PROCUREMENT
PROCEDURES AS PER
CVC GUIDELINES
DEBENDRA KUMAR SAHU
DY MATERIALS MANAGER
VISAKHAPATNAM PORT TRUST
PROCUREMENT
Procurement is the process of purchasing goods or
services and is usually in reference to business
spending, which is usually involves several areas of
a company/bussiness.
VIGILANCE GUIDELINES
Vigilance is the state of being watchful or alert for
possible danger or difficulties or some other kind of
trouble.
Vigilance guidelines is the guidelines issued by the CVC
from time to time to avoid dangers, difficulties and
troubles in tendering process for better transparency and
competition
PROCUREMENT
PROCEDURES
A procurement process is a series of steps that an
organization identifies and follows in order to obtain
goods or services for their goals and objectives.
Step 1 – Needs Recognition.
Step 2 – Purchase Requisition.
Step 3 – Requisition review.
Step 4 – Selection of vendors and market.
Step 5 – Bid invitation and evaluation.
Stap 6- Negotiate price and terms.
Step 7 – Finalisation of the Purchase Order/contract.
Step 8- Receipt and inspection of the delivered goods.
Step 9 – Receipt of Invoice and Process of Payment.
Step 10 – Delivery and Audit of the Order.
Step 11- Dispute management.
Step 12 – Maintain Accurate Record.
TENDER
Tendering usually refers to the process whereby
governments and financial institutions invite
contractors to place a bid for work on a construction
project or materials supply that must be submitted
within a finite deadline.
WHY
TENDERING ????
FUNDAMENTALPRINCIPLE OF PUBLIC BUYING
(A) Procurement of goods in Public
Interest –
i. Efficiency
,
ii. Economy,
iii. Transparency
(B) Fair &Equitable treatment of suppliers
(C)Promotion of Competition
PUBLIC PROCUREMENT : YARDSTICKS
—
Specifications in terms of quality
—
Need based procurement (avoid
excess)
—
Fair
,Reasonable &Transparent
procedure
—
Procurement VsRequirement
—
Reasonableness of Rate
—
Each stage of procurement should be
recorded
5 R’s OF PROCUREMENT
i) Right Quality
ii) Right Quantity
iii) Right Price.
v) Right Time and Place
v) Right Source
PUBLIC PROCUREMENT CYCLE
i) Need Assessment: Need assessment, formulation
of Specifications and Procurement Planning;
ii) Bid Invitation: Preparing bid documents,
publication, receipt and opening of bids;
iii) Bid Evaluation: Evaluation of bids and award of
contract;
iv) Contract Execution: Contract management and
closure;
v) Disposal of Scrap: Disposal of Scrap through
various modes of disposal.
NEED ASSESSMENT
•The expression/description of the need.
•Method of satisfying it.
•Time-schedule and place.
•Formulation of Specification.
•Estimation of Cost.
THE EXPRESSION/DESCRIPTION OF THE NEED
The following Guidelines to comply with the ‘Procurement
Guidelines for the Value for Money (VfM) and to ensure wide
competition.
a) Use Unambiguous, complete, using common terminology
prevalent in relevant trade.
b) Except in case of proprietary purchase from a selected
single source, reference to brand names, catalogue
numbers or other details that limit any materials.
c) Owning/leasing/hiring/out sourcing or through Public
Private Partnership (PPP), and so on) may be determined.
d) The quantity of the subject matter of procurement,
commensurate with economy units of quantity.
e) Time-schedule and place of product/work/service delivery
FORMULATION OF SPECIFICATIONS
Ensure value for money(VFM), transparency, level
playing field and ensuring widest competition.
i) Provides a level playing field and ensures the widest
competition;
ii) Be unambiguous, precise, objective, functional,
broad based/generic, standardised (for items
procured repeatedly) and measurable.
iii) Set out the required technical, qualitative and
performance characteristics to meet just the bare
essential needs of the Procuring Entity without
including superfluous and nonessential features.
iv) All dimensions incorporated in the specifications
shall be indicated in metric units.
FORMULATION OF SPECIFICATIONS
V) Make use of best practices. Preference should be given to
procure the goods which carry the BIS mark.
VI) Commensurate with VfM, avoid procurement of obsolete
goods and require that all goods and materials be new,
unused and of the most recent or current models.
VI) Should have emphasis on factors such as efficiency,
optimum fuel/power consumption, use of environmental-
friendly materials, reduced noise and emission levels, low
maintenance cost, and so on. Government of India has set
up the Bureau of Energy Efficiency (BEE)
VII) Comply with sustainability criteria and legal requirements
of environment or pollution control and other mandatory
and statutory regulations, or internal guidelines, if any,
applicable to the goods to be purchased;
•A standardized product is a product that regardless of what company furnishes the good, consumers regard the product furnish
STANDARDISATION
.Standardization is the process of creating protocols to
guide the creation of a good or service based on the
consensus of all the relevant parties in the industry. ...
Standardization also helps in ensuring the safety,
interoperability, and compatibility of goods produced.
.The 3’S refer to standardization, simplification and
specialization three related which are at the roof of any
economic analysis of product design.
PISTON INDUSTRY- Standard sizes of piston are
produced for different products .
NUT &BOLT INDUSTRY- standard nut and bolts are
produced so that they can be easily available in market
in case of
COPYING PAPER
Whether ISI Marked:YES
Size of paper:Legal/Protrait
GSM of paper:75
"Number of sheets per Ream“:500
"ISO Brightness,percent,Min" (N>=80):90
Opacity percent,Min (N>=85):90
"One minute Cobb test both sides,g/m2,Max" (N<=25):25
"Tensile Index Machine Direction (MD) ,Nm/g, Min“:50(N>=40)
Tensile Index Cross Direction(CD),Nm/g,Min (N>=25)35
"Tear Index in mN m²/g,Machine Direction(MD),Min”(N>=3.5)4.5
"Tear Index in mN m²/g,Cross Direction(CD)Min," (N>=4.5)5
"Smoothness for both sides in ml/min,Max" (150<=N<=300)284
"Ash content(900◦C),percent by mass,Max" (N<=16)15
Thickness in µm,Min (N>=100+/-5)100
"Moisture content,percent,Max" (4<=N<=5.5)5
"Taber Stiffness ,Machine Direction(MD),Min" (N>=2)4
DESK TOP COMPUTER
Chipset Series: Intel Q Series
Chipset Number: Intel Q 470
Processor Make:Intel
Processor Generation:10
Number of Cores per Processor:8
Processor DescriptionIntel Core: i7
Processor NumberIntel Core :i7 10700
Operating System (Factory Pre-Loaded):Windows10
Professional RAM Size (GB):8
RAM Expandability up to( using spare DIMM Slots in GB):64
Type of Drives used to populate the Internal BaysHDD ,SSD
Total HDD Capacity (GB):1000
Total SSD Capacity (GB):256
Monitor Technology:TN
LED Backlit Monitor Size (INCHES):18.5
Monitor Resolution (PIXELS)1366x768
On Site OEM Warranty (Year)3
ALMIRAH
MaterialM S Sheet:Grade D of IS:513/2008
Material of Almirah Doors:Grade D of IS:513/Latest
Sheet Thickness of door in mm0.7 mm
Sheet Thickness of 0.7 mm minimum
No of shelves (Nos)4
Type of Shelves:Adjustable
Locker Provided:yes
Number of Doors (Nos)2
Height (Without Pedestal) (in mm) (+/- 10 mm)2400
Width in mm (± 7 mm)900 millimeter
Depth in mm (±5 mm)505 millimeter
Width of Stiffner in mm (±5 mm)N.A
WARANTEE PERIOD IN NUMBER OF YEARS1
BICYCLE
TypeTwo Wheeled Cycles for Men
Weight of Bicycle (kg)15
Applicable Indian StandardIS 10613:2004
Size of Frame (cm) 56
Reflector Yes
Bell Yes
Lock Yes
Stand Yes
Basket yes
Thickness of Crank at Axle Hole (mm)34 millimeter
Type of RimBeaded Edge(BE)
Material of RimAluminium
Size Designation of Rim26
Thickness of tube (mm)2 millimeter
Top Tube Diameter (mm)32 millimeter
No. of Holes in Rear Wheel36
Front Axle Length (mm)38 millimeter
Hub Axle Diameter for Front Wheel (mm)1 millimeter
Material of NippleBrass Conforming to IS 2704
THE ESTIMATED COST
•Processes, approvals and establishing reasonableness of prices
should be worked out in a realistic and objective manner.
•The prevailing market price ascertained through a market
survey or budgetary quotes from potential parties.
• For equipment/craft which are uniquely custom-built to buyer’s
•Likewise rates should be compared with recent
orders/purchases of similar equipment by other states/
Departments.
• Estimated rate in past indents of the same goods.
• Last purchase price of this or similar or nearly equivalent
requirements.
• Costing analysis based on costs of various components/raw
materials of the item;
THE ESTIMATED COST
• Rough assessment from the price of the
assembly/machine of which the item is a part or vice versa.
• Through the internal or external expert costing agencies.
• As a last resort, rough assessment from the opportunity
cost of not using this item at all.
• These methods are not mutually exclusive and can be
supplemented with escalations to cater for inflation, price
increases of raw materials, labour, energy, statutory
changes, price indices, and so on, to make them usable in
conditions prevailing currently.
•In case of foreign currencies, the rate should be reduced to
a common denomination of Indian Rupees.
• Price indices can be obtained from the Internet.
PROCUREMENT PLANNING
Procuring Entity should take following decisions to
initiate procurement, to ensure conformity to the
Procurement Guidelines:
i) Within 14 (Fourteen) working days of receipt of the
indent from the user Department, the procuring
authorities should critically review the description and TS
enclosed with the indent for
completeness/approvals/funding, VfM and possibility of
the widest competition and seek clarifications from the
indenting officer, if needed, before initiating such
procurement.
ii)Reassessment of the quantity and appropriate
aggregation of quantities of various
iii) Determine and declare in documents, any limitation on
participation of bidders as per the Government’s
procurement policy.
PROCUREMENT PLANNING
v) Selection of a system of bidding (single/two stage;
single/two bids; suitability for e-Procurement or reverse
auction).
v) Select the mode of procurement (open tenders, limited
tenders, single tenders, rate contracts, and so on).
vi) Decisions on the timeframe for completing various
stages of procurement, which should be declared in the
pre-qualification/bidder registration or bidding
documents.
vii) Integrated procurement plan should be prepared for
goods, works and services for the ensuing financial year
based on the latest cost estimates, and realistic time
schedule for procurement
GFR 2017: Procurement of goods and services
—
Rule 142 : This chapter contains the general rules
applicable to all Ministries or Departments,
regarding procurement of goods required for use in
the public service.
Rule 143: Definition of Goods: The term ‘goods’ used
in this chapter includes all materials, intangible
products like software, training and maintenance,
works and services etc.
Rule 144 Fundamental principles of public buying
(for all procurements including procurement of
works)
GFR 2017: Procurementof goodsand services
Rule 145: Authorities competent to purchase goods.
Rule 146 Procurement of goods required on mobilisation
of military operations.
Rule 147 Powers for procurement of goods. The Ministries
or Departments have been delegated full powers to make
their own arrangements for procurement of goods.
Rate Contract. Organisation shall conclude rate contracts
through DGS&D. Govt of ndiahas established the GeM for
common use Goods and Servioes. GeM.
Rule 149 Government e-Marke place
(GeM):Government of india has established the
Government e- Marketplace (GeM) for common use
Goods and Servioes.
RULE 149,GFR 2017
THE GEM PORTAL SHALL BE UTILIZED BY THE
GOVERNMENT BUYERS FOR DIRECT ON-LINE PURCHASES
AS UNDER :-
(i) UP TO RS.25,000/- THROUGH ANY OF THE AVAILABLE
SUPPLIERS ON THE GEM, MEETING THE REQUISITE
QUALITY, SPECIFICATION AND DELIVERY PERIOD
(ii) ABOVE RS.25,000/- UP TO RS.5,00,000/- THROUGH
THE GEM SELLER HAVING LOWEST PRICE AMONGST THE
AVAILABLE SELLERS, OF AT LEAST THREE DIFFERENT
MANUFACTURERS, ON GEM
(iii) ABOVE RS.5,00,000/- THROUGH THE SUPPLIER
HAVING LOWEST PRICE, MANDATORILY OBTAINING BIDS,
USING ONLINE BIDDING OR REVERSE AUCTION TOOL
PROVIDED ON GEM.
Rule 150 Registration of Suppliers
Credentials, capability, QC systems, past
performance, after sale service, financial
background,
Reg for period 1-3 years depending upon nature of
goods.
At the End of period all including new have to apply
for registration afresh.
Performance to be watched by the department
Remove from the list, defaulters in terms of bad
quality, delays ,falsification of records/decleration
Rule 151 Debarment from bidding
(i) A bidder shall be debarred if he has been
convicted of an offence— (a) under the
Prevention of Corruption Act, 1988; or (b) the
Indian Penal Code or any other law for the time
being in force for a period not exceeding three
years commencing from the date of d e b a r m e n t .
(ii) D e p a r t m e n t o f Commerce (DGS&D) will
maintain such list which will also be displayed
on the website of DGS&D as well as Central
Public Procurement Portal.
(iii) A procuring entity may debar a bidder or any of
its successors, from participating in any
procurement process undertaken by it, for a
period not exceeding two years, if it determines
that the bidder has breached the code of
integrity.
Rule 152 Enlistment of Indian Agents
. As per the Compulsory Enlistment Scheme of the
Department of Expenditure, Ministry of Finance, it is
compulsory for Indian agents, who desire to quote
directly on behalf of their foreign principals, to get
themselves enlisted with the Central Purchase
Organisation (eg. DGS&D). However, such enlistment
is not equivalent to registration of suppliers as
mentioned under Rule 150.
Rule 153 Reserved Items and other
Purchase/Price Preference Policy
(i) The Central Government, through
administrative instructions, has reserved all
items of hand spun and hand-woven textiles
(khadi goods) for exclusive purchase from Khadi
Village Industries Commission (KVIC
(ii) Ministry of Micro, Small and Medium Enterprises
(MSME) have notified procurement policy under
section 11 of the Micro, Small and Medium
Enterprises Development Act, 2006.
(iii) The Central Government may, by notification,
provide for mandatory procurement of any
goods or services from any category of bidders,
locally provided goods and services.
Rule 154 Purchase of goods without quotation
Purchase of goods upto the value of Rs. 25,000
(Rupees twenty five thousand) only on each occasion
may be made without inviting quotations or bids on
the basis of a certificate to be recorded by the
competent authority.
“I,, am personally satisfied that these goods
purchased are of the requisite quality and
specification and have been purchased from a reliable
supplier at a reasonable price.”
Rule 155 Purchase of goods by Purchase Committee
Purchase of goods costing above Rs. 25,000 (Rupees
twenty five thousand only) and upto Rs.2,50,000/-
(Rupees two lakh and fifty thousand only) on each
occasion may be made on the recommendations of a
duly constituted Local Purchase Committee consisting
of three members of an appropriate level as decided
by the Head of the Department.
Committee’s responsibilities
a) Market Survey
b) Reasonableness of Rates
c) Quality & Specifications
d) Identify appropriate supplier
e) Joint Certificatebythe Committee
Joint Certificate by the Committee
“Certified that we, ---------, members of the
purchase committee are jointly and individually
satisfied that the goods recommended for purchase
are of the requisite specification and quality, priced
at the prevailing market rate and the supplier
recommended is reliable and competent to supply
the goods under procurement and the firm is not
debarred by Department of Commerce or Ministry/
Department concerned.”
Rule 156
Ministry and departments may purchase from
suppliers on terms and conditions specified in rate
contract. Make own arrangement for inspection.
CPO(DGS&D) should host updated details of
different rate contracted items on the web-site
for the use of procuring Department
Rule 157
Demand not to be divided into small quantities
to make piece meal purchases to avoid sanction
by higher authority wrt estimated value of total
demand.
Except in cases covered under Rule
154,155, and 156(1), Ministries or
Departments shall procure goods
under the powers referred to in Rule
147 above by following the standard
method of obtaining bids in :
(i) Advertised Tender Enquiry
(ii) Limited Tender Enquiry
(iii) Two-Stage Bidding
(iv) Single Tender Enquiry
(v) Electronic Reverse Auctions
Rule 158 Purchase of goods by obtaining bids.
Rule 159 E-Publishing
(i) It is mandatory for all Ministries/ Departments
to publish their tender enquiries, corrigenda
thereon and details of bid awards on the Central
Public Procurement Portal (CPPP).
(ii) Individual cases where confidentiality is
required, for reasons of national security, would
be exempted from the mandatory e-publishing
requirement.
(iii) The above instructions apply to all Tender
Enquiries, Requests for Proposals, Requests for
Expressions of Interest, Notice for pre
Qualification/ Registration
Rule 159 E-Publishing
(iv) In the case of procurements made though
DGS&D Rate Contracts or t h r o u g h a n y o t h
e r C e n t r a l Procurement Organizations
(CPOs) only award details need to be published.
(v)These instructions would not apply to
procurements made in terms of provisions of
Rules 154 (Purchase of goods without
quotations) or 155 (Purchase of goods by
purchase committee) of General Financial
Rules.
E-Procurement
It is mandatory to receive all bids through e-
procurement portals in respect of all
procurements.
Departments which do not have a large volume
of procurement may use e- procurement solution
developed by NIC.
Other Departments may either use e-
procurement solution developed by NIC or engage
any other service provider following due process.
RULE 161: Method ofobtainingbid:
Advertised TenderEnquiry(open)
—
Tender value >= 25 Lac
—
—
Publish atown website &NIC website
—
NIT to Indian Embassies abroad as well as
foreign embassies in India
—
Three Weeks time from dateof
publication of bid
Rule :162- LIMITEDTENDER ENQUIRY
—
Value up to 25 Lac
—
Bid document should be sent to Regd.
Suppliers by Speed Post/Regd Post/
Courier/ e-mail
—
No. of supplier firms in Ltd.Tender should
be more than three
—
Web based publicity also through CPPP
and Department’s website,
—
N.B. – Sufficient time should be givenin
Ltd.Tender
LIMITEDTENDER ENQUIRY
Certificate that demand is urgent. Add
expenditure justified in view of urgency.
Put on record the nature of urgency and reasons
why procurement could not be anticipated.
sufficient reasons to be recorded that Open
tendering not in public interest.
Sources of supply are definitely known and
possibility of fresh sources is remote.
Rule 163 Two Bid System
1. For high value plant ,machinery of
complex and technical nature items.
2. TechnicalBid (Tech.+ Comm.Terms )
3. Financial Bid (Item wise price )
(1) + (2) = (3) MainEnvelop
Firstly T
ech. Bid shall be opened and
evaluated
 Secondly Fin. Bid of Technically
acceptable offer should be opened &
evaluated
Rule 164 two stage bidding
Obtain bids in two stages with receipt of financial bids
after receipt and evaluation of technical bids
It is not feasible to formulate detailed specifications or
identify specific characteristics
Rapid technological advances or market fluctuations or
both
All first stage bids, which are otherwise eligible, shall be
evaluated, may hold discussions with the bidders, and
consider revising the relevant terms and conditions of the
procurement
Invite bids from all those bidders whose bids at the first
stage were not rejected, to present final bid with bid
prices in response to a revised set of terms and conditions
of the procurement
Rule 165 late bids
Bids received after the specified date and time
should not be considered.
Rule 166 SingleTender
Ifonly aparticular firm is the
manufacturer
Emergency need to procure from a
particular source
T
echnicalreason to be recorded
(standardization of machinery – HP
,
SONY etc.)
N.B. - Single response to an open bid
can’tbe termed as Single Tender
Rule 167 Electronic Reverse Auction
(i) Electronic Reverse Auction means an online real-
time purchasing technique utilised by the procuring
entity to select the successful bid.
(ii) A procuring entity may choose to procure a
subject matter of procurement by the electronic
reverse auction method,
(iii) The procedure for electronic reverse auction
similar to e-procurement; and (b) The invitation shall,
in addition to the information as specified in e-
procurement, include details relating to access to and
registration for the auction, opening and closing of the
auction and Norms for conduct of the auction.
Rule 168 Contents of Bidding Document
—
Instruction to Bidder
—
Conditions of Contract
—
Schedule of Requirement
—
Specifications &alliedTech.details
—
Price Schedule
—
Contract Form
—
Other Standard Forms
Rule 169 Maintenance Contract
Depending on the cost and nature of the goods to be
purchased, it may also be necessary to enter into
maintenance contract(s) of suitable period either with
the supplier of the goods or with any other competent
firm, not necessarily the supplier of the subject goods.
Such maintenance contracts are especially needed for
sophisticated and costly equipment and machinery. It
may, however, be kept in mind that the equipment or
machinery is maintained free of charge by the supplier
during its warranty period or such other extended
periods as the contract terms may provide and the paid
maintenance should commence only thereafter.
Rule 170 Earnest Money Deposit
—
To safeguard the interest of Deptt
(withdrawal /alter the bid by bidder)
—
Exemption – Regd.With CentralPurchase
Organisation /National Small Industries
Corporation
—
EMD - 2 % to 5% of estimatedvalue
—
Can be DD/ FDR/Banker Cheque /BG
—
Unsuccessful bidders EMD should be
returned /refundedatthe earliest.
Rule 171 Performance Security
—
From the successful bidders
—
Amount – 5%to 10%
—
DD/FDR
—Should be valid for 60 days beyond the
date of completion of all the contractual
obligations of the supplier including
warranty
—
Bid Security should be refunded to
the successful bidder on receipt of
Performance Security
PROCESS ATA GLANCE
 Estimate (Qty. andAmount)
 EOI – Expressionof Interest
 RFP/RFQ – Request for Proposal /Quotation
 PBC – Pre BidConference
 NIT – Notice Inviting Tender
 APPROVAL
 WEB PUBLICITY
 EMD – Earnest Money Deposit
 BIDDING
TOC – Tender Opening Committee (Tech)
APPROVAL
PROCESS ATA GLANCE


TOC – Tender Opening Committee(Fin.Bid)

APPROVAL


TEC – Tender Evaluation Committee

 APPROVAL

PO - Purchase Order

AWARD OF CONTRACT

SD - Security Deposit

AGREEMENT

REFUND OF EMD

NOTICE /WEB PUBLICITYABOUT AWARD
OF CONTRACT(Downloadable form)
Rule 172 (1) Advance payment to supplier
Ordinarily, payments for supply and services rendered are
released only after the services have been rendered
Advance payment may be necessary by firms holding
maintenance, fabrication contracts, turn-key contracts etc
Limits 30% of the contract value to private firms
40% of the contract value to a State or Central
Government Agency or a PSU
In case of maintenance contract, the amount payable for
6 months under the contract.
Ministries/Departments may relax the ceilings in
consultation with the FA
Adequate safeguard in the form of BG should be obtained
from the firm obtained from the firm.
Rule 172(2) Part payment to suppliers
Part payment permitted depending upon terms of
contract.
After dispatch of goods from premises.
Rule 173 TRANCEPARECY, COMPETITION FAIRENESS
the text of the bidding document should be self-
contained and comprehensive without any
ambiguities, clearly spelt out in the bidding
document in simple language.
The bidding document should contain, (a) the
criteria for eligibility and qualifications to be met
by the bidders such as minimum level of
experience, past performance, technical
capability, manufacturing facilities and financial
position, goods indicating any legal restrictions etc
(c) the procedure as well as date, time and place
for sending the bids; (d) date, time and place of
opening of the bid; (e) terms of delivery; (f)
special terms affecting performance,
Rule 173 TRANCEPARECY, COMPETITION FAIRENESS
suitable provision should be kept in the bidding
document to enable a bidder to question the
bidding conditions, bidding process and/or
rejection of its bid. The bidders should be given
reasonable time to send their bids. The
specifications of the required goods should be
clearly stated without any ambiguity so that the
prospective bidders can send meaningful bids. In
order to attract sufficient number of bidders, the
specifications should be broad based to the extent
feasible. Efforts should also be made to use
standard specifications which are widely known to
the industry. .
Rule 173 TRANCEPARECY, COMPETITION AND FAIRENESS
Criteria for determining responsiveness of bids,
criteria as well as factors to be taken into account
for evaluating the bids on a common platform and
the criteria for awarding the contract to the
responsive lowest bidder should be clearly indicated
in the bidding documents. Bids received should be
evaluated in terms of the conditions already
incorporated in the bidding documents; no new
condition which was not incorporated in the bidding
documents should be brought in for evaluation of the
bids. Determination of a bid’s responsiveness
should be based on the contents of the bid itself
without recourse to extrinsic evidence.
Rule 174 Efficiency, Economy and Accountability in
Public Procurement System
Public Procurement procedure to ensure efficiency, economy
and accountability in the system. To achieve the same, the
following key areas should be addressed:
1. To reduce delay, appropriate time frame for each stage of
procurement should be prescribed by the Ministry or
Department. Such a time frame will also make the concerned
purchase officials more alert.
2. To minimize the time needed for decision making and
placement of contract, every Ministry/Department with the
approval of the competent authority, may delegate, where
necessary, appropriate purchasing powers to the lower
functionaries. 3. The Ministries or Departments should ensure
placement of contract within the original validity of the bids.
Extension of bid validity should be resorted to only in
exceptional circumstances.
Rule 175 CODE OF INTEGRITY
Promise by the Principal not to seek any illegal
benefit.
Promise by the bidders not to offer any benefit to
the employees of the principal.
Bidders not to enter into any understanding with
other bidders regarding prices and rigging etc.
Bidders not to pass any information of the
procurement entity.
Foreign bidders to disclose the details of its agent
in India. Indian bidders to disclose their foreign
associates.
Bidders to disclose payments to be made to agents
and any misintention to influence tender.
Rule 176 BUY BACK OFFER
If it is decided to replace an existing old item with a
new and better version – the department may trade
the existing old item while purchasing the new one
A suitable clause is to be incorporated in the
bidding document so that the prospective and
interested bidders can formulate their bids
accordingly
The time as well as the mode of handing over the
old item to the successful bidder to be suitably
incorporated in the bidding document
Provision should also be kept in the bidding
document to enable the purchaser either to trade or
not to trade the old item, while purchasing the new
one
EVALUATION OF TECHNO-COMMERCIAL BID
Evaluation of Techno-commercial Bid In evaluation of the techno-
commercial bid, conformity of the eligibility/ qualification, technical and
commercial conditions of the offered goods to those in the bid document
is ascertained to be considered for evaluation.
i) Evaluation of eligibility/qualification Criteria
ii) Evaluation of Technical Suitability.
iii)Evaluation of Commercial Conditions.
iv) Considering Minor Deviations not amount to material deviations.
v) Declaration of Successful Bidders
BIDDER HAS RIGHT TO QUESTION REJECTION AT TECHNO-
COMMERCIAL STAGE
EVALUATION PROCESS -micro
—Tender is sealed
—
Tender documents must clearly
specify evaluation criteria.
—
Two types of Bids:
◦ Technical
◦ Financial
—
Tender evaluation to be in
accordance with evaluation criteria.
EVALUATION PROCESS -micro
—
Time taken for evaluation and
extension of tender validity.
—
Process of tender evaluation to be
confidential until the award of the
contract is notified.
—
Difference between TOC (Tender
Opening Committee) & TEC
(Tender Evaluation Committee)
EVALUATION PROCESS -micro
—
The factors for initial examination:
◦ Whether the tenderer meets the eligibility
criteria ?
◦ Whether the crucial documents have been
submitted &duly signed /attested ?
◦ Whether the requisite EMD (Earnest Money
Deposit) has been furnished ?
EVALUATION PROCESS -micro
—
Satisfaction of Conditions specific to the
contract
—
SampleTesting
—
Capacity Evaluation.
—
Turnover
—
Statutory documentation
—
Arrival atOutcome Price of the bid
—
Determination of L-1, L-2,L-3……
—
Determining Reasonableness of the L-1 Rates
—
Recommendation for Negotiation (if require)
CVC Guidelines: Pre-AwardStage
—
Financial and Technical sanction of competent
authority is available.
—
Adequate and wide publicity is given.
Advertisement is posted on website and tender
documents are availablefor downloading.
—
Convenient tender receiving/opening time and
address of the tender receiving officials/tender
box are properly notified.
—In the case of limited tender
, panel is prepared in
atransparent manner clearly publishing the
eligibility criteria.The panel is updated regularly.
—Pre-qualification criteria are properly defined/
notified.
CVC Guidelines: Pre-AwardStage
—Short listed firms/consultants are fulfillingthe
eligibility criteria.There is no deviation from notified
criteria during evaluation.
—Experience certificates submitted havebeen duly
verified.
—Tenders/bids are opened in the presence of bidders/
their authorised representative.
—Corrections/omissions/additions etc.,in price bid are
properly numbered and attested and accounted page
–wise.Tender summary note/Tender opening register
is scrupulously maintained.
—Conditions having financial implications are not
altered after opening of the price bids.
CVC Guidelines:Negotiations
—
Circular No.4/3/07,3rd March, 2007
As post tender negotiations could often
be a source of corruption, it is directed that
there should be no post-tender negotiations
with L-1, except in certain exceptional
situations. Such exceptional situations would
include, procurement of proprietary items,
items with limited sources of supply and
items where there is suspicion of a cartel
formation. The justification and details of such
negotiations should be duly recorded and
documented without any loss of time.
Latest guideline of CVC on negotiation
Procurement ofWorks, Goods
and Services - Guidelines on
Tenders/Use of website
—
http://cvc.nic.in/proc_works.htm
VIGILANCE ANGLE
AND
SAFE GUARDS
Definition of Vigilance
To be watchful
To be alert
What is happening
And what can happen
As per George Bernard Show “ Man is moral but we
have not tested him. So cannot say that he is
sincere”
Keep a watch on the people working under you.
Try to remove opportunities to reduce the crime
“Wearer of shoes know where it Pinches”
American- All Open offices United Kingdom- Room
wise “More open working less chance of Corruption
Objectives of vigilance
Raising strong signals regarding complexities in
procedure. i.e. System Analysis
Identifying places and point of corruption. i.e. for
inspections, surprise checks and posting of suitable
hands (and if this is not feasible closer supervision of
work) including rotation of staff
Eliminate the corruption and the crooked staff
Watch of work
Inside and outside conduct and contacts
Realize that cumbersome procedure are the main
stay of corruption.
I. Modify/ eliminate the blocks.
II. Simplify procedure codify them in manual to
remove ambiguity.
III. Should have list of bad and loose integrity
persons.
IV. Visit pressure points frequently to ensure, no
leakage happens
COST OF PROCUREMENT
PUBLIC PROCUREMENT IN INDIA
CONSTITUTES ABOUT 28% OF GDP
CANNON OF PUBLIC PROCUREMENT
This is to procure work, material, services of the
specified quality within the specified time at the most
competitive prices in a fair, just and transparent
manner. In brief, the watchwords in this context are
• Transparency
• Fairness/equal opportunity(Article 14 of constitution)
• Value for money
• Quality
• Time
GUIDING DOCUMENTS
•GENERAL FINANCE RULES-2017
•PROCUREMENT MANUAL FOR
MATERSALS/WORK/SERVICES UPDATED.
•CVC GUIDELINES
•DELIGATION OF POWERS
•NIT-MAIN/GCC/SCC/ANNEXURES OF TENDERS
APPROVED
REQUIREMENTS
Whether it was essential to get the work
through contractual agency?
Whether the work could have been done
within existing resources?
Whether the spending proposed is
justified.
SPECIFICATIONS:
1. Identify the purpose & plan in advance.
2. Clubbing the similar requirements from all units.
3. Description of item should be clear and complete
with I.S.specification/drawing if any.
4. Specification should not be prepared meeting single
product/specific make.
5.Use Products With Standard Specification.
6. Sample clause if any should be only for ascertaining
‘TOUCH, FEEL & FINISH’ but not for its quality.
7. If the demand of the item is recurring, convert the
same as Stock item.
8. The description of the item should normally be
arranged in Order. A. Basic commodity B.Variance in
kind or use. C. Composition/size/color/shape
D.Specification/drawing No.
STANDARDS OF FINANCIAL PROPRIETY
• The Expenditure should not be prima facie be
more than the occasion demands
• Every Govt. Servant should exercise the same
VIGILANCE in respect of expenditure incurred
from public money as a person of a ordinary
prudence would exercise in respect of the
expenditure of his own money
•No authority should exercise its powers of
sanctioning expenditure to pass an order, which will
directly or indirectly to its own advantage.
•Public moneys should not be utilised for the benefit
of a particular person or section of the community
APPOINTMENT OF CONSULTANT
Consultant appointed when absolutely essential for
specialized job.
Awarding consultancy contract in transparent and
fair manner.
The consultants role should be well defined as well
as payment conditions.
No change of payment conditions after award of
contract.
The payment made to consultant should be
commensurate with the work done by them.
over dependence on consultants to be avoided.
Role of consultants should be advisory.
case of conflict of interest in appointment.
PRE-QUALIFICATION CRITERIA (PQ)
The PQ criteria is a yardstick to allow or disallow
the firms to participate in the bids.
A vaguely defined PQ criteria results in stalling the
process of finalizing the contract or award of the
contract in a non-transparent manner.
PQ criteria for renderers is provided in some of the
tender to have experienced and resourceful
contractors for timely and proper execution of works.
The PQ criteria should be clear and unambiguous.
The PQ criteria should not be too restrictive.
Prequalification/Post Qualification shall be made
taking into account their capacity to accomplice
work.
PRE-QUALIFICATION CRITERIA (PQ)
(i) experience and past performance on similar
contracts. (ii) capabilities of personnel, equipment
and manufacturing facilities (iii) financial standing
through latest I.T.C.C., Annual report (balance sheet
and Profit & Loss Account) of last 3 years. The
quantity, delivery and value requirement
It is observed that at times this eligibility criteria
is loosely and selectively applied in various tenders
to favour particular firm.
It is expected that eligibility criteria is applied in
true spirit and uniformly keeping basic objective in
mind.
It should not to be used as a tool to eliminate
unfavourable lower bidders.
NOTICE INVITING TENDER
Notice inviting tender contains, general description,
technical specifications of the work, with quantity, unit
and estimated rates. General and special rules and
directions, terms and conditions of the proposed contract,
schedule of materials with prices proposed to be issued by
the department, earnest money to be deposited prior to
tendering, security deposit to be deposited on acceptance
of the offer or prior to executing the contract and time
for completion of the work. This part is applicable to
tenders of all kinds of works.
NOTICE INVITING TENDER
Tender Notice shall be issued at least 21 days in
advance from the date of tender opening
In case of urgency – 10-14 days with approval of
HOD
Issue of tender schedules With the approval of
tender calling authority – at least 15 days prior to the
date of tender opening
Date on which the tender documents will be made
available on the website / in the office shall be
clearly brought out in the Tender Notice
Eligibility criteria and similar nature of works should
be specifically mentioned in Tender Notice and in the
tender documents for OT above Rs. 50 lakhs
NOTICE INVITING TENDER
•Should be invariably on a Public Tender basis.
• Tenders should be both for technical and financial
bids.
• Technical bids should be scrutinized before financial
bids are opened.
• List of suppliers should be reviewed periodically.
•Delivery samples should be got checked with basic
samples.
Open Tenders Common Irregularities
Most Widely Publicized in prescribed form
Any individual or firm can participate in the Open
Tender
Basic Requirement - Free and Fair Competition
Tender should Normally be awarded to Lowest
Suitable Tenderer
Inadequate tender notice
Inadequate time for participation
Inadequate publicity
Late availability of tender documents
Tender box not available in advance
Deviations in eligibility criteria
LIMITED TENDERS COMMON IRREGULARITIES
Tender Notice issued to selected firms
Firms short listed in advance, based on past
experience, expertise, and specialization
List of selected firms require finance concurrence
and competent authority's approval
Proof of Service necessary 7
Arbitrary selection of firms.
Firms with better experience ignored and firms
with dubious credential selected.
Inadequate time given for participation in tender.
Tender notice not sent to all the firms.
Bogus firms selected to inflate the number.
Rates can be reasonably higher since the
competition is restricted.
SINGLE TENDER COMMON IRREGULARITIES
Tender is invited from single pre- selected bidder of
proven capacity
Used in emergencies and exceptional cases
Where other tender routes can not be followed due
to exigencies of given situation
When item is propriety item or only one firm is
capable of doing the work
Projecting undue/artificial urgency
Selecting unsuitable tenderer based on exaggerated
credential ignoring his past failures.
Accepting exorbitant rates on the grounds of
urgency then merrily giving extensions with token
penalty or without penalty.
RECEIPT OF TENDERS
A proper arrangement for the receipt of tenders at
scheduled date and time through tender box needs to
be adopted.
Commission, where due to the bulky size of tender
documents the bid conditions envisaged submission of
tenders by hand to a designated officer and the
information about these officers should also be
displayed at the entrance/reception of the premises
where tenders are to be deposited so as to ensure
convenient approach for the bidders.
TENDERS OPENING
Opened at the specified time, date and place by an
officer nominated in the presence of authorised reps
of tenderers.
Seal of the Tender Box to be checked
Tenders should be serially numbered
Initials on cover page and all other loose sheets
attached by tenders.
Rates quoted should be circled.
Corrections, over writings & omissions to be
numbered and written on each page and attested
with date.
Check completeness of tender form (for tampering
etc.) downloaded from internet
TENDERS OPENING (CONTD …)
Name of the tenderers and rates quoted by each
tenderer should be read out
No clarifications to be solicited from tenderers
Samples, if any to be initialed
Any Blank Column shall be struck off.
LATE tenders to be marked and to be returned to
the firm.
Both the Accounts and Executive witnessing
officials are INDIVIDUALLY responsible the procedure
laid down for tender opening.
Comparative statement
Details of offers received
Period of validity of offers.
EMD details of each tenderer.
Last accepted rates for similar type of works.
Financial implications on the special conditions.
Remarks on special conditions quoted by the
tenderer.
Credentials of the tenderer.
Other certificates/documents submitted by the
tenderer.
Details of the contracts of the tenderer during the
last 3 years
BACK TO BACK TIE UP / AWARD
ON NOMINATION BASIS
•Back to back basis that the works are being awarded in
an ad-hoc and arbitrary manner without inviting tenders
and ascertaining the performance, capability and
experience of the tenderers.
• In some cases, the works were awarded on single tender
basis/limited tender basis though sufficient time was
available with the Organisation to invite open tenders.
•No transparency in selection of contractor for the back to
back tie up which is the main source of corruption.
•Collusion among the contractors was observed where
more than one contractor was involved at various stages.
Ineligible contractor obtains the contract through the
PSUs.
BACK TO BACK TIE UP / AWARD ON NOMINATION BASIS
Purchase preference misused by the PSUs.
No supervision by the PSU as they put the staff mainly for
coordination work.
Quality ultimately suffers due to lack of supervision by the PSUs.
contractor, has to execute the work by functioning like a contractor
instead of sub-letting the 100% work on back to back basis.
Open tenders to be invited for selection of sub-contractors as far as
possible.
In case, it is not possible to invite open tenders, selection should be
carried out by inviting limited tenders from the panel approved in
the following manner. Panel of contractors are to be prepared for
different categories monetary limits, regions, in a transparent
manner clearly publishing the eligibility criteria etc. The above
panel is to be updated every year.
BACK TO BACK TIE UP / AWARD ON NOMINATION BASIS
The terms and conditions of the contract of the
client especially those pertaining to subletting of
works should be strictly adhered to by the PSUs.
Adequate staff to be deployed by the PSUs to ensure
quality in construction etc.
There is a need to bring greater transparency and
accountability in award of such contracts on
nomination basis and reports relating to such awards
will be submitted to the Board every quarter.
The audit committee may be required to check at
least 10% of such cases. for necessary observance.
Further, all nomination/single tender contracts be
posted on the website ex
TENDER NEGOTIATIONS
•There should be no post-tender negotiations with L-1,
except in certain exceptional situations.
•procurement of proprietary items,
• items with limited sources of supply
•items where there is suspicion of a cartel formation.
•The justification and details of such negotiations
should be duly recorded and documented without any
loss of time.
•ii) In cases of jeopardizing the essential operations,
maintenance and safety, negotiations would be
permitted with L-1 bidder(s) for the supply of a bare
minimum quantity. The balance quantity should,
however, be procured expeditiously through a re-
tender, following the normal tendering process.
TENDER NEGOTIATIONS
•Negotiations should not be allowed to be misused as a tool
for bargaining with L-1 with dubious intentions
• It is reiterated that in case L-1 backs-out, there should be
a re-tender.
•If L-1 alone is not capable of supplying and there was no
prior decision to split the quantities, then the quantity being
finally ordered should be distributed among the other
bidders in a manner that is fair, transparent and equitable.
Counter-offers to L-1, in order to arrive at an acceptable
price, shall amount to negotiations. However, any counter-
offer thereafter to L-2, L-3, etc., (at the rates accepted by
L-1) in case of splitting of quantities, as predisclosed in the
tender, shall not be deemed to be a negotiation.
CONSIDERATION OF INDIAN AGENTS
In order to maintain the sanctity of tendering
system, it is advised that the purchases should
preferably be made directly from the
manufacturers. Either the Indian Agent on behalf of
the foreign principal or the foreign principal
directly could bid in a tender but not both. Further,
in cases where an agent participates in a tender on
behalf of one manufacturer, he should not be
allowed to quote on behalf of another
manufacturer along with the first manufacturer in a
subsequent / parallel tender for the same item.
IRREGULARITIES IN GENERAL
Twisting, Suppression, exaggeration, Manipulation,
and Half truth by TC to
Depict better placed bidder as unsuitable or less
suitable
Exaggerating track record of favourite bidder
Suppression/ down playing his past failures
Exaggerating past failures of his main rival Contd.
Ignoring/Suppressing otherwise satisfactory
credentials of main rival
Projecting the lowest rates of main rival as
‘unworkable’ on the basis of exaggerated estimated
cost
Projecting undue/ artificial urgency bypassing
lowest offer
IRREGULARITIES IN GENERAL
Manipulating technical aspect to reject
inconvenient bids on artificial grounds.
Considering tender on extraneous conditions not
included in the tender.
Falsely Certifying that the quality of product/
material offered by favourite firm as okay vis-a-vis
specifications
Deliberately painting the quality of product offered
by the better placed bidder as unsuitable.
Exaggerating capacity/ resources of favorite
contractor and downplaying that of his rival (lower
bidders)
IRREGULARITIES IN GENERAL
Favoritism i.e. Award of contract to favoured
firm bypassing more deserving lower tenderer/s
on flimsy grounds
Award of contract at exorbitant rates
Execution of Substandard work
Acceptance of Substandard Supplies
Overpayment / Payment of work not done
Failure to Carryout out Quality Check
Misappropriation of material by contractor in
connivance with officials
IRREGULARITIES IN EXECUTION
OF CONTRACT
Failure to incorporate accepted tender
conditions in contract agreement.
Introduction of conditions having financial
implications. Change in specifications during
execution.
Altering the location or nature of work giving
undue advantage to the tenderer.
IRREGULARITIES IN EXECUTION OF
CONTRACT
Unreasonable variations in terms of quantity
Introduction of new non-schedule items.
Acceptance of material of inferior brand than
specified in contract agreement.
Acceptance of material after date of expiry.
Acceptance of under specification supply.
Accepting material without inspection
certificate.
Accepting material without delivery challans.
IRREGULARITIES IN EXECUTION
OF CONTRACT
Acceptance of under specification work or
supply
Not following laid down procedure
By passing certain processes
Not conducting requisite tests
Use of un passed raw materials
RING FORMATION
Ring/ Cartel formation among the bidders leads to
elimination of competition and award of contract at
exorbitant rates.
At times it is done with active collusion with
officers concerned.
The ring formation becomes more important in case
of limited tenders thus an attempt should be made to
identify sister concerns.
In case of suspected ring formation with high rates,
tender cancellation is advisable.
AWARD OF TENDER AT EXORBITANT RATES
Due to high pitching estimates.
Tenderers are guided by estimated cost given in NIT
and often estimated cost are used to assess
reasonability of rates.
Picking up ‘Comparable rates’ selectively.
Preparing rate analysis after the opening of tender
to justify the high rates received.
Unrealistic short completion period may lead to
high rate.
By assuming unreasonably high rates towards
transportation cost, labour cost, local taxes, inflation etc.
Modifying description of items to make them Non- Stock
items in case Of Stores and Non-Schedule item in case
works items leading to purchase/ execution of works at
high rate.
POINTS TO BE KEPT IN MIND
Tender opening register must be maintained in emd,
tender cost,returning of sighned credentials documents,
samples,remarks of quoted by renderers are recorded.
This must be signed by renderers and tender opening
officers present at the time of opening.
Delayed tenders i.e. received after closing of box of
tender to be rejected.
POINTS TO BE KEPT IN MIND
Under no circumstances no member of TC
should refer the case to any officer/staff under
him for scrutiny / comments.
Rate register should be maintained religiously
in which accepted rates are recorded
chronologically and any adverse remarks
regarding their non-comparability should also be
recorded.
The register can be referred to see that the
rates LAR taken in briefing note are
representative.
ADVANCE PAYMENT
•If the advance is to be given, it should be expressly
stated in the NIT/Bid Documents, indicating the amount,
rate of interest and submission of BG of equivalent
amount.
•The advance payment may be released in stages
depending upon the progress of the work and mobilization
of required equipments etc.
• There should be a provision in the contract for
adjustment of advance progressively even as the bills are
cleared for payment.
•In case of „Machinery and Equipment advance‟, insurance
and hypothecation to the employer should be ensured.
•Utilization certificate from the contractor for the mob
advance should be obtained
OVER PAYMENT
Temporary overpayment in Running Bills
Payment in anticipation of work to be done or supply to
made Final overpayment
Payment for the services not rendered
Inflated measurement
Multiple measurement
ACCEPTANCE OF BANK GUARANTEE
•BG shall be in the form of irrecovarable BG
issued by nationalized and scheduled banks.
•Bank guaranty should be scrupulously
compared with the VPT Performa.
•Should be executed on stamp paper of proper
value.
•Eliminate the possibility of acceptance of any
forged / fake bank guarantees.
•Confirmation of issuing banks should be
obtained for genuiness.
POSTING DETAILS OF AWARD OF TENDERS ON
WEBSITE
All the organisations to post on their web-sites
a summary, every month, containing details of
all the contracts/purchases made above a
threshold value (to be fixed by the
organisations) covering at least 60% of the
value of the transactions every month to start
with on a continuous basis.
LEVERAGING TECHNOLOGY
•Transparency through effective use of websites in discharge
of regulatory, enforcement and other functions of Govt.
Authorized.
•Issue tenders publish the tender advertisements on e-
tendering platforms. ...
•Bidders need to enroll themselves at the
online tendering platforms to generate user ids and
passwords.
•One needs to upload the requisite documents and mention
the bids online.
•E-Payments
•Post on the website, summary every month, of all the
tenders/works contracts of value more than tha a certain
thresshold value of Engg./Mech/Elec/ Medical departments
DELAY IN PAYMENT TO VENDORS
E-payments brings economy and efficiency and at the
same time reducing corruption.
Reducing transaction costs involved in making payments
by way of cheques and sending the same through courier.
e-payments to vendors and employees instead of making
payments by issue of cheques.
Payments are to be made on “firstcome-first-serve” basis.
Payment should be made within a bench mark period from
the date it is due.
Should verify the outstanding bills position by
Contractors, suppliers.
E-TENDERING/E-PROCUREMENT
CVC advising organizations to follow a fair,
transparent and open tendering procedure, to
select the application service provider for
implementing their e-tendering solutions.
IT PROCUREMENT
Turnkey contracts for net-working of computer systems.
Inclusion of these unrelated items creates opportunities
for malpractices-third party view about the scope of
turnkey projects.
Measures To Curb The Menace Of Counterfeit And
Refurbished IT Products
diligence as well as curbing the menace of counterfeit and
refurbished IT products disguised as new
OEM that would certify that all the
components/parts/assembly/software used in the
Desktops and Servers like Hard disk, Monitors, Memory etc
were original/new components/parts/assembly/software,
and that no refurbished/duplicate/ second hand
components /parts / assembly / software were being used
or would be used,
LATEST GUIDELINES ON TENDERS
•No EMD, Cost of Tenders & SD of 3% of the contract
value to be remitted through RTGS/E-Transfer to VPT
account.
•PG shall be in the form of irrevocable BG issued by
nationalised or scheduled bank – 3% of the contract
value. PG shall be furnished by the successful
contractor within 15 days from the date of issue of
acceptance letter & before the signing of the contract
and valid upto expiry of the maintenance period
Clause.
Periodical rotation of Officers
Periodical rotation of Officers/staff in sensitive
posts. Review of Immovable property returns
submitted by Officers/Staff. Proper implementation
of DA Rules to weed out corrupt officers. Institution
of effective grievance procedure enquiry.

Más contenido relacionado

La actualidad más candente

Tendering and Procurement Best Practices
Tendering and Procurement Best PracticesTendering and Procurement Best Practices
Tendering and Procurement Best PracticesSHKLaw
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Types of tenders &amp; stages for successful tendering
Types of tenders &amp; stages for successful tenderingTypes of tenders &amp; stages for successful tendering
Types of tenders &amp; stages for successful tenderingAditya Sanyal
 
Rights of tenants under tamilnadu rent control act
Rights of tenants under tamilnadu rent control actRights of tenants under tamilnadu rent control act
Rights of tenants under tamilnadu rent control actAltacit Global
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTVISHNU VIJAYAN
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid EvaluationVj NiroSh
 
The Law of Tendering
The Law of TenderingThe Law of Tendering
The Law of TenderingNow Dentons
 
Value Engineering
Value EngineeringValue Engineering
Value EngineeringEdwinJacob5
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
Tendering, Contract and Execution
Tendering, Contract and ExecutionTendering, Contract and Execution
Tendering, Contract and ExecutionDr K M SONI
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
Consumer protection act 1986 - Legal Environment of Business - Business Law ...
Consumer protection act  1986 - Legal Environment of Business - Business Law ...Consumer protection act  1986 - Legal Environment of Business - Business Law ...
Consumer protection act 1986 - Legal Environment of Business - Business Law ...manumelwin
 
U.P. APARTMENT RULES 2010
U.P. APARTMENT RULES 2010U.P. APARTMENT RULES 2010
U.P. APARTMENT RULES 2010ApnaComplex
 
THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016
THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016
THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016Narmdeshwar Singh
 
Consumer prorection council
Consumer prorection councilConsumer prorection council
Consumer prorection councilSravani Sravi
 
Introduction to public procurement
Introduction to public procurement Introduction to public procurement
Introduction to public procurement Dr. Heera Lal IAS
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 

La actualidad más candente (20)

Tendering and Procurement Best Practices
Tendering and Procurement Best PracticesTendering and Procurement Best Practices
Tendering and Procurement Best Practices
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Types of tenders &amp; stages for successful tendering
Types of tenders &amp; stages for successful tenderingTypes of tenders &amp; stages for successful tendering
Types of tenders &amp; stages for successful tendering
 
Procurement of services
Procurement of  servicesProcurement of  services
Procurement of services
 
Rights of tenants under tamilnadu rent control act
Rights of tenants under tamilnadu rent control actRights of tenants under tamilnadu rent control act
Rights of tenants under tamilnadu rent control act
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
The Law of Tendering
The Law of TenderingThe Law of Tendering
The Law of Tendering
 
Value Engineering
Value EngineeringValue Engineering
Value Engineering
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Tendering, Contract and Execution
Tendering, Contract and ExecutionTendering, Contract and Execution
Tendering, Contract and Execution
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Consumer protection act 1986 - Legal Environment of Business - Business Law ...
Consumer protection act  1986 - Legal Environment of Business - Business Law ...Consumer protection act  1986 - Legal Environment of Business - Business Law ...
Consumer protection act 1986 - Legal Environment of Business - Business Law ...
 
U.P. APARTMENT RULES 2010
U.P. APARTMENT RULES 2010U.P. APARTMENT RULES 2010
U.P. APARTMENT RULES 2010
 
contract procedure
contract procedurecontract procedure
contract procedure
 
THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016
THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016
THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016
 
Consumer prorection council
Consumer prorection councilConsumer prorection council
Consumer prorection council
 
Introduction to public procurement
Introduction to public procurement Introduction to public procurement
Introduction to public procurement
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 

Similar a Tendering process CVC guidelines-converted.pptx

Operations in Source to Pay (S2P) Cycle
Operations in Source to Pay (S2P) CycleOperations in Source to Pay (S2P) Cycle
Operations in Source to Pay (S2P) CycleIRJET Journal
 
Pgpm13 project procurement and materials
Pgpm13 project procurement and materialsPgpm13 project procurement and materials
Pgpm13 project procurement and materialssakariya88
 
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdfahsansaeed78
 
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdfahsansaeed78
 
World Class Procurement
World Class ProcurementWorld Class Procurement
World Class Procurementmwekesser
 
Procurement ops450
Procurement ops450Procurement ops450
Procurement ops450kahogan62
 
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdfahsansaeed78
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahidashahida quraishi
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid Daoud
 
Param 15 supplies and disposals(dsg&d)
Param 15  supplies and disposals(dsg&d)Param 15  supplies and disposals(dsg&d)
Param 15 supplies and disposals(dsg&d)samjune
 
Product life cycle costing
Product life cycle costingProduct life cycle costing
Product life cycle costingArchanaNargund1
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSGanesh Bhorkade
 
Pricing , lisencing and portfolios in tech transfer
Pricing , lisencing and portfolios in tech transferPricing , lisencing and portfolios in tech transfer
Pricing , lisencing and portfolios in tech transferRakshaSharma26
 

Similar a Tendering process CVC guidelines-converted.pptx (20)

Operations in Source to Pay (S2P) Cycle
Operations in Source to Pay (S2P) CycleOperations in Source to Pay (S2P) Cycle
Operations in Source to Pay (S2P) Cycle
 
Pgpm13 project procurement and materials
Pgpm13 project procurement and materialsPgpm13 project procurement and materials
Pgpm13 project procurement and materials
 
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management.pdf
 
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
1661351055Unit 7 1059-V1 Specialised Buying & Vendor Management (1).pdf
 
Purchase and procurement
Purchase and procurementPurchase and procurement
Purchase and procurement
 
Foundation of supply management
Foundation of supply managementFoundation of supply management
Foundation of supply management
 
World Class Procurement
World Class ProcurementWorld Class Procurement
World Class Procurement
 
Procurement ops450
Procurement ops450Procurement ops450
Procurement ops450
 
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
1661351055Unit 6 1058-V1 Purchase and Stores Management.pdf
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Procurement Strategy Development
Procurement Strategy DevelopmentProcurement Strategy Development
Procurement Strategy Development
 
GLOBAL SOURCING
GLOBAL SOURCINGGLOBAL SOURCING
GLOBAL SOURCING
 
Pom unit 1
Pom unit 1Pom unit 1
Pom unit 1
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahida
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016
 
Param 15 supplies and disposals(dsg&d)
Param 15  supplies and disposals(dsg&d)Param 15  supplies and disposals(dsg&d)
Param 15 supplies and disposals(dsg&d)
 
Product life cycle costing
Product life cycle costingProduct life cycle costing
Product life cycle costing
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
 
Project Procurement Management
Project Procurement ManagementProject Procurement Management
Project Procurement Management
 
Pricing , lisencing and portfolios in tech transfer
Pricing , lisencing and portfolios in tech transferPricing , lisencing and portfolios in tech transfer
Pricing , lisencing and portfolios in tech transfer
 

Último

ΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτος
ΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτοςΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτος
ΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτοςNewsroom8
 
Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024Money Forward
 
OAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptx
OAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptxOAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptx
OAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptxhiddenlevers
 
Demographic transition and the rise of wealth inequality
Demographic transition and the rise of wealth inequalityDemographic transition and the rise of wealth inequality
Demographic transition and the rise of wealth inequalityGRAPE
 
Introduction to Health Economics Dr. R. Kurinji Malar.pptx
Introduction to Health Economics Dr. R. Kurinji Malar.pptxIntroduction to Health Economics Dr. R. Kurinji Malar.pptx
Introduction to Health Economics Dr. R. Kurinji Malar.pptxDrRkurinjiMalarkurin
 
What is sip and What are its Benefits in 2024
What is sip and What are its Benefits in 2024What is sip and What are its Benefits in 2024
What is sip and What are its Benefits in 2024prajwalgopocket
 
ekthesi-trapeza-tis-ellados-gia-2023.pdf
ekthesi-trapeza-tis-ellados-gia-2023.pdfekthesi-trapeza-tis-ellados-gia-2023.pdf
ekthesi-trapeza-tis-ellados-gia-2023.pdfSteliosTheodorou4
 
Global Economic Outlook, 2024 - Scholaride Consulting
Global Economic Outlook, 2024 - Scholaride ConsultingGlobal Economic Outlook, 2024 - Scholaride Consulting
Global Economic Outlook, 2024 - Scholaride Consultingswastiknandyofficial
 
Banking: Commercial and Central Banking.pptx
Banking: Commercial and Central Banking.pptxBanking: Commercial and Central Banking.pptx
Banking: Commercial and Central Banking.pptxANTHONYAKINYOSOYE1
 
Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...
Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...
Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...Amil baba
 
Building pressure? Rising rents, and what to expect in the future
Building pressure? Rising rents, and what to expect in the futureBuilding pressure? Rising rents, and what to expect in the future
Building pressure? Rising rents, and what to expect in the futureResolutionFoundation
 
10 QuickBooks Tips 2024 - Globus Finanza.pdf
10 QuickBooks Tips 2024 - Globus Finanza.pdf10 QuickBooks Tips 2024 - Globus Finanza.pdf
10 QuickBooks Tips 2024 - Globus Finanza.pdfglobusfinanza
 
Zimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdf
Zimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdfZimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdf
Zimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdfFREELANCER
 
TACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptx
TACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptxTACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptx
TACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptxKathlynVillar
 
Thoma Bravo Equity - Presentation Pension Fund
Thoma Bravo Equity - Presentation Pension FundThoma Bravo Equity - Presentation Pension Fund
Thoma Bravo Equity - Presentation Pension FundAshwinJey
 
2B Nation-State.pptx contemporary world nation
2B  Nation-State.pptx contemporary world nation2B  Nation-State.pptx contemporary world nation
2B Nation-State.pptx contemporary world nationko9240888
 
2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptx2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptxHenry Tapper
 
Aon-UK-DC-Pension-Tracker-Q1-2024. slideshare
Aon-UK-DC-Pension-Tracker-Q1-2024. slideshareAon-UK-DC-Pension-Tracker-Q1-2024. slideshare
Aon-UK-DC-Pension-Tracker-Q1-2024. slideshareHenry Tapper
 
Hello this ppt is about seminar final project
Hello this ppt is about seminar final projectHello this ppt is about seminar final project
Hello this ppt is about seminar final projectninnasirsi
 

Último (19)

ΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτος
ΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτοςΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτος
ΤτΕ: Ανάπτυξη 2,3% και πληθωρισμός 2,8% φέτος
 
Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024Money Forward Integrated Report “Forward Map” 2024
Money Forward Integrated Report “Forward Map” 2024
 
OAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptx
OAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptxOAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptx
OAT_RI_Ep18 WeighingTheRisks_Mar24_GlobalCredit.pptx
 
Demographic transition and the rise of wealth inequality
Demographic transition and the rise of wealth inequalityDemographic transition and the rise of wealth inequality
Demographic transition and the rise of wealth inequality
 
Introduction to Health Economics Dr. R. Kurinji Malar.pptx
Introduction to Health Economics Dr. R. Kurinji Malar.pptxIntroduction to Health Economics Dr. R. Kurinji Malar.pptx
Introduction to Health Economics Dr. R. Kurinji Malar.pptx
 
What is sip and What are its Benefits in 2024
What is sip and What are its Benefits in 2024What is sip and What are its Benefits in 2024
What is sip and What are its Benefits in 2024
 
ekthesi-trapeza-tis-ellados-gia-2023.pdf
ekthesi-trapeza-tis-ellados-gia-2023.pdfekthesi-trapeza-tis-ellados-gia-2023.pdf
ekthesi-trapeza-tis-ellados-gia-2023.pdf
 
Global Economic Outlook, 2024 - Scholaride Consulting
Global Economic Outlook, 2024 - Scholaride ConsultingGlobal Economic Outlook, 2024 - Scholaride Consulting
Global Economic Outlook, 2024 - Scholaride Consulting
 
Banking: Commercial and Central Banking.pptx
Banking: Commercial and Central Banking.pptxBanking: Commercial and Central Banking.pptx
Banking: Commercial and Central Banking.pptx
 
Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...
Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...
Uk-NO1 Rohani Amil In Islamabad Amil Baba in Rawalpindi Kala Jadu Amil In Raw...
 
Building pressure? Rising rents, and what to expect in the future
Building pressure? Rising rents, and what to expect in the futureBuilding pressure? Rising rents, and what to expect in the future
Building pressure? Rising rents, and what to expect in the future
 
10 QuickBooks Tips 2024 - Globus Finanza.pdf
10 QuickBooks Tips 2024 - Globus Finanza.pdf10 QuickBooks Tips 2024 - Globus Finanza.pdf
10 QuickBooks Tips 2024 - Globus Finanza.pdf
 
Zimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdf
Zimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdfZimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdf
Zimbabwe's New Gold-Backed Currency- A Path to Stability or Another Monetary.pdf
 
TACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptx
TACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptxTACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptx
TACLOBAN-CITY-DIVISION-POPQUIZ-2023.pptx
 
Thoma Bravo Equity - Presentation Pension Fund
Thoma Bravo Equity - Presentation Pension FundThoma Bravo Equity - Presentation Pension Fund
Thoma Bravo Equity - Presentation Pension Fund
 
2B Nation-State.pptx contemporary world nation
2B  Nation-State.pptx contemporary world nation2B  Nation-State.pptx contemporary world nation
2B Nation-State.pptx contemporary world nation
 
2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptx2024-04-09 - Pension Playpen roundtable - slides.pptx
2024-04-09 - Pension Playpen roundtable - slides.pptx
 
Aon-UK-DC-Pension-Tracker-Q1-2024. slideshare
Aon-UK-DC-Pension-Tracker-Q1-2024. slideshareAon-UK-DC-Pension-Tracker-Q1-2024. slideshare
Aon-UK-DC-Pension-Tracker-Q1-2024. slideshare
 
Hello this ppt is about seminar final project
Hello this ppt is about seminar final projectHello this ppt is about seminar final project
Hello this ppt is about seminar final project
 

Tendering process CVC guidelines-converted.pptx

  • 1. PROCUREMENT PROCEDURES AS PER CVC GUIDELINES DEBENDRA KUMAR SAHU DY MATERIALS MANAGER VISAKHAPATNAM PORT TRUST
  • 2. PROCUREMENT Procurement is the process of purchasing goods or services and is usually in reference to business spending, which is usually involves several areas of a company/bussiness.
  • 3. VIGILANCE GUIDELINES Vigilance is the state of being watchful or alert for possible danger or difficulties or some other kind of trouble. Vigilance guidelines is the guidelines issued by the CVC from time to time to avoid dangers, difficulties and troubles in tendering process for better transparency and competition
  • 4. PROCUREMENT PROCEDURES A procurement process is a series of steps that an organization identifies and follows in order to obtain goods or services for their goals and objectives. Step 1 – Needs Recognition. Step 2 – Purchase Requisition. Step 3 – Requisition review. Step 4 – Selection of vendors and market. Step 5 – Bid invitation and evaluation. Stap 6- Negotiate price and terms. Step 7 – Finalisation of the Purchase Order/contract. Step 8- Receipt and inspection of the delivered goods. Step 9 – Receipt of Invoice and Process of Payment. Step 10 – Delivery and Audit of the Order. Step 11- Dispute management. Step 12 – Maintain Accurate Record.
  • 5. TENDER Tendering usually refers to the process whereby governments and financial institutions invite contractors to place a bid for work on a construction project or materials supply that must be submitted within a finite deadline.
  • 7. FUNDAMENTALPRINCIPLE OF PUBLIC BUYING (A) Procurement of goods in Public Interest – i. Efficiency , ii. Economy, iii. Transparency (B) Fair &Equitable treatment of suppliers (C)Promotion of Competition
  • 8. PUBLIC PROCUREMENT : YARDSTICKS — Specifications in terms of quality — Need based procurement (avoid excess) — Fair ,Reasonable &Transparent procedure — Procurement VsRequirement — Reasonableness of Rate — Each stage of procurement should be recorded
  • 9. 5 R’s OF PROCUREMENT i) Right Quality ii) Right Quantity iii) Right Price. v) Right Time and Place v) Right Source
  • 10. PUBLIC PROCUREMENT CYCLE i) Need Assessment: Need assessment, formulation of Specifications and Procurement Planning; ii) Bid Invitation: Preparing bid documents, publication, receipt and opening of bids; iii) Bid Evaluation: Evaluation of bids and award of contract; iv) Contract Execution: Contract management and closure; v) Disposal of Scrap: Disposal of Scrap through various modes of disposal.
  • 11. NEED ASSESSMENT •The expression/description of the need. •Method of satisfying it. •Time-schedule and place. •Formulation of Specification. •Estimation of Cost.
  • 12. THE EXPRESSION/DESCRIPTION OF THE NEED The following Guidelines to comply with the ‘Procurement Guidelines for the Value for Money (VfM) and to ensure wide competition. a) Use Unambiguous, complete, using common terminology prevalent in relevant trade. b) Except in case of proprietary purchase from a selected single source, reference to brand names, catalogue numbers or other details that limit any materials. c) Owning/leasing/hiring/out sourcing or through Public Private Partnership (PPP), and so on) may be determined. d) The quantity of the subject matter of procurement, commensurate with economy units of quantity. e) Time-schedule and place of product/work/service delivery
  • 13. FORMULATION OF SPECIFICATIONS Ensure value for money(VFM), transparency, level playing field and ensuring widest competition. i) Provides a level playing field and ensures the widest competition; ii) Be unambiguous, precise, objective, functional, broad based/generic, standardised (for items procured repeatedly) and measurable. iii) Set out the required technical, qualitative and performance characteristics to meet just the bare essential needs of the Procuring Entity without including superfluous and nonessential features. iv) All dimensions incorporated in the specifications shall be indicated in metric units.
  • 14. FORMULATION OF SPECIFICATIONS V) Make use of best practices. Preference should be given to procure the goods which carry the BIS mark. VI) Commensurate with VfM, avoid procurement of obsolete goods and require that all goods and materials be new, unused and of the most recent or current models. VI) Should have emphasis on factors such as efficiency, optimum fuel/power consumption, use of environmental- friendly materials, reduced noise and emission levels, low maintenance cost, and so on. Government of India has set up the Bureau of Energy Efficiency (BEE) VII) Comply with sustainability criteria and legal requirements of environment or pollution control and other mandatory and statutory regulations, or internal guidelines, if any, applicable to the goods to be purchased; •A standardized product is a product that regardless of what company furnishes the good, consumers regard the product furnish
  • 15. STANDARDISATION .Standardization is the process of creating protocols to guide the creation of a good or service based on the consensus of all the relevant parties in the industry. ... Standardization also helps in ensuring the safety, interoperability, and compatibility of goods produced. .The 3’S refer to standardization, simplification and specialization three related which are at the roof of any economic analysis of product design. PISTON INDUSTRY- Standard sizes of piston are produced for different products . NUT &BOLT INDUSTRY- standard nut and bolts are produced so that they can be easily available in market in case of
  • 16. COPYING PAPER Whether ISI Marked:YES Size of paper:Legal/Protrait GSM of paper:75 "Number of sheets per Ream“:500 "ISO Brightness,percent,Min" (N>=80):90 Opacity percent,Min (N>=85):90 "One minute Cobb test both sides,g/m2,Max" (N<=25):25 "Tensile Index Machine Direction (MD) ,Nm/g, Min“:50(N>=40) Tensile Index Cross Direction(CD),Nm/g,Min (N>=25)35 "Tear Index in mN m²/g,Machine Direction(MD),Min”(N>=3.5)4.5 "Tear Index in mN m²/g,Cross Direction(CD)Min," (N>=4.5)5 "Smoothness for both sides in ml/min,Max" (150<=N<=300)284 "Ash content(900◦C),percent by mass,Max" (N<=16)15 Thickness in µm,Min (N>=100+/-5)100 "Moisture content,percent,Max" (4<=N<=5.5)5 "Taber Stiffness ,Machine Direction(MD),Min" (N>=2)4
  • 17. DESK TOP COMPUTER Chipset Series: Intel Q Series Chipset Number: Intel Q 470 Processor Make:Intel Processor Generation:10 Number of Cores per Processor:8 Processor DescriptionIntel Core: i7 Processor NumberIntel Core :i7 10700 Operating System (Factory Pre-Loaded):Windows10 Professional RAM Size (GB):8 RAM Expandability up to( using spare DIMM Slots in GB):64 Type of Drives used to populate the Internal BaysHDD ,SSD Total HDD Capacity (GB):1000 Total SSD Capacity (GB):256 Monitor Technology:TN LED Backlit Monitor Size (INCHES):18.5 Monitor Resolution (PIXELS)1366x768 On Site OEM Warranty (Year)3
  • 18. ALMIRAH MaterialM S Sheet:Grade D of IS:513/2008 Material of Almirah Doors:Grade D of IS:513/Latest Sheet Thickness of door in mm0.7 mm Sheet Thickness of 0.7 mm minimum No of shelves (Nos)4 Type of Shelves:Adjustable Locker Provided:yes Number of Doors (Nos)2 Height (Without Pedestal) (in mm) (+/- 10 mm)2400 Width in mm (± 7 mm)900 millimeter Depth in mm (±5 mm)505 millimeter Width of Stiffner in mm (±5 mm)N.A WARANTEE PERIOD IN NUMBER OF YEARS1
  • 19. BICYCLE TypeTwo Wheeled Cycles for Men Weight of Bicycle (kg)15 Applicable Indian StandardIS 10613:2004 Size of Frame (cm) 56 Reflector Yes Bell Yes Lock Yes Stand Yes Basket yes Thickness of Crank at Axle Hole (mm)34 millimeter Type of RimBeaded Edge(BE) Material of RimAluminium Size Designation of Rim26 Thickness of tube (mm)2 millimeter Top Tube Diameter (mm)32 millimeter No. of Holes in Rear Wheel36 Front Axle Length (mm)38 millimeter Hub Axle Diameter for Front Wheel (mm)1 millimeter Material of NippleBrass Conforming to IS 2704
  • 20. THE ESTIMATED COST •Processes, approvals and establishing reasonableness of prices should be worked out in a realistic and objective manner. •The prevailing market price ascertained through a market survey or budgetary quotes from potential parties. • For equipment/craft which are uniquely custom-built to buyer’s •Likewise rates should be compared with recent orders/purchases of similar equipment by other states/ Departments. • Estimated rate in past indents of the same goods. • Last purchase price of this or similar or nearly equivalent requirements. • Costing analysis based on costs of various components/raw materials of the item;
  • 21. THE ESTIMATED COST • Rough assessment from the price of the assembly/machine of which the item is a part or vice versa. • Through the internal or external expert costing agencies. • As a last resort, rough assessment from the opportunity cost of not using this item at all. • These methods are not mutually exclusive and can be supplemented with escalations to cater for inflation, price increases of raw materials, labour, energy, statutory changes, price indices, and so on, to make them usable in conditions prevailing currently. •In case of foreign currencies, the rate should be reduced to a common denomination of Indian Rupees. • Price indices can be obtained from the Internet.
  • 22. PROCUREMENT PLANNING Procuring Entity should take following decisions to initiate procurement, to ensure conformity to the Procurement Guidelines: i) Within 14 (Fourteen) working days of receipt of the indent from the user Department, the procuring authorities should critically review the description and TS enclosed with the indent for completeness/approvals/funding, VfM and possibility of the widest competition and seek clarifications from the indenting officer, if needed, before initiating such procurement. ii)Reassessment of the quantity and appropriate aggregation of quantities of various iii) Determine and declare in documents, any limitation on participation of bidders as per the Government’s procurement policy.
  • 23. PROCUREMENT PLANNING v) Selection of a system of bidding (single/two stage; single/two bids; suitability for e-Procurement or reverse auction). v) Select the mode of procurement (open tenders, limited tenders, single tenders, rate contracts, and so on). vi) Decisions on the timeframe for completing various stages of procurement, which should be declared in the pre-qualification/bidder registration or bidding documents. vii) Integrated procurement plan should be prepared for goods, works and services for the ensuing financial year based on the latest cost estimates, and realistic time schedule for procurement
  • 24. GFR 2017: Procurement of goods and services — Rule 142 : This chapter contains the general rules applicable to all Ministries or Departments, regarding procurement of goods required for use in the public service. Rule 143: Definition of Goods: The term ‘goods’ used in this chapter includes all materials, intangible products like software, training and maintenance, works and services etc. Rule 144 Fundamental principles of public buying (for all procurements including procurement of works)
  • 25. GFR 2017: Procurementof goodsand services Rule 145: Authorities competent to purchase goods. Rule 146 Procurement of goods required on mobilisation of military operations. Rule 147 Powers for procurement of goods. The Ministries or Departments have been delegated full powers to make their own arrangements for procurement of goods. Rate Contract. Organisation shall conclude rate contracts through DGS&D. Govt of ndiahas established the GeM for common use Goods and Servioes. GeM. Rule 149 Government e-Marke place (GeM):Government of india has established the Government e- Marketplace (GeM) for common use Goods and Servioes.
  • 26. RULE 149,GFR 2017 THE GEM PORTAL SHALL BE UTILIZED BY THE GOVERNMENT BUYERS FOR DIRECT ON-LINE PURCHASES AS UNDER :- (i) UP TO RS.25,000/- THROUGH ANY OF THE AVAILABLE SUPPLIERS ON THE GEM, MEETING THE REQUISITE QUALITY, SPECIFICATION AND DELIVERY PERIOD (ii) ABOVE RS.25,000/- UP TO RS.5,00,000/- THROUGH THE GEM SELLER HAVING LOWEST PRICE AMONGST THE AVAILABLE SELLERS, OF AT LEAST THREE DIFFERENT MANUFACTURERS, ON GEM (iii) ABOVE RS.5,00,000/- THROUGH THE SUPPLIER HAVING LOWEST PRICE, MANDATORILY OBTAINING BIDS, USING ONLINE BIDDING OR REVERSE AUCTION TOOL PROVIDED ON GEM.
  • 27. Rule 150 Registration of Suppliers Credentials, capability, QC systems, past performance, after sale service, financial background, Reg for period 1-3 years depending upon nature of goods. At the End of period all including new have to apply for registration afresh. Performance to be watched by the department Remove from the list, defaulters in terms of bad quality, delays ,falsification of records/decleration
  • 28. Rule 151 Debarment from bidding (i) A bidder shall be debarred if he has been convicted of an offence— (a) under the Prevention of Corruption Act, 1988; or (b) the Indian Penal Code or any other law for the time being in force for a period not exceeding three years commencing from the date of d e b a r m e n t . (ii) D e p a r t m e n t o f Commerce (DGS&D) will maintain such list which will also be displayed on the website of DGS&D as well as Central Public Procurement Portal. (iii) A procuring entity may debar a bidder or any of its successors, from participating in any procurement process undertaken by it, for a period not exceeding two years, if it determines that the bidder has breached the code of integrity.
  • 29. Rule 152 Enlistment of Indian Agents . As per the Compulsory Enlistment Scheme of the Department of Expenditure, Ministry of Finance, it is compulsory for Indian agents, who desire to quote directly on behalf of their foreign principals, to get themselves enlisted with the Central Purchase Organisation (eg. DGS&D). However, such enlistment is not equivalent to registration of suppliers as mentioned under Rule 150.
  • 30. Rule 153 Reserved Items and other Purchase/Price Preference Policy (i) The Central Government, through administrative instructions, has reserved all items of hand spun and hand-woven textiles (khadi goods) for exclusive purchase from Khadi Village Industries Commission (KVIC (ii) Ministry of Micro, Small and Medium Enterprises (MSME) have notified procurement policy under section 11 of the Micro, Small and Medium Enterprises Development Act, 2006. (iii) The Central Government may, by notification, provide for mandatory procurement of any goods or services from any category of bidders, locally provided goods and services.
  • 31. Rule 154 Purchase of goods without quotation Purchase of goods upto the value of Rs. 25,000 (Rupees twenty five thousand) only on each occasion may be made without inviting quotations or bids on the basis of a certificate to be recorded by the competent authority. “I,, am personally satisfied that these goods purchased are of the requisite quality and specification and have been purchased from a reliable supplier at a reasonable price.”
  • 32. Rule 155 Purchase of goods by Purchase Committee Purchase of goods costing above Rs. 25,000 (Rupees twenty five thousand only) and upto Rs.2,50,000/- (Rupees two lakh and fifty thousand only) on each occasion may be made on the recommendations of a duly constituted Local Purchase Committee consisting of three members of an appropriate level as decided by the Head of the Department. Committee’s responsibilities a) Market Survey b) Reasonableness of Rates c) Quality & Specifications d) Identify appropriate supplier e) Joint Certificatebythe Committee
  • 33. Joint Certificate by the Committee “Certified that we, ---------, members of the purchase committee are jointly and individually satisfied that the goods recommended for purchase are of the requisite specification and quality, priced at the prevailing market rate and the supplier recommended is reliable and competent to supply the goods under procurement and the firm is not debarred by Department of Commerce or Ministry/ Department concerned.”
  • 34. Rule 156 Ministry and departments may purchase from suppliers on terms and conditions specified in rate contract. Make own arrangement for inspection. CPO(DGS&D) should host updated details of different rate contracted items on the web-site for the use of procuring Department Rule 157 Demand not to be divided into small quantities to make piece meal purchases to avoid sanction by higher authority wrt estimated value of total demand.
  • 35. Except in cases covered under Rule 154,155, and 156(1), Ministries or Departments shall procure goods under the powers referred to in Rule 147 above by following the standard method of obtaining bids in : (i) Advertised Tender Enquiry (ii) Limited Tender Enquiry (iii) Two-Stage Bidding (iv) Single Tender Enquiry (v) Electronic Reverse Auctions Rule 158 Purchase of goods by obtaining bids.
  • 36. Rule 159 E-Publishing (i) It is mandatory for all Ministries/ Departments to publish their tender enquiries, corrigenda thereon and details of bid awards on the Central Public Procurement Portal (CPPP). (ii) Individual cases where confidentiality is required, for reasons of national security, would be exempted from the mandatory e-publishing requirement. (iii) The above instructions apply to all Tender Enquiries, Requests for Proposals, Requests for Expressions of Interest, Notice for pre Qualification/ Registration
  • 37. Rule 159 E-Publishing (iv) In the case of procurements made though DGS&D Rate Contracts or t h r o u g h a n y o t h e r C e n t r a l Procurement Organizations (CPOs) only award details need to be published. (v)These instructions would not apply to procurements made in terms of provisions of Rules 154 (Purchase of goods without quotations) or 155 (Purchase of goods by purchase committee) of General Financial Rules.
  • 38. E-Procurement It is mandatory to receive all bids through e- procurement portals in respect of all procurements. Departments which do not have a large volume of procurement may use e- procurement solution developed by NIC. Other Departments may either use e- procurement solution developed by NIC or engage any other service provider following due process.
  • 39. RULE 161: Method ofobtainingbid: Advertised TenderEnquiry(open) — Tender value >= 25 Lac — — Publish atown website &NIC website — NIT to Indian Embassies abroad as well as foreign embassies in India — Three Weeks time from dateof publication of bid
  • 40. Rule :162- LIMITEDTENDER ENQUIRY — Value up to 25 Lac — Bid document should be sent to Regd. Suppliers by Speed Post/Regd Post/ Courier/ e-mail — No. of supplier firms in Ltd.Tender should be more than three — Web based publicity also through CPPP and Department’s website, — N.B. – Sufficient time should be givenin Ltd.Tender
  • 41. LIMITEDTENDER ENQUIRY Certificate that demand is urgent. Add expenditure justified in view of urgency. Put on record the nature of urgency and reasons why procurement could not be anticipated. sufficient reasons to be recorded that Open tendering not in public interest. Sources of supply are definitely known and possibility of fresh sources is remote.
  • 42. Rule 163 Two Bid System 1. For high value plant ,machinery of complex and technical nature items. 2. TechnicalBid (Tech.+ Comm.Terms ) 3. Financial Bid (Item wise price ) (1) + (2) = (3) MainEnvelop Firstly T ech. Bid shall be opened and evaluated  Secondly Fin. Bid of Technically acceptable offer should be opened & evaluated
  • 43. Rule 164 two stage bidding Obtain bids in two stages with receipt of financial bids after receipt and evaluation of technical bids It is not feasible to formulate detailed specifications or identify specific characteristics Rapid technological advances or market fluctuations or both All first stage bids, which are otherwise eligible, shall be evaluated, may hold discussions with the bidders, and consider revising the relevant terms and conditions of the procurement Invite bids from all those bidders whose bids at the first stage were not rejected, to present final bid with bid prices in response to a revised set of terms and conditions of the procurement
  • 44. Rule 165 late bids Bids received after the specified date and time should not be considered.
  • 45. Rule 166 SingleTender Ifonly aparticular firm is the manufacturer Emergency need to procure from a particular source T echnicalreason to be recorded (standardization of machinery – HP , SONY etc.) N.B. - Single response to an open bid can’tbe termed as Single Tender
  • 46. Rule 167 Electronic Reverse Auction (i) Electronic Reverse Auction means an online real- time purchasing technique utilised by the procuring entity to select the successful bid. (ii) A procuring entity may choose to procure a subject matter of procurement by the electronic reverse auction method, (iii) The procedure for electronic reverse auction similar to e-procurement; and (b) The invitation shall, in addition to the information as specified in e- procurement, include details relating to access to and registration for the auction, opening and closing of the auction and Norms for conduct of the auction.
  • 47. Rule 168 Contents of Bidding Document — Instruction to Bidder — Conditions of Contract — Schedule of Requirement — Specifications &alliedTech.details — Price Schedule — Contract Form — Other Standard Forms
  • 48. Rule 169 Maintenance Contract Depending on the cost and nature of the goods to be purchased, it may also be necessary to enter into maintenance contract(s) of suitable period either with the supplier of the goods or with any other competent firm, not necessarily the supplier of the subject goods. Such maintenance contracts are especially needed for sophisticated and costly equipment and machinery. It may, however, be kept in mind that the equipment or machinery is maintained free of charge by the supplier during its warranty period or such other extended periods as the contract terms may provide and the paid maintenance should commence only thereafter.
  • 49. Rule 170 Earnest Money Deposit — To safeguard the interest of Deptt (withdrawal /alter the bid by bidder) — Exemption – Regd.With CentralPurchase Organisation /National Small Industries Corporation — EMD - 2 % to 5% of estimatedvalue — Can be DD/ FDR/Banker Cheque /BG — Unsuccessful bidders EMD should be returned /refundedatthe earliest.
  • 50. Rule 171 Performance Security — From the successful bidders — Amount – 5%to 10% — DD/FDR —Should be valid for 60 days beyond the date of completion of all the contractual obligations of the supplier including warranty — Bid Security should be refunded to the successful bidder on receipt of Performance Security
  • 51. PROCESS ATA GLANCE  Estimate (Qty. andAmount)  EOI – Expressionof Interest  RFP/RFQ – Request for Proposal /Quotation  PBC – Pre BidConference  NIT – Notice Inviting Tender  APPROVAL  WEB PUBLICITY  EMD – Earnest Money Deposit  BIDDING TOC – Tender Opening Committee (Tech) APPROVAL
  • 52. PROCESS ATA GLANCE   TOC – Tender Opening Committee(Fin.Bid)  APPROVAL   TEC – Tender Evaluation Committee   APPROVAL  PO - Purchase Order  AWARD OF CONTRACT  SD - Security Deposit  AGREEMENT  REFUND OF EMD  NOTICE /WEB PUBLICITYABOUT AWARD OF CONTRACT(Downloadable form)
  • 53. Rule 172 (1) Advance payment to supplier Ordinarily, payments for supply and services rendered are released only after the services have been rendered Advance payment may be necessary by firms holding maintenance, fabrication contracts, turn-key contracts etc Limits 30% of the contract value to private firms 40% of the contract value to a State or Central Government Agency or a PSU In case of maintenance contract, the amount payable for 6 months under the contract. Ministries/Departments may relax the ceilings in consultation with the FA Adequate safeguard in the form of BG should be obtained from the firm obtained from the firm.
  • 54. Rule 172(2) Part payment to suppliers Part payment permitted depending upon terms of contract. After dispatch of goods from premises.
  • 55. Rule 173 TRANCEPARECY, COMPETITION FAIRENESS the text of the bidding document should be self- contained and comprehensive without any ambiguities, clearly spelt out in the bidding document in simple language. The bidding document should contain, (a) the criteria for eligibility and qualifications to be met by the bidders such as minimum level of experience, past performance, technical capability, manufacturing facilities and financial position, goods indicating any legal restrictions etc (c) the procedure as well as date, time and place for sending the bids; (d) date, time and place of opening of the bid; (e) terms of delivery; (f) special terms affecting performance,
  • 56. Rule 173 TRANCEPARECY, COMPETITION FAIRENESS suitable provision should be kept in the bidding document to enable a bidder to question the bidding conditions, bidding process and/or rejection of its bid. The bidders should be given reasonable time to send their bids. The specifications of the required goods should be clearly stated without any ambiguity so that the prospective bidders can send meaningful bids. In order to attract sufficient number of bidders, the specifications should be broad based to the extent feasible. Efforts should also be made to use standard specifications which are widely known to the industry. .
  • 57. Rule 173 TRANCEPARECY, COMPETITION AND FAIRENESS Criteria for determining responsiveness of bids, criteria as well as factors to be taken into account for evaluating the bids on a common platform and the criteria for awarding the contract to the responsive lowest bidder should be clearly indicated in the bidding documents. Bids received should be evaluated in terms of the conditions already incorporated in the bidding documents; no new condition which was not incorporated in the bidding documents should be brought in for evaluation of the bids. Determination of a bid’s responsiveness should be based on the contents of the bid itself without recourse to extrinsic evidence.
  • 58. Rule 174 Efficiency, Economy and Accountability in Public Procurement System Public Procurement procedure to ensure efficiency, economy and accountability in the system. To achieve the same, the following key areas should be addressed: 1. To reduce delay, appropriate time frame for each stage of procurement should be prescribed by the Ministry or Department. Such a time frame will also make the concerned purchase officials more alert. 2. To minimize the time needed for decision making and placement of contract, every Ministry/Department with the approval of the competent authority, may delegate, where necessary, appropriate purchasing powers to the lower functionaries. 3. The Ministries or Departments should ensure placement of contract within the original validity of the bids. Extension of bid validity should be resorted to only in exceptional circumstances.
  • 59. Rule 175 CODE OF INTEGRITY Promise by the Principal not to seek any illegal benefit. Promise by the bidders not to offer any benefit to the employees of the principal. Bidders not to enter into any understanding with other bidders regarding prices and rigging etc. Bidders not to pass any information of the procurement entity. Foreign bidders to disclose the details of its agent in India. Indian bidders to disclose their foreign associates. Bidders to disclose payments to be made to agents and any misintention to influence tender.
  • 60. Rule 176 BUY BACK OFFER If it is decided to replace an existing old item with a new and better version – the department may trade the existing old item while purchasing the new one A suitable clause is to be incorporated in the bidding document so that the prospective and interested bidders can formulate their bids accordingly The time as well as the mode of handing over the old item to the successful bidder to be suitably incorporated in the bidding document Provision should also be kept in the bidding document to enable the purchaser either to trade or not to trade the old item, while purchasing the new one
  • 61. EVALUATION OF TECHNO-COMMERCIAL BID Evaluation of Techno-commercial Bid In evaluation of the techno- commercial bid, conformity of the eligibility/ qualification, technical and commercial conditions of the offered goods to those in the bid document is ascertained to be considered for evaluation. i) Evaluation of eligibility/qualification Criteria ii) Evaluation of Technical Suitability. iii)Evaluation of Commercial Conditions. iv) Considering Minor Deviations not amount to material deviations. v) Declaration of Successful Bidders BIDDER HAS RIGHT TO QUESTION REJECTION AT TECHNO- COMMERCIAL STAGE
  • 62. EVALUATION PROCESS -micro —Tender is sealed — Tender documents must clearly specify evaluation criteria. — Two types of Bids: ◦ Technical ◦ Financial — Tender evaluation to be in accordance with evaluation criteria.
  • 63. EVALUATION PROCESS -micro — Time taken for evaluation and extension of tender validity. — Process of tender evaluation to be confidential until the award of the contract is notified. — Difference between TOC (Tender Opening Committee) & TEC (Tender Evaluation Committee)
  • 64. EVALUATION PROCESS -micro — The factors for initial examination: ◦ Whether the tenderer meets the eligibility criteria ? ◦ Whether the crucial documents have been submitted &duly signed /attested ? ◦ Whether the requisite EMD (Earnest Money Deposit) has been furnished ?
  • 65. EVALUATION PROCESS -micro — Satisfaction of Conditions specific to the contract — SampleTesting — Capacity Evaluation. — Turnover — Statutory documentation — Arrival atOutcome Price of the bid — Determination of L-1, L-2,L-3…… — Determining Reasonableness of the L-1 Rates — Recommendation for Negotiation (if require)
  • 66. CVC Guidelines: Pre-AwardStage — Financial and Technical sanction of competent authority is available. — Adequate and wide publicity is given. Advertisement is posted on website and tender documents are availablefor downloading. — Convenient tender receiving/opening time and address of the tender receiving officials/tender box are properly notified. —In the case of limited tender , panel is prepared in atransparent manner clearly publishing the eligibility criteria.The panel is updated regularly. —Pre-qualification criteria are properly defined/ notified.
  • 67. CVC Guidelines: Pre-AwardStage —Short listed firms/consultants are fulfillingthe eligibility criteria.There is no deviation from notified criteria during evaluation. —Experience certificates submitted havebeen duly verified. —Tenders/bids are opened in the presence of bidders/ their authorised representative. —Corrections/omissions/additions etc.,in price bid are properly numbered and attested and accounted page –wise.Tender summary note/Tender opening register is scrupulously maintained. —Conditions having financial implications are not altered after opening of the price bids.
  • 68. CVC Guidelines:Negotiations — Circular No.4/3/07,3rd March, 2007 As post tender negotiations could often be a source of corruption, it is directed that there should be no post-tender negotiations with L-1, except in certain exceptional situations. Such exceptional situations would include, procurement of proprietary items, items with limited sources of supply and items where there is suspicion of a cartel formation. The justification and details of such negotiations should be duly recorded and documented without any loss of time.
  • 69. Latest guideline of CVC on negotiation
  • 70. Procurement ofWorks, Goods and Services - Guidelines on Tenders/Use of website — http://cvc.nic.in/proc_works.htm
  • 72. Definition of Vigilance To be watchful To be alert What is happening And what can happen As per George Bernard Show “ Man is moral but we have not tested him. So cannot say that he is sincere” Keep a watch on the people working under you. Try to remove opportunities to reduce the crime “Wearer of shoes know where it Pinches” American- All Open offices United Kingdom- Room wise “More open working less chance of Corruption
  • 73. Objectives of vigilance Raising strong signals regarding complexities in procedure. i.e. System Analysis Identifying places and point of corruption. i.e. for inspections, surprise checks and posting of suitable hands (and if this is not feasible closer supervision of work) including rotation of staff Eliminate the corruption and the crooked staff Watch of work Inside and outside conduct and contacts
  • 74. Realize that cumbersome procedure are the main stay of corruption. I. Modify/ eliminate the blocks. II. Simplify procedure codify them in manual to remove ambiguity. III. Should have list of bad and loose integrity persons. IV. Visit pressure points frequently to ensure, no leakage happens
  • 75. COST OF PROCUREMENT PUBLIC PROCUREMENT IN INDIA CONSTITUTES ABOUT 28% OF GDP
  • 76. CANNON OF PUBLIC PROCUREMENT This is to procure work, material, services of the specified quality within the specified time at the most competitive prices in a fair, just and transparent manner. In brief, the watchwords in this context are • Transparency • Fairness/equal opportunity(Article 14 of constitution) • Value for money • Quality • Time
  • 77. GUIDING DOCUMENTS •GENERAL FINANCE RULES-2017 •PROCUREMENT MANUAL FOR MATERSALS/WORK/SERVICES UPDATED. •CVC GUIDELINES •DELIGATION OF POWERS •NIT-MAIN/GCC/SCC/ANNEXURES OF TENDERS APPROVED
  • 78. REQUIREMENTS Whether it was essential to get the work through contractual agency? Whether the work could have been done within existing resources? Whether the spending proposed is justified.
  • 79. SPECIFICATIONS: 1. Identify the purpose & plan in advance. 2. Clubbing the similar requirements from all units. 3. Description of item should be clear and complete with I.S.specification/drawing if any. 4. Specification should not be prepared meeting single product/specific make. 5.Use Products With Standard Specification. 6. Sample clause if any should be only for ascertaining ‘TOUCH, FEEL & FINISH’ but not for its quality. 7. If the demand of the item is recurring, convert the same as Stock item. 8. The description of the item should normally be arranged in Order. A. Basic commodity B.Variance in kind or use. C. Composition/size/color/shape D.Specification/drawing No.
  • 80. STANDARDS OF FINANCIAL PROPRIETY • The Expenditure should not be prima facie be more than the occasion demands • Every Govt. Servant should exercise the same VIGILANCE in respect of expenditure incurred from public money as a person of a ordinary prudence would exercise in respect of the expenditure of his own money •No authority should exercise its powers of sanctioning expenditure to pass an order, which will directly or indirectly to its own advantage. •Public moneys should not be utilised for the benefit of a particular person or section of the community
  • 81. APPOINTMENT OF CONSULTANT Consultant appointed when absolutely essential for specialized job. Awarding consultancy contract in transparent and fair manner. The consultants role should be well defined as well as payment conditions. No change of payment conditions after award of contract. The payment made to consultant should be commensurate with the work done by them. over dependence on consultants to be avoided. Role of consultants should be advisory. case of conflict of interest in appointment.
  • 82. PRE-QUALIFICATION CRITERIA (PQ) The PQ criteria is a yardstick to allow or disallow the firms to participate in the bids. A vaguely defined PQ criteria results in stalling the process of finalizing the contract or award of the contract in a non-transparent manner. PQ criteria for renderers is provided in some of the tender to have experienced and resourceful contractors for timely and proper execution of works. The PQ criteria should be clear and unambiguous. The PQ criteria should not be too restrictive. Prequalification/Post Qualification shall be made taking into account their capacity to accomplice work.
  • 83. PRE-QUALIFICATION CRITERIA (PQ) (i) experience and past performance on similar contracts. (ii) capabilities of personnel, equipment and manufacturing facilities (iii) financial standing through latest I.T.C.C., Annual report (balance sheet and Profit & Loss Account) of last 3 years. The quantity, delivery and value requirement It is observed that at times this eligibility criteria is loosely and selectively applied in various tenders to favour particular firm. It is expected that eligibility criteria is applied in true spirit and uniformly keeping basic objective in mind. It should not to be used as a tool to eliminate unfavourable lower bidders.
  • 84. NOTICE INVITING TENDER Notice inviting tender contains, general description, technical specifications of the work, with quantity, unit and estimated rates. General and special rules and directions, terms and conditions of the proposed contract, schedule of materials with prices proposed to be issued by the department, earnest money to be deposited prior to tendering, security deposit to be deposited on acceptance of the offer or prior to executing the contract and time for completion of the work. This part is applicable to tenders of all kinds of works.
  • 85. NOTICE INVITING TENDER Tender Notice shall be issued at least 21 days in advance from the date of tender opening In case of urgency – 10-14 days with approval of HOD Issue of tender schedules With the approval of tender calling authority – at least 15 days prior to the date of tender opening Date on which the tender documents will be made available on the website / in the office shall be clearly brought out in the Tender Notice Eligibility criteria and similar nature of works should be specifically mentioned in Tender Notice and in the tender documents for OT above Rs. 50 lakhs
  • 86. NOTICE INVITING TENDER •Should be invariably on a Public Tender basis. • Tenders should be both for technical and financial bids. • Technical bids should be scrutinized before financial bids are opened. • List of suppliers should be reviewed periodically. •Delivery samples should be got checked with basic samples.
  • 87. Open Tenders Common Irregularities Most Widely Publicized in prescribed form Any individual or firm can participate in the Open Tender Basic Requirement - Free and Fair Competition Tender should Normally be awarded to Lowest Suitable Tenderer Inadequate tender notice Inadequate time for participation Inadequate publicity Late availability of tender documents Tender box not available in advance Deviations in eligibility criteria
  • 88. LIMITED TENDERS COMMON IRREGULARITIES Tender Notice issued to selected firms Firms short listed in advance, based on past experience, expertise, and specialization List of selected firms require finance concurrence and competent authority's approval Proof of Service necessary 7 Arbitrary selection of firms. Firms with better experience ignored and firms with dubious credential selected. Inadequate time given for participation in tender. Tender notice not sent to all the firms. Bogus firms selected to inflate the number. Rates can be reasonably higher since the competition is restricted.
  • 89. SINGLE TENDER COMMON IRREGULARITIES Tender is invited from single pre- selected bidder of proven capacity Used in emergencies and exceptional cases Where other tender routes can not be followed due to exigencies of given situation When item is propriety item or only one firm is capable of doing the work Projecting undue/artificial urgency Selecting unsuitable tenderer based on exaggerated credential ignoring his past failures. Accepting exorbitant rates on the grounds of urgency then merrily giving extensions with token penalty or without penalty.
  • 90. RECEIPT OF TENDERS A proper arrangement for the receipt of tenders at scheduled date and time through tender box needs to be adopted. Commission, where due to the bulky size of tender documents the bid conditions envisaged submission of tenders by hand to a designated officer and the information about these officers should also be displayed at the entrance/reception of the premises where tenders are to be deposited so as to ensure convenient approach for the bidders.
  • 91. TENDERS OPENING Opened at the specified time, date and place by an officer nominated in the presence of authorised reps of tenderers. Seal of the Tender Box to be checked Tenders should be serially numbered Initials on cover page and all other loose sheets attached by tenders. Rates quoted should be circled. Corrections, over writings & omissions to be numbered and written on each page and attested with date. Check completeness of tender form (for tampering etc.) downloaded from internet
  • 92. TENDERS OPENING (CONTD …) Name of the tenderers and rates quoted by each tenderer should be read out No clarifications to be solicited from tenderers Samples, if any to be initialed Any Blank Column shall be struck off. LATE tenders to be marked and to be returned to the firm. Both the Accounts and Executive witnessing officials are INDIVIDUALLY responsible the procedure laid down for tender opening.
  • 93. Comparative statement Details of offers received Period of validity of offers. EMD details of each tenderer. Last accepted rates for similar type of works. Financial implications on the special conditions. Remarks on special conditions quoted by the tenderer. Credentials of the tenderer. Other certificates/documents submitted by the tenderer. Details of the contracts of the tenderer during the last 3 years
  • 94. BACK TO BACK TIE UP / AWARD ON NOMINATION BASIS •Back to back basis that the works are being awarded in an ad-hoc and arbitrary manner without inviting tenders and ascertaining the performance, capability and experience of the tenderers. • In some cases, the works were awarded on single tender basis/limited tender basis though sufficient time was available with the Organisation to invite open tenders. •No transparency in selection of contractor for the back to back tie up which is the main source of corruption. •Collusion among the contractors was observed where more than one contractor was involved at various stages. Ineligible contractor obtains the contract through the PSUs.
  • 95. BACK TO BACK TIE UP / AWARD ON NOMINATION BASIS Purchase preference misused by the PSUs. No supervision by the PSU as they put the staff mainly for coordination work. Quality ultimately suffers due to lack of supervision by the PSUs. contractor, has to execute the work by functioning like a contractor instead of sub-letting the 100% work on back to back basis. Open tenders to be invited for selection of sub-contractors as far as possible. In case, it is not possible to invite open tenders, selection should be carried out by inviting limited tenders from the panel approved in the following manner. Panel of contractors are to be prepared for different categories monetary limits, regions, in a transparent manner clearly publishing the eligibility criteria etc. The above panel is to be updated every year.
  • 96. BACK TO BACK TIE UP / AWARD ON NOMINATION BASIS The terms and conditions of the contract of the client especially those pertaining to subletting of works should be strictly adhered to by the PSUs. Adequate staff to be deployed by the PSUs to ensure quality in construction etc. There is a need to bring greater transparency and accountability in award of such contracts on nomination basis and reports relating to such awards will be submitted to the Board every quarter. The audit committee may be required to check at least 10% of such cases. for necessary observance. Further, all nomination/single tender contracts be posted on the website ex
  • 97. TENDER NEGOTIATIONS •There should be no post-tender negotiations with L-1, except in certain exceptional situations. •procurement of proprietary items, • items with limited sources of supply •items where there is suspicion of a cartel formation. •The justification and details of such negotiations should be duly recorded and documented without any loss of time. •ii) In cases of jeopardizing the essential operations, maintenance and safety, negotiations would be permitted with L-1 bidder(s) for the supply of a bare minimum quantity. The balance quantity should, however, be procured expeditiously through a re- tender, following the normal tendering process.
  • 98. TENDER NEGOTIATIONS •Negotiations should not be allowed to be misused as a tool for bargaining with L-1 with dubious intentions • It is reiterated that in case L-1 backs-out, there should be a re-tender. •If L-1 alone is not capable of supplying and there was no prior decision to split the quantities, then the quantity being finally ordered should be distributed among the other bidders in a manner that is fair, transparent and equitable. Counter-offers to L-1, in order to arrive at an acceptable price, shall amount to negotiations. However, any counter- offer thereafter to L-2, L-3, etc., (at the rates accepted by L-1) in case of splitting of quantities, as predisclosed in the tender, shall not be deemed to be a negotiation.
  • 99. CONSIDERATION OF INDIAN AGENTS In order to maintain the sanctity of tendering system, it is advised that the purchases should preferably be made directly from the manufacturers. Either the Indian Agent on behalf of the foreign principal or the foreign principal directly could bid in a tender but not both. Further, in cases where an agent participates in a tender on behalf of one manufacturer, he should not be allowed to quote on behalf of another manufacturer along with the first manufacturer in a subsequent / parallel tender for the same item.
  • 100. IRREGULARITIES IN GENERAL Twisting, Suppression, exaggeration, Manipulation, and Half truth by TC to Depict better placed bidder as unsuitable or less suitable Exaggerating track record of favourite bidder Suppression/ down playing his past failures Exaggerating past failures of his main rival Contd. Ignoring/Suppressing otherwise satisfactory credentials of main rival Projecting the lowest rates of main rival as ‘unworkable’ on the basis of exaggerated estimated cost Projecting undue/ artificial urgency bypassing lowest offer
  • 101. IRREGULARITIES IN GENERAL Manipulating technical aspect to reject inconvenient bids on artificial grounds. Considering tender on extraneous conditions not included in the tender. Falsely Certifying that the quality of product/ material offered by favourite firm as okay vis-a-vis specifications Deliberately painting the quality of product offered by the better placed bidder as unsuitable. Exaggerating capacity/ resources of favorite contractor and downplaying that of his rival (lower bidders)
  • 102. IRREGULARITIES IN GENERAL Favoritism i.e. Award of contract to favoured firm bypassing more deserving lower tenderer/s on flimsy grounds Award of contract at exorbitant rates Execution of Substandard work Acceptance of Substandard Supplies Overpayment / Payment of work not done Failure to Carryout out Quality Check Misappropriation of material by contractor in connivance with officials
  • 103. IRREGULARITIES IN EXECUTION OF CONTRACT Failure to incorporate accepted tender conditions in contract agreement. Introduction of conditions having financial implications. Change in specifications during execution. Altering the location or nature of work giving undue advantage to the tenderer.
  • 104. IRREGULARITIES IN EXECUTION OF CONTRACT Unreasonable variations in terms of quantity Introduction of new non-schedule items. Acceptance of material of inferior brand than specified in contract agreement. Acceptance of material after date of expiry. Acceptance of under specification supply. Accepting material without inspection certificate. Accepting material without delivery challans.
  • 105. IRREGULARITIES IN EXECUTION OF CONTRACT Acceptance of under specification work or supply Not following laid down procedure By passing certain processes Not conducting requisite tests Use of un passed raw materials
  • 106. RING FORMATION Ring/ Cartel formation among the bidders leads to elimination of competition and award of contract at exorbitant rates. At times it is done with active collusion with officers concerned. The ring formation becomes more important in case of limited tenders thus an attempt should be made to identify sister concerns. In case of suspected ring formation with high rates, tender cancellation is advisable.
  • 107. AWARD OF TENDER AT EXORBITANT RATES Due to high pitching estimates. Tenderers are guided by estimated cost given in NIT and often estimated cost are used to assess reasonability of rates. Picking up ‘Comparable rates’ selectively. Preparing rate analysis after the opening of tender to justify the high rates received. Unrealistic short completion period may lead to high rate.
  • 108. By assuming unreasonably high rates towards transportation cost, labour cost, local taxes, inflation etc. Modifying description of items to make them Non- Stock items in case Of Stores and Non-Schedule item in case works items leading to purchase/ execution of works at high rate.
  • 109. POINTS TO BE KEPT IN MIND Tender opening register must be maintained in emd, tender cost,returning of sighned credentials documents, samples,remarks of quoted by renderers are recorded. This must be signed by renderers and tender opening officers present at the time of opening. Delayed tenders i.e. received after closing of box of tender to be rejected.
  • 110. POINTS TO BE KEPT IN MIND Under no circumstances no member of TC should refer the case to any officer/staff under him for scrutiny / comments. Rate register should be maintained religiously in which accepted rates are recorded chronologically and any adverse remarks regarding their non-comparability should also be recorded. The register can be referred to see that the rates LAR taken in briefing note are representative.
  • 111. ADVANCE PAYMENT •If the advance is to be given, it should be expressly stated in the NIT/Bid Documents, indicating the amount, rate of interest and submission of BG of equivalent amount. •The advance payment may be released in stages depending upon the progress of the work and mobilization of required equipments etc. • There should be a provision in the contract for adjustment of advance progressively even as the bills are cleared for payment. •In case of „Machinery and Equipment advance‟, insurance and hypothecation to the employer should be ensured. •Utilization certificate from the contractor for the mob advance should be obtained
  • 112. OVER PAYMENT Temporary overpayment in Running Bills Payment in anticipation of work to be done or supply to made Final overpayment Payment for the services not rendered Inflated measurement Multiple measurement
  • 113. ACCEPTANCE OF BANK GUARANTEE •BG shall be in the form of irrecovarable BG issued by nationalized and scheduled banks. •Bank guaranty should be scrupulously compared with the VPT Performa. •Should be executed on stamp paper of proper value. •Eliminate the possibility of acceptance of any forged / fake bank guarantees. •Confirmation of issuing banks should be obtained for genuiness.
  • 114. POSTING DETAILS OF AWARD OF TENDERS ON WEBSITE All the organisations to post on their web-sites a summary, every month, containing details of all the contracts/purchases made above a threshold value (to be fixed by the organisations) covering at least 60% of the value of the transactions every month to start with on a continuous basis.
  • 115. LEVERAGING TECHNOLOGY •Transparency through effective use of websites in discharge of regulatory, enforcement and other functions of Govt. Authorized. •Issue tenders publish the tender advertisements on e- tendering platforms. ... •Bidders need to enroll themselves at the online tendering platforms to generate user ids and passwords. •One needs to upload the requisite documents and mention the bids online. •E-Payments •Post on the website, summary every month, of all the tenders/works contracts of value more than tha a certain thresshold value of Engg./Mech/Elec/ Medical departments
  • 116. DELAY IN PAYMENT TO VENDORS E-payments brings economy and efficiency and at the same time reducing corruption. Reducing transaction costs involved in making payments by way of cheques and sending the same through courier. e-payments to vendors and employees instead of making payments by issue of cheques. Payments are to be made on “firstcome-first-serve” basis. Payment should be made within a bench mark period from the date it is due. Should verify the outstanding bills position by Contractors, suppliers.
  • 117. E-TENDERING/E-PROCUREMENT CVC advising organizations to follow a fair, transparent and open tendering procedure, to select the application service provider for implementing their e-tendering solutions.
  • 118. IT PROCUREMENT Turnkey contracts for net-working of computer systems. Inclusion of these unrelated items creates opportunities for malpractices-third party view about the scope of turnkey projects. Measures To Curb The Menace Of Counterfeit And Refurbished IT Products diligence as well as curbing the menace of counterfeit and refurbished IT products disguised as new OEM that would certify that all the components/parts/assembly/software used in the Desktops and Servers like Hard disk, Monitors, Memory etc were original/new components/parts/assembly/software, and that no refurbished/duplicate/ second hand components /parts / assembly / software were being used or would be used,
  • 119. LATEST GUIDELINES ON TENDERS •No EMD, Cost of Tenders & SD of 3% of the contract value to be remitted through RTGS/E-Transfer to VPT account. •PG shall be in the form of irrevocable BG issued by nationalised or scheduled bank – 3% of the contract value. PG shall be furnished by the successful contractor within 15 days from the date of issue of acceptance letter & before the signing of the contract and valid upto expiry of the maintenance period Clause.
  • 120. Periodical rotation of Officers Periodical rotation of Officers/staff in sensitive posts. Review of Immovable property returns submitted by Officers/Staff. Proper implementation of DA Rules to weed out corrupt officers. Institution of effective grievance procedure enquiry.