SlideShare una empresa de Scribd logo
1 de 64
Descargar para leer sin conexión
Availability Based
tariff
Presented By:
WASEEM HASHMAT
DY.SUPDT (CHP-O)
Outline of Presentation
• Old Tariff Methodology
• Chronological Sequence of Implementation of ABT
• CERC Tariff regulations
• Concept of ABT
• How the mechanism work with scheduling
• Components of Fixed cost
• Computation of Energy Charge -Thermal
• Advantage of ABT
OLD TARIFFOLD TARIFF
SINGLE PART TARIFF :
 A system of single-part tariff was in vogue in India for pricing of
thermal power prior to 1992.
 The single-part tariff for a station was calculated so as to cover
both the fixed cost as well as the variable (energy) cost at a certain
(normative) generation level.
 A sort of incentive and disincentive was inherent in the single-part
tariff.
 This had induced maximization of generation all the time (in peak
load as well as off-peak hours).
 Led to sharp difference between CGs & SEBs on who should back
down.
OLD TARIFFOLD TARIFF
TWO PART TARIFF :
It has two parts:
1. Fixed Charges
2. Variable charges
Fixed charges include
1. Return on equity
2. O&M charges
3. Interest on loans
4. Interest on working capital
5. Depreciation.
6. Taxes and Duties
Variable Charges i.e. cost of fuel, varies directly with level of generation, consists of
1. Primary fuel (Coal/Gas)
2. Secondary fuel - Oil
 K P Rao Tariff did not encourage grid discipline
 Low frequency during peak hours
 High frequency during off-peak hours
 Rapid changes in frequency and fluctuating voltages
 Reasons
 Conflicting commercial interest in the tariff structure-
SEBs/CGS
 Lack of generating capacity and transmission systems
Two Part Tariff ……..Two Part Tariff ……..DrawbacksDrawbacks
Chronological Sequence of Implementation of ABT
1990 : K. P. Rao Committee – Proposed Two – Part Tariff
structure consisting of Fixed and Variable charges
1993-94 : A structured study by M/s ECC, USA, funded by ADB,
sponsored by World Bank as a covenant of loans to POWERGRID
→ Availability Based Tariff (ABT)
1995-98 : NTF / RTFs, formed for ABT implementation.
NTF/RTF-National/Regional task force
1999 : Matter transferred to CERC : Hearings etc.
2000 : CERC Order, but stayed due to petitions
2001-02 : Problems of regional grid operation continued
: Many intractable commercial disputes also arose
2002-03 : ABT implemented successfully. ADB-Asian development bank
GEN. TARIFF DETERMINATION PROCERDUREGEN. TARIFF DETERMINATION PROCERDURE
Tariff Regulations issued by CERC
Petition to CERC prepared in line
with the Regulations
Financial Details Operational Details
Serve a Copy of application
on each beneficiary
SUBMIT THE APPLICATION TO CERC WITH
• Proof of Dispatch of Application to beneficiaries
• Address of Website hosting the Application
•Application fee draft
Post the application
on Website
Publish Notice in at least two daily newspaper, one in
English & other Vernacular Language within 7 days
Tariff Policy Issued by GOI taken as Guidelines by CERC
CERC Tariff Regulations
Terms and Conditions of Tariff
for three year period
Effective from
1.4.2001 to 31.3.2004.
CERC Notification
dated 26
March,2001,CERC
Regulation-2001.
CERC Notification
dated 21 September,
2001
(First Amendment).
CERC Notification
dated 08 July, 2002,
(First Amendment).
CERC Notification
dated 01 May, 2003
(First Amendment).
Several petitions filed by NTPC during the period 2001-2004Several petitions filed by NTPC during the period 2001-2004
E.g. Petition number-E.g. Petition number- R P 82/2001 in 2/99R P 82/2001 in 2/99
Petition for removing difficulties faced during ABT implementation .Petition for removing difficulties faced during ABT implementation .
CERC Tariff Regulations
CERC-(Terms & Conditions of Tariff)
FY 2004-09
On 26th
March 2004
Petition number-Petition number- I.A. No. 49/2008157/2004
Approval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) forApproval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) for
the period from 1.4.2004 to 31.3.2009.the period from 1.4.2004 to 31.3.2009.
CERC-(Terms & Conditions of Tariff)
FY 2009-14
On 19th
January 2009
Petition number-Petition number- Petition No. 225/2009
Approval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) forApproval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) for
the period from 1.4.2009 to 31.3.2014.the period from 1.4.2009 to 31.3.2014.
 It is a performance-based tariff for the supply of electricity by generators
owned and controlled by the central government.
 It is also a new system of scheduling and despatch, which requires both
generators and beneficiaries to commit to day-ahead schedules.
System of rewards and penalties to enforce day ahead pre-committed
schedules
(though variations are permitted if notified One and one half hours in advance).
It has three parts:
 Fixed charge (FC) payable every month by each beneficiary to the
generator for making capacity available for use. The FC is not the same for
each beneficiary.
It varies with the share of a beneficiary in a generators capacity. The FC,
payable by each beneficiary, will also vary with the level of availability
achieved by a generator.
Concept of ABT
 Energy charge (variable charge) (defined as per the prevailing
operational cost norms) per kwh of energy supplied as per a pre-
committed schedule of supply drawn upon a daily basis.
 Charge for Unscheduled Interchange (UI charge) for the supply
and consumption of energy in variation from the pre-committed daily
schedule.
This charge varies inversely with the system frequency prevailing at
the time of supply/consumption.
 Settlement period of 15 minutes.
 Applicability - Central Stations and drawal from the grid by
beneficiaries
Concept of ABT
How the mechanism work
*ISGS-Interstategeneratingstations*ISGS-Interstategeneratingstations
TIME TABLE FOR EXCHANGE OF INFORMATION
IN RESPECT OF SCHEDULING
By 10.00 hrs. ISGSs shall advise NRLDC the Station-wise MW and MWh
capabilities
By 1100 Hrs. NRLDC shall advise the States / Beneficiaries the Station wise
MW & MWh entitlements.
By 1500 hrs. SLDCs/ Beneficiaries shall communicate the Station-wise
requisitions and details of bilateral exchanges to NRLDC.
By 1700 hrs. NRLDC shall convey the ex-power plant despatch schedule to
each ISGS and net drawal schedule to each State /
Beneficiary. The details of unrequisitioned surpluses shall
also be intimated.
By 2200 hrs.* ISGSs / States / Beneficiaries shall inform the modifications,
if any, for incorporating in the final schedule
By 2300 hrs. NRLDC shall issue the final despatch and drawal schedule for
the next day.
* Since issuing the final despatch and drawal schedule is a critical activity
and considerable time is involved in its preparation and carrying out requisite
moderation, if any, it has been agreed to complete this activity by 2100 hrs.
How the mechanism work
 The CGs/ISGS declare their expected output capacity for the next day
to RLDC by 9 am referred as DC in MWs
 RLDC break-up the DC as per beneficiaries plant-wise share and
convey their entitlement to their SLDCs by 10 am.
 SLDCs sent back their requisition and drawal schedule by 3 pm.
 RLDC aggregates these requisitions and determines dispatch schedule
(Schedule generation) for CGs and drawal schedule for beneficiaries.
duly incorporating any bilateral agreement and adjusting for transmission losses.
 Schedule are then issued by RLDC to all concerned and become
operational datum by 5 pm
How the mechanism work
 During contingencies, the CGs can revise their DC and beneficiaries can
prospectively revise requisition and schedule will be revised by RLDC.
 The schedules are also used for determination of the amounts payable as
energy charges.
 Each day starting from 00.00 Hrs will be divided into 96 time blocks of
15 minutes intervals.
 Deviations from schedules are determined in 15-minute time blocks
through special metering.
These deviations are priced depending on frequency.
 As frequency, AG and SG can vary ,so average of these for 15 minutes
with be final figure for calculation.
Generating StationGenerating Station
1000 MW1000 MW
Coal fired
Three beneficiaries A,B & C
RLDC
DC-900 MW (ex-bus) for next day
State-
A
(30%)
270 MW
SLDC-A
10 am
State-
B
(30%)
270 MW
State-
C
(40%)
360 MW
10 am
10 am
9 am
3 pm 3 pm
3 pm
The Daily Scheduling process
SLDC-
B
SLDC-
C
Suppose requisition received from SLDC to RLDC ( by 3 pm)
A- Fully requisition of their share -270 MW (24 hrs)
B- Fully requisition of their share -270 MW (24 hrs)
C- Requisition 360 MW during day but 200 MW during night
 Now RLDC issue dispatch schedule to both generating stations as
well as beneficiaries by 5 pm.
and would be effective from following midnight (unless modified in the
intervening hours) and will be called Scheduled generation.
 A, B and C shall pay capacity (Fixed) charge for whole day
corresponding to plant availability of 900 MW.
(generating station will get fixed cost corresponds to 900MW)
 Energy charge payment by three states corresponds to:
[270x24MWh ,270x 24 MWh and (360x16 + 200x8) MWh]
Hence, energy charge payment will be made for scheduled generation.
The Daily Scheduling process
Forced Outage:
RLDC To Revise The Schedules Based On Revised Declared
Capability As Advised By The Generator.
The revised schedules to become effective from the 4th time- block
Planned Outage Or Asked By Beneficiaries:
The Revised Schedules / Declared Capability To Become Effective
From The 6th Time-block.
RLDC, on its own, can revise the schedules in the interest of better
system operation.
Merit Order Scheduling
 Beneficiaries to pay the capacity charges as per entitlement.
 Energy charges on schedule generation and not on actual generation.
 Comparison of own generation with UI rate based on variable charge.
 Low UI At High Frequencies Encourage Backing down By Costly
Units And Over Drawl By Beneficiaries.
 High UI Rate At Low Frequencies Encourage Maximum Generation
By All And Curtailment Of Over Drawl.
How the beneficiaries share the payment
 Beneficiaries pay the fixed cost in proportion to their share in
respective plant.
 Payment of fixed cost dependent on Declared capacity (DC) of the
plant for the day.
 Variable cost paid by beneficiaries would be the fuel cost for energy
scheduled to be supplied to them.( Schedule of generation as sent by
RLDC).
 If beneficiaries draw more power than scheduled to be supplied, he
has to pay excess drawal at the rate dependent on system condition.
 If beneficiaries draw less power he gets paid back for energy not
drawn dependent on system condition.
 The actual energy supplied by generating station may differ from
what was scheduled.
 This deviation from the schedule technically termed as Unscheduled
Interchange (UI).
 The generating station receive or pay back for excess or shortfall of
the scheduled generation, supplied at a rate dependent on frequency
at that time.
 The relationship between UI rate and grid frequency, for the
interconnected system is specified by CERC.
 Latest UI regulation by CERC is effective from 03/05/2010.
(First amendment of principal UI regulation-2009)
Deviation from schedule
Deviation from schedule
 Most recent UI regulation which was supposed to be effective
from 2nd
April 2012 is on hold due to petition.
(Second amendment of principal UI regulation)
 Below 50.2 Hz and upto 49.7 Hz, linear in 0.02 Hz step,
at the rate 15.5 paise / kWh.
 Below 49.7 Hz and upto 49.5 Hz, linear in 0.02 Hz step,
at the rate 47.0 paise /kWh.
 Below 49.50 Hz at the rate 873.00 paise /kWh.
 UI rate is zero above frequency 50.2 Hz and the break even
frequency was considered 50.06 Hz
Unscheduled Interchange
Additional UI for over drawal:
 Below 49.5 Hz to 49.2 Hz@40% of the UI Charges at
49.5 Hz of Rs. 8.73/kWh.
 Below 49.2 Hz @100% of the UI Charges at 49.5 Hz of
Rs. 8.73/kWh
Additional UI for Under Injection:
Below 49.5 Hz & up to 49.2 Hz, Additional UI is 20% of the
Unscheduled Interchange Charge of 873.0 Paise/kWh
(corresponding to the grid frequency of below 49.5 Hz)
Below 49.2 Hz, Additional UI is 40 % of Unscheduled Interchange
Charge of 873.0 Paise/kWh
Additional UI
UI Price Vector
08/06/13 28CERC
New UI Regulation
UI charge when Actual Generation is in
excess of 105 % of Declared Capacity in
a Time Block or in excess of 101 % of
average Declared Capacity over a day
corresponding to grid frequency interval
of below 49.70 Hz and not below 49.68
Hz i.e. 403 paisa/kWh.
Earlier it was zero.
New UI Regulation
Under injection of electricity by a
generating station during a time block shall
not exceed 12% of scheduled injection
when frequency is below 49.7 Hz and 3%
on daily aggregate basis for all time blocks
when frequency is below 49.7 Hz.
CAPACITY
CHARGES
ENERGY
CHARGES
UI
MECHANISM
FIXED
CHARGES
+ +
VARIABLE
CHARGES BALANCE
Based on Declared
Capacity
Target avl-85%
Based on Schedule
Generation
Components of ABT
for recovery
of Annual
Fixed Costs)
for recovery of
Primary Fuel
Costs
for deviation
from the
schedule
As per frequency
linked rate
Fixed cost – These costs are permanent in nature independent
of level of production/generation.
Components of Fixed costComponents of Fixed cost ::
1. Return on Equity1. Return on Equity
2. Interest on Loan Capital2. Interest on Loan Capital
3. Depreciation3. Depreciation
4.4. Interest on Working CapitalInterest on Working Capital
5.5. Operation and Maintenance ExpensesOperation and Maintenance Expenses
New addition to AFC –New addition to AFC – Applicable for Coal Stations onlyApplicable for Coal Stations only
6.6. Cost of Secondary Fuel OilCost of Secondary Fuel Oil **
7.7. Either Compensatory Allowance for coal based stations uptoEither Compensatory Allowance for coal based stations upto
25 years of life or Special Allowance in lieu of R&M beyond25 years of life or Special Allowance in lieu of R&M beyond
25 years.25 years.**
** Included in CERC tariff regulation 2009-14Included in CERC tariff regulation 2009-14
Annual Fixed Charges
Definition of 'Return On Equity – ROEDefinition of 'Return On Equity – ROE’(RONW)’(RONW)**
The amount of net income returned as a percentage of shareholdersThe amount of net income returned as a percentage of shareholders
equity. Return on equity measures a corporation’s profitability by revealingequity. Return on equity measures a corporation’s profitability by revealing
how much profit a company generates with the money shareholders havehow much profit a company generates with the money shareholders have
invested.invested.
ROE is expressed as a percentage and calculated as:ROE is expressed as a percentage and calculated as:
Return on Equity = Net Income (PBTReturn on Equity = Net Income (PBT****)/Shareholder's Equity (Rs))/Shareholder's Equity (Rs)
Indirect method of taking profit through fixed cost.
Every generating station has certain percentage of debt (loan) and equity
i.e., 70:30 for new plant and 50:50 for existing plants, existing before
1/4/2009.(As per CERC tariff regulation 2009-14).
Certain percentage of that equity (money by shareholders) will be taken as
fixed cost (percentage will be decided by CERC).
1. Return on equity
 ROE will be used for capacity addition or giving dividend
to share holders or can be kept as reserve and surplus.
 If equity employed is less than 30%, the actual equity and
loan shall be considered for determination of return on
equity.
 Pre Tax Return to incentivise investment in sector.
 Rate of Return will be 15.5% for existing stations (CERC
Regulation 2009-14)
 Reason for increase in ROE is the Prime Lending Rate
(PLR) of the public sector banks have increased during
this period. (March 2004 10.25% -January 2009 14.00%)
Return on equity
Actual equity in excess of 30% will be treated as loanActual equity in excess of 30% will be treated as loan
 ROE will be 23.481% for the companies paying normal
tax.
This is given by formula:
Rate of pre-tax return on equity = Base rate / (1-t)
Where t is the applicable tax rate
Base rate is 15.5 %.
t = 33.99 % for company paying normal tax.
Objective
To provide fair return on the investment by
the investor and for generation of internal
resources for capacity additions.
Return on equity
Return on equity
Return on equity
(CoG)(CoG)
Return on equity
(CoG)(CoG)
 Approval for return on equity for SSTPS for the period
2009-14 given by hearing on petition no- 225/2009
CERCtariffregulation2009-14
 Products / services which are basic need of society, used by
all sections of society irrespective of their status , infrastructure
/ basic amenities normally falls in this category . Prices/
tariffs are determined by the Govt. body / independent
regulator . During the price determination , all the costs
required to produce the product / services along with
reasonable profit ( return on capital/equity ) are considered.
Cost plus method is employed to avoid stranded cost of
redundant assets , to insulate the consumers from vide
market fluctuations, market abuse by dominant players .
Examples – Electricity, Petroleum, Fertilizer, Railways etc.
Price = Cost+ Profit
Cost Plus Price Mechanism
 Interest on loan is calculated based on the weighted
average rate of interest and applied to the outstanding
loans.
 Loans are reduced to the extent of repayment each year
during the tariff period.
 No interest element is included in tariff after repayment of
the entire loan.
 To be charged from 1st year of CoD irrespective of
moratorium.
2. Interest on Loan CapitalInterest on Loan Capital
CERC tariff regulation 2009-14
Depreciation is an important element of cost and forms a part of the
fixed cost recovery. The objective is that the recoveries through
depreciation should be adequate to provide resources to the
investor to replace the assets after their useful life.
Depreciable value 90% (except land).
Depreciable life:
Thermal - 25 years for both coal and gas station
Hydro - 35 years
Rates as per latest CERC notification for coal based stations
3.6% of capital cost.
AAD (Advance against depreciation) is removed from CERC
Regulation 2009-14,hence rate of depreciation in increasing.
3. DepreciationDepreciation
CERCtariffregulation2009-14
 Coal Based StationsCoal Based Stations
 1.5 months fuel expenses for pit head and 2 months for1.5 months fuel expenses for pit head and 2 months for
non pit head.non pit head.
 Secondary fuel oil for 2 monthsSecondary fuel oil for 2 months
 Maintenance spares @ 20% of O&MMaintenance spares @ 20% of O&M
 Receivables for 2 monthsReceivables for 2 months
 O&M expenses for 1 monthO&M expenses for 1 month
 Cost of fuel wrt Price & GCV of preceding 3 months.Cost of fuel wrt Price & GCV of preceding 3 months.
 Rate of interest will be SBI PLR as on 1.4.2009 andRate of interest will be SBI PLR as on 1.4.2009 and
no fuel escalation will be permitted in workingno fuel escalation will be permitted in working
capital whereas rebate will be payable at currentcapital whereas rebate will be payable at current
priceprice
4. Interest on Working CapitalInterest on Working Capital
CERC tariff regulation 2009-14
For SSTPSFor SSTPS
4. Interest on Working CapitalInterest on Working Capital
Petition No. 225/2009
5. Operation and Maintenance ExpensesOperation and Maintenance Expenses
COMPONENTS OF O&M EXPENSES
The Operation & Maintenance cost :
Expenditure incurred on the employees including gratuity, CPF, medical,
education allowances etc
+
Repair and maintenance expenses including stores and consumables,
+
Consumption of capital spares which are not a part of capital cost
+
Security expenses,
+
Administrative expenses etc. of the generating stations
+
Corporate expenses apportioned to each generating stations
+
Others (water Charge+ insurance etc)
5. Operation and Maintenance ExpensesOperation and Maintenance Expenses
Methodology adopted by CERC while fixing O&M Norms
 The actual O&M expenses of Central utilities for the years
2003-04 to 2007-08 are taken and then averaged.
 Then incentive & ex-gratia paid to its employees, donations,
loss in stock, prior period adjustments, claims and advances
are written off.
 Based on escalation rates for the year 2003-4 to 2007-08, the
annual escalation rate worked out as 5.72%.
 The average normalized operation and maintenance expenses
at 2007-08 price level shall be escalated at the rate of 5.72% to
arrive at the operation and maintenance expenses for year
2009-10
5. Operation and Maintenance ExpensesOperation and Maintenance Expenses
 Provided that operation and maintenance expenses for the year
2009-10 shall be further rationalized considering 50% increase
in employee cost on account of pay revision.
As per CERC regulation 2009-14 the O&M will be:
CERCtariffregulation2009-
14
5. Operation and Maintenance ExpensesOperation and Maintenance Expenses
 In addition to the normative O&M cost the regulator has also
allowed a separate compensation allowance for meeting the
expenses on new capital assets, which will be based on year of
completion of the project.
CERC tariff regulation 2009-14
Reasons for shifting secondary oil cost to Capacity charge
 Secondary oil is required occasionally,and at a load
above about 70% it is normally not required to be fired.
Therefore, energy charge consisting of Coal as well as
oil charges does not give real situation on merit order.
 Generators are scheduled to generate as per "merit-
order.
6. Cost of Secondary Fuel OilCost of Secondary Fuel Oil
CERC tariff regulation 2009-14
 Expenses on secondary fuel oil in Rupees shall be computed
corresponding to normative secondary fuel oil consumption
= SFC x LPSFi x NAPAF x 24 x NDY x IC x 10
Where,
SFC – Normative Specific Fuel Oil consumption in ml/kWh
LPSFi – Weighted Average Landed Price of Secondary Fuel in
Rs./ml considered initially
NAPAF – Normative Annual Plant Availability Factor in
percentage
NDY – Number of days in a year
IC - Installed Capacity in MW.
6. Cost of Secondary Fuel OilCost of Secondary Fuel Oil
CERC tariff regulation 2009-14
 Alternatively, we may avail a ‘special allowance’ for coal based station @
Rs. 5 lakh / MW / year with annual escalation of 5.72% during 2009-14 as
compensation for meeting the R&M expenses beyond the useful life.
Compensatory Allowance for SSTPS
7. Special Allowance in lieu of R&M orSpecial Allowance in lieu of R&M or
Compensatory AllowanceCompensatory Allowance
CERCtariffregulation2009-14
Station for 08-09 for 09-10
Singrauli Nil 9.2
Rihand-I Nil 3.5
Rihand-II Nil 0
Unchahar-I Nil 1.5
Unchahar-II Nil 0
Unchahar-III Nil 0
Tanda Nil 1.5
Annual fixed cost of claimed by the petitioner (SSTPS) for
2009-14
Petition No.189/2009
Annual Fixed Charges
Annual fixed cost Approved by CERC for SSTPS:
Petition No. 225/2009 Date of Order-7/8/2012
Annual Fixed Charges
44 paisa100 % Fixed cost at 85 %
Availability
Comparison of fixed cost from 2009-12 with 2004-09
Annual Fixed Charges
www.icra.in
Annual Fixed Charges
Incentive:
 Incentive will be in the form of increased AFC with respect to
Availability.
 Again, this incentive will be double for Old stations w.r.t. new
stations.
– For stations > 10 years
= (AFC x NDM / NDY) x (PAFM / NAPAF)
– For stations <= 10 years
= (AFC x NDM / NDY) x 0.5 (1.0 + PAFM / NAPAF)
Case : Singrauli
 If availability is increased by 1%,then station will get extra 6.62
Cr/Yr (base is 85 %)
 Or station will get extra 37.77 paisa/Unit above 85% of
availability.
Normative Annual Plant Availability Factor (NAPAF)
 normative annual plant availability factor’ or ‘NAPAF’ in
relation to a generating station means the availability factor.
 At 85% of availability, full Fixed Charge will be recovered. If
this availability increases above 85%, then Fixed charge will
also increase.
Annual Fixed Charges
Computation of Energy Charge -Thermal
The energy charge shall cover the primary fuel cost
(Energy charge rate in Rs./kWh) x {Scheduled energy (ex-bus) for the
month in kWh.}
Computation of Energy charges (EC)Computation of Energy charges (EC)
Energy Charge covering primary fuel cost shall be payable for totalEnergy Charge covering primary fuel cost shall be payable for total
ex-bus energy scheduled to be supplied to the beneficiary duringex-bus energy scheduled to be supplied to the beneficiary during
the calendar month, at the specified energy charge rate.the calendar month, at the specified energy charge rate.
Energy charge rate (Energy charge rate (ECECRR) in Rs. per kWh on ex-power plant basis:) in Rs. per kWh on ex-power plant basis:
For coal or lignite fired based stationsFor coal or lignite fired based stations
ECR = (GHR – SFC x CVSF) x LPPF / CVPF x 100 / (100 – AUX)}ECR = (GHR – SFC x CVSF) x LPPF / CVPF x 100 / (100 – AUX)}
CERC tariff regulation 2009-14
Computation of Energy Charge -Thermal
Landed Cost of CoalLanded Cost of Coal
Price of coal corresponding to the grade and quality inclusivePrice of coal corresponding to the grade and quality inclusive
of royalty, taxes and duties applicable & transportation cost.of royalty, taxes and duties applicable & transportation cost.
Considering normative transit and handling losses :Considering normative transit and handling losses :
Pit head stations : 0.2% ; Non-Pit head stations : 0.8%Pit head stations : 0.2% ; Non-Pit head stations : 0.8%
CERCtariffregulation2009-14
Computation of Energy Charge -Thermal
www.icra.in
Energy charges for thermal power stations are linked to the normative operational
parameters as specified by the regulator
Heat rate comparison of 2004-9 and 2009-14Heat rate comparison of 2004-9 and 2009-14
Computation of Energy Charge -Thermal
The Energy Charge Rate claimed by the SSTPS and approved.
However, energy charge on month to month basis will be billed by
the petitioner as per the 2009 Tariff Regulations.
PetitionNo.225/2009
Advantages of ABT
GRID DISCIPLINE
 Adherence to the schedule
 Commercial incentives for operational discipline leads to
better load management. Backing down under high
frequency is encouraged.
FACILITATES TRADING IN CAPACITY AND ENERGY
MERIT ORDER OPERATION
ECONOMIC GENERATION
Capacity Charge and Energy Charge do not depend on actual
plant generation / drawal. No metering required for this as they
are based on off-line figures. All deviations taken care of by UI
PERFORM, ACHIEVE AND TRADE

Más contenido relacionado

La actualidad más candente

Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorVijay Menghani
 
From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...Amitava Nag
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNAIPPAI
 
NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)Ravi Pohani
 
Power scenario in india
Power scenario in indiaPower scenario in india
Power scenario in indiaAnkur Mahajan
 
Multi year tariffs and regulations
Multi year tariffs and regulationsMulti year tariffs and regulations
Multi year tariffs and regulationsNavajyoti Martha
 
001 conservation-Energy Audit -Methods
001 conservation-Energy Audit -Methods 001 conservation-Energy Audit -Methods
001 conservation-Energy Audit -Methods Anil Palamwar
 
Indian electricity market and power exchanges
Indian electricity market and power exchangesIndian electricity market and power exchanges
Indian electricity market and power exchangesNageswar Rao
 
Electricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsElectricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsAmitava Nag
 
Renewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) MechanismRenewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) MechanismKranav Sharma
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationJerry Sakala
 
Power Plant cost & its site selection
Power Plant cost & its site selectionPower Plant cost & its site selection
Power Plant cost & its site selectionSamandeep Singh
 

La actualidad más candente (20)

Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
 
From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...From centralised long-term planning to market-based access: Proposed change i...
From centralised long-term planning to market-based access: Proposed change i...
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
 
NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)NPTI 15th batch Indian electricity grid code (IEGC)
NPTI 15th batch Indian electricity grid code (IEGC)
 
Power scenario in india
Power scenario in indiaPower scenario in india
Power scenario in india
 
Indian Electricity Grid Code
Indian Electricity Grid CodeIndian Electricity Grid Code
Indian Electricity Grid Code
 
OPEN ACCESS REGULATION
OPEN ACCESS REGULATIONOPEN ACCESS REGULATION
OPEN ACCESS REGULATION
 
Multi year tariffs and regulations
Multi year tariffs and regulationsMulti year tariffs and regulations
Multi year tariffs and regulations
 
001 conservation-Energy Audit -Methods
001 conservation-Energy Audit -Methods 001 conservation-Energy Audit -Methods
001 conservation-Energy Audit -Methods
 
Indian electricity market and power exchanges
Indian electricity market and power exchangesIndian electricity market and power exchanges
Indian electricity market and power exchanges
 
Electricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendmentsElectricity Act 2003 and its proposed amendments
Electricity Act 2003 and its proposed amendments
 
Availability Based Tariff and UI charges
Availability Based Tariff and UI chargesAvailability Based Tariff and UI charges
Availability Based Tariff and UI charges
 
Renewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) MechanismRenewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) Mechanism
 
Abt meter
Abt meterAbt meter
Abt meter
 
Electricity market 2030_presentation_long_new
Electricity market 2030_presentation_long_newElectricity market 2030_presentation_long_new
Electricity market 2030_presentation_long_new
 
Power Markets & Trading in India
Power Markets & Trading in IndiaPower Markets & Trading in India
Power Markets & Trading in India
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentation
 
Power Plant cost & its site selection
Power Plant cost & its site selectionPower Plant cost & its site selection
Power Plant cost & its site selection
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 

Destacado

DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANTDEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANTAkash M
 
Engineering Australia Excellence Award - Port Hedland Port Authority
Engineering Australia Excellence Award - Port Hedland Port AuthorityEngineering Australia Excellence Award - Port Hedland Port Authority
Engineering Australia Excellence Award - Port Hedland Port AuthorityChailee Richards
 
Coal seam fire and spontaneous heating [recovered]
Coal seam fire and spontaneous heating [recovered]Coal seam fire and spontaneous heating [recovered]
Coal seam fire and spontaneous heating [recovered]Abhishek Kumar Pandey
 
Spontaneous Combustion
Spontaneous CombustionSpontaneous Combustion
Spontaneous CombustionRon Thaman
 
Tariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEATariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEAAshish Verma
 
Spontaneous combustion of coal
Spontaneous combustion of coalSpontaneous combustion of coal
Spontaneous combustion of coalMohit Jain
 
Best ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantBest ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantRonak Thakare
 

Destacado (8)

DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANTDEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
DEVELOPMENT OF CONDITION BASED MAINTENAENCE FOR COAL HANDLING PLANT
 
Engineering Australia Excellence Award - Port Hedland Port Authority
Engineering Australia Excellence Award - Port Hedland Port AuthorityEngineering Australia Excellence Award - Port Hedland Port Authority
Engineering Australia Excellence Award - Port Hedland Port Authority
 
Coal seam fire and spontaneous heating [recovered]
Coal seam fire and spontaneous heating [recovered]Coal seam fire and spontaneous heating [recovered]
Coal seam fire and spontaneous heating [recovered]
 
Spontaneous Combustion
Spontaneous CombustionSpontaneous Combustion
Spontaneous Combustion
 
Tariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEATariff and Duty of Electricity supply in various State of India-A review by CEA
Tariff and Duty of Electricity supply in various State of India-A review by CEA
 
Spontaneous combustion of coal
Spontaneous combustion of coalSpontaneous combustion of coal
Spontaneous combustion of coal
 
Fly ash presentation
Fly ash presentationFly ash presentation
Fly ash presentation
 
Best ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantBest ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plant
 

Similar a ABT a complete report and a case study

Presentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptxPresentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptxRuchikavanjari6thstd
 
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureSALMAN SAEED
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)professionalpanorama
 
Cost appraisal of chhabra thermal
Cost appraisal of chhabra thermalCost appraisal of chhabra thermal
Cost appraisal of chhabra thermalTapasya123
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewIOSR Journals
 
Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...
Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...
Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...Matthew Behrens
 
Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)Dhruv Agarwal
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
 
Forecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forForecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forJay Ranvir
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyJay Ranvir
 
23.01.2023_Tariff Presentations_O_M.pptx
23.01.2023_Tariff Presentations_O_M.pptx23.01.2023_Tariff Presentations_O_M.pptx
23.01.2023_Tariff Presentations_O_M.pptxGholamRabbaniGhause
 
What is availability tariff
What is availability tariffWhat is availability tariff
What is availability tariffJay Ranvir
 
Technical minimum schedule for ppt f
Technical minimum schedule for  ppt fTechnical minimum schedule for  ppt f
Technical minimum schedule for ppt fvickylko11
 
Indian power sector
Indian power sectorIndian power sector
Indian power sectorVivek Mohan
 

Similar a ABT a complete report and a case study (20)

Presentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptxPresentation_on_DSM_and_ABTmechanisam.pptx
Presentation_on_DSM_and_ABTmechanisam.pptx
 
Commercial presentation
Commercial presentationCommercial presentation
Commercial presentation
 
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
 
Cost appraisal of chhabra thermal
Cost appraisal of chhabra thermalCost appraisal of chhabra thermal
Cost appraisal of chhabra thermal
 
Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
 
Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...
Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...
Wind Prospect Poster 023 - Optimising Facility Power Curve Calculations in So...
 
Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)Power system operation corporation ltd (posoco)
Power system operation corporation ltd (posoco)
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
Forecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forForecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling for
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind Energy
 
23.01.2023_Tariff Presentations_O_M.pptx
23.01.2023_Tariff Presentations_O_M.pptx23.01.2023_Tariff Presentations_O_M.pptx
23.01.2023_Tariff Presentations_O_M.pptx
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
 
What is availability tariff
What is availability tariffWhat is availability tariff
What is availability tariff
 
Technical minimum schedule for ppt f
Technical minimum schedule for  ppt fTechnical minimum schedule for  ppt f
Technical minimum schedule for ppt f
 
Indian power sector
Indian power sectorIndian power sector
Indian power sector
 
CHAP 3.4 - TARIFF.pdf
CHAP 3.4 - TARIFF.pdfCHAP 3.4 - TARIFF.pdf
CHAP 3.4 - TARIFF.pdf
 

Último

Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfPrerana Jadhav
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
CLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptxCLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptxAnupam32727
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...DhatriParmar
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQuiz Club NITW
 
Indexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfIndexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfChristalin Nelson
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Celine George
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17Celine George
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWQuiz Club NITW
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
ARTERIAL BLOOD GAS ANALYSIS........pptx
ARTERIAL BLOOD  GAS ANALYSIS........pptxARTERIAL BLOOD  GAS ANALYSIS........pptx
ARTERIAL BLOOD GAS ANALYSIS........pptxAneriPatwari
 

Último (20)

Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdf
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
CLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptxCLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptx
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
 
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of EngineeringFaculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
 
Indexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfIndexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdf
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITW
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptxINCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
 
Mattingly "AI & Prompt Design: Large Language Models"
Mattingly "AI & Prompt Design: Large Language Models"Mattingly "AI & Prompt Design: Large Language Models"
Mattingly "AI & Prompt Design: Large Language Models"
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
ARTERIAL BLOOD GAS ANALYSIS........pptx
ARTERIAL BLOOD  GAS ANALYSIS........pptxARTERIAL BLOOD  GAS ANALYSIS........pptx
ARTERIAL BLOOD GAS ANALYSIS........pptx
 

ABT a complete report and a case study

  • 2. Outline of Presentation • Old Tariff Methodology • Chronological Sequence of Implementation of ABT • CERC Tariff regulations • Concept of ABT • How the mechanism work with scheduling • Components of Fixed cost • Computation of Energy Charge -Thermal • Advantage of ABT
  • 3. OLD TARIFFOLD TARIFF SINGLE PART TARIFF :  A system of single-part tariff was in vogue in India for pricing of thermal power prior to 1992.  The single-part tariff for a station was calculated so as to cover both the fixed cost as well as the variable (energy) cost at a certain (normative) generation level.  A sort of incentive and disincentive was inherent in the single-part tariff.  This had induced maximization of generation all the time (in peak load as well as off-peak hours).  Led to sharp difference between CGs & SEBs on who should back down.
  • 4. OLD TARIFFOLD TARIFF TWO PART TARIFF : It has two parts: 1. Fixed Charges 2. Variable charges Fixed charges include 1. Return on equity 2. O&M charges 3. Interest on loans 4. Interest on working capital 5. Depreciation. 6. Taxes and Duties Variable Charges i.e. cost of fuel, varies directly with level of generation, consists of 1. Primary fuel (Coal/Gas) 2. Secondary fuel - Oil
  • 5.  K P Rao Tariff did not encourage grid discipline  Low frequency during peak hours  High frequency during off-peak hours  Rapid changes in frequency and fluctuating voltages  Reasons  Conflicting commercial interest in the tariff structure- SEBs/CGS  Lack of generating capacity and transmission systems Two Part Tariff ……..Two Part Tariff ……..DrawbacksDrawbacks
  • 6. Chronological Sequence of Implementation of ABT 1990 : K. P. Rao Committee – Proposed Two – Part Tariff structure consisting of Fixed and Variable charges 1993-94 : A structured study by M/s ECC, USA, funded by ADB, sponsored by World Bank as a covenant of loans to POWERGRID → Availability Based Tariff (ABT) 1995-98 : NTF / RTFs, formed for ABT implementation. NTF/RTF-National/Regional task force 1999 : Matter transferred to CERC : Hearings etc. 2000 : CERC Order, but stayed due to petitions 2001-02 : Problems of regional grid operation continued : Many intractable commercial disputes also arose 2002-03 : ABT implemented successfully. ADB-Asian development bank
  • 7. GEN. TARIFF DETERMINATION PROCERDUREGEN. TARIFF DETERMINATION PROCERDURE Tariff Regulations issued by CERC Petition to CERC prepared in line with the Regulations Financial Details Operational Details Serve a Copy of application on each beneficiary SUBMIT THE APPLICATION TO CERC WITH • Proof of Dispatch of Application to beneficiaries • Address of Website hosting the Application •Application fee draft Post the application on Website Publish Notice in at least two daily newspaper, one in English & other Vernacular Language within 7 days Tariff Policy Issued by GOI taken as Guidelines by CERC
  • 8. CERC Tariff Regulations Terms and Conditions of Tariff for three year period Effective from 1.4.2001 to 31.3.2004. CERC Notification dated 26 March,2001,CERC Regulation-2001. CERC Notification dated 21 September, 2001 (First Amendment). CERC Notification dated 08 July, 2002, (First Amendment). CERC Notification dated 01 May, 2003 (First Amendment). Several petitions filed by NTPC during the period 2001-2004Several petitions filed by NTPC during the period 2001-2004 E.g. Petition number-E.g. Petition number- R P 82/2001 in 2/99R P 82/2001 in 2/99 Petition for removing difficulties faced during ABT implementation .Petition for removing difficulties faced during ABT implementation .
  • 9. CERC Tariff Regulations CERC-(Terms & Conditions of Tariff) FY 2004-09 On 26th March 2004 Petition number-Petition number- I.A. No. 49/2008157/2004 Approval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) forApproval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) for the period from 1.4.2004 to 31.3.2009.the period from 1.4.2004 to 31.3.2009. CERC-(Terms & Conditions of Tariff) FY 2009-14 On 19th January 2009 Petition number-Petition number- Petition No. 225/2009 Approval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) forApproval of tariff in respect of Singrauli Super Thermal Power Station (2000 MW) for the period from 1.4.2009 to 31.3.2014.the period from 1.4.2009 to 31.3.2014.
  • 10.  It is a performance-based tariff for the supply of electricity by generators owned and controlled by the central government.  It is also a new system of scheduling and despatch, which requires both generators and beneficiaries to commit to day-ahead schedules. System of rewards and penalties to enforce day ahead pre-committed schedules (though variations are permitted if notified One and one half hours in advance). It has three parts:  Fixed charge (FC) payable every month by each beneficiary to the generator for making capacity available for use. The FC is not the same for each beneficiary. It varies with the share of a beneficiary in a generators capacity. The FC, payable by each beneficiary, will also vary with the level of availability achieved by a generator. Concept of ABT
  • 11.  Energy charge (variable charge) (defined as per the prevailing operational cost norms) per kwh of energy supplied as per a pre- committed schedule of supply drawn upon a daily basis.  Charge for Unscheduled Interchange (UI charge) for the supply and consumption of energy in variation from the pre-committed daily schedule. This charge varies inversely with the system frequency prevailing at the time of supply/consumption.  Settlement period of 15 minutes.  Applicability - Central Stations and drawal from the grid by beneficiaries Concept of ABT
  • 12. How the mechanism work *ISGS-Interstategeneratingstations*ISGS-Interstategeneratingstations
  • 13. TIME TABLE FOR EXCHANGE OF INFORMATION IN RESPECT OF SCHEDULING By 10.00 hrs. ISGSs shall advise NRLDC the Station-wise MW and MWh capabilities By 1100 Hrs. NRLDC shall advise the States / Beneficiaries the Station wise MW & MWh entitlements. By 1500 hrs. SLDCs/ Beneficiaries shall communicate the Station-wise requisitions and details of bilateral exchanges to NRLDC. By 1700 hrs. NRLDC shall convey the ex-power plant despatch schedule to each ISGS and net drawal schedule to each State / Beneficiary. The details of unrequisitioned surpluses shall also be intimated. By 2200 hrs.* ISGSs / States / Beneficiaries shall inform the modifications, if any, for incorporating in the final schedule By 2300 hrs. NRLDC shall issue the final despatch and drawal schedule for the next day. * Since issuing the final despatch and drawal schedule is a critical activity and considerable time is involved in its preparation and carrying out requisite moderation, if any, it has been agreed to complete this activity by 2100 hrs.
  • 14. How the mechanism work  The CGs/ISGS declare their expected output capacity for the next day to RLDC by 9 am referred as DC in MWs  RLDC break-up the DC as per beneficiaries plant-wise share and convey their entitlement to their SLDCs by 10 am.  SLDCs sent back their requisition and drawal schedule by 3 pm.  RLDC aggregates these requisitions and determines dispatch schedule (Schedule generation) for CGs and drawal schedule for beneficiaries. duly incorporating any bilateral agreement and adjusting for transmission losses.  Schedule are then issued by RLDC to all concerned and become operational datum by 5 pm
  • 15. How the mechanism work  During contingencies, the CGs can revise their DC and beneficiaries can prospectively revise requisition and schedule will be revised by RLDC.  The schedules are also used for determination of the amounts payable as energy charges.  Each day starting from 00.00 Hrs will be divided into 96 time blocks of 15 minutes intervals.  Deviations from schedules are determined in 15-minute time blocks through special metering. These deviations are priced depending on frequency.  As frequency, AG and SG can vary ,so average of these for 15 minutes with be final figure for calculation.
  • 16. Generating StationGenerating Station 1000 MW1000 MW Coal fired Three beneficiaries A,B & C RLDC DC-900 MW (ex-bus) for next day State- A (30%) 270 MW SLDC-A 10 am State- B (30%) 270 MW State- C (40%) 360 MW 10 am 10 am 9 am 3 pm 3 pm 3 pm The Daily Scheduling process SLDC- B SLDC- C
  • 17. Suppose requisition received from SLDC to RLDC ( by 3 pm) A- Fully requisition of their share -270 MW (24 hrs) B- Fully requisition of their share -270 MW (24 hrs) C- Requisition 360 MW during day but 200 MW during night  Now RLDC issue dispatch schedule to both generating stations as well as beneficiaries by 5 pm. and would be effective from following midnight (unless modified in the intervening hours) and will be called Scheduled generation.  A, B and C shall pay capacity (Fixed) charge for whole day corresponding to plant availability of 900 MW. (generating station will get fixed cost corresponds to 900MW)  Energy charge payment by three states corresponds to: [270x24MWh ,270x 24 MWh and (360x16 + 200x8) MWh] Hence, energy charge payment will be made for scheduled generation.
  • 18.
  • 19. The Daily Scheduling process Forced Outage: RLDC To Revise The Schedules Based On Revised Declared Capability As Advised By The Generator. The revised schedules to become effective from the 4th time- block Planned Outage Or Asked By Beneficiaries: The Revised Schedules / Declared Capability To Become Effective From The 6th Time-block. RLDC, on its own, can revise the schedules in the interest of better system operation.
  • 20. Merit Order Scheduling  Beneficiaries to pay the capacity charges as per entitlement.  Energy charges on schedule generation and not on actual generation.  Comparison of own generation with UI rate based on variable charge.  Low UI At High Frequencies Encourage Backing down By Costly Units And Over Drawl By Beneficiaries.  High UI Rate At Low Frequencies Encourage Maximum Generation By All And Curtailment Of Over Drawl.
  • 21. How the beneficiaries share the payment  Beneficiaries pay the fixed cost in proportion to their share in respective plant.  Payment of fixed cost dependent on Declared capacity (DC) of the plant for the day.  Variable cost paid by beneficiaries would be the fuel cost for energy scheduled to be supplied to them.( Schedule of generation as sent by RLDC).  If beneficiaries draw more power than scheduled to be supplied, he has to pay excess drawal at the rate dependent on system condition.  If beneficiaries draw less power he gets paid back for energy not drawn dependent on system condition.
  • 22.  The actual energy supplied by generating station may differ from what was scheduled.  This deviation from the schedule technically termed as Unscheduled Interchange (UI).  The generating station receive or pay back for excess or shortfall of the scheduled generation, supplied at a rate dependent on frequency at that time.  The relationship between UI rate and grid frequency, for the interconnected system is specified by CERC.  Latest UI regulation by CERC is effective from 03/05/2010. (First amendment of principal UI regulation-2009) Deviation from schedule
  • 23. Deviation from schedule  Most recent UI regulation which was supposed to be effective from 2nd April 2012 is on hold due to petition. (Second amendment of principal UI regulation)  Below 50.2 Hz and upto 49.7 Hz, linear in 0.02 Hz step, at the rate 15.5 paise / kWh.  Below 49.7 Hz and upto 49.5 Hz, linear in 0.02 Hz step, at the rate 47.0 paise /kWh.  Below 49.50 Hz at the rate 873.00 paise /kWh.  UI rate is zero above frequency 50.2 Hz and the break even frequency was considered 50.06 Hz
  • 25.
  • 26.
  • 27. Additional UI for over drawal:  Below 49.5 Hz to 49.2 Hz@40% of the UI Charges at 49.5 Hz of Rs. 8.73/kWh.  Below 49.2 Hz @100% of the UI Charges at 49.5 Hz of Rs. 8.73/kWh Additional UI for Under Injection: Below 49.5 Hz & up to 49.2 Hz, Additional UI is 20% of the Unscheduled Interchange Charge of 873.0 Paise/kWh (corresponding to the grid frequency of below 49.5 Hz) Below 49.2 Hz, Additional UI is 40 % of Unscheduled Interchange Charge of 873.0 Paise/kWh Additional UI
  • 29. New UI Regulation UI charge when Actual Generation is in excess of 105 % of Declared Capacity in a Time Block or in excess of 101 % of average Declared Capacity over a day corresponding to grid frequency interval of below 49.70 Hz and not below 49.68 Hz i.e. 403 paisa/kWh. Earlier it was zero.
  • 30. New UI Regulation Under injection of electricity by a generating station during a time block shall not exceed 12% of scheduled injection when frequency is below 49.7 Hz and 3% on daily aggregate basis for all time blocks when frequency is below 49.7 Hz.
  • 31.
  • 32.
  • 33. CAPACITY CHARGES ENERGY CHARGES UI MECHANISM FIXED CHARGES + + VARIABLE CHARGES BALANCE Based on Declared Capacity Target avl-85% Based on Schedule Generation Components of ABT for recovery of Annual Fixed Costs) for recovery of Primary Fuel Costs for deviation from the schedule As per frequency linked rate
  • 34. Fixed cost – These costs are permanent in nature independent of level of production/generation. Components of Fixed costComponents of Fixed cost :: 1. Return on Equity1. Return on Equity 2. Interest on Loan Capital2. Interest on Loan Capital 3. Depreciation3. Depreciation 4.4. Interest on Working CapitalInterest on Working Capital 5.5. Operation and Maintenance ExpensesOperation and Maintenance Expenses New addition to AFC –New addition to AFC – Applicable for Coal Stations onlyApplicable for Coal Stations only 6.6. Cost of Secondary Fuel OilCost of Secondary Fuel Oil ** 7.7. Either Compensatory Allowance for coal based stations uptoEither Compensatory Allowance for coal based stations upto 25 years of life or Special Allowance in lieu of R&M beyond25 years of life or Special Allowance in lieu of R&M beyond 25 years.25 years.** ** Included in CERC tariff regulation 2009-14Included in CERC tariff regulation 2009-14 Annual Fixed Charges
  • 35. Definition of 'Return On Equity – ROEDefinition of 'Return On Equity – ROE’(RONW)’(RONW)** The amount of net income returned as a percentage of shareholdersThe amount of net income returned as a percentage of shareholders equity. Return on equity measures a corporation’s profitability by revealingequity. Return on equity measures a corporation’s profitability by revealing how much profit a company generates with the money shareholders havehow much profit a company generates with the money shareholders have invested.invested. ROE is expressed as a percentage and calculated as:ROE is expressed as a percentage and calculated as: Return on Equity = Net Income (PBTReturn on Equity = Net Income (PBT****)/Shareholder's Equity (Rs))/Shareholder's Equity (Rs) Indirect method of taking profit through fixed cost. Every generating station has certain percentage of debt (loan) and equity i.e., 70:30 for new plant and 50:50 for existing plants, existing before 1/4/2009.(As per CERC tariff regulation 2009-14). Certain percentage of that equity (money by shareholders) will be taken as fixed cost (percentage will be decided by CERC). 1. Return on equity
  • 36.  ROE will be used for capacity addition or giving dividend to share holders or can be kept as reserve and surplus.  If equity employed is less than 30%, the actual equity and loan shall be considered for determination of return on equity.  Pre Tax Return to incentivise investment in sector.  Rate of Return will be 15.5% for existing stations (CERC Regulation 2009-14)  Reason for increase in ROE is the Prime Lending Rate (PLR) of the public sector banks have increased during this period. (March 2004 10.25% -January 2009 14.00%) Return on equity Actual equity in excess of 30% will be treated as loanActual equity in excess of 30% will be treated as loan
  • 37.  ROE will be 23.481% for the companies paying normal tax. This is given by formula: Rate of pre-tax return on equity = Base rate / (1-t) Where t is the applicable tax rate Base rate is 15.5 %. t = 33.99 % for company paying normal tax. Objective To provide fair return on the investment by the investor and for generation of internal resources for capacity additions. Return on equity
  • 40. Return on equity (CoG)(CoG)  Approval for return on equity for SSTPS for the period 2009-14 given by hearing on petition no- 225/2009 CERCtariffregulation2009-14
  • 41.  Products / services which are basic need of society, used by all sections of society irrespective of their status , infrastructure / basic amenities normally falls in this category . Prices/ tariffs are determined by the Govt. body / independent regulator . During the price determination , all the costs required to produce the product / services along with reasonable profit ( return on capital/equity ) are considered. Cost plus method is employed to avoid stranded cost of redundant assets , to insulate the consumers from vide market fluctuations, market abuse by dominant players . Examples – Electricity, Petroleum, Fertilizer, Railways etc. Price = Cost+ Profit Cost Plus Price Mechanism
  • 42.  Interest on loan is calculated based on the weighted average rate of interest and applied to the outstanding loans.  Loans are reduced to the extent of repayment each year during the tariff period.  No interest element is included in tariff after repayment of the entire loan.  To be charged from 1st year of CoD irrespective of moratorium. 2. Interest on Loan CapitalInterest on Loan Capital CERC tariff regulation 2009-14
  • 43. Depreciation is an important element of cost and forms a part of the fixed cost recovery. The objective is that the recoveries through depreciation should be adequate to provide resources to the investor to replace the assets after their useful life. Depreciable value 90% (except land). Depreciable life: Thermal - 25 years for both coal and gas station Hydro - 35 years Rates as per latest CERC notification for coal based stations 3.6% of capital cost. AAD (Advance against depreciation) is removed from CERC Regulation 2009-14,hence rate of depreciation in increasing. 3. DepreciationDepreciation CERCtariffregulation2009-14
  • 44.  Coal Based StationsCoal Based Stations  1.5 months fuel expenses for pit head and 2 months for1.5 months fuel expenses for pit head and 2 months for non pit head.non pit head.  Secondary fuel oil for 2 monthsSecondary fuel oil for 2 months  Maintenance spares @ 20% of O&MMaintenance spares @ 20% of O&M  Receivables for 2 monthsReceivables for 2 months  O&M expenses for 1 monthO&M expenses for 1 month  Cost of fuel wrt Price & GCV of preceding 3 months.Cost of fuel wrt Price & GCV of preceding 3 months.  Rate of interest will be SBI PLR as on 1.4.2009 andRate of interest will be SBI PLR as on 1.4.2009 and no fuel escalation will be permitted in workingno fuel escalation will be permitted in working capital whereas rebate will be payable at currentcapital whereas rebate will be payable at current priceprice 4. Interest on Working CapitalInterest on Working Capital CERC tariff regulation 2009-14
  • 45. For SSTPSFor SSTPS 4. Interest on Working CapitalInterest on Working Capital Petition No. 225/2009
  • 46. 5. Operation and Maintenance ExpensesOperation and Maintenance Expenses COMPONENTS OF O&M EXPENSES The Operation & Maintenance cost : Expenditure incurred on the employees including gratuity, CPF, medical, education allowances etc + Repair and maintenance expenses including stores and consumables, + Consumption of capital spares which are not a part of capital cost + Security expenses, + Administrative expenses etc. of the generating stations + Corporate expenses apportioned to each generating stations + Others (water Charge+ insurance etc)
  • 47. 5. Operation and Maintenance ExpensesOperation and Maintenance Expenses Methodology adopted by CERC while fixing O&M Norms  The actual O&M expenses of Central utilities for the years 2003-04 to 2007-08 are taken and then averaged.  Then incentive & ex-gratia paid to its employees, donations, loss in stock, prior period adjustments, claims and advances are written off.  Based on escalation rates for the year 2003-4 to 2007-08, the annual escalation rate worked out as 5.72%.  The average normalized operation and maintenance expenses at 2007-08 price level shall be escalated at the rate of 5.72% to arrive at the operation and maintenance expenses for year 2009-10
  • 48. 5. Operation and Maintenance ExpensesOperation and Maintenance Expenses  Provided that operation and maintenance expenses for the year 2009-10 shall be further rationalized considering 50% increase in employee cost on account of pay revision. As per CERC regulation 2009-14 the O&M will be: CERCtariffregulation2009- 14
  • 49. 5. Operation and Maintenance ExpensesOperation and Maintenance Expenses  In addition to the normative O&M cost the regulator has also allowed a separate compensation allowance for meeting the expenses on new capital assets, which will be based on year of completion of the project. CERC tariff regulation 2009-14
  • 50. Reasons for shifting secondary oil cost to Capacity charge  Secondary oil is required occasionally,and at a load above about 70% it is normally not required to be fired. Therefore, energy charge consisting of Coal as well as oil charges does not give real situation on merit order.  Generators are scheduled to generate as per "merit- order. 6. Cost of Secondary Fuel OilCost of Secondary Fuel Oil CERC tariff regulation 2009-14
  • 51.  Expenses on secondary fuel oil in Rupees shall be computed corresponding to normative secondary fuel oil consumption = SFC x LPSFi x NAPAF x 24 x NDY x IC x 10 Where, SFC – Normative Specific Fuel Oil consumption in ml/kWh LPSFi – Weighted Average Landed Price of Secondary Fuel in Rs./ml considered initially NAPAF – Normative Annual Plant Availability Factor in percentage NDY – Number of days in a year IC - Installed Capacity in MW. 6. Cost of Secondary Fuel OilCost of Secondary Fuel Oil CERC tariff regulation 2009-14
  • 52.  Alternatively, we may avail a ‘special allowance’ for coal based station @ Rs. 5 lakh / MW / year with annual escalation of 5.72% during 2009-14 as compensation for meeting the R&M expenses beyond the useful life. Compensatory Allowance for SSTPS 7. Special Allowance in lieu of R&M orSpecial Allowance in lieu of R&M or Compensatory AllowanceCompensatory Allowance CERCtariffregulation2009-14 Station for 08-09 for 09-10 Singrauli Nil 9.2 Rihand-I Nil 3.5 Rihand-II Nil 0 Unchahar-I Nil 1.5 Unchahar-II Nil 0 Unchahar-III Nil 0 Tanda Nil 1.5
  • 53. Annual fixed cost of claimed by the petitioner (SSTPS) for 2009-14 Petition No.189/2009 Annual Fixed Charges
  • 54. Annual fixed cost Approved by CERC for SSTPS: Petition No. 225/2009 Date of Order-7/8/2012 Annual Fixed Charges 44 paisa100 % Fixed cost at 85 % Availability
  • 55. Comparison of fixed cost from 2009-12 with 2004-09 Annual Fixed Charges www.icra.in
  • 56. Annual Fixed Charges Incentive:  Incentive will be in the form of increased AFC with respect to Availability.  Again, this incentive will be double for Old stations w.r.t. new stations. – For stations > 10 years = (AFC x NDM / NDY) x (PAFM / NAPAF) – For stations <= 10 years = (AFC x NDM / NDY) x 0.5 (1.0 + PAFM / NAPAF) Case : Singrauli  If availability is increased by 1%,then station will get extra 6.62 Cr/Yr (base is 85 %)  Or station will get extra 37.77 paisa/Unit above 85% of availability.
  • 57. Normative Annual Plant Availability Factor (NAPAF)  normative annual plant availability factor’ or ‘NAPAF’ in relation to a generating station means the availability factor.  At 85% of availability, full Fixed Charge will be recovered. If this availability increases above 85%, then Fixed charge will also increase. Annual Fixed Charges
  • 58. Computation of Energy Charge -Thermal The energy charge shall cover the primary fuel cost (Energy charge rate in Rs./kWh) x {Scheduled energy (ex-bus) for the month in kWh.} Computation of Energy charges (EC)Computation of Energy charges (EC) Energy Charge covering primary fuel cost shall be payable for totalEnergy Charge covering primary fuel cost shall be payable for total ex-bus energy scheduled to be supplied to the beneficiary duringex-bus energy scheduled to be supplied to the beneficiary during the calendar month, at the specified energy charge rate.the calendar month, at the specified energy charge rate. Energy charge rate (Energy charge rate (ECECRR) in Rs. per kWh on ex-power plant basis:) in Rs. per kWh on ex-power plant basis: For coal or lignite fired based stationsFor coal or lignite fired based stations ECR = (GHR – SFC x CVSF) x LPPF / CVPF x 100 / (100 – AUX)}ECR = (GHR – SFC x CVSF) x LPPF / CVPF x 100 / (100 – AUX)} CERC tariff regulation 2009-14
  • 59. Computation of Energy Charge -Thermal Landed Cost of CoalLanded Cost of Coal Price of coal corresponding to the grade and quality inclusivePrice of coal corresponding to the grade and quality inclusive of royalty, taxes and duties applicable & transportation cost.of royalty, taxes and duties applicable & transportation cost. Considering normative transit and handling losses :Considering normative transit and handling losses : Pit head stations : 0.2% ; Non-Pit head stations : 0.8%Pit head stations : 0.2% ; Non-Pit head stations : 0.8% CERCtariffregulation2009-14
  • 60. Computation of Energy Charge -Thermal www.icra.in Energy charges for thermal power stations are linked to the normative operational parameters as specified by the regulator Heat rate comparison of 2004-9 and 2009-14Heat rate comparison of 2004-9 and 2009-14
  • 61. Computation of Energy Charge -Thermal The Energy Charge Rate claimed by the SSTPS and approved. However, energy charge on month to month basis will be billed by the petitioner as per the 2009 Tariff Regulations. PetitionNo.225/2009
  • 62. Advantages of ABT GRID DISCIPLINE  Adherence to the schedule  Commercial incentives for operational discipline leads to better load management. Backing down under high frequency is encouraged. FACILITATES TRADING IN CAPACITY AND ENERGY MERIT ORDER OPERATION ECONOMIC GENERATION Capacity Charge and Energy Charge do not depend on actual plant generation / drawal. No metering required for this as they are based on off-line figures. All deviations taken care of by UI
  • 63.