SlideShare una empresa de Scribd logo
1 de 208
AXELOS.com
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from
AXELOS Limited.
PRINCE2® Foundation
1
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Learning Objectives
To help you understand PRINCE2 in respect of its:
• Principles, processes, themes, techniques and roles for successful
project management
• Management products that are input and output of the processes.
So that you may:
• Attempt your exam(s) of choice with confidence
• Begin to apply the method, tailoring it to your
projects’ needs.
2
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Course Topics
• Overview, Principles and
Tailoring PRINCE2 to the
project environment (OV)
• Business Case theme (BC)
• Organization theme (OR)
• Quality theme (QU)
• Plans theme (PL)
• Risk theme (RK)
• Change theme (CH)
• Progress theme (PG).
• Starting up a Project process
(SU)
• Initiating a Project process (IP)
• Directing a Project process (DP)
• Managing a Stage Boundary
process (SB)
• Controlling a Stage process
(CS)
• Managing Product Delivery
process (MP)
• Closing a Project process (CP).
3
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Examination Information
Foundation
• Multiple choice questions
• 60 questions per paper
• 33 marks required (out of 60 available) to pass: 55%
• One hour's (60 minutes) duration
• Closed book.
4
PUBLIC
PUBLIC
Overview of PRINCE2
5
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
What is a project
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P3-4
A project is a temporary organization that is created for the
purpose of delivering one or more business products according to
an agreed Business Case
• Characteristics:
• Change
• Temporary
• Cross-functional
• Unique
• Uncertainty.
Six project
variables to control:
• Time
• Cost
• Scope
• Quality
• Risk
• Benefits
6
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Programmes and Projects: Differences
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P217-8, 309
• Programme = A temporary, flexible organization created to co-
ordinate, direct and oversee the implementation of a set of
related projects and activities in order to deliver outcomes and
benefits related to the organization’s strategic objectives.
• Deals with the big, strategic picture
• Is initiated to realize benefits through change
• Proceeds in tranches, with benefits reviews in between.
• PRINCE2 is a method for project management; MSP® is a method for
programme management.
7
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
How does PRINCE2 Help?
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P5, 7
• Provides four integrated elements for successful project
management:
• Principles
• Processes
• Themes
• Tailoring PRINCE2 to the project environment.
• Benefits of using PRINCE2:
• Established best practice – no need to re-invent the wheel
• Flexible, scalable, tailorable, transferable
• Active stakeholder engagement
• Provides consistency across project work
• Promotes continual improvement.
8
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
What are Principles?
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P11-4
• A guiding obligation for good practice
• 7 Principles
• Continued Business Justification
• Learn from Experience
• Defined Roles and Responsibilities
• Manage by Stages
• Manage by Exception
• Focus on Products
• Tailor to Suit the Environment.
9
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Processes
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P113
Starting
up a
Project
Directing a Project
Initiating a
Project
Controlling a
Stage
Managing
Product
Delivery
Managing
Product
Delivery
Directing
Managing
Delivering
Controlling a
Stage
SB SB CP
Pre-Project
Initiation
Stage
Subsequent
Delivery
Stages
Final Stage
10
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Themes
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P17-8
• Aspects of project management that need to be continually
addressed – the Project Manager’s toolbox
• Enable the PRINCE2 processes to be effective - if the process
requires action the Theme provides guidance on how it should be
done
• 7 Themes
• Business Case
• Quality
• Organization
• Plans
• Risk
• Change
• Progress.
12
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
The Project Environment
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P215
• Tailoring - Done by the project team to adapt the method to the
context of a specific project
• Roles and responsibilities to allocate
• Management products to use and how
• Number, length and nature of stages
• Tolerances, reporting and reviewing
• Use of PRINCE2 processes.
13
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Management Products
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P235
• Baseline Management Products
• Define aspects of the project and, once approved, are subject to Change Control,
e.g. Business Case
• Records
• Dynamic management products that maintain information regarding project
progress, e.g. Risk Register
• Reports
• Management products that provide a snapshot of the status of certain aspects of
the project, e.g. Highlight Report
• Records and Reports not subject to Change Control, but other
aspects of Configuration Management still apply, e.g. version control,
safe storage.
14
PUBLIC
PUBLIC
Organization Theme
Who?
15
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Key Concepts
PRINCE2® manual ref: P31
Defined roles and
responsibilities
• A temporary organization…
• Every project needs effective direction, management, control and
communication
• Project’s structure of accountability and responsibilities (the who?)
• Customer/supplier environment
• Roles, NOT jobs.
16
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Customer/Supplier Environment
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P224-7
• Customer – specifies project result and (probably) funds the project
• Supplier – provides resources and skills to produce desired result
• In-house or commercial relationship
17
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Three Projects Interests
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P32
Consider the difference between “stakeholders” and “decision-makers”
Business
User Supplier
The
project
18
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Four Levels of Management
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33
Starting
up a
Project
Directing a Project
Initiating a
Project
Controlling a
Stage
Managing
Product
Delivery
Managing
Product
Delivery
Directing
Managing
Delivering
Controlling
a Stage
SB SB CP
Pre-Project
Initiation
Stage
Subsequent
Delivery Stages
Final Stage
Project Board
Project Manager
Team Manager
Project
management
team
Corporate or Programme Management
19
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Project Management Team Structure
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33
Corporate or programme management
Project Board
Senior User(s) Senior Supplier(s)
Team members
Change Authority
Project Support
Project Manager
Team Manager(s)
Business, User &
Supplier Project
Assurance
Executive
Project
Management
Team
20
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
The Project Board
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P34-5, 269-70
Customer
• Three roles:
• Executive – business interests
• Senior User – user interests
• Senior Supplier – supplier interests.
• Authority and responsibility for the project within the remit of the
project mandate (initially)
• Characteristics:
• Authority
• Credibility
• Ability to delegate
• Availability.
21
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Project Board: Executive
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P35, 270
• Role:
• Final responsibility for the project and its success or failure
• Must ensure that the project has a sound business basis (‘business case’) and
represents value for money throughout the life of the project.
• Responsibilities:
• Chairs the Board and owns the Business Case
• Represents the “business” interests – should this project be done?
• Ensures the Project is delivering against targets and remains focused on
achieving objectives
• Key decision-maker – role cannot be shared.
22
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Role:
• Ensures that requirements are fully specified and agreed before
project delivery begins
• Accountable to the Executive for the delivery of benefits.
Responsibilities:
• Ensures that user resources are made available
• Ensures that the required outcome for the project is clearly specified
and signed-off
• Monitors progress and maintains focus on the deliverables from a
user perspective
• Signs-off completed deliverables against agreed quality criteria
• Resolves user conflicts.
Project Board: Senior User
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P35, 270-1
23
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Role:
• Designing and developing, procuring and implementing the end
product
• Achieving the results specified by the Senior User to the level of
quality required
• May be in-house or external
.
Responsibilities:
• Provides cost information for the Business Case
• Ensures supplier resources are made available
• Responsible for the technical integrity of the products, their quality
and for delivering the outputs required by the users
• Advises on development strategy, design and methods.
Project Board: Senior Supplier
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P35-6, 271
24
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Ensures that the project is being run to the required
quality standards, that project controls are being
executed and that the Project Board is happy with the
Project Manager’s performance
• Provides advice and guidance to the Project Manager
• Assurance is the responsibility of all members of the
Project Board – they can carry it out themselves or
delegate
• Business, user and supplier assurance
• Cannot be delegated to the Project Manager
• Should be involved in all processes.
Project Assurance
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P36, 273-4
25
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Who is permitted to authorize Requests for Change or
Off-specifications?
• Configuration Management Strategy should define
rating scales for severity of changes
• Depending on severity, the request for change could be
handled by:
• Corporate or programme management
• Project Board
• Delegated to a Change Authority
• Delegated to the Project Manager.
• Any delegated authority must be agreed in role
description.
Change Authority
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P36, 274
26
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Responsible on a day-to-day basis for the project
• Responsible for planning and control within the project
• Responsible for the project delivering the required result on time
and to budget
• Reports progress and exceptions to the Project Board
• Role should not be shared.
The Project Manager
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P38, 271-2
27
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Ensures the products allocated by the Project Manager are
produced to required quality level within constraints of time
and cost
• Plans and manages the work of a team
• Reports progress, issues and risks to Project Manager
• Could be combined with role of Project Manager
• Ensure relationship with Senior Supplier is understood.
Team Manager
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P38-9, 272-3
28
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• The use of a separate person to perform Project
Support is optional and will depend on such things as
the size and the complexity of the project
• Typical activities might include:
• Planning / Re-planning
• Management of Risk
• Change Control
• Data gathering and collation
• Administration
• Specialist advice / guidance
• Links to other projects / programmes.
Project Support
Copyright © AXELOS Limited 2017 PRINCE2 ® manual ref: P39, 274-5
29
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Project Management Team Structure
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33
Corporate or programme management
Project Board
Team members
Project
Management
Team
30
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Project Management Team Structure
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33
Corporate or programme management
Project Board
Senior User(s) Senior Supplier(s)
Team members
Change Authority
Project Support
Project Manager
Team Manager(s)
Business, User &
Supplier Project
Assurance
Executive
Project
Management
Team
31
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Stakeholder = any party that can affect, be affected by
or perceive itself to be affected by a project
• Communication Management Strategy
• Description of the means and frequency of
communication to parties both internal
and external to the project
• Documented during Initiating a Project
• Communication activities should be put
in plans.
Working with Stakeholders
Communication
Mgmt Strategy
A.4
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
32
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
To be following PRINCE2, a project must, as a minimum:
• define its organization structure and roles.
• document the rules for delegating change authority
responsibilities, if required
• define its approach to communicating and engaging with
stakeholders.
PRINCE2 requires that two products are produced and
maintained for the organization theme:
 PID
 Communication Management Approach
PRINCE2’s Requirements for Organization
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
33
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Manager
OR1: Which role represents the
business interests in the project?
D Corporate or programme management
C Executive
B Project Assurance
34
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A During Starting up a Project
OR2: When is the Project
Manager appointed?
D In Directing a Project
C When the Project Mandate is created
B During Initiating a Project
35
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Corporate or programme management
OR3: Which role will decide how supplier
assurance will be carried out in the project?
D Project Mandate
C Executive
B Senior Supplier
36
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Anyone that can affect, be affected by or
perceive itself to be affected by a project
OR4: Project stakeholders can be best
described as…?
D Anyone in the project management team
C Those who have the authority to commit
resources and funds
B The main driving force behind a project
37
PUBLIC
PUBLIC
Starting up a Project
Process
40
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Triggered by Project Mandate from Corporate or Programme
Management
• Purpose
• Do we have a worthwhile and viable project?
• Pre-requisite for Initiation
• Define and agree base project information.
• Objective
• Is there business justification for Initiation?
• Do the necessary project authorities exist for Initiation?
• Sufficient information is available to define the What?
Who? How? of the project
• The Initiation Stage is planned.
Starting up a Project - Context
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P121-2
41
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Process Overview
Copyright © AXELOS Limited 2017 PRINCE2 ® manual ref: P121
Project
mandate
Corporate or
programme
management
Directing a
Project
Appoint the Executive
and
the Project Manager
Design and appoint
the project
management team
Select the project
approach and assemble
the Project Brief
Request to
initiate a
project
Plan the
initiation stage
Starting up a Project
Capture
previous
lessons
Prepare the outline
Business Case
42
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Appoint the Executive and the
Project Manager
Organization
Corporate or programme
management appoint…
…who
appoints…
the Executive the Project Manager
Executive
Role
Description
Appendix C
PM
Role
Description
Appendix C
Daily
Log
A.7
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P123-4, 270, 271, 242
We need a decision-maker (Executive) and a day-to-day manager
(Project Manager)
43
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Capture Previous Lessons
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P124, 248
Lessons Log
A.14
Previous projects’
Lessons Reports
Corporate or
programme
management
Other interested
parties
External experts
44
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Design and Appoint the Project
Management Team
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P124-6, Appendix C
Organization
Corporate or programme management
Project Board
Senior User(s) Senior Supplier(s)
Team members
Change Authority
Project Support
Project Manager
Team Manager(s)
Business, User
and
Supplier Project
Assurance
Executive
Project
Management
Team Role
Descriptions
App C
Project
Management
Team Role
Descriptions
App C
Project
Management
Team Role
Descriptions
App C
Project
Management
Team Role
Descriptions
Appendix C
45
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Prepare the Outline Business Case
Business Case,
Quality
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P126-8, 256
The Executive…
• Drafts the outline Business
Case:
• Background information to the
project
• Contribution to
corporate/programme objectives
• Project objectives
• Project funding.
The Project Manager…
• Creates the Project Product
Description (A.21):
• What is the project to deliver?
• Customer Quality Expectations
• Acceptance Criteria.
• Summarises key risks in outline
Business Case.
46
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Select the Project Approach…
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P128-30
• Definition of the Project Approach is a pre-requisite to project
planning
• Dependant on customer and supplier standards
• Approach taken must be appropriate to deliver project product and
achieve outline Business Case
• Considerations:
• Lessons from previous projects
• Corporate/programme strategies and/or standards
• Security considerations
• Training needs
• Operational environment.
47
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
…and Assemble the Project Brief
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P128-30, 253
Business Case,
Quality, Risk
Project
Brief
A.19
Project
Definition
Outline
Business Case
Project
Approach
Project
Management Team
structure
Project
Product Description
Issues and Risks?
48
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Plan the Initiation Stage
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P130-1, 250
• Create a Stage Plan (A.16) for the initiation stage:
– Lessons?
– Reporting and controls?
– Constraints?
– Risks?
Pre-project
SU
SB CP
IP
Initiation
stage
Subsequent
delivery stage(s)
Final delivery
stage
Directing
Managing
Delivering
Directing a Project
SB
Controlling a Stage Controlling a Stage
Managing Product Delivery Managing Product
Delivery
Scope of the plan
Plans
49
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Summary
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P121
Project mandate
Corporate or
programme
management
Directing a
Project
Appoint the Executive
and
the Project Manager
Design and appoint
the project
management team
Select the project
approach and assemble
the Project Brief
Request to
initiate a project
Plan the
initiation stage
Starting up a Project
Capture
previous lessons
Prepare the outline
Business Case
Defined roles and
responsibilities
Continued
business
justification
Learn from
experience
Manage by
stages
Focus on
products
Manage by
exception
Tailor to suit the
project
environment
50
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
SU1: Which of the following forms part of
the Project Brief?
D Daily Log
C Stage Plan
B Project Mandate
A Project Product Description
51
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Mandate
SU2: Which of the following is created when
appointing the Executive and the Project Manager?
D Daily Log
C Lessons Log
B Outline Business Case
52
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Senior User
SU3: Which role drafts the outline
Business Case?
D Executive
C Project Assurance
B Project Manager
53
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Senior Supplier and Senior User
SU4: With whom should the Project
Manager consult when creating the
Project Product Description?
D Corporate or programme management
C Executive and Project Support
B Executive and Senior User
54
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Initiating a Project
SU5: Which process follows Starting up
a Project?
D Closing a Project
C Directing a Project
B Controlling a Stage
55
PUBLIC
PUBLIC
Business Case
Why?
57
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Purpose
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P21
Continued
Business
Justification
• Is the project:
• Desirable?
• Viable?
• Achievable?
• Documents the business justification for the project
• Supports project decision-making
• Responsibility of the Executive.
58
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Mix of information for investment decisions
• Cost
• Risk
• Benefit
• Contribution to strategic objectives
• Provides confidence for Project Board
and Stakeholders
• Dynamic not static.
What is a Business Case?
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P21
59
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Compulsory project
• Legal, regulatory
• Not for profit
• Public sector, charity
• Evolving
• Research and development
• Customer / Supplier
• Multi-Organization
• Joint ventures, inter-governmental.
Types of Business Case
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P22
60
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
• Executive summary
• Reasons
• Business options (include ‘do nothing’)
• Expected benefits
• Expected dis-benefits
• Timescale
• Costs
• Investment appraisal
• Major risks.
Business Case Contents
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P25-7, 217-8, 237
61
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Outputs, Outcomes, (Dis-)Benefits
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P25-6
Output
A project produces
outputs…
Outcomes
Which, when used,
produce
outcomes…
Benefits Dis-benefits
Which deliver
measurable results
perceived as positive
(Benefits) or negative
(Dis-benefits) by
stakeholders
A new medicine
Quicker, more
effective patient
treatment
25% reduction in
cost of treatment
5% of patients suffer minor
side-effects
62
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Business Case in the Project Lifecycle
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P23
Pre-Project
Initiation
Stage
Subsequent
Delivery Stages
Final Delivery
Stage
Post
Project
Outline
Business
Case
Detailed
Business
Case
Updated
Business
Case
Updated
Business
Case
? ? ? ?
Business
Case
development
Business
Case
maintenance
Benefits? Benefits? Benefits?
Benefits Review Plan
Based on AXELOS
PRINCE2® material.
Material is reproduced
under licence from
AXELOS.
Business Case A.2
Benefits Review Plan A.1
63
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Responsibilities
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P28
Corporate or
Programme
Management
Responsible for Benefits Review Plan (post-project)
Holds Senior User to account for benefits realization (post project)
Executive Responsible for the Business Case and Benefits Review Plan
throughout the project
Project
Manager
Prepares the Business Case on behalf of Executive
Analyses impact of any issues and risks on the Business Case
Assesses Business Case at the end of every management stage
and reports on project performance at closure
Project
Assurance
Assists in Business Case development
Verifies and monitors Business Case against external events and
project progress
Verifies and monitors the Benefits Review Plan
64
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Controlling a Stage
BC1: Which process creates the
Benefits Review Plan?
D Managing a Stage Boundary
C Initiating a Project
B Starting up a Project
65
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Manager
BC2: Which role is responsible for
drafting the outline Business Case?
D Corporate or Programme Management
C Senior User
B Executive
66
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Result of change derived from using
products
BC3: Which statement best
describes an output?
D A management product
C An advantage for a stakeholder
B Any of the project’s specialist products
67
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Learn from experience
BC4: Which principle does the
Business Case theme support?
D Continued business justification
C Manage by stages
B Focus on products
68
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Premature closure
BC5: Which business option should
always be considered?
D Not-for-profit
C Commercial
B Do nothing
69
PUBLIC
PUBLIC
Directing a Project
Process
71
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Directing a Project - Context
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P135-6
• Starts on completion of Starting up a Project
• Trigger is request to initiate a project
• Covers the activities of the Project Board
• Monitor project progress via reports
• Event-driven decisions
• No need for other ‘progress meetings’
• Flow of information
• Corporate or programme management
• Project Manager.
72
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Process Overview
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P135
Directing a Project
Managing a
Stage Boundary
Authority to
initiate a project
Request to
deliver a project
Closing a Project
Initiating
a Project
Starting up
a Project
Request to
initiate a project
Stage
authorization
Exception Plan
approved
Request to
approve
Exception Plan
Request to
approve
Next Stage Plan
Exception Plan
request
Project Manager
request for
advice
Exception
raised
New issue
Project Board
advice and
decisions
Premature
close
Closure
recommendation
Controlling a Stage
Authorize project
closure
Give ad hoc
direction
Authorize a Stage or
Exception Plan
Authorize
the project
Authorize
initiation
Initiation
notification
Project
authorization
notification
Project Board
request for
advice
Corporate
advice and
decisions
Closure
notification
73
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Authorize Initiation
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P136-7
Starting up a Project Initiating a Project
Authorize Initiation
• Is investment to initiate project worthwhile?
• Review and approve Project Brief
• Review and approve Initiation Stage Plan.
Request to initiate a project
Project Brief
Initiation Stage Plan
Initiation Notification to corporate or
programme management
Authority to initiate a project
Organization,
Business Case,
Quality, Risk
74
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
DP1: Which of the following are received
by ‘give ad hoc direction’?
D Highlight Report, Product Status Account
C End Stage Report, End Project Report
B Exception Report, End Stage Report
A Highlight Report, Issue Report
75
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
DP2: Which of the following statements
is false?
D Directing a Project starts on completion
of the Starting up a Project process
C Directing a Project is predominantly a
time-driven process
B The Project Board can trigger premature
closure at any point after initiation has
been authorized
A Directing a Project is predominantly an
event-driven process
76
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
DP3: Which role(s) carry out Directing
a Project?
D Corporate/Programme Management
and Project Board
C Project Board and Project Assurance
B Project Manager and Project Board
A Project Board Executive
77
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
DP4: Which activity approves the
original PID?
D Authorize a project
C Authorize a Stage or Exception Plan
B Authorize initiation
A Give ad hoc direction
78
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
DP5: Which two products will the Project Board
use to decide whether to authorize initiation?
D PID, Initiation Stage Plan
C End Stage Report, PID
B Project Mandate, outline Business Case
A Initiation Stage Plan, Project Brief
79
PUBLIC
PUBLIC
Initiating a Project
Process
80
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Initiating a Project - Context
• Triggered by Authority to Initiate a Project from Project Board
• Purpose
• Establish firm foundations on which to deliver the project
• Enables the organization to understand the work to be done
before committing to significant expenditure
• Objective
• Ensures there is a common understanding of:
• Why the project is required
• Scope and quality of project deliverables
• How, when and by whom the deliverables will be produced
• How the project will be controlled
• Information required throughout the project.
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: p149-150
81
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Process Overview
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P149
82
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Prepare the Communication
Management Strategy / Approach
Organization
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P155-6, 239
• Should be last strategy to be produced
• Facilitates stakeholder engagement
• Defines both internal and external project communications activities:
• Procedures
• Tools and techniques
• Records and reports
• Roles and responsibilities
• Stakeholder analysis
• Information needs
• Communication related to the other strategies.
• Appendix A.4.
83
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Create the Project Plan
Plans
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P159-61, 250, 251
Review
Project
Brief
Review
Lessons
Log
Review
Risk/Issue
Registers
Create Project Plan
- Create Product Descriptions
- Update Configuration Item Records
- Update project management team
structure
Project Product
Description
Project Approach
Lessons from
previous projects?
Related risks
or issues?
New risks
or issues?
Seek Project
Board approval
Consult Project
Assurance
84
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Set up the Project Controls
Progress
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P156-8
• Done in conjunction with creating the Project Plan
• Project controls can include:
• Communication between project management levels
• Number and length of stages
• Tolerances
• Mechanisms for dealing with issues and exceptions
• Summarized in PID.
85
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Refine the Business Case
Business Case
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P161-2, 235, 237
Review
Project
Brief
Review
Lessons
Log
Review Risk
Register
Refine the Business Case
- Create detailed Business Case
- Create Benefits Review Plan
Outline
Business Case
Lessons from
previous projects?
Major Project
Risks
New risks
or issues?
Seek Project
Board approval
Consult Project
Assurance
Project Plan
Time
and cost
86
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Assemble the Project Initiation
Documentation
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P1623-4, 254
Information
from Starting up
a Project
Assemble the Project
Initiation Documentation
- Tailoring of PRINCE2
Project Brief
Stage boundary
approaching
Request to
deliver a project
Consult Project
Assurance
Information
from Initiating a
Project
Strategies, Project Plan, Business
Case, Project Controls
Focal point of
the ‘what, why,
who, how,
where, when
and how much
of the project
87
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Summary
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P149
Initiating a Project
Managing a
Stage Boundary
Prepare the
Risk Management
Strategy
Prepare the
Change
Management Strategy
Prepare the
Quality Management
Strategy
Prepare the
Communication
Management Strategy
Set up the
project controls
Create the
Project Plan
Refine the
Business Case
Assemble the
Project Initiation
Documentation
Authority to
initiate project
Request to
deliver a project
Stage boundary
approaching
Defined roles and
responsibilities
Continued
business
justification
Learn from
experience
Manage by
stages
Focus on
products
Manage by
exception
Tailor to suit
the project
environment
88
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
IP1: Which of the following is NOT a
strategy produced by Initiating a Project?
D Configuration Management Strategy
C Quality Management Strategy
B Communication Management Strategy
A Change Management Strategy
89
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Set up Project Controls
IP2: Which activity produces the Benefits
Review Plan?
D Prepare the Risk Management Strategy
C Assemble the PID
B Refine the Business Case
90
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Resource names
IP4: What information does the Project
Plan provide to refine the Business Case?
D Activity lists
C Time and cost
B Project tolerances
92
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Refine the Business Case
IP5: In which activity are Product
Descriptions created?
D Create the Project Plan
C Assemble the PID
B Set up Project Controls
93
PUBLIC
PUBLIC
Plans Theme
How?
How Much?
When?
94
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Purpose of Plans
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P61
Plan
Delegate
Monitor
Control
Effective project management relies on effective planning as
without a plan there is no control.
Business Case,
Risk
95
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Acquire
resources
What is a Plan?
Achieve our
objectives
Build on our
achievements
Recover from
exceptions
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P61
A method or way of proceeding thought out in advance.
It helps us to:
96
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Levels of Plan
Project Plan
Stage Plan
Team Plan
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P61-2, 250
Plan
A.16
Manage by
stages
Manage by
exception
PRINCE2 proposes 3 levels of plan to reflect the needs of different
levels of the Project Management Team in controlling the project.
97
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
The Project Plan
Project Plan
Stage Plan
Team Plan
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P62
Provides a statement of how and when a project’s time, cost,
scope and quality targets are to be achieved
• Shows major products, activities and resources
• Provides the Business Case with project costs
• Is used by the Project Board to monitor and control project costs and
progress
• Identifies major project control points (e.g. stages)
• Should be in line with corporate/programme plans.
98
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
The Stage Plan
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P62
Project Plan
Stage Plan
Team Plan
• For each Stage identified, a Stage Plan is required
• Each element within the Project Plan will now be broken down to a
level of detail to enable adequate day-to-day control by the Project
Manager
• Identifies the method of quality checking products and activities
involved
• Each Stage Plan is completed near to the end of the preceding stage
• Gives greater confidence in the plan
• Assistance from Team Managers/members.
99
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
The Team Plan
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P62-3
Project Plan
Stage Plan
Team Plan
• An optional plan
• Need determined by size and complexity of project
• Contains detailed information to assist in the management of
Work Packages
• Detailed activity and resource requirements for quality control
• May be prepared in parallel with Stage Plan
• Could be owned by Third party suppliers on certain
projects – the Project Manager may not have
control over Team Plans.
100
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
The Exception Plan
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P63
Project Plan
Stage Plan
Team Plan
Prepared for the appropriate management level to show the
actions required to recover from the effect of a tolerance
deviation
• Same level of detail and format
• Picks up from current plan actuals
• Continues to the end of the plan
• Will become the new baselined Project Plan or current Stage Plan
• Exception Plan for Stage Plan – approved by Project Board
• Exception Plan for Project Plan – approved by Corporate or
Programme. Management.
101
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Plans in the Project Lifecycle
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P31, 73
Pre-project
SU
SB CP
IP
Initiation
stage
Subsequent
delivery stage(s)
Final delivery
stage
Directing
Managing
Delivering
Directing a Project
SB
Controlling a Stage Controlling a Stage
Managing Product
Delivery
Managing
Product
Delivery
Project
Plan
Stage
Plan
Team
Plan(s)
102
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
How to Produce a Plan
Analyse
the
risks
Repeated for:
• Project Plan
• Stage Plan
• Team Plan
(optional)
Prerequisite
Define and analyse the product
Identify activities and
dependencies
Prepare estimates
Prepare the schedule
Document the plan
Design the plan
Copyright © AXELOS Limited 2017
PRINCE2® manual ref: P63
Use
Product-
Based
Planning
technique
Focus on
products
103
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Product-Based Planning
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P64-7, 251, 256, Appendix D
Project
Plan
only
1. Write the Project Product Description
• Created in Starting up a Project
• Appendix A.21
2. Create the product breakdown structure
• Hierarchy of products to be produced by the plan
• Appendix D
3. Write Product Descriptions
• Understand each product in detail
• Appendix A.17
4. Create the product flow diagram
• Defines sequence in which products will be developed
• Appendix D
104
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
To be following PRINCE2, a project must, as a minimum:
• ensure that plans enable the business case to be realized (PRINCE2’s
continued business justification principle)
• have at least two management stages: an initiation stage and at least one
further management stage. The more complex and risky a project, the
more management stages that will be required (PRINCE2’s manage by
stages principle)
• produce a project plan for the project as a whole and a stage plan for
each management stage (PRINCE2’s manage by stages principle)
• use product-based planning for the project plan, stage plans and
exception plans. It may be optionally used for team plans. alternative
approaches may be used. produce specific plans for managing exceptions
(PRINCE2’s manage by exception principle)
• define the roles and responsibilities for planning (PRINCE2’s defined roles
and responsibilities principle)
• use lessons to inform planning (PRINCE2’s learn from experience principle)
PRINCE2’s Requirements for Plan
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
105
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project, Stage, Team Plans
PL1: Which levels of plan are
recommended by PRINCE2®?
D Stage, Product, Work Package Plans
C Programme, Project, Stage Plans
B Project, Stage, Product Plans
106
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Manager
PL2: Which role is responsible for
preparing the Project Plan?
D Executive
C Project Support
B Project Board
107
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Business Case
PL3: Which of the following forms
part of a Plan?
D Project definition
C External dependencies
B Project Brief
108
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Team Plans are optional
PL4: Which of the following
statements is INCORRECT?
D The Project Plan needs to be aligned with
the Business Case
C The Project Plan is baselined at the end of
the Initiation Stage
B A Stage Plan covers the work of a technical
stage
109
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Product Description, product flow
diagram
PL5: Which of the following are
created in Product-Based Planning?
D Estimate, budget
C Product breakdown structure, schedule
B Product Description, activity list
110
PUBLIC
PUBLIC
Risk
What if?
111
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Purpose
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P77
Continued
business
justification
To identify assess and control uncertainty and, as a result,
improve the ability of the project to succeed
• Systematic and proactive approach
• Cost-effective risk management procedures
• Continual and unavoidable activity.
112
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
What is a Risk?
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P77
• An uncertain event or set of events that, should it occur, will
have an effect on the achievement of objectives
• Consists of:
• Probability that it will occur
• Impact on objectives
• Also consider its Proximity
• May be:
• Negative - Threat
• Positive – Opportunity.
113
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Risk Management Procedure
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P80-7
Identify
Assess
Plan
Implement
Communicate
114
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Risk Appetite
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P78
Long-term
Medium-term
Short-term
Strategic
Operational
Project
Programme
Business
change
An organization’s unique attitude to risk
115
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Identify
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P80-81
Cause - Event - Effect
• Context:
• Relating to Risk Management Strategy
• Early Warning Indicators
• Risks
• Capture in Risk Register
• Prepare and monitor Indicators
• Understand Stakeholders’ views.
116
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Assess
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P82-3
Consider using a Risk Summary
• Estimate:
• Probability and Impact
• Proximity (how quickly it might happen)
• How it may change over the life of the projects.
• Evaluate
• Net effects of aggregated threats and opportunities
• Within tolerance?
• Continued business justification.
117
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Summary Risk Profile
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P83-4
Probability
Very
High
1,2 13 5
High 19 3,4 18 15
Medium 10 16 9,11
Low 14 17 7
Very
Low
6 20 12 8
Very
Low
Low Medium High
Very
High
Impact
Risks 5 and 15
are beyond risk
tolerance
118
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Impact Probability Grid
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P83-5
Probability
0.9
Very
High
0.045 0.09 0.18 0.36 0.72
0.7 High 0.035 0.07 0.14 0.28 0.56
0.5 Medium 0.025 0.05 0.10 0.20 0.40
0.3 Low 0.015 0.03 0.05 0.12 0.24
0.1
Very
Low
0.005 0.01 0.02 0.04 0.08
Very
Low
Low Medium High
Very
High
0.05 0.1 0.2 0.4 0.8
Impact
119
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P84-5
Plan - Risk Responses
Threat responses Opportunity responses
Exploit
Avoid
Reduce
(probability and/or impact)
Fallback
(reduces impact only)
Transfer
(reduces impact only, and often only
the financial impact)
Enhance
Share
Reject
Accept
120
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Implement
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P84-6, 88
Could be
the same
person
• Action the selected Response(s):
• Monitor Implementation
• Take any corrective action
• Review roles and responsibilities
• Risk Owner - responsible for the management, monitoring and
control of all aspects of a particular risk assigned to them,
including the implementation
of the selected responses
• Risk Actionee - assigned to carry out
risk response action(s) to respond to a particular risk or set of
risks. They support and take direction from the Risk Owner.
121
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Communicate
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P80-1
• Formally:
• Agree a Work Package
• Checkpoint Reports
• Highlight Reports
• End Stage Report
• End Project Report (Residual Risk)
• Lesson Report.
• Informally
• Risk Workshops
• Feedback to Concern authors
• Anything appropriate for organization.
122
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
To be following PRINCE2, a project must, as a minimum:
• define its risk management approach, which must minimally cover:
– how risks are identified and assessed, how risk management responses are
planned and implemented and how the management of risk is communicated
throughout the project lifecycle
– assessing whether identified risks might have a material impact on the business
justification of the project (PRINCE2’s continued business justification principle)
– the roles and responsibilities for risk management (PRINCE2’s defined roles and
responsibilities principle)
• maintain some form of risk register to record identified risks and decisions relating
to their analysis, management and review
• ensure that project risks are identified, assessed, managed and reviewed
throughout the project lifecycle
• use lessons to inform risk identification and management (PRINCE2’s learn from
experience principle).
PRINCE2’s Requirements for Risk
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
123
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A If it is part of a programme
RK1: When can risk management be
safely left out of a Project?
D Never
C If we have done something similar before
B When the project is small or urgent
124
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Identify, Implement, Plan, Communicate
RK2: What are the steps in the Risk
Management Procedure?
D Communicate, Assess, Implement, Monitor
C Identify, Assess, Plan, Implement,
Communicate
B Communicate, Plan, Identify, Assess,
Implement
125
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Negative opportunity or positive threat
RK3: A Risk can be…?
D Negative threat or positive opportunity
C Anything that is a threat
B Something we did not see coming
126
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Avoid
RK4: Which Risk Response is used for
both threats and opportunities?
D Share
C Fallback
B Reject
127
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Attitude to risk taking
RK5: Which of these should appear in
a Risk Management Strategy?
D Proximity of an individual risk
C Assigning risk owners
B Risk Budget amount
128
PUBLIC
PUBLIC
Quality
What?
130
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
What is Quality?
The means by which the project will create and verify
products that are fit for purpose.
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P48
Learn from
experience
131
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Quality Assurance vs. Project Assurance
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P48
• Quality Assurance
• Checks to ensure that the relevant corporate standards and
policies have been complied with and assures the organization
that quality is in place
• Reports to the relevant organization
• External to the project.
• Project Assurance
• Checks that the project is being conducted appropriately and
properly
• Reports to a member of the Project Board
• Within the project.
132
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Approach to Quality
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P48, 50, 54
Learn from
experience
• Quality Planning
• Defining quality criteria, methods and responsibilities, including
effort for quality control and product acceptance
• Quality Control
• Checking to ensure that the finished product conforms to the
pre-determined quality criteria
• Carrying out the quality methods
• Maintaining quality and approval records
• Gaining Acceptance
• Eliminating causes of unsatisfactory performance.
133
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Quality Register
Quality
Activity
ID
Product
ID
Product
Quality
Method
Producer
Reviewer(s)
Approver(s)
Target
Review
Date
Actual
Review
Date
Target
Approval
Date
Actual
Approval
Date
Result
1 121 Test
Plan
Inspection Ali John,
Rita
14-Feb Pass
2 124 Water
Pump
Performance
Test
Paulo Ali,
Bob
John 20-Mar NA Fail
3 124 Maintenance
Test
Rita Pass
. . . . . . . . . . .
Water
Pump
Paulo
Paulo
Ali,
Amir
21-Feb 21-Feb 28-Feb
20-Mar 27-Mar
21-Mar 21-Mar 27-Mar 27-Mar
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P53-4, 258
• Created in Initiating a Project and populated as plans are developed
• Summarizes all planned and actual quality activities
• Updated by Team Manager, but may be maintained by Project
Support.
134
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Quality Audit Trail
Customer’s
Quality
Expectations
Acceptance
Criteria
Quality Planning
Project
Product
Description
Quality
Management
Strategy
Product
Descriptions
Quality Control
Quality
Register
Products Produced
Products
Quality Checked
Quality Register
Updated
Acceptance
Criteria
Sign-off!!
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P49, 58
135
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Quality Methods
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P53-4
• “In Process”
• Built in to product development, can include checks, calibrations,
automation, workshops, surveys, etc.
• Appraisal
• Testing – objective and quantifiable criteria
• Quality Inspection – subjective judgement required, e.g. Quality
Review.
136
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Quality Review
Preparation
Review
Approved
Minor
Defects
Major
Defects
Corrective
Action
Configuration
Library
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P55-6
Review
Preparation
Review
Meeting
Agenda
Review
Follow-up
137
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Quality Review Roles
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P55-6
Chair
• Responsible for
the overall
conduct of the
review
Presenter
• Introduces and
presents the
product
• Coordinates
work after the
review
Administrator
• Supports the
Chair and
records results
and actions
Reviewer(s)
• Submits
questions and
reviews product
• Confirms
corrections
138
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
To be following PRINCE2, a project must, as a minimum:
• define its quality management approach. This approach must minimally
cover:
• the project’s approach to quality control
• the project’s approach to project assurance
• how the management of quality is communicated throughout the project
lifecycle
• the roles and responsibilities for quality management
• specify explicit quality criteria for products in their product descriptions
(PRINCE2’s focus on products principle)
• maintain records in some form of quality register
• specify the customer’s quality expectations and prioritized acceptance
criteria for the project in the project product description
• use lessons to inform quality planning, the definition of quality
expectations and quality criteria (PRINCE2’s learn from experience
principle)
PRINCE2’s Requirements for Quality
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
139
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Authorize Initiation
QU1: When does the Project Board first
see the Customer’s Quality Expectations?
D Authorize a Stage
C Give Ad-hoc Direction
B Authorize a Project
140
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Product Description
QU2: What product summarizes quality
activities that are planned?
D Quality Plan
C Quality Register
B Project Plan
141
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Assurance
QU3: Which of these must be independent
of the Project Management Team?
D Quality Reviewers
C Quality Control
B Quality Assurance
142
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Assessing and correcting a product
QU4: What is the purpose of a
quality review?
D Method of systematic inspection
C Checks that quality has been done
B Accepts the product for the customer
143
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Being fit for purpose
QU5: What is the best description
of ‘quality’?
D Being reliable in use
C Being the best it can be
B Being easy to use
144
PUBLIC
PUBLIC
Progress
Where are we now?
Where are we going?
Should we carry on?
145
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Purpose of Progress
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P101
Plan
Delegate
Monitor
Control
Decision-
making
Continued
Business
Justification
To establish mechanisms to monitor and compare actual achievements
against those planned; provide a forecast for […] the project’s
continued viability; and control any unacceptable deviations.
146
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Progress Controls
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P101, 106
• Enable each level in the project management team to:
• Make decisions and give authorizations
• Handle exceptions and changes
• Monitor progress (actual vs. plan)
• Learn from experience.
• Event-driven controls
– Take place when a specific event occurs, e.g. end of a stage
• Time-driven controls
– Take place a pre-defined periodic intervals, e.g. monthly
Highlight Report.
147
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
How to Define Stages
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P104-5
Number of
stages?
Length of
stages?
Planning horizons – how
far ahead can we plan?
How much risk is
involved?
Key decision
points?
Balance too many short
stages vs. too few long
ones
Confidence in
plans?
Where do technical
stages end?
Alignment with the
programme?
Manage by stages
148
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Work Package
Tolerances
Controlled Delegation
Corporate Management
Project Tolerances
Stage Tolerances
Team Manager
Team
Plan
Work Package progress
(Checkpoint Reports)/
Issues
Project Manager
Stage
Plan
Stage progress
(Highlight Reports)/
Exception Reports
Project Board
Project
Plan
Project progress/
exceptions
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P103, 109
Manage by
Exception
149
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Baselines for Progress Control
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P106-7
• Project Plan (A.16)
• Project-level performance targets and tolerances
• Tolerance threats escalated to corporate/programme
management via the Project Board.
• Stage Plans (A.16)
• Basis for day-to-day control
• Exception Plan (A.16)
• May be requested by Project Board following receipt of and
Exception Report
• Work Package (A.26)
• Authorized by Project Manager
• Tolerance threats raised as issues.
150
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Reviewing Progress
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P107
• Daily Log (A.7)
• Project Manager’s project diary
• Tool to record actions.
• Issue Register (A.12)
• Repository of all formal issues raised
• Product Status Account (A.18)
• Report on data held by Configuration Item Records
• Quality Register (A.23)
• Repository of all information related to planned and actual quality
activities
• Risk Register (A.25)
• Repository of all identified risks.
151
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Reporting Progress
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P108-9
• Checkpoint Report (A.3)
• Time-driven report from Team Manager to Project Manager
• Frequency defined in Work Package
• Highlight Report (A.11)
• Time-driven report from Project Manager to Project Board
• Frequency defined in Communication Management Strategy
• End Stage Report (A.9)
• Produced in Managing a Stage Boundary
• End Project Report (A.8)
• Produced in Closing a Project.
152
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Capturing and Reporting Lessons
Learn from
experience
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P108
• Lessons Log (A.14)
• Opened in Starting up a Project to record lessons to be applied
to this project
• Also records all lessons identified when reviewing progress
• Lessons Report (A.15)
• Report on significant lessons with relevance for future projects
• Can be created at any time during a project
• At least created during Closing a Project and included in End
Project Report.
153
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
To be following PRINCE2, a project must, as a minimum:
• define its approach to controlling progress in the PID
• be managed by stages (PRINCE2’s manage by stages principle)
• set tolerances and be managed by exception against these tolerances
(PRINCE2’s manage by exception principle)
• review the business justification when exceptions are raised (PRINCE2’s
continued business justification principle)
• learn lessons (PRINCE2’s learn from experience principle)
PRINCE2 provides progress control through:
• delegating authority from one level of management to the level below it
• dividing the project into management stages and authorizing the project
one management stage at a time (PRINCE2’s manage by stages principle)
• time-driven and event-driven progress reporting and reviews
• raising exceptions (PRINCE2’s manage by exception principle)
PRINCE2’s Requirements for Progress
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
154
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Board
PG1: Which role sets project-level
tolerances?
D Project Assurance
C Corporate/programme management
B Project Manager
155
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Continued business justification
PG2: The setting of tolerance supports
which PRINCE2 Principle?
D Focus on products
C Manage by stages
B Manage by exception
156
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A An issue should be raised
PG3: How should the Project Manager be
notified of Work Package exceptions?
D A note in the Quality Register
C Checkpoint Report
B Exception Report
157
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A End Stage Report
PG4: Which of the following is a
time-driven control?
D Checkpoint Report
C Exception Report
B Issue Report
158
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Too many short stages vs. too few long ones
PG5: Which of the following is not a
consideration when defining a project’s stages?
D Project Board availability
C Levels of risk
B Planning horizons
159
PUBLIC
PUBLIC
Controlling a Stage
Process
160
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Controlling a Stage - Context
Manage by Stages
Manage by Exception
Continued Business
Justification
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P167-8
• Triggered by stage authorization or Exception Plan approval by the
Project Board
• To assign work to be done, monitor such work, deal with issues,
report progress to the Project Board, and take corrective actions
to ensure that the stage remains within tolerance
• Objective
• Focus on delivery of stage’s products within
constraints and tolerances
• Control risks and issues
• Review Business Case.
161
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Work Packages
Authorize Work
Packages
Review Work
Package Status
Receive
completed Work
Packages
Managing
Product
Delivery
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P168-73
Plans, Progress,
Quality, Risk
• Interface with Team Manager
• Agreement of Work Package
(A.26)
• Receipt of Checkpoint Report
• Update registers and stage
plan to reflect progress
• Confirmation of specialist
product approvals.
162
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Problem Handling
Capture and
examine issues
and risks
Give ad hoc
direction
Review the
stage status
Escalate issues
and risks
Take corrective
action
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P176-82
• Capture of events that require
managing
• Handle formal issues with
Issue Report (A.13)
• Forecast any tolerance
threats
• Assessment and
recommendation of corrective
actions
• Raise Exception Reports
(A.10).
163
Change, Progress,
Business Case, Risk
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Monitoring and Reporting
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P173-7
Review Work
Package status
Give ad hoc
direction
Review the
stage status
Report highlights
Progress,
organization,
Business Case,
Risk
• Identify deviations from plan
• Progress updates to the Stage
Plan
• Progress reporting to Project
Board and other stakeholders
• Production of Highlight Report
(A.11)
• Triggers for the next stage and
closing the project.
164
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
CS1: What can be used alongside the
Checkpoint Report to review Work Package
status?
D Exception Report
C End Stage Report
B Quality Register
A Issue Report
165
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
CS2: When should Highlight Reports
be produced?
D When the Project Board ask for them
C When highlights occur
B Every month
A At the frequency defined in the
Communications Management Strategy
166
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
CS3: What should the Project Manager do
when stage tolerance is forecast to be exceeded?
D Do nothing
C Produce an Exception Report
B Take corrective action
A Produce an Issue Report
167
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
CS4: Which principle does the activity
“escalate issues and risks” support?
D Manage by exception
C Learn from experience
B Focus on products
A Continued business justification
168
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
CS5: In which activity is the Lessons
Log updated?
D Authorize Work Packages
C Report highlights
B Review Work Package Status
A Review stage status
169
PUBLIC
PUBLIC
Managing Product Delivery
Process
170
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Managing Product Delivery - Context
• Triggered by authority to deliver a Work Package from Project
Manager (Controlling a Stage)
• Purpose
• To control the link between the Project Manager and the
Team Manager(s), by placing formal requirements on
accepting, executing and delivering project work
• Objective
• Work is authorized and agreed before it commences
• All parties are clear on what has to be delivered, within what
constraints
• Products are delivered to expectations
• Accurate, timely progress information is provided to the Project
Manager.
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P185-7
171
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Process Overview
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P186
Accept a
work package
Execute a
work package
Deliver a
W
ork Pa kage
Authority to
deliver
work package
Completed
Work
Package
Controlling a Stage
Managing Product Delivery
Deliver a work
package
172
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Accept a Work Package
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P187-8, 251, 261 Plans, Risk,
Quality, Progress
Authorize a Work
Package
Controlling a Stage
Accept a Work
Package
Managing Product Delivery
Authority to deliver a Work Package
- Team Plan created - New risks raised
- Quality Register updated - Work Package approved
173
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Execute a Work Package
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P188-90, 238 Change, Risk,
Quality, Progress
Review Work
Package status
Controlling a Stage
Execute a Work
Package
Managing Product Delivery
Checkpoint Report Quality Register
- Specialist products created - New risks raised
- Team Plan and CIRs updated - New issues raised
174
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Deliver a Work Package
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P190
Plans, Quality,
Progress
Receive completed
Work Packages
Controlling a Stage
Deliver a Work
Package
Managing Product Delivery
Completed Work Package
- Work Package updated - Team Plan updated
175
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Summary
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P186
Accept a
work package
Execute a
work package
Deliver a
W
ork Pa kage
Authority to
deliver
work package
Completed
Work
Package
Controlling a Stage
Managing Product Delivery
Deliver a work
package
176
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
MP1: In which activity are Checkpoint
Reports produced?
D Delivering a Work Package
C Executing a Work Package
B Reviewing Work Package Status
A Accepting a Work Package
177
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Write an Exception Report
MP2: What should the Team Manager
do when Work Package tolerance is forecast
to be exceeded?
D Nothing, carry on
C Raise an Issue
B Talk to the Project Manager
178
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Quality check products
MP3: The purpose of Managing Product
Delivery is to…?
D Agree the work to be done
C Define Configuration Management
procedures
B Control the link between Project Manager
and the Team Manager(s)
179
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A The Checkpoint Report is time-driven
MP4: Which statement is incorrect?
D Work Package tolerances are set by the
Project Manager
C The Team Plan is the element of delegation
from Project Manager to Team Manager
B Product Descriptions are included in the
Work Package
180
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Executive
MP5: Approval for completed products is
obtained from?
D A majority of those testing the product
C Project Manager
B The Authorities identified in the Product
Description
181
PUBLIC
PUBLIC
Managing a Stage Boundary
Process
182
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Managing a Stage Boundary - Purpose
PAST
PRESENT
FUTURE
LEARN
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193
To enable the Project Board to be provided with sufficient information
by the Project Manager so that it can review the success of the
current stage, approve the next Stage Plan, review the updated
Project Plan, and confirm continued business justification and
acceptability of the risks.
183
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Managing a Stage Boundary - Context
Routine stage end
• All products in the current
stage completed and approved
• Review and update the PID to
demonstrate ongoing viability
of the project
• Plan next stage and request
authorization to proceed
• Record lessons.
Exceptions
• Produce Exception Plan
• Request approval to replace
Project or Stage Plan with
Exception Plan.
• Triggered by:
• Stage boundary approaching (routine)
• Exception Plan request (from Project Board)
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193-4
184
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Process Overview
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193
Managing a Stage Boundary
Plan the
next stage
Update the
Project
Plan
Update the
Business
Case
Report
stage end
Produce
an
Exception
Plan
Assemble
the PID
Review
the stage
status
Exception
Plan
Request
Request to
approve
next Stage
Plan
Request to
approve
Exception
Plan
Stage boundary
approaching
185
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Report Stage End
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P199-200, 244
Progress
End Stage
Report
A.9
Directing a Project –
Project Board
Request to
approve next
Stage Plan/
Exception Plan
Distribution to other
Stakeholders? –
see Communication
Management
Strategy
• Current Business Case status
and benefits achieved
• Stage objectives met?
• Plans still achievable?
• Review team performance
• Review Product Status
Account for product
performance
• Results of quality activities
• Issues and risks?
• Lessons Report?
186
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
SB1: Which process does not trigger
Managing a Stage Boundary?
D Controlling a Stage
C Starting up a Project
B Directing a Project
A Initiating a Project
187
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Only the Project Board
SB2: To whom should the End Stage
Report be distributed?
D Project Assurance
C Corporate/Programme Management
B The stakeholders named in the
Communications Management Strategy
188
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Business Case
SB3: Along with the Project Plan,
what else is updated by Managing a
Stage Boundary?
D All of the above
C Risk Register
B Configuration Item Records
189
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Provide a means by which an exception
process can be implemented
SB4: A purpose of Managing a Stage
Boundary is to …?
D Provide a regular progress report to the
Project Board
C Sign off all products completed within the
stage that is coming to an end
B Authorize the start of the next stage and
set its tolerances
190
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A End Stage Report, Exception Plan
SB5: Which products can be produced in
Managing a Stage Boundary?
D Stage Plan, Exception Report
C Product Status Account, End Project Report
B End Stage Report, Highlight Report
191
PUBLIC
PUBLIC
Change
What’s the impact?
192
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Change is Inevitable…
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P91
Issue and Change Control
Configuration Management
The purpose of the Change theme is to identify, assess and
control any potential and approved changes to the baseline.
A prerequisite of effective issue and change control is the
establishment of an appropriate configuration
management system.
193
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Issues
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P91-2
Any event that has happened, was not planned, and requires
management action.
• An issue can be about anything related to the project
• Anyone with an interest in the project and/or its outcome can raise an
issue at any time
• types of issue:
• Off-specification
• Problem/concern.
194
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
What is Configuration Management?
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P91
The technical and administrative activity concerned with the
creation, maintenance and controlled change of configuration
throughout the life of a product (or item)
• Configuration Item = an entity subject to configuration management
• Component of a product
• Product
• Release
• Enables impact assessment by holding information about
relationships
• Maintains baselines – a defined state
195
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Configuration Management Procedure
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P94
• Planning - Level of configuration management required and how to
achieve this
• Identification - Unique identification of each product and version
• Control - Nothing moves or changes without authorization
• Status Accounting - Reporting on current and historical data –
Product Status Account
• Verification and Audit - Reviews and audits to check actual product
state against records held.
196
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
To be following PRINCE2, a project must, as a minimum:
• define its change control approach. This approach must minimally cover:
– how issues are identified and managed
– assessing whether identified issues might have a material impact on the business
justification of the project (PRINCE2’s continued business justification principle)
– the roles and responsibilities for change control (PRINCE2’s defined roles and
responsibilities principle), including a defined change authority
• define how product baselines are created, maintained and controlled
• maintain some form of issue register to record identified issues and decisions relating to their
analysis, management and review
• ensure that project issues are captured, examined, managed and reviewed throughout the
project lifecycle
• use lessons to inform issue identification and management (PRINCE2’s learn from experience
principle).
PRINCE2 requires that the following products are produced and maintained:
• Issue register Captures and maintains information on all the issues that are being formally
managed.
• Change control approach Identifies how, and by whom, the project’s products will be
controlled and protected.
PRINCE2’s Requirements for Change
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2
197
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Initiation Stage
CH1: When is the Issue Register created?
D Controlling a Stage
C Managing a Stage Boundary
B Starting up a Project
198
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Issue Register
CH2: Which of the following can be
used to handle issues informally?
D Daily Log
C Configuration Item Records
B Issue Report
199
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Problem/concern
CH3: Which of the following is NOT
a type of issue?
D Request for Change
C Off-specification
B Question/query
200
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Initiating a Project
CH4: When should the use of a
Change Budget be decided upon?
D Controlling a Stage
C Starting up a Project
B Directing a Project
201
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Planning
CH5: Which of the following is not a
Configuration Management activity?
D Identification
C Verification and audit
B Capturing
202
PUBLIC
PUBLIC
Closing a Project
Process
203
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Closing a Project - Purpose
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P205
To provide a fixed point at which acceptance for the project
product is confirmed, and to recognize that objectives set out in
the original Project Initiation Documentation have been achieved
(or approved changes to the objectives have been achieved), or
that the project has nothing more to contribute.
204
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Closing a Project - Context
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193-4
• Triggered by:
• Project end approaching (routine)
• Premature closure (from Project Board)
• Objective
• Confirm acceptance of the project’s products
• Ensure that operational and maintenance environment exists to
support products in use
• Evaluate project performance and assess any benefits realized
to date
• Address matters to be actioned after project closure
• Unrealized benefits
• Open issues and risks.
205
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Process Overview
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P205
Closing a Project
Prepare
planned
closure
Hand over
products
Evaluate the
project
Recommend
project
closure
Prepare
premature
closure
Review
the stage
status
Premature
closure
Closure re-
commendation
Project end
approaching
Directing a
Project
206
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
Evaluate the Project
Copyright © AXELOS Limited 2017 PRINCE2®
manual ref: P210-11, 243, 249
All Themes
Original and
current PID
Issue, Risk,
Quality
Registers
Evaluate the Project
- Review of project and team performance
against targets
-Assessment of results vs. expected benefits
- Review lessons, measurements and
success of tailoring
Project’s original
intent vs. approved
changes
Project data
Consult Project
Assurance
Lessons Log
What went well?
What went badly?
Useful metrics, etc.
End Project
Report A.8
207
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
CP1: When should the activities of
Closing a Project be performed?
D Projects never really close
C As part of the end of the final stage
B After the end of the final stage
A As the final stage of a project
208
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Highlight Report
CP2: Which report is created in
“prepare premature closure”?
D Issue Report
C Product Status Account
B End Project Report
209
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Project Manager
CP3: Which role carries out the
activities of Closing a Project?
D All of the above
C Corporate or Programme Management
B Project Support
210
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A End Stage Report
CP4: The End Project Report
contains which other report?
D Lessons Report
C Checkpoint Report
B Issue Report
211
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
A Company policy
CP5: Why should all project information
be archived in Closing a Project?
D It may contain sensitive information
C So it can be re-used on future projects
B To permit future audit of the project
212
PUBLIC
PUBLIC
Summary and Close
213
PUBLIC
PUBLIC
© FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited
reproduced under licence from AXELOS Limited.
PRINCE2
Starting
up a
Project
Directing a Project
Initiating a
Project
Controlling a
Stage
Managing
Product
Delivery
Managing
Product
Delivery
Directing
Managing
Delivering
Controlling a
Stage
S
B
S
B
CP
Pre-Project
Initiation
Stage
Subsequent
Delivery
Stages
Final Stage
Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P113
214
PUBLIC
PUBLIC
Exam Preparation
215

Más contenido relacionado

La actualidad más candente

PRINCE2 - Presentation
PRINCE2 - PresentationPRINCE2 - Presentation
PRINCE2 - PresentationMatt Trigg
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetKnowledge Train
 
Prince2 for Value Driven Project Management
Prince2 for Value Driven Project ManagementPrince2 for Value Driven Project Management
Prince2 for Value Driven Project ManagementEdureka!
 
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...Stefan Ondek, PMP, CSPM
 
Prince2 quick guide
Prince2 quick guidePrince2 quick guide
Prince2 quick guideMaven
 
7 Principles of PRINCE 2
7 Principles of PRINCE 27 Principles of PRINCE 2
7 Principles of PRINCE 2Barry Hodge
 
An introduction to prince2
An introduction to prince2An introduction to prince2
An introduction to prince2Business Beam
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSvetlana Sidenko
 
Comparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBokComparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBokSimon Buehring
 
Prince2 Vs PMBOK
Prince2 Vs PMBOKPrince2 Vs PMBOK
Prince2 Vs PMBOKsundong
 
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadfP2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadfAnne Starr
 
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours! Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours! Knowledge Train
 
Prince2 explained in 30mins
Prince2 explained in 30minsPrince2 explained in 30mins
Prince2 explained in 30minsILX Group
 
PRINCE2 key terms and free revision notes to pass the certification exam
PRINCE2 key terms and free revision notes to pass the certification examPRINCE2 key terms and free revision notes to pass the certification exam
PRINCE2 key terms and free revision notes to pass the certification examprojectingIT
 
Prince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedPrince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedCTE Solutions Inc.
 
7 Processes of Prince2
7 Processes of Prince27 Processes of Prince2
7 Processes of Prince2Barry Hodge
 
A simple PRINCE2 glossary
A simple PRINCE2 glossaryA simple PRINCE2 glossary
A simple PRINCE2 glossaryFrank Turley
 
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...Branislav Gablas PMP (5k)
 
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013 PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013 Martin Boudikianov
 

La actualidad más candente (20)

PRINCE2 - Presentation
PRINCE2 - PresentationPRINCE2 - Presentation
PRINCE2 - Presentation
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
 
Prince2 for Value Driven Project Management
Prince2 for Value Driven Project ManagementPrince2 for Value Driven Project Management
Prince2 for Value Driven Project Management
 
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
International Project Management Standards - PRINCE2, PMI & Co. And Their Ben...
 
Prince2 quick guide
Prince2 quick guidePrince2 quick guide
Prince2 quick guide
 
7 Principles of PRINCE 2
7 Principles of PRINCE 27 Principles of PRINCE 2
7 Principles of PRINCE 2
 
An introduction to prince2
An introduction to prince2An introduction to prince2
An introduction to prince2
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® method
 
Comparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBokComparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBok
 
Prince2 Vs PMBOK
Prince2 Vs PMBOKPrince2 Vs PMBOK
Prince2 Vs PMBOK
 
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadfP2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
 
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours! Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
Learn the SECRETS to passing your PRINCE2 Foundation exam with flying colours!
 
Prince2 explained in 30mins
Prince2 explained in 30minsPrince2 explained in 30mins
Prince2 explained in 30mins
 
PRINCE2 key terms and free revision notes to pass the certification exam
PRINCE2 key terms and free revision notes to pass the certification examPRINCE2 key terms and free revision notes to pass the certification exam
PRINCE2 key terms and free revision notes to pass the certification exam
 
Prince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedPrince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison Demystified
 
7 Processes of Prince2
7 Processes of Prince27 Processes of Prince2
7 Processes of Prince2
 
A simple PRINCE2 glossary
A simple PRINCE2 glossaryA simple PRINCE2 glossary
A simple PRINCE2 glossary
 
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
PRINCE2 Agile - Which is the difference between PRINCE2 and other Agile Frame...
 
Prince2 2005 Vs Prince2 2009
Prince2 2005 Vs Prince2 2009Prince2 2005 Vs Prince2 2009
Prince2 2005 Vs Prince2 2009
 
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013 PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
PRINCE2 - Skillshare @ Betahaus| Sofia 18. March 2013
 

Similar a Overview of PRINCE2 Project Management

PRINCE2 Certification Training - Foundation & Practitioner Part 17
PRINCE2 Certification Training - Foundation & Practitioner Part 17PRINCE2 Certification Training - Foundation & Practitioner Part 17
PRINCE2 Certification Training - Foundation & Practitioner Part 17Skillogic Solutions
 
PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6Skillogic Solutions
 
Prince2 + ITIL = Success! an ITSM Academy Webinar
Prince2 + ITIL = Success! an ITSM Academy WebinarPrince2 + ITIL = Success! an ITSM Academy Webinar
Prince2 + ITIL = Success! an ITSM Academy WebinarITSM Academy, Inc.
 
Project Management Introduction General PM lifecycles
Project Management Introduction General PM lifecyclesProject Management Introduction General PM lifecycles
Project Management Introduction General PM lifecyclesSerdar Temiz
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI ApproachZaur Ahmadov, PMP
 
Pmbok introudction
Pmbok introudctionPmbok introudction
Pmbok introudctionokarajhe
 
Epm demonstration projerct online and project server 2013
Epm demonstration projerct online and project server 2013Epm demonstration projerct online and project server 2013
Epm demonstration projerct online and project server 2013Jerome Quinton
 
8 reasons to adopt AgilePM
8 reasons to adopt AgilePM8 reasons to adopt AgilePM
8 reasons to adopt AgilePMMark Constable
 
Large public sector projects – what determines failure or success? Scrum Gath...
Large public sector projects – what determines failure or success? Scrum Gath...Large public sector projects – what determines failure or success? Scrum Gath...
Large public sector projects – what determines failure or success? Scrum Gath...Remi Hansen
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)sai12234
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)sai12234
 
Chapter 14 project closeout
Chapter 14 project closeoutChapter 14 project closeout
Chapter 14 project closeoutRohanMistry15
 
Arkatay about Certificates for project managers
Arkatay about Certificates for project managersArkatay about Certificates for project managers
Arkatay about Certificates for project managersJan Raaschou
 
Introduction To Project Management
Introduction To Project Management Introduction To Project Management
Introduction To Project Management Nada Abandah, OPM3
 
Introduction to Project and Project Management
Introduction to Project and Project ManagementIntroduction to Project and Project Management
Introduction to Project and Project ManagementMahbubun Nabi Rasel
 

Similar a Overview of PRINCE2 Project Management (20)

PRINCE2 Certification Training - Foundation & Practitioner Part 17
PRINCE2 Certification Training - Foundation & Practitioner Part 17PRINCE2 Certification Training - Foundation & Practitioner Part 17
PRINCE2 Certification Training - Foundation & Practitioner Part 17
 
PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6PRINCE2 Certification Training - Foundation & Practitioner Part 6
PRINCE2 Certification Training - Foundation & Practitioner Part 6
 
Prince2 + ITIL = Success! an ITSM Academy Webinar
Prince2 + ITIL = Success! an ITSM Academy WebinarPrince2 + ITIL = Success! an ITSM Academy Webinar
Prince2 + ITIL = Success! an ITSM Academy Webinar
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Project Management Introduction General PM lifecycles
Project Management Introduction General PM lifecyclesProject Management Introduction General PM lifecycles
Project Management Introduction General PM lifecycles
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
14 key changes in pmbok ® guide sixth edition
14 key changes in pmbok ® guide sixth edition14 key changes in pmbok ® guide sixth edition
14 key changes in pmbok ® guide sixth edition
 
PMP
PMPPMP
PMP
 
Pmbok introudction
Pmbok introudctionPmbok introudction
Pmbok introudction
 
Epm demonstration projerct online and project server 2013
Epm demonstration projerct online and project server 2013Epm demonstration projerct online and project server 2013
Epm demonstration projerct online and project server 2013
 
8 reasons to adopt AgilePM
8 reasons to adopt AgilePM8 reasons to adopt AgilePM
8 reasons to adopt AgilePM
 
Prince2 quick guide
Prince2 quick guidePrince2 quick guide
Prince2 quick guide
 
Large public sector projects – what determines failure or success? Scrum Gath...
Large public sector projects – what determines failure or success? Scrum Gath...Large public sector projects – what determines failure or success? Scrum Gath...
Large public sector projects – what determines failure or success? Scrum Gath...
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
 
Pmp pmbok6 -2018 (1)
Pmp   pmbok6 -2018 (1)Pmp   pmbok6 -2018 (1)
Pmp pmbok6 -2018 (1)
 
Chapter 14 project closeout
Chapter 14 project closeoutChapter 14 project closeout
Chapter 14 project closeout
 
Arkatay about Certificates for project managers
Arkatay about Certificates for project managersArkatay about Certificates for project managers
Arkatay about Certificates for project managers
 
Introduction To Project Management
Introduction To Project Management Introduction To Project Management
Introduction To Project Management
 
Introduction to Project and Project Management
Introduction to Project and Project ManagementIntroduction to Project and Project Management
Introduction to Project and Project Management
 

Más de Anne Starr

I01letor20so201leutor2020
I01letor20so201leutor2020I01letor20so201leutor2020
I01letor20so201leutor2020Anne Starr
 
Iso27001leadauditor2020
Iso27001leadauditor2020Iso27001leadauditor2020
Iso27001leadauditor2020Anne Starr
 
Dncybersecurity
DncybersecurityDncybersecurity
DncybersecurityAnne Starr
 
Dancyrityshy 1foundatioieh
Dancyrityshy 1foundatioiehDancyrityshy 1foundatioieh
Dancyrityshy 1foundatioiehAnne Starr
 
2 slides(2ndvariadaystion)
2 slides(2ndvariadaystion)2 slides(2ndvariadaystion)
2 slides(2ndvariadaystion)Anne Starr
 
Awtitioneressentialsdeckscloudprac401-577
Awtitioneressentialsdeckscloudprac401-577Awtitioneressentialsdeckscloudprac401-577
Awtitioneressentialsdeckscloudprac401-577Anne Starr
 
01wslouAsentialsdeck2dpractitioneres-400
01wslouAsentialsdeck2dpractitioneres-40001wslouAsentialsdeck2dpractitioneres-400
01wslouAsentialsdeck2dpractitioneres-400Anne Starr
 
uderessAwscloentialsdeck1-2ion00
uderessAwscloentialsdeck1-2ion00uderessAwscloentialsdeck1-2ion00
uderessAwscloentialsdeck1-2ion00Anne Starr
 
Cloudhnologysstecociat
CloudhnologysstecociatCloudhnologysstecociat
CloudhnologysstecociatAnne Starr
 
Cmbysantocsddsh
CmbysantocsddshCmbysantocsddsh
CmbysantocsddshAnne Starr
 
Cddmbysantcsosh
CddmbysantcsoshCddmbysantcsosh
CddmbysantcsoshAnne Starr
 
Ccbysantsddosh
Ccbysantsddosh  Ccbysantsddosh
Ccbysantsddosh Anne Starr
 

Más de Anne Starr (20)

I01letor20so201leutor2020
I01letor20so201leutor2020I01letor20so201leutor2020
I01letor20so201leutor2020
 
Iso27001leadauditor2020
Iso27001leadauditor2020Iso27001leadauditor2020
Iso27001leadauditor2020
 
Ccsddm5days
Ccsddm5daysCcsddm5days
Ccsddm5days
 
Dayblic
DayblicDayblic
Dayblic
 
Day1cspbeblic
Day1cspbeblicDay1cspbeblic
Day1cspbeblic
 
Dncybersecurity
DncybersecurityDncybersecurity
Dncybersecurity
 
Dancyrityshy 1foundatioieh
Dancyrityshy 1foundatioiehDancyrityshy 1foundatioieh
Dancyrityshy 1foundatioieh
 
2 slides(2ndvariadaystion)
2 slides(2ndvariadaystion)2 slides(2ndvariadaystion)
2 slides(2ndvariadaystion)
 
Sec4
Sec4Sec4
Sec4
 
Secuntialesse
SecuntialesseSecuntialesse
Secuntialesse
 
Securityic2
Securityic2Securityic2
Securityic2
 
)k
)k)k
)k
 
inte
inteinte
inte
 
Awtitioneressentialsdeckscloudprac401-577
Awtitioneressentialsdeckscloudprac401-577Awtitioneressentialsdeckscloudprac401-577
Awtitioneressentialsdeckscloudprac401-577
 
01wslouAsentialsdeck2dpractitioneres-400
01wslouAsentialsdeck2dpractitioneres-40001wslouAsentialsdeck2dpractitioneres-400
01wslouAsentialsdeck2dpractitioneres-400
 
uderessAwscloentialsdeck1-2ion00
uderessAwscloentialsdeck1-2ion00uderessAwscloentialsdeck1-2ion00
uderessAwscloentialsdeck1-2ion00
 
Cloudhnologysstecociat
CloudhnologysstecociatCloudhnologysstecociat
Cloudhnologysstecociat
 
Cmbysantocsddsh
CmbysantocsddshCmbysantocsddsh
Cmbysantocsddsh
 
Cddmbysantcsosh
CddmbysantcsoshCddmbysantcsosh
Cddmbysantcsosh
 
Ccbysantsddosh
Ccbysantsddosh  Ccbysantsddosh
Ccbysantsddosh
 

Último

Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!Mint Automotive
 
Control-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAGControl-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAGVikrantPawar37
 
248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf
248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf
248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdfkushkruthik555
 
ABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILES
ABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILESABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILES
ABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILESsriharshaganjam1
 
A Comprehensive Exploration of the Components and Parts Found in Diesel Engines
A Comprehensive Exploration of the Components and Parts Found in Diesel EnginesA Comprehensive Exploration of the Components and Parts Found in Diesel Engines
A Comprehensive Exploration of the Components and Parts Found in Diesel EnginesROJANE BERNAS, PhD.
 
Mastering Mercedes Engine Care Top Tips for Rowlett, TX Residents
Mastering Mercedes Engine Care Top Tips for Rowlett, TX ResidentsMastering Mercedes Engine Care Top Tips for Rowlett, TX Residents
Mastering Mercedes Engine Care Top Tips for Rowlett, TX ResidentsRowlett Motorwerks
 
Welcome to Auto Know University Orientation
Welcome to Auto Know University OrientationWelcome to Auto Know University Orientation
Welcome to Auto Know University Orientationxlr8sales
 
Pros and cons of buying used fleet vehicles.pptx
Pros and cons of buying used fleet vehicles.pptxPros and cons of buying used fleet vehicles.pptx
Pros and cons of buying used fleet vehicles.pptxjennifermiller8137
 
Building a Future Where Everyone Can Ride and Drive Electric by Bridget Gilmore
Building a Future Where Everyone Can Ride and Drive Electric by Bridget GilmoreBuilding a Future Where Everyone Can Ride and Drive Electric by Bridget Gilmore
Building a Future Where Everyone Can Ride and Drive Electric by Bridget GilmoreForth
 
Human Resource Practices TATA MOTORS.pdf
Human Resource Practices TATA MOTORS.pdfHuman Resource Practices TATA MOTORS.pdf
Human Resource Practices TATA MOTORS.pdfAditiMishra247289
 
-The-Present-Simple-Tense.pdf english hh
-The-Present-Simple-Tense.pdf english hh-The-Present-Simple-Tense.pdf english hh
-The-Present-Simple-Tense.pdf english hhmhamadhawlery16
 
Lighting the Way Understanding Jaguar Car Check Engine Light Service
Lighting the Way Understanding Jaguar Car Check Engine Light ServiceLighting the Way Understanding Jaguar Car Check Engine Light Service
Lighting the Way Understanding Jaguar Car Check Engine Light ServiceImport Car Center
 

Último (12)

Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
Can't Roll Up Your Audi A4 Power Window Let's Uncover the Issue!
 
Control-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAGControl-Plan-Training.pptx for the Automotive standard AIAG
Control-Plan-Training.pptx for the Automotive standard AIAG
 
248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf
248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf
248649330-Animatronics-Technical-Seminar-Report-by-Aswin-Sarang.pdf
 
ABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILES
ABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILESABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILES
ABOUT REGENERATIVE BRAKING SYSTEM ON AUTOMOBILES
 
A Comprehensive Exploration of the Components and Parts Found in Diesel Engines
A Comprehensive Exploration of the Components and Parts Found in Diesel EnginesA Comprehensive Exploration of the Components and Parts Found in Diesel Engines
A Comprehensive Exploration of the Components and Parts Found in Diesel Engines
 
Mastering Mercedes Engine Care Top Tips for Rowlett, TX Residents
Mastering Mercedes Engine Care Top Tips for Rowlett, TX ResidentsMastering Mercedes Engine Care Top Tips for Rowlett, TX Residents
Mastering Mercedes Engine Care Top Tips for Rowlett, TX Residents
 
Welcome to Auto Know University Orientation
Welcome to Auto Know University OrientationWelcome to Auto Know University Orientation
Welcome to Auto Know University Orientation
 
Pros and cons of buying used fleet vehicles.pptx
Pros and cons of buying used fleet vehicles.pptxPros and cons of buying used fleet vehicles.pptx
Pros and cons of buying used fleet vehicles.pptx
 
Building a Future Where Everyone Can Ride and Drive Electric by Bridget Gilmore
Building a Future Where Everyone Can Ride and Drive Electric by Bridget GilmoreBuilding a Future Where Everyone Can Ride and Drive Electric by Bridget Gilmore
Building a Future Where Everyone Can Ride and Drive Electric by Bridget Gilmore
 
Human Resource Practices TATA MOTORS.pdf
Human Resource Practices TATA MOTORS.pdfHuman Resource Practices TATA MOTORS.pdf
Human Resource Practices TATA MOTORS.pdf
 
-The-Present-Simple-Tense.pdf english hh
-The-Present-Simple-Tense.pdf english hh-The-Present-Simple-Tense.pdf english hh
-The-Present-Simple-Tense.pdf english hh
 
Lighting the Way Understanding Jaguar Car Check Engine Light Service
Lighting the Way Understanding Jaguar Car Check Engine Light ServiceLighting the Way Understanding Jaguar Car Check Engine Light Service
Lighting the Way Understanding Jaguar Car Check Engine Light Service
 

Overview of PRINCE2 Project Management

  • 1. AXELOS.com PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. PRINCE2® Foundation 1
  • 2. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Learning Objectives To help you understand PRINCE2 in respect of its: • Principles, processes, themes, techniques and roles for successful project management • Management products that are input and output of the processes. So that you may: • Attempt your exam(s) of choice with confidence • Begin to apply the method, tailoring it to your projects’ needs. 2
  • 3. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Course Topics • Overview, Principles and Tailoring PRINCE2 to the project environment (OV) • Business Case theme (BC) • Organization theme (OR) • Quality theme (QU) • Plans theme (PL) • Risk theme (RK) • Change theme (CH) • Progress theme (PG). • Starting up a Project process (SU) • Initiating a Project process (IP) • Directing a Project process (DP) • Managing a Stage Boundary process (SB) • Controlling a Stage process (CS) • Managing Product Delivery process (MP) • Closing a Project process (CP). 3
  • 4. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Examination Information Foundation • Multiple choice questions • 60 questions per paper • 33 marks required (out of 60 available) to pass: 55% • One hour's (60 minutes) duration • Closed book. 4
  • 6. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. What is a project Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P3-4 A project is a temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case • Characteristics: • Change • Temporary • Cross-functional • Unique • Uncertainty. Six project variables to control: • Time • Cost • Scope • Quality • Risk • Benefits 6
  • 7. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Programmes and Projects: Differences Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P217-8, 309 • Programme = A temporary, flexible organization created to co- ordinate, direct and oversee the implementation of a set of related projects and activities in order to deliver outcomes and benefits related to the organization’s strategic objectives. • Deals with the big, strategic picture • Is initiated to realize benefits through change • Proceeds in tranches, with benefits reviews in between. • PRINCE2 is a method for project management; MSP® is a method for programme management. 7
  • 8. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. How does PRINCE2 Help? Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P5, 7 • Provides four integrated elements for successful project management: • Principles • Processes • Themes • Tailoring PRINCE2 to the project environment. • Benefits of using PRINCE2: • Established best practice – no need to re-invent the wheel • Flexible, scalable, tailorable, transferable • Active stakeholder engagement • Provides consistency across project work • Promotes continual improvement. 8
  • 9. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. What are Principles? Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P11-4 • A guiding obligation for good practice • 7 Principles • Continued Business Justification • Learn from Experience • Defined Roles and Responsibilities • Manage by Stages • Manage by Exception • Focus on Products • Tailor to Suit the Environment. 9
  • 10. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Processes Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P113 Starting up a Project Directing a Project Initiating a Project Controlling a Stage Managing Product Delivery Managing Product Delivery Directing Managing Delivering Controlling a Stage SB SB CP Pre-Project Initiation Stage Subsequent Delivery Stages Final Stage 10
  • 11. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Themes Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P17-8 • Aspects of project management that need to be continually addressed – the Project Manager’s toolbox • Enable the PRINCE2 processes to be effective - if the process requires action the Theme provides guidance on how it should be done • 7 Themes • Business Case • Quality • Organization • Plans • Risk • Change • Progress. 12
  • 12. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. The Project Environment Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P215 • Tailoring - Done by the project team to adapt the method to the context of a specific project • Roles and responsibilities to allocate • Management products to use and how • Number, length and nature of stages • Tolerances, reporting and reviewing • Use of PRINCE2 processes. 13
  • 13. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Management Products Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P235 • Baseline Management Products • Define aspects of the project and, once approved, are subject to Change Control, e.g. Business Case • Records • Dynamic management products that maintain information regarding project progress, e.g. Risk Register • Reports • Management products that provide a snapshot of the status of certain aspects of the project, e.g. Highlight Report • Records and Reports not subject to Change Control, but other aspects of Configuration Management still apply, e.g. version control, safe storage. 14
  • 15. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Key Concepts PRINCE2® manual ref: P31 Defined roles and responsibilities • A temporary organization… • Every project needs effective direction, management, control and communication • Project’s structure of accountability and responsibilities (the who?) • Customer/supplier environment • Roles, NOT jobs. 16
  • 16. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Customer/Supplier Environment Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P224-7 • Customer – specifies project result and (probably) funds the project • Supplier – provides resources and skills to produce desired result • In-house or commercial relationship 17
  • 17. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Three Projects Interests Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P32 Consider the difference between “stakeholders” and “decision-makers” Business User Supplier The project 18
  • 18. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Four Levels of Management Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33 Starting up a Project Directing a Project Initiating a Project Controlling a Stage Managing Product Delivery Managing Product Delivery Directing Managing Delivering Controlling a Stage SB SB CP Pre-Project Initiation Stage Subsequent Delivery Stages Final Stage Project Board Project Manager Team Manager Project management team Corporate or Programme Management 19
  • 19. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Project Management Team Structure Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33 Corporate or programme management Project Board Senior User(s) Senior Supplier(s) Team members Change Authority Project Support Project Manager Team Manager(s) Business, User & Supplier Project Assurance Executive Project Management Team 20
  • 20. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. The Project Board Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P34-5, 269-70 Customer • Three roles: • Executive – business interests • Senior User – user interests • Senior Supplier – supplier interests. • Authority and responsibility for the project within the remit of the project mandate (initially) • Characteristics: • Authority • Credibility • Ability to delegate • Availability. 21
  • 21. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Project Board: Executive Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P35, 270 • Role: • Final responsibility for the project and its success or failure • Must ensure that the project has a sound business basis (‘business case’) and represents value for money throughout the life of the project. • Responsibilities: • Chairs the Board and owns the Business Case • Represents the “business” interests – should this project be done? • Ensures the Project is delivering against targets and remains focused on achieving objectives • Key decision-maker – role cannot be shared. 22
  • 22. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Role: • Ensures that requirements are fully specified and agreed before project delivery begins • Accountable to the Executive for the delivery of benefits. Responsibilities: • Ensures that user resources are made available • Ensures that the required outcome for the project is clearly specified and signed-off • Monitors progress and maintains focus on the deliverables from a user perspective • Signs-off completed deliverables against agreed quality criteria • Resolves user conflicts. Project Board: Senior User Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P35, 270-1 23
  • 23. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Role: • Designing and developing, procuring and implementing the end product • Achieving the results specified by the Senior User to the level of quality required • May be in-house or external . Responsibilities: • Provides cost information for the Business Case • Ensures supplier resources are made available • Responsible for the technical integrity of the products, their quality and for delivering the outputs required by the users • Advises on development strategy, design and methods. Project Board: Senior Supplier Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P35-6, 271 24
  • 24. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Ensures that the project is being run to the required quality standards, that project controls are being executed and that the Project Board is happy with the Project Manager’s performance • Provides advice and guidance to the Project Manager • Assurance is the responsibility of all members of the Project Board – they can carry it out themselves or delegate • Business, user and supplier assurance • Cannot be delegated to the Project Manager • Should be involved in all processes. Project Assurance Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P36, 273-4 25
  • 25. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Who is permitted to authorize Requests for Change or Off-specifications? • Configuration Management Strategy should define rating scales for severity of changes • Depending on severity, the request for change could be handled by: • Corporate or programme management • Project Board • Delegated to a Change Authority • Delegated to the Project Manager. • Any delegated authority must be agreed in role description. Change Authority Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P36, 274 26
  • 26. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Responsible on a day-to-day basis for the project • Responsible for planning and control within the project • Responsible for the project delivering the required result on time and to budget • Reports progress and exceptions to the Project Board • Role should not be shared. The Project Manager Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P38, 271-2 27
  • 27. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Ensures the products allocated by the Project Manager are produced to required quality level within constraints of time and cost • Plans and manages the work of a team • Reports progress, issues and risks to Project Manager • Could be combined with role of Project Manager • Ensure relationship with Senior Supplier is understood. Team Manager Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P38-9, 272-3 28
  • 28. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • The use of a separate person to perform Project Support is optional and will depend on such things as the size and the complexity of the project • Typical activities might include: • Planning / Re-planning • Management of Risk • Change Control • Data gathering and collation • Administration • Specialist advice / guidance • Links to other projects / programmes. Project Support Copyright © AXELOS Limited 2017 PRINCE2 ® manual ref: P39, 274-5 29
  • 29. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Project Management Team Structure Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33 Corporate or programme management Project Board Team members Project Management Team 30
  • 30. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Project Management Team Structure Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P33 Corporate or programme management Project Board Senior User(s) Senior Supplier(s) Team members Change Authority Project Support Project Manager Team Manager(s) Business, User & Supplier Project Assurance Executive Project Management Team 31
  • 31. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Stakeholder = any party that can affect, be affected by or perceive itself to be affected by a project • Communication Management Strategy • Description of the means and frequency of communication to parties both internal and external to the project • Documented during Initiating a Project • Communication activities should be put in plans. Working with Stakeholders Communication Mgmt Strategy A.4 Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 32
  • 32. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. To be following PRINCE2, a project must, as a minimum: • define its organization structure and roles. • document the rules for delegating change authority responsibilities, if required • define its approach to communicating and engaging with stakeholders. PRINCE2 requires that two products are produced and maintained for the organization theme:  PID  Communication Management Approach PRINCE2’s Requirements for Organization Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 33
  • 33. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Manager OR1: Which role represents the business interests in the project? D Corporate or programme management C Executive B Project Assurance 34
  • 34. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A During Starting up a Project OR2: When is the Project Manager appointed? D In Directing a Project C When the Project Mandate is created B During Initiating a Project 35
  • 35. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Corporate or programme management OR3: Which role will decide how supplier assurance will be carried out in the project? D Project Mandate C Executive B Senior Supplier 36
  • 36. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Anyone that can affect, be affected by or perceive itself to be affected by a project OR4: Project stakeholders can be best described as…? D Anyone in the project management team C Those who have the authority to commit resources and funds B The main driving force behind a project 37
  • 37. PUBLIC PUBLIC Starting up a Project Process 40
  • 38. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Triggered by Project Mandate from Corporate or Programme Management • Purpose • Do we have a worthwhile and viable project? • Pre-requisite for Initiation • Define and agree base project information. • Objective • Is there business justification for Initiation? • Do the necessary project authorities exist for Initiation? • Sufficient information is available to define the What? Who? How? of the project • The Initiation Stage is planned. Starting up a Project - Context Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P121-2 41
  • 39. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Process Overview Copyright © AXELOS Limited 2017 PRINCE2 ® manual ref: P121 Project mandate Corporate or programme management Directing a Project Appoint the Executive and the Project Manager Design and appoint the project management team Select the project approach and assemble the Project Brief Request to initiate a project Plan the initiation stage Starting up a Project Capture previous lessons Prepare the outline Business Case 42
  • 40. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Appoint the Executive and the Project Manager Organization Corporate or programme management appoint… …who appoints… the Executive the Project Manager Executive Role Description Appendix C PM Role Description Appendix C Daily Log A.7 Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P123-4, 270, 271, 242 We need a decision-maker (Executive) and a day-to-day manager (Project Manager) 43
  • 41. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Capture Previous Lessons Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P124, 248 Lessons Log A.14 Previous projects’ Lessons Reports Corporate or programme management Other interested parties External experts 44
  • 42. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Design and Appoint the Project Management Team Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P124-6, Appendix C Organization Corporate or programme management Project Board Senior User(s) Senior Supplier(s) Team members Change Authority Project Support Project Manager Team Manager(s) Business, User and Supplier Project Assurance Executive Project Management Team Role Descriptions App C Project Management Team Role Descriptions App C Project Management Team Role Descriptions App C Project Management Team Role Descriptions Appendix C 45
  • 43. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Prepare the Outline Business Case Business Case, Quality Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P126-8, 256 The Executive… • Drafts the outline Business Case: • Background information to the project • Contribution to corporate/programme objectives • Project objectives • Project funding. The Project Manager… • Creates the Project Product Description (A.21): • What is the project to deliver? • Customer Quality Expectations • Acceptance Criteria. • Summarises key risks in outline Business Case. 46
  • 44. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Select the Project Approach… Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P128-30 • Definition of the Project Approach is a pre-requisite to project planning • Dependant on customer and supplier standards • Approach taken must be appropriate to deliver project product and achieve outline Business Case • Considerations: • Lessons from previous projects • Corporate/programme strategies and/or standards • Security considerations • Training needs • Operational environment. 47
  • 45. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. …and Assemble the Project Brief Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P128-30, 253 Business Case, Quality, Risk Project Brief A.19 Project Definition Outline Business Case Project Approach Project Management Team structure Project Product Description Issues and Risks? 48
  • 46. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Plan the Initiation Stage Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P130-1, 250 • Create a Stage Plan (A.16) for the initiation stage: – Lessons? – Reporting and controls? – Constraints? – Risks? Pre-project SU SB CP IP Initiation stage Subsequent delivery stage(s) Final delivery stage Directing Managing Delivering Directing a Project SB Controlling a Stage Controlling a Stage Managing Product Delivery Managing Product Delivery Scope of the plan Plans 49
  • 47. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Summary Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P121 Project mandate Corporate or programme management Directing a Project Appoint the Executive and the Project Manager Design and appoint the project management team Select the project approach and assemble the Project Brief Request to initiate a project Plan the initiation stage Starting up a Project Capture previous lessons Prepare the outline Business Case Defined roles and responsibilities Continued business justification Learn from experience Manage by stages Focus on products Manage by exception Tailor to suit the project environment 50
  • 48. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. SU1: Which of the following forms part of the Project Brief? D Daily Log C Stage Plan B Project Mandate A Project Product Description 51
  • 49. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Mandate SU2: Which of the following is created when appointing the Executive and the Project Manager? D Daily Log C Lessons Log B Outline Business Case 52
  • 50. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Senior User SU3: Which role drafts the outline Business Case? D Executive C Project Assurance B Project Manager 53
  • 51. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Senior Supplier and Senior User SU4: With whom should the Project Manager consult when creating the Project Product Description? D Corporate or programme management C Executive and Project Support B Executive and Senior User 54
  • 52. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Initiating a Project SU5: Which process follows Starting up a Project? D Closing a Project C Directing a Project B Controlling a Stage 55
  • 54. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Purpose Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P21 Continued Business Justification • Is the project: • Desirable? • Viable? • Achievable? • Documents the business justification for the project • Supports project decision-making • Responsibility of the Executive. 58
  • 55. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Mix of information for investment decisions • Cost • Risk • Benefit • Contribution to strategic objectives • Provides confidence for Project Board and Stakeholders • Dynamic not static. What is a Business Case? Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P21 59
  • 56. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Compulsory project • Legal, regulatory • Not for profit • Public sector, charity • Evolving • Research and development • Customer / Supplier • Multi-Organization • Joint ventures, inter-governmental. Types of Business Case Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P22 60
  • 57. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. • Executive summary • Reasons • Business options (include ‘do nothing’) • Expected benefits • Expected dis-benefits • Timescale • Costs • Investment appraisal • Major risks. Business Case Contents Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P25-7, 217-8, 237 61
  • 58. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Outputs, Outcomes, (Dis-)Benefits Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P25-6 Output A project produces outputs… Outcomes Which, when used, produce outcomes… Benefits Dis-benefits Which deliver measurable results perceived as positive (Benefits) or negative (Dis-benefits) by stakeholders A new medicine Quicker, more effective patient treatment 25% reduction in cost of treatment 5% of patients suffer minor side-effects 62
  • 59. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Business Case in the Project Lifecycle Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P23 Pre-Project Initiation Stage Subsequent Delivery Stages Final Delivery Stage Post Project Outline Business Case Detailed Business Case Updated Business Case Updated Business Case ? ? ? ? Business Case development Business Case maintenance Benefits? Benefits? Benefits? Benefits Review Plan Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS. Business Case A.2 Benefits Review Plan A.1 63
  • 60. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Responsibilities Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P28 Corporate or Programme Management Responsible for Benefits Review Plan (post-project) Holds Senior User to account for benefits realization (post project) Executive Responsible for the Business Case and Benefits Review Plan throughout the project Project Manager Prepares the Business Case on behalf of Executive Analyses impact of any issues and risks on the Business Case Assesses Business Case at the end of every management stage and reports on project performance at closure Project Assurance Assists in Business Case development Verifies and monitors Business Case against external events and project progress Verifies and monitors the Benefits Review Plan 64
  • 61. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Controlling a Stage BC1: Which process creates the Benefits Review Plan? D Managing a Stage Boundary C Initiating a Project B Starting up a Project 65
  • 62. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Manager BC2: Which role is responsible for drafting the outline Business Case? D Corporate or Programme Management C Senior User B Executive 66
  • 63. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Result of change derived from using products BC3: Which statement best describes an output? D A management product C An advantage for a stakeholder B Any of the project’s specialist products 67
  • 64. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Learn from experience BC4: Which principle does the Business Case theme support? D Continued business justification C Manage by stages B Focus on products 68
  • 65. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Premature closure BC5: Which business option should always be considered? D Not-for-profit C Commercial B Do nothing 69
  • 67. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Directing a Project - Context Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P135-6 • Starts on completion of Starting up a Project • Trigger is request to initiate a project • Covers the activities of the Project Board • Monitor project progress via reports • Event-driven decisions • No need for other ‘progress meetings’ • Flow of information • Corporate or programme management • Project Manager. 72
  • 68. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Process Overview Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P135 Directing a Project Managing a Stage Boundary Authority to initiate a project Request to deliver a project Closing a Project Initiating a Project Starting up a Project Request to initiate a project Stage authorization Exception Plan approved Request to approve Exception Plan Request to approve Next Stage Plan Exception Plan request Project Manager request for advice Exception raised New issue Project Board advice and decisions Premature close Closure recommendation Controlling a Stage Authorize project closure Give ad hoc direction Authorize a Stage or Exception Plan Authorize the project Authorize initiation Initiation notification Project authorization notification Project Board request for advice Corporate advice and decisions Closure notification 73
  • 69. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Authorize Initiation Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P136-7 Starting up a Project Initiating a Project Authorize Initiation • Is investment to initiate project worthwhile? • Review and approve Project Brief • Review and approve Initiation Stage Plan. Request to initiate a project Project Brief Initiation Stage Plan Initiation Notification to corporate or programme management Authority to initiate a project Organization, Business Case, Quality, Risk 74
  • 70. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. DP1: Which of the following are received by ‘give ad hoc direction’? D Highlight Report, Product Status Account C End Stage Report, End Project Report B Exception Report, End Stage Report A Highlight Report, Issue Report 75
  • 71. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. DP2: Which of the following statements is false? D Directing a Project starts on completion of the Starting up a Project process C Directing a Project is predominantly a time-driven process B The Project Board can trigger premature closure at any point after initiation has been authorized A Directing a Project is predominantly an event-driven process 76
  • 72. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. DP3: Which role(s) carry out Directing a Project? D Corporate/Programme Management and Project Board C Project Board and Project Assurance B Project Manager and Project Board A Project Board Executive 77
  • 73. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. DP4: Which activity approves the original PID? D Authorize a project C Authorize a Stage or Exception Plan B Authorize initiation A Give ad hoc direction 78
  • 74. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. DP5: Which two products will the Project Board use to decide whether to authorize initiation? D PID, Initiation Stage Plan C End Stage Report, PID B Project Mandate, outline Business Case A Initiation Stage Plan, Project Brief 79
  • 76. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Initiating a Project - Context • Triggered by Authority to Initiate a Project from Project Board • Purpose • Establish firm foundations on which to deliver the project • Enables the organization to understand the work to be done before committing to significant expenditure • Objective • Ensures there is a common understanding of: • Why the project is required • Scope and quality of project deliverables • How, when and by whom the deliverables will be produced • How the project will be controlled • Information required throughout the project. Copyright © AXELOS Limited 2017 PRINCE2® manual ref: p149-150 81
  • 77. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Process Overview Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P149 82
  • 78. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Prepare the Communication Management Strategy / Approach Organization Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P155-6, 239 • Should be last strategy to be produced • Facilitates stakeholder engagement • Defines both internal and external project communications activities: • Procedures • Tools and techniques • Records and reports • Roles and responsibilities • Stakeholder analysis • Information needs • Communication related to the other strategies. • Appendix A.4. 83
  • 79. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Create the Project Plan Plans Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P159-61, 250, 251 Review Project Brief Review Lessons Log Review Risk/Issue Registers Create Project Plan - Create Product Descriptions - Update Configuration Item Records - Update project management team structure Project Product Description Project Approach Lessons from previous projects? Related risks or issues? New risks or issues? Seek Project Board approval Consult Project Assurance 84
  • 80. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Set up the Project Controls Progress Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P156-8 • Done in conjunction with creating the Project Plan • Project controls can include: • Communication between project management levels • Number and length of stages • Tolerances • Mechanisms for dealing with issues and exceptions • Summarized in PID. 85
  • 81. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Refine the Business Case Business Case Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P161-2, 235, 237 Review Project Brief Review Lessons Log Review Risk Register Refine the Business Case - Create detailed Business Case - Create Benefits Review Plan Outline Business Case Lessons from previous projects? Major Project Risks New risks or issues? Seek Project Board approval Consult Project Assurance Project Plan Time and cost 86
  • 82. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Assemble the Project Initiation Documentation Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P1623-4, 254 Information from Starting up a Project Assemble the Project Initiation Documentation - Tailoring of PRINCE2 Project Brief Stage boundary approaching Request to deliver a project Consult Project Assurance Information from Initiating a Project Strategies, Project Plan, Business Case, Project Controls Focal point of the ‘what, why, who, how, where, when and how much of the project 87
  • 83. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Summary Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P149 Initiating a Project Managing a Stage Boundary Prepare the Risk Management Strategy Prepare the Change Management Strategy Prepare the Quality Management Strategy Prepare the Communication Management Strategy Set up the project controls Create the Project Plan Refine the Business Case Assemble the Project Initiation Documentation Authority to initiate project Request to deliver a project Stage boundary approaching Defined roles and responsibilities Continued business justification Learn from experience Manage by stages Focus on products Manage by exception Tailor to suit the project environment 88
  • 84. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. IP1: Which of the following is NOT a strategy produced by Initiating a Project? D Configuration Management Strategy C Quality Management Strategy B Communication Management Strategy A Change Management Strategy 89
  • 85. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Set up Project Controls IP2: Which activity produces the Benefits Review Plan? D Prepare the Risk Management Strategy C Assemble the PID B Refine the Business Case 90
  • 86. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Resource names IP4: What information does the Project Plan provide to refine the Business Case? D Activity lists C Time and cost B Project tolerances 92
  • 87. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Refine the Business Case IP5: In which activity are Product Descriptions created? D Create the Project Plan C Assemble the PID B Set up Project Controls 93
  • 89. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Purpose of Plans Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P61 Plan Delegate Monitor Control Effective project management relies on effective planning as without a plan there is no control. Business Case, Risk 95
  • 90. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Acquire resources What is a Plan? Achieve our objectives Build on our achievements Recover from exceptions Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P61 A method or way of proceeding thought out in advance. It helps us to: 96
  • 91. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Levels of Plan Project Plan Stage Plan Team Plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P61-2, 250 Plan A.16 Manage by stages Manage by exception PRINCE2 proposes 3 levels of plan to reflect the needs of different levels of the Project Management Team in controlling the project. 97
  • 92. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. The Project Plan Project Plan Stage Plan Team Plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P62 Provides a statement of how and when a project’s time, cost, scope and quality targets are to be achieved • Shows major products, activities and resources • Provides the Business Case with project costs • Is used by the Project Board to monitor and control project costs and progress • Identifies major project control points (e.g. stages) • Should be in line with corporate/programme plans. 98
  • 93. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. The Stage Plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P62 Project Plan Stage Plan Team Plan • For each Stage identified, a Stage Plan is required • Each element within the Project Plan will now be broken down to a level of detail to enable adequate day-to-day control by the Project Manager • Identifies the method of quality checking products and activities involved • Each Stage Plan is completed near to the end of the preceding stage • Gives greater confidence in the plan • Assistance from Team Managers/members. 99
  • 94. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. The Team Plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P62-3 Project Plan Stage Plan Team Plan • An optional plan • Need determined by size and complexity of project • Contains detailed information to assist in the management of Work Packages • Detailed activity and resource requirements for quality control • May be prepared in parallel with Stage Plan • Could be owned by Third party suppliers on certain projects – the Project Manager may not have control over Team Plans. 100
  • 95. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. The Exception Plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P63 Project Plan Stage Plan Team Plan Prepared for the appropriate management level to show the actions required to recover from the effect of a tolerance deviation • Same level of detail and format • Picks up from current plan actuals • Continues to the end of the plan • Will become the new baselined Project Plan or current Stage Plan • Exception Plan for Stage Plan – approved by Project Board • Exception Plan for Project Plan – approved by Corporate or Programme. Management. 101
  • 96. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Plans in the Project Lifecycle Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P31, 73 Pre-project SU SB CP IP Initiation stage Subsequent delivery stage(s) Final delivery stage Directing Managing Delivering Directing a Project SB Controlling a Stage Controlling a Stage Managing Product Delivery Managing Product Delivery Project Plan Stage Plan Team Plan(s) 102
  • 97. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. How to Produce a Plan Analyse the risks Repeated for: • Project Plan • Stage Plan • Team Plan (optional) Prerequisite Define and analyse the product Identify activities and dependencies Prepare estimates Prepare the schedule Document the plan Design the plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P63 Use Product- Based Planning technique Focus on products 103
  • 98. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Product-Based Planning Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P64-7, 251, 256, Appendix D Project Plan only 1. Write the Project Product Description • Created in Starting up a Project • Appendix A.21 2. Create the product breakdown structure • Hierarchy of products to be produced by the plan • Appendix D 3. Write Product Descriptions • Understand each product in detail • Appendix A.17 4. Create the product flow diagram • Defines sequence in which products will be developed • Appendix D 104
  • 99. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. To be following PRINCE2, a project must, as a minimum: • ensure that plans enable the business case to be realized (PRINCE2’s continued business justification principle) • have at least two management stages: an initiation stage and at least one further management stage. The more complex and risky a project, the more management stages that will be required (PRINCE2’s manage by stages principle) • produce a project plan for the project as a whole and a stage plan for each management stage (PRINCE2’s manage by stages principle) • use product-based planning for the project plan, stage plans and exception plans. It may be optionally used for team plans. alternative approaches may be used. produce specific plans for managing exceptions (PRINCE2’s manage by exception principle) • define the roles and responsibilities for planning (PRINCE2’s defined roles and responsibilities principle) • use lessons to inform planning (PRINCE2’s learn from experience principle) PRINCE2’s Requirements for Plan Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 105
  • 100. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project, Stage, Team Plans PL1: Which levels of plan are recommended by PRINCE2®? D Stage, Product, Work Package Plans C Programme, Project, Stage Plans B Project, Stage, Product Plans 106
  • 101. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Manager PL2: Which role is responsible for preparing the Project Plan? D Executive C Project Support B Project Board 107
  • 102. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Business Case PL3: Which of the following forms part of a Plan? D Project definition C External dependencies B Project Brief 108
  • 103. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Team Plans are optional PL4: Which of the following statements is INCORRECT? D The Project Plan needs to be aligned with the Business Case C The Project Plan is baselined at the end of the Initiation Stage B A Stage Plan covers the work of a technical stage 109
  • 104. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Product Description, product flow diagram PL5: Which of the following are created in Product-Based Planning? D Estimate, budget C Product breakdown structure, schedule B Product Description, activity list 110
  • 106. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Purpose Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P77 Continued business justification To identify assess and control uncertainty and, as a result, improve the ability of the project to succeed • Systematic and proactive approach • Cost-effective risk management procedures • Continual and unavoidable activity. 112
  • 107. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. What is a Risk? Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P77 • An uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives • Consists of: • Probability that it will occur • Impact on objectives • Also consider its Proximity • May be: • Negative - Threat • Positive – Opportunity. 113
  • 108. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Risk Management Procedure Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P80-7 Identify Assess Plan Implement Communicate 114
  • 109. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Risk Appetite Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P78 Long-term Medium-term Short-term Strategic Operational Project Programme Business change An organization’s unique attitude to risk 115
  • 110. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Identify Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P80-81 Cause - Event - Effect • Context: • Relating to Risk Management Strategy • Early Warning Indicators • Risks • Capture in Risk Register • Prepare and monitor Indicators • Understand Stakeholders’ views. 116
  • 111. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Assess Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P82-3 Consider using a Risk Summary • Estimate: • Probability and Impact • Proximity (how quickly it might happen) • How it may change over the life of the projects. • Evaluate • Net effects of aggregated threats and opportunities • Within tolerance? • Continued business justification. 117
  • 112. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Summary Risk Profile Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P83-4 Probability Very High 1,2 13 5 High 19 3,4 18 15 Medium 10 16 9,11 Low 14 17 7 Very Low 6 20 12 8 Very Low Low Medium High Very High Impact Risks 5 and 15 are beyond risk tolerance 118
  • 113. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Impact Probability Grid Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P83-5 Probability 0.9 Very High 0.045 0.09 0.18 0.36 0.72 0.7 High 0.035 0.07 0.14 0.28 0.56 0.5 Medium 0.025 0.05 0.10 0.20 0.40 0.3 Low 0.015 0.03 0.05 0.12 0.24 0.1 Very Low 0.005 0.01 0.02 0.04 0.08 Very Low Low Medium High Very High 0.05 0.1 0.2 0.4 0.8 Impact 119
  • 114. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P84-5 Plan - Risk Responses Threat responses Opportunity responses Exploit Avoid Reduce (probability and/or impact) Fallback (reduces impact only) Transfer (reduces impact only, and often only the financial impact) Enhance Share Reject Accept 120
  • 115. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Implement Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P84-6, 88 Could be the same person • Action the selected Response(s): • Monitor Implementation • Take any corrective action • Review roles and responsibilities • Risk Owner - responsible for the management, monitoring and control of all aspects of a particular risk assigned to them, including the implementation of the selected responses • Risk Actionee - assigned to carry out risk response action(s) to respond to a particular risk or set of risks. They support and take direction from the Risk Owner. 121
  • 116. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Communicate Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P80-1 • Formally: • Agree a Work Package • Checkpoint Reports • Highlight Reports • End Stage Report • End Project Report (Residual Risk) • Lesson Report. • Informally • Risk Workshops • Feedback to Concern authors • Anything appropriate for organization. 122
  • 117. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. To be following PRINCE2, a project must, as a minimum: • define its risk management approach, which must minimally cover: – how risks are identified and assessed, how risk management responses are planned and implemented and how the management of risk is communicated throughout the project lifecycle – assessing whether identified risks might have a material impact on the business justification of the project (PRINCE2’s continued business justification principle) – the roles and responsibilities for risk management (PRINCE2’s defined roles and responsibilities principle) • maintain some form of risk register to record identified risks and decisions relating to their analysis, management and review • ensure that project risks are identified, assessed, managed and reviewed throughout the project lifecycle • use lessons to inform risk identification and management (PRINCE2’s learn from experience principle). PRINCE2’s Requirements for Risk Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 123
  • 118. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A If it is part of a programme RK1: When can risk management be safely left out of a Project? D Never C If we have done something similar before B When the project is small or urgent 124
  • 119. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Identify, Implement, Plan, Communicate RK2: What are the steps in the Risk Management Procedure? D Communicate, Assess, Implement, Monitor C Identify, Assess, Plan, Implement, Communicate B Communicate, Plan, Identify, Assess, Implement 125
  • 120. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Negative opportunity or positive threat RK3: A Risk can be…? D Negative threat or positive opportunity C Anything that is a threat B Something we did not see coming 126
  • 121. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Avoid RK4: Which Risk Response is used for both threats and opportunities? D Share C Fallback B Reject 127
  • 122. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Attitude to risk taking RK5: Which of these should appear in a Risk Management Strategy? D Proximity of an individual risk C Assigning risk owners B Risk Budget amount 128
  • 124. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. What is Quality? The means by which the project will create and verify products that are fit for purpose. Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P48 Learn from experience 131
  • 125. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Quality Assurance vs. Project Assurance Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P48 • Quality Assurance • Checks to ensure that the relevant corporate standards and policies have been complied with and assures the organization that quality is in place • Reports to the relevant organization • External to the project. • Project Assurance • Checks that the project is being conducted appropriately and properly • Reports to a member of the Project Board • Within the project. 132
  • 126. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Approach to Quality Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P48, 50, 54 Learn from experience • Quality Planning • Defining quality criteria, methods and responsibilities, including effort for quality control and product acceptance • Quality Control • Checking to ensure that the finished product conforms to the pre-determined quality criteria • Carrying out the quality methods • Maintaining quality and approval records • Gaining Acceptance • Eliminating causes of unsatisfactory performance. 133
  • 127. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Quality Register Quality Activity ID Product ID Product Quality Method Producer Reviewer(s) Approver(s) Target Review Date Actual Review Date Target Approval Date Actual Approval Date Result 1 121 Test Plan Inspection Ali John, Rita 14-Feb Pass 2 124 Water Pump Performance Test Paulo Ali, Bob John 20-Mar NA Fail 3 124 Maintenance Test Rita Pass . . . . . . . . . . . Water Pump Paulo Paulo Ali, Amir 21-Feb 21-Feb 28-Feb 20-Mar 27-Mar 21-Mar 21-Mar 27-Mar 27-Mar Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P53-4, 258 • Created in Initiating a Project and populated as plans are developed • Summarizes all planned and actual quality activities • Updated by Team Manager, but may be maintained by Project Support. 134
  • 128. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Quality Audit Trail Customer’s Quality Expectations Acceptance Criteria Quality Planning Project Product Description Quality Management Strategy Product Descriptions Quality Control Quality Register Products Produced Products Quality Checked Quality Register Updated Acceptance Criteria Sign-off!! Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P49, 58 135
  • 129. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Quality Methods Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P53-4 • “In Process” • Built in to product development, can include checks, calibrations, automation, workshops, surveys, etc. • Appraisal • Testing – objective and quantifiable criteria • Quality Inspection – subjective judgement required, e.g. Quality Review. 136
  • 130. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Quality Review Preparation Review Approved Minor Defects Major Defects Corrective Action Configuration Library Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P55-6 Review Preparation Review Meeting Agenda Review Follow-up 137
  • 131. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Quality Review Roles Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P55-6 Chair • Responsible for the overall conduct of the review Presenter • Introduces and presents the product • Coordinates work after the review Administrator • Supports the Chair and records results and actions Reviewer(s) • Submits questions and reviews product • Confirms corrections 138
  • 132. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. To be following PRINCE2, a project must, as a minimum: • define its quality management approach. This approach must minimally cover: • the project’s approach to quality control • the project’s approach to project assurance • how the management of quality is communicated throughout the project lifecycle • the roles and responsibilities for quality management • specify explicit quality criteria for products in their product descriptions (PRINCE2’s focus on products principle) • maintain records in some form of quality register • specify the customer’s quality expectations and prioritized acceptance criteria for the project in the project product description • use lessons to inform quality planning, the definition of quality expectations and quality criteria (PRINCE2’s learn from experience principle) PRINCE2’s Requirements for Quality Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 139
  • 133. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Authorize Initiation QU1: When does the Project Board first see the Customer’s Quality Expectations? D Authorize a Stage C Give Ad-hoc Direction B Authorize a Project 140
  • 134. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Product Description QU2: What product summarizes quality activities that are planned? D Quality Plan C Quality Register B Project Plan 141
  • 135. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Assurance QU3: Which of these must be independent of the Project Management Team? D Quality Reviewers C Quality Control B Quality Assurance 142
  • 136. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Assessing and correcting a product QU4: What is the purpose of a quality review? D Method of systematic inspection C Checks that quality has been done B Accepts the product for the customer 143
  • 137. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Being fit for purpose QU5: What is the best description of ‘quality’? D Being reliable in use C Being the best it can be B Being easy to use 144
  • 138. PUBLIC PUBLIC Progress Where are we now? Where are we going? Should we carry on? 145
  • 139. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Purpose of Progress Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P101 Plan Delegate Monitor Control Decision- making Continued Business Justification To establish mechanisms to monitor and compare actual achievements against those planned; provide a forecast for […] the project’s continued viability; and control any unacceptable deviations. 146
  • 140. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Progress Controls Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P101, 106 • Enable each level in the project management team to: • Make decisions and give authorizations • Handle exceptions and changes • Monitor progress (actual vs. plan) • Learn from experience. • Event-driven controls – Take place when a specific event occurs, e.g. end of a stage • Time-driven controls – Take place a pre-defined periodic intervals, e.g. monthly Highlight Report. 147
  • 141. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. How to Define Stages Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P104-5 Number of stages? Length of stages? Planning horizons – how far ahead can we plan? How much risk is involved? Key decision points? Balance too many short stages vs. too few long ones Confidence in plans? Where do technical stages end? Alignment with the programme? Manage by stages 148
  • 142. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Work Package Tolerances Controlled Delegation Corporate Management Project Tolerances Stage Tolerances Team Manager Team Plan Work Package progress (Checkpoint Reports)/ Issues Project Manager Stage Plan Stage progress (Highlight Reports)/ Exception Reports Project Board Project Plan Project progress/ exceptions Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P103, 109 Manage by Exception 149
  • 143. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Baselines for Progress Control Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P106-7 • Project Plan (A.16) • Project-level performance targets and tolerances • Tolerance threats escalated to corporate/programme management via the Project Board. • Stage Plans (A.16) • Basis for day-to-day control • Exception Plan (A.16) • May be requested by Project Board following receipt of and Exception Report • Work Package (A.26) • Authorized by Project Manager • Tolerance threats raised as issues. 150
  • 144. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Reviewing Progress Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P107 • Daily Log (A.7) • Project Manager’s project diary • Tool to record actions. • Issue Register (A.12) • Repository of all formal issues raised • Product Status Account (A.18) • Report on data held by Configuration Item Records • Quality Register (A.23) • Repository of all information related to planned and actual quality activities • Risk Register (A.25) • Repository of all identified risks. 151
  • 145. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Reporting Progress Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P108-9 • Checkpoint Report (A.3) • Time-driven report from Team Manager to Project Manager • Frequency defined in Work Package • Highlight Report (A.11) • Time-driven report from Project Manager to Project Board • Frequency defined in Communication Management Strategy • End Stage Report (A.9) • Produced in Managing a Stage Boundary • End Project Report (A.8) • Produced in Closing a Project. 152
  • 146. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Capturing and Reporting Lessons Learn from experience Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P108 • Lessons Log (A.14) • Opened in Starting up a Project to record lessons to be applied to this project • Also records all lessons identified when reviewing progress • Lessons Report (A.15) • Report on significant lessons with relevance for future projects • Can be created at any time during a project • At least created during Closing a Project and included in End Project Report. 153
  • 147. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. To be following PRINCE2, a project must, as a minimum: • define its approach to controlling progress in the PID • be managed by stages (PRINCE2’s manage by stages principle) • set tolerances and be managed by exception against these tolerances (PRINCE2’s manage by exception principle) • review the business justification when exceptions are raised (PRINCE2’s continued business justification principle) • learn lessons (PRINCE2’s learn from experience principle) PRINCE2 provides progress control through: • delegating authority from one level of management to the level below it • dividing the project into management stages and authorizing the project one management stage at a time (PRINCE2’s manage by stages principle) • time-driven and event-driven progress reporting and reviews • raising exceptions (PRINCE2’s manage by exception principle) PRINCE2’s Requirements for Progress Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 154
  • 148. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Board PG1: Which role sets project-level tolerances? D Project Assurance C Corporate/programme management B Project Manager 155
  • 149. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Continued business justification PG2: The setting of tolerance supports which PRINCE2 Principle? D Focus on products C Manage by stages B Manage by exception 156
  • 150. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A An issue should be raised PG3: How should the Project Manager be notified of Work Package exceptions? D A note in the Quality Register C Checkpoint Report B Exception Report 157
  • 151. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A End Stage Report PG4: Which of the following is a time-driven control? D Checkpoint Report C Exception Report B Issue Report 158
  • 152. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Too many short stages vs. too few long ones PG5: Which of the following is not a consideration when defining a project’s stages? D Project Board availability C Levels of risk B Planning horizons 159
  • 154. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Controlling a Stage - Context Manage by Stages Manage by Exception Continued Business Justification Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P167-8 • Triggered by stage authorization or Exception Plan approval by the Project Board • To assign work to be done, monitor such work, deal with issues, report progress to the Project Board, and take corrective actions to ensure that the stage remains within tolerance • Objective • Focus on delivery of stage’s products within constraints and tolerances • Control risks and issues • Review Business Case. 161
  • 155. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Work Packages Authorize Work Packages Review Work Package Status Receive completed Work Packages Managing Product Delivery Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P168-73 Plans, Progress, Quality, Risk • Interface with Team Manager • Agreement of Work Package (A.26) • Receipt of Checkpoint Report • Update registers and stage plan to reflect progress • Confirmation of specialist product approvals. 162
  • 156. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Problem Handling Capture and examine issues and risks Give ad hoc direction Review the stage status Escalate issues and risks Take corrective action Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P176-82 • Capture of events that require managing • Handle formal issues with Issue Report (A.13) • Forecast any tolerance threats • Assessment and recommendation of corrective actions • Raise Exception Reports (A.10). 163 Change, Progress, Business Case, Risk
  • 157. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Monitoring and Reporting Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P173-7 Review Work Package status Give ad hoc direction Review the stage status Report highlights Progress, organization, Business Case, Risk • Identify deviations from plan • Progress updates to the Stage Plan • Progress reporting to Project Board and other stakeholders • Production of Highlight Report (A.11) • Triggers for the next stage and closing the project. 164
  • 158. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. CS1: What can be used alongside the Checkpoint Report to review Work Package status? D Exception Report C End Stage Report B Quality Register A Issue Report 165
  • 159. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. CS2: When should Highlight Reports be produced? D When the Project Board ask for them C When highlights occur B Every month A At the frequency defined in the Communications Management Strategy 166
  • 160. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. CS3: What should the Project Manager do when stage tolerance is forecast to be exceeded? D Do nothing C Produce an Exception Report B Take corrective action A Produce an Issue Report 167
  • 161. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. CS4: Which principle does the activity “escalate issues and risks” support? D Manage by exception C Learn from experience B Focus on products A Continued business justification 168
  • 162. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. CS5: In which activity is the Lessons Log updated? D Authorize Work Packages C Report highlights B Review Work Package Status A Review stage status 169
  • 164. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Managing Product Delivery - Context • Triggered by authority to deliver a Work Package from Project Manager (Controlling a Stage) • Purpose • To control the link between the Project Manager and the Team Manager(s), by placing formal requirements on accepting, executing and delivering project work • Objective • Work is authorized and agreed before it commences • All parties are clear on what has to be delivered, within what constraints • Products are delivered to expectations • Accurate, timely progress information is provided to the Project Manager. Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P185-7 171
  • 165. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Process Overview Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P186 Accept a work package Execute a work package Deliver a W ork Pa kage Authority to deliver work package Completed Work Package Controlling a Stage Managing Product Delivery Deliver a work package 172
  • 166. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Accept a Work Package Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P187-8, 251, 261 Plans, Risk, Quality, Progress Authorize a Work Package Controlling a Stage Accept a Work Package Managing Product Delivery Authority to deliver a Work Package - Team Plan created - New risks raised - Quality Register updated - Work Package approved 173
  • 167. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Execute a Work Package Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P188-90, 238 Change, Risk, Quality, Progress Review Work Package status Controlling a Stage Execute a Work Package Managing Product Delivery Checkpoint Report Quality Register - Specialist products created - New risks raised - Team Plan and CIRs updated - New issues raised 174
  • 168. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Deliver a Work Package Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P190 Plans, Quality, Progress Receive completed Work Packages Controlling a Stage Deliver a Work Package Managing Product Delivery Completed Work Package - Work Package updated - Team Plan updated 175
  • 169. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Summary Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P186 Accept a work package Execute a work package Deliver a W ork Pa kage Authority to deliver work package Completed Work Package Controlling a Stage Managing Product Delivery Deliver a work package 176
  • 170. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. MP1: In which activity are Checkpoint Reports produced? D Delivering a Work Package C Executing a Work Package B Reviewing Work Package Status A Accepting a Work Package 177
  • 171. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Write an Exception Report MP2: What should the Team Manager do when Work Package tolerance is forecast to be exceeded? D Nothing, carry on C Raise an Issue B Talk to the Project Manager 178
  • 172. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Quality check products MP3: The purpose of Managing Product Delivery is to…? D Agree the work to be done C Define Configuration Management procedures B Control the link between Project Manager and the Team Manager(s) 179
  • 173. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A The Checkpoint Report is time-driven MP4: Which statement is incorrect? D Work Package tolerances are set by the Project Manager C The Team Plan is the element of delegation from Project Manager to Team Manager B Product Descriptions are included in the Work Package 180
  • 174. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Executive MP5: Approval for completed products is obtained from? D A majority of those testing the product C Project Manager B The Authorities identified in the Product Description 181
  • 175. PUBLIC PUBLIC Managing a Stage Boundary Process 182
  • 176. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Managing a Stage Boundary - Purpose PAST PRESENT FUTURE LEARN Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193 To enable the Project Board to be provided with sufficient information by the Project Manager so that it can review the success of the current stage, approve the next Stage Plan, review the updated Project Plan, and confirm continued business justification and acceptability of the risks. 183
  • 177. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Managing a Stage Boundary - Context Routine stage end • All products in the current stage completed and approved • Review and update the PID to demonstrate ongoing viability of the project • Plan next stage and request authorization to proceed • Record lessons. Exceptions • Produce Exception Plan • Request approval to replace Project or Stage Plan with Exception Plan. • Triggered by: • Stage boundary approaching (routine) • Exception Plan request (from Project Board) Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193-4 184
  • 178. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Process Overview Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193 Managing a Stage Boundary Plan the next stage Update the Project Plan Update the Business Case Report stage end Produce an Exception Plan Assemble the PID Review the stage status Exception Plan Request Request to approve next Stage Plan Request to approve Exception Plan Stage boundary approaching 185
  • 179. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Report Stage End Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P199-200, 244 Progress End Stage Report A.9 Directing a Project – Project Board Request to approve next Stage Plan/ Exception Plan Distribution to other Stakeholders? – see Communication Management Strategy • Current Business Case status and benefits achieved • Stage objectives met? • Plans still achievable? • Review team performance • Review Product Status Account for product performance • Results of quality activities • Issues and risks? • Lessons Report? 186
  • 180. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. SB1: Which process does not trigger Managing a Stage Boundary? D Controlling a Stage C Starting up a Project B Directing a Project A Initiating a Project 187
  • 181. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Only the Project Board SB2: To whom should the End Stage Report be distributed? D Project Assurance C Corporate/Programme Management B The stakeholders named in the Communications Management Strategy 188
  • 182. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Business Case SB3: Along with the Project Plan, what else is updated by Managing a Stage Boundary? D All of the above C Risk Register B Configuration Item Records 189
  • 183. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Provide a means by which an exception process can be implemented SB4: A purpose of Managing a Stage Boundary is to …? D Provide a regular progress report to the Project Board C Sign off all products completed within the stage that is coming to an end B Authorize the start of the next stage and set its tolerances 190
  • 184. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A End Stage Report, Exception Plan SB5: Which products can be produced in Managing a Stage Boundary? D Stage Plan, Exception Report C Product Status Account, End Project Report B End Stage Report, Highlight Report 191
  • 186. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Change is Inevitable… Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P91 Issue and Change Control Configuration Management The purpose of the Change theme is to identify, assess and control any potential and approved changes to the baseline. A prerequisite of effective issue and change control is the establishment of an appropriate configuration management system. 193
  • 187. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Issues Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P91-2 Any event that has happened, was not planned, and requires management action. • An issue can be about anything related to the project • Anyone with an interest in the project and/or its outcome can raise an issue at any time • types of issue: • Off-specification • Problem/concern. 194
  • 188. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. What is Configuration Management? Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P91 The technical and administrative activity concerned with the creation, maintenance and controlled change of configuration throughout the life of a product (or item) • Configuration Item = an entity subject to configuration management • Component of a product • Product • Release • Enables impact assessment by holding information about relationships • Maintains baselines – a defined state 195
  • 189. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Configuration Management Procedure Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P94 • Planning - Level of configuration management required and how to achieve this • Identification - Unique identification of each product and version • Control - Nothing moves or changes without authorization • Status Accounting - Reporting on current and historical data – Product Status Account • Verification and Audit - Reviews and audits to check actual product state against records held. 196
  • 190. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. To be following PRINCE2, a project must, as a minimum: • define its change control approach. This approach must minimally cover: – how issues are identified and managed – assessing whether identified issues might have a material impact on the business justification of the project (PRINCE2’s continued business justification principle) – the roles and responsibilities for change control (PRINCE2’s defined roles and responsibilities principle), including a defined change authority • define how product baselines are created, maintained and controlled • maintain some form of issue register to record identified issues and decisions relating to their analysis, management and review • ensure that project issues are captured, examined, managed and reviewed throughout the project lifecycle • use lessons to inform issue identification and management (PRINCE2’s learn from experience principle). PRINCE2 requires that the following products are produced and maintained: • Issue register Captures and maintains information on all the issues that are being formally managed. • Change control approach Identifies how, and by whom, the project’s products will be controlled and protected. PRINCE2’s Requirements for Change Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P41-2 197
  • 191. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Initiation Stage CH1: When is the Issue Register created? D Controlling a Stage C Managing a Stage Boundary B Starting up a Project 198
  • 192. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Issue Register CH2: Which of the following can be used to handle issues informally? D Daily Log C Configuration Item Records B Issue Report 199
  • 193. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Problem/concern CH3: Which of the following is NOT a type of issue? D Request for Change C Off-specification B Question/query 200
  • 194. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Initiating a Project CH4: When should the use of a Change Budget be decided upon? D Controlling a Stage C Starting up a Project B Directing a Project 201
  • 195. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Planning CH5: Which of the following is not a Configuration Management activity? D Identification C Verification and audit B Capturing 202
  • 197. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Closing a Project - Purpose Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P205 To provide a fixed point at which acceptance for the project product is confirmed, and to recognize that objectives set out in the original Project Initiation Documentation have been achieved (or approved changes to the objectives have been achieved), or that the project has nothing more to contribute. 204
  • 198. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Closing a Project - Context Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P193-4 • Triggered by: • Project end approaching (routine) • Premature closure (from Project Board) • Objective • Confirm acceptance of the project’s products • Ensure that operational and maintenance environment exists to support products in use • Evaluate project performance and assess any benefits realized to date • Address matters to be actioned after project closure • Unrealized benefits • Open issues and risks. 205
  • 199. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Process Overview Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P205 Closing a Project Prepare planned closure Hand over products Evaluate the project Recommend project closure Prepare premature closure Review the stage status Premature closure Closure re- commendation Project end approaching Directing a Project 206
  • 200. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. Evaluate the Project Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P210-11, 243, 249 All Themes Original and current PID Issue, Risk, Quality Registers Evaluate the Project - Review of project and team performance against targets -Assessment of results vs. expected benefits - Review lessons, measurements and success of tailoring Project’s original intent vs. approved changes Project data Consult Project Assurance Lessons Log What went well? What went badly? Useful metrics, etc. End Project Report A.8 207
  • 201. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. CP1: When should the activities of Closing a Project be performed? D Projects never really close C As part of the end of the final stage B After the end of the final stage A As the final stage of a project 208
  • 202. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Highlight Report CP2: Which report is created in “prepare premature closure”? D Issue Report C Product Status Account B End Project Report 209
  • 203. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Project Manager CP3: Which role carries out the activities of Closing a Project? D All of the above C Corporate or Programme Management B Project Support 210
  • 204. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A End Stage Report CP4: The End Project Report contains which other report? D Lessons Report C Checkpoint Report B Issue Report 211
  • 205. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. A Company policy CP5: Why should all project information be archived in Closing a Project? D It may contain sensitive information C So it can be re-used on future projects B To permit future audit of the project 212
  • 207. PUBLIC PUBLIC © FGI Limited, save for PRINCE2 text and diagrams which are © AXELOS Limited reproduced under licence from AXELOS Limited. PRINCE2 Starting up a Project Directing a Project Initiating a Project Controlling a Stage Managing Product Delivery Managing Product Delivery Directing Managing Delivering Controlling a Stage S B S B CP Pre-Project Initiation Stage Subsequent Delivery Stages Final Stage Copyright © AXELOS Limited 2017 PRINCE2® manual ref: P113 214