SlideShare a Scribd company logo
1 of 1
Abstract Analysis
Optimizing Aggregate Production
CEMEX Balcones Quarry
Arda Onkol, Jonathan Edmunds,
Joshua Klein, Fernando Espinosa de los Monteros
CEMEX is a global company that specializes in the production and
distribution of cement, concrete, aggregates, and related building
materials. Balcones Quarry specializes in crushed aggregate, which
accounts for 60 to 75% of the volume of ready-mix concrete and is crucial
to the properties of the mix. The New Braunfels Quarry seeks to achieve
high process efficiency by optimizing the number of haul trucks and
loaders, minimizing machine downtime, eliminating wait time, and
increasing total material output.
The Main Problem
In the current quarry setup, there are 3 different rock loading sites serviced
by two Caterpillar Loaders 992 and one 993, respectively. Typically, there are
eight Caterpillar 777-Series (100 ton) haul trucks that get rocks constantly
loaded and unloaded throughout the day. When the haul trucks arrive at the
hopper, there is a often a line of at least one or two other trucks waiting to
dump. This idle time in the traffic line causes less trips in between sites and
the hopper, longer cycle and wait times, and higher costs caused by a
potential decrease in material throughput.
Bottleneck Identification
After creating a flow process chart and studying the time study data
provided by CEMEX, we identified activities prior to the haul trucks
reaching the hopper that were adding time to the entire process, having
an effect on the main bottleneck located at the Dump Zone. The current
hopper has a capacity of 50 tons, which causes a delay when the 100 ton
capacity haul trucks dump their loads.
Simulation and Optimization
• For traffic:
• Interval/cadence system to help alleviate “all trucks at once”
problem.
• Outsource an ios /Android application to have the quarry traffic
routes and data mine the real vehicle location and routing times.
• For time study:
• Machines need to be labeled or named for identification purposes.
• All data must be kept in same format and electronically.
• Revision of current time study sheet.
• For equipment:
• Acquire another loader so it may replace the lower capacity one.
• Acquire or remove a haul truck so hopper can run at full efficiency.
• Acquire a hopper that may handle the trucks’ full capacity dump.
Solution Recommendations
Average Total DT Frequencies
Total Time
(mins)
Cumulative
Time Cumulative% Individual%
100 Ton 89 4693 4693 72.52% 72.52%
992 Loader 31 1533 6226 96.21% 23.69%
993 Loader 6 245 6471 100.00% 3.79%
Special Thanks To:
• Dr. Jesus Jimenez – Industrial Engineering Capstone Faculty Advisor
• Dr. Eduardo Perez – Industrial Engineering Faculty Advisor
• Dr. Enes Bilgin – Supply Chain Faculty Advisor
• Reid Pierson – Engineer at Balcones Quarry Aggregates, CEMEX
• Adam Slusser – Operations Manager at Balcones Quarry Aggregates, CEMEX
• Freddy Aird – Engineer Quarry Manager at Balcones Quarry Aggregates, CEMEX.
Time Study data sheets created to
ensure that there are no
inconsistencies in record keeping.
These include the identification of
the truck, operational down time
length, the root cause of the down
time, maintenance/operational issue
details, daily total loads for
production, and total weight
processed.
The truck queue sheet is to record
the specific truck service time at the
time of arrival at the hopper and
queue wait time according to
number of trucks at the hopper
bottleneck.
Based on the previous yearly production
data from 2015 and the first 3 months of
2016, a scatter line plot was created to
show and compare the current monthly
production; theoretical production with
the bottleneck and forecasted
production for the year was analyzed,
assuming no changes in production
processes and forecasted production of
the CEMEX goal of 45k TONS/day.
This graph shows hopper utilization. The work
hours and down times calculated from the given
data were used to find out how hopper efficiency
processes the rocks, since the bottleneck of the
operations is present here. The goal is to keep the
hopper running as much as possible to increase
daily production. A potential removal of a truck and
changing hopper capacity will make significant
improvements in production level.
These pie charts were created from the
current data in order to show which
machines in operation are causing the
most down times and how frequently
they fail.
With the time study we evaluated the dumping
process as a queuing problem with a beta arrival
rate, lognormal serving rate with 1 server.
Hopper
Temporary
Dumping
Area
Using Google Maps to get a birds eye view of the quarry. We mapped out the
current traffic routes used by the haul truck drivers. After creating the routes we
then used Google Maps again to measure out each section of the routes we
created. In order to insure all the route distances are accurately proportional to
their real-world counterparts.
Process
❖ The data below shows all
routes and their distances;
along with the reference files.
Graphs represent the nine, eight, and seven trucks simulated to
achieve maximum number of material throughput on an average
daily basis.
Graph analytic simulations
including two 993 loaders at the
furthest work sites.
Graph analytic simulations
representing the current
equipment system.
Data generated from the
simulation presents that if a new
hopper is implemented, with
twice the capacity and a new 993
loader at the furthest site, daily
throughput will increase to
approximately 50 loads per day.
The equipment cost and the
payment periods are given in the
table. An estimated yearly profit
after the implementation is
calculated after subtracting the
equipment yearly costs.
• The simulation was created using Sources, Servers, Vehicles,
Sink, Paths, Time Paths, and Transfer Nodes.
• The Paths, Transfer Nodes, and Time Paths were used to
create the traffic routes used by the haul truck. Even though
we used paths set to a specific distance we add in time
paths to model the backing up process of the haul trucks
when entering a loading or dumping area. The paths were
set with a speed limit, not to allow passing, choose shortest
path or weighted path for intersections, and to check if an
intersection was clear before crossing the road (which was
triggered as a vehicle entered or exited a node).
• The Sources represent the three loading areas in operation
by CEMEX, with the Servers marking the each loading area
available, and the Sink represents the hopper. The three
area we choose to simulate are East wall North, Pavilion Pit,
and West Pit dig sites.
• The vehicle objects were used to represent the haul trucks.
All the loading and unloading logic was put directly into the
Vehicle object rather than the servers, to allow more
freedom in choosing which dig sites to simulate with the
two different types of loaders used by CEMEX. The entity
priority request logic was also added to the vehicles.

More Related Content

What's hot

Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status Report
UGPTI
 
joyglobalpresentationsiemenstrifectamar2016-160429150056
joyglobalpresentationsiemenstrifectamar2016-160429150056joyglobalpresentationsiemenstrifectamar2016-160429150056
joyglobalpresentationsiemenstrifectamar2016-160429150056
Darren Simoni
 
Présentation1 Linked In english ind B
Présentation1 Linked In english ind BPrésentation1 Linked In english ind B
Présentation1 Linked In english ind B
Jean-Claude Rodet
 
S11 ORA 4 2015 - Technology 03
S11 ORA 4 2015 - Technology 03S11 ORA 4 2015 - Technology 03
S11 ORA 4 2015 - Technology 03
Ali Ramady
 
Half Warm Mix Recycling Asphalt in Urban Roads
Half Warm Mix Recycling Asphalt in Urban RoadsHalf Warm Mix Recycling Asphalt in Urban Roads
Half Warm Mix Recycling Asphalt in Urban Roads
512004715
 

What's hot (20)

Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status Report
 
joyglobalpresentationsiemenstrifectamar2016-160429150056
joyglobalpresentationsiemenstrifectamar2016-160429150056joyglobalpresentationsiemenstrifectamar2016-160429150056
joyglobalpresentationsiemenstrifectamar2016-160429150056
 
Pascual icoms10
Pascual icoms10Pascual icoms10
Pascual icoms10
 
Lng use in trucking
Lng use in truckingLng use in trucking
Lng use in trucking
 
CNG & LNG for Heavy Duty Trucking
CNG & LNG forHeavy Duty TruckingCNG & LNG forHeavy Duty Trucking
CNG & LNG for Heavy Duty Trucking
 
Conveyor vs haul_truck
Conveyor vs haul_truckConveyor vs haul_truck
Conveyor vs haul_truck
 
SMCTA 101 Corridor Managed Lanes 092816
SMCTA 101 Corridor Managed Lanes 092816SMCTA 101 Corridor Managed Lanes 092816
SMCTA 101 Corridor Managed Lanes 092816
 
Sediment and Erosion Control (SEC) Laboratory
Sediment and Erosion Control (SEC) Laboratory Sediment and Erosion Control (SEC) Laboratory
Sediment and Erosion Control (SEC) Laboratory
 
Eka-stockpile-optimization-article
Eka-stockpile-optimization-articleEka-stockpile-optimization-article
Eka-stockpile-optimization-article
 
LNG in Transportation Executive Summary
LNG in Transportation Executive SummaryLNG in Transportation Executive Summary
LNG in Transportation Executive Summary
 
Présentation1 Linked In english ind B
Présentation1 Linked In english ind BPrésentation1 Linked In english ind B
Présentation1 Linked In english ind B
 
Updated combined transportation_facility_report.pdf 2
Updated combined transportation_facility_report.pdf 2Updated combined transportation_facility_report.pdf 2
Updated combined transportation_facility_report.pdf 2
 
Transportation enginering
Transportation engineringTransportation enginering
Transportation enginering
 
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
PowerLogistics Asia 2014 - Challenging Infrastructure & Constraints - Project...
 
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
 
S11 ORA 4 2015 - Technology 03
S11 ORA 4 2015 - Technology 03S11 ORA 4 2015 - Technology 03
S11 ORA 4 2015 - Technology 03
 
Traffic Growth and Transportation Safety in the Bakken Oil Producing Region
Traffic Growth and Transportation Safety in the Bakken Oil Producing RegionTraffic Growth and Transportation Safety in the Bakken Oil Producing Region
Traffic Growth and Transportation Safety in the Bakken Oil Producing Region
 
Half Warm Mix Recycling Asphalt in Urban Roads
Half Warm Mix Recycling Asphalt in Urban RoadsHalf Warm Mix Recycling Asphalt in Urban Roads
Half Warm Mix Recycling Asphalt in Urban Roads
 
Half Warm Recycling Asphalt Mix- ESR6
Half Warm Recycling Asphalt Mix- ESR6Half Warm Recycling Asphalt Mix- ESR6
Half Warm Recycling Asphalt Mix- ESR6
 
HWMRA in Urban Roads
HWMRA in Urban RoadsHWMRA in Urban Roads
HWMRA in Urban Roads
 

Viewers also liked (6)

Quarry Optimization Module
Quarry Optimization ModuleQuarry Optimization Module
Quarry Optimization Module
 
Query Optimization
Query OptimizationQuery Optimization
Query Optimization
 
Kitaly Venance D. - Blast Design Optimization to Improve Material Fragmentati...
Kitaly Venance D. - Blast Design Optimization to Improve Material Fragmentati...Kitaly Venance D. - Blast Design Optimization to Improve Material Fragmentati...
Kitaly Venance D. - Blast Design Optimization to Improve Material Fragmentati...
 
SHIFTing the way we work at CEMEX
SHIFTing the way we work at CEMEXSHIFTing the way we work at CEMEX
SHIFTing the way we work at CEMEX
 
SQL Joins and Query Optimization
SQL Joins and Query OptimizationSQL Joins and Query Optimization
SQL Joins and Query Optimization
 
Risikomanangement in der Entwicklung
Risikomanangement in der EntwicklungRisikomanangement in der Entwicklung
Risikomanangement in der Entwicklung
 

Similar to CEMEX_SeniorDesignPosterUpdate4.21.3.pptx

Information marketing-weighing systems sales scenarios.usa-en-v1.4
Information marketing-weighing systems sales scenarios.usa-en-v1.4Information marketing-weighing systems sales scenarios.usa-en-v1.4
Information marketing-weighing systems sales scenarios.usa-en-v1.4
Ascorel
 
Mine Engineering project
Mine Engineering projectMine Engineering project
Mine Engineering project
Lawrence Tjale
 

Similar to CEMEX_SeniorDesignPosterUpdate4.21.3.pptx (20)

Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet Management
 
Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MI
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Information marketing-weighing systems sales scenarios.usa-en-v1.4
Information marketing-weighing systems sales scenarios.usa-en-v1.4Information marketing-weighing systems sales scenarios.usa-en-v1.4
Information marketing-weighing systems sales scenarios.usa-en-v1.4
 
Tugger Route Generation - Flow Planner - Dr. Dave Sly
Tugger Route Generation - Flow Planner - Dr. Dave SlyTugger Route Generation - Flow Planner - Dr. Dave Sly
Tugger Route Generation - Flow Planner - Dr. Dave Sly
 
maquinarias.pptx
maquinarias.pptxmaquinarias.pptx
maquinarias.pptx
 
ABB_PT61_V11
ABB_PT61_V11ABB_PT61_V11
ABB_PT61_V11
 
Five questions to ask when selecting cranes for waste-to-energy facilities
Five questions to ask when selecting cranes for waste-to-energy facilitiesFive questions to ask when selecting cranes for waste-to-energy facilities
Five questions to ask when selecting cranes for waste-to-energy facilities
 
Mine Engineering project
Mine Engineering projectMine Engineering project
Mine Engineering project
 
cross docking Project review
cross docking Project reviewcross docking Project review
cross docking Project review
 
himanshu (1)
himanshu (1)himanshu (1)
himanshu (1)
 
aakash101.pptx
aakash101.pptxaakash101.pptx
aakash101.pptx
 
Clc presentation jjb 01.29.2014 fv
Clc presentation jjb 01.29.2014 fvClc presentation jjb 01.29.2014 fv
Clc presentation jjb 01.29.2014 fv
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminal
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
Truck loading and unloading technical specification
Truck loading and unloading technical specificationTruck loading and unloading technical specification
Truck loading and unloading technical specification
 
Shivendra singh
Shivendra singhShivendra singh
Shivendra singh
 
Appointment system tru x_usc_hackathon
Appointment system tru x_usc_hackathonAppointment system tru x_usc_hackathon
Appointment system tru x_usc_hackathon
 
Real time shovel payload feedback for improved productivity, MineWare
Real time shovel payload feedback for improved productivity, MineWare  Real time shovel payload feedback for improved productivity, MineWare
Real time shovel payload feedback for improved productivity, MineWare
 
ISM 2016 A Mining Imperative: Enhanced accuracy of real-time spatial data and...
ISM 2016 A Mining Imperative: Enhanced accuracy of real-time spatial data and...ISM 2016 A Mining Imperative: Enhanced accuracy of real-time spatial data and...
ISM 2016 A Mining Imperative: Enhanced accuracy of real-time spatial data and...
 

CEMEX_SeniorDesignPosterUpdate4.21.3.pptx

  • 1. Abstract Analysis Optimizing Aggregate Production CEMEX Balcones Quarry Arda Onkol, Jonathan Edmunds, Joshua Klein, Fernando Espinosa de los Monteros CEMEX is a global company that specializes in the production and distribution of cement, concrete, aggregates, and related building materials. Balcones Quarry specializes in crushed aggregate, which accounts for 60 to 75% of the volume of ready-mix concrete and is crucial to the properties of the mix. The New Braunfels Quarry seeks to achieve high process efficiency by optimizing the number of haul trucks and loaders, minimizing machine downtime, eliminating wait time, and increasing total material output. The Main Problem In the current quarry setup, there are 3 different rock loading sites serviced by two Caterpillar Loaders 992 and one 993, respectively. Typically, there are eight Caterpillar 777-Series (100 ton) haul trucks that get rocks constantly loaded and unloaded throughout the day. When the haul trucks arrive at the hopper, there is a often a line of at least one or two other trucks waiting to dump. This idle time in the traffic line causes less trips in between sites and the hopper, longer cycle and wait times, and higher costs caused by a potential decrease in material throughput. Bottleneck Identification After creating a flow process chart and studying the time study data provided by CEMEX, we identified activities prior to the haul trucks reaching the hopper that were adding time to the entire process, having an effect on the main bottleneck located at the Dump Zone. The current hopper has a capacity of 50 tons, which causes a delay when the 100 ton capacity haul trucks dump their loads. Simulation and Optimization • For traffic: • Interval/cadence system to help alleviate “all trucks at once” problem. • Outsource an ios /Android application to have the quarry traffic routes and data mine the real vehicle location and routing times. • For time study: • Machines need to be labeled or named for identification purposes. • All data must be kept in same format and electronically. • Revision of current time study sheet. • For equipment: • Acquire another loader so it may replace the lower capacity one. • Acquire or remove a haul truck so hopper can run at full efficiency. • Acquire a hopper that may handle the trucks’ full capacity dump. Solution Recommendations Average Total DT Frequencies Total Time (mins) Cumulative Time Cumulative% Individual% 100 Ton 89 4693 4693 72.52% 72.52% 992 Loader 31 1533 6226 96.21% 23.69% 993 Loader 6 245 6471 100.00% 3.79% Special Thanks To: • Dr. Jesus Jimenez – Industrial Engineering Capstone Faculty Advisor • Dr. Eduardo Perez – Industrial Engineering Faculty Advisor • Dr. Enes Bilgin – Supply Chain Faculty Advisor • Reid Pierson – Engineer at Balcones Quarry Aggregates, CEMEX • Adam Slusser – Operations Manager at Balcones Quarry Aggregates, CEMEX • Freddy Aird – Engineer Quarry Manager at Balcones Quarry Aggregates, CEMEX. Time Study data sheets created to ensure that there are no inconsistencies in record keeping. These include the identification of the truck, operational down time length, the root cause of the down time, maintenance/operational issue details, daily total loads for production, and total weight processed. The truck queue sheet is to record the specific truck service time at the time of arrival at the hopper and queue wait time according to number of trucks at the hopper bottleneck. Based on the previous yearly production data from 2015 and the first 3 months of 2016, a scatter line plot was created to show and compare the current monthly production; theoretical production with the bottleneck and forecasted production for the year was analyzed, assuming no changes in production processes and forecasted production of the CEMEX goal of 45k TONS/day. This graph shows hopper utilization. The work hours and down times calculated from the given data were used to find out how hopper efficiency processes the rocks, since the bottleneck of the operations is present here. The goal is to keep the hopper running as much as possible to increase daily production. A potential removal of a truck and changing hopper capacity will make significant improvements in production level. These pie charts were created from the current data in order to show which machines in operation are causing the most down times and how frequently they fail. With the time study we evaluated the dumping process as a queuing problem with a beta arrival rate, lognormal serving rate with 1 server. Hopper Temporary Dumping Area Using Google Maps to get a birds eye view of the quarry. We mapped out the current traffic routes used by the haul truck drivers. After creating the routes we then used Google Maps again to measure out each section of the routes we created. In order to insure all the route distances are accurately proportional to their real-world counterparts. Process ❖ The data below shows all routes and their distances; along with the reference files. Graphs represent the nine, eight, and seven trucks simulated to achieve maximum number of material throughput on an average daily basis. Graph analytic simulations including two 993 loaders at the furthest work sites. Graph analytic simulations representing the current equipment system. Data generated from the simulation presents that if a new hopper is implemented, with twice the capacity and a new 993 loader at the furthest site, daily throughput will increase to approximately 50 loads per day. The equipment cost and the payment periods are given in the table. An estimated yearly profit after the implementation is calculated after subtracting the equipment yearly costs. • The simulation was created using Sources, Servers, Vehicles, Sink, Paths, Time Paths, and Transfer Nodes. • The Paths, Transfer Nodes, and Time Paths were used to create the traffic routes used by the haul truck. Even though we used paths set to a specific distance we add in time paths to model the backing up process of the haul trucks when entering a loading or dumping area. The paths were set with a speed limit, not to allow passing, choose shortest path or weighted path for intersections, and to check if an intersection was clear before crossing the road (which was triggered as a vehicle entered or exited a node). • The Sources represent the three loading areas in operation by CEMEX, with the Servers marking the each loading area available, and the Sink represents the hopper. The three area we choose to simulate are East wall North, Pavilion Pit, and West Pit dig sites. • The vehicle objects were used to represent the haul trucks. All the loading and unloading logic was put directly into the Vehicle object rather than the servers, to allow more freedom in choosing which dig sites to simulate with the two different types of loaders used by CEMEX. The entity priority request logic was also added to the vehicles.