Standard costing and Variance Analysis

A
Arunkumar DunaAssistant Professor, GFGC, Koppa en Government First Grade College, Koppa
STANDARD COSTING
ARUN KUMAR M.Com., (Ph.D.)
Asst. Professor,
Department of Commerce,
Govt. First Grade College, Koppa
g-mail: arunkumarduna@gmail.com
STANDARD
The term standard is a predetermined measurable quantity set in
defined conditions against which actual performance can be
compared.
In Simple, we can say the term standard refers to predetermined
rate against which performance is judged
STANDARD COST
Standard-cost is defined by CIMA in the following way:—A predetermined calculation of how
much cost should be used under specified working conditions.
In other words, this is theoretically the amount of money a company will have to spend to
produce a product or perform a service under normal conditions
Standard Costing
Standard costing is a technique which is used in many industries,
where production is of repetitive nature.
Standard Costing is the method of measuring the differences
between the costs actually incurred in manufacturing and the
expected costs under “standard condition”, which always refers to
a specific costing rule which serves as the basis.
Variance Analysis
A variance is the difference between the standards and the actual
performance
When the actual results are better than the expected results,
there will be a favourable variance (F)
If the actual results are worse than the expected results, there
will be an adverse variance (A)
Classification Of Variances
Functional Basis
Measurement Basis
Result Basis
Functional Basis
Functional
Basis
Variance related
to Cost factor
Material
Labour
Variance related
to Sales factor Overhead
Measurement Basis
Difference between the
standard cost and the actual
cost in terms of money is
known as absolute variance.
Difference is expressed as a
percentage of the standard
cost, it is known as relative
variance.
Result basis When the actual results are better than the
expected results, there will be a
favourable variance (F)
If the actual results are worse than the
expected results, there will be an adverse
variance (A)
Cost variance
• Cost variance = Price variance + Quantity variance
Cost variance is the difference between the standard cost and the Actual cost
• Price variance = (standard price – actual price)*Actual quantity
A price variance reflects the extent of the profit change resulting from the change in activity
level
• Quantity variance = (standard quantity – actual quantity)* standard
cost
A quantity variance reflects the extent of the profit change resulting from the change in activity level
Three types of cost variance
• Material cost variance
• Labour cost variance
• Variable overheads variance
Material Cost variance
Material Cost Variances
Material Price Variances Material Usage Variances
Material Mix Variance
Material Yield Variance
MATERIAL COST VARIANCE:
Material cost variance is the difference between standard cost and
actual cost. Mathematically it is written as
Formula:
MCV = (SQ × SP) – (AQ × AP)
Material Cost Variance = Standard quantity × Standard Price-(Actual
quantity × Actual Price)
Or
Material Price Variance:
It measures variance arises in the material cost due to difference in actual material
purchase price from standard material price. Mathematically it is written as:
Material Price Variance:
𝐴𝑐𝑡𝑢𝑎𝑙 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 ∗ × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑟𝑖𝑐𝑒 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑖𝑐𝑒)
MPV = AQ x (SP-AP)
Or
*Here actual quantity means actual quantity of material purchased. If in
the question material purchase is not given, it is taken as equal to material
Material Usage Variance:
It measures variance in material cost due to usage/ consumption of
materials. It is computed as well
Material Usage Variance:
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒 × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) ∗
MUV: SP (SQ − AQ)
Or
*Here actual quantity means actual quantity of material used
Material Mix Variance:
Variance in material consumption may arise due to difference in proportion
used actually from the standard mix/ proportion. It arises only when two
more inputs are used to produce a product.
Material Mix Variance = (Revised standard quantity – Actual quantity) × Standard price
Or
MMV= (RSQ – AQ) × SP
Where;
RSQ =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑜𝑛𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
𝑻𝒐𝒕𝒂𝒍 𝑜𝑓 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝐴𝑙𝑙 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
× Total of Actual of all material
Material Yield Variance (or Material Sub-usage Variance):
Variance in material consumption which arise due to yield or productivity of the inputs.
It may arise due to use of sub-standard quality of materials, inefficiency of workers or
due to wrong processing.
Material Revised Usage Variance =
(𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒
Or
MRUV = (SQ – RSQ) SP
Material Yield Variance:
(𝐴𝑐𝑡𝑢𝑎𝑙 𝑌𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑌𝑖𝑒𝑙𝑑) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑟𝑖𝑐𝑒
Or
MYV = (AY – SY) SOP
Verification of the Formula:
Material Cost Variance = Material Usage Variance + Material
Price Variance*
Or
Material Cost Variance = (Material Mix Variance + Material
Revised usage Variance) +Material price variance
*If material purchase quantity and material consumed quantity is same
The Standard material required to manufacture one unit of product
‘X’ is 10 Kgs, and the standard price per kg of material is ₹ 25 Kgs.
The cost account records, however reveals that 11,500 Kgs,
Materials costing ₹ 2, 76,000 were used for manufacture of 1,000
units of product ‘X’. Calculate material variances.
Illustration 1
Calculation of Material Variance
 Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)
 Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)
 Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃
Given:
SQ: For Production of 1 unit Required 10 Kgs of Material
There fore for 1000 units = 1000 × 10 = 10,000 Kgs
AQ: 11,500 Kgs
SP: ₹ 25
AP: ₹ 24 ( 2,76,000/11,500Kgs)
The Standard material required to
manufacture one unit of product ‘X’ is 10
Kgs, and the standard price per kg of
material is ₹ 25 Kgs. The cost account
records, however reveals that 11,500 Kgs,
Materials costing ₹ 2, 76,000 were used for
manufacture of 1,000 units of product ‘X’.
= (10,000Kgs× ₹ 25) – (11,500 × ₹24)
= 2,50,000 – 2,76,000
= ₹ 26,000(A)
= (25 – 24) × 11,500
= 1 × 11,500
= ₹ 11,500 (F)
= (10,000 – 11,500) × 25
= (- 1,500) × 25
= ₹ 37,500 (A)
SQ: 10,000 Kgs
AQ : 11,500 Kgs
SP: ₹ 25
AP: ₹ 24
MCV = (SQ × SP) – (AQ × AP)
MPV = (SP – AP) × AQ
MUV = (SQ – AQ) × SP
Darling Company limited works on the standard costing system and
produces X. The standard estimates of material for the manufacturer
of 1,000 units of product X is 400 Kgs at ₹ 2.5 per kg. In the month
of January 2018, manufactured 2,000 units of product X and it is
found that 820 Kgs of material is consumed at ₹ 2.60 per kg.
Calculate - Material Variance
Illustration 2
Calculation of Material Variance
 Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)
 Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)
 Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃
Given:
SQ = for 1000 units need 400 kgs = for 2000 units
400
1000
× 2,000 = 800
AQ = 820 kgs for 2000 units
SP = ₹ 2.5
AP = ₹ 2.6
The standard estimates of material for
the manufacturer of 1,000 units of
product X is 400 Kgs at ₹ 2.5 per kg. In
the month of January 2018,
manufactured 2,000 units of product X
and it is found that 820 Kgs of material
is consumed at ₹ 2.60 per kg.
= (800 × 2.50) – (820 × 2.60)
= 2,000 – 2132
= 132 (A)
= (2.50 – 2.60) × 820
= ( - 0.10) × 820
= 82 (A)
= (800 – 820) × 2.50
= (- 20) – 2.5
= 50 (A)
SQ: 800
AQ: 820
SP: ₹ 2.5
AP: ₹ 2.6
MCV = (SQ × SP) – (AQ × AP)
MPV = (SP – AP) × AQ
MUV = (SQ – AQ) ×SP
LABOUR VARIANCE
LABOUR COST VARIANCE
Labour cost variance is the difference between standard
labour cost allowed for actual output achieved and actual
labour cost. It is also known as wages variance.
(𝑆𝑡𝑑. ℎ𝑜𝑢𝑟 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟) − (𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠
× 𝐴𝑐𝑡𝑢𝑎𝑙 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟)
Labour Cost Variance:
𝐿𝑎𝑏𝑜𝑢𝑟 𝐶𝑜𝑠𝑡 Variance = St. Labour Cost for actual output − Actual labour cost
or
Labour Cost Variance
Labour Efficiency Variance
Labour Yield VarianceIdle- Time VarianceLabour Mix Variance
Labour Rate Variance
Classification of Labour Cost Variance
Labour Rate (Pay) Variance
Labour rate variance arises due to “difference in actual rate paid
from standard rate”
Labour Rate Variance = (Std. Rate - Actual Rate) × Actual Hours
Labour Efficiency (Time) Variance
Labour efficiency variance arises due to “deviation in the
working hour from the set standard”
Labour Efficiency Variance:
𝑆𝑡𝑑. 𝑅𝑎𝑡𝑒 (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠) ∗
*Actual time worked
Idle Time Variance
Idle Time Variance is calculated for the unproductive
labour hours. Here idle time means labour idle time arises
due to abnormal
Idle Time Variance:𝐼𝑑𝑒𝑙 ℎ𝑜𝑢𝑟𝑠 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 (or) ITV = IH × SR
Labour Mix Variance - (Gang Composition
Variance):
Labour Mix variance which arises due to change in the proportion
or combination of different skill set i.e. number of skilled workers,
semi-skilled workers and un-skilled workers.
Labour Mix Variance:(𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 − 𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠) × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒
Revised Standard Hours:
𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒
𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠
× 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠
Labour Yield Variance
Labour Yield variance which arises due to productivity
of workers
Labour Yield Variance:
𝐴𝑐𝑡𝑢𝑎𝑙 𝑦𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑑. 𝑌𝑖𝑒𝑙𝑑 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑖𝑛𝑝𝑢𝑡 𝑆𝑡𝑑. 𝐿𝑎𝑏𝑜𝑢𝑟 𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑜𝑓 𝑜𝑢𝑡𝑝𝑢𝑡
Labour Revised Efficiency Variance:
(𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝑟𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠) 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒
Or
Dept. A
Actual direct wages ₹ 2,000
Standard hours 8,000
Standard rate per hour ₹ 30 paise
Actual hours worked 8,200
From the following, calculate labour variances of department A
Given:
SH : 8000
SR: ₹ 0.30
AH : 8200
AR: ?
AR = 𝐴𝑐𝑡𝑢𝑎𝑙 𝐷𝑖𝑟𝑒𝑐𝑡 𝑊𝑎𝑔𝑒𝑠
𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘𝑒𝑑
= ₹ 2000
8200 ℎ𝑜𝑢𝑟𝑠
AR= 0.2439AR: ₹ 0.2439
ILLUSTRATION
Calculation of Labour variance
= (8,000 Hr × ₹0.30) – (8,200 Hr × ₹0.2439)
= ₹ 2400 – ₹ 2,000
= ₹ 400(F)
1. Labour cost variance = (SH × SR) – (AH × AR)
2. Labour rate (pay) variance = (SR – AR) × AH
3. Labour efficiency (time) variance = (SH – AH) × SR
LCV = (SH × SR) – (AH × AR)
SH : 8000
SR: ₹ 0.30
AH : 8200
AR: ₹ 0.2439
= (₹ 0.30 – ₹ 0.2439) × 8200 Hr
= ₹ .00561 × 8200 Hr
= 460 (F)
= (8000 – 8200) × ₹ 0.30
= (-200) × 0.30
= 60 (A)
LPV = (SR – AR) × AH
LEV = (SH – AH) × SR
Labour Cost Variance 400 (F)
Labour Efficiency (Time) Variance 60 (A)Labour Rate Variance 460 (F)
The information regarding composition and the weekly wages rates of labour force
engaged on a job scheduled to be completed in 60 weeks are as follows:
Types of labour
Standard Actual
No. of workers
Weekly wage rate
per hour
No. of workers
Weekly wage
rate per hour
Skilled 75 60 70 70
Semi-skilled 45 40 30 50
Unskilled 60 30 80 20
The work completed in 62 weeks.
Calculate:
(a) Labour cost variance
(b) Labour rate variance
(c) Labor efficiency variance
(d) Labour mix variance
ILLUSTRATION
Workers
Standard Mix
Hours
(No. of Workers × 60
Weeks)
Rate Per Hour Cost
Skilled 75 × 60 = 4,500 60 2,70,000
Semi-Skilled 45 × 60 = 2,700 40 1,08,000
Unskilled 60 × 60 = 3,600 30 1,08,000
Total 10,800 4,86,000
Calculation of Labour Variance:
Workers
Actual Mix
Hours
(No. of Workers ×
62 Weeks)
Rate Per Hour Cost
Skilled 70 × 62 = 4,340 70 3,03,800
Semi-Skilled 30 × 62 = 1,860 50 93,000
Unskilled 80 × 62 = 4,960 20 99,200
Total 11,160 4,96,000
Labour Cost Variance
LCV = SC - AC = ₹
Skilled = 2,70,000 - 3,03,000 = 33,800(A)
Semi- Skilled = 1,08,000 - 93,000 = 15,000 (F)
Unskilled = 1,08,000 - 99,200 = 8,800 (F)
= 10,000(A)
Labour Rate (Pay) Variance:
LRV = (SR – AR) × AH = ₹
Skilled = (60 – 70) × 4,340 = 43,400(A)
Semi- Skilled = (40 – 50) × 1,860 = 18,600 (A)
Unskilled = (30 – 20) × 4,960 = 49,600 (F)
=12,400 (A)
Labour Efficiency Variance:
LEV = (SH – AH) × SR = ₹
Skilled = (4,500 – 4,340) × 60 = 9,600 (F)
Semi- Skilled = (2,700 – 1,860) × 40 = 33,600 (F)
Unskilled = (3,600 – 4,960) × 30 = 40,800 (A)
= 2,400 (F)
Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹
Revised Standard Hours:
𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒
𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠
× 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠
Unskilled =
3,600
10,800
× 11,160 = 3,720
Skilled =
4,500
10,800
× 11,160 = 4,650
Semi skilled =
2,700
10,800
× 11,160 = 2,790
Workers
Standard Mix Actual Mix
Hours
(No. of Workers × 60 Weeks)
Hours
(No. of Workers × 62 Weeks)
Skilled 4,500 4,340
Semi-Skilled 2,700 1,860
Skilled 3,600 4,960
Total 10,800 11,160
Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹
LMV = (RST – AT) × SR = ₹
Skilled = (4,650 – 4,340) × 60 = 18,600 (F)
Semi- Skilled = (2,790 – 1,860) × 40 = 37,200 (F)
Unskilled = (3,720 – 4,960) × 30 = 37,200 (A)
LCV Rs. 10,000 (A)
LRV Rs. 12,400(A) LEV 2,400 (F)
Thank You
1 de 42

Recomendados

Standard costs and variance analysis por
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysisSumit Malhotra
36K vistas17 diapositivas
Variance Analysis por
Variance AnalysisVariance Analysis
Variance AnalysisDr. Rana Singh
49.4K vistas64 diapositivas
Chapter 07 Marginal Costing por
Chapter 07   Marginal CostingChapter 07   Marginal Costing
Chapter 07 Marginal Costingayanthimadhumali
14.5K vistas41 diapositivas
Ca chap 13 standard costing&variance analysis(2) por
Ca chap 13 standard costing&variance analysis(2)Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)DSDEVDA
16.9K vistas64 diapositivas
Standard costing por
Standard costingStandard costing
Standard costingabner domingo
2.6K vistas24 diapositivas
Standard costing por
Standard costingStandard costing
Standard costingSamitha Jayaweera
6.9K vistas24 diapositivas

Más contenido relacionado

La actualidad más candente

marginal and absorption costing por
marginal and absorption costingmarginal and absorption costing
marginal and absorption costingsangeeta saini
5.8K vistas18 diapositivas
Absorption Costing and Marginal Costing ppt por
Absorption Costing and Marginal Costing pptAbsorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing pptVaseemParry
1.1K vistas16 diapositivas
Standard costing presentation por
Standard costing presentationStandard costing presentation
Standard costing presentationJay Singh
43.5K vistas54 diapositivas
Cost of capital por
Cost of capitalCost of capital
Cost of capitalVisakhapatnam
13.4K vistas48 diapositivas
Lecture 2 Cost Terminology and Classification por
Lecture 2 Cost Terminology and ClassificationLecture 2 Cost Terminology and Classification
Lecture 2 Cost Terminology and ClassificationRiri Ariyanty
1.9K vistas23 diapositivas
Variance Analysis por
Variance AnalysisVariance Analysis
Variance AnalysisDr. Rana Singh
97.9K vistas63 diapositivas

La actualidad más candente(20)

marginal and absorption costing por sangeeta saini
marginal and absorption costingmarginal and absorption costing
marginal and absorption costing
sangeeta saini5.8K vistas
Absorption Costing and Marginal Costing ppt por VaseemParry
Absorption Costing and Marginal Costing pptAbsorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing ppt
VaseemParry1.1K vistas
Standard costing presentation por Jay Singh
Standard costing presentationStandard costing presentation
Standard costing presentation
Jay Singh43.5K vistas
Lecture 2 Cost Terminology and Classification por Riri Ariyanty
Lecture 2 Cost Terminology and ClassificationLecture 2 Cost Terminology and Classification
Lecture 2 Cost Terminology and Classification
Riri Ariyanty1.9K vistas
Process costing por Kalpita1702
Process costingProcess costing
Process costing
Kalpita170216.5K vistas
Cost Behavior Analysis por JhOnie JhOan
Cost Behavior AnalysisCost Behavior Analysis
Cost Behavior Analysis
JhOnie JhOan19.4K vistas
Costing for material labour and overhead por ankita bhan
Costing for material labour and overheadCosting for material labour and overhead
Costing for material labour and overhead
ankita bhan10.3K vistas
Process costing por Prem Chand
Process costingProcess costing
Process costing
Prem Chand8.7K vistas
Cost Accounting por ashu1983
Cost AccountingCost Accounting
Cost Accounting
ashu1983151K vistas
Standard costing por zaidul2
Standard costingStandard costing
Standard costing
zaidul247.6K vistas
Managerial Accounting ed 15 Chapter 10 por SharonLong
Managerial Accounting ed 15 Chapter 10Managerial Accounting ed 15 Chapter 10
Managerial Accounting ed 15 Chapter 10
SharonLong9.7K vistas

Similar a Standard costing and Variance Analysis

Projecto variance por
Projecto varianceProjecto variance
Projecto varianceMarcos Rodriguez
2.5K vistas48 diapositivas
Akaun Chapter 11 por
Akaun Chapter 11Akaun Chapter 11
Akaun Chapter 11WanBK Leo
2.1K vistas34 diapositivas
Standard Costing por
Standard Costing Standard Costing
Standard Costing Nitin Parbhakar
4.6K vistas35 diapositivas
Standard-Costing-Variance-Analysis.ppt por
Standard-Costing-Variance-Analysis.pptStandard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.pptJomarDoctora
29 vistas34 diapositivas
Variance analysis por
Variance analysisVariance analysis
Variance analysissai precious
14.2K vistas13 diapositivas
Amresh management accounting por
Amresh management accountingAmresh management accounting
Amresh management accountingAMRESH VELGEKAR
953 vistas20 diapositivas

Similar a Standard costing and Variance Analysis(20)

Akaun Chapter 11 por WanBK Leo
Akaun Chapter 11Akaun Chapter 11
Akaun Chapter 11
WanBK Leo2.1K vistas
Standard-Costing-Variance-Analysis.ppt por JomarDoctora
Standard-Costing-Variance-Analysis.pptStandard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.ppt
JomarDoctora29 vistas
Variance analysis por sai precious
Variance analysisVariance analysis
Variance analysis
sai precious 14.2K vistas
Standard cost, labor & material variance por Awais052
Standard cost, labor & material varianceStandard cost, labor & material variance
Standard cost, labor & material variance
Awais0523.6K vistas
Stdcostingppt por Taha Rais
StdcostingpptStdcostingppt
Stdcostingppt
Taha Rais2.1K vistas
Standard costing and variances por pankajmaini
Standard costing and variancesStandard costing and variances
Standard costing and variances
pankajmaini2.9K vistas
Standard Costing Operational Performance Measures And por afiali
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures And
afiali3.1K vistas
Lecture_5_-_Standard_Costing_and_variance_analysis.pdf por NeoRamalivhana
Lecture_5_-_Standard_Costing_and_variance_analysis.pdfLecture_5_-_Standard_Costing_and_variance_analysis.pdf
Lecture_5_-_Standard_Costing_and_variance_analysis.pdf
NeoRamalivhana16 vistas
Standard costing por ramla khan
Standard costingStandard costing
Standard costing
ramla khan46 vistas
Understanding SAP production order variance por Dhaval Gala
Understanding SAP production order varianceUnderstanding SAP production order variance
Understanding SAP production order variance
Dhaval Gala3.7K vistas

Último

Solar System and Galaxies.pptx por
Solar System and Galaxies.pptxSolar System and Galaxies.pptx
Solar System and Galaxies.pptxDrHafizKosar
85 vistas26 diapositivas
Google solution challenge..pptx por
Google solution challenge..pptxGoogle solution challenge..pptx
Google solution challenge..pptxChitreshGyanani1
98 vistas18 diapositivas
Are we onboard yet University of Sussex.pptx por
Are we onboard yet University of Sussex.pptxAre we onboard yet University of Sussex.pptx
Are we onboard yet University of Sussex.pptxJisc
77 vistas7 diapositivas
The basics - information, data, technology and systems.pdf por
The basics - information, data, technology and systems.pdfThe basics - information, data, technology and systems.pdf
The basics - information, data, technology and systems.pdfJonathanCovena1
88 vistas1 diapositiva
The Open Access Community Framework (OACF) 2023 (1).pptx por
The Open Access Community Framework (OACF) 2023 (1).pptxThe Open Access Community Framework (OACF) 2023 (1).pptx
The Open Access Community Framework (OACF) 2023 (1).pptxJisc
85 vistas7 diapositivas

Último(20)

Solar System and Galaxies.pptx por DrHafizKosar
Solar System and Galaxies.pptxSolar System and Galaxies.pptx
Solar System and Galaxies.pptx
DrHafizKosar85 vistas
Are we onboard yet University of Sussex.pptx por Jisc
Are we onboard yet University of Sussex.pptxAre we onboard yet University of Sussex.pptx
Are we onboard yet University of Sussex.pptx
Jisc77 vistas
The basics - information, data, technology and systems.pdf por JonathanCovena1
The basics - information, data, technology and systems.pdfThe basics - information, data, technology and systems.pdf
The basics - information, data, technology and systems.pdf
JonathanCovena188 vistas
The Open Access Community Framework (OACF) 2023 (1).pptx por Jisc
The Open Access Community Framework (OACF) 2023 (1).pptxThe Open Access Community Framework (OACF) 2023 (1).pptx
The Open Access Community Framework (OACF) 2023 (1).pptx
Jisc85 vistas
Narration ppt.pptx por TARIQ KHAN
Narration  ppt.pptxNarration  ppt.pptx
Narration ppt.pptx
TARIQ KHAN119 vistas
The Accursed House by Émile Gaboriau por DivyaSheta
The Accursed House  by Émile GaboriauThe Accursed House  by Émile Gaboriau
The Accursed House by Émile Gaboriau
DivyaSheta158 vistas
JiscOAWeek_LAIR_slides_October2023.pptx por Jisc
JiscOAWeek_LAIR_slides_October2023.pptxJiscOAWeek_LAIR_slides_October2023.pptx
JiscOAWeek_LAIR_slides_October2023.pptx
Jisc79 vistas
Class 10 English notes 23-24.pptx por TARIQ KHAN
Class 10 English notes 23-24.pptxClass 10 English notes 23-24.pptx
Class 10 English notes 23-24.pptx
TARIQ KHAN107 vistas
Psychology KS5 por WestHatch
Psychology KS5Psychology KS5
Psychology KS5
WestHatch77 vistas
Class 10 English lesson plans por TARIQ KHAN
Class 10 English  lesson plansClass 10 English  lesson plans
Class 10 English lesson plans
TARIQ KHAN257 vistas
AI Tools for Business and Startups por Svetlin Nakov
AI Tools for Business and StartupsAI Tools for Business and Startups
AI Tools for Business and Startups
Svetlin Nakov101 vistas
Education and Diversity.pptx por DrHafizKosar
Education and Diversity.pptxEducation and Diversity.pptx
Education and Diversity.pptx
DrHafizKosar118 vistas
Psychology KS4 por WestHatch
Psychology KS4Psychology KS4
Psychology KS4
WestHatch68 vistas

Standard costing and Variance Analysis

  • 1. STANDARD COSTING ARUN KUMAR M.Com., (Ph.D.) Asst. Professor, Department of Commerce, Govt. First Grade College, Koppa g-mail: arunkumarduna@gmail.com
  • 2. STANDARD The term standard is a predetermined measurable quantity set in defined conditions against which actual performance can be compared. In Simple, we can say the term standard refers to predetermined rate against which performance is judged
  • 3. STANDARD COST Standard-cost is defined by CIMA in the following way:—A predetermined calculation of how much cost should be used under specified working conditions. In other words, this is theoretically the amount of money a company will have to spend to produce a product or perform a service under normal conditions
  • 4. Standard Costing Standard costing is a technique which is used in many industries, where production is of repetitive nature. Standard Costing is the method of measuring the differences between the costs actually incurred in manufacturing and the expected costs under “standard condition”, which always refers to a specific costing rule which serves as the basis.
  • 5. Variance Analysis A variance is the difference between the standards and the actual performance When the actual results are better than the expected results, there will be a favourable variance (F) If the actual results are worse than the expected results, there will be an adverse variance (A)
  • 6. Classification Of Variances Functional Basis Measurement Basis Result Basis
  • 7. Functional Basis Functional Basis Variance related to Cost factor Material Labour Variance related to Sales factor Overhead
  • 8. Measurement Basis Difference between the standard cost and the actual cost in terms of money is known as absolute variance. Difference is expressed as a percentage of the standard cost, it is known as relative variance.
  • 9. Result basis When the actual results are better than the expected results, there will be a favourable variance (F) If the actual results are worse than the expected results, there will be an adverse variance (A)
  • 10. Cost variance • Cost variance = Price variance + Quantity variance Cost variance is the difference between the standard cost and the Actual cost • Price variance = (standard price – actual price)*Actual quantity A price variance reflects the extent of the profit change resulting from the change in activity level • Quantity variance = (standard quantity – actual quantity)* standard cost A quantity variance reflects the extent of the profit change resulting from the change in activity level
  • 11. Three types of cost variance • Material cost variance • Labour cost variance • Variable overheads variance
  • 12. Material Cost variance Material Cost Variances Material Price Variances Material Usage Variances Material Mix Variance Material Yield Variance
  • 13. MATERIAL COST VARIANCE: Material cost variance is the difference between standard cost and actual cost. Mathematically it is written as Formula: MCV = (SQ × SP) – (AQ × AP) Material Cost Variance = Standard quantity × Standard Price-(Actual quantity × Actual Price) Or
  • 14. Material Price Variance: It measures variance arises in the material cost due to difference in actual material purchase price from standard material price. Mathematically it is written as: Material Price Variance: 𝐴𝑐𝑡𝑢𝑎𝑙 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 ∗ × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑟𝑖𝑐𝑒 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑖𝑐𝑒) MPV = AQ x (SP-AP) Or *Here actual quantity means actual quantity of material purchased. If in the question material purchase is not given, it is taken as equal to material
  • 15. Material Usage Variance: It measures variance in material cost due to usage/ consumption of materials. It is computed as well Material Usage Variance: 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒 × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) ∗ MUV: SP (SQ − AQ) Or *Here actual quantity means actual quantity of material used
  • 16. Material Mix Variance: Variance in material consumption may arise due to difference in proportion used actually from the standard mix/ proportion. It arises only when two more inputs are used to produce a product. Material Mix Variance = (Revised standard quantity – Actual quantity) × Standard price Or MMV= (RSQ – AQ) × SP Where; RSQ = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑜𝑛𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑻𝒐𝒕𝒂𝒍 𝑜𝑓 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝐴𝑙𝑙 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 × Total of Actual of all material
  • 17. Material Yield Variance (or Material Sub-usage Variance): Variance in material consumption which arise due to yield or productivity of the inputs. It may arise due to use of sub-standard quality of materials, inefficiency of workers or due to wrong processing. Material Revised Usage Variance = (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒 Or MRUV = (SQ – RSQ) SP Material Yield Variance: (𝐴𝑐𝑡𝑢𝑎𝑙 𝑌𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑌𝑖𝑒𝑙𝑑) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑟𝑖𝑐𝑒 Or MYV = (AY – SY) SOP
  • 18. Verification of the Formula: Material Cost Variance = Material Usage Variance + Material Price Variance* Or Material Cost Variance = (Material Mix Variance + Material Revised usage Variance) +Material price variance *If material purchase quantity and material consumed quantity is same
  • 19. The Standard material required to manufacture one unit of product ‘X’ is 10 Kgs, and the standard price per kg of material is ₹ 25 Kgs. The cost account records, however reveals that 11,500 Kgs, Materials costing ₹ 2, 76,000 were used for manufacture of 1,000 units of product ‘X’. Calculate material variances. Illustration 1
  • 20. Calculation of Material Variance  Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)  Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)  Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃 Given: SQ: For Production of 1 unit Required 10 Kgs of Material There fore for 1000 units = 1000 × 10 = 10,000 Kgs AQ: 11,500 Kgs SP: ₹ 25 AP: ₹ 24 ( 2,76,000/11,500Kgs) The Standard material required to manufacture one unit of product ‘X’ is 10 Kgs, and the standard price per kg of material is ₹ 25 Kgs. The cost account records, however reveals that 11,500 Kgs, Materials costing ₹ 2, 76,000 were used for manufacture of 1,000 units of product ‘X’.
  • 21. = (10,000Kgs× ₹ 25) – (11,500 × ₹24) = 2,50,000 – 2,76,000 = ₹ 26,000(A) = (25 – 24) × 11,500 = 1 × 11,500 = ₹ 11,500 (F) = (10,000 – 11,500) × 25 = (- 1,500) × 25 = ₹ 37,500 (A) SQ: 10,000 Kgs AQ : 11,500 Kgs SP: ₹ 25 AP: ₹ 24 MCV = (SQ × SP) – (AQ × AP) MPV = (SP – AP) × AQ MUV = (SQ – AQ) × SP
  • 22. Darling Company limited works on the standard costing system and produces X. The standard estimates of material for the manufacturer of 1,000 units of product X is 400 Kgs at ₹ 2.5 per kg. In the month of January 2018, manufactured 2,000 units of product X and it is found that 820 Kgs of material is consumed at ₹ 2.60 per kg. Calculate - Material Variance Illustration 2
  • 23. Calculation of Material Variance  Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)  Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)  Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃 Given: SQ = for 1000 units need 400 kgs = for 2000 units 400 1000 × 2,000 = 800 AQ = 820 kgs for 2000 units SP = ₹ 2.5 AP = ₹ 2.6 The standard estimates of material for the manufacturer of 1,000 units of product X is 400 Kgs at ₹ 2.5 per kg. In the month of January 2018, manufactured 2,000 units of product X and it is found that 820 Kgs of material is consumed at ₹ 2.60 per kg.
  • 24. = (800 × 2.50) – (820 × 2.60) = 2,000 – 2132 = 132 (A) = (2.50 – 2.60) × 820 = ( - 0.10) × 820 = 82 (A) = (800 – 820) × 2.50 = (- 20) – 2.5 = 50 (A) SQ: 800 AQ: 820 SP: ₹ 2.5 AP: ₹ 2.6 MCV = (SQ × SP) – (AQ × AP) MPV = (SP – AP) × AQ MUV = (SQ – AQ) ×SP
  • 26. LABOUR COST VARIANCE Labour cost variance is the difference between standard labour cost allowed for actual output achieved and actual labour cost. It is also known as wages variance. (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟) − (𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠 × 𝐴𝑐𝑡𝑢𝑎𝑙 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟) Labour Cost Variance: 𝐿𝑎𝑏𝑜𝑢𝑟 𝐶𝑜𝑠𝑡 Variance = St. Labour Cost for actual output − Actual labour cost or
  • 27. Labour Cost Variance Labour Efficiency Variance Labour Yield VarianceIdle- Time VarianceLabour Mix Variance Labour Rate Variance Classification of Labour Cost Variance
  • 28. Labour Rate (Pay) Variance Labour rate variance arises due to “difference in actual rate paid from standard rate” Labour Rate Variance = (Std. Rate - Actual Rate) × Actual Hours
  • 29. Labour Efficiency (Time) Variance Labour efficiency variance arises due to “deviation in the working hour from the set standard” Labour Efficiency Variance: 𝑆𝑡𝑑. 𝑅𝑎𝑡𝑒 (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠) ∗ *Actual time worked
  • 30. Idle Time Variance Idle Time Variance is calculated for the unproductive labour hours. Here idle time means labour idle time arises due to abnormal Idle Time Variance:𝐼𝑑𝑒𝑙 ℎ𝑜𝑢𝑟𝑠 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 (or) ITV = IH × SR
  • 31. Labour Mix Variance - (Gang Composition Variance): Labour Mix variance which arises due to change in the proportion or combination of different skill set i.e. number of skilled workers, semi-skilled workers and un-skilled workers. Labour Mix Variance:(𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 − 𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠) × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 Revised Standard Hours: 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒 𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠 × 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠
  • 32. Labour Yield Variance Labour Yield variance which arises due to productivity of workers Labour Yield Variance: 𝐴𝑐𝑡𝑢𝑎𝑙 𝑦𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑑. 𝑌𝑖𝑒𝑙𝑑 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑖𝑛𝑝𝑢𝑡 𝑆𝑡𝑑. 𝐿𝑎𝑏𝑜𝑢𝑟 𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑜𝑓 𝑜𝑢𝑡𝑝𝑢𝑡 Labour Revised Efficiency Variance: (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝑟𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠) 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 Or
  • 33. Dept. A Actual direct wages ₹ 2,000 Standard hours 8,000 Standard rate per hour ₹ 30 paise Actual hours worked 8,200 From the following, calculate labour variances of department A Given: SH : 8000 SR: ₹ 0.30 AH : 8200 AR: ? AR = 𝐴𝑐𝑡𝑢𝑎𝑙 𝐷𝑖𝑟𝑒𝑐𝑡 𝑊𝑎𝑔𝑒𝑠 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘𝑒𝑑 = ₹ 2000 8200 ℎ𝑜𝑢𝑟𝑠 AR= 0.2439AR: ₹ 0.2439 ILLUSTRATION
  • 34. Calculation of Labour variance = (8,000 Hr × ₹0.30) – (8,200 Hr × ₹0.2439) = ₹ 2400 – ₹ 2,000 = ₹ 400(F) 1. Labour cost variance = (SH × SR) – (AH × AR) 2. Labour rate (pay) variance = (SR – AR) × AH 3. Labour efficiency (time) variance = (SH – AH) × SR LCV = (SH × SR) – (AH × AR) SH : 8000 SR: ₹ 0.30 AH : 8200 AR: ₹ 0.2439
  • 35. = (₹ 0.30 – ₹ 0.2439) × 8200 Hr = ₹ .00561 × 8200 Hr = 460 (F) = (8000 – 8200) × ₹ 0.30 = (-200) × 0.30 = 60 (A) LPV = (SR – AR) × AH LEV = (SH – AH) × SR Labour Cost Variance 400 (F) Labour Efficiency (Time) Variance 60 (A)Labour Rate Variance 460 (F)
  • 36. The information regarding composition and the weekly wages rates of labour force engaged on a job scheduled to be completed in 60 weeks are as follows: Types of labour Standard Actual No. of workers Weekly wage rate per hour No. of workers Weekly wage rate per hour Skilled 75 60 70 70 Semi-skilled 45 40 30 50 Unskilled 60 30 80 20 The work completed in 62 weeks. Calculate: (a) Labour cost variance (b) Labour rate variance (c) Labor efficiency variance (d) Labour mix variance ILLUSTRATION
  • 37. Workers Standard Mix Hours (No. of Workers × 60 Weeks) Rate Per Hour Cost Skilled 75 × 60 = 4,500 60 2,70,000 Semi-Skilled 45 × 60 = 2,700 40 1,08,000 Unskilled 60 × 60 = 3,600 30 1,08,000 Total 10,800 4,86,000 Calculation of Labour Variance: Workers Actual Mix Hours (No. of Workers × 62 Weeks) Rate Per Hour Cost Skilled 70 × 62 = 4,340 70 3,03,800 Semi-Skilled 30 × 62 = 1,860 50 93,000 Unskilled 80 × 62 = 4,960 20 99,200 Total 11,160 4,96,000
  • 38. Labour Cost Variance LCV = SC - AC = ₹ Skilled = 2,70,000 - 3,03,000 = 33,800(A) Semi- Skilled = 1,08,000 - 93,000 = 15,000 (F) Unskilled = 1,08,000 - 99,200 = 8,800 (F) = 10,000(A) Labour Rate (Pay) Variance: LRV = (SR – AR) × AH = ₹ Skilled = (60 – 70) × 4,340 = 43,400(A) Semi- Skilled = (40 – 50) × 1,860 = 18,600 (A) Unskilled = (30 – 20) × 4,960 = 49,600 (F) =12,400 (A)
  • 39. Labour Efficiency Variance: LEV = (SH – AH) × SR = ₹ Skilled = (4,500 – 4,340) × 60 = 9,600 (F) Semi- Skilled = (2,700 – 1,860) × 40 = 33,600 (F) Unskilled = (3,600 – 4,960) × 30 = 40,800 (A) = 2,400 (F) Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹
  • 40. Revised Standard Hours: 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒 𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠 × 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠 Unskilled = 3,600 10,800 × 11,160 = 3,720 Skilled = 4,500 10,800 × 11,160 = 4,650 Semi skilled = 2,700 10,800 × 11,160 = 2,790 Workers Standard Mix Actual Mix Hours (No. of Workers × 60 Weeks) Hours (No. of Workers × 62 Weeks) Skilled 4,500 4,340 Semi-Skilled 2,700 1,860 Skilled 3,600 4,960 Total 10,800 11,160
  • 41. Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹 LMV = (RST – AT) × SR = ₹ Skilled = (4,650 – 4,340) × 60 = 18,600 (F) Semi- Skilled = (2,790 – 1,860) × 40 = 37,200 (F) Unskilled = (3,720 – 4,960) × 30 = 37,200 (A) LCV Rs. 10,000 (A) LRV Rs. 12,400(A) LEV 2,400 (F)