business, including: Product planning, cost and development Manufacturing Marketing and sales Inventory management Shipping and payment 24
  • 25. ERP systems could be used in the construction industry for the following general purposes: 1. To improve responsibilities in relation to customers. 2. To strength supply chain partnerships. 3. To enhance organizational flexibility. 4. To improve decision-making capabilities. 5. To reduce project completion time and cost. 25
  • 26. 26
  • 27. 27
  • 28. Without the proper resource allocation, one will pay the price for late job completions and cost overruns. The goal of resource leveling is to assign resources to project activities in a manner that will improve productivity and efficiency. During the last two decades, the construction industry has progressed in this trend of improving resource allocation it merely out of interest but as a means of survival in a more competitive world. 28
  • 29. 29
  • 30. 30