The current issue and full text archive of this journal is available at
                                                 www.emeraldinsight.com/1463-7154.htm




BPMJ
14,2                                   ERP innovation implementation
                                        model incorporating change
                                               management
228
                                                                        M.J. Kemp and G.C. Low
                                               School of Information Systems, Technology and Management,
                                                  The University of New South Wales, Sydney, Australia

                                     Abstract
                                     Purpose – The purpose of this research is to develop and provide a preliminary validation of a model
                                     for how change management during an ERP implementation affects the effectiveness of that ERP
                                     implementation.
                                     Design/methodology/approach – This paper proposes a revised Klein et al. innovation
                                     implementation model that explicitly considers change management. The applicability of the
                                     revised model to describe the effect of change management on the implementation climate and
                                     implementation effectiveness of an ERP implementation is assessed using a case study at a large
                                     Australian multinational organisation.
                                     Findings – Specific change management activities are identified and described. Qualitative
                                     verification of a proposed ERP innovation implementation model that incorporates the effect of
                                     change management is provided.
                                     Originality/value – Change management was seen as being an important factor in influencing the
                                     effectiveness of the ERP project. This study is the first step in the longer-term empirical validation of
                                     the modified innovation implementation model.
                                     Keywords Change management, Manufacturing resource planning
                                     Paper type Research paper

                                     Introduction
                                     Many large organisations have made significant investments of both time and capital to
                                     implement ERP systems, however not all implementations go as well as intended (Bingi
                                     et al., 1999; Kumar and van Hillegersberg, 2000). Owing to the complex nature of ERP
                                     systems, many implementations have been difficult, lengthy and over budget,
                                     terminated before completion, and/or failed to achieve their business objectives even a
                                     year after implementation (Volkoff, 1999). ERP systems are organisation-wide systems
                                     and their implementation involves multiple stakeholders, often in geographically
                                     disperse locations. Therefore, an ERP system requires data standardisation, integration
                                     of the system with other information systems and management of consultants and
                                     vendors (Soh et al., 2000). Traditional project management challenges are magnified in
                                     such environments, making the implementation more difficult, expensive and
                                     failure-prone (Holland and Light, 1999). This complexity suggests that results
                                     obtained in other simpler technology implementation environments do not
Business Process Management          automatically apply to ERP environments (Markus et al., 2000). The significance of a
Journal                              new ERP system and the inherent risks in implementing such a system make it essential
Vol. 14 No. 2, 2008
pp. 228-242                          that organisations focus on ways to improve ERP implementations.
q Emerald Group Publishing Limited       Al-Mudimigh et al. (2001) suggest that, the five key critical success factors are top
1463-7154
DOI 10.1108/14637150810864952        management support, business case, change management, project management
and training. Change management is a particularly important factor in the adoption,              ERP innovation
adaptation and acceptance phases of ERP systems implementation (Somers and                       implementation
Nelson, 2004). Somers and Nelson (2004) reinforces the key role change management
has in an ERP implementation by observing that many ERP implementations fail to                          model
achieve the expected benefits possibly because companies underestimate the effort
involved in change management.
   This paper proposes an extended innovation implementation model that explicitly                               229
incorporates the impact of change management. As a first step in the longer-term
empirical validation of the modified innovation implementation model, we examine the
applicability of the model to describe how change management during an ERP
implementation affects the implementation climate and implementation effectiveness
in a major Australian Organisation.

Literature review
ERP systems are an example of an innovation – a “idea, practice, or object that is perceived
as new by an individual or other unit of adoption” (Rogers, 1995). Implementation of an
innovation is described as “the process of gaining targeted employees’ appropriate and
committed use of an innovation” (Klein and Sorra, 1996). When introducing an innovation
such as an ERP system to an organisation, the implementation process needs to be
managed so that the expected benefits are achieved. Users require ongoing support from
the organisation such as training, maintenance and equipment upgrades in order to achieve
implementation effectiveness. It has been suggested that many new systems fail due to
implementation failure, rather than innovation failure (Klein et al., 2001). The factors
leading to implementation effectiveness can be described using the model proposed by
Klein et al. (2001), Figure 1. Change management is not explicitly included in this model,
although its effect would be expected to influence implementation climate.
   For an ERP system, change management is required to prepare users for the
introduction of the new system, reduce resistance towards the system and influence
user attitudes towards that system. Approaches to managing change can be drawn
from marketing research, and from studying the implementation life cycle (Aladwani,
2001). The ERP adoption model (Aladwani, 2001) suggests that change management
and management support should positively influence system awareness, feelings
towards the system and the intention to adopt that system for users to actually adopt
the system.
   Change management initiatives for a new information system should focus on
changes specifically in the areas of technology, business process and organisation,
and culture (Benjamin and Levinson, 1993). There is a strong focus in the literature
on culture and politics as significant impediments to change (El Sawy, 1985).


     Management     Implementation
     Support        Climate
                                         Implementation     Implementation
                                                                                 Innovation
                                         Effectiveness      Effectiveness
                                         (Use)              (Use Time 2)
                                                                                 Effectiveness               Figure 1.
                                                                                                      Klein et al. (2001)
     Financial      Implementation
                                                                                                             innovation
     Resource       Policies and
     Availability   Practices                                                                     implementation model
BPMJ                          Therefore, change management should focus on creating an environment where the
14,2                          change can be implemented (Motwani et al., 2002). Suggested activities include:
                                 .
                                   project championship (Beath, 1991; Martinsons, 1993);
                                 .
                                   training (Igbaria et al., 1997);
                                 .
                                   communication of system features and benefits (Debrabander and Thiers, 1984;
230                                Markus, 1983);
                                 .
                                   communication of new business processes and organisational structure (Grover
                                   et al., 1995; Joshi, 1991); and
                                 .
                                   rewards and incentives (Allen and Kilmann, 2001; Joshi, 1991).

                              Research model
                              The Klein et al. (2001) innovation implementation model, Figure 1, does not explicitly
                              consider the impact that change management has on implementation climate. A climate
                              favourable to the implementation of a new system represents favourable user experiences
                              and attitudes towards the implementation. Therefore, by managing the change that
                              occurs during the implementation at an individual or departmental level, user attitudes
                              towards the system are more likely to be positive and the overall implementation climate is
                              more likely to be favourable. The construct of “change management” has been added to the
                              innovation implementation model to represent the effect that change management can
                              have on implementation climate. The modified model is shown in Figure 2.
                                 The implementation climate for an innovation can be described as the sum of
                              employees’ observations and experiences regarding the innovation. The Aladwani ERP
                              adoption model describes the situation where users’ awareness, feelings and intention
                              to adopt an ERP system are affected by change management and management support.
                              User awareness, feelings and intention to adopt an ERP system are equivalent to the
                              experiences and observations of users during an ERP implementation (ie. implementation
                              climate), therefore the Aladwani ERP adoption model can be considered as providing
                              a greater level of detail regarding change management and implementation climate.


                                                      Management
                                                       Support




                                        Change                 Implementation
                                       Management                 Climate



                                                                                  Implementation           Innovation
                                                                                   Effectiveness          Effectiveness


Figure 2.                               Financial              Implementation
Modified Klein et al. (2001)             Resource                 Policies &
model                                  Availability               Practices
Hence, it is possible to describe the “dotted portion” of the modified innovation          ERP innovation
implementation model shown in Figure 2 in greater detail to reflect the definitions of      implementation
change management activities and climate in the ERP adoption model. The list of change
management activities (from the ERP adoption model) has been updated to also include              model
the additional information systems change management activities discussed previously.
   Through using this model, Figure 3, the impact of change management on
implementation climate and innovation effectiveness can be investigated. Specifically,                     231
the research questions are:
  RQ1. Do the identified change management activities affect the implementation
       climate?
  RQ2. Does implementation climate (feelings awareness response, favourable
       feelings response and favourable adoption intention) impact the effectiveness
       of the ERP implementation?

Research methodology
As a first step in the longer-term empirical validation of the revised innovation
implementation model, we examine the applicability of the revised model to describe
how the change management activities during an ERP implementation affect the

                                    Management Support




       Change Management Activities                Implementation
                                                      Climate
       Communication of ERP benefits
      Communication of ERP operations
      Communicationof system features                Favourable
         Communication of changed                    Awareness
                processes                             Response




       Involvement of individuals and
                   groups                            Favourable       Implementation
          Quality of ERP interface                Feelings Response    Effectiveness
             Quality of training
           Level of adoption costs



       Opinion leader support/ project                                                                  Figure 3.
                 champion                            Favourable                          Proposed ERP innovation
          Timing/phases of ERP                        Adoption                              implementation model
              implementation                          Intention                              incorporating change
           Rewards & incentives                                                                     managenment
BPMJ   implementation climate and implementation effectiveness in a major Australian
       organisation using a structured-case based approach (Carroll and Swatman, 2000).
14,2
       Case study selection
       The case study organisation is a major Australian Multinational Organisation. The
       organisation is currently in the process of implementing an ERP system, called “ABC”
232    from one of the two major vendors. It is being implemented in conjunction with
       re-engineering of the related business processes. The system will house the HR, finance,
       payroll and procurement transactions that are carried out on a day-to-day basis in the
       organisation. The ABC system is being implemented in a series of managed releases.
          As part of its implementation process, the organisation established a change
       management team as part of the project team. The team was responsible for preparing
       the organisation for the changes that the ABC system would initiate. This identified
       the organisation and the ABC program as being an excellent research setting for
       investigating change management practices in an ERP implementation.

       Data collection
       The ABC implementation at the organisation saw a variety of change management
       activities implemented. Various departments were recipients of a range of change
       management activities according to the assessed impact that the change would have and the
       readiness of users in those departments. Various forms of data collection were employed:
           .
              Interviews. A range of interviewees was sought, representing a cross-section of
              the users of the ABC system. Interviewees were recruited from two departments,
              which were selected based on the change management activities employed in
              those departments. The operations department had little focused change
              management, while the human resources department was the recipient of
              targeted activities.
                 Five executives and three monthly paid staff were interviewed across both
              departments using a snowball sampling technique. The interviews were
              designed to be semi-structured with open-ended questions covering
              implementation effectiveness, implementation climate (awareness response,
              feelings response and adoption intention) and change management activities.
              Each interview lasted approximately half-an-hour, and was held in the
              interviewee’s office or another location nominated by the interviewee.
           .
              Review of organisational documents. Surveys, reports and other documents that
              were generated as part of the ABC implementation were reviewed. Documents
              relating to the entire change management effort were examined, with particular
              emphasis on documents relating to the two departments from which
              interviewees were selected.
           .
              Surveys. Triangulation was achieved through the collection of survey data from
              a small set of respondents in the two departments. The strength of the
              respondents’ agreement with a range of statements (Table I) was measured on a
              five-point Likert scale, ranging from 1 – strongly disagree to 5 – strongly agree.
              The statements are related to the both the system itself (content, accuracy,
              format, ease of use and timeliness) and the effects of change management
              experienced (adoption intention, feelings response, system awareness,
              management support, and change management effectiveness).
ERP innovation
                                       Operations
                                       department         HR department       All users      implementation
                                     Median    Range     Median    Range   Median    Range           model
Content                                4.0       2-4      3.0       3-4     4.0       3-4
Accuracy                               4.0       2-4      3.0       2-4     4.0       2-4
Format                                 4.0       3-4      3.5       2-4     4.0       2-4                  233
Ease of use                            4.0       2-5      3.0       1-4     4.0       1-5
Timeliness                             4.0       4        4.0       1-4     4.0       1-4
Adoption intention                     4.0       3-4      4.0       1-5     4.0       1-5
System awareness                       4.0       2-4      3.5       2-4     4.0       2-5
Communicators                          n/a       n/a      3.0       2-5     3.0       2-5
Communications                         4.0       3-4      3.5       2-4     4.0       2-4
Traininga                              4.0       4        4.0       4       4.0       4
Feelings response                      3.0       2-4      4.0       1-5     4.0       1-5
User involvement                       3.0       3-4      4.0       4-5     3.5       3-5
Management support                     4.0       4-5      4.0       4-5     4.0       4-5
Change management effectiveness        3.0       2-4      3.5       1-4     3.0       1-4
                                                                                                          Table I.
Note: aOnly applicable for users who attended training                                       User survey responses


Analysis techniques
All interviews were transcribed and these transcriptions were analysed using a three
stage coding process: open coding, axial coding and selective coding (Strauss and
Corbin, 1997). The purpose of coding is two-fold: to look for patterns among the data
and to look for patterns that give meaning to the case study (Merriam, 1985).
   The open coding stage involved an exploration of the data to generate initial codes.
However, the concepts in a conceptual framework can be used as initial codes in
guiding the analysis provided this does not prevent the identification of other codes to
incorporate new themes (Carroll and Swatman, 2000; Neuman, 2003). Hence, the model
for planned change (Kolb and Frohman, 1970) was utilised to provide a framework for
identifying initial change management codes.
   The second axial coding stage involved the analysis of codes developed in open
coding for recurring themes or overlapping central categories. Selective coding involved
scanning existing codes for cases that illustrate themes within the case study. Major
themes or concepts were used to guide the search. In particular, multiple instances of
empirical evidence were sought from the interviews, review of organisational
documents and the surveys in order to strengthen and validate findings from the study.

Case study
Release 1 of the ERP system, comprising payroll functionality, was rolled out in
September 2003 for monthly paid and executive staff (representing approximately 1,200
users). Release 2 went live in October 2004 and consisted of HR self-service functions for
managers and other employees. The Release 2 user base represents a much larger
number of users. Five further releases are planned covering performance management,
customer service, finance, purchasing and procurement, and portal implementation.
   Prior to the implementation of the ABC system, each department was responsible
for maintaining its own payroll and HR system, leading to duplication of the types
of data stored and staff roles in each department. To alleviate these problems,
BPMJ   a “shared services” approach to service provision was adopted, where a single point of
14,2   contact for all business services was established. A large number of existing HR and
       payroll staff were moved to a new shared services department, where use of the ABC
       system has replaced or connects to the departmental HR and payroll systems. Business
       services are provided by shared services to all departments at agreed service levels and
       at agreed costs. A new call centre handles questions regarding the ABC system and
234    other HR and payroll queries.
          The new “shared services” approach was implemented at the same time as Release 1
       of the ABC system, however there was not a great deal of system functionality
       available at that time. In order to take advantage of the new structure, interim
       processes using forms and direct contact with shared services were implemented.
       These interim processes mirrored the processes that would exist when Release 2 was
       released, but required more manual processing. When Release 2 of the system arrived,
       the processes were again updated to reflect the availability of system functionality.

       Implementation team
       Staffs from three major organisations are responsible for implementing the ABC
       system. Organisation staff with relevant experience and skills have been seconded to
       the project, for varying amounts of time as required. The hardware infrastructure and
       web hosting services are being provided by an outsourcing vendor while a consulting
       organisation is leading the implementation activities and managing the change of
       business processes. The ERP vendor is carrying out any required changes to the basic
       ERP software purchased.

       Change management team
       The change management team was formed from key staff from the organisation and
       the consulting organisation which had experience in managing change associated with
       changes in processes. The team was formed shortly after the beginning of the ABC
       program.

       Change management
       The change management team performed a number of tasks to diagnose, plan, deliver
       and evaluate the change management activities required for the ABC implementation.

       Implementation climate assessment
       Before implementation commenced, the change management team made an assessment
       of the implementation climate. This involved assessing the impact of the system on
       business processes, assessing the gap between current and required capabilities and
       preparing a change management readiness assessment. The implementation climate
       assessment helped to identify areas of the business that would require specific and
       targeted change management activities.

       Scoping and planning
       The information gathered during the implementation climate assessment was used to
       create a transition plan describing how to move from the current implementation
       climate to the users having the required skills and knowledge to operate the ABC
       system successfully. The people transition plan provided a roadmap for individuals
impacted by the change initiatives. The plan outlined the strategy, timing and          ERP innovation
execution plan for the transition of staff. Change management activities were planned   implementation
as a result of the people transition plan, and were detailed in separate documents
(eg. training plan).                                                                            model
   Planning was also required for the communications that would be necessary as a
result of the ABC program. The communication plan detailed the stakeholders, key
messages and timing of communications to user groups. Key messages included                       235
system features, benefits of using the system, progress of development and impact of
changed processes.

Change management delivery
A range of change management activities was performed during the implementation of
the ABC system. Most of the change management activities were targeted at specific
groups of users, rather than being intended for all users of the system. Strategies
included:
   .
      Communicating information on system features, system benefits and changed
      processes using various options including organisation newsletters, ABC system
      “open days” conference room pilots of the system, and departmental briefings.
   .
      Implementing a project championship program. The change management team,
      with assistance from the organisation general managers and HR staff, selected
      change agents from functional areas to be impacted by the ABC system. These
      change agents, known as “Communicators” were the primary communication
      channel in support of the ABC system implementation. The role and function of
      communicators were detailed in the communication plan.
   .
      Training users across the organisation, focusing on the departments where
      change would be greatest. A range of training was implemented, from online
      courses to intensive classroom-based training days. Training was mandatory
      and face-to-face for users with “high” or “medium” capability gap assessments,
      and online and optional for all other users.
   .
      Involving affected users in all aspects of the change process.
   .
      Adopting a phased implementation to help minimise resistance to the changes.

Benefits analysis
During the scoping and planning phase of the ABC system, a program wide benefits
baseline was prepared which included all potential business benefits arising from the
ABC system. A primary tool in the realisation of business benefits for each release is
the benefit action plan. It defines the required states for four key project factors:
process, people, organisation and technology.

Discussion
Some change management activities suggested in the revised ERP innovation
implementation model (Figure 3) were not considered by the change management team
during the ABC implementation. These were quality of ERP interface, level of adoption
cost, and rewards and incentives. In this case, a standard application was purchased
with minimal customization thus largely removing the ability to customize the
interface.
BPMJ       The effectiveness of the implementation is discussed, from the perspective of the users
14,2   of the ERP system. Analysis of effects of the change management on the implementation
       climate was completed through interviews with organisation staffs from two
       departments. The operations department was identified as an area that required little
       change management before the introduction of the ABC system, while the HR department
       required intensive change management to prepare for the release of the system.
236
       Effect of change management on implementation climate
       The effect of change management on implementation climate will be assessed using
       the three aspects of implementation climate (system awareness, feelings response and
       adoption intention) proposed in the research model (Figure 3).
          System awareness. A high level of system awareness was achieved during the ERP
       implementation. When questioned, users were able to explain the features of the
       system in considerable detail, and were able to recall a large number of the benefits of
       using the system mentioned by the change management team before the release of the
       system. This finding was confirmed by the survey data (Table I).
          System awareness was primarily achieved through communications. The users
       gave this a relatively high-median score of 4.0, Table I. This suggests that, the
       communications aspect of the ABC program was well managed.
          Differences were seen in the ability of users to discuss the changes that were made
       to the processes as a result of the system implementation. HR staff were much more
       able to describe the changes that had occurred throughout the department. For
       example, HR staff were able to fully describe the role of the new shared services
       department and the way in which processes relating to management of information
       had changed. Operations department staff described Shared Services as “a transaction
       processing centre” and “where you go when you need help”. While these descriptions
       are accurate, they are certainly not a complete explanation of the role of shared
       services in the ABC system implementation. This suggests that, the role of Shared
       Services was not fully communicated to all users before the release of the system. Some
       of the differences in the ability to explain process change may lie in the fact that HR
       staff are much closer to the processes that have changed, as they use the system on a
       daily basis. However, operations department staff should be able to explain the role of
       shared services more comprehensively than they did, as executives within the
       operations department are responsible for managing both their own and their
       employees’ HR data, and the interim processes between Release 1 and 2 required direct
       contact with shared services. A failure to understand the role of shared services
       impacts on the ability of users to know where to get help if required, and may therefore
       affect the feelings of users towards the system. This then has an effect on the feelings
       response of users towards the system.
          Feelings response. Feelings towards the system should be impacted by user
       involvement and user training. For staff that did not have a particular role in the
       development of the system, regular briefings and communications helped them feel
       informed about the progress of development. The HR department was the recipient of
       targeted change management activities while the operations department had little
       focused change management. This difference was reflected in the higher median score
       for user involvement for the HR group (4.0) compared with the operations department
       group (3.0). It is also reflected in the ratings of feelings response, Table I.
Discussion with users regarding training showed that the feelings of those users               ERP innovation
who believed the training was excessive or inadequate were less positive towards the
system than the feelings of the users who believed that the training was adequate.
                                                                                                  implementation
Those who attended training scored a much higher median score for the feelings                            model
response questions (a median score of 4.25 for those who attended training, compared
with 3.0 for those who did not). This suggests that training assists in improving the
feelings response of users, and thus improves the adoption intention.                                       237
   Adoption intention. Although users could easily identify problems and frustrations
with the system, general resistance to the system amongst users was low. Most
believed that the system was necessary and would not attempt to delay progress. All
users had been keen to have a look at what was actually in the system after hearing
about it for many months before its release. The high level of adoption intention
expressed in the interviews is confirmed by its relatively high-median score of 4.0 in
the survey results. Adoption intention was improved through change management
activities such as project championship and phased ERP implementation.
   Users in both departments supported the idea of a phased implementation.
However, the downside of a phased implementation was that if one release is delayed,
the completion dates for future releases are also delayed. Release 2 of the system was
released seven months after its intended release date. As change management needs to
occur prior to the release of the system, the change management team implemented the
change activities far earlier than required. Communications were then required to
reassure staff members that the system was still being implemented, and would be
released when it was ready. One user commented:
   They kept sending messages saying that the system was still coming. But no amount of
   communication is going to change the fact that the system isn’t here yet. It made the system
   team seem really incompetent.
Discussion with users regarding the project showed that the late release of Release 2
was the main reason for any user resistance towards the ABC system.

Effect of management support on implementation climate
Interviewees commented that there was an attitude of overall support from the
organisation, and that their manager was in support of the system prior to its release.
This indicates that, the organisation as a whole was publicly very supportive of
the system and was able to show encouragement through the provision of resources.
Some managers spoke of showing supportiveness of the system when dealing with
their own staff, even if they were personally somewhat sceptical of the benefits
claimed. The high level of management support was confirmed by survey data relating
to the attitude of managers towards the project. All users surveyed responded with
“Agree” or “Strongly Agree” when asked about the level of support for the project from
both managers and the organisation as a whole, Table I.

Implementation effectiveness
The feelings of all interviewed users towards the system prior to its release were
positive. All interviewees indicated that, they logged into the system when it was
released just to see what was available.
   All change management activities mentioned in planning documents prepared by
the change management team were implemented prior to the system being released.
BPMJ   The climate prior to its release was one expectant of better results than what were
14,2   being achieved with the legacy systems. HR staff were satisfied on the whole with the
       way the change in their department was managed. However, operations department
       staff were neutral. Staff were not overly interested in the system and the benefits using
       the system can bring. Some users claimed that they are unaware of how to use the
       system or when usage of the system is required. This suggests that, the capability gap
238    assessment for the operations department may have been incorrect and more formal
       user training was required. Their necessary capabilities required were rated at a low
       level and their current skills were seen as adequate, which did not necessitate a formal
       change management process in this department.

       Conclusions
       This study identified the major activities used in an ERP implementation through a case
       study of the ABC program in the case study organisation. It has shown that change
       management is an important factor in an ERP implementation. The implementation of
       the ABC system followed the research model shown in Figure 3. The change
       management activities affected the implementation climate. In turn, the implementation
       climate affected the effectiveness of the implementation.
          The change management activities had the required effect on the climate for
       implementation. The activities implemented assisted in informing users about the
       system, and enabling the provision of skills required when the system was implemented.
       There were noticeable differences between users who had participated in change
       management activities either through optional involvement or the provision of extra
       change management activities in some departments and those who did not participate.
          Some aspects of the change management program could have been better managed.
       Managers tended to publicly support the implementation of the ABC system, but
       privately believed that the system would not be of much benefit. A theme often
       discussed in interviews was the fact that often users did not understand why the
       organisation had undertaken the ABC implementation and did not believe that it was
       necessary. Many wondered why a system that cost so much was being implemented
       when it was not providing any greater functionality, and at times was less efficient
       than legacy systems. This suggests that managers should be informed of the
       motivation for implementing the ERP system, rather than just being informed of
       benefits and be expected to advocate the system within their departments. It also
       suggests that the change management activity, “level of adoption cost” should be
       specifically addressed as part of the change management process.
          There are indications that the users’ expectations for the system were different to
       the actual features of the implemented system. Some users gave a very low score for
       the survey question relating to whether the features of the system were as expected.
       This indicates that although users were aware of the system and its benefits, the actual
       system did not have the features expected by users. This could be a result of the
       change management team overstating the benefits, or not explaining them clearly, or
       the users misunderstanding what they were being told.
          This suggests that communications about the system must be very clear and match
       with what the system actually offers. The users were disappointed and resistance
       towards the system increased when it was different to what they expected. It would
       have been beneficial for more users to see the system for themselves prior to its release
in order to accurately gauge the functionality offered. However, the ABC system may          ERP innovation
be different to other ERP implementations in that the change management team must            implementation
also provide details on modules to be released in future phases. Users may expect to see
a module in the next phase, when in reality it may not be implemented for a number of                model
years. If the implementation is a phased implementation, care should be taken to
accurately inform users of when each feature will be released.
   The implemented change management activities also affected different areas of                       239
the organisation in different ways. Each department within the organisation
received a very different range of change management activities based on the
identified needs, and it is evident that the range and types of change management
received impact upon the effectiveness of the ERP implementation. When assessing
the need for change management in each department, the change management team
implemented activities that they believed would provide the best implementation
climate for the most realistic amount of work. At the end of the change
management process, the change management team expected that the
implementation climate across the organisation would be similar. In reality,
the implementation climate differed throughout the organisation. The general
attitude to the system by those in the department that received less change
management was less positive than for those who were the recipients of more
targeted activities. This indicates that change management is required throughout
an organisation implementing an ERP system, even if the changes in one particular
area of the organisation are not particularly great.
   Despite the problems identified by users after the release of the system, the change
management activities have been successful. Users who were sceptical when hearing
about the project are now generally well equipped to use the system. This indicates
that ERP implementations similar to the ABC system would benefit from similar types
of change management activities.
   The effect of change management and management support on implementation
climate are supported by the case study. In addition there is support for the impact of
implementation climate on implementation effectiveness. However, there may be other
factors that determine implementation effectiveness. Although users may be able to
use the system as intended, they are not always able to use it well. Interviews with HR
staff showed that some aspects of the system such as speed of the system and quality
of interface design prevent the staff from using the system to its full potential. This
suggests that more implementation climate is not the only factor in determining
implementation effectiveness, and that features of the system itself do play a part in the
success of an ERP implementation.

Further research
This research is a first step in the longer-term empirical validation of the revised
innovation implementation model, Figure 2. This model will be extended to incorporate
the effect of system features (technology fit) on implementation effectiveness based on
the research findings.
   The empirical validation of the expanded model is planned using survey data
obtained from users involved in ERP implementations in various organisations.
Structural equation modeling, using partial least squares, will be used to test the
overall fit of the structural model. The research constructs will be derived from
BPMJ   the Klein et al. (2001) and Aladwani (2001) models. Since most users will have little
14,2   understanding of the financial resource availability this construct (and its associated
       hypotheses) will be omitted from the analysis.
          The accompanying research hypotheses are described below:
          H1. Implementation climate is positively correlated with implementation
              effectiveness.
240
          H1.1 Favourable awareness response is positively correlated with implementation
               effectiveness.
          H1.2 Favourable feelings response is positively correlated with implementation
               effectiveness.
          H1.3 Favourable adoption intention is positively correlated with implementation
               effectiveness.
          H2. Change management is positively correlated with the implementation climate.
          H2.1 Change management activities (communications issues) are positively
               correlated with favourable awareness response.
          H2.2 Change management activities (involvement of individuals and groups,
               and quality of training) are positively correlated with favourable feelings
               response
          H2.3 Change management activities (project champion support, and timing/phases
               of ERP implementation) are positively correlated with favourable adoption
               intention.
          H3. Management support is a moderating variable between change management
              and the implementation climate.
          H4. Technology fit is positively correlated with implementation effectiveness.
          H5. Implementation policies and practices are positively correlated with
              implementation effectiveness.


       References
       Aladwani, A.M. (2001), “Change management strategies for successful ERP implementation”,
             Business Process Management Journal, Vol. 7 No. 3, pp. 266-75.
       Allen, R.S. and Kilmann, R.H. (2001), “The role of the reward system for a total
             quality management based strategy”, Journal of Organizational Change, Vol. 14 No. 2,
             pp. 110-31.
       Al-Mudimigh, A., Zairi, M. and Al-Mashari, M. (2001), “ERP software implementation:
             an interactive framework”, European Journal of Information Systems, Vol. 10,
             pp. 216-26.
       Beath, C. (1991), “Supporting the information technology champion”, MIS Quarterly, Vol. 15
             No. 3, pp. 355-72.
       Benjamin, R. and Levinson, E. (1993), “A strategic framework for managing IT-enabled change”,
             Sloan Management Review, Vol. 34 No. 4, pp. 23-34.
Bingi, P., Sharma, M.K. and Godla, J. (1999), “Critical issues affecting an ERP implementation”,       ERP innovation
       Information Systems Management, Vol. 16 No. 3, pp. 7-14.
                                                                                                       implementation
Carroll, J.M. and Swatman, P.A. (2000), “Structured-case: a methodological framework for
       building theory in information systems research”, European Journal of Information                       model
       Systems, Vol. 9 No. 4, pp. 235-42.
Debrabander, B. and Thiers, G. (1984), “Successful information system development in relation to
       situational factors which affect effective communication between MIS users and EDP                        241
       specialists”, Management Science, Vol. 30 No. 2, pp. 137-55.
El Sawy, O.A. (1985), “Implementation by cultural infusion: an approach for managing the
       introduction of information technologies”, MIS Quarterly, Vol. 9 No. 2, pp. 131-40.
Grover, V., Jeong, S.R., Kettinger, W. and Teng, J. (1995), “The implementation of business
       process reengineering”, Journal of Management Information Systems, Vol. 12 No. 1,
       pp. 109-44.
Holland, C.P. and Light, B. (1999), “A critical success factors model for ERP implementation”,
       IEEE Software, May/June, pp. 30-6.
Igbaria, M., Zinatelli, N., Cragg, P. and Cavaye, A.M. (1997), “Personal computing acceptance
       factors in small firms: a structural equation model”, MIS Quarterly, Vol. 21 No. 3,
       pp. 279-305.
Joshi, K. (1991), “A model of users’ perspective on change: the case of information systems
       technology implementation”, MIS Quarterly, Vol. 15 No. 3, pp. 229-42.
Klein, K. and Sorra, J.S. (1996), “The challenge of innovation implementation”, The Academy of
       Management Review, Vol. 21 No. 4, p. 1055.
Klein, K., Conn, A. and Sorra, J.S. (2001), “Implementing computerized technology:
       an organizational analysis”, Journal of Applied Psychology, Vol. 86 No. 5, pp. 811-24.
Kolb, D.A. and Frohman, A.L. (1970), “An organization development approach to consulting”,
       Sloan Management Review, Vol. 12 No. 1, pp. 51-65.
Kumar, K. and van Hillegersberg, J. (2000), “ERP experience and evolution”, Communications of
       the ACM, Vol. 43 No. 4, pp. 23-6.
Markus, M.L. (1983), “Power, politics, and MIS implementation”, Communications of the ACM,
       Vol. 26, pp. 430-44.
Markus, M.L., Axline, S., Petrie, D. and Tanis, C. (2000), “Learning from adopters’ experiences
       with ERP: problems encountered and success achieved”, Journal of Information
       Technology, Vol. 15 No. 4, pp. 245-65.
Martinsons, M.G. (1993), “Cultivating the champions for strategic information systems”,
       Journal of Systems Management, Vol. 44 No. 8, pp. 31-4.
Merriam, S. (1985), “The case study in educational research: a review of selected literature”,
       The Journal of Educational Thought, Vol. 19 No. 3, pp. 204-17.
Motwani, J., Mirchandani, D., Madan, M. and Gunasekaran, A. (2002), “Successful
       implementation of ERP projects: evidence from two case studies”, International Journal
       of Production Economics, Vol. 75 Nos 1/2, p. 83.
Neuman, W.L. (2003), Social Research Methods – Qualitative and Quantitative Approaches,
       Allyn and Bacon, Boston, MA.
Rogers, E.M. (1995), Diffusion of Innovations, The Free Press, New York, NY.
Soh, C., Kien, S.S. and Tay-Yap, J. (2000), “Cultural fits and misfits: is ERP a universal solution?”,
       Communications of the ACM, Vol. 43 No. 4, pp. 47-51.
BPMJ   Somers, T.M. and Nelson, K.G. (2004), “A taxonomy of players and activities across
             the ERP project life cycle”, Information & Management, Vol. 41 No. 3, pp. 257-78.
14,2   Strauss, A. and Corbin, J. (1997), Grounded Theory in Practice, Sage, London.
       Volkoff, O. (1999), “Using the structural model of technology to analyze an ERP implementation”,
             AMCIS, Milwaukee, August 13-15, pp. 235-7.

242    Corresponding author
       G.C. Low can be contacted at: g.low@unsw.edu.au




       To purchase reprints of this article please e-mail: reprints@emeraldinsight.com
       Or visit our web site for further details: www.emeraldinsight.com/reprints

Más contenido relacionado

La actualidad más candente

CMMI - High Maturity Misconceptions and Pitfalls
CMMI - High Maturity Misconceptions and PitfallsCMMI - High Maturity Misconceptions and Pitfalls
CMMI - High Maturity Misconceptions and PitfallsRajesh Naik
 
Enterprise transformation - What is transformed?
Enterprise transformation - What is transformed?Enterprise transformation - What is transformed?
Enterprise transformation - What is transformed?Frederick Halas
 
Ii 1 Iess1 0 2010
Ii 1 Iess1 0 2010Ii 1 Iess1 0 2010
Ii 1 Iess1 0 2010IESS
 
Performance improvement methodology
Performance improvement methodologyPerformance improvement methodology
Performance improvement methodologyMaher Salam
 
The Mathematics Behind Project Management
The Mathematics Behind Project ManagementThe Mathematics Behind Project Management
The Mathematics Behind Project Managementsystred
 
Overview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementOverview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementNelson Piedra
 
Accu2010 archrefactoring
Accu2010 archrefactoringAccu2010 archrefactoring
Accu2010 archrefactoringMichael Stal
 
5.a systematic
5.a systematic5.a systematic
5.a systematiclibfsb
 
Pbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentationPbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentationMichaelMcNamara
 
Service Support Quick Reference
Service Support Quick ReferenceService Support Quick Reference
Service Support Quick Referenceguest5f36a4
 
Policy Design @ HSREPP 2010 Conference the Hague
Policy Design @ HSREPP 2010 Conference the HaguePolicy Design @ HSREPP 2010 Conference the Hague
Policy Design @ HSREPP 2010 Conference the HagueMaria Kapsali
 
Mathematical concepts applied to operations management
Mathematical concepts applied to operations managementMathematical concepts applied to operations management
Mathematical concepts applied to operations managementRakesh Kariholoo
 
intro to maint management systems
intro to maint management systemsintro to maint management systems
intro to maint management systemsBill Sheppard
 
Power Distribution Asset Management 2012
Power Distribution Asset Management 2012Power Distribution Asset Management 2012
Power Distribution Asset Management 2012Ola Odejayi
 
Simulating a PhD: My journey and future research directions
Simulating a PhD: My journey and future research directionsSimulating a PhD: My journey and future research directions
Simulating a PhD: My journey and future research directionsmilesweaver
 
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...QAI
 

La actualidad más candente (18)

CMMI - High Maturity Misconceptions and Pitfalls
CMMI - High Maturity Misconceptions and PitfallsCMMI - High Maturity Misconceptions and Pitfalls
CMMI - High Maturity Misconceptions and Pitfalls
 
Enterprise transformation - What is transformed?
Enterprise transformation - What is transformed?Enterprise transformation - What is transformed?
Enterprise transformation - What is transformed?
 
Ii 1 Iess1 0 2010
Ii 1 Iess1 0 2010Ii 1 Iess1 0 2010
Ii 1 Iess1 0 2010
 
Performance improvement methodology
Performance improvement methodologyPerformance improvement methodology
Performance improvement methodology
 
The Mathematics Behind Project Management
The Mathematics Behind Project ManagementThe Mathematics Behind Project Management
The Mathematics Behind Project Management
 
Overview of CMMI and Software Process Improvement
Overview of CMMI and Software Process ImprovementOverview of CMMI and Software Process Improvement
Overview of CMMI and Software Process Improvement
 
Accu2010 archrefactoring
Accu2010 archrefactoringAccu2010 archrefactoring
Accu2010 archrefactoring
 
5.a systematic
5.a systematic5.a systematic
5.a systematic
 
Pbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentationPbi Marcus Evans Sept2011presentation
Pbi Marcus Evans Sept2011presentation
 
Service Support Quick Reference
Service Support Quick ReferenceService Support Quick Reference
Service Support Quick Reference
 
Policy Design @ HSREPP 2010 Conference the Hague
Policy Design @ HSREPP 2010 Conference the HaguePolicy Design @ HSREPP 2010 Conference the Hague
Policy Design @ HSREPP 2010 Conference the Hague
 
Mathematical concepts applied to operations management
Mathematical concepts applied to operations managementMathematical concepts applied to operations management
Mathematical concepts applied to operations management
 
intro to maint management systems
intro to maint management systemsintro to maint management systems
intro to maint management systems
 
Power Distribution Asset Management 2012
Power Distribution Asset Management 2012Power Distribution Asset Management 2012
Power Distribution Asset Management 2012
 
BPM enabled e-governance
BPM enabled e-governanceBPM enabled e-governance
BPM enabled e-governance
 
Simulating a PhD: My journey and future research directions
Simulating a PhD: My journey and future research directionsSimulating a PhD: My journey and future research directions
Simulating a PhD: My journey and future research directions
 
Track 4 Dale Uitto 2015 Paper
Track 4 Dale Uitto 2015 PaperTrack 4 Dale Uitto 2015 Paper
Track 4 Dale Uitto 2015 Paper
 
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
CMMI High Maturity Best Practices HMBP 2010: Deploying High Maturity Practice...
 

Similar a ERP Innovation Implementation Model Incorporating Change Management

5.an integrated
5.an integrated5.an integrated
5.an integratedlibfsb
 
A New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business ChangeA New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business ChangeJulie Davis
 
8. Erp Managing The Implementation Process
8. Erp   Managing The Implementation Process8. Erp   Managing The Implementation Process
8. Erp Managing The Implementation ProcessDonovan Mulder
 
Abb case study 1
Abb case study 1Abb case study 1
Abb case study 1apn18
 
Group 5 change management presentation
Group 5   change management presentationGroup 5   change management presentation
Group 5 change management presentationMatlosa
 
CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...
CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...
CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...ijait
 
Erp research agenda(imds)
Erp research agenda(imds)Erp research agenda(imds)
Erp research agenda(imds)012roger
 
Succeeding with Transformational Initiatives: Practical Approaches for Managi...
Succeeding with Transformational Initiatives: Practical Approaches for Managi...Succeeding with Transformational Initiatives: Practical Approaches for Managi...
Succeeding with Transformational Initiatives: Practical Approaches for Managi...Arab Federation for Digital Economy
 
The Hidden Financial Costs Of Erp Software
The Hidden Financial Costs Of Erp SoftwareThe Hidden Financial Costs Of Erp Software
The Hidden Financial Costs Of Erp SoftwareDonovan Mulder
 
Pre assessment model for erp implementation
Pre assessment model for erp implementationPre assessment model for erp implementation
Pre assessment model for erp implementationIAEME Publication
 
Pre assessment model for erp implementation
Pre assessment model for erp implementationPre assessment model for erp implementation
Pre assessment model for erp implementationIAEME Publication
 
Research evolution on implementation and adoption behaviour of information sy...
Research evolution on implementation and adoption behaviour of information sy...Research evolution on implementation and adoption behaviour of information sy...
Research evolution on implementation and adoption behaviour of information sy...LenaFrau
 
Correlation Between Proper Training / Involvement and ERP Acceptance and the ...
Correlation Between Proper Training / Involvement and ERP Acceptance and the ...Correlation Between Proper Training / Involvement and ERP Acceptance and the ...
Correlation Between Proper Training / Involvement and ERP Acceptance and the ...Dr. Kerem Koseoglu
 
Adopting integrated application lifecycle management within a large-scale sof...
Adopting integrated application lifecycle management within a large-scale sof...Adopting integrated application lifecycle management within a large-scale sof...
Adopting integrated application lifecycle management within a large-scale sof...mustafa sarac
 
14. Business Process Approach Towards An Inter Organizational Enterprise System
14. Business Process Approach Towards An Inter Organizational Enterprise System14. Business Process Approach Towards An Inter Organizational Enterprise System
14. Business Process Approach Towards An Inter Organizational Enterprise SystemDonovan Mulder
 
An Approach of Improve Efficiencies through DevOps Adoption
An Approach of Improve Efficiencies through DevOps AdoptionAn Approach of Improve Efficiencies through DevOps Adoption
An Approach of Improve Efficiencies through DevOps AdoptionIRJET Journal
 

Similar a ERP Innovation Implementation Model Incorporating Change Management (20)

10.1.1.87.8236
10.1.1.87.823610.1.1.87.8236
10.1.1.87.8236
 
5.an integrated
5.an integrated5.an integrated
5.an integrated
 
A New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business ChangeA New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business Change
 
TOC's role in IT success
TOC's role in IT successTOC's role in IT success
TOC's role in IT success
 
8. Erp Managing The Implementation Process
8. Erp   Managing The Implementation Process8. Erp   Managing The Implementation Process
8. Erp Managing The Implementation Process
 
Abb case study 1
Abb case study 1Abb case study 1
Abb case study 1
 
Group 5 change management presentation
Group 5   change management presentationGroup 5   change management presentation
Group 5 change management presentation
 
CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...
CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...
CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE I...
 
1.doc
1.doc1.doc
1.doc
 
Erp research agenda(imds)
Erp research agenda(imds)Erp research agenda(imds)
Erp research agenda(imds)
 
amaratunga2003.pdf
amaratunga2003.pdfamaratunga2003.pdf
amaratunga2003.pdf
 
Succeeding with Transformational Initiatives: Practical Approaches for Managi...
Succeeding with Transformational Initiatives: Practical Approaches for Managi...Succeeding with Transformational Initiatives: Practical Approaches for Managi...
Succeeding with Transformational Initiatives: Practical Approaches for Managi...
 
The Hidden Financial Costs Of Erp Software
The Hidden Financial Costs Of Erp SoftwareThe Hidden Financial Costs Of Erp Software
The Hidden Financial Costs Of Erp Software
 
Pre assessment model for erp implementation
Pre assessment model for erp implementationPre assessment model for erp implementation
Pre assessment model for erp implementation
 
Pre assessment model for erp implementation
Pre assessment model for erp implementationPre assessment model for erp implementation
Pre assessment model for erp implementation
 
Research evolution on implementation and adoption behaviour of information sy...
Research evolution on implementation and adoption behaviour of information sy...Research evolution on implementation and adoption behaviour of information sy...
Research evolution on implementation and adoption behaviour of information sy...
 
Correlation Between Proper Training / Involvement and ERP Acceptance and the ...
Correlation Between Proper Training / Involvement and ERP Acceptance and the ...Correlation Between Proper Training / Involvement and ERP Acceptance and the ...
Correlation Between Proper Training / Involvement and ERP Acceptance and the ...
 
Adopting integrated application lifecycle management within a large-scale sof...
Adopting integrated application lifecycle management within a large-scale sof...Adopting integrated application lifecycle management within a large-scale sof...
Adopting integrated application lifecycle management within a large-scale sof...
 
14. Business Process Approach Towards An Inter Organizational Enterprise System
14. Business Process Approach Towards An Inter Organizational Enterprise System14. Business Process Approach Towards An Inter Organizational Enterprise System
14. Business Process Approach Towards An Inter Organizational Enterprise System
 
An Approach of Improve Efficiencies through DevOps Adoption
An Approach of Improve Efficiencies through DevOps AdoptionAn Approach of Improve Efficiencies through DevOps Adoption
An Approach of Improve Efficiencies through DevOps Adoption
 

Más de Donovan Mulder

Towards A Model Of Organisational Prerequistes For Enterprise Wide Sys Integ
Towards A Model Of Organisational Prerequistes For Enterprise Wide Sys IntegTowards A Model Of Organisational Prerequistes For Enterprise Wide Sys Integ
Towards A Model Of Organisational Prerequistes For Enterprise Wide Sys IntegDonovan Mulder
 
The Royalty Of Loyalty Crm, Quality And Retention
The Royalty Of Loyalty Crm, Quality And RetentionThe Royalty Of Loyalty Crm, Quality And Retention
The Royalty Of Loyalty Crm, Quality And RetentionDonovan Mulder
 
The Critical Success Factors For Erp Implementation An Organisational Fit Per...
The Critical Success Factors For Erp Implementation An Organisational Fit Per...The Critical Success Factors For Erp Implementation An Organisational Fit Per...
The Critical Success Factors For Erp Implementation An Organisational Fit Per...Donovan Mulder
 
Realising Enhanced Value Due To Business Network Redesign Through Extended Er...
Realising Enhanced Value Due To Business Network Redesign Through Extended Er...Realising Enhanced Value Due To Business Network Redesign Through Extended Er...
Realising Enhanced Value Due To Business Network Redesign Through Extended Er...Donovan Mulder
 
Managing Dirty Data In Organization Using Erp
Managing Dirty Data In Organization Using ErpManaging Dirty Data In Organization Using Erp
Managing Dirty Data In Organization Using ErpDonovan Mulder
 
Implementing Erp Systems In Small And Midsize Manufacturing Firms
Implementing Erp Systems In Small And Midsize Manufacturing FirmsImplementing Erp Systems In Small And Midsize Manufacturing Firms
Implementing Erp Systems In Small And Midsize Manufacturing FirmsDonovan Mulder
 
16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems
16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems
16. Erp Ii A Conceptual Framework For Next Generation Enterprise SystemsDonovan Mulder
 
15. Assessing Risk In Erp Projects Identify And Prioritize The Factors
15. Assessing Risk In Erp Projects Identify And Prioritize The Factors15. Assessing Risk In Erp Projects Identify And Prioritize The Factors
15. Assessing Risk In Erp Projects Identify And Prioritize The FactorsDonovan Mulder
 
13. Effectiveness Of Erp Systems
13. Effectiveness Of Erp Systems13. Effectiveness Of Erp Systems
13. Effectiveness Of Erp SystemsDonovan Mulder
 
10. What Managers Should Know About Erp Erpii
10. What Managers Should Know About Erp Erpii10. What Managers Should Know About Erp Erpii
10. What Managers Should Know About Erp ErpiiDonovan Mulder
 
12. Managing Risk Factors In Erp Implementation And Design
12. Managing Risk Factors In Erp Implementation And Design12. Managing Risk Factors In Erp Implementation And Design
12. Managing Risk Factors In Erp Implementation And DesignDonovan Mulder
 
11. Requirements Of An Erp Enterprise Erp Modeller
11. Requirements Of An Erp Enterprise Erp Modeller11. Requirements Of An Erp Enterprise Erp Modeller
11. Requirements Of An Erp Enterprise Erp ModellerDonovan Mulder
 
9. Factors Affecting Erp System Adoption
9. Factors Affecting Erp System Adoption9. Factors Affecting Erp System Adoption
9. Factors Affecting Erp System AdoptionDonovan Mulder
 
7. A Conceptual Model For Erp
7. A Conceptual Model For Erp7. A Conceptual Model For Erp
7. A Conceptual Model For ErpDonovan Mulder
 
4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...
4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...
4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...Donovan Mulder
 
5. Change Management Strategies For Successful Erp Implementation
5. Change Management Strategies For Successful Erp Implementation5. Change Management Strategies For Successful Erp Implementation
5. Change Management Strategies For Successful Erp ImplementationDonovan Mulder
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp ImplementationDonovan Mulder
 
1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach
1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach
1. An Erp Performance Measurement Framework Using A Fuzzy Integral ApproachDonovan Mulder
 
Using A Km Framework To Evaluate An Erp System Implementation
Using A Km Framework To Evaluate An Erp System ImplementationUsing A Km Framework To Evaluate An Erp System Implementation
Using A Km Framework To Evaluate An Erp System ImplementationDonovan Mulder
 

Más de Donovan Mulder (20)

Towards A Model Of Organisational Prerequistes For Enterprise Wide Sys Integ
Towards A Model Of Organisational Prerequistes For Enterprise Wide Sys IntegTowards A Model Of Organisational Prerequistes For Enterprise Wide Sys Integ
Towards A Model Of Organisational Prerequistes For Enterprise Wide Sys Integ
 
The Royalty Of Loyalty Crm, Quality And Retention
The Royalty Of Loyalty Crm, Quality And RetentionThe Royalty Of Loyalty Crm, Quality And Retention
The Royalty Of Loyalty Crm, Quality And Retention
 
The Critical Success Factors For Erp Implementation An Organisational Fit Per...
The Critical Success Factors For Erp Implementation An Organisational Fit Per...The Critical Success Factors For Erp Implementation An Organisational Fit Per...
The Critical Success Factors For Erp Implementation An Organisational Fit Per...
 
Realising Enhanced Value Due To Business Network Redesign Through Extended Er...
Realising Enhanced Value Due To Business Network Redesign Through Extended Er...Realising Enhanced Value Due To Business Network Redesign Through Extended Er...
Realising Enhanced Value Due To Business Network Redesign Through Extended Er...
 
Managing Dirty Data In Organization Using Erp
Managing Dirty Data In Organization Using ErpManaging Dirty Data In Organization Using Erp
Managing Dirty Data In Organization Using Erp
 
Implementing Erp Systems In Small And Midsize Manufacturing Firms
Implementing Erp Systems In Small And Midsize Manufacturing FirmsImplementing Erp Systems In Small And Midsize Manufacturing Firms
Implementing Erp Systems In Small And Midsize Manufacturing Firms
 
Higher Order Testing
Higher Order TestingHigher Order Testing
Higher Order Testing
 
16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems
16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems
16. Erp Ii A Conceptual Framework For Next Generation Enterprise Systems
 
15. Assessing Risk In Erp Projects Identify And Prioritize The Factors
15. Assessing Risk In Erp Projects Identify And Prioritize The Factors15. Assessing Risk In Erp Projects Identify And Prioritize The Factors
15. Assessing Risk In Erp Projects Identify And Prioritize The Factors
 
13. Effectiveness Of Erp Systems
13. Effectiveness Of Erp Systems13. Effectiveness Of Erp Systems
13. Effectiveness Of Erp Systems
 
10. What Managers Should Know About Erp Erpii
10. What Managers Should Know About Erp Erpii10. What Managers Should Know About Erp Erpii
10. What Managers Should Know About Erp Erpii
 
12. Managing Risk Factors In Erp Implementation And Design
12. Managing Risk Factors In Erp Implementation And Design12. Managing Risk Factors In Erp Implementation And Design
12. Managing Risk Factors In Erp Implementation And Design
 
11. Requirements Of An Erp Enterprise Erp Modeller
11. Requirements Of An Erp Enterprise Erp Modeller11. Requirements Of An Erp Enterprise Erp Modeller
11. Requirements Of An Erp Enterprise Erp Modeller
 
9. Factors Affecting Erp System Adoption
9. Factors Affecting Erp System Adoption9. Factors Affecting Erp System Adoption
9. Factors Affecting Erp System Adoption
 
7. A Conceptual Model For Erp
7. A Conceptual Model For Erp7. A Conceptual Model For Erp
7. A Conceptual Model For Erp
 
4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...
4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...
4. Expectation And Reality In Erp Implementation Consultant And Solution Prov...
 
5. Change Management Strategies For Successful Erp Implementation
5. Change Management Strategies For Successful Erp Implementation5. Change Management Strategies For Successful Erp Implementation
5. Change Management Strategies For Successful Erp Implementation
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation
 
1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach
1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach
1. An Erp Performance Measurement Framework Using A Fuzzy Integral Approach
 
Using A Km Framework To Evaluate An Erp System Implementation
Using A Km Framework To Evaluate An Erp System ImplementationUsing A Km Framework To Evaluate An Erp System Implementation
Using A Km Framework To Evaluate An Erp System Implementation
 

Último

Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524najka9823
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 

Último (20)

Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 

ERP Innovation Implementation Model Incorporating Change Management

  • 1. The current issue and full text archive of this journal is available at www.emeraldinsight.com/1463-7154.htm BPMJ 14,2 ERP innovation implementation model incorporating change management 228 M.J. Kemp and G.C. Low School of Information Systems, Technology and Management, The University of New South Wales, Sydney, Australia Abstract Purpose – The purpose of this research is to develop and provide a preliminary validation of a model for how change management during an ERP implementation affects the effectiveness of that ERP implementation. Design/methodology/approach – This paper proposes a revised Klein et al. innovation implementation model that explicitly considers change management. The applicability of the revised model to describe the effect of change management on the implementation climate and implementation effectiveness of an ERP implementation is assessed using a case study at a large Australian multinational organisation. Findings – Specific change management activities are identified and described. Qualitative verification of a proposed ERP innovation implementation model that incorporates the effect of change management is provided. Originality/value – Change management was seen as being an important factor in influencing the effectiveness of the ERP project. This study is the first step in the longer-term empirical validation of the modified innovation implementation model. Keywords Change management, Manufacturing resource planning Paper type Research paper Introduction Many large organisations have made significant investments of both time and capital to implement ERP systems, however not all implementations go as well as intended (Bingi et al., 1999; Kumar and van Hillegersberg, 2000). Owing to the complex nature of ERP systems, many implementations have been difficult, lengthy and over budget, terminated before completion, and/or failed to achieve their business objectives even a year after implementation (Volkoff, 1999). ERP systems are organisation-wide systems and their implementation involves multiple stakeholders, often in geographically disperse locations. Therefore, an ERP system requires data standardisation, integration of the system with other information systems and management of consultants and vendors (Soh et al., 2000). Traditional project management challenges are magnified in such environments, making the implementation more difficult, expensive and failure-prone (Holland and Light, 1999). This complexity suggests that results obtained in other simpler technology implementation environments do not Business Process Management automatically apply to ERP environments (Markus et al., 2000). The significance of a Journal new ERP system and the inherent risks in implementing such a system make it essential Vol. 14 No. 2, 2008 pp. 228-242 that organisations focus on ways to improve ERP implementations. q Emerald Group Publishing Limited Al-Mudimigh et al. (2001) suggest that, the five key critical success factors are top 1463-7154 DOI 10.1108/14637150810864952 management support, business case, change management, project management
  • 2. and training. Change management is a particularly important factor in the adoption, ERP innovation adaptation and acceptance phases of ERP systems implementation (Somers and implementation Nelson, 2004). Somers and Nelson (2004) reinforces the key role change management has in an ERP implementation by observing that many ERP implementations fail to model achieve the expected benefits possibly because companies underestimate the effort involved in change management. This paper proposes an extended innovation implementation model that explicitly 229 incorporates the impact of change management. As a first step in the longer-term empirical validation of the modified innovation implementation model, we examine the applicability of the model to describe how change management during an ERP implementation affects the implementation climate and implementation effectiveness in a major Australian Organisation. Literature review ERP systems are an example of an innovation – a “idea, practice, or object that is perceived as new by an individual or other unit of adoption” (Rogers, 1995). Implementation of an innovation is described as “the process of gaining targeted employees’ appropriate and committed use of an innovation” (Klein and Sorra, 1996). When introducing an innovation such as an ERP system to an organisation, the implementation process needs to be managed so that the expected benefits are achieved. Users require ongoing support from the organisation such as training, maintenance and equipment upgrades in order to achieve implementation effectiveness. It has been suggested that many new systems fail due to implementation failure, rather than innovation failure (Klein et al., 2001). The factors leading to implementation effectiveness can be described using the model proposed by Klein et al. (2001), Figure 1. Change management is not explicitly included in this model, although its effect would be expected to influence implementation climate. For an ERP system, change management is required to prepare users for the introduction of the new system, reduce resistance towards the system and influence user attitudes towards that system. Approaches to managing change can be drawn from marketing research, and from studying the implementation life cycle (Aladwani, 2001). The ERP adoption model (Aladwani, 2001) suggests that change management and management support should positively influence system awareness, feelings towards the system and the intention to adopt that system for users to actually adopt the system. Change management initiatives for a new information system should focus on changes specifically in the areas of technology, business process and organisation, and culture (Benjamin and Levinson, 1993). There is a strong focus in the literature on culture and politics as significant impediments to change (El Sawy, 1985). Management Implementation Support Climate Implementation Implementation Innovation Effectiveness Effectiveness (Use) (Use Time 2) Effectiveness Figure 1. Klein et al. (2001) Financial Implementation innovation Resource Policies and Availability Practices implementation model
  • 3. BPMJ Therefore, change management should focus on creating an environment where the 14,2 change can be implemented (Motwani et al., 2002). Suggested activities include: . project championship (Beath, 1991; Martinsons, 1993); . training (Igbaria et al., 1997); . communication of system features and benefits (Debrabander and Thiers, 1984; 230 Markus, 1983); . communication of new business processes and organisational structure (Grover et al., 1995; Joshi, 1991); and . rewards and incentives (Allen and Kilmann, 2001; Joshi, 1991). Research model The Klein et al. (2001) innovation implementation model, Figure 1, does not explicitly consider the impact that change management has on implementation climate. A climate favourable to the implementation of a new system represents favourable user experiences and attitudes towards the implementation. Therefore, by managing the change that occurs during the implementation at an individual or departmental level, user attitudes towards the system are more likely to be positive and the overall implementation climate is more likely to be favourable. The construct of “change management” has been added to the innovation implementation model to represent the effect that change management can have on implementation climate. The modified model is shown in Figure 2. The implementation climate for an innovation can be described as the sum of employees’ observations and experiences regarding the innovation. The Aladwani ERP adoption model describes the situation where users’ awareness, feelings and intention to adopt an ERP system are affected by change management and management support. User awareness, feelings and intention to adopt an ERP system are equivalent to the experiences and observations of users during an ERP implementation (ie. implementation climate), therefore the Aladwani ERP adoption model can be considered as providing a greater level of detail regarding change management and implementation climate. Management Support Change Implementation Management Climate Implementation Innovation Effectiveness Effectiveness Figure 2. Financial Implementation Modified Klein et al. (2001) Resource Policies & model Availability Practices
  • 4. Hence, it is possible to describe the “dotted portion” of the modified innovation ERP innovation implementation model shown in Figure 2 in greater detail to reflect the definitions of implementation change management activities and climate in the ERP adoption model. The list of change management activities (from the ERP adoption model) has been updated to also include model the additional information systems change management activities discussed previously. Through using this model, Figure 3, the impact of change management on implementation climate and innovation effectiveness can be investigated. Specifically, 231 the research questions are: RQ1. Do the identified change management activities affect the implementation climate? RQ2. Does implementation climate (feelings awareness response, favourable feelings response and favourable adoption intention) impact the effectiveness of the ERP implementation? Research methodology As a first step in the longer-term empirical validation of the revised innovation implementation model, we examine the applicability of the revised model to describe how the change management activities during an ERP implementation affect the Management Support Change Management Activities Implementation Climate Communication of ERP benefits Communication of ERP operations Communicationof system features Favourable Communication of changed Awareness processes Response Involvement of individuals and groups Favourable Implementation Quality of ERP interface Feelings Response Effectiveness Quality of training Level of adoption costs Opinion leader support/ project Figure 3. champion Favourable Proposed ERP innovation Timing/phases of ERP Adoption implementation model implementation Intention incorporating change Rewards & incentives managenment
  • 5. BPMJ implementation climate and implementation effectiveness in a major Australian organisation using a structured-case based approach (Carroll and Swatman, 2000). 14,2 Case study selection The case study organisation is a major Australian Multinational Organisation. The organisation is currently in the process of implementing an ERP system, called “ABC” 232 from one of the two major vendors. It is being implemented in conjunction with re-engineering of the related business processes. The system will house the HR, finance, payroll and procurement transactions that are carried out on a day-to-day basis in the organisation. The ABC system is being implemented in a series of managed releases. As part of its implementation process, the organisation established a change management team as part of the project team. The team was responsible for preparing the organisation for the changes that the ABC system would initiate. This identified the organisation and the ABC program as being an excellent research setting for investigating change management practices in an ERP implementation. Data collection The ABC implementation at the organisation saw a variety of change management activities implemented. Various departments were recipients of a range of change management activities according to the assessed impact that the change would have and the readiness of users in those departments. Various forms of data collection were employed: . Interviews. A range of interviewees was sought, representing a cross-section of the users of the ABC system. Interviewees were recruited from two departments, which were selected based on the change management activities employed in those departments. The operations department had little focused change management, while the human resources department was the recipient of targeted activities. Five executives and three monthly paid staff were interviewed across both departments using a snowball sampling technique. The interviews were designed to be semi-structured with open-ended questions covering implementation effectiveness, implementation climate (awareness response, feelings response and adoption intention) and change management activities. Each interview lasted approximately half-an-hour, and was held in the interviewee’s office or another location nominated by the interviewee. . Review of organisational documents. Surveys, reports and other documents that were generated as part of the ABC implementation were reviewed. Documents relating to the entire change management effort were examined, with particular emphasis on documents relating to the two departments from which interviewees were selected. . Surveys. Triangulation was achieved through the collection of survey data from a small set of respondents in the two departments. The strength of the respondents’ agreement with a range of statements (Table I) was measured on a five-point Likert scale, ranging from 1 – strongly disagree to 5 – strongly agree. The statements are related to the both the system itself (content, accuracy, format, ease of use and timeliness) and the effects of change management experienced (adoption intention, feelings response, system awareness, management support, and change management effectiveness).
  • 6. ERP innovation Operations department HR department All users implementation Median Range Median Range Median Range model Content 4.0 2-4 3.0 3-4 4.0 3-4 Accuracy 4.0 2-4 3.0 2-4 4.0 2-4 Format 4.0 3-4 3.5 2-4 4.0 2-4 233 Ease of use 4.0 2-5 3.0 1-4 4.0 1-5 Timeliness 4.0 4 4.0 1-4 4.0 1-4 Adoption intention 4.0 3-4 4.0 1-5 4.0 1-5 System awareness 4.0 2-4 3.5 2-4 4.0 2-5 Communicators n/a n/a 3.0 2-5 3.0 2-5 Communications 4.0 3-4 3.5 2-4 4.0 2-4 Traininga 4.0 4 4.0 4 4.0 4 Feelings response 3.0 2-4 4.0 1-5 4.0 1-5 User involvement 3.0 3-4 4.0 4-5 3.5 3-5 Management support 4.0 4-5 4.0 4-5 4.0 4-5 Change management effectiveness 3.0 2-4 3.5 1-4 3.0 1-4 Table I. Note: aOnly applicable for users who attended training User survey responses Analysis techniques All interviews were transcribed and these transcriptions were analysed using a three stage coding process: open coding, axial coding and selective coding (Strauss and Corbin, 1997). The purpose of coding is two-fold: to look for patterns among the data and to look for patterns that give meaning to the case study (Merriam, 1985). The open coding stage involved an exploration of the data to generate initial codes. However, the concepts in a conceptual framework can be used as initial codes in guiding the analysis provided this does not prevent the identification of other codes to incorporate new themes (Carroll and Swatman, 2000; Neuman, 2003). Hence, the model for planned change (Kolb and Frohman, 1970) was utilised to provide a framework for identifying initial change management codes. The second axial coding stage involved the analysis of codes developed in open coding for recurring themes or overlapping central categories. Selective coding involved scanning existing codes for cases that illustrate themes within the case study. Major themes or concepts were used to guide the search. In particular, multiple instances of empirical evidence were sought from the interviews, review of organisational documents and the surveys in order to strengthen and validate findings from the study. Case study Release 1 of the ERP system, comprising payroll functionality, was rolled out in September 2003 for monthly paid and executive staff (representing approximately 1,200 users). Release 2 went live in October 2004 and consisted of HR self-service functions for managers and other employees. The Release 2 user base represents a much larger number of users. Five further releases are planned covering performance management, customer service, finance, purchasing and procurement, and portal implementation. Prior to the implementation of the ABC system, each department was responsible for maintaining its own payroll and HR system, leading to duplication of the types of data stored and staff roles in each department. To alleviate these problems,
  • 7. BPMJ a “shared services” approach to service provision was adopted, where a single point of 14,2 contact for all business services was established. A large number of existing HR and payroll staff were moved to a new shared services department, where use of the ABC system has replaced or connects to the departmental HR and payroll systems. Business services are provided by shared services to all departments at agreed service levels and at agreed costs. A new call centre handles questions regarding the ABC system and 234 other HR and payroll queries. The new “shared services” approach was implemented at the same time as Release 1 of the ABC system, however there was not a great deal of system functionality available at that time. In order to take advantage of the new structure, interim processes using forms and direct contact with shared services were implemented. These interim processes mirrored the processes that would exist when Release 2 was released, but required more manual processing. When Release 2 of the system arrived, the processes were again updated to reflect the availability of system functionality. Implementation team Staffs from three major organisations are responsible for implementing the ABC system. Organisation staff with relevant experience and skills have been seconded to the project, for varying amounts of time as required. The hardware infrastructure and web hosting services are being provided by an outsourcing vendor while a consulting organisation is leading the implementation activities and managing the change of business processes. The ERP vendor is carrying out any required changes to the basic ERP software purchased. Change management team The change management team was formed from key staff from the organisation and the consulting organisation which had experience in managing change associated with changes in processes. The team was formed shortly after the beginning of the ABC program. Change management The change management team performed a number of tasks to diagnose, plan, deliver and evaluate the change management activities required for the ABC implementation. Implementation climate assessment Before implementation commenced, the change management team made an assessment of the implementation climate. This involved assessing the impact of the system on business processes, assessing the gap between current and required capabilities and preparing a change management readiness assessment. The implementation climate assessment helped to identify areas of the business that would require specific and targeted change management activities. Scoping and planning The information gathered during the implementation climate assessment was used to create a transition plan describing how to move from the current implementation climate to the users having the required skills and knowledge to operate the ABC system successfully. The people transition plan provided a roadmap for individuals
  • 8. impacted by the change initiatives. The plan outlined the strategy, timing and ERP innovation execution plan for the transition of staff. Change management activities were planned implementation as a result of the people transition plan, and were detailed in separate documents (eg. training plan). model Planning was also required for the communications that would be necessary as a result of the ABC program. The communication plan detailed the stakeholders, key messages and timing of communications to user groups. Key messages included 235 system features, benefits of using the system, progress of development and impact of changed processes. Change management delivery A range of change management activities was performed during the implementation of the ABC system. Most of the change management activities were targeted at specific groups of users, rather than being intended for all users of the system. Strategies included: . Communicating information on system features, system benefits and changed processes using various options including organisation newsletters, ABC system “open days” conference room pilots of the system, and departmental briefings. . Implementing a project championship program. The change management team, with assistance from the organisation general managers and HR staff, selected change agents from functional areas to be impacted by the ABC system. These change agents, known as “Communicators” were the primary communication channel in support of the ABC system implementation. The role and function of communicators were detailed in the communication plan. . Training users across the organisation, focusing on the departments where change would be greatest. A range of training was implemented, from online courses to intensive classroom-based training days. Training was mandatory and face-to-face for users with “high” or “medium” capability gap assessments, and online and optional for all other users. . Involving affected users in all aspects of the change process. . Adopting a phased implementation to help minimise resistance to the changes. Benefits analysis During the scoping and planning phase of the ABC system, a program wide benefits baseline was prepared which included all potential business benefits arising from the ABC system. A primary tool in the realisation of business benefits for each release is the benefit action plan. It defines the required states for four key project factors: process, people, organisation and technology. Discussion Some change management activities suggested in the revised ERP innovation implementation model (Figure 3) were not considered by the change management team during the ABC implementation. These were quality of ERP interface, level of adoption cost, and rewards and incentives. In this case, a standard application was purchased with minimal customization thus largely removing the ability to customize the interface.
  • 9. BPMJ The effectiveness of the implementation is discussed, from the perspective of the users 14,2 of the ERP system. Analysis of effects of the change management on the implementation climate was completed through interviews with organisation staffs from two departments. The operations department was identified as an area that required little change management before the introduction of the ABC system, while the HR department required intensive change management to prepare for the release of the system. 236 Effect of change management on implementation climate The effect of change management on implementation climate will be assessed using the three aspects of implementation climate (system awareness, feelings response and adoption intention) proposed in the research model (Figure 3). System awareness. A high level of system awareness was achieved during the ERP implementation. When questioned, users were able to explain the features of the system in considerable detail, and were able to recall a large number of the benefits of using the system mentioned by the change management team before the release of the system. This finding was confirmed by the survey data (Table I). System awareness was primarily achieved through communications. The users gave this a relatively high-median score of 4.0, Table I. This suggests that, the communications aspect of the ABC program was well managed. Differences were seen in the ability of users to discuss the changes that were made to the processes as a result of the system implementation. HR staff were much more able to describe the changes that had occurred throughout the department. For example, HR staff were able to fully describe the role of the new shared services department and the way in which processes relating to management of information had changed. Operations department staff described Shared Services as “a transaction processing centre” and “where you go when you need help”. While these descriptions are accurate, they are certainly not a complete explanation of the role of shared services in the ABC system implementation. This suggests that, the role of Shared Services was not fully communicated to all users before the release of the system. Some of the differences in the ability to explain process change may lie in the fact that HR staff are much closer to the processes that have changed, as they use the system on a daily basis. However, operations department staff should be able to explain the role of shared services more comprehensively than they did, as executives within the operations department are responsible for managing both their own and their employees’ HR data, and the interim processes between Release 1 and 2 required direct contact with shared services. A failure to understand the role of shared services impacts on the ability of users to know where to get help if required, and may therefore affect the feelings of users towards the system. This then has an effect on the feelings response of users towards the system. Feelings response. Feelings towards the system should be impacted by user involvement and user training. For staff that did not have a particular role in the development of the system, regular briefings and communications helped them feel informed about the progress of development. The HR department was the recipient of targeted change management activities while the operations department had little focused change management. This difference was reflected in the higher median score for user involvement for the HR group (4.0) compared with the operations department group (3.0). It is also reflected in the ratings of feelings response, Table I.
  • 10. Discussion with users regarding training showed that the feelings of those users ERP innovation who believed the training was excessive or inadequate were less positive towards the system than the feelings of the users who believed that the training was adequate. implementation Those who attended training scored a much higher median score for the feelings model response questions (a median score of 4.25 for those who attended training, compared with 3.0 for those who did not). This suggests that training assists in improving the feelings response of users, and thus improves the adoption intention. 237 Adoption intention. Although users could easily identify problems and frustrations with the system, general resistance to the system amongst users was low. Most believed that the system was necessary and would not attempt to delay progress. All users had been keen to have a look at what was actually in the system after hearing about it for many months before its release. The high level of adoption intention expressed in the interviews is confirmed by its relatively high-median score of 4.0 in the survey results. Adoption intention was improved through change management activities such as project championship and phased ERP implementation. Users in both departments supported the idea of a phased implementation. However, the downside of a phased implementation was that if one release is delayed, the completion dates for future releases are also delayed. Release 2 of the system was released seven months after its intended release date. As change management needs to occur prior to the release of the system, the change management team implemented the change activities far earlier than required. Communications were then required to reassure staff members that the system was still being implemented, and would be released when it was ready. One user commented: They kept sending messages saying that the system was still coming. But no amount of communication is going to change the fact that the system isn’t here yet. It made the system team seem really incompetent. Discussion with users regarding the project showed that the late release of Release 2 was the main reason for any user resistance towards the ABC system. Effect of management support on implementation climate Interviewees commented that there was an attitude of overall support from the organisation, and that their manager was in support of the system prior to its release. This indicates that, the organisation as a whole was publicly very supportive of the system and was able to show encouragement through the provision of resources. Some managers spoke of showing supportiveness of the system when dealing with their own staff, even if they were personally somewhat sceptical of the benefits claimed. The high level of management support was confirmed by survey data relating to the attitude of managers towards the project. All users surveyed responded with “Agree” or “Strongly Agree” when asked about the level of support for the project from both managers and the organisation as a whole, Table I. Implementation effectiveness The feelings of all interviewed users towards the system prior to its release were positive. All interviewees indicated that, they logged into the system when it was released just to see what was available. All change management activities mentioned in planning documents prepared by the change management team were implemented prior to the system being released.
  • 11. BPMJ The climate prior to its release was one expectant of better results than what were 14,2 being achieved with the legacy systems. HR staff were satisfied on the whole with the way the change in their department was managed. However, operations department staff were neutral. Staff were not overly interested in the system and the benefits using the system can bring. Some users claimed that they are unaware of how to use the system or when usage of the system is required. This suggests that, the capability gap 238 assessment for the operations department may have been incorrect and more formal user training was required. Their necessary capabilities required were rated at a low level and their current skills were seen as adequate, which did not necessitate a formal change management process in this department. Conclusions This study identified the major activities used in an ERP implementation through a case study of the ABC program in the case study organisation. It has shown that change management is an important factor in an ERP implementation. The implementation of the ABC system followed the research model shown in Figure 3. The change management activities affected the implementation climate. In turn, the implementation climate affected the effectiveness of the implementation. The change management activities had the required effect on the climate for implementation. The activities implemented assisted in informing users about the system, and enabling the provision of skills required when the system was implemented. There were noticeable differences between users who had participated in change management activities either through optional involvement or the provision of extra change management activities in some departments and those who did not participate. Some aspects of the change management program could have been better managed. Managers tended to publicly support the implementation of the ABC system, but privately believed that the system would not be of much benefit. A theme often discussed in interviews was the fact that often users did not understand why the organisation had undertaken the ABC implementation and did not believe that it was necessary. Many wondered why a system that cost so much was being implemented when it was not providing any greater functionality, and at times was less efficient than legacy systems. This suggests that managers should be informed of the motivation for implementing the ERP system, rather than just being informed of benefits and be expected to advocate the system within their departments. It also suggests that the change management activity, “level of adoption cost” should be specifically addressed as part of the change management process. There are indications that the users’ expectations for the system were different to the actual features of the implemented system. Some users gave a very low score for the survey question relating to whether the features of the system were as expected. This indicates that although users were aware of the system and its benefits, the actual system did not have the features expected by users. This could be a result of the change management team overstating the benefits, or not explaining them clearly, or the users misunderstanding what they were being told. This suggests that communications about the system must be very clear and match with what the system actually offers. The users were disappointed and resistance towards the system increased when it was different to what they expected. It would have been beneficial for more users to see the system for themselves prior to its release
  • 12. in order to accurately gauge the functionality offered. However, the ABC system may ERP innovation be different to other ERP implementations in that the change management team must implementation also provide details on modules to be released in future phases. Users may expect to see a module in the next phase, when in reality it may not be implemented for a number of model years. If the implementation is a phased implementation, care should be taken to accurately inform users of when each feature will be released. The implemented change management activities also affected different areas of 239 the organisation in different ways. Each department within the organisation received a very different range of change management activities based on the identified needs, and it is evident that the range and types of change management received impact upon the effectiveness of the ERP implementation. When assessing the need for change management in each department, the change management team implemented activities that they believed would provide the best implementation climate for the most realistic amount of work. At the end of the change management process, the change management team expected that the implementation climate across the organisation would be similar. In reality, the implementation climate differed throughout the organisation. The general attitude to the system by those in the department that received less change management was less positive than for those who were the recipients of more targeted activities. This indicates that change management is required throughout an organisation implementing an ERP system, even if the changes in one particular area of the organisation are not particularly great. Despite the problems identified by users after the release of the system, the change management activities have been successful. Users who were sceptical when hearing about the project are now generally well equipped to use the system. This indicates that ERP implementations similar to the ABC system would benefit from similar types of change management activities. The effect of change management and management support on implementation climate are supported by the case study. In addition there is support for the impact of implementation climate on implementation effectiveness. However, there may be other factors that determine implementation effectiveness. Although users may be able to use the system as intended, they are not always able to use it well. Interviews with HR staff showed that some aspects of the system such as speed of the system and quality of interface design prevent the staff from using the system to its full potential. This suggests that more implementation climate is not the only factor in determining implementation effectiveness, and that features of the system itself do play a part in the success of an ERP implementation. Further research This research is a first step in the longer-term empirical validation of the revised innovation implementation model, Figure 2. This model will be extended to incorporate the effect of system features (technology fit) on implementation effectiveness based on the research findings. The empirical validation of the expanded model is planned using survey data obtained from users involved in ERP implementations in various organisations. Structural equation modeling, using partial least squares, will be used to test the overall fit of the structural model. The research constructs will be derived from
  • 13. BPMJ the Klein et al. (2001) and Aladwani (2001) models. Since most users will have little 14,2 understanding of the financial resource availability this construct (and its associated hypotheses) will be omitted from the analysis. The accompanying research hypotheses are described below: H1. Implementation climate is positively correlated with implementation effectiveness. 240 H1.1 Favourable awareness response is positively correlated with implementation effectiveness. H1.2 Favourable feelings response is positively correlated with implementation effectiveness. H1.3 Favourable adoption intention is positively correlated with implementation effectiveness. H2. Change management is positively correlated with the implementation climate. H2.1 Change management activities (communications issues) are positively correlated with favourable awareness response. H2.2 Change management activities (involvement of individuals and groups, and quality of training) are positively correlated with favourable feelings response H2.3 Change management activities (project champion support, and timing/phases of ERP implementation) are positively correlated with favourable adoption intention. H3. Management support is a moderating variable between change management and the implementation climate. H4. Technology fit is positively correlated with implementation effectiveness. H5. Implementation policies and practices are positively correlated with implementation effectiveness. References Aladwani, A.M. (2001), “Change management strategies for successful ERP implementation”, Business Process Management Journal, Vol. 7 No. 3, pp. 266-75. Allen, R.S. and Kilmann, R.H. (2001), “The role of the reward system for a total quality management based strategy”, Journal of Organizational Change, Vol. 14 No. 2, pp. 110-31. Al-Mudimigh, A., Zairi, M. and Al-Mashari, M. (2001), “ERP software implementation: an interactive framework”, European Journal of Information Systems, Vol. 10, pp. 216-26. Beath, C. (1991), “Supporting the information technology champion”, MIS Quarterly, Vol. 15 No. 3, pp. 355-72. Benjamin, R. and Levinson, E. (1993), “A strategic framework for managing IT-enabled change”, Sloan Management Review, Vol. 34 No. 4, pp. 23-34.
  • 14. Bingi, P., Sharma, M.K. and Godla, J. (1999), “Critical issues affecting an ERP implementation”, ERP innovation Information Systems Management, Vol. 16 No. 3, pp. 7-14. implementation Carroll, J.M. and Swatman, P.A. (2000), “Structured-case: a methodological framework for building theory in information systems research”, European Journal of Information model Systems, Vol. 9 No. 4, pp. 235-42. Debrabander, B. and Thiers, G. (1984), “Successful information system development in relation to situational factors which affect effective communication between MIS users and EDP 241 specialists”, Management Science, Vol. 30 No. 2, pp. 137-55. El Sawy, O.A. (1985), “Implementation by cultural infusion: an approach for managing the introduction of information technologies”, MIS Quarterly, Vol. 9 No. 2, pp. 131-40. Grover, V., Jeong, S.R., Kettinger, W. and Teng, J. (1995), “The implementation of business process reengineering”, Journal of Management Information Systems, Vol. 12 No. 1, pp. 109-44. Holland, C.P. and Light, B. (1999), “A critical success factors model for ERP implementation”, IEEE Software, May/June, pp. 30-6. Igbaria, M., Zinatelli, N., Cragg, P. and Cavaye, A.M. (1997), “Personal computing acceptance factors in small firms: a structural equation model”, MIS Quarterly, Vol. 21 No. 3, pp. 279-305. Joshi, K. (1991), “A model of users’ perspective on change: the case of information systems technology implementation”, MIS Quarterly, Vol. 15 No. 3, pp. 229-42. Klein, K. and Sorra, J.S. (1996), “The challenge of innovation implementation”, The Academy of Management Review, Vol. 21 No. 4, p. 1055. Klein, K., Conn, A. and Sorra, J.S. (2001), “Implementing computerized technology: an organizational analysis”, Journal of Applied Psychology, Vol. 86 No. 5, pp. 811-24. Kolb, D.A. and Frohman, A.L. (1970), “An organization development approach to consulting”, Sloan Management Review, Vol. 12 No. 1, pp. 51-65. Kumar, K. and van Hillegersberg, J. (2000), “ERP experience and evolution”, Communications of the ACM, Vol. 43 No. 4, pp. 23-6. Markus, M.L. (1983), “Power, politics, and MIS implementation”, Communications of the ACM, Vol. 26, pp. 430-44. Markus, M.L., Axline, S., Petrie, D. and Tanis, C. (2000), “Learning from adopters’ experiences with ERP: problems encountered and success achieved”, Journal of Information Technology, Vol. 15 No. 4, pp. 245-65. Martinsons, M.G. (1993), “Cultivating the champions for strategic information systems”, Journal of Systems Management, Vol. 44 No. 8, pp. 31-4. Merriam, S. (1985), “The case study in educational research: a review of selected literature”, The Journal of Educational Thought, Vol. 19 No. 3, pp. 204-17. Motwani, J., Mirchandani, D., Madan, M. and Gunasekaran, A. (2002), “Successful implementation of ERP projects: evidence from two case studies”, International Journal of Production Economics, Vol. 75 Nos 1/2, p. 83. Neuman, W.L. (2003), Social Research Methods – Qualitative and Quantitative Approaches, Allyn and Bacon, Boston, MA. Rogers, E.M. (1995), Diffusion of Innovations, The Free Press, New York, NY. Soh, C., Kien, S.S. and Tay-Yap, J. (2000), “Cultural fits and misfits: is ERP a universal solution?”, Communications of the ACM, Vol. 43 No. 4, pp. 47-51.
  • 15. BPMJ Somers, T.M. and Nelson, K.G. (2004), “A taxonomy of players and activities across the ERP project life cycle”, Information & Management, Vol. 41 No. 3, pp. 257-78. 14,2 Strauss, A. and Corbin, J. (1997), Grounded Theory in Practice, Sage, London. Volkoff, O. (1999), “Using the structural model of technology to analyze an ERP implementation”, AMCIS, Milwaukee, August 13-15, pp. 235-7. 242 Corresponding author G.C. Low can be contacted at: g.low@unsw.edu.au To purchase reprints of this article please e-mail: reprints@emeraldinsight.com Or visit our web site for further details: www.emeraldinsight.com/reprints