Presentation on construction best management practices for Cold-in-place Recycle (CIR) success, delivered by Dennis McElroy, FMG, at the CalAPA Fall Asphalt Pavement Conference, Oct. 24-25, 2018 in Sacramento, CA.
3. CIR Is Not Hot Mix Asphalt!
Its not AC and its not AB. It’s really in-between.
Material properties are different and expectations should be
different.
As an industry we all need to have an open mind with these
materials.
We need to utilize the hard work others have done so we can
learn faster and use technology like this in more and more
areas.
PARTNERING
www.FMGCoInc.com
12. Best Management Practices Starts
With Picking The Right Road At The
Right Time
▪ Need to verify
existing pavement
thickness in advance
▪ Understand your traffic
count & subgrade info
▪ Do a pavement design
▪ UC DAVIS PRC is a
great resource!
22. IMPORTANT
Both binder types have similar long term performance
characteristics.
Each with their own specifications and specific test
methods.
DO NOT BLEND THE SPECS TOGETHER!
Caltrans NSSP’s (approved April 2018)
Section 30-5 CIR using Emulsified Asphalt
Section 30-6 CIR using Foamed Asphalt
www.FMGCoInc.com
23. Where Do I Get The Proper
Specification?
Caltrans CIR homepage online was last updated:
06/15/2011
Talk to the CIR contractors or agency’s that have
already completed a project.
- Most of the contractors who specialize in CIR will
provide lunch and learn opportunities or will be
willing to share lessons learned.
- www.RoadResource.org is also a great resource.
www.FMGCoInc.com
24. Critical! Before Starting A Project!
www.FMGCoInc.com
JITT Training – Just in time training
This can be after samples have been pulled and a mix design has
been developed.
1. JITT training needs to be done before the work within the
pavement section begins.
2. Have the conversations that you don’t want to have.
3. Staging areas, Traffic handling, mix design, contingency plan,
on site contacts, who is responsible for what, concerns from
all sides, etc.
4. This meeting, with all parties involved, will set the tone and
expectations of the project.
26. 2. Do Your Milling First.
Key cut and conforms need to be done before CIR if they are
within the area to be recycled.
IF YOU DON’T HAVE TO, DON’T MILL THE CIR SURFACE.
34. Cold Material – Minimal cross traffic, emergency vehicles and driveway
access is ok.
www.FMGCoInc.com
35. Final CIR Surface Before The Overlay
Time between completion of
CIR and final surfacing:
Foamed Asphalt
Minimum: 2 to 3 days of
curing
Maximum: 15 days of
exposure to traffic
Emulsions
Minimum: Moisture 2% or
less.
Supplemental Compaction
Maximum: 15 days of
exposure to traffic
www.FMGCoInc.com
36. Final CIR Surface Before The Overlay
What is Supplemental Compaction?
◦ Re-Rolling the entire CIR Surface
prior to smoothness testing or
final surfacing.
◦ After moisture loss due to curing
there are more air voids in the
mixture. Re-rolling the surface
takes out those voids.
Foamed Asphalt doesn’t require
supplemental compaction.
www.FMGCoInc.com
37. Need to apply tack coat before the HMA
overlay is placed.
◦ A fog seal was applied on the final CIR
surface?
Overlay Install, Tack Coat applied
in front of paver & Final CIR Surface
www.FMGCoInc.com
40. Cul De Sacs Contd.
Paved exterior of cul de sac
CIR Ties into new paved exterior of the cul de sac
And directly to the lip of gutter.
AC Paving was left 2” low along lip of gutter. NO milling required later.
www.FMGCoInc.com