SlideShare una empresa de Scribd logo
1 de 49
1
Chapter 7Chapter 7
Project Cost ManagementProject Cost Management
2
The Importance of Project CostThe Importance of Project Cost
ManagementManagement
• IT projects have a poor track record for meeting
cost goals
• Average cost overrun from 1995 CHAOS study
was 189% of the original estimates; improved to
145% in the 2001 study
• In 1995, cancelled IT projects cost the U.S. over
$81 billion
3
What is Cost and Project CostWhat is Cost and Project Cost
Management?Management?
• Cost is a resource sacrificed or foregone to
achieve a specific objective or something given
up in exchange
• Costs are usually measured in monetary units
like dollars
• Project cost management includes the processes
required to ensure that the project is completed
within an approved budget
4
Project Cost ManagementProject Cost Management
ProcessesProcesses
• Cost Estimating - developing an approximation
of the costs of the resources needed to complete
project activities.
• Cost Budgeting - aggregating the estimated costs
of individual activities or work packages to
establish a cost baseline.
• Cost Control - influencing the factors that create
cost variances and controlling changes to the
project budget.
5
Project Cost ManagementProject Cost Management
• Project Cost Management is primarily concerned
with the cost of the resources needed to complete
schedule activities.
• Project Cost Management should also consider
the effect of project decisions on the cost of using,
maintaining, and supporting the product, service,
or result of the project.
6
7
8
Cost EstimatingCost Estimating
• Estimating schedule activity costs involves
developing an approximation of the costs of the
resources needed to complete each schedule
activity.
• Cost estimating includes identifying and
considering various costing alternatives.
• Cost estimates are generally expressed in units
of currency (dollars, euro, yen, etc.) to facilitate
comparisons both within and across projects.
9
Cost Estimating contd.Cost Estimating contd.
• If the performing organization does not have
formally trained project cost estimators, then the
project team will need to supply both the
resources and the expertise to perform project
cost estimating activities.
10
11
Cost Estimating: InputsCost Estimating: Inputs
1. Enterprise Environmental Factors
1. Marketplace conditions.
2. Commercial databases.
2. Organizational Process Assets
1. Cost estimating policies.
2. Cost estimating templates.
3. Historical information.
4. Project files.
5. Project team knowledge.
6. Lessons learned.
12
Cost Estimating: Inputs contd.Cost Estimating: Inputs contd.
3. Project Scope Statement
4. Work Breakdown Structure
5. WBS Dictionary
6. Project Management Plan
13
Cost Estimating: Tools andCost Estimating: Tools and
TechniquesTechniques
1. Analogous Estimating
– using the actual cost of previous, similar projects as the
basis for estimating the cost of the current project.
1. Determine Resource Cost Rates
– The person determining the rates or the group preparing the
estimates must know the unit cost rates, such as staff cost
per hour and bulk material cost per cubic yard, for each
resource to estimate schedule activity costs.
1. Bottom-up Estimating
– involves estimating the cost of individual work packages or
individual schedule activities with the lowest level of
detail.
14
Cost Estimating: Tools andCost Estimating: Tools and
Techniques contd.Techniques contd.
4. Parametric Estimating
– Is a technique that uses a statistical relationship
between historical data and other variables (e.g.
lines of code in software development, required
labor hours) to calculate a cost estimate for a
schedule activity resource.
4. Project Management Software
– such as cost estimating software applications,
computerized spreadsheets, and simulation and
statistical tools, are widely used to assist with cost
estimating.
4. Vendor Bid Analysis
15
Cost Estimating: Tools andCost Estimating: Tools and
Techniques contd.Techniques contd.
7. Reserve Analysis
– Many cost estimators include reserves, also called
contingency allowances, as costs in many schedule activity
cost estimates.
– Contingency reserves are estimated costs to be used at the
discretion of the project manager to deal with anticipated,
but not certain, events
7. Cost of Quality
– Cost of quality (Section 8.1.2.4) can also be used to
prepare the schedule activity cost estimate.
16
Cost Estimating: OutputsCost Estimating: Outputs
1. Activity Cost Estimates
– is a quantitative assessment of the likely costs of the
resources required to complete schedule activities.
1. Activity Cost Estimate Supporting Detail
– The amount and type of additional details supporting the
schedule activity cost estimate vary by application area.
Supporting detail for the activity cost estimates should
include:
• Description of the schedule activity/s project scope of work
• Documentation of the basis for the estimate (i.e., how it was
developed)
• Documentation of any assumptions made
• Documentation of any constraints
• Indication of the range of possible estimates (e.g., $10,000 (-10% /
+15%) to indicate that the item is expected to cost between $9,000
and $11,500).
17
Cost Estimating: Outputs contd.Cost Estimating: Outputs contd.
3. Requested Changes
– The Cost Estimating process may generate requested
changes that may affect the cost management plan,
activity resource requirements, and other
components of the project management plan.
3. Cost Management Plan (Updates)
– If approved change requests result from the Cost
Estimating process, then the cost management plan
component of the project management plan is
updated if those approved changes impact the
management of costs.
18
Cost BudgetingCost Budgeting
• Involves aggregating the estimated costs of
individual schedule activities or work packages to
establish a total cost baseline for measuring
project performance.
• The project scope statement provides the
summary budget.
• However, schedule activity or work package cost
estimates are prepared prior to the detailed budget
requests and work authorization.
19
20
Cost Budgeting: InputsCost Budgeting: Inputs
1. Project Scope Statement
2. Work Breakdown Structure
3. WBS Dictionary
4. Activity Cost Estimates
5. Activity Cost Estimate Supporting Detail
6. Project Schedule
7. Resource Calendars
8. Contract
9. Cost Management Plan
21
Cost Budgeting: Tools andCost Budgeting: Tools and
TechniquesTechniques
1. Cost Aggregation
– Schedule activity cost estimates are aggregated by work packages in
accordance with the WBS.
1. Reserve Analysis
– Reserve analysis (Section 11.6.2.5) establishes contingency reserves,
such as the management contingency reserve, that are allowances for
unplanned, but potentially required, changes. Such changes may result
from risks identified in the risk register
1. Parametric Estimating
– involves using project characteristics (parameters) in a mathematical
model to predict total project costs.
1. Funding Limit Reconciliation
– the expenditure of funds is reconciled with the funding limits set by the
customer or performing organization on the disbursement of funds for
the project.
22
Cost Budgeting: OutputsCost Budgeting: Outputs
1. Cost Baseline
– The cost baseline is a time-phased budget that is
used as a basis against which to measure, monitor,
and control overall cost performance on the
project.
1. Project Funding Requirements
– Funding requirements, total and periodic (e.g.,
annual or quarterly), are derived from the cost
baseline and can be established to exceed, usually
by a margin, to allow for either early progress or
cost overruns.
23
24
Cost Budgeting: Outputs contd.Cost Budgeting: Outputs contd.
3. Cost Management Plan (Updates)
4. Requested Changes
25
Cost ControlCost Control
• Project cost control includes:
– Influencing the factors that create changes to the cost
baseline
– Ensuring requested changes are agreed upon
– Managing the actual changes when and as they occur
– Assuring that potential cost overruns do not exceed the
authorized funding periodically and in total for the project
– Monitoring cost performance to detect and understand
variances from the cost baseline
– Recording all appropriate changes accurately against the cost
baseline
– Preventing incorrect, inappropriate, or unapproved changes
from being included in the reported cost or resource usage
– Informing appropriate stakeholders of approved changes
– Acting to bring expected cost overruns within acceptable
limits.
26
27
Cost Control: InputsCost Control: Inputs
1. Cost Baseline
2. Project Funding Requirements
3. Performance Reports
– Performance reports (Section 10.3.3.1) provide information
on cost and resource performance as a result of actual work
progress.
1. Work Performance Information
– pertaining to the status and cost of project activities being
performed is collected. This information includes, but is
not limited to:
• Deliverables that have been completed and those not yet completed
• Costs authorized and incurred
• Estimates to complete the schedule activities
• Percent physically complete of the schedule activities.
1. Approved Change Requests
2. Project Management Plan
28
Cost Control: Tools and TechniquesCost Control: Tools and Techniques
1. Cost Change Control System
– A cost change control system, documented in the cost
management plan, defines the procedures by which the cost
baseline can be changed.
1. Performance Measurement Analysis
– Performance measurement techniques help to assess the
magnitude of any variances that will invariably occur.
– The earned value technique (EVT) compares the
cumulative value of the budgeted cost of work performed
(earned) at the original allocated budget amount to both the
budgeted cost of work scheduled (planned) and to the
actual cost of work performed (actual).
29
Performance Measurement AnalysisPerformance Measurement Analysis
• The earned value technique involves developing these
key values for each schedule activity, work package, or
control account:
– Planned value (PV). PV is the budgeted cost for the work
scheduled to be completed on an activity or WBS component
up to a given point in time.
– Earned value (EV). EV is the budgeted amount for the work
actually completed on the schedule activity or WBS
component during a given time period.
– Actual cost (AC). AC is the total cost incurred in
accomplishing work on the schedule activity or WBS
component during a given time period. This AC must
correspond in definition and coverage to whatever was
budgeted for the PV and the EV (e.g., direct hours only, direct
costs only, or all costs including indirect costs).
30
Performance MeasurementPerformance Measurement
Analysis contd.Analysis contd.
– Estimate to complete (ETC) and estimate at
completion (EAC).
31
Cost variance (CV).Cost variance (CV).
• CV equals earned value (EV) minus actual cost
(AC). The cost variance at the end of the project
will be the difference between the budget at
completion (BAC) and the actual amount spent.
Formula: CV= EV-AC
32
Schedule variance (SV).Schedule variance (SV).
• SV equals earned value (EV) minus planned
value (PV). Schedule variance will ultimately
equal zero when the project is completed
because all of the planned values will have been
earned. Formula: SV = EV-PV
33
Performance MeasurementPerformance Measurement
Analysis contd.Analysis contd.
• These two values, the CV and SV, can be
converted to efficiency indicators to reflect the
cost and schedule performance of any project.
34
Cost performance index (CPI).Cost performance index (CPI).
• A CPI value less than 1.0 indicates a cost
overrun of the estimates. A CPI value greater
than 1.0 indicates a cost underrun of the
estimates. CPI equals the ratio of the EV to the
AC. The CPI is the most commonly used cost-
efficiency indicator. Formula: CPI = EV/AC
35
Cumulative CPI (CPICumulative CPI (CPICC
).).
• The cumulative CPI is widely used to forecast
project costs at completion. CPIC
equals the sum
of the periodic earned values (EVC
) divided by
the sum of the individual actual costs (ACC
).
Formula: CPIC
= EVC
/ACC
36
Schedule performance index (SPI)Schedule performance index (SPI)
• The SPI is used, in addition to the schedule
status (Section 6.6.2.1), to predict the
completion date and is sometimes used in
conjunction with the CPI to forecast the project
completion estimates. SPI equals the ratio of the
EV to the PV.
Formula: SPI = EV/PV
37
38
Cost Control: Tools andCost Control: Tools and
TechniquesTechniques
3. Forecasting
– Forecasting includes making estimates or predictions of
conditions in the project’s future based on information and
knowledge available at the time of the forecast.
– Forecasting techniques help to assess the cost or the amount
of work to complete schedule activities, which is called the
EAC.
– Forecasting techniques also help to determine the ETC,
which is the estimate for completing the remaining work for
a schedule activity, work package, or control account.
39
ETC based on new estimateETC based on new estimate
• ETC equals the revised estimate for the work
remaining, as determined by the performing
organization. This more accurate and comprehensive
completion estimate is an independent, non-calculated
estimate to complete for all the work remaining, and
considers the performance or production of the
resource(s) to date.
• Alternatively, to calculate ETC using earned value
data, one of two formulas is typically used:
– ETC based on atypical variances.
– ETC based on typical variances.
40
ETC based on atypical variances.ETC based on atypical variances.
• This approach is most often used when current
variances are seen as atypical and the project
management team expectations are that similar
variances will not occur in the future. ETC
equals the BAC minus the cumulative earned
value to date (EVC
).
Formula: ETC = (BAC - EVC
)
41
ETC based on typical variances.ETC based on typical variances.
• This approach is most often used when current
variances are seen as typical of future variances.
ETC equals the BAC minus the cumulative EVC
(the remaining PV) divided by the cumulative
cost performance index (CPIC
).
Formula: ETC = (BAC - EVC
) / CPIC
42
EAC using a new estimate.EAC using a new estimate.
• EAC equals the actual costs to date (ACC
) plus a
new ETC that is provided by the performing
organization. This approach is most often used
when past performance shows that the original
estimating assumptions were fundamentally
flawed or that they are no longer relevant due to
a change in conditions.
Formula: EAC = ACC
+ ETC
43
Forecasting contd.Forecasting contd.
• The two most common forecasting techniques
for calculating EAC using earned value data are
some variation of:
– EAC using remaining budget.
– EAC using CPIC.
44
EAC using remaining budgetEAC using remaining budget
• EAC equals ACC
plus the budget required to
complete the remaining work, which is the
budget at completion (BAC) minus the earned
value (EV). This approach is most often used
when current variances are seen as atypical and
the project management team expectations are
that similar variances will not occur in the
future.
Formula: EAC = ACC
+BAC - EVC
45
EAC using CPIEAC using CPICC
• EAC equals actual costs to date (ACC
) plus the
budget required to complete the remaining
project work, which is the BAC minus the EV,
modified by a performance factor (often the
CPIC
). This approach is most often used when
current variances are seen as typical of future
variances.
Formula: EAC = ACC
+ ((BAC - EVC
) / CPIC
)
46
Cost Control: Tools andCost Control: Tools and
Techniques contd.Techniques contd.
4. Project Performance Reviews
– Performance reviews compare cost performance
over time, schedule activities or work packages
overrunning and under running budget (planned
value), milestones due, and milestones met.
– performance-reporting techniques:
• Variance analysis.
• Trend analysis.
• Earned value technique.
47
Cost Control: Tools andCost Control: Tools and
Techniques contd.Techniques contd.
5. Project Management Software
– Project management software, such as
computerized spreadsheets, is often used to
monitor PV versus AC, and to forecast the effects
of changes or variances.
5. Variance Management
– The cost management plan (Section 7.1.3.4)
describes how cost variances will be managed, for
example, having different responses to major or
minor problems.
48
Cost Control: OutputsCost Control: Outputs
1. Cost Estimates (Updates)
2. Cost Baseline (Updates)
3. Performance Measurements
4. Forecasted Completion
5. Requested Changes
6. Recommended Corrective Actions
7. Organizational Process Assets (Updates)
8. Project Management Plan (Updates)
49
End Chapter 7End Chapter 7

Más contenido relacionado

La actualidad más candente

Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elementsharoldtaylor1113
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012satish526
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Managementjonash99
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementReetesh Gupta
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measuresPavan Kumar
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr. Pramod Deshpande
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 

La actualidad más candente (20)

Project Execution and PM Elements
Project Execution and PM ElementsProject Execution and PM Elements
Project Execution and PM Elements
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measures
 
Project management
Project managementProject management
Project management
 
095 Project Cycle Management
095 Project Cycle Management095 Project Cycle Management
095 Project Cycle Management
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
Project engineer
Project engineerProject engineer
Project engineer
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 

Similar a 7 cost managmenet

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
Cost & value management
Cost & value management Cost & value management
Cost & value management kamariya keyur
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxbjohn46
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdfAliaaAl4
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.pptMohamadAGhareb
 

Similar a 7 cost managmenet (20)

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
Cost & value management
Cost & value management Cost & value management
Cost & value management
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Cost managment
Cost managmentCost managment
Cost managment
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Project cost management
Project cost management Project cost management
Project cost management
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdf
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.ppt
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 

Más de Ala Ibrahim

06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
05 project scope management
05  project scope management05  project scope management
05 project scope managementAla Ibrahim
 
04 project integration management
04  project integration management04  project integration management
04 project integration managementAla Ibrahim
 
03 project management processes for a project
03  project management processes for a project03  project management processes for a project
03 project management processes for a projectAla Ibrahim
 
02 project life cyce and organization
02  project life cyce and organization02  project life cyce and organization
02 project life cyce and organizationAla Ibrahim
 

Más de Ala Ibrahim (6)

06 project time management
06  project time management06  project time management
06 project time management
 
05 project scope management
05  project scope management05  project scope management
05 project scope management
 
04 project integration management
04  project integration management04  project integration management
04 project integration management
 
03 project management processes for a project
03  project management processes for a project03  project management processes for a project
03 project management processes for a project
 
02 project life cyce and organization
02  project life cyce and organization02  project life cyce and organization
02 project life cyce and organization
 
01 introduction
01  introduction01  introduction
01 introduction
 

Último

SensoDat: Simulation-based Sensor Dataset of Self-driving Cars
SensoDat: Simulation-based Sensor Dataset of Self-driving CarsSensoDat: Simulation-based Sensor Dataset of Self-driving Cars
SensoDat: Simulation-based Sensor Dataset of Self-driving CarsChristian Birchler
 
Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)
Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)
Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)jennyeacort
 
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company OdishaBalasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odishasmiwainfosol
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024StefanoLambiase
 
Introduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdfIntroduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdfFerryKemperman
 
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...Cizo Technology Services
 
Powering Real-Time Decisions with Continuous Data Streams
Powering Real-Time Decisions with Continuous Data StreamsPowering Real-Time Decisions with Continuous Data Streams
Powering Real-Time Decisions with Continuous Data StreamsSafe Software
 
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...Angel Borroy López
 
Unveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsUnveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsAhmed Mohamed
 
Unveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesUnveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesŁukasz Chruściel
 
Ahmed Motair CV April 2024 (Senior SW Developer)
Ahmed Motair CV April 2024 (Senior SW Developer)Ahmed Motair CV April 2024 (Senior SW Developer)
Ahmed Motair CV April 2024 (Senior SW Developer)Ahmed Mater
 
Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...
Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...
Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...OnePlan Solutions
 
Simplifying Microservices & Apps - The art of effortless development - Meetup...
Simplifying Microservices & Apps - The art of effortless development - Meetup...Simplifying Microservices & Apps - The art of effortless development - Meetup...
Simplifying Microservices & Apps - The art of effortless development - Meetup...Rob Geurden
 
How To Manage Restaurant Staff -BTRESTRO
How To Manage Restaurant Staff -BTRESTROHow To Manage Restaurant Staff -BTRESTRO
How To Manage Restaurant Staff -BTRESTROmotivationalword821
 
MYjobs Presentation Django-based project
MYjobs Presentation Django-based projectMYjobs Presentation Django-based project
MYjobs Presentation Django-based projectAnoyGreter
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmSujith Sukumaran
 
Xen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfXen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfStefano Stabellini
 
Comparing Linux OS Image Update Models - EOSS 2024.pdf
Comparing Linux OS Image Update Models - EOSS 2024.pdfComparing Linux OS Image Update Models - EOSS 2024.pdf
Comparing Linux OS Image Update Models - EOSS 2024.pdfDrew Moseley
 
Post Quantum Cryptography – The Impact on Identity
Post Quantum Cryptography – The Impact on IdentityPost Quantum Cryptography – The Impact on Identity
Post Quantum Cryptography – The Impact on Identityteam-WIBU
 

Último (20)

SensoDat: Simulation-based Sensor Dataset of Self-driving Cars
SensoDat: Simulation-based Sensor Dataset of Self-driving CarsSensoDat: Simulation-based Sensor Dataset of Self-driving Cars
SensoDat: Simulation-based Sensor Dataset of Self-driving Cars
 
Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)
Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)
Call Us🔝>༒+91-9711147426⇛Call In girls karol bagh (Delhi)
 
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company OdishaBalasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
Balasore Best It Company|| Top 10 IT Company || Balasore Software company Odisha
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
 
Introduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdfIntroduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdf
 
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
Global Identity Enrolment and Verification Pro Solution - Cizo Technology Ser...
 
Powering Real-Time Decisions with Continuous Data Streams
Powering Real-Time Decisions with Continuous Data StreamsPowering Real-Time Decisions with Continuous Data Streams
Powering Real-Time Decisions with Continuous Data Streams
 
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
Alfresco TTL#157 - Troubleshooting Made Easy: Deciphering Alfresco mTLS Confi...
 
Unveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsUnveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML Diagrams
 
Unveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesUnveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New Features
 
Ahmed Motair CV April 2024 (Senior SW Developer)
Ahmed Motair CV April 2024 (Senior SW Developer)Ahmed Motair CV April 2024 (Senior SW Developer)
Ahmed Motair CV April 2024 (Senior SW Developer)
 
Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...
Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...
Tech Tuesday - Mastering Time Management Unlock the Power of OnePlan's Timesh...
 
Simplifying Microservices & Apps - The art of effortless development - Meetup...
Simplifying Microservices & Apps - The art of effortless development - Meetup...Simplifying Microservices & Apps - The art of effortless development - Meetup...
Simplifying Microservices & Apps - The art of effortless development - Meetup...
 
How To Manage Restaurant Staff -BTRESTRO
How To Manage Restaurant Staff -BTRESTROHow To Manage Restaurant Staff -BTRESTRO
How To Manage Restaurant Staff -BTRESTRO
 
MYjobs Presentation Django-based project
MYjobs Presentation Django-based projectMYjobs Presentation Django-based project
MYjobs Presentation Django-based project
 
Hot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Patel Nagar🔝 9953056974 🔝 escort Service
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalm
 
Xen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfXen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdf
 
Comparing Linux OS Image Update Models - EOSS 2024.pdf
Comparing Linux OS Image Update Models - EOSS 2024.pdfComparing Linux OS Image Update Models - EOSS 2024.pdf
Comparing Linux OS Image Update Models - EOSS 2024.pdf
 
Post Quantum Cryptography – The Impact on Identity
Post Quantum Cryptography – The Impact on IdentityPost Quantum Cryptography – The Impact on Identity
Post Quantum Cryptography – The Impact on Identity
 

7 cost managmenet

  • 1. 1 Chapter 7Chapter 7 Project Cost ManagementProject Cost Management
  • 2. 2 The Importance of Project CostThe Importance of Project Cost ManagementManagement • IT projects have a poor track record for meeting cost goals • Average cost overrun from 1995 CHAOS study was 189% of the original estimates; improved to 145% in the 2001 study • In 1995, cancelled IT projects cost the U.S. over $81 billion
  • 3. 3 What is Cost and Project CostWhat is Cost and Project Cost Management?Management? • Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange • Costs are usually measured in monetary units like dollars • Project cost management includes the processes required to ensure that the project is completed within an approved budget
  • 4. 4 Project Cost ManagementProject Cost Management ProcessesProcesses • Cost Estimating - developing an approximation of the costs of the resources needed to complete project activities. • Cost Budgeting - aggregating the estimated costs of individual activities or work packages to establish a cost baseline. • Cost Control - influencing the factors that create cost variances and controlling changes to the project budget.
  • 5. 5 Project Cost ManagementProject Cost Management • Project Cost Management is primarily concerned with the cost of the resources needed to complete schedule activities. • Project Cost Management should also consider the effect of project decisions on the cost of using, maintaining, and supporting the product, service, or result of the project.
  • 6. 6
  • 7. 7
  • 8. 8 Cost EstimatingCost Estimating • Estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity. • Cost estimating includes identifying and considering various costing alternatives. • Cost estimates are generally expressed in units of currency (dollars, euro, yen, etc.) to facilitate comparisons both within and across projects.
  • 9. 9 Cost Estimating contd.Cost Estimating contd. • If the performing organization does not have formally trained project cost estimators, then the project team will need to supply both the resources and the expertise to perform project cost estimating activities.
  • 10. 10
  • 11. 11 Cost Estimating: InputsCost Estimating: Inputs 1. Enterprise Environmental Factors 1. Marketplace conditions. 2. Commercial databases. 2. Organizational Process Assets 1. Cost estimating policies. 2. Cost estimating templates. 3. Historical information. 4. Project files. 5. Project team knowledge. 6. Lessons learned.
  • 12. 12 Cost Estimating: Inputs contd.Cost Estimating: Inputs contd. 3. Project Scope Statement 4. Work Breakdown Structure 5. WBS Dictionary 6. Project Management Plan
  • 13. 13 Cost Estimating: Tools andCost Estimating: Tools and TechniquesTechniques 1. Analogous Estimating – using the actual cost of previous, similar projects as the basis for estimating the cost of the current project. 1. Determine Resource Cost Rates – The person determining the rates or the group preparing the estimates must know the unit cost rates, such as staff cost per hour and bulk material cost per cubic yard, for each resource to estimate schedule activity costs. 1. Bottom-up Estimating – involves estimating the cost of individual work packages or individual schedule activities with the lowest level of detail.
  • 14. 14 Cost Estimating: Tools andCost Estimating: Tools and Techniques contd.Techniques contd. 4. Parametric Estimating – Is a technique that uses a statistical relationship between historical data and other variables (e.g. lines of code in software development, required labor hours) to calculate a cost estimate for a schedule activity resource. 4. Project Management Software – such as cost estimating software applications, computerized spreadsheets, and simulation and statistical tools, are widely used to assist with cost estimating. 4. Vendor Bid Analysis
  • 15. 15 Cost Estimating: Tools andCost Estimating: Tools and Techniques contd.Techniques contd. 7. Reserve Analysis – Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. – Contingency reserves are estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events 7. Cost of Quality – Cost of quality (Section 8.1.2.4) can also be used to prepare the schedule activity cost estimate.
  • 16. 16 Cost Estimating: OutputsCost Estimating: Outputs 1. Activity Cost Estimates – is a quantitative assessment of the likely costs of the resources required to complete schedule activities. 1. Activity Cost Estimate Supporting Detail – The amount and type of additional details supporting the schedule activity cost estimate vary by application area. Supporting detail for the activity cost estimates should include: • Description of the schedule activity/s project scope of work • Documentation of the basis for the estimate (i.e., how it was developed) • Documentation of any assumptions made • Documentation of any constraints • Indication of the range of possible estimates (e.g., $10,000 (-10% / +15%) to indicate that the item is expected to cost between $9,000 and $11,500).
  • 17. 17 Cost Estimating: Outputs contd.Cost Estimating: Outputs contd. 3. Requested Changes – The Cost Estimating process may generate requested changes that may affect the cost management plan, activity resource requirements, and other components of the project management plan. 3. Cost Management Plan (Updates) – If approved change requests result from the Cost Estimating process, then the cost management plan component of the project management plan is updated if those approved changes impact the management of costs.
  • 18. 18 Cost BudgetingCost Budgeting • Involves aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for measuring project performance. • The project scope statement provides the summary budget. • However, schedule activity or work package cost estimates are prepared prior to the detailed budget requests and work authorization.
  • 19. 19
  • 20. 20 Cost Budgeting: InputsCost Budgeting: Inputs 1. Project Scope Statement 2. Work Breakdown Structure 3. WBS Dictionary 4. Activity Cost Estimates 5. Activity Cost Estimate Supporting Detail 6. Project Schedule 7. Resource Calendars 8. Contract 9. Cost Management Plan
  • 21. 21 Cost Budgeting: Tools andCost Budgeting: Tools and TechniquesTechniques 1. Cost Aggregation – Schedule activity cost estimates are aggregated by work packages in accordance with the WBS. 1. Reserve Analysis – Reserve analysis (Section 11.6.2.5) establishes contingency reserves, such as the management contingency reserve, that are allowances for unplanned, but potentially required, changes. Such changes may result from risks identified in the risk register 1. Parametric Estimating – involves using project characteristics (parameters) in a mathematical model to predict total project costs. 1. Funding Limit Reconciliation – the expenditure of funds is reconciled with the funding limits set by the customer or performing organization on the disbursement of funds for the project.
  • 22. 22 Cost Budgeting: OutputsCost Budgeting: Outputs 1. Cost Baseline – The cost baseline is a time-phased budget that is used as a basis against which to measure, monitor, and control overall cost performance on the project. 1. Project Funding Requirements – Funding requirements, total and periodic (e.g., annual or quarterly), are derived from the cost baseline and can be established to exceed, usually by a margin, to allow for either early progress or cost overruns.
  • 23. 23
  • 24. 24 Cost Budgeting: Outputs contd.Cost Budgeting: Outputs contd. 3. Cost Management Plan (Updates) 4. Requested Changes
  • 25. 25 Cost ControlCost Control • Project cost control includes: – Influencing the factors that create changes to the cost baseline – Ensuring requested changes are agreed upon – Managing the actual changes when and as they occur – Assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project – Monitoring cost performance to detect and understand variances from the cost baseline – Recording all appropriate changes accurately against the cost baseline – Preventing incorrect, inappropriate, or unapproved changes from being included in the reported cost or resource usage – Informing appropriate stakeholders of approved changes – Acting to bring expected cost overruns within acceptable limits.
  • 26. 26
  • 27. 27 Cost Control: InputsCost Control: Inputs 1. Cost Baseline 2. Project Funding Requirements 3. Performance Reports – Performance reports (Section 10.3.3.1) provide information on cost and resource performance as a result of actual work progress. 1. Work Performance Information – pertaining to the status and cost of project activities being performed is collected. This information includes, but is not limited to: • Deliverables that have been completed and those not yet completed • Costs authorized and incurred • Estimates to complete the schedule activities • Percent physically complete of the schedule activities. 1. Approved Change Requests 2. Project Management Plan
  • 28. 28 Cost Control: Tools and TechniquesCost Control: Tools and Techniques 1. Cost Change Control System – A cost change control system, documented in the cost management plan, defines the procedures by which the cost baseline can be changed. 1. Performance Measurement Analysis – Performance measurement techniques help to assess the magnitude of any variances that will invariably occur. – The earned value technique (EVT) compares the cumulative value of the budgeted cost of work performed (earned) at the original allocated budget amount to both the budgeted cost of work scheduled (planned) and to the actual cost of work performed (actual).
  • 29. 29 Performance Measurement AnalysisPerformance Measurement Analysis • The earned value technique involves developing these key values for each schedule activity, work package, or control account: – Planned value (PV). PV is the budgeted cost for the work scheduled to be completed on an activity or WBS component up to a given point in time. – Earned value (EV). EV is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period. – Actual cost (AC). AC is the total cost incurred in accomplishing work on the schedule activity or WBS component during a given time period. This AC must correspond in definition and coverage to whatever was budgeted for the PV and the EV (e.g., direct hours only, direct costs only, or all costs including indirect costs).
  • 30. 30 Performance MeasurementPerformance Measurement Analysis contd.Analysis contd. – Estimate to complete (ETC) and estimate at completion (EAC).
  • 31. 31 Cost variance (CV).Cost variance (CV). • CV equals earned value (EV) minus actual cost (AC). The cost variance at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. Formula: CV= EV-AC
  • 32. 32 Schedule variance (SV).Schedule variance (SV). • SV equals earned value (EV) minus planned value (PV). Schedule variance will ultimately equal zero when the project is completed because all of the planned values will have been earned. Formula: SV = EV-PV
  • 33. 33 Performance MeasurementPerformance Measurement Analysis contd.Analysis contd. • These two values, the CV and SV, can be converted to efficiency indicators to reflect the cost and schedule performance of any project.
  • 34. 34 Cost performance index (CPI).Cost performance index (CPI). • A CPI value less than 1.0 indicates a cost overrun of the estimates. A CPI value greater than 1.0 indicates a cost underrun of the estimates. CPI equals the ratio of the EV to the AC. The CPI is the most commonly used cost- efficiency indicator. Formula: CPI = EV/AC
  • 35. 35 Cumulative CPI (CPICumulative CPI (CPICC ).). • The cumulative CPI is widely used to forecast project costs at completion. CPIC equals the sum of the periodic earned values (EVC ) divided by the sum of the individual actual costs (ACC ). Formula: CPIC = EVC /ACC
  • 36. 36 Schedule performance index (SPI)Schedule performance index (SPI) • The SPI is used, in addition to the schedule status (Section 6.6.2.1), to predict the completion date and is sometimes used in conjunction with the CPI to forecast the project completion estimates. SPI equals the ratio of the EV to the PV. Formula: SPI = EV/PV
  • 37. 37
  • 38. 38 Cost Control: Tools andCost Control: Tools and TechniquesTechniques 3. Forecasting – Forecasting includes making estimates or predictions of conditions in the project’s future based on information and knowledge available at the time of the forecast. – Forecasting techniques help to assess the cost or the amount of work to complete schedule activities, which is called the EAC. – Forecasting techniques also help to determine the ETC, which is the estimate for completing the remaining work for a schedule activity, work package, or control account.
  • 39. 39 ETC based on new estimateETC based on new estimate • ETC equals the revised estimate for the work remaining, as determined by the performing organization. This more accurate and comprehensive completion estimate is an independent, non-calculated estimate to complete for all the work remaining, and considers the performance or production of the resource(s) to date. • Alternatively, to calculate ETC using earned value data, one of two formulas is typically used: – ETC based on atypical variances. – ETC based on typical variances.
  • 40. 40 ETC based on atypical variances.ETC based on atypical variances. • This approach is most often used when current variances are seen as atypical and the project management team expectations are that similar variances will not occur in the future. ETC equals the BAC minus the cumulative earned value to date (EVC ). Formula: ETC = (BAC - EVC )
  • 41. 41 ETC based on typical variances.ETC based on typical variances. • This approach is most often used when current variances are seen as typical of future variances. ETC equals the BAC minus the cumulative EVC (the remaining PV) divided by the cumulative cost performance index (CPIC ). Formula: ETC = (BAC - EVC ) / CPIC
  • 42. 42 EAC using a new estimate.EAC using a new estimate. • EAC equals the actual costs to date (ACC ) plus a new ETC that is provided by the performing organization. This approach is most often used when past performance shows that the original estimating assumptions were fundamentally flawed or that they are no longer relevant due to a change in conditions. Formula: EAC = ACC + ETC
  • 43. 43 Forecasting contd.Forecasting contd. • The two most common forecasting techniques for calculating EAC using earned value data are some variation of: – EAC using remaining budget. – EAC using CPIC.
  • 44. 44 EAC using remaining budgetEAC using remaining budget • EAC equals ACC plus the budget required to complete the remaining work, which is the budget at completion (BAC) minus the earned value (EV). This approach is most often used when current variances are seen as atypical and the project management team expectations are that similar variances will not occur in the future. Formula: EAC = ACC +BAC - EVC
  • 45. 45 EAC using CPIEAC using CPICC • EAC equals actual costs to date (ACC ) plus the budget required to complete the remaining project work, which is the BAC minus the EV, modified by a performance factor (often the CPIC ). This approach is most often used when current variances are seen as typical of future variances. Formula: EAC = ACC + ((BAC - EVC ) / CPIC )
  • 46. 46 Cost Control: Tools andCost Control: Tools and Techniques contd.Techniques contd. 4. Project Performance Reviews – Performance reviews compare cost performance over time, schedule activities or work packages overrunning and under running budget (planned value), milestones due, and milestones met. – performance-reporting techniques: • Variance analysis. • Trend analysis. • Earned value technique.
  • 47. 47 Cost Control: Tools andCost Control: Tools and Techniques contd.Techniques contd. 5. Project Management Software – Project management software, such as computerized spreadsheets, is often used to monitor PV versus AC, and to forecast the effects of changes or variances. 5. Variance Management – The cost management plan (Section 7.1.3.4) describes how cost variances will be managed, for example, having different responses to major or minor problems.
  • 48. 48 Cost Control: OutputsCost Control: Outputs 1. Cost Estimates (Updates) 2. Cost Baseline (Updates) 3. Performance Measurements 4. Forecasted Completion 5. Requested Changes 6. Recommended Corrective Actions 7. Organizational Process Assets (Updates) 8. Project Management Plan (Updates)
  • 49. 49 End Chapter 7End Chapter 7