PSP & Guidelines MOP.pptx

PUMPED STORAGE HYDROPOWER
Guidelines issued by Ministry of Power, Government of India
Abhishek Mallick
Executive Engineer (E&M)
POWER PROJECTS DIVISION, SCCL
● PSH acts as an energy store, If there is a surplus of power in the grid,
the pumped storage power station switches to pumping mode – an
electric motor drives the pump turbines, which pumps water from a
lower reservoir to a higher storage basin.
● If the demand for electricity in the grid rises, water is released from
the upper basin via a pressure pipeline to the bottom. The water causes
the pump turbines to rotate, now operating in turbine mode and used to
drive the generators. Within seconds, electricity is generated and fed
into the grid.
ABOUT PSP TECHNOLOGY:
PSP & Guidelines MOP.pptx
● ON-STREAM: Both reservoirs are located on any river
/stream
● OFF-STREAM OPEN LOOP - Only one of the reservoirs is
located on any river/ stream.
● OFF-STREAM CLOSED LOOP - None of the reservoirs is
located on any river/ stream
4
TYPES OF PSP:
OPEN-LOOP & CLOSED-LOOP PSH
● Pumped storage
Hydropower + Solar
Power/ Wind Power
● Once the solar power is
more than the needed,
excess is used to pump
water from lower
reservoir to upper
reservoir.
● If there is no solar power
generation, the water
flows from upper basin
to the lower and drives a
turbine to produce
power.
HYBRID PSP CONCEPT:
HIGHLIGHTS OF PSP
 PSP are also known as ‘Water Battery/ Green Battery’
 Long service life of 40-50 years
 Offers critical back up during peak hours (Flexible/Reliable)
 No residual environment impacts
 High economical value: Pumped storage plants works at an efficiency level
upto 82 percent
 PSP are designed for 06 hours of operations
 CEA estimate Potential: 103 GW- ON River, OFF River- Being estimated
 As per report by CEA 26.7 GW PSP are required by 2032
PRO CONS
Flexible and Reliable Long Planning and construction time
Long Service Life Specific geographical condition for
upper reservoir and lower reservoir
Relatively high efficiency upto 85% Large amount of initial investment
Most viable option Long Pay back period
Reduces energy wastage
PRO & CONS:
9
GUIDELINES ISSUED BY M.O.P
Dt. 10.04.2023
ENABLERS FOR PSP
 Environmental Clearances- PSP on existing reservoirs and on off-the-river
sites may be treated as a separate category for processing of applications
(Appraised under B2 category of MOEF &CC for grant of EC) . As per MOEF&CC
draft notification dated 11.10.22 the following criteria will be treated as B2 for
grant of EC:
1. Projects which do not attract Forest Clearance/ Wildlife Clearance
2. Projects where no new reservoirs are created
3. Projects where existing reservoirs are not expanded or structurally
modified
 Cost of Pumping Power- Three factors:
1. Cost of Input Power (Viability depends on availability of affordable input
power)
2. Conversion Losses
3. Cost of Storage
Value of Peak Power- PSP is capable of offering several services such as:
•Spinning Reserves- Generation capacity that is on-line but unloaded and
that can respond within 10 minutes to compensate for generation or
transmission outages, Reactive Support
•Reactive Support- used to provide the voltage levels necessary for active
power to do useful work
•Black start- the ability of generation to restart parts of the power system
to recover from a blackout
•Frequency response, faster start up’s and shutdowns which are essential
for grid stability
MEASURES TAKEN BY GOI FOR PROMOTION OF PSP
• States to allot PSP to PSU (Annex-I)
• Energy Storage Obligation (Annex-II)
• Waiver of ISTS Charges for PSP (Annex-III)- (Extendable to PSP where
construction work is awarded by 30.06.2025
• Budgetary Support (Annex-IV)
• Timelines for formulation and concurrence of DPR’s for PSP reduced from
900 days to 720 days and CEA shall further reduce timeline for Off-stream
closed loop PSP and PSP on existing hydro projects (Where one reservoir is
available)
• Since No tariff/ financial evaluation by CEA for tariff based Competitive
bidding, concurrence reduced from 150 days to 75 days. For other mode of
award concurrence reduced from 150 days to 125 days.
• Central Government will notify a benchmark tariff of storage for investment
decisions
BENEFITS TO BE EXTENDED BY STATE
• No upfront fee shall be charged by state government
• State Government shall consider reimbursement of SGST on PSP project
components.
• States may exempt Stamp duty and Registration fee for land to be
acquired by off-the-river PSP
• Government land may be provided at a concessional rate to the developers
on annual lease rent basis.
• To avoid double taxation, Electricity Duty and Cross subsidy charges shall
not be applicable for Pumping power and may be levied on final
consumption of electricity
• No requirement of Local Area Development fund
ALLOTMENT OF PSP PROJECTS
State Government may allot project sites to developers in the following
manner:
1. On Nomination Basis to CPSU/SPSU:
-States may award projects directly to PSU on nomination basis
- Award of EPC shall be through Competitive Bidding
2. Allotment through Competitive Bidding:
- May be allotted to Private developers by two stage competitive bidding
Stage 1: Pre-qualification based on financial strength, experience, turnover,
ability to meet performance guarantees
Stage 2: Bids to be called on quantifiable parameters such as concession period
of project or any other parameter as specified by Central/State Govt.
For above two modes:
• Home state shall have right of first refusal upto 80% of Project Capacity and
developer is free to sell power in any mode
• Tariff shall be fixed by appropriate commission u/s 62 of elec act 2003,
3. Allotment through Tariff Based Competitive Bidding:
May be awarded to a developer in TBCB mode:
 Survey & Investigation and Prep of DPR may be given to SPV under State/Central PSU
 SPV responsible for Pre-construction activities such as Project Report, Land
Acquisition, Environment & Forest Clearance etc.
 DPR may be subsequently bid out for construction and SPV transferred to the
successful bidder on the basis of :
 COMPOSITE TARIFF (including Cost of Input Power)- Input power arranged by
developer
 TARIFF FOR STORAGE ON MWh BASIS: Input Power Arranged by the procurer of the
storage Capacity
 Appropriate commission shall adopt the tariff u/s 63 of Electricity Act, 2003
4. Self Identified Off-Stream Pumped Storage Projects:
 Developers may also identify potential off stream sites where PSP can be constructed
 Allotment from state government not required
 All statutory clearances need to be obtained from central/state agencies before
construction
 All concessions would be provided
MARKET REFORMS/ CONSIDERATIONS:
 Timeline: Start of Construction within 02 years from the date of allotment,
relaxation of 01 year where delay is due to FC & EC.
 Appropriate commission shall ensure monetization of services offered by PSP
such as Spinning reserves, ramping support, black start etc
 Appropriate commission shall notify Peak and Off-Peak tariffs for generation
to provide appropriate pricing signal to peak and base load generating plants
 PSP allowed to participate in all market segments of Power exchange including
High price segment of Day Ahead Market (HP-DAM)
 During monsoon- 80% Power to home state at secondary tariff fixed by
CERC. Remaining 20 % can be sold
 In case contracted capacity is not fully utilized by agency, developer is free
to transfer usage of capacity to other interested consumers. Gains to be
shared with original beneficiary in ratio of 50:50
 Financial institutions like PFC, REC and IREDA shall treat PSP at par with
other renewable energy projects while extending loans of 20-25 years . Debt
equity ratio can be upto 80:20
 Green Finance: PSP may be supported through concessional climate
finance. Sovereign green bonds issues for mobilizing resources for green
infrastructure as a part of the government’s overall market borrowings may
be deployed
Annexure-II
MOP Letter 22.07.2022
(RPO & ENERGY STORAGE OBLIGATION Trajectory 2029-30):
 Large Hydro Projects (LHP’s) including PSP>25 MW as a part of RE.
 LHP’s commissioned after 08.03.2019 will be considered for RPO through a
separate obligation i.e Hydro Power Purchase Obligation (HPO).
 RPO shall be calculated in energy terms as a percentage of total consumption
of electricity.
 Wind RPO shall be met only by energy produced from Wind Power Plants
commissioned after 31st Mar 2022.
 Renewable Energy Certificate mechanism corresponding to Hydro Power to
be developed by CERC to facilitate compliance of HPO would have a capping
price of Rs 5.50/Unit from 08.03.20190 to 31.03.2021 and with an annual
escalation @ 5% thereafter.
RENEWABLE PURCHASE OBLIGATION
TRAJECTORY 2029-30
YEAR WIND RPO HPO OTHER RPO TOTAL RPO
2022-23 0.81% 0.35% 23.44% 24.6%
2023-24 1.6% 0.66% 24.81% 27.07%
2024-25 2.46% 1.08% 26.37% 29.91%
2025-26 3.36% 1.48% 28.17% 33.01%
2026-27 4.29% 1.8% 29.86% 35.95%
2027-28 5.23% 2.16% 31.43% 38.82%
2028-29 6.16% 2.51% 32.69% 41.36%
2029-30 6.94% 2.82% 33.57% 43.33%
ENERGY STORAGE OBLIGATION
 Shall be calculated in energy terms as a
percentage of total consumption of
electricity- Subject to fulfillment of
condition that at least 85% of electricity
stored is procured from RE Source
 POSOCO will maintain data related to
compliance of RPO obligations
FY
Storage
(On Energy
basis)
2023-24 1%
2024-25 1.50%
2025-26 2%
2026-27 2.50%
2027-28 3%
2028-29 3.50%
2029-30 4%
Annexure-III
MOP Letter 23.11.2023 (WAIVER OF ISTS):
 For Solar, Wind, Hydro PSP and BESS Projects commissioned upto 30.06.2025, the
waiver of ISTS charges shall be applicable
• At least 51% of electricity requirement for pumping water at PSP/ Batter charging at
BESS is from Solar/Wind
• Electricity Generated/ Supplied by PSP & BESS
• For Green Hydrogen Plants commissioned upto 30.06.2025- Hydrogen produced using
electricity from SOLAR/WIND/PSP/ BESS
• ISTS (Inter state transmission system)
• Waiver shall be applicable for a period of 25 years for solar, wind and hydro PSP or for a
period of 12 Years for BESS
• Waiver is for ISTS charges and not for losses.
Projects Commissioned before 30.06.2025 No ISTS Charges Applicable
01.07.2025 30.06.2026 25 %
01.07.2026 30.06.2027 50 %
01.07.2027 30.06.2028 75 %
01.07.2028 Onwards 100 %
Annexure-IV
MOP letter 28.09.2021
Budgetary Support towards Cost of Enabling Infrastructure i/e Roads,
Bridges
 Shall be provided for project starting construction after 08.03.2019
 Budgetary support would be provided after appraisal/ approval of each
project by PIB/CCEA (Cabinet Committee on economic affairs) through
MOP
 Limit is 1.5 Cr/MW upto 200 MW and 1.0 Cr/MW for projects above 200 MW
 Will be provided as reimbursement after achieving milestones
 In-Principle approval of MOP is required for budgetary support
 Procedure- After DPR concurrence by State Govt/CEA (Annex-I) to be
submitted to CEA
Eligibility:
 Cap>25MW concurred either by CEA or State Government wherein
LOA is issued after 08.03.2019
 All roads and bridges required to connect major components like
DAM, Power House, Adits (Tunnel), Surge Shafts, Pressure shafts,
TRT (tunnel for return water to tank) etc of the project to state/
national highway including strengthening / widening shall be
considered for budgetary support
 For Construction of Road/Bridges (Land Acquisition Cost/ All
statutory taxes, levies, duties, cess shall be included in budgetary
support)
1 de 23

Recomendados

Renewable energy resources por
Renewable energy resourcesRenewable energy resources
Renewable energy resourcesshalini2093
31.4K vistas30 diapositivas
Solar Policy in India (Article) por
Solar Policy in India (Article) Solar Policy in India (Article)
Solar Policy in India (Article) Arpit Kurel
163 vistas14 diapositivas
The Opportunities and Challenges of Renewable Energy Integration With Low-Car... por
The Opportunities and Challenges of Renewable Energy Integration With Low-Car...The Opportunities and Challenges of Renewable Energy Integration With Low-Car...
The Opportunities and Challenges of Renewable Energy Integration With Low-Car...OECD Environment
145 vistas8 diapositivas
Roopur power plant and iran nuclear conflict por
Roopur power plant and iran nuclear conflictRoopur power plant and iran nuclear conflict
Roopur power plant and iran nuclear conflictImran Sajol
640 vistas32 diapositivas
Green Hydrogen Financial Model Toolkit por
Green Hydrogen Financial Model ToolkitGreen Hydrogen Financial Model Toolkit
Green Hydrogen Financial Model ToolkitFadi Maalouf, PMP
421 vistas36 diapositivas
CONVENTIONAL AND NON CONVENTIONAL RESOURCES por
CONVENTIONAL AND NON CONVENTIONAL RESOURCES CONVENTIONAL AND NON CONVENTIONAL RESOURCES
CONVENTIONAL AND NON CONVENTIONAL RESOURCES Rhythm Narula
459 vistas13 diapositivas

Más contenido relacionado

La actualidad más candente

Presentation by MNRE on Solar Parks por
Presentation by MNRE on Solar ParksPresentation by MNRE on Solar Parks
Presentation by MNRE on Solar ParksGensol Engineering Limited
4.3K vistas19 diapositivas
Renewable Energy Sector Funding por
Renewable Energy Sector FundingRenewable Energy Sector Funding
Renewable Energy Sector FundingResurgent India
2.1K vistas36 diapositivas
Energy Conservation por
Energy ConservationEnergy Conservation
Energy ConservationPiyushjauhari3
1.3K vistas23 diapositivas
Energy roadmap to net-zero transmissions: MEMR, Indonesia por
Energy roadmap to net-zero transmissions: MEMR, IndonesiaEnergy roadmap to net-zero transmissions: MEMR, Indonesia
Energy roadmap to net-zero transmissions: MEMR, IndonesiaOECD Environment
1.5K vistas18 diapositivas
The value of Guarantees of Origin: empowering consumers in the energy transition por
The value of Guarantees of Origin: empowering consumers in the energy transitionThe value of Guarantees of Origin: empowering consumers in the energy transition
The value of Guarantees of Origin: empowering consumers in the energy transitionLeonardo ENERGY
353 vistas32 diapositivas

La actualidad más candente(20)

Renewable Energy Sector Funding por Resurgent India
Renewable Energy Sector FundingRenewable Energy Sector Funding
Renewable Energy Sector Funding
Resurgent India2.1K vistas
Energy roadmap to net-zero transmissions: MEMR, Indonesia por OECD Environment
Energy roadmap to net-zero transmissions: MEMR, IndonesiaEnergy roadmap to net-zero transmissions: MEMR, Indonesia
Energy roadmap to net-zero transmissions: MEMR, Indonesia
OECD Environment1.5K vistas
The value of Guarantees of Origin: empowering consumers in the energy transition por Leonardo ENERGY
The value of Guarantees of Origin: empowering consumers in the energy transitionThe value of Guarantees of Origin: empowering consumers in the energy transition
The value of Guarantees of Origin: empowering consumers in the energy transition
Leonardo ENERGY353 vistas
Business Plan: Biomass Power Plant por Sunil Kumar
Business Plan: Biomass Power PlantBusiness Plan: Biomass Power Plant
Business Plan: Biomass Power Plant
Sunil Kumar12.7K vistas
Energy in Australia: Past, present and future por IEA-ETSAP
Energy in Australia: Past, present and futureEnergy in Australia: Past, present and future
Energy in Australia: Past, present and future
IEA-ETSAP367 vistas
Presentation On Impact Of Nuclear Power Plant por Avijit Karmakar
Presentation On Impact Of Nuclear Power PlantPresentation On Impact Of Nuclear Power Plant
Presentation On Impact Of Nuclear Power Plant
Avijit Karmakar2.6K vistas
ENERGY SCENARIO IN PAKISTAN.Ali Raza por Ali Raza
ENERGY SCENARIO IN PAKISTAN.Ali RazaENERGY SCENARIO IN PAKISTAN.Ali Raza
ENERGY SCENARIO IN PAKISTAN.Ali Raza
Ali Raza1.9K vistas
Dhabol PPT power debacle por ALOK KUMAR
Dhabol PPT power debacleDhabol PPT power debacle
Dhabol PPT power debacle
ALOK KUMAR1.1K vistas
Development of Renewable Energy and Energy Conservations towards Net Zero Emi... por Sampe Purba
Development of Renewable Energy and Energy Conservations towards Net Zero Emi...Development of Renewable Energy and Energy Conservations towards Net Zero Emi...
Development of Renewable Energy and Energy Conservations towards Net Zero Emi...
Sampe Purba324 vistas
Wind energy(Pakistan) por MUHAMMAD UMAIR
Wind energy(Pakistan)Wind energy(Pakistan)
Wind energy(Pakistan)
MUHAMMAD UMAIR10.9K vistas
panki power plant training.ppt por Abhishek Awasthi
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
Abhishek Awasthi16.6K vistas

Similar a PSP & Guidelines MOP.pptx

Renewable Energy - Recent Initiatives por
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesSaurabh Mehta
1.2K vistas25 diapositivas
HYDRO_POLICY_UK_2015 por
HYDRO_POLICY_UK_2015HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015Anil Khadka
432 vistas12 diapositivas
Manipur solar policy 2014 por
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
757 vistas8 diapositivas
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018 por
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Gensol Engineering Limited
1.9K vistas8 diapositivas
Small Power Generation Plant por
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation PlantCraig Abednego Malone
333 vistas17 diapositivas
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019 por
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
1.4K vistas2 diapositivas

Similar a PSP & Guidelines MOP.pptx(20)

Renewable Energy - Recent Initiatives por Saurabh Mehta
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
Saurabh Mehta1.2K vistas
HYDRO_POLICY_UK_2015 por Anil Khadka
HYDRO_POLICY_UK_2015HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015
Anil Khadka432 vistas
Manipur solar policy 2014 por Headway Solar
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014
Headway Solar757 vistas
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh... por electricitygovernance
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
Renewable Energy Hydrosector India por HIMADRI BANERJI
Renewable Energy Hydrosector IndiaRenewable Energy Hydrosector India
Renewable Energy Hydrosector India
HIMADRI BANERJI741 vistas
Net energy metering manual for three schemes por Private Consultants
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
Private Consultants2.6K vistas
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O... por Resurgent India
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Resurgent India282 vistas
Renewables will shape Argentina’s new energy matrix por Doris Capurro
Renewables will shape Argentina’s new	energy matrixRenewables will shape Argentina’s new	energy matrix
Renewables will shape Argentina’s new energy matrix
Doris Capurro276 vistas
Gujarat Wind Power Policy 2013 por Spark Network
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
Spark Network780 vistas
Tariff policy of India: Salient Points por Amitava Nag
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
Amitava Nag2.8K vistas
Analysis on Wind Solar Hybrid Tender.pptx por ssuser387308
Analysis on Wind Solar Hybrid Tender.pptxAnalysis on Wind Solar Hybrid Tender.pptx
Analysis on Wind Solar Hybrid Tender.pptx
ssuser3873085 vistas
Andhra pradesh solar policy 2015 por Headway Solar
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015
Headway Solar538 vistas

Último

START Newsletter 3 por
START Newsletter 3START Newsletter 3
START Newsletter 3Start Project
6 vistas25 diapositivas
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for Growth por
BCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for GrowthBCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for Growth
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for GrowthInnomantra
10 vistas4 diapositivas
REACTJS.pdf por
REACTJS.pdfREACTJS.pdf
REACTJS.pdfArthyR3
35 vistas16 diapositivas
MK__Cert.pdf por
MK__Cert.pdfMK__Cert.pdf
MK__Cert.pdfHassan Khan
16 vistas1 diapositiva
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc... por
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...csegroupvn
6 vistas210 diapositivas
Searching in Data Structure por
Searching in Data StructureSearching in Data Structure
Searching in Data Structureraghavbirla63
14 vistas8 diapositivas

Último(20)

BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for Growth por Innomantra
BCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for GrowthBCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for Growth
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for Growth
Innomantra 10 vistas
REACTJS.pdf por ArthyR3
REACTJS.pdfREACTJS.pdf
REACTJS.pdf
ArthyR335 vistas
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc... por csegroupvn
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...
csegroupvn6 vistas
Searching in Data Structure por raghavbirla63
Searching in Data StructureSearching in Data Structure
Searching in Data Structure
raghavbirla6314 vistas
Proposal Presentation.pptx por keytonallamon
Proposal Presentation.pptxProposal Presentation.pptx
Proposal Presentation.pptx
keytonallamon63 vistas
Design_Discover_Develop_Campaign.pptx por ShivanshSeth6
Design_Discover_Develop_Campaign.pptxDesign_Discover_Develop_Campaign.pptx
Design_Discover_Develop_Campaign.pptx
ShivanshSeth645 vistas
ASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdf por AlhamduKure
ASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdfASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdf
ASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdf
AlhamduKure6 vistas
Update 42 models(Diode/General ) in SPICE PARK(DEC2023) por Tsuyoshi Horigome
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
Tsuyoshi Horigome39 vistas
SPICE PARK DEC2023 (6,625 SPICE Models) por Tsuyoshi Horigome
SPICE PARK DEC2023 (6,625 SPICE Models) SPICE PARK DEC2023 (6,625 SPICE Models)
SPICE PARK DEC2023 (6,625 SPICE Models)
Tsuyoshi Horigome36 vistas
Web Dev Session 1.pptx por VedVekhande
Web Dev Session 1.pptxWeb Dev Session 1.pptx
Web Dev Session 1.pptx
VedVekhande13 vistas
Design of machine elements-UNIT 3.pptx por gopinathcreddy
Design of machine elements-UNIT 3.pptxDesign of machine elements-UNIT 3.pptx
Design of machine elements-UNIT 3.pptx
gopinathcreddy34 vistas
Ansari: Practical experiences with an LLM-based Islamic Assistant por M Waleed Kadous
Ansari: Practical experiences with an LLM-based Islamic AssistantAnsari: Practical experiences with an LLM-based Islamic Assistant
Ansari: Practical experiences with an LLM-based Islamic Assistant
M Waleed Kadous7 vistas
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx por lwang78
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
lwang78165 vistas
SUMIT SQL PROJECT SUPERSTORE 1.pptx por Sumit Jadhav
SUMIT SQL PROJECT SUPERSTORE 1.pptxSUMIT SQL PROJECT SUPERSTORE 1.pptx
SUMIT SQL PROJECT SUPERSTORE 1.pptx
Sumit Jadhav 22 vistas
fakenews_DBDA_Mar23.pptx por deepmitra8
fakenews_DBDA_Mar23.pptxfakenews_DBDA_Mar23.pptx
fakenews_DBDA_Mar23.pptx
deepmitra816 vistas

PSP & Guidelines MOP.pptx

  • 1. PUMPED STORAGE HYDROPOWER Guidelines issued by Ministry of Power, Government of India Abhishek Mallick Executive Engineer (E&M) POWER PROJECTS DIVISION, SCCL
  • 2. ● PSH acts as an energy store, If there is a surplus of power in the grid, the pumped storage power station switches to pumping mode – an electric motor drives the pump turbines, which pumps water from a lower reservoir to a higher storage basin. ● If the demand for electricity in the grid rises, water is released from the upper basin via a pressure pipeline to the bottom. The water causes the pump turbines to rotate, now operating in turbine mode and used to drive the generators. Within seconds, electricity is generated and fed into the grid. ABOUT PSP TECHNOLOGY:
  • 4. ● ON-STREAM: Both reservoirs are located on any river /stream ● OFF-STREAM OPEN LOOP - Only one of the reservoirs is located on any river/ stream. ● OFF-STREAM CLOSED LOOP - None of the reservoirs is located on any river/ stream 4 TYPES OF PSP:
  • 6. ● Pumped storage Hydropower + Solar Power/ Wind Power ● Once the solar power is more than the needed, excess is used to pump water from lower reservoir to upper reservoir. ● If there is no solar power generation, the water flows from upper basin to the lower and drives a turbine to produce power. HYBRID PSP CONCEPT:
  • 7. HIGHLIGHTS OF PSP  PSP are also known as ‘Water Battery/ Green Battery’  Long service life of 40-50 years  Offers critical back up during peak hours (Flexible/Reliable)  No residual environment impacts  High economical value: Pumped storage plants works at an efficiency level upto 82 percent  PSP are designed for 06 hours of operations  CEA estimate Potential: 103 GW- ON River, OFF River- Being estimated  As per report by CEA 26.7 GW PSP are required by 2032
  • 8. PRO CONS Flexible and Reliable Long Planning and construction time Long Service Life Specific geographical condition for upper reservoir and lower reservoir Relatively high efficiency upto 85% Large amount of initial investment Most viable option Long Pay back period Reduces energy wastage PRO & CONS:
  • 9. 9 GUIDELINES ISSUED BY M.O.P Dt. 10.04.2023
  • 10. ENABLERS FOR PSP  Environmental Clearances- PSP on existing reservoirs and on off-the-river sites may be treated as a separate category for processing of applications (Appraised under B2 category of MOEF &CC for grant of EC) . As per MOEF&CC draft notification dated 11.10.22 the following criteria will be treated as B2 for grant of EC: 1. Projects which do not attract Forest Clearance/ Wildlife Clearance 2. Projects where no new reservoirs are created 3. Projects where existing reservoirs are not expanded or structurally modified  Cost of Pumping Power- Three factors: 1. Cost of Input Power (Viability depends on availability of affordable input power) 2. Conversion Losses 3. Cost of Storage
  • 11. Value of Peak Power- PSP is capable of offering several services such as: •Spinning Reserves- Generation capacity that is on-line but unloaded and that can respond within 10 minutes to compensate for generation or transmission outages, Reactive Support •Reactive Support- used to provide the voltage levels necessary for active power to do useful work •Black start- the ability of generation to restart parts of the power system to recover from a blackout •Frequency response, faster start up’s and shutdowns which are essential for grid stability
  • 12. MEASURES TAKEN BY GOI FOR PROMOTION OF PSP • States to allot PSP to PSU (Annex-I) • Energy Storage Obligation (Annex-II) • Waiver of ISTS Charges for PSP (Annex-III)- (Extendable to PSP where construction work is awarded by 30.06.2025 • Budgetary Support (Annex-IV) • Timelines for formulation and concurrence of DPR’s for PSP reduced from 900 days to 720 days and CEA shall further reduce timeline for Off-stream closed loop PSP and PSP on existing hydro projects (Where one reservoir is available) • Since No tariff/ financial evaluation by CEA for tariff based Competitive bidding, concurrence reduced from 150 days to 75 days. For other mode of award concurrence reduced from 150 days to 125 days. • Central Government will notify a benchmark tariff of storage for investment decisions
  • 13. BENEFITS TO BE EXTENDED BY STATE • No upfront fee shall be charged by state government • State Government shall consider reimbursement of SGST on PSP project components. • States may exempt Stamp duty and Registration fee for land to be acquired by off-the-river PSP • Government land may be provided at a concessional rate to the developers on annual lease rent basis. • To avoid double taxation, Electricity Duty and Cross subsidy charges shall not be applicable for Pumping power and may be levied on final consumption of electricity • No requirement of Local Area Development fund
  • 14. ALLOTMENT OF PSP PROJECTS State Government may allot project sites to developers in the following manner: 1. On Nomination Basis to CPSU/SPSU: -States may award projects directly to PSU on nomination basis - Award of EPC shall be through Competitive Bidding 2. Allotment through Competitive Bidding: - May be allotted to Private developers by two stage competitive bidding Stage 1: Pre-qualification based on financial strength, experience, turnover, ability to meet performance guarantees Stage 2: Bids to be called on quantifiable parameters such as concession period of project or any other parameter as specified by Central/State Govt. For above two modes: • Home state shall have right of first refusal upto 80% of Project Capacity and developer is free to sell power in any mode • Tariff shall be fixed by appropriate commission u/s 62 of elec act 2003,
  • 15. 3. Allotment through Tariff Based Competitive Bidding: May be awarded to a developer in TBCB mode:  Survey & Investigation and Prep of DPR may be given to SPV under State/Central PSU  SPV responsible for Pre-construction activities such as Project Report, Land Acquisition, Environment & Forest Clearance etc.  DPR may be subsequently bid out for construction and SPV transferred to the successful bidder on the basis of :  COMPOSITE TARIFF (including Cost of Input Power)- Input power arranged by developer  TARIFF FOR STORAGE ON MWh BASIS: Input Power Arranged by the procurer of the storage Capacity  Appropriate commission shall adopt the tariff u/s 63 of Electricity Act, 2003 4. Self Identified Off-Stream Pumped Storage Projects:  Developers may also identify potential off stream sites where PSP can be constructed  Allotment from state government not required  All statutory clearances need to be obtained from central/state agencies before construction  All concessions would be provided
  • 16. MARKET REFORMS/ CONSIDERATIONS:  Timeline: Start of Construction within 02 years from the date of allotment, relaxation of 01 year where delay is due to FC & EC.  Appropriate commission shall ensure monetization of services offered by PSP such as Spinning reserves, ramping support, black start etc  Appropriate commission shall notify Peak and Off-Peak tariffs for generation to provide appropriate pricing signal to peak and base load generating plants  PSP allowed to participate in all market segments of Power exchange including High price segment of Day Ahead Market (HP-DAM)
  • 17.  During monsoon- 80% Power to home state at secondary tariff fixed by CERC. Remaining 20 % can be sold  In case contracted capacity is not fully utilized by agency, developer is free to transfer usage of capacity to other interested consumers. Gains to be shared with original beneficiary in ratio of 50:50  Financial institutions like PFC, REC and IREDA shall treat PSP at par with other renewable energy projects while extending loans of 20-25 years . Debt equity ratio can be upto 80:20  Green Finance: PSP may be supported through concessional climate finance. Sovereign green bonds issues for mobilizing resources for green infrastructure as a part of the government’s overall market borrowings may be deployed
  • 18. Annexure-II MOP Letter 22.07.2022 (RPO & ENERGY STORAGE OBLIGATION Trajectory 2029-30):  Large Hydro Projects (LHP’s) including PSP>25 MW as a part of RE.  LHP’s commissioned after 08.03.2019 will be considered for RPO through a separate obligation i.e Hydro Power Purchase Obligation (HPO).  RPO shall be calculated in energy terms as a percentage of total consumption of electricity.  Wind RPO shall be met only by energy produced from Wind Power Plants commissioned after 31st Mar 2022.  Renewable Energy Certificate mechanism corresponding to Hydro Power to be developed by CERC to facilitate compliance of HPO would have a capping price of Rs 5.50/Unit from 08.03.20190 to 31.03.2021 and with an annual escalation @ 5% thereafter.
  • 19. RENEWABLE PURCHASE OBLIGATION TRAJECTORY 2029-30 YEAR WIND RPO HPO OTHER RPO TOTAL RPO 2022-23 0.81% 0.35% 23.44% 24.6% 2023-24 1.6% 0.66% 24.81% 27.07% 2024-25 2.46% 1.08% 26.37% 29.91% 2025-26 3.36% 1.48% 28.17% 33.01% 2026-27 4.29% 1.8% 29.86% 35.95% 2027-28 5.23% 2.16% 31.43% 38.82% 2028-29 6.16% 2.51% 32.69% 41.36% 2029-30 6.94% 2.82% 33.57% 43.33%
  • 20. ENERGY STORAGE OBLIGATION  Shall be calculated in energy terms as a percentage of total consumption of electricity- Subject to fulfillment of condition that at least 85% of electricity stored is procured from RE Source  POSOCO will maintain data related to compliance of RPO obligations FY Storage (On Energy basis) 2023-24 1% 2024-25 1.50% 2025-26 2% 2026-27 2.50% 2027-28 3% 2028-29 3.50% 2029-30 4%
  • 21. Annexure-III MOP Letter 23.11.2023 (WAIVER OF ISTS):  For Solar, Wind, Hydro PSP and BESS Projects commissioned upto 30.06.2025, the waiver of ISTS charges shall be applicable • At least 51% of electricity requirement for pumping water at PSP/ Batter charging at BESS is from Solar/Wind • Electricity Generated/ Supplied by PSP & BESS • For Green Hydrogen Plants commissioned upto 30.06.2025- Hydrogen produced using electricity from SOLAR/WIND/PSP/ BESS • ISTS (Inter state transmission system) • Waiver shall be applicable for a period of 25 years for solar, wind and hydro PSP or for a period of 12 Years for BESS • Waiver is for ISTS charges and not for losses. Projects Commissioned before 30.06.2025 No ISTS Charges Applicable 01.07.2025 30.06.2026 25 % 01.07.2026 30.06.2027 50 % 01.07.2027 30.06.2028 75 % 01.07.2028 Onwards 100 %
  • 22. Annexure-IV MOP letter 28.09.2021 Budgetary Support towards Cost of Enabling Infrastructure i/e Roads, Bridges  Shall be provided for project starting construction after 08.03.2019  Budgetary support would be provided after appraisal/ approval of each project by PIB/CCEA (Cabinet Committee on economic affairs) through MOP  Limit is 1.5 Cr/MW upto 200 MW and 1.0 Cr/MW for projects above 200 MW  Will be provided as reimbursement after achieving milestones  In-Principle approval of MOP is required for budgetary support  Procedure- After DPR concurrence by State Govt/CEA (Annex-I) to be submitted to CEA
  • 23. Eligibility:  Cap>25MW concurred either by CEA or State Government wherein LOA is issued after 08.03.2019  All roads and bridges required to connect major components like DAM, Power House, Adits (Tunnel), Surge Shafts, Pressure shafts, TRT (tunnel for return water to tank) etc of the project to state/ national highway including strengthening / widening shall be considered for budgetary support  For Construction of Road/Bridges (Land Acquisition Cost/ All statutory taxes, levies, duties, cess shall be included in budgetary support)